This section summarises the key environmental
outcomes arising from the assessments completed in this EIA Report for the
proposed Gas Receiving Stations (GRSs) at the Black
Point Power Station (BPPS) and submarine gas pipelines connected to BPPS. For each of the environmental components
assessed, a summary of key environmental sensitive receivers is completed,
together with an overview of the key potential environmental impacts and key
mitigation measures, highlighting their benefits where necessary.
The summary of each of the components is structured
as follows:
·
List
of sensitive receivers;
·
Key
Environmental Problems Avoided / Environmental Outcomes;
·
Assessment
Methodology and Criteria;
·
Construction
Impacts;
·
Operation
Impacts;
·
Key
Mitigation Measures;
·
Residual
Impacts; and
·
Compliance
with the guidelines and criteria of the Environmental
Impact Assessment Ordinance - Technical Memorandum (EIAO-TM).
Table 13.1 presents a summary of the findings of the assessment
of impacts to air quality as a result of the construction and operation of this
Project. Full details of the
assessment and mitigation measures are presented in Section 4 of this EIA Report.
Table 13.1 Summary
of Environmental Assessment and Outcomes – Air Quality
- AIR QUALITY - |
|
Air Sensitive Receivers (ASRs) |
·
In accordance with the Study Brief, the
study area for the air quality assessment is generally defined by a distance of
500 m from the boundary of the Project site. Air Sensitive Receivers (ASRs) were
identified in accordance with the criteria in EIAO-TM Annex 12. ·
The nearest ASR is the |
Key Environmental Issues Avoided / Environmental Outcomes |
·
Air sensitive receivers have been avoided
by choosing a remote location for the GRSs and a
route to BPPS for the offshore pipelines that avoids ASRs. |
Assessment Methodology and Criteria |
·
An air dispersion model, Industrial
Source Complex (ISCST3), recommended in the EPD’s
Guideline of Choice of Models and Model Parameter, was employed to predict
the air quality impacts. The
“rural” dispersion mode was used in the model run. In addition, the local terrain has
also been incorporated into the model to account for terrain-induced impacts
to dispersion. ·
A highly conservative approach was
adopted during the air quality impact assessment modelling exercise by
assuming that the emissions from the gas heaters were continuous. ·
Isopleths of predicted maximum hourly,
daily average and annual average concentrations of NO2 at 1.5 m, 5
m and 10 m above ground level were plotted, taking the background concentrations
into consideration for comparison with the relevant criteria. |
Key Construction Impacts |
·
Potential nuisance from dust generating
activities and gaseous emission from construction plant during construction
of the GRSs have been assessed and were found to be
minimal. Impact on air quality at
the ASR is not anticipated. |
Key Operation Impacts |
·
The emission of key pollutants at all
identified ASRs are well within the respective AQO criteria, even allowing
for the very conservative assumptions used for the project-related emissions. |
Key Mitigation Measures |
Construction Phase: ·
Dust control measures stipulated in the Air Pollution Control (Construction Dust)
Regulation will be implemented during the construction of the GRSs to control the potential fugitive dust emissions. ·
Site practices such as regular
maintenance and checking of the diesel powered mechanical equipment will be
adopted to avoid any black smoke emissions and to minimize gaseous emissions. Operation Phase: ·
No exceedance
of the NO2 and CO criteria is anticipated at the ASRs and
therefore no mitigation measures are required. |
Residual Impacts |
Construction
Phase: ·
With the implementation
of the recommended dust and gaseous emissions control measures, no residual
impacts are anticipated. Operation Phase: ·
No adverse
residual operation air quality impact is anticipated. |
Compliance with EIAO-TM |
·
The assessment and the impacts are
acceptable and in compliance with the EIAO-TM
Annexes 4 and 12 and applicable
assessment standards/ criteria. |
Table 13.2
presents a summary of the findings of the assessment of impacts to ambient noise
as a result of the construction and operation of this Project. Full details of the noise assessment are
presented in Section 5 of this EIA Report.
