15                                        Conclusions

15.1                                  Introduction

This Section presents a summary of the key conclusions of this EIA associated with the construction and operation of two submarine gas pipelines and two Gas Receiving Stations (GRSs) at the Black Point Power Station (BPPS).  The purpose of the assessment was to thoroughly evaluate the proposed Project in terms of predicted impacts to key environmental sensitive receivers and to determine whether this option can meet the requirements of the EIAO-TM.

15.2                                  Consideration of Alternatives

This EIA Study has examined a series of Alternatives as follows:

·           Consideration of Alternative GRS Locations (Section 2.1); and

·           Consideration of Alternative Construction Methods & Sequences (Sections 2.2 to 2.4).

15.2.1                            Consideration of Alternative GRS Locations

An alternative site location study was conducted to determine the most suitable location(s) in proximity to the BPPS for the GRSs.  The study was conducted to investigate not only the environmental considerations of each location, but to include an in depth examination of the engineering and technical aspects of the GRSs at each location.  The preferred location that was taken forward to the EIA stage was based on locating one GRS on existing land within the site boundary of the BPPS, and locating the other GRS on newly reclaimed land adjacent to the existing GRS at BPPS at the same location proposed as part of the HKLNG EIA ([1]).  This location provided a series of environmental benefits when compared to the other locations examined, including:

·           A reduction in the seabed areal extent of the reclamation, as one of the new GRSs will be located on existing land within BPPS;

·           Avoidance of potential impacts on terrestrial ecology as vegetation clearance and slope cutting is avoided; and

·           A reduction in dredging volumes through siting one GRS on existing land and through selection of reclamation design and construction methodology, hence reducing off-site impacts during disposal of dredged muds.

15.2.2                            Consideration of Alternative Construction Methods & Sequences

·           Reclamation:  Two construction options have been considered, the Fully Dredged Option and the Partially Dredged Option.  In line with local construction practice, the Partially Dredged Option will be adopted for the Project.

·           Submarine Gas Pipelines:  The submarine gas pipelines will require protection measures against anchor drop and drag and so trenching for pipelines will be necessary in some sections.  An evaluation of three installation methods, including grab dredging, dredging by trailing suction hopper dredger and jetting, was undertaken to evaluate their engineering feasibility, schedule implications and overall environmental performance.  It was concluded that although all three methods are viable and environmentally acceptable, grab dredging and jetting will be adopted for this Project.  The use of jetting for certain sections of the pipelines alignment will reduce the volumes of dredged material substantially from 0.428 Mm3 to 0.253 Mm3 (bulk volume) per pipeline.  The adoption of jetting will also shorten the period for marine construction works and hence reduce the severity of impacts to marine ecological resources

·           Phasing:  The Project will involve two phases of construction works:

o        First Phase: installation of the first pipeline (Pipeline 1) and construction of the co-located GRS; and

o        Second Phase: installation of the second pipeline (Pipeline 2) and construction of the reclamation and the associated GRS.

The construction of the two phases is expected to be separate with the First Phase construction commencing in 2011 in order to receive the replacement gas in 2012.  The Second Phase of construction is expected to commence within 24 months following commissioning of the First Phase.  By phasing the works the arisings of dredged muds will be spread out over a longer time period.

15.3                                  Air Quality

The potential impacts to air quality caused by construction and operational activities of this Project have been assessed in Section 4 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 4 and 12 respectively.

One Air Sensitive Receiver (ASR, at the BPPS Administration Building) was identified and the potential impacts arising from the construction and operation phases of the Project to the ASR have been evaluated. 

With the implementation of standard mitigation measures, no adverse impact associated with potential dust nuisance from dust generating activities is anticipated during the construction phase.  Gaseous emissions from the construction plant are also minimal and no adverse impact to the ASR is anticipated.

During the operation phase, air emissions from the gas heaters at the Gas Receiving Stations at BPPS were identified as potential sources of air quality impacts.  As a conservative assumption, it was assumed that the gas heaters were operating continuously.  Even with this set of assumptions, the modelling indicated that the air quality impacts are low and well within the respective criteria at the identified ASR.  No unacceptable air quality impact is thus anticipated during operation of the project.

15.4                                  Noise

The potential impacts of noise caused by construction and operational activities of this Project have been assessed in Section 5 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 5 and 13 respectively.

No existing NSR has been identified within the Study Area, and no planned NSR has been identified within 2 km from the Project Site.  Potential noise impacts arising from the construction and operation phases have been evaluated and it was considered that potential noise impacts arising from the Project are expected to be insignificant and acceptable.  In view of the insignificant construction and operation noise impacts, mitigation measures are therefore not required and noise monitoring is also not considered to be necessary.

