This section presents the Hazard to Life Assessment (HA) for the proposed Project in accordance with the requirements of the EIA Study Brief section 3.4.11, and is structured as follows:
Section 7.2: Identifies the Potentially Hazardous Facilities (PHI) for this Project;
Section 7.3: Presents the project data required for the assessment;
Section 7.4: Identify potential hazards of this Project;
Section 7.5: Provides discussion on the findings of consequence assessment;
Section 7.6: Provides discussion on the findings of frequency assessment;
Section 7.7: Provides discussion on the findings of risk prediction;
Section 7.8: Presents the conclusion of the Hazard to Life Assessment and proposes potential mitigation measures to address the identified impacts.
The hazard to life assessment has been undertaken in accordance with the requirements of the Study Brief and Annexes 4 of the EIAO-TM. Potentially Hazardous Facilities (PHI) located in the vicinity of the proposed Project were identified for the assessment. The assessment concluded that the risks posed by identified PHIs on the sensitive receivers, neighbouring population and the dredging workers satisfy the Hong Kong Government Risk Guidelines.
Appropriate mitigation measures have been recommended to further reduce the risks as low as reasonably practicable.
As required under the Study Brief, a Hazard
to Life Assessment (HA) has been undertaken by BMT Asia Pacific Limited (BMT),
the nominated sub-consultant to conduct the Hazard to Life Assessment
(HA) within the EIA. This assessment considered the risks to
the workers and users arising from
the Project and has provided appropriate mitigation
measures to minimise the risk to an acceptable or As Low As Reasonably
Practicable (ALARP) level.
7.1.1.1 List of Abbreviations
ALARP |
As Low As Reasonably Practicable |
BMT |
BMT Asia Pacific Ltd |
CBA |
Cost Benefit Analysis |
CEDD |
Civil Engineering and Development Department |
CFA |
Court of Final Appeal |
CFD |
Computational Fluid Dynamics |
CZ |
Consultation Zone |
EIA |
Environmental Impact Assessment |
EIAO |
Environmental Impact Assessment Ordinance |
HA |
Hazard to Life Assessment |
ICAF |
The Implied Cost of Averting a Fatality |
MHIDAS |
Major Hazard Incident Data Access Services |
MS |
Methodology Statement |
MTIA |
Marine Traffic Impact Assessment |
PHI |
Potential Hazardous Installations |
PlanD |
Planning Department |
PLL |
Potential Loss of Life |
QRA |
Quantitative Risk Assessment |
TM |
Technical Memorandum |
UKHSE |
|
7.1.2 Project Overview
The purpose of the Project is to dredge the seabed of Kwai Tsing Container Basin (KTCB), as well as portions of Northern Fairway and Western Fairway to provide the necessary manoeuvring basin and approach channel to Kwai Tsing Container Port (KTCP) with adequate draft for the new generation of the ultra-large container ships (ULCS).
The location of the Project includes the whole KTCB as well as portions of Northern Fairway and Western Fairway which are shown in Figure 7.1. Project sites are currently used by the container ships of KTCP and other vessels navigating in the vicinity.
The objective of the
HA is to assess the potential risk to construction workers and users during the construction (dredging work) of the Project due to their
presence within the consultation zones of Potentially Hazardous Installations
(PHIs) (LPG/oil depots), and hence the effect of this additional risk to the
original risk of the PHIs. The results of the assessment are compared with the
Hong Kong Government Risk Guidelines (HKRG).
The detailed requirement of the study (see Condition
The Applicant shall
follow the criteria for evaluating hazard to life as stated in Annex 4 of the
TM.
The Applicant shall
carry out a hazard assessment for the potential risk to construction workers
and users during construction stages of the Project due to their presence
within the consultation zones of PHIs (LPG/oil depots). The hazard assessment
shall include the following:
i.
Identification
of hazardous scenario associated with the operation of the existing PHIs
present in the Study Area of the Project with
a view to determining a set of relevant hazard scenarios to be included in a
Quantitative Risk Assessment (QRA);
ii.
Execution
of a QRA of the set of hazardous scenarios determined in (i), expressing
population risks in both individual and societal terms;
iii.
Comparison
of individual and societal risk with the criteria for evaluating hazard to life
stipulated in Annex 4 of the TM; and
iv.
Identification
and assessment of practicable and cost-effective risk mitigation measures.
The methodology to
be used in the hazard assessment shall be consistent with previous studies
having similar issues (e.g. EIA study for the Permanent Aviation Fuel facility
for Hong Kong International Airport) or otherwise be agreed by the Director
prior to carrying out of the hazard assessment.
As shown in Figure 7.2, 3 LPG/ oil depots at the southern part of Tsing Yi are located in vicinity of the proposed dredging area. They are considered as Potentially Hazardous Installations (PHI) as recorded in the PHI Register managed by the Housing, Planning and Lands Bureau.
