Table 11.1 Project
Implementation Schedule
EIA Ref |
EM&A Log Ref. |
Environmental Protection
Measures* |
Location /Duration of
measures/ Timing of completion of measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and
Guidelines |
|||
Des |
C |
O |
Dec |
||||||
A Air Quality |
|||||||||
3.73 |
2.5 |
Air
Pollution Control (Construction Dust) Regulation & Good Site Practices ·
Use of regular watering, with complete coverage, to reduce dust
emissions from exposed site surfaces and unpaved roads, particularly during
dry weather. ·
Use of frequent watering for particularly dusty construction areas and
areas close to ASRs. ·
Side enclosure and covering of any aggregate or dusty material storage
piles to reduce emissions. Where
this is not practicable owing to frequent usage, watering should be applied
to aggregate fines. ·
Open stockpiles should be avoided or covered. Where possible, prevent placing dusty
material storage piles near ASRs. ·
Tarpaulin covering of all dusty vehicle loads transported to, from and
between site locations. ·
Establishment and use of vehicle wheel and body washing facilities at
the exit points of the site. ·
Provision of wind shield and dust extraction units or similar dust
mitigation measures at the loading points, and use of water sprinklers at the
loading area where dust generation is likely during the loading process of
loose material, particularly in dry seasons/ periods. ·
Imposition of speed controls for vehicles on unpaved site roads. 8 kilometers per hour is the
recommended limit. ·
Where possible, routing of vehicles and positioning of construction
plant should be at the maximum possible distance from ASRs. ·
Every stock of more than 20 bags of cement or dry pulverised fuel ash
(PFA) should be covered entirely by impervious sheeting or placed in an area
sheltered on the top and the 3 sides. ·
Cement or dry PFA delivered in bulk should be stored in a closed silo
fitted with an audible high level alarm which is interlocked with the
material filling line and no overfilling is allowed. ·
Loading, unloading, transfer, handling or storage of bulk cement or
dry PFA should be carried out in a totally enclosed system or facility, and
any vent or exhaust should be fitted with an effective fabric filter or
equivalent air pollution control system |
Construction
Site/During Construction Period |
Contractor |
|
Ö |
|
|
Air Pollution Control
(Construction Dust) Regulation |
3.78 |
2.7 & 2.13 – 2.19 |
·
Commissioning tests shall be conducted to confirm the centralized air
pollution control unit, the cogen units and the standby
flaring unit against the design emission levels as stated in Tables 3.7 – 3.9. ·
Odour monitoring shall be conducted at the stack exhaust of the
centralized air pollution control unit weekly in the first month of the
commissioning stage. |
OWTF Stacks/ During Design
& Commissioning Stage |
Contractor |
Ö |
|
Ö |
|
EIAO-TM |
3.78 |
2.7-2.12 |
Air Pollution Control and Stack Monitoring · Stack monitoring shall be
installed for the centralized air pollution control unit and cogen units of OWTF to ensure that the air emissions from
OWTF would meet the design emission limits as well as EPD criteria. |
OWTF Stacks/ During design
& Operation |
OWTF Operator |
Ö |
|
Ö |
|
EIAO-TM |
3.78 |
2.20-2.28 |
· Odour Patrol at site
boundary of OWTF |
OWTF Site Boundary/During
Operation (The need to
continue the odour patrol after the end of the 2-year monitoring period would
depend on the monitoring results and should be agreed with EPD) |
OWTF Operator |
Ö |
|
Ö |
|
EIAO-TM |
B Hazard
to Life |
|||||||||
4.102 |
3.3 |
Construction Phase · The number of workers on
site during construction stage should be kept at the same level as the
assessment. · Construction works should
be suspended when delivery of chlorine takes place. · 3m high fence should be
constructed along the boundary facing the SHWWTW. · Emergency evacuation
procedures should be formulated and the Contractor should ensure all workers
on site should be familiar with these procedures as well as the route to
escape in case of gas release incident. Relevant Departments, such as Fire
Services Department (FSD), should be consulted during the development of
Emergency procedures. Diagram showing the escape routes to a safe place
should be posted in the site notice boards and at the entrance/exit of site.