Table 13.2 Summary
of Environmental Assessment and Outcomes - Noise
-
NOISE - |
|
Noise
Sensitive Receivers (NSRs) |
·
In accordance with the Study Brief, the
Study Area for the noise assessment includes all areas within 300 m from the
Project Boundary. ·
No existing Noise Sensitive Receiver
(NSR) as per the criteria in EIAO-TM
Annex 13 has been identified within the Study Area, and no planned NSR
has been identified within 2 km from the Project Site. |
Key
Environmental Problems Avoided / Environmental Outcomes |
·
NSRs have been avoided by choosing a remote
location for the GRSs and an offshore pipeline
route to BPPS which will avoid NSRs during its
construction phase. |
Assessment
Methodology and Criteria |
·
The methodology for the noise impact
assessment is in accordance with the procedures outlined in the GW-TM, which is issued under the NCO
and the EIAO-TM. ·
Using a conservative approach, each work
activity has been assumed to operate simultaneously. Based on the construction programme,
cumulative noise impact throughout the construction phase has been assessed. |
Key
Construction Impacts |
·
Findings of the detailed desktop review
indicate that no NSRs were identified within the
Study Area. Further quantitative
assessment for predicting construction noise levels at NSRs
was therefore not undertaken. |
Key
Operation Impacts |
·
There will be no significant plant
emitting noise in the GRSs, hence significant noise associated with the operation of
this Project is not anticipated. |
Key
Mitigation Measures |
·
No unacceptable potential noise impact is
anticipated and thus mitigation measures are not required for the
construction and operation phases. |
Residual
Impacts |
·
No adverse residual construction or
operation noise impact is anticipated. |
Compliance
with EIAO-TM |
·
The assessment and the impacts are
acceptable and in compliance with the EIAO-TM
Annexes 5 and 13 and applicable
assessment standards and criteria. |
Table 13.3 presents a summary of the findings of the
assessment of impacts to water quality as a result of the construction and
operation of this Project. Full
details of the assessment are presented in Section
6 of this EIA Report.
Table 13.3 Summary
of Environmental Assessment and Outcomes – Water Quality
- WATER QUALITY - |
|
Sensitive Receivers (SRs) |
The following Sensitive Receivers have been
identified (values in brackets indicate approximate distance from Project): Fisheries Resources: ·
Oyster
production area at ·
Recognised
spawning grounds of commercial fisheries resources in north Lantau (> 4.5 km); ·
Artificial Reef
Deployment Area at Sha Chau
and Lung Kwu Chau (>
7.5 km); Marine Ecological Resources: ·
Mangroves: Sheung Pak Nai, Ngau Hom Shek
(> 5 km); ·
·
Intertidal
Mudflats: Ha Pak Nai (~ 2.5 km); ·
Seagrass Beds: Ha Pak Nai, Pak Nai (> 3 km); ·
Horseshoe Crab
Nursery Grounds: Ha Pak Nai, Pak Nai, Sheung Pak Nai and Ngau Hom Shek (> 3 km); Water Quality: ·
Non-gazetted
Beaches: Lung Kwu Sheung
Tan, Lung Kwu Tan (> 2 km); ·
·
Seawater
Intakes: Black Point Power Station, Castle Peak Power Station, Tuen Mun Area 38, Shiu Wing Steel Mill (> 1 km). |
Key Environmental Issues Avoided / Environmental Outcomes |
·
Disturbance to
sensitive receivers has been avoided as a result of the site/ route selection
process of the GRS reclamation and pipelines. ·
Potential
project layouts, construction design and methods were examined on the basis
of their potential environmental impacts. The adopted layout has reduced the
reclamation to approximately 0.5 ha.