¡
N6 : Exxon
Mobil Tsing Yi East Terminal for LPG and oil at TYTL 46RP
¡ N8 : Exxon Mobil Tsing Yi West Terminal for LPG and oil at TYTL 115
¡ N11 : China Resources Petrochemicals Co. Ltd (now SINOPEC) LPG and oil depot at TYTL 127
The
The estimated risk levels of hazardous installations have been compared to the Hong Kong Government Risk Guidelines stipulated in Annex 4 of the Technical Memorandum for Environmental Impact Assessment Ordinance (EIAO-TM) to determine the acceptability.
Individual Risk Guideline: The maximum level of off-site
risk should not exceed
Societal Risk Guideline: It is presented graphically in Figure 7.3. The societal risk guideline is expressed in terms of lines plotting the frequency (F) of N or more fatalities in the off-site population from hazardous scenarios at the facility of concern. There are three areas as described below:
¡ Acceptable where the risk is so low that no action is necessary;
¡ Unacceptable where the risk is so high that they should be reduced regardless of the cost or else the hazardous activity should not proceed; and
¡ ALARP (As Low As Reasonably Practicable) where the risk associated with the hazardous activity should be reduced to a level “as low as reasonably practicable”, in which the priority of measures is established on the basis of practicality and cost to implement versus the risk reduction achieved.
7.1.5 Approach and Methodology
The proposed methodology for the HA is shown schematically in Figure 7.4:
The hazard assessment consists of the following steps and is explained in the subsequent sections:
¡
Information
Collection
¡ Hazard Identification
¡ Frequency Assessment
¡ Consequence Assessment
¡ Risk Summation and Assessment
¡ Risk Mitigation and Recommendations
An assessment of the two LPG/ oil depots has been conducted previously in the EIA study for Route 9 between Tsing Yi and Cheung Sha Wan (Route 9 EIA) (Highways Department, 1999) [2]. Information in the aforementioned report has been referenced where appropriate.
This report is structured in a Hazard to Life Assessment report manner, which is presented as follows:
¡ Section 7.1 states the background of this study;
¡ Section 7.2 provides the descriptions of potentially hazardous facilities;
¡ Section 7.3 describes the project data used in this study;
¡ Section 7.4 presents hazard identification;
¡ Section 7.5 presents consequences assessment;
¡ Section 7.6 presents failure frequency assessment;
¡ Section 7.7 summarises risk assessment results and compares with the Hong Kong Government Risk Guidelines;
¡ Section 7.8 draws conclusions and gives recommendations on further risk mitigation measures;
¡ Section 7.9 lists references used in this study.
7.2 Potentially Hazardous Facilities
The 2 LPG/ oil
depots (N6 and N11) are situated on a coastal fringe of reclaimed land at
elevations between 4 to 6 meters above mean sea level at the south of the Tsing
Yi Island. The neighbouring area is mainly industrial. Container Terminal 9,
Dow Chemical Plant and Cheung Sha Wan-Tsing Yi
section of
7.2.2 Hazardous Storage and Operations
Information on the hazardous facilities was extracted from
previous EIA study for Route 9 between Tsing Yi and Cheung Sha Wan (Route 9
EIA) (Highways Department, 1999) [2]. LPG is stored at both facilities, as
listed in Table 7.1. Attempts were made but failed
to obtain the most up-to-date data on equipment
and operations of the
two PHIs, since both owners of the
PHIs do not wish to disclose details of their facilities due to confidentiality
issues. The reasons given were that by disclosing such information to the
consultants, this will be published in the EIA report, which will be available
to the general public.
Although updated information is not available, satellite
maps and site surveys indicate that the equipment and
operations in the two PHIs are mostly similar to those in Year 1999. Hence it was considered reasonable
to adopt the equipment and
operations information for the two PHIs from the previous
Route 9 EIA report.
Table 7.1: LPG Throughput and Storage
Depot |
LPG Throughput (tonnes per year) |
Storage Vessels |
Storage Type |
N6 (ExxonMobil) |
Information not available |
3 x 850 te Tankers 7.5 te |
Aboveground vessels(1) |
N11 (SINOPEC) |
35,000 |
3 x 700 te Tankers 8 te |
Cylinders, sand mounded bullets |
Note: (1) Site survey reveals the LPG vessels are installed aboveground,
although mounded type is recommended and assumed in Route 9 EIA.
Other than LPG, liquid petroleum products are stored in the SINOPEC depot N11, including leaded and unleaded gasoline, diesel, kerosene and oils. Chemical solvents, such as toluene, isopropyl alcohol, acetone and styrene monomer, are also stored in the N11 depot.
ExxonMobil depot N6 also stores and handles a range of petroleum liquids.