A copy of the latest version emergency procedures should be dispatched to
Tung Chung Fire Station for reference once available. · The emergency procedures
should specify means of providing a rapid and direct warning (e.g. Siren and
Flashing Light) to construction workers in the event of chlorine gas release
in the SHWWTW. · The Contractor should
establish a communication channel with the SHWWTW operation personnel and FSD
during construction stage. In case of any hazardous incidents in the
treatment works, operation personnel of SHWWTW should advise the Contractor
to inform construction workers to proceed with emergency procedure. The
Contractor should appoint a Liaison Officer to communicate with FSD Incident
Commander on site in case of emergency. · Introduction training
should be provided to any staff before carryout construction works at the
Project site. · Periodic drills should be
coordinated and conducted to ensure all construction personnel are familiar
with the emergency procedures. Upon completion of the drills, a review on
every step taken should be conducted to identify area of improvement. Prior
notice of periodic drills should be given to Station Commander of Tung Chung
Fire Station. Joint operational exercise with FSD and SHWWTW is recommended. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
|
4.103 |
3.4 |
Design Phase · The site office should be
close to the western boundary of the Project site and away from the SHWWTW’s
chlorine store as far as possible. |
Work
Site / During Design Period |
OWTF
operator |
Ö |
|
|
|
|
4.103 |
3.4 |
Operation Phase · 3m high fence should be
constructed along the boundary facing the SHWWTW · Emergency evacuation procedures should be
formulated and the Contractor should ensure on site staff should be familiar
with these procedures. Diagram showing the escape routes to a safe place
should be posted in the site notice boards and at the entrance/exit of site.
A copy of the latest version emergency procedures should be dispatched to
Tung Chung Fire Station for reference once available. · The emergency procedures
should specify means of providing a rapid and direct warning (e.g. Siren and
Flashing Light) to personnel on site in the event of chlorine gas release in
the SHWWTW. · The Contractor should
establish a communication channel with the SHWWTW operation personnel and
FSD. In case of any hazardous incidents in the treatment works, operation
personnel of SHWWTW should advise the Contractor to inform personnel on site
to proceed with emergency procedure. The Contractor should appoint a Liaison
Officer to communicate with FSD Incident Commander on site in case of
emergency. · Periodic drills should be
coordinated and conducted to ensure all on site personnel are familiar with
the emergency procedures. Upon completion of the drills, a review on every
step taken should be conducted to identify area of improvement. Prior notice
of periodic drills should be given to Station Commander of Tung Chung Fire
Station. Joint operational exercise with FSD and SHWWTW is recommended. |
Work
Site / During Operation Period |
Contractor |
|
|
Ö |
|
|
C Water Quality |
|||||||||
5.44 |
4.5 |
Construction site run-off and general construction
activities: The mitigation measures as
outlined in the ProPECC PN 1/94 Construction Site Drainage should be adopted
where applicable. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO |
5.45 |
4.5 |
Excavation of Soil Materials |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO |
5.46 |
4.5 |
Accidental
spillage of chemicals: Contractor must register
as a chemical waste producer if chemical wastes would be produced from the
construction activities. The
Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular
the Waste Disposal (Chemical Waste) (General) Regulation should be observed
and complied with for control of chemical wastes. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO, WDO |
5.47 |
4.5 |
Maintenance of vehicles
and equipments involving activities with potential for leakage and spillage
should only be undertaken within the areas which appropriately equipped to
control these discharges. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO, WDO |
5.48 |
4.5 |
Oils and fuels should only
be used and stored in designated areas which have pollution prevention
facilities. All fuel tanks and
storage areas should be sited on sealed areas in order to prevent spillage of
fuels and solvents to the nearby watercourses. All waste oils and fuels should be
collected in designated tanks prior to disposal. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO, WDO |
5.49 |
4.5 |
Disposal of chemical
wastes should be carried out in compl · Suitable containers should be used to hold the
chemical wastes to avoid leakage or spillage during storage, handling and
transport. · Chemical waste containers should be suitably labeled,
to notify and warn the personnel who are handling the wastes, to avoid
accidents. · Storage area should be selected at a safe location on
site and adequate space should be allocated to the storage area. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO, WDO |
5.50 |
4.5 |
Construction solid waste,
debris and rubbish on site should be collected, handled and disposed of
properly to avoid entering to the nearby watercourses. Stockpiles of cement and other
construction materials should be kept covered when not being used. Rubbish and litter from construction
sites should also be collected to prevent spreading of rubbish and litter
from the site area. It is
recommended to clean the construction sites on a regular basis. |
Construction
Site/ During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, ProPECC PN 1/94;
WPCO, WDO |
5.51 |
4.5 |
Sewage Effluent The presence of
construction workers generates sewage.