15.5                                  Water Quality

The potential impacts to water quality caused by construction and operational activities of this Project have been assessed in Section 6 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 6 and 14 respectively.

Sensitive receivers potentially affected by construction and operational activities of the Project have been identified and the potential impacts have been evaluated.  The key sensitive receivers include the Sha Chau and Lung Kwu Chau Marine Park, commercial fisheries spawning habitat, ecologically sensitive areas, beaches and water intakes.  The assessment, utilising water quality and hydrodynamic models, has examined the potential impacts caused by marine works (i.e. dredging, jetting, reclamation and pipeline installation) on water quality due to the increases of suspended sediments concentrations, potential decreases of dissolved oxygen and increases in nutrients concentration, as well as those caused by operational activities such as the alteration of the hydrodynamic regime.

Potential impacts arising from the proposed marine construction works are predicted to be mainly confined to the specific works areas.  Modelling results indicate that the suspended solids elevations as a result of the proposed marine works are expected to be compliant with the assessment criteria at the point specific sensitive receivers in both seasons.  The predicted elevations of suspended sediment concentrations during the construction phase are transient in nature and not predicted to cause adverse impacts to water quality at the sensitive receivers.

Results of operation-phase computational modelling indicated that unacceptable impacts to hydrodynamic regime, water quality and sedimentation pattern as a result of the proposed reclamation are not expected to occur as the reclamation is very small.

Projects that are planned to be constructed at the same time of this Project have been evaluated for potential cumulative water quality impacts and the assessment indicates that cumulative impacts are not expected to occur due to the large separation distance of these concurrent projects with this Project.

Water quality monitoring is recommended for the construction phase and the specific monitoring requirements are detailed in the Environmental Monitoring and Audit (EM&A) Manual associated with this EIA Report.  As no unacceptable impacts have been predicted to occur during the operation of the GRSs and submarine pipelines, no mitigation measures or monitoring are considered necessary.

15.6                                  Waste Management

The potential impacts to waste management caused by construction and operational activities of this Project have been assessed in Section 7 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 7 and 15 respectively.

The key potential impacts during the construction phase are related to wastes generated from dredging, reclamation, seawall construction, filling and concreting.  The storage, handling, collection, transport, disposal and/or re-utilisation of these materials and their associated environmental impacts have been the primary focus of the assessment.

The Project is planned to take place in phases.  For the First Phase of the Project, Sections 1 and 3 of the pipeline would be installed by dredging while Sections 2 and 4 of the pipeline would be installed by jetting.  About 0.253 Mm3 (bulk volume) sediment will be generated from Sections 1 and 3 of the pipeline.  The final volumes will be subject to detailed sediment sampling, testing and analysis in accordance with the PNAP 252 and disposal method reviewed prior to the commencement of the dredging activities.  About 0.029 Mm3 (bulk volume) of the dredged sediment is expected to be Category L sediment.  MFC has no objection in-principle to allocating disposal space for the Mfail sediment dredged from Sections 1 and 3 of the pipeline route (about 0.060 Mm3 bulk volume), subject to the availability of disposal space at the time of CAPCO's application and at the proposed programme for disposal.  CAPCO is exploring alternative disposal sites (such as cross boundary disposal to Mainland China ([2])) for the remaining 0.164 Mm3 (bulk volume) of Category Mpass sediment.  A dumping permit will be applied from the DEP prior to the commencement of the dredging work.

The Second Phase Project is expected to also generate approximately 0.253 Mm3 (bulk volume) from the installation of the submarine pipeline.  At present the dredging works for the reclamation for the second GRS are expected to give rise to a bulked volume of 0.156 Mm3 of contaminated mud. 

It is estimated that a total bulk volume of 0.828 Mm3 of fill materials are required for this Project, and surplus public fill material is not anticipated.  Other wastes produced during the construction phase are of small quantity and will be disposed of according to their nature, avoiding any potential adverse impact.

The operation of the GRSs will generate minimal quantity of waste, and the potential environmental impacts associated with the storage, handling, collection, transport and disposal of waste produced during operational activities have been estimated to be not significant and will therefore meet the criteria specified in the EIAO TM.

Potential impacts as a result of the waste produced during the construction phase have been reduced through the adoption of specific mitigation measures and in particular through the establishment and implementation of a Waste Management Plan (WMP).

