5              water quality

Introduction

5.1          The Project is to construct and operate a biological treatment facility to convert source-separated organic waste into compost and biogas.  A process flow diagram is illustrated in Figure 2.3. 

5.2          During construction phase, the key concerns would include the potential water quality impacts from site run-off, sewage from workforce, and discharge of wastewater from various construction activities.  During operational phase, wastewater would be generated from organic waste treatment processes, which might have potential water quality impacts on the water environment, if uncontrolled.

5.3          This section identifies and assesses potential water quality impacts associated with the construction and operation of the Project.  Recommendations for mitigation measures have been provided to minimise potential adverse water quality impacts and to ensure the acceptability of any residual impacts.

Environmental Legislation, Policies, Plans, Standards and Criteria

Water Pollution Control Ordinance (WPCO)

5.4          The Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) is issued by the EPD under Section 16 of the EIAO.  It specifies the assessment method and criteria that need to be followed in EIA.  Reference sections in EIAO-TM has provided the details of assessment criteria and guidelines that are relevant to the water quality impact assessment, including:

Ÿ  Annex 6 Criteria for Evaluating Water Pollution

Ÿ  Annex 14 Guidelines for Assessment of Water Pollution.

 

Marine Water Quality Objectives

5.5          The Water Pollution Control Ordinance (WPCO) provides the major statutory framework for the protection and control of water quality in Hong Kong.  According to WPCO and its subsidiary legislation, Hong Kong waters are divided into ten Water Control Zones (WCZ).  Corresponding statements of Water Quality Objectives (WQO) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in WCZ based on their beneficial uses.  The study area is located within North Western WCZ and the corresponding WQOs are listed in Table 5.1 in the following.

 Table 5.1          Summary of Water Quality Objectives for the North Western WCZ

Parameters

Objectives

Sub-Zone

Offensive Odour, Tints

Not to be present

Whole zone

Visible foam, oil scum, litter

Not to be present

Whole zone

Dissolved Oxygen (DO) within 2 m of the seabed

Not less than 2.0 mg/L for 90% of samples

Marine waters

Depth-averaged DO

Not less than 4.0 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones and other inland waters

Not less than 4.0 mg/L for 90 % sample

Marine waters

pH

To be in the range of 6.5 - 8.5, change due to human activity not to exceed 0.2

Marine waters excepting Bathing Beach Subzones

To be in the range of 6.5 – 8.5

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

To be in the range of 6.0 –9.0

Other inland waters

To be in the range of 6.0 –9.0 for 95% samples

Bathing Beach Subzones

Salinity

Change due to human activity not to exceed 10% of ambient

Whole zone

Temperature

Change due to human activity not to exceed 2 oC

Whole zone

Suspended solids (SS)

Not to raise the ambient level by 30% caused by human activity

Marine waters

Not to cause the annual median to exceed 20 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

Not to cause the annual median to exceed 25 mg/L

Inland waters

Unionized Ammonia (UIA)

Annual mean not to exceed 0.021 mg/L as unionized form

Whole zone

Nutrients

Shall not cause excessive algal growth

Marine waters

Total Inorganic Nitrogen (TIN)

Annual mean depth-averaged inorganic nitrogen not to exceed 0.3 mg/L

Castle Peak Bay Subzone

Annual mean depth-averaged inorganic nitrogen not to exceed 0.5 mg/L

Marine waters excepting Castle Peak Bay Subzone

Bacteria

Not exceed 610 per 100ml, calculated as the geometric mean of all samples collected in one calendar year

Secondary Contact Recreation Subzones

Should be less than 1 per 100 ml, calculated as the running median of the most recent 5 consecutive samples taken between 7 and 21 days.

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

Not exceed 1000 per 100 ml, calculated as the running median of the most recent 5 consecutive samples taken between 7 and 21 days

Tuen Mun (C) Subzone and other inland waters

Not exceed 180 per 100 ml, calculated as the geometric mean of all samples collected from March to October inclusive. Samples should be taken at least 3 times in one calendar month at intervals of between 3 and 14 days.

Bathing Beach Subzones

Colour

Not to exceed 30 Hazen units

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

Not to exceed 50 Hazen units

Tuen Mun (C) Subzone and other inland waters

5-Day Biochemical Oxygen Demand (BOD5)

Not to exceed 3 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

Not to exceed 5 mg/L

Inland waters

Chemical Oxygen Demand (COD)

Not to exceed 15 mg/L

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

Not to exceed 30 mg/L

Inland waters

Toxins

Should not cause a risk to any beneficial uses of the aquatic environment

Whole zone

Waste discharge shall not cause the toxins in water significant to produce toxic carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms.