It is recommended to provide sufficient chemical toilets in the works
areas. The toilet facilities
should be more than 30m from any watercourse. A licensed waste collector should be
deployed to clean the chemical toilets on a regular basis. |
Work
Site / During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
5.52 |
4.5 |
Notices should be posted
at conspicuous locations to remind the workers not to discharge any sewage or
wastewater into the nearby environment during the construction phase of the
project. Regular environmental
audit on the construction site can provide an effective control of any
malpractices and can achieve continual improvement of environmental
performance on site. |
Work
Site / During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
5.53 |
4.5 |
To minimize the potential water quality impacts from
the nullah reconstruction works, the practices outlined below should be
adopted where applicable: The proposed works should
be carried out within the dry season between October and March when the flow
in the open nullah is low. The use of less or
smaller construction plants may be specified to reduce the disturbance to the
nullah bed. Temporary storage
of materials (e.g. equipment, filling materials, chemicals and fuel) and
temporary stockpile of construction materials should be located well away
from the nullah and any water courses during carrying out of the construction
works. Stockpiling of
construction materials and dusty materials should be covered and located away
from the nullah any water courses. Construction
debris and spoil should be covered up and/or disposed of as soon as possible
to avoid being washed into the nullah and nearby water receivers. Construction
activities, which generate large amount of wastewater, should be carried out
in a distance away from the nullah, where practicable. Construction
effluent, site run-off and sewage should be properly collected and/or
treated. Any works site
inside the nullah should be temporarily isolated,
such as by placing of sandbags or silt curtains with lead edge at bottom and
properly supported props to prevent adverse impact on the water quality. Proper shoring may
need to be erected in order to prevent soil/mud from slipping into the nullah
and nearby watercourse. Supervisory staff
should be assigned to station on site to closely supervise and monitor the
works. |
Work
Site / During Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM, WPCO |
5.54 |
4.5 |
Wastewater
from Organic Waste Treatment Process The Project site will be
equipped with an adequately sized wastewater treatment plant. A high rate type of active sludge
system specifically designed for the removal of nitrogen components from the wastewater in combination with conversion
of residual BOD and COD would be deployed. The wastewater treatment plant would
also be incorporated with SHARON or annamox technology or equivalent to
achieve high total overall nitrogen removal. Wastewater generated from the OWTF
(including wastewater from dewatering process, leachate from waste reception
area, condensate from biogas handling, wastewater from scrubber of air treatment
system and any surplus water from truck washing facility) will be diverted to
the wastewater treatment plant.
Treated effluent will then be stored temporarily in order to be used
as process water within the plants.
The storage volume would be around 20 m3. Overflow from the tank will be discharged
to foul sewers. The polluting
parameters in effluent shall be in compl ·
Cleaning and maintenance of treatment facilities
should be conducted on a regular basis to ensure that removal rate of each
treatment facility would not be reduced. ·
Cleaning and maintenance of pipelines should be
carried out on a regular basis to prevent block of pipeline and leaching of
wastewater, and therefore prevent overflowed or leached wastewater
discharging into nearby drainages and water streams. · Regular site
inspection should be conducted to ensure that no wastewater can be directly
discharged into nearby water streams. |
Work
Site / During Design & Operation Period |
OWTF
Operator |
|
|
Ö |
|
TM-DSS; WPCO; WDO |
5.55 |
4.5 |
In the scrubber, spraying water should be
re-circulated to minimize the need for external water. The spraying water would be collected
at the bottom of the scrubber.