·
Impacts to
water quality have been reduced by the adoption of optimal installation
techniques for all sections of the pipelines. ·
The amount of
material to be dredged and hence disposed of has been reduced by optimising
project design and phasing, thereby reducing impacts to water quality during
dredging and disposal operations. |
Assessment Methodology and Criteria |
·
The potential
impacts due to the construction and operation of the Project and associated developments
were assessed following the EIAO-TM
Annex 6 guidelines and the impacts evaluated based on the criteria in EIAO-TM Annex 14. ·
Impacts due to
the dispersion of fine sediment in suspension during the construction of the
GRS reclamation and submarine pipelines have been assessed using
computational modelling (Delft3D-FLOW and Delft3D-WAQ models). ·
The simulation
of operation impacts on water quality has also been studied by means of
computational modelling. The
models have been used to simulate the effects of the physical presence of the
reclamation of hydrodynamic regime, flushing and sedimentation patterns, and
water quality changes. ·
Analysis of EPD
routine water quality data from the years of 1998 to 2007 has been undertaken
to determine the allowable increase in suspended solids concentrations. |
Key Construction Impacts |
The
water quality modelling works have indicated that the construction works
(i.e. dredging, jetting and backfilling) can proceed at the recommended
working rates without causing unacceptable impacts to water quality sensitive
receivers. ·
Suspended Solids (SS): The majority of SS elevations in water have been predicted to remain
within relatively close proximity to the dredging and jetting works and, as
such, the majority of sediment has been predicted to settle within relatively
close proximity to the works areas.
Thus, no unacceptable impacts are expected to be posed by the
works. Results of modelling
works also indicated that pipeline
installation works in Mainland waters are not expected to cause unacceptable
impacts to sensitive receivers in ·
Water Quality (Dissolved Oxygen, Nutrients, and Heavy
Metals): The dispersion of sediment due
to dredging / jetting operations is not expected to impact the general water
quality of the receiving waters.
Effects will be transient, localised in extent, of small magnitude and
compliant with applicable standards.
Thus, no unacceptable impacts are expected to be posed by the works. ·
Other Discharges: Wastewater discharges, land based construction activities, vessel
discharges and contaminants are not predicted to cause unacceptable impacts
to the water quality sensitive receivers. |
Key Operation Impacts |
·
Hydrodynamics: The
reclamation footprint is very small and as such, adverse impacts to
hydrodynamics were demonstrated as not to occur. No adverse impacts to water quality as
a result of these minor changes in hydrodynamics were predicted. ·
|
Key Mitigation Measures |
·
Siting: The
GRS reclamation and submarine pipelines are sited with the principal aim of
avoiding direct impacts to sensitive receivers. ·
Reduction
in Indirect Impacts: The GRS reclamation and submarine
pipelines are located at distances from water quality sensitive receivers
where the dispersion of sediments from the construction works does not affect
the receivers at levels of concern (as defined by the WQO and tolerance
criterion). ·
Adoption
of Acceptable Construction Rates: The modelling work has
demonstrated that the selected working rates for the dredging/ jetting
operations will not cause unacceptable impacts to the receiving water
quality. Aside from these pro-active measures that have been
adopted, a number of operational constraints and standard site practice
measures for dredging/ jetting and construction activities are also
recommended. |
Residual Impacts |
·
No unacceptable
residual impacts have been predicted to occur during the construction phase
and operation phase. |
Compliance with EIAO-TM |
·
The assessment
and the impacts are acceptable and in compliance with the EIAO-TM Annexes 6 and 14 and applicable assessment standards/criteria. |
Table 13.4 presents a summary of the findings of the
assessment of impacts to waste management as a result of the construction and
operation of this Project. The
details of the assessment are presented in full in Section 7 of this EIA Report.
