4                                            Consideration of Design and Engineering Alternatives

4.1                                      Introduction

In accordance with Clause 3.3.2 of the EIA Study Brief, this section of the EIA Report considers design and construction options as part of the assessment of alternatives for the proposed offshore wind farm development.  The section has been divided into a discussion of the following alternatives:

·           wind farm size and layout;

·           wind turbine structural components;

·           wind turbine lighting and marking; and

·           construction methods.

Based on the above considerations, the preferred development scenario is presented in Section 5.

4.2                                      Wind Farm Size and Layout

4.2.1                                Wind Farm Capacity

In order to help meeting renewable energy targets for Hong Kong (see Section 2), HK Electric is considering the development of a wind farm with a proposed capacity of around 100 MW.  This proposed capacity represents about 1.6% of HK Electric’s total electricity sent out in 2008 and also would provide between 1-2% of the electricity consumption of Hong Kong, thereby helping to meet Government targets (see Section 2).  The alternative sites assessment has confirmed that there is sufficient area available for the development of an offshore wind farm of this scale (see Section 3). 

4.2.2                                Wind Farm Layout

Identification of the preferred layout of the turbines within the identified development area has considered the following factors:

·           Site constraints;

·           Submarine cable crossings;

·           Wind characteristics and wake loss;

·           Seabed characteristics; and

·           Cable circuit layout.

Site Constraints

Section 3 of this EIA Report has considered a number of environmental and physical constraints that have determined the boundary within which the wind farm could be located.  Some of the key constraints are summarised as follows:

·           Presence of high volume marine traffic routes to the east, west and north – including the avoidance of marine fairways and buffer zones;

·           Location of helicopter flight paths to the north and west;

·           Distance from sensitive sites around the coast of Cheung Chau and Lamma Island, including a proposed Marine Park;

·           Presence of a gas pipeline to the east of the site;

·           Presence of the South Cheung Chau open seafloor mud disposal area to the west of the site;

·           Boundary of Hong Kong Territorial Waters to the south of the site; and

·           Proximity to Visual Sensitive Receiver’s, including those at Lamma Island, Hong Kong Island, Cheung Chau and Shek Kwu Chau.

Based on these constraints a preferred boundary has been developed as shown in Figure 1.1 in Section 1 of this EIA Report.  In addition to the above constraints, the marine archaeological investigation undertaken for the EIA has confirmed the presence of a wreck site in proximity to the wind farm area, which has been avoided as part of the configuration of the wind farm layout (see Section 12).

Wind Characteristics and Wake Loss

Although wind monitoring at the site has not yet been carried out, the predominant wind direction at the wind farm site is north easterly with also a relatively large incidence of northerly and south-easterly winds (see Figure 4.1).  This is an important consideration when looking at the potential for wake losses across the wind farm.

Figure 4.1       Annual Wind Rose for Cheung Chau (1993-2008) ([1])

Wind rose for all months

 

Each individual turbine will lead to a reduction in wind speed immediately behind it.  This effect is reduced downwind of the turbine as the “wake” region mixes with the unaffected airstream, so that a distance of approximately ten rotor diameters the wind speed will be similar to the original value.  Individual turbines therefore need to be suitably spaced to maintain energy capture across the wind farm area.  Figure 4.2 demonstrates a typical “wake effect”.

Figure 4.2       Contours in Velocity Magnitude in ms-1 at a Wind Velocity of 10 ms-1 at turbine hub height ([2])

wake1


Typical spacing between turbines within a wind farm is 5 times to 10 times rotor diameter in the prevailing wind direction and 3 times to 5 times rotor diameter in the crosswind direction.  Table 4.1 shows the spacing arrangements required under the different turbines scenarios with a minimum and maximum rotor diameter discussed in Section 4.2 below.

Table 4.1        Wind Turbine Spacing Requirement for Different Turbines

Rotor Diameter

Cross wind Spacing (m)

(North – South)

Prevailing Wind Spacing  (m)

(East – West)

 

Minimum

Maximum

Minimum

Maximum

80

240

400

400

800

111

333

555

555

1,110

 

An examination of wake loss has not been undertaken for the Project at the time of writing the EIA.  For the purpose of this EIA a value between the minimum and maximum spacing has been taken forward for the maximum rotor diameter within the overall area available for development that is not constrained (see above and Section 3).  Therefore at the wind farm site the proposed separation distance will be between the minimum and maximum spacing presented in Table 4.1 for a rotor diameter of 111 m (see Section 5).  It should be noted, however, that the actual wind spacing between turbines will be optimised during the Detailed Design with the overall intention to reduce the footprint of the wind farm area without compromising turbine operation.