Excess water would be discharged to the wastewater treatment plant as
described in Section 5.54. |
Work Site / During Design & Operation Period |
OWTF
Operator |
Ö |
|
Ö |
|
TM-DSS; WPCO; WDO |
5.56 |
4.5 |
The waste reception, treatment facilities and compost
storages of OWTF should be located in enclosed buildings to prevent
generation of contaminated rain runoff. All surface runoff such as
washed water generated in the treatment processes areas should be properly
collected and diverted to the on-site wastewater treatment plant as described
in Section 5.54. |
Work Site / During Design & Operation Period |
OWTF
Operator |
Ö |
|
Ö |
|
TM-DSS; WPCO; WDO |
5.57 |
4.5 |
All drainage system for collection and transferring
wastewater generated in the OWTF to the on-site wastewater treatment plant as
described in Section 5.54 should be capable of preventing clogging and easy
maintenance and cleaning. |
Work Site / During Design & Operation Period |
OWTF
Operator |
Ö |
|
Ö |
|
TM-DSS; WPCO; WDO |
D.1 Waste
Management |
|||||||||
6.41 |
5.4 |
Good Site Practices Recommendations for good
site practices during the construction phase would include: ·
Obtain relevant waste
disposal permits from appropriate authorities, in accordance with the Waste Disposal
Ordinance (Cap. 354) and subsidiary Regulations and the Land (Miscellaneous
Provisions) Ordinance (Cap. 28); ·
Provide staff training
for proper waste management and chemical handling procedures; ·
Provide sufficient waste
disposal points and regular waste collection; ·
Provide appropriate
measures to minimize windblown litter and dust during transportation of waste
by either covering trucks or by transporting wastes in enclosed containers; ·
Carry out regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors; ·
Separate chemical wastes
for special handling and disposed of to licensed facility for treatment; and ·
Employ licensed waste
collector to collect waste. |
Work Site / During Construction Period |
Contractor |
|
Ö |
|
|
WDO;
LDO; ETWB TCW No. 19/2005 |
6.42 |
5.5 |
Waste Reduction Measures Waste reduction is best
achieved at the planning and design stage, as well as by ensuring the
implementation of good site practices.
Recommendations to achieve waste reduction include: ·
Design foundation works
that could minimise the amount of excavated material to be generated; ·
Provide training to
workers on the importance of site cleanliness and appropriate waste
management procedures, including waste reduction, reuse and recycling; ·
Sort out demolition
debris and excavated materials from demolition works to recover reusable/
recyclable portions (i.e. soil, broken concrete, metal etc.); ·
Segregate and store
different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal; ·
Encourage the collection
of aluminium cans by providing separate labelled bins to enable this waste to
be segregated from other general refuse generated by the workforce; and ·
Plan and stock
construction materials carefully to minimize the amount of waste to be
generated and to avoid unnecessary generation of waste. |
Work Site / During Design & Construction Period |
Contractor |
Ö |
Ö |
|
|
|
6.44 |
5.7 |
Excavated
and C&D Materials ·
A WMP, which becomes part
of the Environmental Management Plan (EMP), should be prepared in accordance
with ETWB TCW No.19/2005; ·
A recording system for
the amount of wastes generated, recycled and disposed of (including the disposal
sites) should be adopted for easy tracking; and · In order to monitor the disposal of excavated and C&D material at
public filling facilities and landfills and to control fly-tipping, a
trip-ticket system should be adopted (refer to ETWB TCW No. 31/2004). |
Work Site / During Design & Construction Period |
Contractor |
Ö |
Ö |
|
|
ETWB
TCW No. 33/2002;ETWB TCW No. 19/2005 ETWB
TCW No. 31/2004 |
6.45
– 6.46 |
5.8-5.9 |
An EMP should be prepared and implemented in accordance with ETWB TCW
No. 19/2005 which describes the arrangements for avoidance, reuse, recovery,
recycling, storage, collection, treatment and disposal of different
categories of waste to be generated from construction activities. The EMP should be submitted to the
Supervising Officer (SO) and Supervising Officer’s Representative (SOR) for
approval. The EMP should be
reviewed regularly and updated, preferably on a monthly basis. A system should be
devised to work for on-site sorting of excavated and C&D materials and
promptly removing all sorted and process materials arising from the
