6A1                                  introduction

6A1.1                            Background

Castle Peak Power Company Limited (CAPCO) proposes to construct and operate two submarine gas pipelines connecting Black Point Power Station (BPPS) with gas export facilities in southern Guangdong Province (Figure 6A.1).  At the BPPS two Gas Receiving Stations (GRSs) will also be constructed and operated to receive the natural gas (Figure 6A.2).  One new GRS will be located within the site boundary of the BPPS, co-located with the existing GRS.  The other new GRS will be situated on a newly reclaimed land (approximately 0.5 ha land area) to be constructed along the artificial seawall of the BPPS.  The site for the new reclamation will be the same as that proposed for the GRS in the South Soko option for the HKLNG EIA ([1]).

Figure 6A.1    Indicative Alignment of the Cross-boundary Submarine Gas Pipelines Connecting the BPPS and the New Gas Export Facilities in Mainland China

 

Figure 6A.2    Locations of Proposed Gas Receiving Stations


6A1.2                            Purpose of the Method Statement

This Method Statement presents information on the approach for the water quality assessment and modelling works for the Study.  It is important to note that at the time of completion of this Method Statement the detailed engineering information for both construction and operation activities is yet to be confirmed and therefore a general approach as to how the modelling works would be carried out is presented herein, with relevant assumptions provided as appropriate. 

The methodology has been based on the following three focus areas, as follows:

·            Model Selection;

·            Input Data; and

·            Scenarios.

6A1.3                            Interpretation of the Requirements: Key Issues and Constraints

The objectives of the modelling exercise are to assess:

·            Effects of construction, which comprises the study of the dispersion of sediments released during construction, including the installation of two submarine gas pipelines and construction of the reclamation for one of the new gas receiving stations at BPPS;

·            Effects of operation due to reclamation, including potential effects on flows and subsequent water quality effects due to changing flows, and potential sedimentation/ siltation around the new reclamation;

·            Any residual impacts, which include any change in hydrodynamic regime (e.g. flushing capacity);

·            Any cumulative impacts due to other projects or activities within the Study Area.

The construction and operational effects have been studied by means of mathematical modelling using the Delft 3D package which is a world leading 2D/3D modelling system to investigate hydrodynamics, sediment transport and morphology and water quality for fluvial, estuarine and coastal environments.

6A1.4                            Model Selection

A new model has been developed using the model setup details of the 3-dimentional model that was adopted in the HKLNG EIA ([2]).

The Delft 3D hydrodynamic (Delft3D-FLOW) and water quality (Delft3D-WAQ) suite of models have been used to simulate potential impacts on hydrodynamics and water quality, respectively, during construction and operation of the Project.

The original Update Model has the required spatial extent for the proposed project facilities, ie waters 2.5 km beyond the HKSAR Boundary (up to the west boundary of Tonggu Fairway) (Figure 6A.3).

Figure 6A.3    Model Grid of the Original Update Model in the Vicinity of Black Point ([3])


 

6A1.5                            Grid Refinement & Subsequent Approval

As seen in Figure 6A.3, the grid size of the original model near the Black Point Power Station (BPPS) is in the order of about 300 m.  During the HKLNG EIA ([4]), local refinement of the water quality and hydrodynamic grids was carried out to provide improved resolution (less than 75 m) in some of the key areas of interest (Figure 6A.4).  A further refinement of the model grids with a target resolution of 50 m ´ 50 m has been implemented by means of the domain decomposition technique in this Study (Figure 6A.5).  The FLOW model grid has subsequently been adopted without further aggregation in the water quality models.

In order to provide locally increased grid resolution, a four-grid Domain Decomposition (DD) system has been setup with the highest resolution (approximately 15 m ´ 30 m) in the immediate vicinity of the BPPS intake and outfall structures.  The existing model grid in the vicinity of Deep Bay has been adjusted and higher resolution DD domains have been included as follows:

·          WHM - an overall domain which is almost same as the original model;

·          TFW - an intermediate domain provides enhanced resolution in a wider area around the Project site and the pipeline alignments;

·          SHZ - Deep Bay domain; and

·          BPP – local BPPS domain with the highest resolution.

 

Figure 6A.4    The Existing Model Grid in the Vicinity of Black Point for HKLNG EIA ([5])

 


 

Figure 6A.5    Refined Model Grid in the Vicinity of Black Point for This Project

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


The model used in this study is based on the Update Model.  Parts of the model were refined to compute flow behaviour with a high resolution in the vicinity of the Black Point Power Station.  To show that the refined model is consistent with the Update Model, computed water levels, depth-averaged current speed and directions, and depth-averaged salinities are compared at two locations in the model (see Box 1).

Comparisons are made between the two models for the wet and dry seasons.  The results for the dry season are shown in Boxes 2 and 3.  For the wet season the results are shown in Boxes 4 and 5.

Given that the models show similar results, the models were considered as consistent.  Differences between the model solutions are caused by:

1)        the higher resolution solution in the finer domains, causing more accurately represented seabed variations and coastlines;

2)        the initial conditions in the runs were not exactly identical, because in the project the single domain run was used to spin-up the salinity and temperature fields for the refined model run.

Box 1              Model Validation Locations


 

Box 2              Model Verification for Point 1 (near BPPS).  Update Model (blue) vs Refined Model (red) – Dry Season


 

Box 3              Model Verification for Point 2.  Update Model (blue) vs Refined Model (red) – Dry Season


 

Box 4              Model Verification for Point 1 (near BPPS).  Update Model (blue) vs Refined Model (red) – Wet Season


 

Box 5              Model Verification for Point 2.  Update Model (blue) vs Refined Model (red) – Wet Season

 

 

 

 

 

 

 


6A1.6                            Coastline & Bathymetry

Hydrodynamic data have been obtained using coastline and bathymetry for a time horizon representative of the construction of the facility (ie 2011 onwards).  Bathymetry and coastline information have been updated in this exercise ([6]) to reflect the depth of Tonggu Fairway and recent changes in coastline (Figure 6A.6).

Figure 6A.6    Updated Bathymetry and Coastline Used in the Present Model


 

6A1.7                            Boundary Conditions

The boundary conditions, adopted in the HKLNG EIA ([7]), have been applied at the outer boundaries of the WHM domain.  The background surface layer temperature is around 23 ºC in the dry season simulations and about 28 ºC in the wet season simulations.