Whole zone

Phenol

Quantities shall not sufficient to produce a specific odour or more than 0.05 mg/L as C6 H5OH

Bathing Beach Subzones

Turbidity

Shall not reduce light transmission substantially from the normal level

Bathing Beach Subzones

Source:   Statement of Water Quality Objectives (North Western Water Control Zone).

 

Technical Memorandum

5.6          Discharges of effluents are subject to control under WPCO.  The Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS), issued under Section 21 of WPCO, gives guidance on permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters).  The limits control the physical, chemical and microbial quality of effluent.  Any sewage from the proposed construction and operation activities must comply with the standards for effluent discharged into the foul sewers, inshore waters and marine waters of the North Western WCZ provided in TM-DSS.

Practice Notes

5.7          A practice note (PN) for professional persons was issued by EPD to provide environmental guidelines for handling and disposal of construction site discharges.  The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with various types of discharge from a construction site.  These include surface runoff, groundwater, boring and drilling water, bentonite slurry, water for testing and sterilisation of water retaining structures and water pipes, wastewater from building construction, acid cleaning, etching and pickling wastewater, and wastewater from site facilities. Practices outlined in the ProPECC PN 1/94 should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.

Description of the Environment

5.8          There is no EPD marine water quality monitoring station in vicinity of the Project Site.  The EPD monitoring stations NM1 and NM2 in North Western WCZ are the nearest monitoring stations to the Project Site.  EPD monitoring data collected at these two monitoring stations in 2007 were summarized in Table 5.2.

5.9          According to the “2007 Marine Water Quality in Hong Kong”, which is the latest available information from EPD at the moment of preparing this EIA Report, compliance with WQO for bottom dissolved oxygen (DO), total inorganic nitrogen, and unionised ammonia were achieved at the two monitoring stations.  Compliance with WQO for depth-averaged DO was also achieved at NM2.  However, depth-averaged levels of DO failed to comply with the WQO at station NM1.

Table 5.2           Baseline Marine Water Quality Condition for North Western WCZ

Parameter

Lantau Island (North)

Pearl Island

WPCO WQO

(in marine waters)

NM1

NM2

Temperature (oC)

23.0
(17.2-27.8)

23.4
(17.3-28.4)

Not more than 2oC in daily temperature range

Salinity

30.9
(26.1-33.1)

29.5
(18.8-33.1)

Not to cause more than 10% change

Dissolved Oxygen (DO) (mg/L)

Depth average

5.7
(3.5-9.2)

6.0
(3.3-9.7)

Not less than 4 mg/L for 90% of the samples

Bottom

5.4
(2.7-9.2)

5.7
(3.0-9.6)

Not less than 2 mg/L for 90% of the samples

Dissolved Oxygen (DO)

(% Saturation)

Depth average

79
(49-116)

83
(46-123)

Not Available

Bottom

75
(39-116)

79
(43-121)

Not Available

pH

8.0
(7.4-8.3)

8.0
(7.5-8.4)

6.5 - 8.5 (± 0.2 from natural range)

Secchi disc Depth (m)

1.8
(0.8-3.5)

1.6
(1.1-2.6)

Not Available

Turbidity (NTU)

14.9
(4.3-28.2)

12.5
(4.3-17.4)

Not Available

Suspended Solids (SS) (mg/L)

8.2
(2.3-14.7)

5.8
(1.8-9.3)

Not more than 30% increase

5-day Biochemical Oxygen Demand (BOD5) (mg/L)

1.0
(0.4-1.9)

1.0
(0.4-2.5)

Not Available

Ammonia Nitrogen (NH3-N) (mg/L)

0.13
(0.05-0.21)

0.13
(0.05-0.23)

Not Available

Unionised Ammonia (UIA) (mg/L)

0.005
(0.001-0.007)

0.006
(0.001-0.010)

Not more than 0.021 mg/L for annual mean

Nitrite Nitrogen (NO2-N)  (mg/L)

0.05
(0.006-0.173)

0.063
(0.008-0.207)

Not Available

Nitrate Nitrogen (NO3-N) (mg/L)

0.207
(0.033-0.437)

0.281
(0.034-0.910)