construction activities to minimize temporary stockpiling on-site. The system should be included in the
EMP identifying the source of generation, estimated quantity, arrangement for
on-site sorting, collection, temporary storage areas and frequency of
collection by recycling Contractors or frequency of removal off-site. |
Work Site / During Design & Construction Period |
Contractor |
Ö |
Ö |
|
|
ETWB
TCW No. 19/2005 |
6.47 |
5.10 |
Should chemical wastes be
produced at the construction site, the Contractor would be required to
register with EPD as a Chemical Waste Producer and to follow the guidelines
stated in the Code of Practice on the Packaging, Labelling and Storage of
Chemical Wastes. Good quality
containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. Appropriate labels should be securely
attached on each chemical waste container indicating the corresponding chemical
characteristics of the chemical waste (such as explosive, flammable,
oxidizing, irritant, toxic, harmful, or corrosive). The Contractor should employ a
licensed collector to transport and dispose of the chemical wastes, to either
the CWTC in Tsing Yi, or any other licensed facilities, in accordance with
the Waste Disposal (Chemical Waste) (General) Regulation. |
Work Site / During Construction Period |
Contractor |
|
Ö |
|
|
Waste
Disposal (Chemical Waste) (General) Regulation |
6.48 |
5.11 |
General Refuse |
Work Site / During Construction Period |
Contractor |
|
Ö |
|
|
Public
Health and Municipal Services Ordinance |
6.50 |
5.12 |
Good Site Practices Good operational
practices should be adopted to minimise waste management impacts: ·
Obtain the necessary
waste disposal permits from the appropriate authorities, in accordance with
the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Chemical Waste)
(General) Regulation and the Land (Miscellaneous Provision) Ordinance (Cap.
28); ·
Nomination of an approved
person to be responsible for good site practice, arrangements for collection
and effective disposal to an appropriate facility of all wastes generated at
the site; ·
Use of a waste haulier
licensed to collect specific category of waste; ·
A trip-ticket system
should be included as one of the contractual requirements and implemented by
the Environmental Team to monitor the disposal of solid wastes at public
filling facilities and landfills, and to control fly tipping. Reference
should be made to ETWB TCW No. 31/2004. ·
Training of site
personnel in proper waste management and chemical waste handling procedures; ·
Separation of chemical
wastes for special handling and appropriate treatment at a licensed facility; ·
Routine cleaning and
maintenance programme for drainage systems, sumps and oil interceptors; ·
Provision of sufficient
waste disposal points and regular collection for disposal; ·
Adoption of appropriate
measures to minimize windblown litter and dust during transportation of
waste, such as covering trucks or transporting wastes in enclosed containers;
and ·
Implementation of a
recording system for the amount of wastes generated, recycled and disposed of
(including the disposal sites). |
During Operation Period |
OWTF Operator |
|
|
Ö |
|
WDO; Waste
Disposal (Chemical Waste) (General) Regulation; Land
(Miscellaneous Provision) Ordinance (Cap. 28); ETWB
TCW No. 31/2004 |
6.51 |
5.13 |
Waste Reduction Measures Good management and
control can prevent the generation of significant amounts of waste. It is
recommended that the following good operational practices should be adopted
to ensure waste reduction: ·
Segregation and storage
of different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal; ·
Encourage collection of
aluminium cans, plastic bottles and packaging material (e.g. carton boxes)
and office paper by individual collectors. Separate labelled bins should be
provided to help segregate this waste from other general refuse generated by
the work force; and ·
Any unused chemicals or
those with remaining functional capacity should be reused as far as
practicable. |
During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.52 |
5.14 |
Wastes Generated from
Pre-Treatment Process |
Pre-Treatment Process / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.53-6.56 |
5.15-5.18 |
Chemical Wastes ·
Plant / equipment maintenance schedules should be
planned in order to minimize the generation of chemical waste. ·
Non-recyclable chemical wastes and lubricants should
be disposed of at appropriate facilities, such as CWTC. Copies or counterfoils from collection
receipts issued by the licensed waste collector should be kept for recording
