The study presented in Annex 12B covers the details of the Quantitative
Risk Assessment (QRA) for the two Gas Receiving Stations (GRSs)
to be built at the Black Point Power Station (BPPS) which will receive natural
gas through two subsea pipelines from the Mainland. This section extends the analysis to
consider also the existing GRS (Figure
12C.1), although this is not included in the EIA Study Brief.
The proposed pipelines from the Mainland
China will terminate at two gas receiving stations (GRSs)
at BPPS. One will be located
adjacent to the existing GRS (co-located GRS), the
second will be located on reclaimed land to the north of the BPPS site (GRS on
reclamation). The two GRSs are not expected to be constructed concurrently. The co-located GRS will be constructed
in 2011 (i.e. First Phase construction) while the construction of the GRS on
reclamation is expected to commence within 24 months of commissioning of the
first pipeline, in around 2014.
As the two GRSs
are not expected to be constructed concurrently, the following cases can be
considered in the analysis:
1)
Existing
GRS operating and co-located GRS under construction (2011);
2)
Existing
and co-located GRS operating (2011);
3)
Existing
and co-located GRS operating and GRS on reclamation under construction (2014);
4)
3 GRSs operating (2021).
In Annex
12B, the following cases have already been assessed:
a)
Only
co-located GRS in operation;
b)
Co-located
GRS in operation and construction of the GRS on reclamation;
c)
Both
co-located and GRS on reclamation operating.
Since the separation distances between the
existing and co-located GRS is similar to that between the co-located GRS and
the GRS on reclamation, the results of case b) and c) can be applied
respectively to case 1 and case 2.
Therefore, this Annex focuses on results
for the following two cases:
·
Case
3: Existing and co-located GRS operating and GRS on reclamation under
construction (2014); and
·
Case
4: All 3 GRSs operating (2021)
Detailed information of the study
methodology is presented in Annex 12B. The same methodology is applied for the existing
GRS, except that coordinates are updated to reflect the actual location of
equipment and leak frequencies are modified to take into account the different
lengths of piping and number of equipment items such as heaters.
Figure
12C.1 GRS Locations
Black Point Power Station Existing GRS GRS on Reclamation (GRS ‘B’) Co-located GRS (GRS ‘A’) |
12C.2
Results
Individual Risk Results
The individual risk (IR) contours
associated with the case 3 in 2014 are shown in Figure
12C.2. The
maximum risk is less than 1´10-5
per year at all locations and hence meets the HKRG requirements.
Figure 12C.2 Individual
Risk Contours (2014) – Case 3
The results for case 4 in
2021 are presented in Figure 12C.3. With three GRSs
operational, the IR has increased and exceeds in some locations 10-5
per year. However, the 10-5 per year contour does not extend offsite
and hence meets the HKRG requirements.
Figure 12C.3 Individual
Risk Contours (2021) – Case 4
Societal Risk Results
Figure 12C.4 shows
the FN Curves for the GRS at the BPPS for construction year 2014 with 2 GRS in
operation and the GRS on reclamation being constructed. Compared to the results presented in Figure 12.9, Section 12, the risks have only increased slightly due to the
predicted slight increase in surrounding marine population. The results are within the acceptable
region.
Figure 12C.4 FN
Curves for GRS – case 3 in year 2014
For the year 2021, when all 3 GRSs
will be operational, the risks are low (Figure
12C.6) due to the remote location of the site and low population in the
vicinity.
Figure 12C.5 FN
Curves for GRS – case 4 in year 2021
Individual risks associated with the facilities meet
the HKRG.
Societal risks associated with the operational phases
of the project are low and lie in the acceptable region of the FN curves.
No significant increase in societal risks was found
for the construction phases of the project. The slight increases found are due
to increase in marine population predicted. Recommendations are nevertheless made in
accordance with best practice to mitigate these construction phase risks:
·
The
most hazardous maintenance operations on the existing GRS will be avoided
during the construction of the GRS on reclamation.
·
Procedures
for evacuation of construction workers will be in place in case of particularly
hazardous operations on existing GRS and co-located GRS.
·
Specific
emergency procedures will be put into place for the evacuation of construction
workers.
·
Additional
gas detectors along the boundary or gas and fire alarms for the detection from
the GRSs in operation for escape and evacuation of
construction workers will be considered.
·
The
construction of a temporary steel wall or other appropriate barrier between the
existing GRS and the GRS on reclamation will be considered to prevent gas
spreading towards the construction site in case of a gas leak in the existing
GRS. This will also prevent the gas
coming in contact with the ignition sources at the construction site, limit
exposure of personnel to any direct flame from the existing GRS and provide
time for construction personnel to evacuate the site.