Not Available

Total Inorganic Nitrogen (TIN) (mg/L)

0.39
(0.09-0.70)

0.48
(0.09-1.05)

Not more than 0.5 mg/L for annual mean

Total Kjeldahl Nitrogen (mg/L)

0.30
(0.23 – 0.38)

0.31
(0.22 – 0.41)

Not Available

Total Nitrogen (TN) (mg/L)

0.56
(0.38-0.87)

0.657
(0.31-1.29)

Not Available

Orthophosphate Phosphorus (OrthoP) (mg/L)

0.025
(0.009-0.039)

0.024
(0.006-0.04)

Not Available

Total Phosphorus (TP) (mg/L)

0.05
(0.03-0.08)

0.05
(0.03-0.07)

Not Available

Silica (as SiO2) (mg/L)

1.3
(0.1 – 2.9)

1.5
(0.1 – 4.1)

Not Available

Chlorophyll-a (µg/L)

5.4
(0.7-17.7)

6
(0.7-20.7)

Not Available

E coli

(cfu/100 mL)

670
(56-3100)

360
(49-1900)

Not Available

Faecal Coliforms

(cfu/100 mL)

1500
(160-7400)

820
(150-5000)

Not Available

Notes:    

1.     Data source: Marine Water Quality In Hong Kong in 2007.

2.     Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: surface, mid-depth, bottom.

3.     Data presented are annual arithmetic means of depth-averaged results except for E. coli and faecal coliforms that are annual geometric means.

4.     Data in brackets indicate the ranges.

Water Sensitive Receivers

5.10        The Project Site is located at Siu Ho Wan and it is bounded northeast by North Lantau Highway and southeast by a disturbed headland where the Siu Ho Wan Water Treatment Works (SHWWTW) are located.  There are no particular areas of conservation value, ecological importance or mariculture activities in the vicinity of the Project Site.  No marine water sensitive receivers are identified.  The closest water sensitive receiver would be an open nullah located in the north-western part of the Project area. No water quality monitoring data are available for the nullah.

Assessment Methodology

5.11        Potential sources of water quality impact that may arise during the Project works were described.  All the identified sources of potential water quality impact were then evaluated and their impact significance determined.  The need for mitigation measures to reduce any identified adverse impacts on water quality to acceptable levels was determined.

Identification of Environmental Impacts

Construction Phase

5.12        Potential sources of water quality impact associated with the construction activities for the Project would include:

Ÿ  construction site runoff;

Ÿ  general construction activities;

Ÿ  excavation of soil materials;

Ÿ  accidental spillage;

Ÿ  sewage effluent;

Ÿ  nullah reconstruction activities

Construction Site Runoff

5.13        Soil surfaces would be exposed during construction phase of the Project.  Site runoff generated during a rainstorm would wash away the soil particles on unpaved lands and areas with exposed topsoil.  This runoff is generally characterized by high concentrations of suspended solids.  Directly release of uncontrolled site runoff would increase SS levels and turbidity in the nearby environment.  Site runoff may also wash away contaminated soil particles and therefore cause water pollution.

5.14        Wind blown dust would be generated from exposed soil surfaces in the works areas. It is possible that wind blown dust would fall directly onto the nearby water bodies when a strong wind occurs.  Dispersion of dust within the works areas may increase the SS levels in surface runoff causing a potential impact to the nearby sensitive receivers.

General Construction Activities

5.15        Land-based construction works may have the potential to cause water pollution.  Various types of construction activities would generate wastewater.  These include general cleaning and polishing, wheel washing, dust suppression and utility installation.  These types of wastewater would contain high concentrations of suspended solids.  Wastewater would also be generated from the accumulation of solid waste such as plastic package and construction materials.  If uncontrolled, these would lead to deterioration in water quality.  Increased nutrient level from contaminated discharges and sewage effluent could also lead to a number of secondary water quality impacts including decreases in DO concentration and localised increase in ammonia nitrogen concentrations which could stimulate algal growth.

Excavation of Soil Materials

5.16        The construction of the Project includes excavation of soil materials.  Excavated soil may have to be stored on-site before being sorted, reused or transported to disposal sites.  If stored as open air stockpiles with no cover during rainfall, excavated soils would have a potential risk to be washed away and back into the nearby water environment, thereby causing sudden increase of SS and oxygen demand.