Wind Monitoring Mast

In addition to the turbines, a wind monitoring mast will be installed within the development area.  The purpose of the mast will be to investigate the meteorological conditions at the site, including key data on wind speed and direction. Wind monitoring mast will consist of a steel lattice tower erected on top of an offshore foundation. Wind measurement equipment including wind vanes and cup anemometers, etc. will be mounted at various levels along the lattice tower to capture wind resources data up to the wind turbine hub height level.  Tidal and wave conditions will also be monitored through sensors installed at underwater levels.  Data collected will be stored and transmitted onshore for subsequent evaluation and analysis.  There are others means of wind monitoring technique including the adoption of LIDAR (Light Detection and Ranging) system which is regarded as a new and innovative technology for wind measurement.  The LIDAR system has not, however, been widely deployed for offshore wind data collection and the effectiveness and reliability of this technique would need further investigation.  Therefore it is assumed at this stage that lattice tower structure will be constructed for the wind monitoring mast and has been taken as basis of this EIA study.

Seabed Characteristics

Seabed properties can alter the practicality of constructing wind turbine foundations.  Potential constraints include the presence of natural or man-made obstructions, seabed slopes and sediment composition.  A geophysical survey has been carried out at the site to determine the seabed characteristics at the wind farm site and along the cable route.  These results and future additional geophysical survey will be used during Detailed Design to verify/modify the location of wind farm structures and the cable route alignment.

Cable Circuit Layout

Subsea power cables are required to connect the wind farm to the electricity distribution system.  This includes the requirement to link turbines to the substation and also to take power from the substation to HK Electric’s grid.  Figure 4.3 provides an illustration of a typical subsea cable that will be installed between turbines.

Figure 4.3       Typical Subsea Cable

 


Section 3 has considered the environmental constraints for the cable route from the wind farm to the landing point so that key environmental features would not be significantly impacted during construction works.

For the inner turbine array, the electrical layout of the wind farm has been determined by assessing the relative costs and benefits of cable configurations including strings of turbines.  Although, the layout of cables is subject to Detailed Design, for the purpose of this EIA, it is assumed that there will be an electrical configuration of five to six strings of turbines running from north to south across the wind farm area.  There will be a requirement for each string of turbines to be linked to the offshore substation.  This configuration would strike a balance between cable lengths and the inherent redundancy of the network should a fault occur between the adjacent turbines.  Furthermore, this configuration reduces the number of cable crossings, which could be associated with more random turbine layouts, particularly related inter turbine array cabling. 

Summary

In order to inform the EIA, a preliminary layout has been developed, which takes account of the site constraints discussed above.  An interim geometric grid pattern has been taken forward that reduce wake loss and reduces potential marine traffic collision risk associated with more random layout patterns (see Section 11) and that is likely to minimise visual impacts associated with turbine scatter (see Section 5).  As discussed, this layout is only preliminary and is subject to refinement during Detailed Design and to meet any recommendations set out in this EIA.

4.3                                      Wind Turbine Structural Components

4.3.1                                Turbine Size and Design

Wind turbines can incorporate two or three rotor blades.  The standard turbine design that is adopted for offshore wind farm developments internationally incorporates 3 blades.  This design also presents potential for greater visual impacts and therefore this design has been considered as the preferred design in this EIA in order to take forward a worse case approach for the assessment.  The wind turbines will be of proven technology and design, which typically incorporates tapered tubular towers attached to a nacelle housing containing the generator, gearbox and other operating equipment.  The turbine transformer will be located either at the tower base (above the high tide level) or at the top of the tower, depending on the type of wind turbine procured.  The transformer will either be oil-filled (surrounded by a bund conforming to the required standards) or cast-resin.  These design elements are set by the manufacturer and therefore alternative design are not available and have not been assessed.

Outline properties of present-day turbines that are likely to be used for the development are shown below in Table 4.2.

Table 4.2        Typical Properties of Commercially Available Wind Turbines

Supplier

Model

Capacity (MW)

Rotor Diameter (m)

Hub Height (m)

Vestas

V90-3.0MW

3

90

Variable

Siemens

SWT-2.3-82

2.3

82

Variable

 

SWT-3.6-107

3.6

107

Variable

GE Energy

3.6sl

3.6

111

Variable

Nordex AG

N90

2.5

80 or 90

Variable

 

A decision has yet to be made on which turbine will be sourced for the wind farm.  The capacity of the turbines could therefore range from 2.3 to 3.6 MW.  It is therefore proposed that the preliminary site layout considers the development of around 30 - 35 nos. of wind turbines so that a capacity of approximately 100MW can be met.  Should 3.6 MW class wind turbine be selected, the number of wind turbines would be reduced to around 28 to 30.