In order to confirm that the construction Contractor(s) has implemented the recommendations of the EIA Report, regular site inspections and audits will be conducted of the waste streams, to determine if wastes are being managed in accordance with the approved procedures and the site WMP.  An appropriate inspection programme should be undertaken with the first inspection conducted at the commencement of the construction works.  Routine site inspections should also include waste management issues.

15.7                                  Marine Ecology

The potential impacts to marine ecology caused by construction and operational activities of this Project have been assessed in Section 8 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 8 and 16 respectively. 

Ecologically sensitive receivers have been identified and the key sensitive receivers include the Sha Chau and Lung Kwu Chau Marine Park and ecologically sensitive areas.

A series of detailed field surveys were conducted during the dry and wet season of 2009 to examine the baseline conditions of the habitats and assemblages within and around the Project’s footprint.  A comprehensive data review of marine mammal baseline conditions was also undertaken using data collected from January 2005 to June 2009 in the Deep Bay and western Northwest Lantau areas to provide up-to-date data for the Indo-Pacific humpback dolphin Sousa chinensis in the vicinity of the Project Site.  Findings of the field surveys and data review confirm that marine ecological resources in close proximity to the proposed Project are regarded to be of low to low-to-moderate ecological values.

Permanent habitat loss due to 0.5 ha of reclamation and short-term disturbance of habitats are considered as environmentally acceptable since the areas affected are relatively small in the context of the extent of similar habitat available in the vicinity and the generally low ecological value of the affected assemblages.  Disturbed habitats are also expected to be recolonised by similar assemblages.  Results of the water quality modelling activities indicate that the impacts arising from the marine works will be transient and confined to the works areas.  It is therefore predicted that there will be no unacceptable impacts to the marine ecology (including marine mammals) of the Study Area as a result of construction activities.  During the operation phase, since unacceptable impacts to water quality are unlikely to occur, indirect impacts to marine ecology are also not anticipated.

Projects that are planned to be constructed at the same time of this Project have been evaluated for potential cumulative impacts and the assessment indicates that cumulative impacts are not expected to occur due to the large separation distance of these concurrent projects with this Project.

Potential impacts to marine mammals, have been reduced through the adoption of specific mitigation measures including the use of predefined/ regular routes and speed limit for marine works vessels in this Project, and the adoption of marine mammal exclusion zones during marine dredging/ jetting works.  Additional marine mammal monitoring programme are also recommended for the construction phase and details of the marine mammal monitoring programme are presented in full in the EM&A Manual associated with this EIA Report.  Marine ecology specific operation phase monitoring is not considered necessary.

The mitigation measures designed to mitigate impacts to water quality to acceptable levels (compliance with assessment criteria) are also expected to mitigate impacts to marine ecological resources.  Monitoring activities designed to detect and mitigate any unacceptable impacts to water quality during construction phase are also expected to serve to protect against unacceptable impacts to marine ecological resources.  The water quality monitoring programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the Project.

15.8                                  Fisheries

The potential impacts to commercial fisheries caused by construction and operational activities of this Project have been assessed in Section 9 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 9 and 17 respectively.

Fisheries sensitive receivers have been identified and the key sensitive receivers include spawning ground of commercial fisheries resources in north Lantau, artificial reefs in the Sha Chau & Lung Kwu Chau Marine Park and oyster production area at Deep Bay.  Findings of the desktop review of baseline conditions of commercial fisheries resources and fishing operations suggest that the Project Area is of low importance to the Hong Kong fishing industry.

Potential impacts to fisheries resources and fishing operations during the construction phase may arise from the permanent loss of habitat due to reclamation, short-term disturbances to fishing grounds, and increased underwater sound, as a result of the marine works.  The water quality modelling activities completed in Section 6 indicate that the impacts arising from the marine works are predicted to be largely confined to the specific works areas and the predicted elevations in suspended sediment concentrations are not predicted to cause large areal exceedances of the assessment criterion.  Adverse impacts to water quality are thus not predicted and neither are consequential impacts to any fishing grounds or species of importance to the fisheries.  During the operation phase, since unacceptable impacts to water quality are unlikely to occur, indirect impacts to fisheries are also not anticipated.  Potential obstruction to fishing activities due to pipeline armour rock placement is not anticipated as it will be installed below or flush with the existing seabed.  The seabed temporarily affected by the pipeline works is, therefore, expected to be restored to its original configuration.