purpose. |
Whole Site / During Operation Period |
OWTF Operator |
|
|
Ö |
|
Waste Disposal (Chemical
Waste) (General) Regulation |
6.57-6.58 |
5.19-5.20 |
General Refuse |
Whole Site / During Operation Period |
OWTF Operator |
|
|
Ö |
|
Public
Health and Municipal Services Ordinance |
D.2 Proposed Land
Contamination Preventive Measures |
|||||||||
6.65 |
5.21 (i) |
Fuel Oil Containers ·
Fuel oil should be stored in suitable containers. ·
All fuel oil containers should be securely closed. ·
Appropriate labels showing the name of fuel oil
should be posted on the containers. ·
Drip trays should be provided for all containers. |
Fuel Oil Storage Containers / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.65 |
5.21 (ii) |
Storage Area ·
Distance between the fuel oil refuelling points and
the fuel oil containers should be minimized. ·
The storage area should be used for fuel oil storage
only. ·
No surface water drains or foul sewers should be
connected to the storage area. ·
The storage area should be enclosed by three sides
by a wall and have an impermeable floor or surface. |
Fuel Oil Storage Area / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.65 |
5.21 (iii) |
Fuel Oil Spillage
Response ·
Training Training on oil spill response actions should be
given to relevant staff. The training should cover the followings: - Tools &
resources to combat oil spillage and fire, e.g. locations of oil spill
handling equipment and fire fighting equipment; - General methods to
deal with oil spillage and fire incidents; - Procedures for
emergency drills in the event of oil spills and fire; and - Regular drills
should be carried out. ·
Communication
Establish communication channel with the Fire
Services Department (FSD) and EPD to report any oil spillage incident so that
necessary assistance from relevant department could be quickly sought. ·
Response
Procedures Any fuel oil spillage within the Project Site should
be immediately reported to the Site Manager with necessary details including
location, source, possible cause and extent of the spillage. Site Manager should immediately attend to the
spillage and initiate any appropriate action to confine and clean up the
spillage. The response procedures should include the following: - Identify and
isolate the source of spillage as soon as possible. - Contain the oil
spillage and avoid infiltration into soil/ groundwater and discharge to storm
water channels. - Remove the oil
spillage. - Clean up the
contaminated area. - If the oil spillage
occurs during refuelling, the refuelling operation should immediately be
stopped. - Recovered
contaminated fuel oil and the associated material to remove the spilled oil
should be considered as chemical waste. The handling and disposal
procedures for chemical wastes are discussed in the following paragraphs. |
Whole Site / During Operation Phase |
OWTF Operator |
|
|
Ö |
|
|
6.66 |
5.22 (i) |
Chemicals and Chemical
Wastes Handling & Storage ·
Chemicals and chemical wastes should only be stored
in suitable containers in purpose-built areas. ·
The storage of chemical wastes should comply with
the requirements of the Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes. ·
The storage areas for chemicals and chemical wastes
should have an impermeable floor or surface. The impermeable floor /
surface should possess the following properties: - Not liable to
chemically react with the materials and their containers to be stored. - Able to withstand
normal loading and physical damage caused by container handling - The integrity and
condition of the impermeable floor or surface should be inspected at regular
intervals to ensure that it is satisfactorily maintained ·
For liquid chemicals and chemical wastes storage,
the storage area should be bunded to contain at least 110% of the storage
capacity of the largest containers or 20% of the total quantity of the
chemicals/chemical wastes stored, whichever is the greater. ·
Storage containers should be checked at regular
intervals for their structural integrity and to ensure that the caps or fill
points are tightly closed. ·
Chemical handling should be conducted by trained
workers under supervision. |
Whole Site / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.66 |
5.22 (ii) |
Chemicals and Chemical
Wastes Spillage Response ·
Training Training on spill response actions should be given
to relevant staff. The training should cover the followings: - Tools &
resources to handle spillage, e.g. locations of spill handling equipment; - General methods to