Other hazardous facilities in the depots include LPG cylinder filling station, fuel oil blending facility and boiler for heating heavy fuel oils.
LPG is imported from the LPG ships at the jetty to the storage vessels. The stored LPG is exported to LPG road tankers in the LPG filling stations inside the depots.
The Study Brief [1] requires that the risk to the construction workers and users during construction stage be assessed due to their presence within the consultation zones of PHIs (LPG/ oil depots). More specifically, the risk due to the presence of different types of population within the consultation zones (CZs) of the 2 depots needs to be assessed. The effect of population before, during and after dredging work on the risk profile of the 2 depots will be studied. Year 2009, 2012 and 2014 are used as the benchmark years for these three stages.
7.3.1.1 Construction Workers Population
The population of construction workers at the dredging site within the two CZs are 15, as estimated from normal dredging works. This group of workers includes operators, banksmen, technicians, ship captains, and other labourers on the dredging platoon, the tugboat and the barge. The population has been assumed to be constant throughout the study period.
7.3.1.2 Nearby Land Population
Area in the vicinity of the two LPG/ oil depots is of industrial use. There is no residential/ recreational development within
In the Planning Department’s Projections of Population
Distribution 2009-2018 [11], promulgated in December 2009, residential
population at Tsing Yi South (TPU 350) has a downward trend, from
7.3.1.3 Nearby Road Population
Traffic population of nearby roads such as
The average traffic population are calculated from the following formula:
The nearby road considered in this study is shown in Figure 7.5. Traffic population are summarised in Table 7.4.
7.3.1.4 Marine Traffic Population
The marine traffic population are adopted from the marine
traffic impact assessment report of this project. Daily traffic at two locations
at Year 2009 are adopted from
the marine traffic survey (see Figure
7.6): South Entrance
of KTCB near the Marine Department Kwai Chung Control Station (KCCS) parallel
to the
Overall population density = S Population density of each class of vessel
Daytime population density of each class of vessel = N × P / (V × 12 hr × W)
Where N is the daytime
traffic of each class of vessel, P is the typical occupancy of the vessel, V is
the typical vessel speed, and W is the fairway width. The calculations are
summarized in Tables 7.5, 7.6 and 7.7.
7.3.1.5 Other Factors to be Considered
Indoor / Outdoor Ratio
For this HA, the construction workers, staff in the open
industrial areas such as Container Terminal 9 and dockyard, and marine traffic
population will be considered as 100% outdoor. An indoor ratio of 95% and 10%
are applied to the population in the industrial buildings and LPG depots
respectively. Passengers in vehicles on the roads are considered as 100% outdoor. These factors have been
adopted in the previous South East Kowloon Development (SEKD) CFS EIA [3] and
Harbour Area Treatment Scheme (HATS) Stage
Temporal Changes in Population
In order to account for the temporal change in population
within a week, the following time periods, and corresponding proportion of
population to be adopted in the modelling, are assumed with reference to the
marine traffic survey of this project, SEKD CFS and HATS Stage
Table 7.2: Temporal Changes in Population
Time Period |
Construction Workers(1)(2) |
Staff at the Industrial Sites(1) |
Vehicle Passengers on the Roads(3) |
Marine Traffic(4) |
Weekday Day |
100% |
100% |
100% |
100% |
Weekday Night |
10% |
10% |
10% |
80% |
Weekend Day |
50% |
40% |
100% |
100% |
Weekend Night |
5% |
5% |
10% |
80% |
Note:
(1) Reference to HATS Stage
(2) Population estimation is adjusted based on the project information.
(3) Reference to SEKD CFS EIA [3].
(4) Estimated from the marine traffic survey of this project.
Table 7.3: Land Population Considered in this Study for Years 2009, 2012 and 2014
Site Name |
Description |
Total Population |
Indoor Ratio |
Occupancy Percentage |
Population |
||||||
|
|
|
|
Weekday |
Weekend |
Weekday |
Weekend |
||||
|
|
|
|
Day |
Night |
Day |
Night |
Day |
Night |
Day |
Night |
Dow Chemical Plant(1) |
Industrial site |
100 |
0.95 |
1 |
0.1 |
0.4 |
0.05 |
100 |
10 |
40 |
5 |
Tien Chu
(Tsing Yi) Industrial Centre(1) |
Industrial site |
60 |
0.95 |
1 |
0.1 |
0.4 |
0.05 |
60 |
6 |
24 |
3 |
|
Industrial site |
150 |
0.95 |
1 |
0.1 |
0.4 |
0.05 |
150 |
15 |
60 |
8 |
Tai Tung (Tsing Yi)(1) |
Industrial site |
200 |
0.95 |
1 |
0.1 |
0.4 |
0.05 |
200 |
20 |
80 |
10 |
Taikoo Paint Factory (desolated)(1) |
Industrial site |
2 |
0.95 |
1 |
0.1 |
0.4 |
0.05 |
2 |
1 |
1 |
1 |
ExxonMobil Tsing Yi West Terminal (N8)(2) |
LPG/ oil depot |
50 |
0.1 |
1 |
0.1 |
0.4 |
0.05 |
50 |
5 |
20 |
3 |
Dockyard (next to ExxonMobil Depot)(3) |
Dockyard |
400 |
0 |
1 |
0.1 |
0.4 |
0.05 |
400 |
40 |
160 |
20 |
Container Terminal 9 and Related Areas(4) |
Container terminal uses |
3300 |
0 |
1 |
0.1 |
0.4 |
0.05 |
3300 |
330 |
1320 |
165 |
Note:
(1) Population estimated from http://www.hktdc.com and site survey.
