Annex 2A-1 Evaluation
Outcomes of Preliminary Screening Study for GRS Locations
Evaluation
Criteria |
Site A |
Site B |
Site C |
Site D |
Site Location |
It comprises a
strip of the western side of the west ash lagoon. The area currently features a concrete
barge landing and a large concrete hardstand storage space. A pumping station compound located
near the southern end of the site is not place any unmanageable constraints
on the development of GRS facilities on the adjacent area. |
It comprises a
new reclamation adjacent to the existing GRS. Two options based on the different
locations of the reclamation were considered: Option 1 is an area between the
existing Yacheng pipeline and the BPPS cooling water outfall, which is the
location previously defined in the HKLNG EIA and Environmental permit; Option
2 is an area between the existing Yacheng pipeline and the Western Ash
lagoon. |
It comprises an
area at the north eastern end of the existing GRS that would be an extension
of the existing compound on which the existing GRS stands. Much of the site area is presently natural
hillside that would have to be cut to create a flat area for the GRS. It should be noted that the existing
power cables that supply electricity to Shekou cross the proposed site area
and that a small portion of the existing GRS compound would have to be
utilised to form the new site. |
The existing GRS features three areas that do not presently have any
equipment or piping installed.
Additionally, the slug catcher is redundant and could be removed,
creating more space area on the south side of the pipe rack. Work previously done for the HKLNG
project showed there is sufficient space for one additional pipeline terminal
and GRS. |
|
The pipelines
could approach the site from the Northwest and be constructed through the existing
seawall. Note that in all cases
the pipeline would have to cross the existing power cables that supply
electricity to Shekou. |
The pipelines
could approach the site from the Northwest and be constructed through the new
seawall in a “slot” prepared during seawall construction. Note that in the case of Option 1 the
pipelines may have to cross the existing Yacheng pipeline depending on
pipeline design. |
The pipelines
could approach the site from the Northwest and be constructed through the
existing seawall. |
The pipelines could approach the site from the Northwest and be
constructed through the existing seawall to the north of the Yacheng
pipeline. |
Fuel |
Fuel gas
headers could easily be routed parallel to the existing sea wall to a mixing
& handling facility constructed within the existing GRS compound. |
Fuel gas
headers could easily be routed to a handling facility constructed within the
existing GRS compound. |
Fuel gas
headers could easily be routed to a handling facility constructed within the
existing GRS compound. |
Fuel gas headers could easily be routed to a handling facility
constructed within the existing GRS compound. |
Constructability |
Site
preparation is expected to be limited to consolidating the existing ground,
filling where required to extend the available site area beyond the existing
hardstand and constructing a secure boundary fence. Existing access roads to the ash
lagoon are presently used by heavy trucks and are considered suitable for construction
access. The existing concrete
wharf is considered suitable for handling of materials and equipment
delivered by barge and there is a large amount of space that could be used
for temporary storage of materials and equipment during construction. Provision of construction power and
water from BPPS could be easily arranged and in general, construction
activities would not be expected to affect or be affected by external factors
related to the existing GRS or power station. Access and egress by at least two
separate routes can easily be maintained for emergency situations. |
Site
preparation would involve construction of the boundary seawall and reclaiming
the site areas within to extend the existing reclamation. Existing access roads through BPPS and
around the perimeter are considered suitable for construction access. The existing heavy lift wharf in BPPS
is considered suitable for handling of materials and equipment delivered by
barge and there is an amount of space within the BPPS property that could be
used for temporary storage of materials and equipment during
construction. Provision of
construction power and water from BPPS could be easily arranged and in
general, construction activities would be expected to affect or be affected
by external factors related to the existing GRS or power station to a limited
extent. Access and egress by at
least two separate routes can easily be maintained for emergency situations. |
Site
preparation would involve cutting the hillside adjacent to the NE end of the
existing GRS. Existing access
roads through BPPS and around the perimeter are considered suitable for
construction access. It should be