Table 13.4 Summary
of Environmental Assessment and Outcomes – Waste Management
- WASTE MANAGEMENT - |
|
Key Environmental Problems Avoided /
Environmental Outcomes |
·
Potential
project layouts, construction design and methods, use of jetting and phasing
of dredging, were examined on the basis of their potential environmental
impacts. The preferred
alternatives have led to the reduction in the amount of dredged material
expected to be produced and, therefore, have brought about an overall
reduction in waste management impacts. |
Assessment Methodology and Criteria |
The potential environmental impacts associated with the
handling and disposal of waste arising from the construction and operation of
this Project are assessed in accordance with the criteria presented in Annexes 7 and 15 of the EIAO-TM: ·
Estimation of the types and quantities of
the wastes to be generated; ·
Assessment of the secondary environmental
impacts due to the management of waste with respect to potential hazards, air
and odour emissions, noise, wastewater discharges and traffic; and ·
Assessment of the potential impacts on
the capacity of waste collection, transfer and disposal facilities. |
Key Construction Impacts |
The key potential impacts during
the construction phase are related to wastes generated from dredging,
reclamation, seawall construction, filling and
concreting. ·
It is noted
that the First Phase Construction is expected to generate about 0.253 Mm3
(bulk volume) of contaminated marine sediments for off-site disposal. For the Second Phase it is estimated
that in total approximately 0.409 Mm3 (bulk volume) of
contaminated marine sediment from the construction of the reclamation and
submarine gas pipelines will require off site disposal. ·
Other wastes
produced during the construction phase are of small quantity and will be
disposed of accordingly to their nature and relevant regulations, avoiding
any potential adverse impact. |
Key Operation Impacts |
·
Small amount of
industrial waste and chemical waste will be produced during the operation
phase. The potential
environmental impacts associated with waste storage, handling, collection,
transport and disposal will meet the criteria specified in the EIAO-TM, thus no unacceptable
operational waste management impact is anticipated. |
Key Mitigation Measures |
·
A Waste Management
Plan will be devised which incorporates mitigation measures that have been
proposed to avoid or reduce potential adverse environmental impacts
associated with handling, collection and disposal of waste arising from the
construction and operation of this Project. |
Residual Impacts |
·
With the
implementation of the recommended mitigation measures, in particular the
establishment and implementation of the Waste Management Plan, no adverse residual
impacts are anticipated from the construction and operation of this Project. |
Compliance with EIAO-TM |
·
The assessment
and the impacts are acceptable and in compliance with the EIAO-TM Annexes 7 and 15 and applicable assessment standards/criteria. |
Table 13.5 presents a summary of the findings of the
assessment of impacts to marine ecology as a result of the construction and
operation of this Project. The
details of the assessment are presented in full in Section 8 of this EIA Report.
Table 13.5 Summary
of Environmental Assessment and Outcomes – Marine Ecology
- MARINE ECOLOGY - |
|
Marine Ecology Sensitive Receivers |
The following marine ecological sensitive
receivers were identified (values in brackets indicate approximate distance
from Project): ·
Seagrass Beds: Pak Nai, Ha Pak Nai (> 3 km); ·
Marine Parks: Sha Chau and Lung Kwu Chau (~ 3 km); ·
Intertidal
Mudflats: Ha Pak Nai (~ 2.5 km); ·
Mangroves: Sheung Pak Nai, Ngau Hom Shek
(> 5 km); ·
Horseshoe Crab
Nursery Grounds: Ha Pak Nai, Pak Nai, Sheung Pak Nai, Ngau Hom
Shek (> 3 km) |
Key Environmental Problems Avoided/ Environmental Outcomes |
·
Disturbance to marine
ecologically sensitive habitats has been avoided as a result of the
site/route selection process of the GRS reclamation and pipelines. ·
Potential
project layouts, construction design and methods were examined on the basis
of their potential environmental impacts. The adopted layout has reduced the
reclamation to approximately 0.5 ha with no loss of natural coastline. ·
Impacts to
marine ecology have been reduced through the adoption of optimal installation
techniques for the pipelines.