(2) Population estimated from Route 9 EIA report [2].
(3) Assume the similar population density as the Container Terminal 9 and Related Areas.
(4) Population estimated from 2003-based TPEDM population data.
Table 7.4: Road Traffic Population Adopted in this Study
|
|
Traffic Population |
|||
|
|
Weekday |
Weekend |
||
Year |
Station |
day |
night |
day |
night |
2009 |
|
229 |
23 |
229 |
23 |
|
501 |
50 |
501 |
50 |
|
Tsing Yi Hong Wan Road(1) |
110 |
11 |
110 |
11 |
|
|
6 |
1 |
6 |
1 |
|
|
11 |
1 |
11 |
1 |
|
2012 |
|
231 |
23 |
231 |
23 |
|
504 |
50 |
504 |
50 |
|
Tsing Yi Hong Wan Road(1) |
144 |
14 |
144 |
14 |
|
|
6 |
1 |
6 |
1 |
|
|
12 |
1 |
12 |
1 |
|
2014 |
|
233 |
23 |
233 |
23 |
|
506 |
51 |
506 |
51 |
|
Tsing Yi Hong Wan Road(1) |
173 |
17 |
173 |
17 |
|
|
6 |
1 |
6 |
1 |
|
|
12 |
1 |
12 |
1 |
Note:
(1) Traffic estimated from 2008 AADT data.
(2) Assume 50% of the
traffic from
(3) Assume 20% of the traffic
from
Table 7.5: Characteristics of Different Vessels
Vessel Class |
Occupancy (persons per
vessel) |
Speed (m/s) |
Fairway Width (m) |
|
Cargo |
O-G Cargo |
20 |
6 |
800 |
River Trade |
5 |
6 |
800 |
|
Tug & Tow |
5 |
2.5 |
800 |
|
Barge (Self Propelled) |
5 |
6 |
800 |
|
Passenger |
O-G Passenger |
500 |
6 |
800 |
Fast Ferry |
150 |
15 |
800 |
|
Conventional Ferry |
50 |
6 |
800 |
|
Fast Launch |
5 |
15 |
800 |
|
Others |
Tug Boats without Towage |
5 |
6 |
800 |
Fishing Vessel |
5 |
6 |
800 |
|
Local DG Vessels |
5 |
6 |
800 |
|
Pleasure Vessels Powered |
100 |
6 |
800 |
|
Unclassified |
5 |
6 |
800 |
Table 7.6: Day-time Marine Traffic Density Across the Study Area
Vessel Classes |
2009 |
2012 |
2014 |
|
Cargo |
O-G Cargo |
3.69 |
3.63 |
3.31 |
River Trade |
14.34 |
13.38 |
12.56 |
|
Tug & Tow |
5.72 |
5.90 |
6.08 |
|
Barge (Self Propelled) |
0.13 |
0.13 |
0.13 |
|
Passenger |
O-G Passenger |
12.06 |
19.29 |
21.70 |
Fast Ferry |
20.99 |
22.15 |
23.02 |
|
Conventional Ferry |
1.71 |
1.47 |
1.34 |
|
Fast Launch |
0.92 |
1.00 |
1.03 |
|
Others |
Tug Boats without Towage |
3.36 |
3.45 |
3.49 |
Fishing Vessel |
0.57 |
0.47 |
0.38 |
|
Local DG Vessels |
1.42 |
1.42 |
1.41 |
|
Pleasure Vessels Powered |
1.02 |
1.02 |
1.02 |
|
Unclassified |
0.07 |
0.07 |
0.07 |
|
TOTAL |
|
66.00 |
73.39 |
75.54 |
Table 7.7: Night-time Marine Traffic Density Across the Study Area
Vessel Classes |
2009 |
2012 |
2014 |
|
Cargo |
O-G Cargo |
2.95 |
2.91 |
2.65 |
River Trade |
11.48 |
10.70 |
10.05 |
|
Tug & Tow |
4.58 |
4.72 |
4.87 |
|
Barge (Self Propelled) |
0.10 |
0.10 |
0.10 |
|
Passenger |
O-G Passenger |
9.65 |
15.43 |
17.36 |
Fast Ferry |
16.80 |
17.72 |
18.42 |
|
Conventional Ferry |
1.37 |
1.18 |
1.07 |
|
Fast Launch |
0.73 |
0.80 |
0.83 |
|
Others |
Tug Boats without Towage |
2.69 |
2.76 |
2.79 |
Fishing Vessel |