6A1.8                            Vector Information

The current patterns under the baseline situation were generated as an output of the baseline hydrodynamic modelling.  Another scenario was used to simulate the tidal flow in the Project area in the presence of the reclamation (i.e. post-project situation).  The hydrodynamic modelling results are presented in Annex 6B as vectors showing the current direction and magnitude. 

6A1.9                            Information on Model Inputs

6A1.9.1                      Details of Hydrodynamic Simulations

All hydrodynamic scenarios were simulated for a spring-neap-cycle during the dry season and a spring-neap-cycle during the wet seasons.  The simulation periods were:

·          Dry season: simulation period from 2 February 12:00h to 22 February 12:00h, simulation period 20 days, time step 12 seconds.

·          Wet season: simulation period from 19 July 04:00h to 10 August 04:00h, simulation period 20 days, time step 12 seconds.

Adequate spin-up was provided for salinity and temperature by using initial values derived from the baseline simulations for the HKLNG EIA ([8]), after interpolation on a single domain version of the WHM.  A 22 day single domain run was conducted with this model to ensure that salinity and temperature fields were sufficiently spun up.  Suitable salinity and temperature fields were selected from the single domain runs and interpolated on the 4 domain model.  These fields were used as initial conditions for the production runs covering a period of 22 days of which the first 7 days were meant to spin up water levels and currents whilst the last 15 days as production.

As explained under Section 6A.1.5, the single domain runs were used as spin-up for the refined model runs.  As the results of the single domain runs are consistent with those of the detailed model, the spin-up period can be considered sufficient (see Boxes 2 to 5).

The hydrodynamic model has included the fresh water inflows from four Pear river outlets as well as from Shenzhen River in Deep Water.  The salinity of the river outflows was assumed to be 0.1 ‰ and the temperatures in the dry and wet seasons were attributed to be 23 ºC and 30 ºC, respectively.

Table 6A.1     Typical Seasonal River Discharge Rates

River

Dry Season (m3 s-1)

Wet Season (m3 s-1)

Humen

1248

7442

Jiaomen

527

4732

Hongqili

128

1535

Hengmen

136

2805

Deep Bay (Shenzhen River)

2.5

16

 

The newly created 4 domain model was found to provide consistent results in comparison with the unrefined WHM and the locally refined model developed as part of the HKLNG EIA ([9]). 

6A1.9.2             Details of Sediment Dispersion / Water Quality Modelling

The sediment dispersion and water quality simulations were driven by the results from the hydrodynamic simulations described in Section 6A1.9.2.  In particular, the velocity components in the three spatial directions were directly derived from the hydrodynamic model.  In addition, the vertical dispersion coefficient was calculated from the turbulent eddy diffusivity generated by the hydrodynamic model.  Given this quantity can approach zero, an additional value of 10-6 m2 s-1 was added to represent molecular diffusion and turbulent diffusion that could not be resolved by the hydrodynamic model.

The horizontal dispersion coefficients in two directions were set to 1 m2 s-1.  This small value was considered to be suitable for use in 3D modelling since all vertical and lateral velocity gradients were already explicitly represented by the velocity components in the 3 spatial directions.

The time step for the water quality simulations was set to 30 minutes whereas the time step for the sediment dispersion simulations had been narrowed down to 2 minutes.  This could not only improve the model accuracy, but also provide sufficient temporal resolution in order to accurately represent the various moving sediment sources in the model.  Both sets of simulations used a fully implicit integration method which provided unconditional stability.  In view of the relatively small temporal and spatial gradients, the selected time step in combination with the locally refined grid ascertained sufficient accuracy.

The sediment dispersion and water quality simulations were modelled for typical spring-neap cycles in the dry and wet seasons.  The time periods representing these seasons were derived from the corresponding hydrodynamic model simulations, where the spin-up periods of 8 days were skipped:

·          Dry season: simulation period from 10 February 12:00h to 22 February 12:00h.

·          Wet season: simulation period from 27 July 04:00h to 10 August 04:00h.

For the water quality simulations, the relevant pollution loadings to the model area were derived from the 2012 time horizon pollution loadings (baseline scenario).  To obtain relevant boundary conditions, the present model was “nested” in the 2012 time horizon (baseline scenario).  This implies that time and space dependent concentrations of all state variables along the model boundaries have been extracted from the output of the Update model, for equivalent simulation periods.  This ascertains that the impact of pollution loadings outside the current model domain can be correctly transferred to the current model via the boundary conditions.

The water quality simulations have been run for 3 consecutive spring neap periods of 14 days where the last cycle is used to produce output.  It has been verified that the simulation results for the third cycle are independent of the initial conditions and constitute cyclical concentration patterns representative for the dry and wet seasons. 

6A1.10                        Uncertainties In Assessment Methodologies

Uncertainties in the assessment of the impacts from suspended sediment plumes should be considered when drawing conclusions from the assessment.  In carrying out the assessment, the worst case assumptions have been made in order to provide a conservative assessment of environmental impacts.  These assumptions are as follows:

·           The assessment is based on the peak dredging and filling rates.  In reality, these will only occur for short period of time;

·           The calculations of loss rates of sediment to suspension are based on conservative estimates for the types of plant and methods of working; and,

·           The assumptions of the dredger forward speed are made only for the modelling purpose but the actual dredging rates may not be the same and will be subject to the weather constraints, site conditions and continued operational progress.  In reality, the dredger moving speed should be calculated from the result of dividing the total volume of dredged materials (m3) by the duration of the dredging works (day).

The conservative assumptions presented above allow a prudent approach to be applied to the water quality assessment.

The following uncertainties have not been included in the modelling assessment:

·            Ad hoc navigation of marine traffic;

·            Propeller scour of seabed sediments from vessels;

·            Near shore scouring of bottom sediment; and

·            Access of marine barges back and forth the site.

6A1.11                        Assessment Scenarios

The water quality modelling exercise was conducted with regard to two main components, construction phase and operation phase as detailed below.