Accidental Spillage and Accumulation of Solid Wastes

5.17        Variety of chemicals would be used for carrying out construction activities.  These chemicals may include petroleum products, spent lubrication oil, grease, mineral oil, solvent and other chemicals.  Accidental spillages of chemicals in the works area may contaminate the surface soils.  The contaminated soil particles may be washed away by construction site runoff causing water pollution.  Accumulation of solid waste (such as debris, rubbish and demolition materials) could also lead to deterioration in water quality, if not well controlled.

Sewage Effluent

5.18        Sewage effluent might be generated from the workforce during the construction phase.  However, this temporary sewage can be adequately treated by interim sewage treatment facilities, such as portable chemical toilets, which can be installed within construction site.

Nullah Decking

5.19        There is an open nullah located within the Project Site boundary at the northwest.  In the reference design of OWTF, it is proposed to deck over the nullah car parking purposes.for use as open space / carpark.  The construction of proposed nullah decking, which would involve demolition of existing nullah, excavation activities, and construction of box culvert, may pollute storm water in the existing open nullah due to potential release of construction wastes, if uncontrolled.

Operational Phase

5.20        The potential operational phase pollution sources include:

Ÿ  domestic sewage effluent from workforce;

Ÿ  wastewater generated from the organic waste treatment processes;

Ÿ  contaminated surface runoff and accidental spillage.

Domestic Sewage Effluent from Workforce

5.21        Sewage effluent generated from workforce is characterized by high levels of nutrients.  Directly discharge of sewage effluent into the water environment would cause excessive algal growth and reduce dissolved oxygen in water bodies.

Organic Waste Treatment Processes

5.22        The organic waste treatment facilities (OWTF) are to convert the source-separated organic waste into compost and biogas.  Wastewater would be generated during the treatment processes.

Wastewater from Dewatering Process

5.23        According to the reference design of OWTF, digestate from the digesters would be pumped to the dewatering units where solids are separated from liquid (i.e. filtrate) and wastewater, resulting in a nominal flow of 143 m3/day and a maximum flow of 172 m3/day.  Major composition would include chemical oxygen demand (COD), biological oxygen demand (BOD), kjeldahl nitrogen (TKN), ammonia-nitrogen (NH3-N) and suspended solid (SS).  If uncontrolled, the wastewater generated would deteriorate water quality and adversely affect aquatic life in the nearby water environment.

Leachate from Waste Reception Area

5.24        Organic waste would be collected and transported to the Site by waste vehicles.  On arrival at the Site, the incoming waste will be unloaded to unloading bays in a reception area.  As the wet nature of organic waste, occasional formation of leachate will be expected in the reception area. 

Condensate from Biogas Handling and Scrubber of the Air Treatment System

5.25        As biogas from digestion would be saturated with moisture, removal of condensate from biogas will be required before entering to Cogen Units.  A small amount of wastewater would then be generated from the process of condensate removal.

5.26        In addition, air pollution emission would be occurred during the course of solid treatment processes.  Thus, air treatment facilities such as scrubber and biofilter would be provided to control air pollution emission.  In the scrubber, air would be treated by spraying water in countercurrent and a small amount of wastewater would then be generated.

Surplus Water from the Truck Washing Facility

5.27        A truck washing facility would be equipped at the Project Site to thoroughly wash the entire exterior of waste collection vehicles leaving the Site.  Water from the truck washing facility would be reused on site.  Surplus water may have potential to be discharged into nearby water environment and cause adverse water quality impact, if uncontrolled.

Contaminated Surface Runoff

5.28        Surface or rainwater runoff generated during the operational phase is also potentially contaminated and may pose similar water quality impact, if not well controlled.

Cumulative Water Quality Impact

5.29        Relevant concurrent projects in the vicinity of OWTF are shown in Table 2.4 under Section 2.  As all the construction works proposed under this Project would be land-based and with implementation of the recommended mitigation measures, any potential water quality impact generated during construction phase of the Project would be localized and minor. No marine construction works would be required under this Project, and hence no significant cumulative water quality impact with other possible concurrent projects would be expected.

5.30        Since all possible effluents, leachate and contaminated runoff from the Project operation shall be treated and their quality be monitored before discharged, no significant cumulative water quality impact imposed by the Project is expected during the operational phase.