0.46 |
0.38 |
0.30 |
|
Local DG Vessels |
1.14 |
1.14 |
1.13 |
|
Pleasure Vessels
Powered |
0.81 |
0.81 |
0.81 |
|
Unclassified |
0.05 |
0.05 |
0.05 |
|
TOTAL |
|
52.80 |
58.71 |
60.43 |
Meteorological conditions, principally the wind
directions, stability and speeds, will affect the consequences of hazard events
(e.g. flammable gas dispersion). For the area concerned, data from the Tsing Yi
weather station were adopted, which is referenced to Route 9 EIA study [2]. The
average ambient temperature adopted is
Table 7.8: Wind Direction Frequencies for Day
Wind Direction (Degree) |
B 2.8 |
D 1.4 |
D 3.8 |
D 7.7 |
E 2.9 |
F 1.1 |
0 |
0.005 |
0.0031 |
0.0042 |
0 |
0.0018 |
0.011 |
30 |
0.0016 |
0.001 |
0 |
0 |
0.0003 |
0.0037 |
60 |
0.0021 |
0.0008 |
0.0005 |
0 |
0.0003 |
0.0052 |
90 |
0.0164 |
0.0052 |
0.0091 |
0.0005 |
0.0013 |
0.0144 |
120 |
0.1206 |
0.0157 |
0.0598 |
0.0104 |
0.0091 |
0.0204 |
150 |
0.1639 |
0.0167 |
0.0196 |
0.0021 |
0.0031 |
0.0151 |
180 |
0.0994 |
0.0133 |
0.0047 |
0.001 |
0.0005 |
0.0063 |
210 |
0.0264 |
0.0037 |
0.0013 |
0.001 |
0 |
0.0029 |
240 |
0.0232 |
0.0044 |
0 |
0 |
0 |
0.0021 |
270 |
0.0381 |
0.006 |
0.0008 |
0 |
0.0005 |
0.0029 |
300 |
0.0378 |
0.0107 |
0.0044 |
0 |
0.0008 |
0.007 |
330 |
0.0759 |
0.017 |
0.0237 |
0.0042 |
0.0076 |
0.0284 |
Table 7.9: Wind Direction Frequencies for Night
Wind Direction (Degree) |
B 1.0 |
D 1.0 |
D 4.0 |
D 7.8 |
E 3.0 |
F 1.1 |
0 |
0 |
0 |
0.0074 |
0.0003 |
0.0059 |
0.0626 |
30 |
0 |
0 |
0.0012 |
0 |
0.0009 |
0.0344 |
60 |
0 |
0 |
0.0009 |
0 |
0.0009 |
0.057 |
90 |
0 |
0 |
0.0222 |
0.0018 |
0.0113 |
0.1044 |
120 |
0 |
0 |
0.1015 |
0.0092 |
0.0495 |
0.1646 |
150 |
0 |
0 |
0.0285 |
0.0033 |
0.0163 |
0.0825 |
180 |
0 |
0 |
0.0033 |
0.0033 |
0.0018 |
0.0181 |
210 |
0 |
0 |
0.0015 |
0.0009 |
0 |
0.0086 |
240 |
0 |
0 |
0.0018 |
0 |
0 |
0.0068 |
270 |
0 |
0 |
0.0003 |
0.0003 |
0.0003 |
0.0104 |
300 |
0 |
0 |
0.0053 |
0 |
0.0042 |
0.0222 |
330 |
0 |
0 |
0.0267 |
0.0027 |
0.022 |
0.0931 |
The information on the hazardous operations is adopted
from the Route 9 EIA study report
[2]. A number of hazardous events may arise from the storage and operations
associated with LPG and other petroleum products. The proposed dredging area is
about
7.4.1 Hazards Related to LPG Facilities
Liquid petroleum gas (LPG) is a mixture of liquefied
propane and butane (3:7) under pressure. Upon release to the ambient
environment it vaporises and
mixes with air, forming a dense flammable gas cloud which tends to flow and
disperse close to the ground along the natural terrain. A significant amount of
LPG is stored and processed at both PHI sites. Uncontrolled release of LPG may
disperse over a long distance and result in a fire upon ignition or an
explosion in a congested area.