·           Construction Phase: the assessment examined potential water quality impacts arising from the following activities:

·           Dredging/ jetting for the installation of the two submarine pipelines (32” – 42”; about 813 mm – 1067 mm) in separate trenches (assuming the two pipelines are 100 m apart).  Sediment dispersion simulations covered pipeline installation works within HKSAR waters and for works within a set distance (ie about 2.5 km) from the HKSAR boundary.

·           Dredging and reclamation works for the construction of the GRS: at present it is expected that the GRS for Pipeline 2 will be placed on a reclaimed land that will need to be dredged to remove soft marine deposits.  Two simulations for one dredged scenario for reclamation were conducted for both the wet and dry seasons.

This Project is expected to adopt a Phased Construction approach.  First Phase will include the installation of Pipeline 1 and Second Phase will consist of the installation of Pipeline 2 and the construction of the GRS at the reclamation site.  At this stage the construction of the two phases are planned to be separate.  First Phase construction will commence in 2011 to allow for First gas to arrive by 2012, while Second Phase construction is expected to commence within 24 months following commissioning of the first pipeline and GRS.

To assess potential project-specific impacts of this phased construction, computational modelling was conducted separately for the First Phase and Second Phase construction.

·           Operation Phase: the assessment examined potential water quality and hydrodynamic impacts arising primarily from the presence of new reclamation for the construction of the GRS.  It is anticipated that the positioning of the reclamation would have the potential to interfere with current patterns and flow regime in the area, which could potentially cause impacts as follows:

o          Changes to the flushing of Deep Bay potentially leading to a deterioration in water quality;

o          Changes in the patterns of sedimentation around the BPPS area; and

o          Changes in the dispersion and dilution of the cooling water effluent discharged from BPPS.

Water quality and hydrodynamic modelling were conducted to examine these potential changes during the operation phase.

A detailed description of the modelling scenarios for construction phase and operation phase is presented in Sections 6A3 and 6A4, respectively.

 

6A2                                  Water Sensitive Receivers

The water quality sensitive receivers (WSRs) have been identified in accordance with Annex 14 of the Technical Memorandum on EIA Process (EIAO, Cap.499, S.16).  These WSRs are illustrated in Figure 6A.7 and listed in Table 6A.2.  The representative WSRs are included as discrete model output points as shown in Figure 6A.8.

Table 6A.2      Water Quality Sensitive Receivers (WSRs) in the Vicinity of the Project Site

Sensitive Receiver

Name

Water Quality Modelling Output Location

Fisheries and Marine Ecological Sensitive Receivers

Fisheries Sensitive Receivers

Oyster Production Area

Sheung Pak Nai

SR2

Recognised Spawning/
Nursery Grounds

Fisheries Spawning Ground in North Lantau

SR8

Artificial Reef Deployment Area

Sha Chau and Lung Kwu Chau

SR6e

Marine Ecological Sensitive Receivers

Mangroves

Sheung Pak Nai

SR2

 

Ngau Hom Shek

SR2a

Marine Parks

Designated Sha Chau and Lung Kwu Chau

SR6a,c

Intertidal Mudflats

Ha Pak Nai

SR1

Seagrass Beds

Sheung Pak Nai

SR2

 

Ha Pak Nai

SR1

Horseshoe Crab Nursery Grounds

Ha Pak Nai

SR1

Between Ngau Hom Shek and Pak Nai

SR2a

Water Quality Sensitive Receivers

Non-gazetted Beaches

Lung Kwu Sheung Tan

SR5a

Lung Kwu Tan

SR5b

Secondary Recreation Subzone

NW WCZ

SR5b

Seawater Intakes

Black Point Power Station

SR4

 

Castle Peak Power Station

SR7a

 

Tuen Mun Area 38

SR7b

 

Shiu Wing Steel Mill

SR7i

 

6A3                                  Construction Phase

For the construction phase the WAQ model has been used to directly simulate the following parameters:

·            suspended sediments (SS); and

·            sediment deposition.

It is assumed that the worst-case construction phase impacts will be at the commencement of dredging, when there is no depression formed to trap sediments disturbed during dredging works.

Note that Dissolved Oxygen (DO) depletion, Total Inorganic Nitrogen (TIN) and Unionised Ammonia-Nitrogen (NH3-N) has been calculated using the modelled maximum SS concentrations.  This method has been adopted in a recently approved EIA ([10]).

6A3.1                            Working Time

The works programme for dredging and reclamation activities for the proposed GRS at BPPS is based on the assumption of a 16 working hours per day with 7 working days per week.  An arrangement of 24 working hours and 7 working days is unlikely to be feasible for Black Point due to the potential noise impact generated by barges travelling at night to the villages located in close proximity to the route of Black Point.

As for the works programme for submarine gas pipeline installation, it is based on the assumption of a 12 working hours (daylight hours) per day with 7 working days per week for grab dredging / jetting for pipeline sections outside of the Urmston Road.  An assumption of a 24 working hours per day with 7 working days per week has been adopted for grab dredging for pipeline sections along the Urmston Road.

The assumption of working time in the model is summarised in Table 6A.3.

Table 6A.3     A summary of working time assumed in the model for various construction activities

Construction Activities

Locations

Assumption of Working Time

Dredging and Reclamation of Gas Receiving Station

BPPS, Black Point

16 hours per day and 7 days per week

 

Dredging and Installation of Submarine Gas Pipelines in Hong Kong waters

From Black Point (BPPS) to HKSAR Boundary

For grab dredging and jetting, 12 hours per day (daytime) and 7 days per week for pipeline sections outside of the Urmston Road

 

 

For grab dredging, 24 hours per day and 7 days per week for pipeline sections along the Urmston Road

Dredging and Installation of Submarine Gas Pipelines in PRC waters

2.5 km beyond the HKSAR Boundary, up to the western boundary of Tonggu Fairway

For both grab dredging and jetting, 24 hours per day and 7 days per week

 

 

6A3.2                            Overview Of Dredging Plants

6A3.2.1                      Grab Dredgers

The submarine pipelines may need to be pre-trenched and this is likely to be done utilising a grab dredger.