No fisheries-specific mitigation measures are required during construction or operation activities as impacts to the fisheries resources and fishing operations are small and of short duration.  The mitigation measures designed to mitigate impacts to water quality to acceptable levels (compliance with assessment criteria) are expected to mitigate impacts to fisheries resources.  The water quality monitoring programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the Project.  To confirm that the seabed affected by the pipeline works has restored to its original configuration, a geophysical survey will be conducted following completion of pipeline works.

15.9                                  Landscape & Visual

The potential impacts to the landscape and visual sensitive receivers caused by the presence of the GRSs at BPPS have been assessed in Section 10 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 9 and 17 respectively.

The assessment has covered a wide range of potential landscape impacts including the alteration of the landscape caused by the reclamation, the introduction of the GRSs in BPPS’s industrialised landscape and the impacts on existing and planned sensitive receivers during construction and operation of the GRSs.  The overall residual impacts on the Landscape Resources are assessed as negligible to slight.

There will be very limited views of the GRSs from most land based viewing locations.  The visual impacts will be larger for the ocean based VSR’s from the Ferry Lane.  Following consideration of the low user numbers in these areas and the analysis of the residual impacts, the overall visual impact is assessed as slight.

According to EIAO TM the Landscape and Visual Impacts are considered acceptable with mitigation.  Measures have been proposed to mitigate the effects of the development.

15.10                              Cultural Heritage

The potential impacts to cultural heritage caused by construction and operational activities of this Project have been assessed in Section 11 of this EIA Report.  The impacts have been identified and analysed to be in compliance with the criteria and guidelines stated in the EIAO TM Annexes 10 and 19 respectively.  The assessment has included a Marine Archaeological Investigation.

There are no declared/ deemed monument, graded/ recorded heritage resources, Built Heritage or Archaeological Sites located within the Project Area, and no sites of cultural heritage protected under the AM Ordinance have been identified.  Therefore construction and operational impacts to sites of cultural heritage are not expected.

Findings of the Marine Archaeological Investigation concluded that no marine sites of cultural heritage/ archaeological value are present in waters surrounding Black Point and along the proposed pipeline corridor.  As such, no impacts to marine archaeological resources are expected.

No impacts on potential cultural heritage and archaeological resources are expected to occur during the operation of the submarine pipelines and GRSs.  As no impacts are expected, no mitigation measure is required.

15.11                              Hazard to Life

The assessment has evaluated the hazards to life associated with the submarine gas pipelines and the GRSs.  The assessment has concluded that the risks related to the operation of the submarine gas pipelines and the GRSs are acceptable as per the individual and societal risk criteria set out in Annex 4 of the EIAO TM.

15.12                              Environmental Monitoring & Audit

The construction and operation of the proposed Project has been demonstrated in this EIA Report to comply with the EIAO-TM requirements.  Actual impacts during the construction works will be monitored through a detailed Environmental Monitoring and Audit (EM&A) programme.  Full details of the EM&A programme are presented in the EM&A Manual attached to this EIA Report.  This programme will provide management actions and supplemental mitigation measures to be employed should impacts arise, thereby ensuring the environmental acceptability of the construction and operation of this Project.

15.13                              Environmental Outcomes

No unacceptable residual impacts have been predicted for the construction and operation of this Project.  It must be noted that for each of the components assessed in the EIA Report, the assessments and the residual impacts have all been shown to be acceptable and in compliance with the relevant assessment standards/criteria of the EIAO TM and the associated Annexes.

15.14                              Environmental & Other Benefits of the Project

There are a number of advantages to the commissioning of this gas supply project for BPPS, which are summarized below. 

1.        Support of Government policy:  Natural gas is widely recognised as a comparatively clean burning fuel and its use is encouraged in the 2005 Policy Address and the current Air Quality Objective Consultation to control emissions from existing power stations in Hong Kong.  As such, this Project is critical to meet the Government policy in a sustainable manner.

2.        Fuel security and reliable supply of electricity:  Dependable fuel sources are critical to maintain reliable power supply to our customers while providing environmental benefits.  This Project allows CAPCO to secure sufficient and dependable replacement gas in a timely manner and to meet ongoing and future needs. 

3.        Environmental benefits:  With sufficient replacement natural gas, CAPCO will be able to maintain compliance with air emission standards.  As natural gas emits virtually no particulates and negligible SO2, as well as less NOx and CO2 than other fossil fuels, it will contribute to further improvements in the regional and local air quality.



([1])         ERM (2006) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities: EIA Study (EIA Study Brief ESB-126/2005). Prepared for CAPCO

([2])         At the time of this EIA CAPCO is preparing a submission to the relevant authorities to determine the feasibility of this option.