This results in less adverse effect on the water quality of the
surrounding areas and thus to the marine ecosystems. |
Assessment Methodology and Criteria |
·
A literature
review was supplemented by a programme of field surveys that covered
intertidal and subtidal assemblages. Additional comprehensive review of
marine mammals was also conducted. ·
The potential
impacts due to the construction and operation of the proposed Project were
assessed following the EIAO-TM Annex 16
guidelines and the impacts evaluated based on criteria in EIAO-TM Annex 8 and Guidance Notes. |
Key Construction Impacts |
·
Potential
construction phase impacts to marine ecological resources, as well as impacts
to marine mammals, may arise from the permanent loss of habitat due to reclamation
and disturbances to benthic habitats in the pipeline corridor and reclamation
works area as a result of the dredging, jetting, reclamation and installation
of the gas pipelines. ·
Water quality
impacts arising from the proposed dredging/ jetting works will be compliant
with assessment criteria, transient and confined to the works areas and,
therefore will not give rise to adverse impacts to marine ecological
resources or marine mammals. |
Key Operation Impacts |
·
Unacceptable
operation phase impacts to marine ecological resources, as well as impacts to
marine mammals, are not expected to arise from the physical presence of the
reclamation on hydrodynamic regime, flushing and sedimentation patterns, and
water quality changes. |
Key Mitigation and Precautionary Measures |
·
Avoid
Direct and Reduce Indirect Impacts to Ecologically Sensitive Habitats: The
site for the GRS reclamation has been selected based on a review of
alternative locations and has avoided natural coastline, key habitats for the
Indo-Pacific humpback dolphin (e.g. Sha Chau and Lung Kwu Chau Marine Park) and areas of high marine mammal
sighting density. The location of
the reclamation at BPPS has a low sighting density of marine mammals. The dispersion of sediment from
dredging/ jetting and backfilling does not affect the receivers at levels of
concern. ·
Pipeline
Alignment: The alignment chosen for the pipelines is at a
sufficient distance from key ecological sensitive habitats, such as the Sha Chau and ·
Installation
Equipment: The use of optimal
techniques during the installation of the pipelines will reduce the
severity of perturbations to water quality and hence allow compliance with
the impact assessment criteria at sensitive receivers. The careful selection of installation
equipment and optimisation of works schedule will help avoid impacts to
sensitive ecological receivers, such as marine mammals. ·
Adoption
of Acceptable Working Rates: The modelling work has demonstrated
that the selected working rates for dredging/ jetting works will not cause
unacceptable impacts to the receiving water quality. Consequently, unacceptable indirect
impacts to marine ecological resources have been avoided. The mitigation measures designed to mitigate impacts
to water quality to acceptable levels (compliance with assessment criteria)
are also expected to mitigate impacts to marine ecological resources. |
Key Mitigation and Precautionary Measures (cont’d) |
·
Specific
mitigation measures have been designed to reduce impacts to the population of
marine mammals which include restrictions on vessel speed, the use of
pre-defined and regular routes by construction traffic, and adoption of
marine mammal exclusion zones around the marine works areas during the
dredging / jetting works. |
Residual Impacts |
The following
residual ecological impacts have been identified: ·
The loss of
approximately 100 m of artificial shoreline which is of low ecological
value. The residual impact is
considered to be acceptable, as the loss of these habitats will be
compensated by the provision of 200 m of seawalls that are expected to become
recolonised by intertidal and subtidal
assemblages of a similar nature after construction. ·
The permanent
loss of approximately 0.5 ha of subtidal soft
bottom assemblages within the reclamation site. The residual impact is considered to
be acceptable as the habitat is of low ecological concern and very small in
size in the context of surrounding similar habitat. ·
The loss of
about 0.5 ha of marine waters within the reclamation site which may serve as
marine mammal habitats. The
residual impact is considered to be acceptable since the habitat which would
be lost is not considered as key marine mammal habitat and with relatively
low dolphin densities. ·
Approximately
16.5 ha of benthic habitats along the pipeline route and reclamation works
area will be lost during dredging/ jetting, but similar subtidal
benthos will recolonise over time. The residual impacts are considered to
be acceptable as the habitats are of low ecological value and because infaunal organisms and epibenthic
fauna are expected to recolonise the sediments
after the pipelines have been laid. |
Compliance with EIAO-TM |
·
The assessment
and the residual impacts are acceptable and in compliance with the EIAO-TM Annexes 8 and 16 and applicable assessment
standards/criteria. |
Table 13.6 presents a summary of the findings of the
assessment of impacts to fisheries as a result of the construction and
operation of this Project. The details
of the assessment are presented in full in Section
9 of this EIA Report.