Grab dredgers may release sediment into suspension by the following mechanisms:

·            Impact of the grab on the seabed as it is lowered;

·            Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·            Leakage of water from the grab as it is hauled above the water surface;

·            Spillage of sediment from over-full grabs;

·            Loss from grabs which cannot be fully closed due to the presence of debris;

·            Release by splashing when loading barges by careless, inaccurate methods; and

·            Disturbance of the seabed as the closed grab is removed.

In the transport of dredging materials, sediment may be lost through leakage from barges.  However, dredging permits in Hong Kong include requirements that barges used for the transport of dredging materials have bottom-doors that are properly maintained and have tight-fitting seals in order to prevent leakage.  Given this requirement, sediment release during transport is not proposed for modelling and its impact on water quality will not be addressed under this Study.

Sediment is also lost to the water column when discharging material at disposal sites.  The amount that is lost depends on a large number of factors including material characteristics, the speed and manner in which it is discharged from the vessel, and the characteristics of the disposal sites.  It is considered that potential water quality issues associated with disposal at the intended government disposal site(s) have already been assessed by CEDD and permitted by EPD, hence and the environmental acceptability of such disposal operations is proven.  Therefore modelling of impacts at disposal sites does not need to be addressed and reference to relevant studies will be provided in the EIA for this Project where appropriate.  It should be noted that the capacity of the existing mud disposal facilities, the East of Sha Chau Mud Pits, is very limited and may not be available at the time of the disposal for this Project.  As such, the Project Proponent has, in discussion with EPD, obtained from the MFC provisional capacities at the appropriate marine disposal site(s) for confined marine sediment disposal (see Section 7 Waste Management Assessment).

Loss rates have been taken from previously accepted EIAs in Hong Kong ([11]) ([12]) ([13]) and have been based on a review of worldwide data on loss rates from dredging operations undertaken as part of assessing the impacts of dredging areas of Kellett Bank for mooring buoys ([14]).  The assessment concluded that for 8 m3 (minimum) grab dredgers working in areas with significant amounts of debris on the seabed (such as in the vicinity of existing mooring buoys) that the loss rates would be 25 kg m-3 dredged, while the loss rate in areas where debris is less likely to hinder operations would be 17 kg m-3 dredged.  The results of the recent geophysical surveys suggested that there are no significant quantities of debris in the vicinity of the dredging areas (see Figure 11.6, Section 11 Cultural Heritage Assessment).  The value of 17 kg m-3, for dredgers with grab size of 12/16 m3, was therefore used for this Study.

Generally, a split-bottom barge could have a capacity of 900 m³.  A bulk factor of 1.3 would normally be applied, giving a dredging rate of 700 m³ per barge.  The hopper dry density for an 800 to 1,000 m3 capacity barge is around 0.75 to 1.24 ton m-3.   Assuming 12 to 24 working hours per day for the proposed construction activities, with allowance on the demobilisation of filled barge and remobilisation of empty barges, approximately 5 to 10 barges could be filled per day, giving a daily dredging rate of approximately 3,500 m3 to 7,000 m3.

The average release rates will, in fact, be somehow less than those indicated above.  The instantaneous dredging (and loss) rates will also decrease as the depth increases.  This is because the assumed dredging production rates are instantaneous rates that will not be maintained due to delays for breakdowns, maintenance, crew changes and time spent relocating the dredgers.  The release rates that are to be modelled area, therefore, considered to represent conservative conditions that will not prevail for any great length of time.

A review of the vector plots at the sites allowed identification of areas that would disperse sediment further than other areas due to higher current velocities.  These areas were consequently being chosen as the locations of the sources of sediment in the model.

6A3.2.2                      Jetting

Jetting would be deployed for the installation of submarine gas pipelines in HKSAR or PRC waters.  The speed of the machine is taken as 360 m day-1 for gas pipeline installation.

The maximum burial depth is assumed to be 5 m typically.  It is envisaged that it will require three passes of the jetting machine to reach the required burial depth.  The volumes of sediment disturbed will vary depending upon whether it is the first, second or third pass.  The consecutive passes may uplift the bottom sediments in a short period of time.  However, this will be temporary and instantaneous disturbances to the seabed since the disturbed sediments are expected to settle on the seabed in a short period after the jetting machine has passed.

The volumes of seabed sediments to be fluidised are assumed to be:

·           First Pass = 5 m3 m-1;

·           Second Pass = 10 m3 m-1; and

·           Third Pass = 15 m3 m-1.

Assuming a conservative case for the third pass (15 m3 per m), the rate of disturbance will be:

Rate of Disturbance (m3 s-1) – 24-hour Working Time in PRC Waters

= 360 m day-1 * (1/86400 s day-1) * 15 m3 m-1

= 0.0625 m3 s-1

when the gas pipeline trench is fully fluidised.

Rate of Disturbance (m3 s-1) – 12-hour Working Time in HKSAR Waters

= 360 m day-1 * (1/43200 s day-1) * 15 m3 m-1

= 0.125 m3 s-1

when the gas pipeline trench is fully fluidised.

The disturbed sediments will constitute a layer of fluid mud flowing across the seabed either side of the jetting machine and only a small portion of this sediment will enter the water column.

It is conservatively assumed that 20% of the disturbed sediments enter suspension and this would give a loss rate.  The loss rate used here has been used in previous projects for submarine utility installations under the EIAO that have been installed using jetting methods and have obtained Environmental Permits:

·           The Proposed Submarine Gas Pipelines from Cheng Tou Jiao Liquefied Natural Gas Receiving Terminal, Shenzhen to Tai Po Gas Production Plant, Hong Kong – EIA Study (AEIAR-071/2003). EP granted on 23 April 2003 (EP-167/2003).

·           132kV Submarine Cable Installation for Wong Chuk Hang - Chung Hom Kok 132kV Circuits (AEP-126/2002).  EP granted on 2 April 2002 (EP-126/2002).

·           FLAG North Asian Loop (AEP-099/2001).  EP granted on 18 June 2001 (EP-099/2001).

·           East Asian Crossing (EAC) Cable System (TKO), Asia Global Crossing (AEP-081/2000).  EP granted on 4 October 2000 (EP-081/2000).

·           East Asian Crossing (EAC) Cable System, Asia Global Crossing (AEP-079/2000).  EP granted on 6 September 2000 (EP-079/2000).

