FOREWORD
Approximately 25% of Hong Kong's electricity generating
capacity presently comes from the Castle Peak Power Company Limited (CAPCO)'s
Black Point Power Station (BPPS). This
power plant is fuelled by natural gas supplied via pipeline from the Yacheng 13-1 field off
The HKSAR Government has
signed a Memorandum of Understanding (MoU) with the
National Energy Administration of the Central People’s Government (NEA) which
enables CAPCO to work with gas suppliers in the Mainland to obtain natural gas
for BPPS. CAPCO, together with CLP
Power Hong Kong Limited (CLP) which operates CAPCO's
generating facilities, have commenced negotiation with both PetroChina
Company Limited (PetroChina) and the China National Offshore Oil Corporation (CNOOC)
to ensure that replacement gas could be made available in 2012.
CAPCO's
present plan is to import gas from Mainland
On the HKSAR side, the
submarine pipelines and the associated GRSs will
require an Environmental Permit (EP) from the HKSAR Government under the
Environmental Impact Assessment Ordinance (EIAO) (CAP 499) as well as approvals
under the Foreshore and Sea-bed (Reclamations) Ordinance (FSRO) (CAP 127) and
the Land Grant permitting processes.
The EIA Permitting process is regarded as the first step for CAPCO to
receive the replacement gas in 2012.
Castle Peak Power Company Limited (CAPCO), a joint venture
between CLP Power Hong Kong Limited (CLP) and ExxonMobil Energy Limited (EMEL),
is presently pursuing a secure and sustainable supply of natural gas to replace
its natural gas fuel supply from the existing Yacheng
13-1 field which is expected to be depleted as early as 2012.
The Hong Kong Special Administrative Region (HKSAR)
Government’s environmental policy includes the control of emissions from
existing power stations in
On 28 August 2008, the
HKSAR Government signed a Memorandum of Understanding (MoU)
with the National Energy Administration of the Central People’s Government
(NEA) in support of continuous supply of natural gas to Hong Kong in the coming
two decades ([1]). As part of the MoU,
the NEA supports the China National Offshore Oil Corporation’s (CNOOC) renewal
of its supply agreement with
In addition, according to
the MoU, it was agreed, in principle, that the
feasibility of supplying natural gas to Hong Kong via the Second West-East
Natural Gas Pipeline would be studied, and that the Mainland would jointly
build with party(ies) in Hong Kong a LNG terminal on
the Mainland for supplying natural gas to
The MoU
has enabled CAPCO to negotiate with Mainland gas suppliers to obtain
replacement gas for BPPS via
new submarine gas pipelines. This
Project, namely Black Point Gas Supply
Project, will provide necessary facilities to enable replacement gas
supplies from Mainland
Preliminary
discussion with Mainland gas suppliers has indicated that the gas export
facilities are likely to be located in southern
It is estimated that the
BPPS can consume up to about 3.4 billion cubic metres (BCM) of natural gas a
year. Increase in demand for
electricity and progressive tightening of emission caps may further increase CAPCO's annual gas demand. The increasing gas demand and the
depleting gas supply from Yacheng 13-1 field require
replacement gas to be available in 2012.
To meet the 2012 target, it is essential that the gas pipeline(s)
between Black Point and Mainland
The submarine pipeline(s) in
Permits to construct and operate the submarine pipeline(s)
and the associated gas export facilities in Mainland
1.2
Purpose &
Nature of the Project
This Project will provide facilities to import
replacement gas from the Mainland. The
present proposal will involve the construction and operation of two submarine
natural gas pipelines connecting BPPS with gas export facilities in Mainland
China, and two GRSs at BPPS ([3]).