Prediction and Evaluation of Environmental Impacts

Construction Phase

Construction Site Runoff

5.31        It is important that proper site practice and good site management are observed to prevent site runoff entering the surrounding waters in particular the open nullah at the northwestern part of the Project Site, avoid disturbance of water bodies and minimise deterioration in water quality.  Recommended mitigation measures are detailed in Section 5.44.  Provided that the recommended mitigation measures are properly implemented, unacceptable impacts on water quality are not anticipated. 

General Construction Activities

5.32        Land-based construction activities may generate wastewater and cause water pollution.  These impacts are likely to be minimal, provided that good constructions and proper site managements would be observed.  It is anticipated that water quality impacts caused by general construction activities would be insignificant with adequate implementations of recommended mitigations as mentioned in Section 5.44.

Excavation of Soil Materials

5.33        There is a potential that excavated soil material is washed away from the construction site to the nearby watercourses during rain event, and hence increases SS concentration and oxygen demand in water bodies.  Mitigation measures are recommended in Section 5.45 to minimise the potential water quality impacts.

Accidental Spillage and Accumulation of Solid Waste

5.34        Site drainage should be well maintained and good construction practices should be observed to ensure that litter, fuels and solvents are managed, stored and handled properly and do not enter the nearby water streams.  No adverse water quality impacts are expected with proper implementation of the recommended mitigation measures.

Sewage Effluent

5.35        Sewage would be generated from the workforce during the construction phase.  However, this temporary sewage can be adequately treated by interim sewage treatment facilities, such as portable chemical toilets, which can be installed within the construction site.  Provided that sewage would not discharge directly to water streams, and chemical toilets are used and properly maintained, it is unlikely that sewage generated from the site would cause significant water impact.

Nullah Decking

5.36        Adoption of good house keeping and mitigation measures would reduce the generation of construction wastes and potential water pollution due to the proposed nullah decking works.  With the implementation of adequate construction site drainage and the provision of mitigation measures as described in Section 5.53, it is anticipated that unacceptable water quality impacts would not arise.

Operational Phase

Sewage Effluent from Workforce

5.37        During the operation of the Project, sewage effluent will be generated from workforce.  Generated sewage should be connected to the foul sewerage system.  No adverse water quality impact is anticipated.

Wastewater from Dewatering Process

5.38        It is expected that dewatering of digestate and filtrate production would result in daily nominal flow of 143 m3 and a maximum flow of 172 m3/day.  The on-site wastewater treatment plant shall deploy suitable treatment processes to reduce the pollution level to an acceptable standard (refer to Section 5.54).  Treated effluent would be stored temporarily in order to be used as process water within the plant.  The storage volume would be around 20 m3.  The effluent to be discharged to foul sewers could be taken as an overflow from the tank.  Levels of contaminants and pollutants in the effluent of the on-site wastewater treatment plant to be discharged to foul sewers shall satisfy the requirements specified in the TM-DSS.  Thus, adverse water quality is not expected.

Leachate from Waste Reception Area

5.39        Because of the wet nature of organic waste, occasional formation of leachate is expected.  The reception area will be provided with a drainage system on the floor connecting to the wastewater treatment plant (refer to Section 5.54).  No direct discharge of leachate would be adopted.  Adverse water quality impact would not be anticipated.

Condensate from Biogas Handling and Scrubber of the Air Treatment System

5.40        Condensate from biogas handling and spraying water from scrubber will be collected and transferred to the wastewater treatment plant (refer to Section 5.54).  No direct discharge of such wastewater would be adopted and therefore adverse water quality impact would not be anticipated.

Surplus Water from the Truck Washing Facility

5.41        A truck washing facility will be equipped and thoroughly wash the entire exterior of waste collection vehicles leaving the Site.  Generated wastewater would be collected and delivered to the wastewater treatment plant (refer to Section 5.54).  No adverse water quality impact would therefore be anticipated.

Contaminated Surface Runoff

5.42        It would be a required site practice not to directly discharge contaminated surface runoff into the surface channel or nearby water bodies.  Based on the reference design of OWTF, the waste reception, treatment facilities and compost storages of OWTF would be located in enclosed buildings to prevent generation of contaminated rain runoff.  All surface runoff such as washed water generated in the treatment processes areas would be properly collected and diverted to the on-site wastewater treatment plant (refer to Section 5.54).  Adverse water quality impact from contaminated surface runoff is not expected.

5.43        Site drainage should be well maintained and good management practices should be observed to ensure that wastes and chemicals are managed, stored and handled properly and do not enter the nearby water streams.  No adverse water quality impacts are expected with proper implementation of the recommended mitigation measures.