noted that the existing cables that supply electricity to Shekou currently
cross the proposed site area. The
existing heavy lift wharf in BPPS is considered suitable for handling of
materials and equipment delivered by barge and there is an amount of space
within the BPPS property that could be used for temporary storage of
materials and equipment during construction. Provision of construction power and
water from BPPS could be easily arranged and in general, construction
activities would be expected to affect or be affected by external factors
related to the existing GRS or power station to a limited extent. Access and egress by at least two
separate routes can easily be maintained for emergency situations. |
Construction within the existing facility would have to be carried out
while the existing facilities are in operation. Previous studies performed in the
course of HKLNG project FEED indicate that the work can be completed however
a number of constraints and risks exist that do not exist on a |
Operability |
The site is
expected to offer an ideal operating environment for the proposed facilities. |
The site is expected
to offer an ideal operating environment for the proposed facilities. |
The site is
expected to offer an ideal operating environment for the proposed facilities. |
The site is expected to offer a suitable ideal operating environment
for the proposed facilities, however operation of the different facilities by
different operators will need to be handled carefully and interfacing
procedures put in place ensuring safety and reliability. |
Impact on
Existing Operations |
Impact on existing
operations during construction and operation are expected to be limited to
minor works required to route the new GRS export headers into the existing
GRS compound for connection to the new gas management facilities. |
Impact on
existing operations during construction and operation are expected to be
limited to minor works required to route the new GRS export headers into the
existing GRS compound for connection to the new gas management facilities. |
Impact on
existing operations during construction and operation are expected to be
limited to minor works required to route the new GRS export headers into the
existing GRS compound for connection to the new gas management
facilities. It is likely that the
existing Shekou power supply cables would have to be repositioned in the
course of site preparation. |
Impact on existing operations during construction and operation could
be limited by planning the construction work to be performed in small
increments over a suitable schedule period. The potential must be recognized,
however, for a mishap during construction or operations having an adverse
impact on the current operation. |
Available Space |
Relative to the
site area required for the new GRS facilities there is adequate space both
for the permanent facilities and for temporary construction laydown areas. |
Relative to the
site area required for the new GRS facilities there are constraints on the
space available for reclamation that include the BPPS cooling water outfall,
the existing Yacheng pipeline and the existing power cables that supply
electricity to Shekou. |
Relative to the
site area required for the new GRS facilities there are constraints on the
space available that make substantial slope cutting the only means of
providing sufficient space for the new facilities. These include the existing GRS
compound to the west and the existing West Ash Lagoon to the east. |
Relative to the site area required for the new GRS facilities there are
tight constraints on the space available for new facilities. The existing vent stack exclusion area
imposes a large obstacle and investigation into alternative arrangements
needs to be carried out during subsequent engineering studies and design
work. |
Layout Options
& Flexibility |
The site provides
flexibility in size and shape for the proposed new GRS compound having few
physical constraints that could impede the development. |
The site
provides limited flexibility in size and shape for the GRS compound because
of the physical constraints that exist as well as the limits on reclamations. |
The site
provides limited flexibility in size and shape for the GRS compound because
of the physical constraints that exist as well as the practical limits on
slope cutting. |
The site provides limited flexibility in layout options because of the
physical constraints that exist. |
Future
Expansion |
The potential
for future expansion of the facilities is not known, however the space required
for the GRS is small compared with the existing clear area available at this
site and therefore it is expected that future expansion could easily be
accommodated. |
The potential
for future expansion of the facilities is not known, however the space
required for the GRS will have to be reclaimed, as would any additional area
identified for future expansion.