LPG related facilities at the two PHIs are identified as follows (with reference to the Route 9 EIA study [2]):
¡ Ship unloading facilities at jetties – equipped with loading arms and hoses
¡ Jetty pipework – equipped with emergency shutdown valves at the ship interface and shore line, for rapid isolation during unloading if a leak or rupture occurs
¡ Distribution pipework within the terminal to the storage vessels
¡ Storage vessels – equipped with isolating and relief valves and fire protection systems (leak detection systems are provided to warn if leaks occur), protected by sand mounding
¡ Export pipework to the tanker loading bays and LPG cylinder filling facilities
¡ Export facilities to LPG barges
Accidental LPG release could result from leaks or catastrophic rupture of the following pressurised LPG equipment:
¡ Ship LPG tanks and associated pipes
¡ Mounded/ Above ground storage vessels and associated pipes
¡ LPG road tankers and associated pipes
¡ Unloading arms/ pipes
¡ Export arms/ pipes
Subsequently the potential hazardous events could be:
¡ Jet fire
¡ Flash fire
¡ Vapour Cloud Explosion (VCE)
¡ Fireball
¡ Boiling Liquid Expanding Vapour Explosion (BLEVE)
Jet fire caused by an immediate ignition of LPG release from a hole may impinge on a nearby LPG container, and lead to catastrophic failure of the container over a period of time into BLEVE. This is possible for ship LPG tanks and LPG road tankers. However, escalation of fire to BLEVE is considered unlikely for mounded LPG storage vessels in the SINOPEC depot.
Representative LPG accidental release scenarios considered in the assessment are summarised below in Table 7.10.
Table 7.10: LPG Accidental Release Scenarios Considered
Facility Type |
Equipment Involved |
Failure Event |
Release Type |
Potential Hazardous Outcomes |
LPG import |
Ship LPG tanks |
Tank rupture |
Instantaneous |
Flash fire, fireball, BLEVE |
|
|
Tank leak |
Continuous |
Flash fire, jet fire |
|
Unloading arm/ pipe |
Arm/ Pipe rupture |
Continuous |
Flash fire, jet fire |
|
|
Arm/ Pipe leak |
Continuous |
Flash fire, jet fire |
LPG storage |
Mounded LPG vessels |
Vessel rupture |
Instantaneous |
Flash fire, VCE, fireball |
|
|
Vessel leak |
Continuous |
Flash fire, VCE, jet fire |
LPG storage |
Above ground LPG vessels |
Vessel rupture |
Instantaneous |
Flash fire, VCE, fireball, BLEVE |
|
|
Vessel leak |
Continuous |
Flash fire, VCE, jet fire |
LPG export |
Export bays |
Arm/ Pipe leak |
Continuous |
Flash fire, VCE, jet fire |
LPG road tanker |
LPG tanker |
Tanker rupture |
Instantaneous |
Flash fire, VCE, fireball, BLEVE |
|
|
Tanker leak |
Continuous |
Flash fire, VCE, jet fire |
7.4.2 Hazards Related to Other Petroleum Products and Chemical Solvents
Other petroleum products and
chemical solvents, as described in Section
7.2.2, are also stored in the PHIs. Compared with LPG,
these products are much less volatile and flammable due to their higher boiling
points and flash points. They are in liquid form under normal condition, and
thus stored in vessels under ambient temperatures and pressures. Accidental
spillage of these petroleum products will result in pool fire, either confined
in the bund area or spread on the sea surface. In the Permanent Aviation Fuel
Facility (PAFF) EIA study [8],
a number of release scenarios have been identified in association with the oil
storage depot of Jet A1 aviation fuel. These scenarios are used as a reference
for the possible scenarios in this Study. They are summarised in Table 7.11.
Table 7.11: LPG Release Events at SINOPEC Depot
Jetty Transfer |
Fire due to
rupture/ leak of oil products from loaded
vessel |
Fire due to
rupture/ leak of loading arm during unloading |
Fire due to
rupture/ leak of jetty equipment |
Fire due to
rupture/ leak of jetty riser |
Fire due to
rupture/ leak of submarine pipeline from jetty to tank farm ESD valve |
Tank Farm Storage |
Fire due to
discharge from tank vent |
Tank head fire or explosion
in tank head space |
Multiple tank head
fires |
Tank failure due
to overpressure |
Explosion in empty
tank (under maintenance) |
Bund fire |
Fire outside bund
due to rupture/ leak of pumps, pipework and fittings |
Fire on sea due to
release through drainage |
Fire due to
instantaneous tank wall failure, bottom seam failure |
Fire due to
instantaneous tank wall failure, unzipping |
Aircraft impact |
Fire due to
multiple tank failure |
Tank boilover |
Fire due to
release from top of tank due to overfilling |
Vapour cloud
explosion or flash fire |
Fire due to 10%
instantaneous release from the top of a tank |
The consequence assessment is conducted in two steps: (1) Source term modelling to determine the release rate, duration and quantity; (2) Effect modelling to determine the gas dispersion, fire and explosion effects based on the output of source term modelling.