·           Submarine Cable Landing Installation in Tong Fuk Lantau for Asia Pacific Cable Network 2 (APCN 2) Fibre Optic Submarine Cable System, EGS.   EP granted on 26 July 2000 (EP-069/2000).

·           Telecommunication Installation at Lot 591SA in DD 328, Tong Fuk, South Lantau Coast and the Associated Cable Landing Work in Tong Fuk, South Lantau for the North Asia Cable (NAC) Fibre Optic Submarine Cable System (AEP-064/2000).  EP granted in June 2000 (EP-064/2000).

To calculate the mass entrainment rate it is necessary to apply a dry density for the material, which is conservatively assumed to be 700 kg m-3 ([15]).  The sediments are entered into the model in the model layer closest to the seabed because this represents the entrainment of sediments to suspension from the layer of fluid mud flowing over the existing seabed.  This approach is considered valid as the jetting machine is fluidising the seabed sediments and not excavating the sediments, consequently there will be little vertical entrainment of sediments into the water column.

The sediments are entered into the model within a series of grid cells to represent the jetting machine moving along the pipeline route.  Thus each grid cell represents a section of the pipeline route and sediments are entered into that grid cell for the length of time it takes the jetting machine to pass the length of that cell, based on the jetting machine speed given above.  Once the jetting machine has passed that grid cell, sediments will then be entered in the next grid cell on the route.  The sediment release in the bed layer (constitute 10%) of the water column is assumed in the model.  These rates have been adopted in the approved EIA ([16]).

6A3.3                            Construction Scenarios

6A3.3.1                      First Phase Construction: Scenario 1

Grab Dredging for Sections of Submarine Gas Pipeline 1

Grab dredger(s) will be deployed during the dredging for specific sections of submarine Pipeline 1 in the HKSAR and PRC waters (Figure 6A.9).   This includes grab dredging works for pipeline sections 1 (Black Point Shore Approach) and 3 (across Urmston Road) in HKSAR waters and about 2.5 km of pipeline (from the HKSAR boundary) in PRC waters.

Following installation, the pipelines will be protected by rock armour.  Typical cross sections of the trench designs that may be used for these sections of the submarine pipeline are shown in Figure 6A.10.  Details of the pipeline protection designs are presented in Section 3 Project Description.  Water quality impacts are not expected from the implementation of the pipeline protection measures as the fines content of the armour rock material is low.

Grab Dredging

The estimated dredged volume, the number of plant and the distance apart between each plant at the associated pipeline section is shown in Table 6A.5.

The dredging operations for the pipeline installation will be carried out by closed grab dredgers.  For the Black Point Shore Approach pipeline section, working hours are assumed to be 12 hours per day with a maximum dredging rate of 4,000 m3 day-1 (ie 0.093 m3 s-1) per dredger, giving a rate of release (in kg s-1) for the dredger as follows:

Loss Rate (kg s-1)

= Dredging Rate (m3 s-1) * Loss Rate (kg m-3)

= 0.093 m3 s-1 * 17 kg m-3

= 1.57 kg s-1

The maximum daily rate of production for the Urmston Road Crossing is assumed to be 8,000 m3 day-1.  Given that the working hours at that section will be 24 hours per day, the loss rate (in kg s-1) for each dredger will also be 1.57 kg s-1.  These assumptions were also applied to the PRC pipeline sections.

6A3.3.2                      First Phase Construction: Scenario 2

Jetting for Sections of Submarine Gas Pipeline 1

Scenario 2 assesses the impacts of sequential jetting works for installing suitable sections of Pipeline 1 in HKSAR and PRC waters.  This includes sections 2 (from Black Point to Urmston Road) and 4 (from Urmston Road to HKSAR Boundary) in HKSAR waters and about 2.5 km of pipeline (from the HKSAR boundary) in PRC waters.  It is expected that the jetting works in both HKSAR and PRC waters will take place after the completion of Pipeline 1 grab dredging activities, i.e. completion of works simulated under Scenario 1.

It is expected that only one jetting machine would be used for post-trenching of both the HKSAR and PRC pipeline sections.  Therefore under this assumption the jetting operations in different pipeline sections in HKSAR and PRC waters will not be concurrent, hence three separate scenarios (Scenarios 2a, 2b and 2c) were simulated.

Working hours have been assumed to be 12 hr and 24 hr per day for works in HKSAR and PRC waters respectively.  The moving speed of the jetting machine was assumed to be 360 m day-1.  The dry density of sediment was taken to be 700 kg m3.

6A3.3.3                      Second Phase Construction: Scenario 3

Scenario 3 allows the assessment of impacts through concurrent activities in HKSAR and PRC waters, including:

·           Reclamation works, i.e. dredging underneath the seawall and backfilling works for the construction of the reclamation; and

·           Pre-trenching for the installation of specific sections of Pipeline 2, including dredging works for pipeline sections 1 (Black Point Shore Approach) and 3 (across Urmston Road) in HKSAR waters and about 2.5 km of pipeline (from the HKSAR boundary) in PRC waters.

Construction Works for Gas Receiving Station

Scenario 3 simulated the dredging and sandfilling works for the reclamation site (Figure 6A.11).  All dredging works will be undertaken by grab dredgers while sandfilling works will be conducted by a pelican barge.  In situ dredging volume is estimated to be 0.120 Mm3.

Grab Dredging

Dredging works will be carried out at the northern side of the BPPS site.  Working hours are assumed to be 16 hours per day and 7 days per week at Black Point. 

Assuming the deployment of two dredgers with a maximum total dredging rate of 8,000 m3 day-1, giving a dredging rate of 0.139 m3 s-1.  The rate of release (in kg s-1) for the dredger will be:

Loss Rate (kg s-1)

= Dredging Rate (m3 s-1) * Loss Rate (kg m-3)

= 0.139 m3 s-1 * 17 kg m-3

= 2.36 kg s-1

Therefore a continuous release rate of 2.36 kg s-1 for each dredger will be adopted in the model throughout the whole water column.

Two stationary sources, BP01 and BP02, have been assumed in the model to represent the grab dredgers.