Preliminary dimensions are not expected to exceed a tip height of +125mPD (see Section 3).  In the event the wind turbine model with a maximum rotor diameter of 111m be adopted, the maximum tip height would be +136mPD.  It was considered appropriate that the maximum rotor diameter of 111 m be taken forward for the impact assessment as this presents potentially a worse case scenario for impacts on the visual environment and ecology. 

4.3.2                                Foundation Design

The wind turbines and wind monitoring mast will be supported on foundations fixed to the seabed.  The final configuration of the support structures for the project will be subject to the following considerations:

·           selection of wind turbine;

·           ground conditions including geology and seabed stability;

·           metocean conditions (wave, current, tide);

·           life-cycle cost; and

·           access and maintenance requirements.

Each foundation type will have an access platform incorporated into the design.  The platform has one or more ladders (with integral personnel safety protection), enabling access to the foundation at any state of the tide.  The structures will have provisions for personnel safety, e.g. life-rings.

The following foundation designs have been considered for the wind turbines which have been derived following preliminary engineering design, using site geological information and representative wind turbine loadings provided by turbine manufacturers and from wind and wave loading estimated specifically for the site.  The design options considered feasible for this wind farm are discussed below.

Monopile

These structures rely on the frictional properties of the hollow steel pile fixed into the seabed either by driving (using a hydraulic hammer), drilling or drilling and driving.  The monopile for this size of turbine is anticipated to have a diameter of 5 to 7 m which will lead to a physical footprint of approximately 38.5 m2 with a pile wall thickness of approximately 80 mm.  Figure 4.4 shows a typical monopile foundation.


Figure 4.4       Monopile Foundation ([3])

5-41

 


Tripod / Tetrapod Pile

The tripod pile foundation consists of a structure connecting three open–ended steel piles located at a distance from a central element attached to the turbine tower.  The diameter of each tripod pile is estimated to be 1.6 m with a 7 m separation distance between each tripod pile.  The subsequent physical footprint will be in the order of 6 m2 for each tripod group (representing the 3 nos. of net pile area).  The piles will be terminated at its top at the seabed level for connecting with an underwater pyramid steel frame substructure. These three piles together with steel frame substructure will support the wind turbine ‘monopole’ tower.  Tripod is commonly adopted in shallow water with moderate wave force.  Figure 4.5 shows a typical tripod pile foundation.

Figure 4.5       Tripod Foundation ([4])

 


The tetrapod pile foundation is similar to the tripod foundation in which 4 piles instead of 3 piles are used.  In addition, the underwater substructure frame will be more robust with layer of bracings.  The diameter of each tetrapod pile is estimated to be 1.6 m with a 15~20m separation distance between each tetrapod pile.  The subsequent physical footprint will be in the order of 8 m2 for each tetrapod group (representing the 4 nos. of net pile area).  These four piles together with steel frame substructure can support a larger intermediate decking platform for placing the wind turbine tower.  Tetrapod is commonly adopted in deeper water with significant wave forces.

Both tripod and tetrapod substructure will require a heavy lifting barge for placing the structure precisely in place.  Deep water welding is required for its connection to the piles.  Figure 4.6 shows a typical tetrapod pile foundation.

Figure 4.6       Tetrapod Foundation

 


Gravity Base Foundation

Gravity base foundations normally consist of a concrete base that sits on the seabed.  This type of foundation relies on the mass of the foundations (sometimes with additional ballast) to withstand any lateral movement of the foundations.  The concept often requires the seabed to be prepared prior to installation, i.e. the top layer of material is removed and replaced by a stone bed.  Post-installation, the base is filled with a suitable ballast material.  In addition, a steel “skirt” may be installed around the base to penetrate into the seabed and to constrain the seabed underneath the base.  Figure 4.7 shows a typical tripod pile foundation.

Figure 4.7       Typical Gravity Base Foundation (1)

 


Scour Protection

Scour is the term used for the localised removal of sediment from the area around the base of support structures located in moving water.  When a structure is placed in a current, the flow is accelerated around the structure, and the vertical velocity gradient of the flow is transformed into a pressure gradient on the leading edge of the structure.  This pressure gradient results in a downward flow on to the seabed forming a vortex, which sweeps around and downstream of the structure.  Locally, shear stress increases at the seabed next to the structure.  If the seabed is erodable (and the shear stresses are of sufficient magnitude), a scour hole forms around the structure.  This phenomenon is known as local or structure-induced sediment scour.  At the structure, any initial period of erosion is followed by a period of equilibrium, reached when the flow alteration caused by the scour hole reduces the magnitude of the shear stresses such that sediment can no longer be mobilized and removed from the hole.

For the purposes of this assessment, it has been assumed that some scouring of the upper soft seabed sediments may occur.  There are two design philosophies used to address scour.  The first is to allow for scour in the design of the foundation (thereby assuming a corresponding larger water depth at the foundation) or to install scour protection around the structure such as rock dumping or fronded mattresses.  Designing the foundations for scour will lead to increases in penetration depths and potentially increase the size of the foundations, and therefore additional fabrication and handling weights both leading to increases in the cost.