Table 13.6 Summary
of Environmental Assessment and Outcomes – Fisheries
- FISHERIES - |
|
Fisheries Sensitive Receivers |
·
Recognised
spawning grounds of commercial fisheries resources in north Lantau (> 4.5 km); ·
Artificial
reefs in the ·
Oyster
production area at |
Key Environmental Issues Avoided/ Environmental Outcomes |
·
Potential
project layouts, construction design and methods were examined on the basis
of their potential environmental impacts. The adopted layout has reduced the
reclamation to approximately 0.5 ha. ·
The submarine
pipelines will be buried in the seabed and protected. The protection measures will be either
flush with, or below, the existing seabed level. This will avoid interference with
fishing operations. |
Assessment Methodology and Criteria |
·
A literature
review was conducted to establish the fisheries importance of the area
surrounding the proposed Project. ·
The potential
impacts due to the construction and operation of the Project and associated
developments were assessed following the EIAO-TM
Annex 17 guidelines and the impacts evaluated based on the criteria in EIAO-TM Annex 9. |
Key Construction Impacts |
·
The permanent
loss of about 0.5 ha of marine habitat due to reclamation and temporary
disturbances to about 16.5 ha benthic habitats within the pipeline corridor and
reclamation works area are not expected to be unacceptable given the small
size and low fisheries importance of the areas affected. ·
Increase in
underwater sound caused by minor increase in marine traffic is not
anticipated to result in unacceptable impacts to fisheries resources. ·
Water quality
impacts arising from the proposed dredging/ jetting or backfilling works are
predicted to be largely confined to the specific works areas and the
predicted elevations in suspended sediment concentrations are predicted to
comply with relevant assessment criteria. Consequential impacts to any fishing
grounds or species of importance to the fishery are therefore not
anticipated. |
Key Operation Impacts |
·
Unacceptable
operation phase impacts to fisheries resources and fishing operations are not
expected to occur. The permanent
loss of about 0.5 ha of fishing ground is not considered to be significant as
the area is of small size and low fisheries importance. ·
Secondary impacts
to fisheries as a result of the physical presence of the reclamation are not
expected to occur. |
Key Mitigation Measures |
·
The mitigation
measures designed to mitigate impacts to water quality to acceptable levels
(compliance with assessment criteria) are expected to mitigate impacts to
fisheries resources. ·
Construction
impacts to fisheries resources and fishing operations have largely been
avoided through the planning and design of the marine works; in particular
those associated with the backfilling and dredging/ jetting. No fisheries-specific mitigation
measures are required during construction. ·
Unacceptable
operation phase impacts are not expected and so no additional
fisheries-specific mitigation measures are required during operation. |
Residual Impacts |
·
The identified
residual impact occurring during the construction phase is the permanent loss
of approximately 0.5 ha of seabed associated with the GRS reclamation. ·
The magnitude
of this residual impact is considered to be within acceptable levels given
the small size and low fisheries importance of the area being lost. |
Compliance with EIAO-TM |
·
The assessment
and the impacts are acceptable and in compliance with the EIAO-TM Annexes 9 and 17 and applicable assessment
standards/criteria. |
13.8
Landscape &
Visual Impact
Table 13.7 presents a summary of the findings of the
assessment of impacts to the landscape and visual environment as a result of
the construction and operation of this Project. The details of the assessment are presented
in full in Section 10 of this EIA Report.