Sandfilling

It is worth noting that backfilling of the reclamation site has been assumed to be undertaken before the construction of a seawall in the model simulations and there would be no sandfilling works for the vertical seawall.  Backfilling works for the reclamation by a pelican barge have been stimulated by assuming a filling rate of 50,000 m3 day-1 (ie 0.868 m3 s-1) with working hours to be 16 per day.  The fill material will be marine sand which generally has a fine content ranging from 2% to 10%.  As the source of material is not available at this stage, the upper bound of the fine content (ie 10%) with a loss rate of 10% will be assumed for the conservative case.

With a representative dry density of the sand fill taken as 1,938 kg m-3, the loss rate in kg s-1 (continuous release in the whole water column) is calculated as:

Loss Rate (kg s-1)

= Percentage Fine Content * Percentage Loss Rate * Filling Rate (m3 s-1) * Dry Density of Sand Fill (kg m-3)

= 10% * 10% * 0.868 m3 s-1 * 1938 kg m-3

=16.8 kg s-1

Since the reclamation area is small and close to the shore, a stationary emission point, BP03, was chosen at a location that represents a worst-case scenario (i.e. closest proximity to the nearest sensitive receiver etc). 

Grab Dredging for Sections of Submarine Gas Pipeline 2

This works sequence is essentially the same as that used under Scenario 1, except that this sequence deals with the dredging for specific sections of submarine Pipeline 2 in the HKSAR and PRC waters (Figure 6A.9).   This includes grab dredging works for pipeline sections 1 (Black Point Shore Approach) and 3 (across Urmston Road) in HKSAR waters and about 2.5 km of pipeline (from the HKSAR boundary) in PRC waters.

The works assumptions for Scenario 1 regarding grab dredging are also adopted for this Scenario.

6A3.3.4                      Second Phase Construction: Scenario 4

Jetting for Sections of Submarine Gas Pipeline 2

Scenario 4 is the same as Scenario 2 except that the sequential pipeline jetting works are for the installation of Pipeline 2.  Impacts of post-trenching along sections 2 (from Black Point to Urmston Road) and 4 (from Urmston Road to HKSAR Boundary) in HKSAR waters and about 2.5 km of pipeline (from the HKSAR boundary) in PRC waters, were assessed.  The works assumptions adopted in Scenario 2 are also adopted in this Scenario.


                   Table 6A.5      Submarine Gas Pipeline Construction Details for HKSAR Sections and PRC Sections

Scenario

 

Section

 

Zone

Plant Used

Protection Type

Total Dredged Volume (m3)

Moving Speed (m hr-1)

Minimum Distance Apart between Each Plant (km)

Dredging/Jetting Rate per Plant (m3 day-1)

Maximum Daily Working Hours

1

HKSAR

Black Point Shore Approach

(KP4.89 – KP4.78)  

Grab Dredger

1

2,000

 

4.75

1.167

4,000

12 hours in daylight

 

HKSAR

Urmston Road Crossing (KP2.52-KP0.73)

Grab Dredger

3

226,000

2.5

1.167

8,000

24 hours

 

PRC

PRC Section (KP0 – SZ-KP1.26)

Grab Dredger

2

N/A

2.5

1.167

8,000

24 hours

 

PRC

Tonggu Fairway Crossing (SZ-KP1.26 – SZ-KP2.5)

Grab Dredger

3

N/A

2.5

1.167

8,000

24 hours

2a

HKSAR

Black Point to Urmston Road (KP4.78-KP2.52)

Jetting Machine

2

0

30

-

5,400

12 hours in daylight

2b

HKSAR

Urmston Road to HKSAR boundary (KP0.73-KP0)

Jetting Machine

2

0

30

-

5,400

12 hours in daylight

2c

PRC

PRC Section (KP0 – SZ-KP1.26)

Jetting Machine

2

0

15

-

5,400

24 hours

 

PRC

Tonggu Fairway Crossing (SZ-KP1.26 – SZ-KP2.5)

Jetting Machine

3

0

15

-

5,400

24 hours

3

HKSAR

Black Point Shore Approach

(KP4.89 – KP4.78)  

Grab Dredger

1

2,000

4.75

1.167

4,000

12 hours in daylight

 

HKSAR

Urmston Road Crossing (KP2.52-KP0.73)

Grab Dredger

3

226,000

2.5

1.167

8,000

24 hours

 

PRC

PRC Section (KP0 – SZ-KP1.26)

Grab Dredger

2

N/A

2.5

1.167

8,000

24 hours

 

PRC

Tonggu Fairway Crossing (SZ-KP1.26 – SZ-KP2.5)

Grab Dredger

3

N/A

2.5

1.167

8,000

24 hours

4a

HKSAR

Black Point to Urmston Road (KP4.78-KP2.52)

Jetting Machine

2

0

30

-

5,400

12 hours in daylight

4b

HKSAR

Urmston Road to HKSAR boundary (KP0.73-KP0)

Jetting Machine

2

0

30

-

5,400

12 hours in daylight

4c

PRC

PRC Section (KP0 – SZ-KP1.26)

Jetting Machine

2

0

15

-

5,400

24 hours

 

PRC

Tonggu Fairway Crossing (SZ-KP1.26 – SZ-KP2.5)

Jetting Machine

3

0

15

-

5,400

24 hours

Note:

[1] Grab Dredger refers to closed grab dredger with a minimum grab size of 8 m3.

[2] The dredger forward speeds are estimated for the purpose of modelling while the actual dredging rates may not be the same and will be subject to the weather constraints, site conditions and continued operational progress.  In reality, the dredger moving speed should be calculated from the result of dividing the total volume of dredged materials (m3) by the duration of the dredging works (day).

 

 


6A3.4                            Construction Programme and Sequence

Tentative construction programme and indicative construction sequence are shown in Figure 6A.12.  Note that jetting works in HKSAR and PRC waters will take place after the completion of all dredging activities in HKSAR Waters.