A number of options are available for the scour protection design, including the use of rock or the use of high tensile strength buoyant frond scour control systems.  Figure 4.8 and 4.9 show a typical scour protection structure and a frond mat system designs, respectively.

Figure 4.8       Scour Protection


 

Figure 4.9       Frond Mat System ([5])

 


The frond mat system has not, however, been deployed in Hong Kong and the effectiveness of this technique is therefore unknown.  Therefore at this stage, it is assumed that rock scour protection will be constructed, if necessary, as this is a proven technology.  In addition, rock scour provides potential environmental benefits as it could act as additional hard substratum for colonisation thereby acting as an artificial reef.

Preferred Foundation Design Option

The preferred design option will be confirmed during the Detailed Design stage.  From geotechnical information and engineering principles available at this time it can be concluded that a gravity base foundation will not be acceptable as the seabed of the wind farm site is composed of soft silty sediments.  The softer seabed could lead to instability in the foundations.  In addition, gravity base foundations will lead to a relatively large footprint of impact, a large amount of sediment excavation and potential for relatively high water quality impacts in comparison to other options.  The gravity base option is not generally the preferred approach for foundation design for international wind farms for these reasons. 

It is therefore proposed that a piled option would be preferred.  In order to inform the impact assessment, it is considered that the monopile option presents the worst case scenario for the wind turbines in terms of disturbance to the seabed as it has a larger footprint.  Also, scour protection would only normally be required for monopile foundations, which could potentially lead to greater impacts during construction and operation associated with seabed disturbance.  It is therefore suggested that assessment of monopile foundations are taken forward for the turbines, which would allow for future flexibility of design.

Since the piling system for the wind monitoring mast is comprised of 8 nos. of 1.6m diameter steel tubular piles fixed into seabed in which each pile individually can be considered as a small monopile, the monopile option will also be taken forward for the wind monitoring mast by considering it as a lattice of small monopiles.  An indicative drawing of the wind monitoring mast design is presented in Figure 4.10.

It is worth noting that the wind monitoring mast pile are terminated at its top at an above sea level of approx. 18 mPD for supporting a concrete deck platform which in turns to support the wind monitoring mast lattice tower.  Without a robust underwater steel substructure, 8 nos. of piles will be adopted in lieu of the typical 3 or 4 nos. for tripod or tetrapod.  Although the nos. of piles will be doubled, heavy lifting barge and risky deep water welding for installing the steel substructure can be avoided.  In addition, conventional static load test on piles can be conducted above water which warrants the timely approval by the Buildings Authority and the subsequent commissioning of the wind monitoring process.  

 

Figure 4.10     Indicative Design for Wind Monitoring Mast Structure


 

4.4                                      Wind Turbine Lighting and Marking

Although the proposed wind farm will not directly impact on aviation routes with the alteration to existing helicopter procedures (see Section 3), the Civil Aviation Department (CAD) requires that the wind turbines be provided with suitable lighting and markings.  In general, markings consist of the use of alternative orange and white bands.  Previous studies ([6]) have investigated the preferred marking option.  A number of proposals for the marking of turbines have been considered as shown in Figure 4.11, which aim to provide the necessary warning without being too visually intrusive.

Figure 4.11     Turbine Marking Options

0019313MM

 


It is clear from Figure 4.11 that Option 1 would have the highest visibility and Options 6, 8 and 9 the lowest visibility.  Consultations with CAD, however, have determined that Options 9 and 10 would be acceptable depending upon their location in the wind farm array.  Option 9 would be acceptable within the wind farm site and Option 10 at the periphery.  These two options are thought to strike the best balance between satisfying the requirements of CAD for the marking of wind turbines whilst being visually less intrusive than other possible options.  This approach has been agreed with CAD as part of the discussions for this Project. 

In addition, to marking, lighting of the wind turbine structures, substation and offshore monitoring mast will be required for aviation and navigation.  Preferred lighting requirements for offshore wind farms have been defined by the CAD.  In addition, discussions with the Marine Department have determined lighting requirements for the turbine structures should be in line with the International Association of Marine Aids to Navigation and Lighthouse Authorities (IALA) Recommendation 0-117 of May 2000.  It is therefore proposed that lighting be taken forward that meets CAD and Marine Department requirements.  Section 5 provides a more detailed discussion of the preferred approach for marking and lighting arrangements for aviation and navigation, with the potential for any impacts to avifauna associated with the selected design assessed in Section 8.