Table 13.7 Summary
of Environmental Assessment and Outcomes – Landscape & Visual
- LANDSCAPE AND VISUAL - |
|
Visually Sensitive Receivers (VSRs), Landscape
Resources (LRs) and Landscape Character Areas (LCAs) |
·
Three Recreational VSRs:
Recreational Transient Vessels, Hikers to Lookout above BPPS and Hikers to ·
Four Occupational VSRs:
Employees at BPPS, Fishermen, Workers on transient marine vessels and Workers
at West New Territories Landfill - these include views seen by workers in the
vicinity ·
Seven LRs:
Mixed Shrubland, Shrubby Grassland, Bare Rock
Slopes, Grassland, Highly Modified Area, Artificial Rocky/ Hard Shoreline and
Seascape ·
Three LCAs:
Inshore Waters Landscape, Industrial Urban Landscape and |
Key Environmental Problems Avoided |
·
Sensitive VSRs
have been avoided by choosing a remote location for the GRSs. ·
Landscape
impacts have been reduced through sighting of the GRSs
on previously disturbed landscape resources. |
Assessment Methodology and Criteria |
·
The methodology of the LVIA was based on Annexes 10 and 18 in the EIAO-TM under
the EIA Ordinance and associated Guidance Notes. ·
The landscape assessment considered the
impact of the proposed development on the existing landscape and particularly
on the landscape character units within 500 m of the development site. ·
The visual assessment examined the impact
of the proposed development on the existing views and the visual amenity,
particularly from the VSRs within the viewshed. ·
In order to illustrate the visual impacts
of the proposed GRSs, photomontages prepared from
selected viewpoints compare the existing conditions with the view after
construction. The residual
impacts are evaluated qualitatively, in accordance with the requirements of Annex 10 of the EIAO-TM. |
Key Impacts |
The
proposed GRSs will only be visible from a limited
number of locations, and these impacts will only be significant at close
proximity to the Black Point Power Station. The analysis has shown that at
distances greater than 2.3 km, the GRSs will not
have a substantial negative impact on the visual environment. ·
The GRSs are
expected to have negligible to moderate landscape impact on the existing LCAs and LRs of the Study Area,
as these LCAs and LRs are
of low to medium sensitivity to change and the magnitude of change is expected
to be negligible to intermediate. ·
The GRSs are
expected to have slight visual impacts on the existing VSRs
of the Study Area, as these VSRs are of low
sensitivity to change and the magnitude of change is expected to be small. |
Key Mitigation Measures |
The
analysis has shown that all seven VSRs selected for
analysis will experience a slight visual impact. The following Visual Mitigation
Measures (VMMs) are proposed to reduce the slight
impacts identified and improve the overall amenity of the development ·
VM 1: The colours of the proposed GRS should be selected to
complement the existing industrial surroundings. To
reduce the potential impacts on the existing LRs
and LCAs and provide a potential enhancement of the
existing landscape quality, Landscape Mitigation Measures (CM) are proposed
in accordance with future Landscape Specification and relevant best practice guidelines: ·
CM1: Site hoardings to be compatible with surrounding landscape. ·
CM2: Edges of the new reclamation to be constructed to match the
existing Rocky Seawall ·
CM3: The tree requiring removal is to be compensated in accordance
with relevant government guidelines |
Residual Impacts |
·
No significant adverse residual impacts
have been identified. The
Landscape and Visual Mitigation Measures proposed will help to mitigate the
impacts on the LCAs, LRs
and VSRs.
Overall the residual impacts are assessed as negligible to slight. |
Compliance with EIAO-TM |
·
The assessment
and the impacts are acceptable with mitigation and in compliance with the EIAO-TM Annexes 10 and 18 and applicable assessment
standards/criteria. |
Table 13.8 presents a summary of the findings of the
assessment of impacts to cultural heritage as a result of the construction and
operation of this Project. The
details of the assessment are presented in full in Section 11 of this EIA Report.