Mitigation Measures of Adverse Environmental Impacts

Construction Phase

Construction Site Runoff and General Construction Activities

5.44        The site practices outlined in ProPECC PN 1/94 “Construction Site Drainage” should be followed as far as practicable in order to minimise surface runoff and the chance of erosion.  These practices include the following items:

Ÿ  At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works and erosion and sedimentation control facilities implemented.  Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct storm water to silt removal facilities.  The design of the temporary on-site drainage system will be undertaken by the contractor prior to the commencement of construction.

Ÿ  Sand/silt removal facilities such as sand/silt traps and sediment basins should be provided to remove sand/silt particles from runoff to meet the requirements of the TM-DSS.  The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94, which states that the retention time for silt/sand traps should be 5 minutes under maximum flow conditions.  The detailed design of the sand/silt traps shall be undertaken by the contractor prior to the commencement of construction.

Ÿ  All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly during rainstorms.  Deposited silt and grit should be regularly removed, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.

Ÿ  Measures should be taken to minimize the ingress of site run-off and drainage into excavations.  Drainage water pumped out from excavations should be discharged into storm drains via silt removal facilities.

Ÿ  If surface excavation works cannot be avoided during the wet season (April to September), temporarily exposed slope/soil surfaces should be covered by a tarpaulin or other means, as far as practicable.  Interception channels should be provided (e.g. along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces.  Arrangements should always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.  Other measures that need to be implemented before, during and after rainstorms are summarized in ProPECC PN 1/94.

Ÿ  All vehicles and plant should be cleaned before leaving the site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and sited wheel washing facility should be provided at every site exit where practicable.  Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

Ÿ  Open stockpiles of construction materials or construction wastes on-site of more than 50m3 should be covered with tarpaulin or similar fabric during rainstorms.

Ÿ  Water used in ground boring and drilling should only be discharged into storm drains via silt removal facilities.

Excavation of Soil Materials

5.45        The construction programme should be properly planned to minimise soil excavation, if any, in rainy seasons.  This prevents soil erosion from exposed soil surfaces.  Any exposed soil surfaces should also be properly protected to minimise dust emission.  In areas where a large amount of exposed soils exist, earth bunds or sand bags should be provided.  Exposed stockpiles should be covered with tarpaulin or impervious sheets at all times.  The stockpiles of materials should be placed at locations away from any stream courses so as to avoid releasing materials into the water bodies.  Final surfaces of earthworks should be compacted and protected by permanent work.

Accidental Spillage and Accumulation of Solid Waste

5.46        Contractor must register as a chemical waste producer if chemical wastes would be produced from construction activities.  The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes.

5.47        Maintenance of vehicles and equipments involving activities with potential for leakage and spillage should only be undertaken within the areas which appropriately equipped to control these discharges.

5.48        Oils and fuels should only be used and stored in designated areas which have pollution prevention facilities.  All fuel tanks and storage areas should be sited on sealed areas in order to prevent spillage of fuels and solvents to the nearby watercourses.  All waste oils and fuels should be collected in designated tanks prior to disposal.

5.49        Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance.  The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes.  General requirements are given as follows:

Ÿ  Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

Ÿ  Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

Ÿ  Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

5.50        Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid entering to the nearby watercourses.  Stockpiles of cement and other construction materials should be kept covered when not being used.  Rubbish and litter from construction sites should also be collected to prevent spreading of rubbish and litter from the site area.  It is recommended to clean the construction sites on a regular basis.

Sewage Effluent

5.51        The presence of construction workers generates sewage.  It is recommended to provide sufficient chemical toilets in the works areas.  The toilet facilities should be more than 30m from any watercourse.  A licensed waste collector should be deployed to clean the chemical toilets on a regular basis.

5.52        Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment during the construction phase of the project.  Regular environmental audit on the construction site can provide an effective control of any malpractices and can achieve continual improvement of environmental performance on site.

Nullah Decking

5.53        To minimize the potential water quality impacts from the construction of proposed nullah decking, the practices outlined below should be adopted where applicable:

Ÿ  The proposed works should be carried out within the dry season between October and March when the flow in the open nullah is low.

Ÿ  The use of less or smaller construction plants may be specified to reduce the disturbance to the nullah bed.

Ÿ  Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from the nullah and any water courses during carrying out of the construction works.

