Table 14B.1: Implementation Schedule for Construction and Operation of Wind
Monitoring Mast
EIA Ref. |
Environmental
Protection Measures |
Duration of
Measures/Timing of Completion of Measures |
Implementation
Agent |
Implementation
Stage |
Relevant
Legislation & Guidelines |
|||
Des |
C |
Post-C |
O |
|||||
1. Water Quality |
||||||||
S
6.8 and EM&A Manual |
The
contractor(s) will ensure that the works cause no visible foam, oil, grease, litter
or other objectionable matter to be present in the water within and adjacent
to the area of marine works. |
During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S
6.8 |
Control
and monitoring systems will be used to alert the crew to leaks or any other
potential risks. |
During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S
6.8 |
All plant will be fully serviced and
inspected before use to limit any potential discharges to the marine
environment |
During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S
6.8 |
Avoid spillage of oil, fuel and
chemicals from structures by adopting appropriate good site practices |
During
Construction |
Contractor(s) |
|
ü |
|
|
Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes |
S
6.8 |
Any
grout used would conform to the relevant environmental standards. In addition, the adoption of appropriate
operational management by the contractor should lead to low potential for
leakage during the pumping phase. |
During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S
6.8 |
No debris shall be willingly
discharged to sea. However, should debris be placed on the seabed,
this will be removed (wherever practicable) |
During
Construction |
Contractor(s) |
|
ü |
|
|
- |
2. Waste Management |
|
|
|
|
|
|
|
|
S
7.6 |
The Contractor shall prepare and implement
a Waste Management Plan which incorporates site-specific factors, such as the
designation of areas for the segregation and temporary storage of reusable
and recyclable materials. |
Contract
mobilisation / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S
7.6 |
The Contractor shall ensure only
licensed waste collectors are used to collect chemical waste for delivery to
a licensed treatment facility |
Contract
mobilisation / During Construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation Code of Practice
on the Packaging, Labelling and Storage of Chemical Wastes |
S
7.6 |
The Contractor shall apply for and
obtain the appropriate licenses/permits for the disposal public fill and
chemical waste. |
Contract
mobilisation / During Construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal
(Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and
Storage of Chemical Wastes Waste Disposal (Charges for Disposal of Construction
Waste) Regulation |
S
7.6 |
EM&A of waste handling,
storage, transportation, disposal procedures and documentation through the
site audit programme shall be undertaken. |
During
Construction |
ET |
|
ü |
|
|
- |
3. Marine Ecology |
||||||||
S
9.12.2 |
The vessel
operators will be required to control
and manage all effluent from vessels. |
During
Construction / Marine works |
Contractor(s) |
|
ü |
|
|
- |
S
9.12.2 |
A policy of no dumping of rubbish, food, oil, or chemicals
will be strictly enforced. This
will also be covered in the contractor briefings. |
During
Construction / Marine works |
Contractor(s) |
|
ü |
|
|
- |
S
9.12.3 |
Vessel operators working on the Project construction
or operation will be given a briefing, alerting them to the possible presence
of marine mammals in the area, and guidelines for safe vessel operations in
the presence of cetaceans. If
high speed vessels are used, they will be required to slow to 10 knots when
passing through a high density dolphin area. |
During
Construction / Marine works |
ET
& Contractor(s) |
|
ü |
|
|
- |
S
9.12.3 |
The
vessel operators will be required to use predefined and regular routes, as these
will become known to porpoise using these waters. This measure will further serve to
minimise disturbance to marine mammals due to vessel movements |
During
Construction / Marine works |
ET
& Contractor(s) |
|
ü |
|
|
- |
S
9.12.4 |
To reduce underwater sound levels associated with
percussive piling, the following steps will be taken: -
Quieter hydraulic hammers should
be used instead of the noisier diesel hammers; -
Acoustic decoupling of noisy
equipment on work barges should be undertaken. |
During
Construction / Marine works |
Contractor(s) |
|
ü |
|
|
- |
S 9.12.4 |
Best practices are recommended to
reduce the impacts to marine mammals: -
Instigate ‘ramping-up’ of the piling
hammer to provide an advance warning system to marine mammals in the
vicinity; -
Activities will be continuous
without short-breaks and avoiding sudden random loud sound emissions |
During
Percussive Piling works for Foundation Construction |
Contractor(s) |
|
ü |
|
|
- |
S
9.12.4 |
An exclusion zone of 500 m radius will be scanned around the
work area for at least 30 minutes prior to the start of percussive
piling. If marine mammals/sea turtles
are observed in the exclusion zone, piling will be delayed until they have
left the area. |
During
Percussive Piling works for Foundation Construction |
ET |
|
ü |
|
|
|
S
9.15.1 |
Marine
percussive piling works to be restricted to a daily maximum of 12 hours
within daylight operations. |
During
Percussive Piling works for Foundation Construction |
Contractor(s) |
|
ü |
|
|
|
4. Fisheries |
||||||||
S
10.7 |
The
impacts to fisheries resources will be minimised by adopting the following
measures: -
The use of competent and
experienced contractors and vessels operators; -
Good planning of the installation
sequence to avoid possible clashes; -
Good promulgation of information
relating to construction activities; -
Thorough auditing of all vessels; -
Observing good industry
construction practices by the Contractors; and, |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
Inform fishermen of possible developments of
the Project in advance |
Marine
Works / During Construction |
Contractor(s)
/ Operator |
|
ü |
|
|
- |
S
10.7 |
Using good engineering practice, including the use of appropriately sized
piles (smaller piles generate lower levels of underwater sound) and piling
equipment. |
Marine
Works / During Construction |
Contractor(s)
|
ü |
ü |
|
|
- |
S
10.7 |
Using ramp-up piling procedures. Blow frequency during this ramping up
period should replicate the intensity that would be undertaken during full
piling (e.g. one blow every two seconds) to provide cues for fish to localize
the sound source. Pile blow
energy should be ramped up gradually over the ‘soft start’ period. |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
The
relevant authorities will be notified of activities in the wind monitoring
mast area during construction activities, including dates of any works. In addition, the Marine Department
will be notified of the final location of the wind monitoring mast structures
so that these can be updated on marine charts. |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
All
vessels engaged in construction activities will be equipped with a Maritime
VHF radio and an agreed frequency channel maintained. All vessels involved in
the construction works will show the correct lights and shapes and ensure
that all movements are promulgated through the Marine Department |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
Consider
the use of Guard Ship during the construction phase, particularly in periods
of high activity. |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
A
safety / exclusion zone of 500 m from any area of construction works will be
established for all non-Project vessels.
The working area will be marked in accordance with Marine Department
Notice No. 23 (2009). |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
Temporary
lighting should be provided for incomplete structures during construction |
Marine
Works / During Construction |
Contractor(s)
|
|
ü |
|
|
- |
S
10.7 |
The
wind monitoring mast should be marked according to the requirements of the Marine
Department. The precise marking
arrangement will be agreed during the Detailed Design Phase. |
Detail
Design |
Designer |
ü |
|
|
|
|
5. Landscape and Visual |
||||||||
S
11.7 |
Appropriate
colours for the wind monitoring mast should be selected to reduce their
visibility |
Detail
Design |
Designer
|
ü |
|
|
|
- |
6. Cultural Heritage |
||||||||
S
12.8 |
No
mitigation measures or EM&A is required for cultural heritage aspect of the
Project. |
- |
- |
|
|
|
|
- |