6A3.5                            Sediment Input Parameters

For simulating sediment impacts the following general parameters have been used:

·            Settling velocity – 0.5 mm s-1

·            Critical shear stress for deposition – 0.2 N m-2

·            Critical shear stress for erosion – 0.3 N m-2

·            Minimum depth where deposition allowed – 0.1 m

·            Resuspension rate – 30 g m-2 d-1

·            Wave calculation method – Tamminga

·            Chezy calculation method – White/Colebrook

·           Bottom roughess – 0.001 m ([17]) 

·            Fetch for wave driven erosion – 35 km

·            Depth gradient effect on waves - absent

The above parameters have been used to simulate the impacts from sediment plumes in Hong Kong associated with uncontaminated mud disposal into the Brothers MBA ([18]) and dredging for the Permanent Aviation Fuel Facility at Sha Chau  ([19]) .  The critical shear stress values for erosion and deposition were determined by laboratory testing of a large sample of marine mud from Hong Kong as part of the original Water Quality and Hydraulic Mathematical Model (WAHMO) studies associated with the new airport at Chek Lap Kok.

 

 

6A4                                  Operation Phase

For the study of operational effects, the approach requires several steps:

1)    Adapting the hydrodynamic model for the new conditions such as the reclamations. 

3)    Running the hydrodynamic model for the specified conditions (wet/dry season) covering a spring-neap cycle.

4)    Running the water quality model (ie Delft3D-WAQ).  The objectives are:

a)    to assess the changes in the dispersion and dilution of the cooling water effluent discharged from BPPS;

b)    to assess the flushing of Deep Bay through a tracer release in Shenzhen River; and

c)    to assess the potential changes in water quality as a result of changes in the circulation near the project sites: to this end up to 5 conservative, ie non-decayable, tracers have been defined, which will be discharged from a number of locations representing main pollution sources (e.g. Hong Kong as a whole, major point sources in the vicinity of the candidate sites).

In addition, an assessment of the potential changes in the patterns of sedimentation along the new reclamation has been conducted.  A similar approach has been adopted in the previously approved HKLNG EIA ([20]).  It is proposed to predict potential variation in patterns of sedimentation around the BPPS area relative to the existing conditions, based on an analysis of modelled shear stresses and existing data on wave conditions and sediment concentration.  The sedimentation assessment consists of the following three phases:

1)    Examine the siltation processes by reviewing the existing sediment concentration data, wave heights, bed sediment and bathymetric changes, if any;

2)    Compile shear stresses maps based on the hydrodynamic results; and

3)    Compare the shear stress distribution before the commencement and after the completion of the construction works to determine whether more sedimentation and/or erosion will be anticipated.  The magnitude of sedimentation (if any) can be estimated by simple calculations incorporating typical critical shear stresses, sediment settling velocities and sediment concentrations.

 

6A5                                  Cumulative IMpacts

It is expected that the construction works of this Project will commence in 2011 to allow for First Gas to arrive by 2012.  According to publicly available sources, the following major developments in northwestern or western Hong Kong waters may be constructed and/or operated concurrently with the construction works for the proposed facilities at Black Point.

·            Hong Kong Link Road (HKLR) of the Hong Kong – Zhuhai – Macao Bridge (HZMB), which is about 15 km south of the pipeline corridor;

·            Hong Kong Boundary Crossing Facilities (HKBCF) of the HZMB, which is about 12 km south of the pipeline corridor;

·            Tuen MunChek Lap Kok Link (TMCLKL), which is about 10 km from the pipeline corridor; and

·            Contaminated Mud Pits (CMPs) at East Sha Chau and South Brothers, which are at least 10 km from the pipeline corridor.

A qualitative assessment of potential cumulative impacts has been conducted and the results are discussed in the Section 6 – Water Quality Impact Assessment.

 

6A6                                  Scenarios

Construction phase scenarios are established in accordance with the tentative construction programme and presented in Table 6A.6.  Table 6A.7 summarises the inputs defined in the sediment dispersion simulations.  To simulate conservative worst cases, potential concurrent activities are simulated at the same time regardless the reality that they may not all occur simultaneously.  It is important to note that the jetting works in HKSAR and PRC waters will take place after the completion of all the dredging operations and there will be only one jetting machine in operation at one time.

 


Table 6A.6     Scenarios of the Construction Works

Scenario ID

Tasks

Details of Construction Activities

Plant Type

First Phase Construction

Scenario 1

Submarine Pipeline 1 (HKSAR & PRC Sections)

Concurrent Grab Dredging at Black Point Shore Approach (KP4.89 – KP4.78), across Urmston Road (KP2.52 – KP0.73) and from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

Grab Dredger

Scenario 2a

Submarine Pipeline 1 (HKSAR Section)

Jetting from Black Point to Urmston Road (KP 4.78 – KP 2.52)

Jetting Machine

Scenario 2b

Submarine Pipeline 1 (HKSAR Section)

Jetting from HKSAR boundary to Urmston Road (KP 0.73 – KP 0)

Jetting Machine

Scenario 2c

Submarine Pipeline 1 (PRC Section)

Jetting from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

Jetting Machine

Second Phase Construction

Scenario 3

Gas Receiving Station

Grab dredging at reclamation seawall trench

Grab Dredger

 

Gas Receiving Station

Backfilling

Pelican Barge

 

Submarine Pipeline 2 (HKSAR & PRC Sections)

Concurrent Grab Dredging at Black Point Shore Approach (KP4.89 – KP4.78), across Urmston Road (KP2.52 – KP0.73) and from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

Grab Dredger

Scenario 4a

Submarine Pipeline 2 (HKSAR Section)

Jetting from Black Point to Urmston Road (KP 4.78 – KP 2.52)

Jetting Machine

Scenario 4b

Submarine Pipeline 2 (HKSAR Section)

Jetting from HKSAR boundary to Urmston Road (KP 0.73 – KP 0)

Jetting Machine

Scenario 4c

Submarine Pipeline 2 (PRC Section)

Jetting from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

Jetting Machine

Notes:

1.          GRS denotes Gas Receiving Station.

2.          Grab dredger refers to a closed grab dredger with a minimum grab size of 8 m3.

3.          KP in the bracket denotes the distance point in kilometer.

 


Table 6A.7      Summary of Model Inputs

Emission Point

No. of Working Plant

Dredging/Jetting/ Sandfilling Rate

Operation Duration

Loss Type

Loss Rate

Loss Rate

Input Layer

 