Ÿ  Stockpiling of construction materials and dusty materials should be covered and located away from the nullah any water courses.

Ÿ  Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nullah and nearby water receivers.

Ÿ  Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the nullah, where practicable.

Ÿ  Construction effluent, site run-off and sewage should be properly collected and/or treated.

Ÿ  Any works site inside the nullah should be temporarily isolated, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props to prevent adverse impact on the water quality.

Ÿ  Proper shoring may need to be erected in order to prevent soil/mud from slipping into the nullah and nearby watercourse.

Ÿ  Supervisory staff should be assigned to station on site to closely supervise and monitor the works.

Operational Phase

5.54        The Project Site will be equipped with an adequately sized wastewater treatment plant.  A high rate type of active sludge system specifically designed for the removal of nitrogen components from the wastewater in combination with conversion of residual BOD and COD would be deployed.  The wastewater treatment plant would also be incorporated with SHARON or annamox technology or equivalent to achieve high total overall nitrogen removal.  Wastewater generated from OWTF (including wastewater from various waste treatment processes such as dewatering and biogas handling processes, leachate from waste reception area, wastewater from scrubber of air treatment system and any surplus water from truck washing facility) will be properly collected and diverted to the wastewater treatment plant.  Treated effluent will then be stored temporarily in order to be used as process water within the plants.  The storage volume would be around 20 m3.  Overflow from the tank will be discharged to foul sewers.  The polluting parameters in effluent shall be in compliance with the requirements specified in TM-DSS.  The design, installation and operation of the wastewater treatment plant shall be licensed under the Waste Disposal Ordinance and subject to the effluent monitoring as required under WPCO which is under the ambit of regional office (RO) of EPD.  To ensure that wastewater can be adequately treated and effluent from treatment plant can meet the standards listed in TM-DSS, the following mitigation measure should be conducted.

Ÿ  Cleaning and maintenance of treatment facilities should be conducted on a regular basis to ensure that removal rate of each treatment facility would not be reduced.

Ÿ  Cleaning and maintenance of pipelines should be carried out on a regular basis to prevent block of pipeline and leaching of wastewater, and therefore prevent overflowed or leached wastewater discharging into nearby drainages and water streams.

Ÿ  Regular site inspection should be conducted to ensure that no wastewater can be directly discharged into nearby water streams.

5.55        In the scrubber, spraying water should be re-circulated to minimize the need for external water.  The spraying water would be collected at the bottom of the scrubber.  Excess water should be properly diverted and discharged to the on-site wastewater treatment plant as described in Section 5.54.

5.56        The waste reception, treatment facilities and compost storages of OWTF should be located in enclosed buildings to prevent generation of contaminated rain runoff.  All surface runoff such as washed water generated in the treatment processes areas should be properly collected and diverted to the on-site wastewater treatment plant as described in Section 5.54.

5.57        All drainage system for collection and transferring wastewater generated in OWTF to the on-site wastewater treatment plant as described in Section 5.54 should be capable of preventing clogging and easy maintenance and cleaning.  

Evaluation of Residual Impacts

Construction Phase

5.58        The construction phase water quality impact would generally be temporary and localised during construction.  No unacceptable residual water quality impacts would be expected during the construction phase of the Project, provided that all the recommended mitigation measures are properly implemented.

Operational Phase

5.59        All sewage or wastewater generated from the operation of the Project will be adequately treated in the on-site wastewater treatment plant before reused on-site or discharged to the public sewerage system.   No residual water quality impacts would be anticipated.

Environmental Monitoring and Audit

5.60        With the implementation of recommended mitigation measures, no unacceptable water quality impact would be expected from the Project.  Water quality monitoring is not considered necessary.  However, it is recommended that regular site inspections should be undertaken to ensure that the recommended mitigation measures are properly implemented during the construction phase of the Project.

Conclusion

5.61        During construction phase, potential water quality impact would be generated from site run-off, sewage from workforce, and discharge of wastewater from various construction activities.  Provided that all the recommended mitigation measures are properly implemented, no adverse water quality impacts would be expected during the construction phase of the Project. To avoid any potential water quality impact, the nullah decking work would be carried out during the dry season, between October and March.

5.62        The operation of OWTF is to convert organic waste into compost and biogas.  All sewage or wastewater generated from the operation of the Project will be adequately treated in the on-site wastewater treatment plant before reused on-site or discharged to the public sewerage system.  No adverse water quality impacts would be anticipated.