4.5                                      Alternative Construction Techniques

4.5.1                                Foundation Installation

A number of alternative construction techniques are available for the construction of the foundations for both the turbines and the wind monitoring mast.  Three alternatives are available for the former, namely percussive or piled foundations or those installed through suction can methods.  For the wind monitoring mast, only percussive or bored piling methods are considered suitable.  A discussion of each of these methods is presented below.

Piled Foundations

Piled foundations are the most common form of foundation method used in the offshore wind industry, transferring both tensile and compressive loads from the foundation into the seabed ([7]).  They have been installed since the 1940’s in water depths up to 150m.  They are simple to construct using large steel tubing and offer the most proven manufacturing option among the different types of foundations.  The installation method involves lifting or floating the structure into position using equipment such as floating crane vessels, drilling jack-up units, and specially constructed installation vessels before driving the piles into the seabed.  Installation depths are typically dependent on the environmental and soil conditions, and can range from 5m to over 120m below the seafloor for some offshore structures.  Piling is typically undertaken using percussive means, with bored piling a less common option.

Percussive Piling

Percussive piling in the marine environment is a proven technology in Hong Kong for a number of structures, i.e. jetties, navigation markers etc.  Typically, percussive piling is achieved by driving steel tubes down to required design soil resistances then filling the tubes from just below seabed level, allowing for a transition zone, with reinforced concrete.

A summary of potential issues from percussive piling methods are presented below.

·            Fine material will be generated as a result of the piling process in the footprint of pile disturbance and in the area adjacent to the pile that will be agitated;

·            Using grout to fix the foundation to the sleeve case with the potential leakage of materials (see Section 5); and

·            Sounds will be generated during piling activities.   

Bored Piles

Bored piling in the marine environment is a also a proven technology in Hong Kong.  Typically bored piling is carried out on buildings or industrial complexes, which require foundations which can bear the load of thousands of tons, in unstable or difficult soil conditions.  Bored piling is cast by using a bored piling machine which has specially designed drilling tools, buckets and grabs to remove the soil and rock.  Bored drilling is often conducted into a depth of 50 metres or more of soil or sediments to ensure stability of the pile and to achieve the required pile carrying capacity.

A summary of potential issues from bored piling methods are presented below.

·            A large casing must be driven into the seabed in order to support the boring equipment which will necessitate a longer construction period;

·            A temporary platform need to be constructed from which the bored piles will be installed. This activity will also generate noise and lengthen construction time.

·            Socketing into the bedrock will require the use of a chisel (noise impacts from socketing may be mitigated by using the reverse circulation drilling method);

·            Sound will be generated during drilling activities;

·            Fine material will be generated as a result of the drilling process, which will need to be pumped to a support barge for disposal.  There is potential for leakage of water and sediments from barges; and

·            Using grout to fix the foundation to the sleeve case with the potential leakage of materials (see Section 5).

·            As the concreting volume is large, the marine transportation will be increased significantly, which will also have a noise/sound impact.

Suction Can

Suction techniques are new to offshore wind farms, although a trial has been undertaken by CLP in Eastern Offshore waters for installation of an offshore wind monitoring mast ([8]).  Suction cans consist of tubular steel foundations installed by sealing the top of the steel buckets and creating a vacuum inside. The difference in hydrostatic pressure and the dead weight of the structures cause the buckets to penetrate the soil. The foundation can, suction pump and associated equipment will be brought to the designated area by crane barge and tug boat.  The crane barge will be deployed to lift the foundation can to the seabed level.  Once the foundation is placed on the seabed, the suction pump will be operated to pump water from inside the foundation.  This will push the foundation into seabed until the desired penetration depth is reached.  This technique is likely to create less sound than the piling techniques and potentially less waste than bored piling.

The primary limiting design condition for the monopod suction caisson is the overturning moment, while for a multi-leg suction caisson configuration; the resistance to tensile loads is paramount ([9]).  As such, a key requirement to suction caissons is the verification of installation ability and uplift capacity, where the seafloor soils must be penetrable and not prone to scour.  A disadvantage to using suction caissons is the limited proven installation data for different types of soils, requiring detailed installation analyses prior to design.  Suction caissons are also susceptible to scour, and piping below the bucket tip may occur in sandy soils.

Most of the current research on suction caissons has been carried out for sands.  However, the material at the proposed wind farm site is considered to be composed of very soft clays and silts.  Therefore, the feasibility of using these foundations would require further investigation.  It is also considered important to note, that the selection of the suction can technique for the offshore wind farm in Southeastern Waters was due to restrictions at the site.  Studies conducted for the wind farm found that geological conditions in the selected area would not be conducive to using piling (either bored or percussive) and hence an alternative method was identified ([10]).  Hence it is possible that should the more proven method of piling have been feasible, such a method would have been selected for the long term installation of turbine foundations.