deal with spillage; and - Procedures for
emergency drills in the event of spills. ·
Communication Establish communication channel with Fire Services
Department (FSD) and EPD to report the spillage incident so that necessary
assistance from relevant department could be quickly sought. ·
Response
Procedures Any spillage within OWTF site should be reported to
the Site Manager. Site Manager shall attend to the spillage and
initiate any appropriate actions needed to confine and clean up the
spillage. The response procedures should include the followings: - Identify and
isolate the source of spillage as soon as possible; - Contain the
spillage and avoid infiltration into soil / groundwater and discharge to
storm water channels (in case the spillage occurs at locations out of the
designated storage areas); - Remove the
spillage; the removal method / procedures documented in the Material Safety
Data Sheet (MSDS) of the chemicals spilled should be observed; - Clean up the
contaminated area (in case the spillage occurs at locations out of the
designated storage areas); and - The waste arising
from the cleanup operation should be considered as chemical wastes. |
Whole Site / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
6.67
– 6.69 |
5.23-5.25 |
Incident Record ·
After any spillage, an incident report should be
prepared by the Site Manager. The incident report should contain
details of the incident including the cause of the incident, the material
spilled and estimated spillage amount, and also the response actions
undertaken. The incident record should be kept carefully and able to be
retrieved when necessary. ·
The incident report should provide sufficient
details for the evaluation of any environmental impacts due to the spillage
and assessment of the effectiveness of measures taken. ·
In case any spillage or accidents results in
significant land contamination, EPD should be informed immediately and the
Project operator should be responsible for the cleanup of the affected
area. The responses procedures described in Sections 6.65-6.66 of the
EIA Report should be followed accordingly together with the land
contamination assessment and remediation guidelines stipulated in the Guidance Manual for Use of Risk-based
Remediation Goals for Contaminated Land Management and the Guidance Note for Contaminated Land
Assessment and Remediation. |
Whole Site / During Operation Period |
OWTF Operator |
|
|
Ö |
|
|
E Landscape and
Visual |
|||||||||
7.99
& Table 7.7 |
Table
6.1 |
Construction
Phase ·
Topsoil,
where identified, should be stripped and stored for re-use in the
construction of the soft landscape works, where practical ·
Compensatory
tree planting should be provided to compensate for felled trees. - Compensation tree species
shall be chosen from both indigenous and ornamental species - Compensatory tree planting
quantities shall be as per DLO approved requirement. ·
Control of
night-time lighting ·
Erection of
decorative screen hoarding compatible with the surrounding setting |
Construction Site/During Design & Construction Stages |
Contractor |
Ö |
Ö |
|
|
|
7.98
& Table 7.8 |
Table
6.2 |
Operation
Phase ·
Aesthetic
design of the façade, including its colour theme, pattern, texture,
materials, finishing and associated structures to harmonize with the
surrounding settings ·
Grass/
groundcover planting to soften the roof ·
Heavy standard
tree planting to screen proposed associated structures ·
Grasscrete paving to
soften the harshness of large paved surface areas wherever possible |
Within Project Area/During Design & Operation
Stages |
OWTF
Operator |
Ö |
|
Ö |
|
|
F Noise |
|||||||||
8.25 |
7.3 |
Good Site Practice: ·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction program; ·
Mobile plant,
if any, should be sited as far from noise sensitive receivers (NSRs) as
possible; ·
Machines and
plant (such as trucks) that may be in intermittent use should be shut down
between work periods or should be throttled down to a minimum; ·
Plant known
to emit noise strongly in one direction should, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs; and ·
Material
stockpiles and other structures should be effectively utilized, wherever
practicable, in screening noise from on-site construction activities. |
Work Site / During
Construction Period |
Contractor |
|
Ö |
|
|
EIAO-TM,
NCO |
* All recommendations and requirements resulted
during the course of EIA Process.
* Des=Design; C=Construction; O=Operation;
Dec=Decommissioning