The proposed pipelines will traverse from BPPS to
natural gas export facilities in southern
Figure 1.1 Indicative
Alignment of the Cross-Boundary Submarine Gas Pipelines Connecting the BPPS and
the New Gas Export Facilities in Mainland
|
The two GRSs are proposed
to be located at BPPS and it is expected that they will be constructed in two
phases. The First Phase GRS will be
constructed and operated within the site boundary of the BPPS, co-located with
the existing GRS operated by CNOOC (hence referred to as the Co-located GRS). The Second Phase GRS will be constructed
and operated on newly reclaimed land (approximately 0.5 ha of land area)
constructed along the existing artificial seawall of the BPPS (hence referred
to as the GRS on reclamation). It should be noted that the site for the
new reclamation will be the same as that proposed for the GRS of the South Soko option in the HKLNG EIA ([6]).
The proposed locations of the GRSs are
presented on Figure 1.2.
Figure 1.2 Suggested
Location of the Gas Receiving Stations (GRSs)
Note: The Outfall, Service Berth and Seawater Intake
are existing facilities of BPPS and hence are not part of this Project.
The following elements of the Project addressed in
this EIA Report are classified as Designated Projects under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO):
·
Schedule
2, Part I, Item H.2 – Installation of submarine gas pipelines connecting the
proposed Gas Receiving Stations at the Black Point Power Station (BPPS) and gas
export facilities in southern
·
Schedule
2, Part I, Item C.12 – A dredging operation exceeding 500,000 m3 for
the reclamation and pipeline trenches.
1.3
Purpose of this
EIA Report
This EIA Report is prepared by ERM-Hong Kong, Limited
(ERM) in accordance with the EIA Study
Brief (No. ESB-208/2009) and the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM).
The purpose of this EIA Study is to provide
information on the nature and extent of environmental impacts arising from the
construction and operation of the Project and related activities that take
place concurrently. This
information will contribute to decisions by the Director of the Environmental
Protection on:
·
The
overall acceptability of any adverse environmental consequences that may arise
as a result of the Project and the associated activities of the Project;
·
The
conditions and requirements for the detailed design, construction and operation
of the Project to mitigate against adverse environmental consequences wherever
practicable; and
·
The
acceptability of residual impacts after the proposed mitigation measures are
implemented.
The detailed requirements of the EIA Study are set
out in Clause 3 of the EIA Study Brief. As specified in the EIA Study Brief, the EIA Study has addressed the key environmental
issues associated with the construction and operation of the Project in
Black Point is the western-most part of the
1.5
Scoping of
Environmental Issues
The potential environmental impacts which may arise
from the construction and operation of the Project were identified and
discussed in the Project Profile for this EIA. The specific scope for this EIA Study is
presented in Clause 3.2 of the EIA Study Brief.
Following this introductory section, the remainder of
this EIA Report is arranged as follows:
Section 2 This
section of the EIA Report presents the findings of assessments in considering
alternative locations for the GRSs at BPPS and
alternative construction methods for the proposed facilities. This section concludes with an
introduction to the preferred scenario for the GRSs
and the submarine gas pipelines.
Section
3 Provides
a description of the Project highlighting the key facilities to be constructed,
the timeline for implementing the Project and the operational activities. This section forms the basis of the
technical assessments presented in Sections
4 – 12 below.
Section
4 Presents
details of an assessment of impacts from the construction and operation of the
Project to air quality sensitive receivers.
Section
5 Presents
details of an assessment of impacts from the construction and operation of the
Project to noise sensitive receivers.
Section
6 Details
the assessment of impacts to water quality sensitive receivers arising from the
construction and operation of the Project.
Section
7 Presents
the waste management implications from construction and operation of the
Project.
Section
8 Presents
details of an assessment of impacts from the construction and operation of the
Project to marine ecological resources.
Section
9 Details
the assessment of impacts to fisheries resources and fishing operations arising
from the construction and operation of the Project.
Section
10 Presents
the details of an assessment of impacts from the construction and operation of
the Project to landscape and visual sensitive receivers.
Section
11 Details
the assessment of impacts from the construction and operation of the Project to
cultural heritage resources.
Section
12 Presents
the quantitative risk assessment from the construction and operation of the
Project.
Section
13 Presents
a summary of the environmental outcomes of this EIA Study.
Section
14 Introduces
a summary of the environmental monitoring and audit (EM&A) measures for the
Project.
Section
15 Presents
the conclusions of the EIA Study.