Preferred Construction Method

It is proposed that the percussive piling method be used for the construction of the wind turbine and wind monitoring mast foundations.  The rationale for such is based on the following:

·           Environmental Impacts;

·           Proven Method;

·           Proven Mitigation;

·           Schedule.

Each of these is discussed below.


Environmental Impact

In contrast to percussive piling, which generates no wastes (i.e. marine sediments) to be brought to the surface, bored drilling activities do generate wastes that require off-site disposal.  For the proposed project, it has been estimated that up to 185,000 m3 of marine sediment would be brought to the surface through bored piling activities for the turbines and wind monitoring mast and hence require disposal at one of Hong Kong’s disposal facilities.  Disturbance and disposal of marine sediments has the potential to increase concentrations of suspended solids within the water column, subsequently potentially reducing dissolved oxygen and increasing nutrient content, and as such methods that avoid waste generation are considered to be environmentally favourable.  As percussive piling has no waste generation associated with these activities this method is considered to have better environmental performance.  It is noted that percussive piling can be expected to generate higher levels of underwater sound than bored piling.  As discussed below there are proven methods available to mitigate the effects of underwater sound generated during percussive piling.

Proven Method

As highlighted above, the typical method to install piles in Hong Kong is through percussive means, i.e. hydraulic hammering.  Such a method has been deemed acceptable for piling operations in Hong Kong and restrictions are applied as set by the EPD ([11]).  Installation of monopiles for wind turbines through percussive piling is also the most common method applied within the industry (see Figure 4.12 for example).

Whilst there are other available technologies and engineering alternatives for the installation of monopiles, these are considered to either still be in their development stage or in their infancy of testing and implementation.  Suction can technology may be viable alternative for installation, however, considering it is yet to be a proven technology in Hong Kong, and has not been employed in other offshore wind farms internationally, the method is not preferred over the more common piled approach.

 

Figure 4.12     Installation of Monopile Turbine Foundation at 60MW Scroby Sands Wind Farm, UK (Source: http://www.mammoetvanoord.com/webfront/base.asp?pageid=26)

 


Proven Mitigation

A series of mitigation measures have been adopted in marine piling works in Hong Kong related to the management of underwater sound impacts related to percussive piling.  The need for these measures has been due to the use of percussive piling in areas considered to be important to marine sensitive receivers, specifically those for marine mammals.

Typical measures are as follows:

·           Piling works are undertaken using hydraulic hammers, which typically have lower sound output than traditional diesel hammers;

·           Piling works take place in daylight hours (e.g. 6am to 6pm);

·           Piling works avoid peak seasons of marine mammals;

·           Piling works are undertaken in marine mammal exclusion zones which are monitored by marine mammal observers;

·           Pre-, during and post-installation monitoring of marine mammal abundance and distribution; and

·           Production of warning sounds before commencing piling, consisting of sufficiently loud but non-hazardous sounds to alert marine mammals in the area.

Key projects have demonstrated that through the effective implementation of the above, impacts to marine mammals can be avoided and percussive means of piling can be undertaken with favourable environmental performance.

It is expected that through the employment of those above mitigation measures which are deemed necessary for the project adverse underwater construction noise associated with the piling works would not be expected to give rise to unacceptable adverse impacts.  Such a conclusion is further examined within the Marine Ecological Assessment (Section 9).

Schedule

Following the principles of seeking to achieve increased environmental performance by limiting the construction period to as short as possible, thereby reducing the potential exposure of sensitive receivers to disturbance or pollution loading, it is considered important to select the most appropriate equipment to achieve this goal.  As described above, the preferred method for installation of the monopile is through piling.  There is, however, a considerable difference in the schedule required for percussive versus bored piling. 

Nearly the entire overseas offshore wind farms have adopted percussive piling as means of monopile foundations.  A review of international experience in construction schedules of offshore wind farms shows that monopile installation using percussive piling methods typically take at most 4 days to install each pile depending on down time due to weather (Table 4.3).  On this basis, it can be seen that the maximum duration of piling for these wind farms under review was approximately 5 months, with variation between depending on the number of piles involved.  Typical depth of piling was 20 – 40 m below seabed.  Subject to the final ground investigation works, it can thus be expected that the installation of up to 35 piles for the proposed wind farm would take in the same order of time, 4 to 5 months, weather dependent.

Table 4.3        Duration of Percussive Piling Works for International Wind Farms

Project

Number of pile / turbine

Pile length [m]

Water depth

(m)

Pile depth in seabed (m)

Duration

Horns Rev I, Denmark

80

34

5 – 15

25

Between 03/02 and 08/02

 

Burbo Bank,  the U.K.

25

35

3.5 – 7.5

20 – 25

Between 10/06/06 and 31/07/06

 

Scroby Sands, the U.K.