Thus a considerable amount of pre-investment would be involved if
plans for future expansion are considered. |
The potential
for future expansion of the facilities is not known, however much of the
space required for the GRS will have to be cut from the hillside, as would
any additional area identified for future expansion. Thus a considerable amount of
pre-investment would be involved if plans for future expansion are
considered. |
The potential for future expansion of the facilities is not known,
however it is felt that there would be insufficient space in the existing
compound for future expansion unless the Yacheng supply ceased and the
relevant facilities were removed to make space available for other new
facilities. |
Safety, Risk
& Health Issues |
None identified |
None identified |
None identified |
None identified |
Environmental
Issues |
None identified |
Moderate consequences
for marine ecological and water quality impacts due to reclamation activities |
Catastrophic
consequences for vegetation and slope cutting |
None identified |
Financial
Impact |
Moderate consequences
for site formation (cost for land fill), foundation construction, land
acquisition and compensation costs. |
Catastrophic
consequences of site formation – reclamation & disposal of contaminated
spoils Moderate
consequences for shore crossing, land acquisition and compensation costs. |
Catastrophic
consequences of Slope Cut& disposal of contaminated spoils Moderate
consequences for land acquisition and compensation costs |
Moderate
consequences for future expansion and flexibility |
Schedule Impact |
Catastrophic
consequences of onshore land gazettal issues and competing with Govt for
usage of site (landfill) |
Moderate
consequences of land gazettal issues |
Moderate
consequences of permitting/ approval and land gazettal issues |
None identified |
Commercial/
Regulatory Concern |
Decommissioning
of the Ash Lagoon would require an EIA itself which is seen to be undesirable
and prone to schedule delay. Land
acquisition by HKSAR Government would also be complex given a conflict of
interest. |
Acquisition of
the land would be covered by either a plot extension (extension of the
existing BPPS plot) or by
acquisition of a new land lot under the provisions of the FSRO and Lands
Department processes. This is
expected to be relatively straightforward and achievable within the target
timeframe. |
Acquisition of
the land could be a complex process because of its current natural
state. Site formation would
necessitate clearing of all vegetation and aggressive slope cutting. Opposition from green groups and other
stakeholders could be expected, leading to further delays to the project. |
Potential legal/ commercial issues that would have to be resolved with
the operator of the existing GRS at BPPS. Construction of new plant in the |
Conclusion |
NOT PREFERRED because of insurmountable schedule impacts
associated with permitting/ approval and land acquisition |
PREFERRED considering an approved EIA for a similar
location is present. |
NOT PREFERRED because of the financial and schedule impacts
associated with permitting/ approval and land acquisition, and terrestrial
habitat loss. |
PREFERRED as there is limited external,
uncontrolled impacts. |
Safety, Risk & Health Issues, Environmental
Issues, Financial Impact and Schedule Impact were evaluated, analysed and
prioritised into three broad categories (Catastrophic,
Moderate, and Insignificant), based on the extent of impacts. The ranking protocols developed for this
review is presented in Annex 2A-2
The design capacity of a GRS is described in Annex 2A-3.
Annex 2A-2 Ranking
Protocols for the Preliminary Screening Study
Annex 2A-3 Design
Capacity of a Gas Receiving Station
Design Capacity of a Gas Receiving
Station (GRS) |
It is critical
that each GRS has sufficient capacity to accommodate the generating capacity
of the BPPS as well as future needs.
This design can ensure that in case failure/ depletion of gas is found
in any of the pipelines, the remaining pipeline(s) and the associated GRS(s)
(i.e. in the worst case, only one pipeline and one GRS can be in operation) can
still provide sufficient capacity to handle BPPS/ HK's fuel need. Such a design can ensure a secure
supply/ use of natural gas as fuel.
It is also important to note that the size of land required for each
GRS does not reduce in proportion to the GRS capacity. During the
early stage of this Project CAPCO has optimised the design of the two
proposed GRSs and the present layout of the GRSs represents a minimal land
requirement, taking into account the engineering and commercial requirements
as well as the construction risk associated with operating gas stations. |
Need for the Existing CNOOC GRS |
The existing
CNOOC GRS is designed to provide sufficient capacity to accommodate the
generating capacity of the BPPS under an individual supply contract. It is understood that depletion of the
gas supply for the Y-13 pipeline (Yacheng 13-1 field) is expected as early as
2012, but the rate of depletion is unknown and it is expected that the
diminishing supply from Yacheng 13-1 will still be used by the BPPS well into
the near future (but at lower supply rates). It is therefore crucial that at
present the CNOOC GRS, and any part of it, stays in operation and is not
decommissioned to allow for a secure supply of gas to HK. |