2.1
Main terrestrial ecological impact
would not be significant in relation to low value habitat loss. About 60% of the total affected habitat
loss area is developed area / wasteground.
Mitigation measures such as ecologically friendly channel features to
provide aquatic habitats for wildlife use and good construction site practices
would be implemented.
2.2
There would also be limited marine
ecological impact to sub-tidal and intertidal habitats with implementation of good
construction site practices.
2.3
Limited fisheries impact is
anticipated during the construction and operation phases with the
implementation of good construction site practices.
2.4
A monitoring and audit programme would be in place to monitor
the impacts from the Project on ecological and fisheries resources.
Detailed Design Phase
2.5
During detailed design phase, an ecological
habitat management plan and ecological friendly design of the proposed open channel
in the SSS, should be developed.
Construction Phase
2.6
The
ecological and fisheries mitigation measures recommended in the EIA report are
outlined in the Implementation Schedule (IS) (Appendix A). In the
event of receipt of complaint and/or observation on non-compliance or area of
improvement during the construction phase, the Contractor should review the
effectiveness of these mitigation measures and propose, design and implement
alternative or additional measures as appropriate.
Operational Phase
2.7
The IS for the recommended
mitigation measures is presented in Appendix
A. These measures should be reviewed,
and refined if necessary, by the MTRC during the detailed design phase to confirm
that they are adequate for minimising potential operational impacts.
2.8
To detect changes and to monitor
the effectiveness of the proposed mitigation measures, ecological monitoring
should be conducted for any works where adverse ecological impacts (without
mitigation measures in place) and any uncertainties are anticipated.
Ecological Impact Monitoring
2.9
Mitigation measures have been
proposed under this Project to control any potential indirect impact to the
avifauna utilizing areas of conservation interest which are sensitive to
disturbance. Impact monitoring
should therefore be conducted during construction phase to monitor the
effectiveness of proposed mitigation measures and detect any unpredicted
indirect ecological impacts arising from the proposed Project. Remedial actions can then be
recommended, where appropriate, based on the impact monitoring results.
2.10
Ecological impact monitoring focusing
on habitats and species of conservation interest should be conducted during the
construction phase at the MPV, TPP, SSS / ERS, PHV, and TUW sites where a
number of avifauna of conservation interest (e.g. overwintering bird, Greater
Painted-snipe) and areas of conservation interest (e.g. country parks,
conservation areas, and wetlands) were recorded.
2.11
Avifaunal communities should be surveyed
quantitatively along transects. Birds
heard or seen along the transects should be identified to species and counted. The nature
of construction works within works area conducting during each impact monitoring
visit should also be recorded. The
quantitative monitoring results should be compared to pre-construction condition. The impact monitoring results should be undertaken
by qualified ecologist(s) with relevant working experience. Should any unpredicted indirect
ecological impacts arising from the proposed Project be detected, remedial
measures should be developed and implemented by the Contractor. The implementation details of the impact
monitoring programme should be described in ecological monitoring plan for Environmental
Protection Department (EPD) approval before commencement of construction
activities. The location, frequency
and duration of construction impact monitoring are provided in Table 2.1.
Table 2.1 Requirement
of Construction Impact Monitoring for Avifaunal Group
Works Area |
Monitoring Location |
Monitoring
Frequency |
Monitoring
Duration |
MPV |
l
Fishponds in Wetland Conservation Area (WCA) within |
Weekly |
During erection of site hoarding |
Monthly |
During construction phase of MPV
works area |
||
Access road leading to TPP |
l
The whole alignment of drainage channel KT5 l
The section of drainage channel 95CD along the proposed
alignment of access upgrading l
The whole alignment of abandoned meander of conservation
interest 43CD-1 |
Weekly |
During erection of site hoarding |
Monthly |
During upgrading and operation of
access road for construction phase activities |
||
Access road leading to SSS / ERS |
l
The section of drainage channel 95CD along the proposed
alignment of access upgrading l
The whole alignment of abandoned meanders of conservation
interest 95CD-4 and 95CD-5 |
Weekly |
During erection of site hoarding |
Monthly |
During upgrading of and operation
access road for construction phase activities |
||
SSS / ERS |
l
Agricultural land within |
Monthly |
During construction phase of SSS /
ERS works area |
TUW |
l
Agricultural land within l
|
Monthly |
During construction phase of TUW
works area |
PHV |
l
|
Monthly |
During construction phase of PHV
works area |
Monitoring of Mitigation Stream Habitats
2.12
Mitigation stream habitats will be
provided within the scheme boundary of the SSS / ERS site in the operational
phase. It is anticipated that the
mitigation stream habitats would provide habitats of similar ecological value
and function to the wildlife utilising the existing watercourse habitats. Prior to commencement of channel works, the
ecological habitat management plan should be prepared to outline the operational
phase ecological monitoring requirements for the mitigation stream habitats.
Monitoring of Impact from Groundwater Drawdown
2.13
Groundwater levels will be
monitored along the whole Project alignment in pre-construction and
construction stages as part of the comprehensive groundwater monitoring
strategy (details refer to EIA Report Appendix
11.8B Hydrogeological Impact Assessment). A monitoring and emergency response plan
(to be prepared by the Contractor), in relation to potential impacts due to
groundwater drawdown, will form part of the EM&A requirement in this
EM&A Manual subject to approval by EPD and Agriculture, Fisheries and
Conservation Department (AFCD) before commencement of the tunnelling and MPV
construction in
Monitoring of Impact from Noise and Vibration
2.14
A monitoring and emergency response
plan (to be prepared by the Contractor), in relation to potential impacts on
fishponds in
2.15
To
safeguard against adverse ecological and fisheries impacts from the
construction of the Project, regular site inspections should be conducted to
ensure proper implementation of the recommended mitigation measures. Section
12 of the Manual sets out inspection requirements and the programme for
verifying the implementation and evaluating the effectiveness of the mitigation
measures.