30

49

2 – 12

30

Between 10/03 and 01/04

 

Rhyl Flats, the U.K.

25

40

6.5 – 12.5

25

Between 04/08 and 07/08

 

Egmond aan Zee, the Netherlands

36

40 – 50

16 – 21

30

Between 05/06 and 07/06

 

Gunfleet Sands, the U.K.

48

50

0.5 – 10

40

Between 10/08 and 03/09

 

Utgrunden, Sweden

7

34

13 – 14

19

Within the month of September 2000

 

Horns Rev II, Denmark

 

91

28 – 40

7 – 17

22

Within one season

Lynn and Inner Dowsing, the U.K.

54

32.3 – 42.8

6 – 13

18.6 – 26

Between 10/07 and 12/07

 

Robin Rigg, the U.K.

60

50

0.3 – 8.7

30 – 40

Between 12/07 and 01/08

 

Kentish Flats, the U.K.

 

30

38 – 44

6.6 – 7.7

28 – 34

2 hours per pile

Arklow Bank, the U.K.

 

7

40

5

35 – 45

Within one season

Princess Amalia, the Netherlands

 

60

54

20 – 24

30

2 hours per pile

 

At the proposed wind farm, the water depth is over 20 m and the general thickness of marine deposits and alluvium as determined from existing drillholes was in excess of 60m (or at a depth greater than -80 mPD).  As such, the strata of weathered bedrock and bedrock may be at depths greater than -100 mPD.  The recorded wave height as indicated in Port Works' publication is in the order of 11 to 12 m.  Consequently, construction of bored piles must be carried out on a large jack up barge or a temporary platform fixed on piled foundation.  Construction of a fixed platform, depending on the size of platform, takes time.  A mono-piled wind turbine may be supported by one large mono pile of about 3 to 7 m in diameter.  Construction of one single piece of bored pile of that range of diameter would require special plant that is very rare if not unavailable; or the mono pile is supported by a cluster of bore piles of smaller diameter, say less than 3 m.  It is assumed for each mono pile a cluster of 3 bore piles are considered necessary, thus about 90 bore piles will be needed for the wind farm.  Construction of a bore pile at sea to depths in excess of 80 m would take about 1- 1.5 month under normal working conditions.  Allowing for concreting and mobilisation, it can conservatively be assumed that ~1.5 to 2 months would be needed to complete one bore pile (assuming the platform for the next cluster of bored piles is erected at the same time).  On this basis, it will take about 70 months (6 years) to complete all 90 piles for 30 mono-piles to the wind farm.  It is assumed that to minimise the noise level, only two sets of bore pile machine are to be employed.  Such duration is considered to be a significant increase and one that may result in the project being environmentally and commercially unviable.

Given the exposed marine working environment in Southwest Lamma, the construction of bored piles in water depths of around -20m would be very different to those encountered during the works for the Shenzhen Western Corridor in Deep Bay (Figure 4.13).  In Deep Bay the water depths were less than -10m and the sea conditions were very sheltered.  Consequently, construction of bored piles could be carried out on a simple access platform which is relatively fast to prepare. 

Figure 4.13     Construction of Temporary Access Bridge in Deep Bay for the Hong Kong – Shenzhen Western Corridor/Deep Bay Link

 


The above approaches contrasts with that required to conduct bored piling in open sea of significant water depth.  A robust piled platform would need to be installed that is capable of handling the exposed weather conditions.  Figure 4.14 presents a typical set up for foundation works at open sea.

Figure 4.14     Construction of Piled Marine Platform for use in Bored Piling works in open sea conditions

tugboat.jpgvibrator.jpg

 


Furthermore, should restrictions be imposed on construction works, such as closed period during marine mammal peak seasons, which can last up to six months, this may push the schedule to over 10 years of piling works with a single set of piling plant, or even 3 years using three sets of piling plants, which is still unrealistically long for piling works.  Moreover, using 3 sets of plant will significant increase the sound footprint for the works.  Such an increase in duration would result in a prolonged exposure of increased levels of marine traffic and underwater sound generating works in these southern waters and would be deemed to be  less preferred on environmental grounds than a construction period of shorter duration.

4.5.2                                Subsea Cable Installation

Grab Dredgers

A grab dredger comprises a rectangular pontoon on which is mounted a revolving crane equipped with a grab.  The dredging operation consists of lowering the grab to the bottom, closing the grab, raising the filled grab to the surface and discharging the contents into a barge.  Grab dredgers are usually held in position while working by anchors and moorings but some have a spud or pile, which can be dropped onto the bottom while the dredger is operating.

Grab dredgers may release sediment into suspension by the following mechanisms:

·           Impact of the grab on the seabed as it is lowered;

·           Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·           Leakage of water from the grab as it is hauled above the water surface;

·           Spillage of sediment from over-full grabs;

·           Loss from grabs which cannot be fully closed due to the presence of debris;

·           Release by splashing when loading barges by careless, inaccurate methods; and

·           Disturbance of the seabed as the closed grab is removed.