 

m3/day/plant

hours

-

 

kg s-1

-

FIRST PHASE CONSTRUCTION: SCENARIO 1

Submarine Gas Pipeline 1

 

 

 

 

 

 

 

HKSAR Section: Grab Dredging at Black Point Shore Approach (KP4.89 - KP4.78)

1 Grab Dredger

4,000

12

Continuous

17 kg m-3

1.57

Whole Column

HKSAR Section: Grab Dredging across Urmston Road (KP2.52-KP0.73)

1 Grab Dredger

8,000

24

Continuous

17 kg m-3

1.57

Whole Column

PRC Section: Grab Dredging from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

2 Grab Dredgers

8,000

24

Continuous

17 kg m-3

1.57

Whole Column

FIRST PHASE CONSTRUCTION: SCENARIO 2

Submarine Gas Pipeline 1

 

 

 

 

 

 

 

SCENARIO 2a

HKSAR Section: Jetting from Black Point to Urmston Road (KP4.78-KP2.52)

1 Jetting Machine

 

5,400

12

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

Bed layer

SCENARIO 2b

HKSAR Section: Jetting from Urmston Road to HKSAR boundary (KP0.73-KP0)

1 Jetting Machine

 

5,400

12

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

Bed layer

SCENARIO 2c

PRC Section: Jetting from HKSAR boundary to western boundary of Tonggu Fairway (KP0 – SZ-KP2.5)

1 Jetting Machine

 

5,400

24

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

 

Bed layer

SECOND PHASE CONSTRUCTION: SCENARIO 3

Dredging/Backfilling for Reclamation

 

 

 

 

 

 

 

Dredging at the reclamation site

2 Grab Dredgers

8,000

16

Continuous

17 kg m-3

2.36

Whole Column

Backfilling of the reclamation area

1 Pelican Barge

50,000

16

Continuous

1 %

16.8

Whole Column

Submarine Gas Pipeline 2

 

 

 

 

 

 

 

HKSAR Section: Grab Dredging at Black Point Shore Approach (KP4.89 - KP4.78)

1 Grab Dredger

4,000

12

Continuous

17 kg m-3

1.57

Whole Column

HKSAR Section: Grab Dredging across Urmston Road (KP2.52-KP0.73)

1 Grab Dredger

8,000

24

Continuous

17 kg m-3

1.57

Whole Column

PRC Section: Grab Dredging from HKSAR boundary to western boundary of the Tonggu Fairway (KP0 – SZ-KP2.5)

2 Grab Dredgers

8,000

24

Continuous

17 kg m-3

1.57

Whole Column

FIRST PHASE CONSTRUCTION: SCENARIO 4

Submarine Gas Pipeline 2

 

 

 

 

 

 

 

SCENARIO 4a

HKSAR Section: Jetting from Black Point to Urmston Road (KP4.78-KP2.52)

1 Jetting Machine

 

5,400

12

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

Bed layer

SCENARIO 4b

HKSAR Section: Jetting from Urmston Road to HKSAR boundary (KP0.73-KP0)

1 Jetting Machine

 

5,400

12

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

Bed layer

SCENARIO 4c

PRC Section: Jetting from HKSAR boundary to western boundary of Tonggu Fairway (KP0 – SZ-KP2.5)

1 Jetting Machine

 

5,400

24

Continuous

20%

Trench Volume

2.92

(1st pass)

5.83

(2nd pass)

8.75

(3rd pass)

 

Bed layer

Note:

[1] Grab Dredger refers to closed grab dredger with a minimum grab size of 8 m3.  TSHD refers to trailing suction hopper dredger.

[2] Jetting for gas pipelines, Loss Rate = Volume to be Fluidised per meter (m3 m-1) x Jetting Speed (m s-1) x Material Dry Density (kg m-3) x 20%.

[3] Bed layer refers to the bottom 10% of the water column.

 


 



 (1) ERM - Hong Kong, Ltd (2006) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities.  For CAPCO.  Final EIA Report.  December 2006.

 (2) ERM - Hong Kong, Ltd (2006) Op Cit

 (3) ERM - Hong Kong, Ltd (2006) Op Cit

 (4) ERM - Hong Kong, Ltd (2006) Op Cit

 (5) ERM - Hong Kong, Ltd (2006) Op Cit

 (6) Updated bathymetry and coastline information have been extracted from the Admiralty Charts (MSA of PRC Chart Nos. 80832 and 80831 [both in Oct 2008 ed]) and aerial photographs

 (7) ERM - Hong Kong, Ltd (2006) Op Cit

 (8) ERM - Hong Kong, Ltd (2006) Op Cit

 (9) ERM - Hong Kong, Ltd (2006) Op Cit

 (10) ERM - Hong Kong, Ltd (2006) Op Cit

 (11) ERM - Hong Kong, Ltd (2006) Op Cit

 (12) ERM (2005). Detailed Site Selection Study for a Contaminated Mud Disposal Facility within the Airport East/East of Sha Chau Area. EIA and Final Site Selection Report. For CEDD. Approved on 1 September 2005.

 (13) ERM (2000). Construction of an International Theme Park in Penny’s Bay of North Lantau together with its Essential Associated Infrastructures – Final EIA Report. For CEDD. Approved on 28 April 2000.

 (14) ERM (1997). EIA: Dredging an Area of Kellett Bank for Reprovisioning of Six Government Mooring Bays. Working Paper on Design Scenarios. For CEDD.

([15])       ERM - Hong Kong, Ltd (2006) Op Cit

([16])       ERM - Hong Kong, Ltd (2006) Op Cit

([17])       The particular formulations used express the bottom roughness by the so-called Nikuradse roughness coefficient, which has the dimension m. (Nikuradse, J., 1932: Gesetzmassigkeiten der turbulenten Stromungen in glatten Rohren. Frosch. Ver. Deutscher

([18])       Mouchel (2002a). Environmental Assessment Study for Backfilling of Marine Borrow Pits at North of the Brothers.  Environmental Assessment Report.

([19])       Mouchel (2002b). Permanent Aviation Fuel Facility.  EIA Report.  Environmental Permit EP-139/20

([20])       ERM - Hong Kong, Ltd (2006) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities.  Siltation Study.  For CAPCO. Final EIA Report.  December 2006.