In this study, the simulation software SAFETI 6.51 by Det Norske Veritas (DNV) is used to calculate the hazardous releases and the effect zones.
LPG is modelled as a mixture of 70% butane and 30%
propane. For instantaneous failure of an
LPG storage vessel, 2 release cases of
100% and 50% inventory are
considered except for above
ground LPG vessels, where an additional case of 20% inventory is considered.
For transient or continuous release, the release rate is determined by hole
size, storage and ambient conditions, and modelled by discharge models in
SAFETI. Duration of discharge is calculated from inventory and release rate. LPG release scenarios modelled for the
study are listed in Tables
7.12 and 7.13 below. The release conditions assumed
for these scenarios are tabulated in Table 7.14 and 7.16.
Table 7.12: LPG Release Events at SINOPEC Depot
Case |
Facility |
Failure Description |
A1.1 |
LPG import |
Tank rupture (full inventory) |
A2.1 |
LPG import |
Tank rupture (half inventory) |
A3.1 |
LPG import |
Catastrophic tank leak due to collision |
A4.1 |
LPG import |
|
B1.1 |
LPG import |
Full bore rupture of marine loading arms |
B2.1 |
LPG import |
|
B3.1 |
LPG import |
|
C1.1 |
LPG storage |
Catastrophic tank leak |
C2.1 |
LPG storage |
|
C3.1 |
LPG storage |
|
C4.1 |
LPG storage |
|
D1.1 |
LPG export |
|
D2.1 |
LPG export |
Leak of LPG cylinders |
D3.1 |
LPG road tanker |
|
D4.1 |
LPG road tanker |
Rupture of road tanker on road |
D5.1 |
LPG road tanker |
|
D6.1 |
LPG road tanker |
|
D7.1 |
LPG road tanker |
BLEVE during road tanker on road |
D8.1 |
LPG road tanker |
BLEVE during road tanker loading |
Table 7.13: LPG Release Events at ExxonMobil Depot
Case |
Facility |
Failure Description |
A1.1 |
LPG import |
Tank rupture (full inventory) |
A2.1 |
LPG import |
Tank rupture (half inventory) |
A3.1 |
LPG import |
Catastrophic tank leak due to collision |
A4.1 |
LPG import |
|
B1.1 |
LPG import |
Full bore rupture of marine loading arms |
B2.1 |
LPG import |
|
B3.1 |
LPG import |
|
C1.1 C1.2 C1.3 C1.4 |
LPG storage |
Catastrophic tank leak 100% inventory 50% inventory 20% inventory |
C2.1 C2.2 C2.3 C2.4 |
LPG storage |
100% inventory 50% inventory 20% inventory |
C3.1 |
LPG storage |
|
C4.1 |
LPG storage |
|
D1.1 |
LPG export |
|
D2.1 |
LPG export |
Leak of LPG cylinders |
D3.1 |
LPG road tanker |
|
D4.1 |
LPG road tanker |
Rupture of road tanker on road |
D5.1 |
LPG road tanker |
|
D6.1 |
LPG road tanker |
|
D7.1 |
LPG road tanker |
BLEVE during road tanker on road |
D8.1 |
LPG road tanker |
BLEVE during road tanker loading |
Gas Dispersion
The UDM model is used for the dispersion of LPG for non-immediate ignition scenarios. The model takes into account various transition phases, from dense cloud dispersion to buoyant passive gas dispersion, in both instantaneous and continuous releases.
Upon release of flammable gas, a number of possible outcomes may occur depending on whether the gas is ignited immediately or ignited after a period of time. The dispersion characteristics are influenced by meteorological conditions and material properties, such as density of the released gas.
Fire scenarios of different kinds may be developed in the presence of ignition source in the proximity of gas release. Vapour cloud explosion may occur in a confined space or a congested area. If no ignition source exists, the gas cloud may disperse downwind and be diluted to the concentration below its Lower Flammable Limit (LFL). In this case, the gas would become too lean to ignite and have no harmful effect.
Jet Fire
For material stored under pressure (pressurised storage or from liquid height above release point), a release will become a jet fire when ignited. The combustion of the jet is influenced by the momentum of the release.
Fireball and BLEVE
Immediate ignition of an instantaneous release of the contents inside a pressurised vessel will result in a fireball. Fireball is characterised by its high thermal radiation intensity and short duration time. The principal hazard of fireball arises from thermal radiation, which is not significantly influenced by weather, wind direction or source of ignition. A BLEVE is similar to a fireball except that it is caused by integrity failure from fire impingement and therefore occurs as escalation events. The physical effects are calculated in the same way as fireballs.
Thermal Radiation
of Fires
The following Probit equation [10] has been used to determine lethal doses for various fire scenarios.
