11.               landfill gas hazard

Introduction

11.1            This section describes the landfill gas monitoring requirements at the Project tunnels within the Ngau Tam Mei Landfill (NTML) Consultation Zone during the construction and operation phases.

11.2            The precautionary measures to minimise landfill gas risk are summarised in the Implementation Schedule.

Monitoring Parameters, Locations and Frequency

11.3            Monitoring of landfill gas shall be conducted during the construction of the tunnels and after the completion of tunnel construction works.  Before the commencement of the operation, the monitoring data gathered should be reviewed with EPD and to determine and confirm the need for monitoring and if required the monitoring requirements during the operation of the Project.

11.4            The proposed parameters, locations and frequency of landfill gas monitoring for various phases of Project are summarised in Table 11.1.

Table 11.1         Parameters, Locations and Frequency of Landfill Gas Monitoring

 

Phase

Monitoring Location

Monitoring Frequency

Monitoring Parameters

(% v/v or %LEL)

Construction

Tunnels within the NTML Consultation Zone (1)

At least daily

·     Methane

·     Carbon Dioxide

·     Oxygen

After completion of tunnel construction work and at least 3 months before commencement of operation

Walkover survey at all joints and cracks, if identified, within the tunnels within the NTML Consultation Zone (2)

Once

·     Methane

·     Carbon Dioxide

·     Oxygen

 

Walkover survey at 20m intervals for section of tunnels under NTML and 50m interval within the NTML Consultation Zone (2)

Weekly

·     Methane

·     Carbon Dioxide

·     Oxygen

Operation

Walkover survey at all joints and cracks, if identified, within the tunnels within the NTML Consultation Zone (3)

Annually

·     Methane

·     Carbon Dioxide

·     Oxygen

 

Walkover survey at 20m intervals for the section of tunnels under NTML and 50m intervals within the NTML Consultation Zone (3) (4)

Weekly (4)

·     Methane

·     Carbon Dioxide

·     Oxygen

Notes:

(1) The monitoring shall be conducted before starting the work of the day

(2) The walkover survey shall be conducted under non-ventilated condition and before starting the work of the day.

(3) The walkover survey shall be conducted under non-ventilated condition and before the first train operates and start-up of ventilation, if applicable.

(4) Tentative schedule. The actual monitoring requirements shall be discussed and agreed with EPD before the commencement of operation.

Monitoring Equipment

11.5            The instrument should be able to measures flammable gas concentration (calibrated with methane gas) in the range of 1 to 10,000 ppm.  The instrument should be intrinsically safe if used in confined area.  The walkover survey should be conducted at a slow pace with the inlet tube of the meter probe a few centimetres above ground surface or close the construction joints / cracks of the tunnels.

Event/Action Plan

Construction Phase

11.6            The trigger levels and actions in the event of gas being detected are detailed in Table 11.2.

Table 11.2         Actions in the Event of Gas Being Detected

 

Parameter

Measurement

Action

O2

< 19% v/v

Increase underground ventilation to restore O2 to >19% v/v

 

 

< 18% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore O2 to >19% v/v

CH4

> 10% LEL

Prohibit hot works

Increase ventilation to restore CH4 to <10% LEL

 

 

>20% LEL

Stop works

Evacuate all personnel

Increase ventilation further to restore CH4 to <10% LEL

CO2

>0.5% v/v

Increase ventilation  to restore CO2 to <0.5% v/v

 

 

> 1.5% v/v

Stop works

Evacuate all personnel

Increase ventilation further to restore CO2 to <0.5%

After Completion of Tunnel Construction Works and Before Commencement of Operation

11.7            Weekly monitoring shall be conducted during this period.  Should methane concentration be higher than 10% LEL, mechanical ventilation is required to be switched on 30 minutes before starting the work of the day and throughout the working day.  In addition, the monitoring frequency should be increased to daily.  If the situation persists in three consecutive occasions, inspection of tunnel seals/ joints should be carried out to identify the location of potential gas ingress.  Rectifications, such as sealing of cracks, shall be carried out.  The daily monitoring requirement can be resumed to weekly if the concentration of methane is consistently below 10% LEL in 7 consecutive days and the ventilation requirement can be resumed to normal.

Operational Phase

11.8            Weekly monitoring is tentatively proposed for the operational phase.  Should methane concentration be higher than 10% LEL, mechanical ventilation is required to be switched on at least 30 minutes before the first train operates to sufficiently dilute the concentration of methane to well below the lower explosive limit to ensure that no explosion will occur when the trains pass through the tunnel until the end of the daily operation.  The monitoring frequency should be increased to daily.  If the situation persists in three consecutive occasions, inspection of tunnel seals/ joints should be carried out to identify the location of potential gas ingress.  Rectifications, such as sealing of cracks, shall be carried out.  The daily monitoring requirement can be resumed to weekly if the concentration of methane is consistently below 10% LEL in 7 consecutive days and the mechanical ventilation requirement can be resumed back to normal condition.