Table 13.8 Summary
of Environmental Assessment and Outcomes – Cultural Heritage
- CULTURAL HERITAGE - |
|
Sensitive Receivers |
·
There is no
declared/ deemed monument, graded/ recorded heritage resources, Built Heritage
or Archaeological Sites located within the proposed land-based Project Area
and works areas. No existing
sites of cultural heritage protected under the Antiquities and Monuments Ordinance have been identified within
the proposed Project Area and works areas. ·
No marine sites
of cultural heritage/ archaeological value are present in waters surrounding
Black Point and along the proposed pipeline corridor |
Key Environmental Issues Avoided/ Environmental Outcomes |
·
Potential layouts were examined on the basis
of their potential environmental impacts. The selected layout has reduced the
area impacted by the footprint of the Project and hence reduced potential
impact on cultural heritage sites. |
Assessment Methodology and Criteria |
·
The study methodology follows the
criteria and guidelines as stated in Annexes
10 and 19 of the EIAO-TM and the criteria for Cultural Heritage Impact Assessment (CHIA)
and Guidelines for Marine
Archaeological Investigation (MAI) as stated EIA Study Brief No.
ESB-208/2009. ·
The baseline study included a desktop
literature review and a Marine Archaeological Investigation. |
Key Impacts |
·
Findings of the Marine Archaeological
Investigation concluded that no marine sites of cultural heritage/
archaeological value are present in waters surrounding Black Point and along
the proposed pipeline corridor.
As such, no impacts to marine archaeological resources are
expected. |
Key Mitigation Measures |
·
No impacts to marine archaeological resources
have been identified and hence no specific mitigation measures are necessary. |
Residual Impacts |
·
No residual impact is expected. |
Compliance with EIAO-TM |
·
The assessment and the residual impacts
are acceptable and in compliance with the EIAO-TM
Annexes 10 and 19 and
applicable assessment standards and criteria. |
Table 13.9 presents a summary of the findings of the
assessment of impacts to quantitative risk as a result of the operation of this
Project. The details of the
assessment are presented in full in Section
12 of this EIA Report.
Table 13.9 Summary
of Environmental Assessment and Outcomes – Quantitative Risk Assessment
QUANTITATIVE RISK ASSESSMENT |
|
Key Environmental Issues Avoided |
·
The Project has
been located in a remote location avoiding populated areas. |
Assessment Methodology and Criteria |
·
The
Quantitative Risk Assessment (QRA) study undertaken for this Project has assessed
the risk associated with the GRSs as well as the
associated submarine gas pipelines from Black Point Power Station (BPPS) to
Mainland ·
The methodology
involved five main components: review of baseline data (review of GRS layout
and surrounding population), risk assessment on generic and site specific
risks, frequencies and likelihood calculation, consequence assessment and
risk assessment. ·
The results
from the risk assessment were compared with the HKRG and, mitigation measures
identified and assessed where appropriate. |
Key Impacts |
Submarine Gas Pipelines: ·
The FN curves
for all sections of the pipelines lie within the Acceptable Region. ·
Individual risk (IR) for all sections are predicted to be less than
the 1 x 10-5 per year as per Annex
4 of the EIAO-TM. Gas Receiving Stations: ·
It can be seen
that the societal risk for the GRSs is within the
Acceptable Region as per Annex 4 of
the EIAO-TM. ·
The IR is less
than 1 x 10-5 per year (i.e. less than one in every 100,000 years)
everywhere on site and at the site boundary, and hence meets the requirements
of Annex 4 of the EIAO-TM. |
Mitigation Measures |
·
No unacceptable
risks are foreseen as a result of the operation of the GRSs
and submarine gas pipelines. No mitigation
measures are thus deemed necessary. |
Residual Impacts |
·
No residual impact is expected. |
Compliance with EIAO-TM |
·
The assessment
and the impacts are in compliance with the EIAO-TM Annex 4. |