During the transport of dredged materials, sediment may be lost through leakage from barges.  However, as discussed above, dredging permits in Hong Kong include requirements for barges so that the potential for leakage is minimised. 

Sediment is also lost to the water column when discharging material at disposal sites.  The amount that is lost depends on a large number of factors including material characteristics, the speed and manner in which it is discharged from the vessel, and the characteristics of the disposal sites.  In addition, closed grab dredging can minimise the loss of sediment and therefore help reduce water quality impacts. 

Trailing Suction Hopper Dredgers

Trailing Suction Hopper Dredgers (TSHD) are designed to use a suction mouth at the end of a long pipe.  As the barge moves, the suction hopper trails along and sucks up the soft seabed sediments.  During dredging the drag head will sink below the level of the surrounding seabed and the seabed sediments will be extracted from the base of the trench formed by the passage of the draghead.  The main source of sediment release is the effect of the draghead when it is immersed in the mud.  This mechanism means that sediment is generally lost to suspension very close to the level of the surrounding seabed.

During dredging marine sediments are pumped into the vessel’s hopper.  Once the hopper is loaded the dredging operation will be stopped and the vessel will sail to a designated disposal area.  A TSHD is usually positioned by dynamic positioning, thus they have no anchor wires.  In comparison to grab dredgers, TSHDs generally have a higher production rate.

Jetting

The jet machine will either be self-propelled or be towed by barge.  The self-propelled machine has wheels resting on the cable and uses the cable for traction.  Stability is achieved with the use of buoyancy aids.  A ‘Non-conventional’ jetting machine may be utilised, as it does not use air to assist with discharge of the sediment.  This results in less adverse effect on the water quality of the surrounding areas. 

From the soil data, a nozzle configuration that best suits the in-situ soil characteristics will be determined.  The method is based on fluidising the muds allowing the cable to sink to the chosen depth. 

During the installation of the submarine utilities using jetting technology, it would be expected that seabed sediment would be released close to the seabed and will settle out relatively quickly.  The sediment would therefore only be in suspension for a short period of time, has reduced lateral spread from the works area and as such, the potential for impacts to occur, such as through the exertion of the oxygen demand on the receiving waters, will be limited.

Preferred Installation Techniques for the Submarine Cable

Jetting, grab dredgers and Trailing Suction Hopper Dredgers (TSHD) are commonly used in Hong Kong.  Since TSHDs have higher production rates and are typically employed on large scale dredging projects, which this is not, it is recommended that grab dredgers and jetting equipment are considered. 

The employment of jetting, grab dredging and TSHD are considered viable engineering options.  However, the generally preferred installation method for submarine cables is the use of jetting as this would lead to lower water quality impacts than dredging techniques due to the potential to cause disturbance and impacts on-site with dredging works and off-site with disposal works.  However, jetting at the nearshore zone would not be suitable for cable installation to shore.  For the nearshore cable installation, there will therefore be a requirement for seabed preparation using grab dredging techniques. 

4.5.3                                Cable Crossing and Protection

The new 22kV, 33kV or other voltage rating according to the proprietary design of wind turbine manufacturer’s submarine cables will have to cross over existing submarine communication cables.  The typical crossing method is to lower the existing communication cable and then lay the new cable above the existing cable (see Section 5).  Additional protection for the submarine cables, including in-situ concrete mat and reinforced concrete covers, could be installed at the crossing points.

 



([1])     http://www.weather.gov.hk/cis/region_climat/CCH/CCH_windrose_year_e.htm

([2])     http://www.ae.hangglide.dk/html/linked.php?go=wake

([4])     www.offshorewindenergy.org

([5])     Airtricity (2005). Greater Gabbard Offshore Wind Farm – Environmental Statement. Image provided by Global Scour Control Systems Ltd

([6])     CLP (2006). EIA-124/2006: A Commercial Scale Wind Turbine Pilot Demonstration at Hei Ling Chau

([7])         Westgate. ZJ, DeJong. JT (2005) Geotechnical Considerations for Offshore Wind Turbines.

([8])     BMT Asia Pacific (2009) Hong Kong Offshore Wind Farm in Southeastern Waters - Environmental Impact Assessment.  Reference ESB-146/2006.  Issue 3.

([9])         Westgate. ZJ, DeJong. JT (2005) Geotechnical Considerations for Offshore Wind Turbines.

([10])    BMT Asia Pacific (2009) Op cit.

([11])    Technical Memorandum on Noise from Percussive Piling. Special Supplement to Gazette No. 20 Vol CXXXIX.  May 1997.