Pr = - 36.38 + 2.56 ln Q4/3 t
where Q is the thermal radiation intensity in W/m2 and t is the exposure time in seconds.
Buildings are assumed to offer protection to occupants again hazards from fires. The protection factor is assumed to be 90% for indoor population.
Flash Fire
An LPG release, if not ignited immediately, will vaporise and form a gas cloud around the release source. This cloud can move in the downwind direction, entraining air as it disperses and get diluted. If it gets ignited before it is diluted to below its LFL, a flash fire will result. Major hazards from flash fire are thermal radiation and direct flame contact. Since the flash combustion of a gas cloud normally lasts for a short duration, the thermal radiation effect on people near a flash fire is limited. Humans who are encompassed outdoors by the flash fire will be fatally injured. A fatality rate of unity is assumed for outdoor population and 90% protection factor is assumed for indoor occupants.
Vapour Cloud
Explosion
If the vapour cloud passes through an area of congestion (e.g. pipe racks, confined space) and gets ignited, the confinement will limit the degree of expansion of the burning cloud, causing an explosion and damage to the surroundings by the overpressure it causes. In the SAFETI package such event is modelled by the Baker-Strehlow model, and the hazardous effects are modelled by two concentric circular areas corresponding to heavy and light building damage, respectively.
Pool Fire
The major consequence of a liquid fuel release incidence is liquid pool fire, either it is confined in the bund or spilled onto the sea. The effect radius of an unconfined pool fire is reasonably approximated as the pool radius, while a confined pool fire (e.g. bund fire) is approximated by the pool size plus the flame drag caused by the wind, which is consistent with the PAFF EIA report. [8]
The consequence results of jet fire, fireball/ BLEVE, flash fire and VCE from a
release source are determined from SAFETI and tabulated in Tables 7.14
and 7.16. Fires due to large LPG releases
(instantaneous,
7.5.3.1 SINOPEC LPG/ Oil Depot
LPG Release
Table 7.14: List of Consequences of Hazardous Events for the SINOPEC Depot (N11)
Facility |
ID |
Sub ID |
Containment |
P (barg) |
T (oC) |
Amount (kg) |
Release Size |
Jet Fire |
Fireball |
Flash Fire |
VCE |
||
|
|
|
|
|
|
|
|
Max Jet length (m) |
Radius (m) |
Duration (s) |
Max Downwind Distance (m) |
|
|
LPG import |
A |
1.1 |
ship tank |
3.75 |
23 |
700000 |
rupture |
|
236 |
26 |
830 |
|
|
LPG import |
A |
2.1 |
ship tank |
3.75 |
23 |
350000 |
rupture |
|
188 |
22 |
640 |
|
|
LPG import |
A |
3.1 |
ship tank |
3.75 |
23 |
700000 |
rupture |
|
236 |
26 |
830 |
|
|
LPG import |
A |
4.1 |
ship tank |
3.75 |
23 |
700000 |
|
108 |
|
|
270 |
|
|
LPG import |
B |
1.1 |
marine loading arm |
5.55 |
23 |
700000 |
|
108 |
|
|
270 |
|
|
LPG import |
B |
2.1 |
marine loading arm |
5.55 |
23 |
700000 |
|
62 |
|
|
140 |
|
|
LPG import |
B |
3.1 |
pipeline |
5.55 |
23 |
700000 |
|
149 |
|
|
380 |
|
|
LPG storage |
C |
1.1 |
tank |
3.75 |
23 |
700000 |
rupture |
|
236 |
26 |
830 |
405 |
810 |
LPG storage |
C |
2.1 |
tank |
3.75 |
23 |
700000 |
|
108 |
|
|
270 |
405 |
810 |
LPG storage |
C |
3.1 |
tank |
3.75 |
23 |
700000 |
|
33 |
|
|
62 |
405 |
810 |
LPG storage |
C |
4.1 |
tank |
3.75 |
23 |
700000 |
|
10 |
|
|
8 |
|
|
LPG export |
D |
1.1 |
pipeline |
5.55 |
23 |
700000 |
|
149 |
|
|
380 |
405 |
810 |
LPG export |
D |
2.1 |
cylinder |
5.55 |
23 |
50 |
|
|
|
|
2 |
|
|
LPG road tanker |
D |
3.1 |
road tanker |
5.55 |
23 |
8000 |
|
108 |
|
|
270 |
91 |
182 |
LPG road tanker |
D |
4.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
LPG road tanker |
D |
5.1 |
road tanker |
5.55 |
23 |
8000 |
|
108 |
|
|
270 |
91 |
182 |
LPG road tanker |
D |
6.1 |
road tanker |
5.55 |
23 |
8000 |
|
10 |
|
|
8 |
|
|
LPG road tanker |
D |
7.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
LPG road tanker |
D |
8.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
Petroleum Product Release
Due to the lack
of available information on the petroleum product storage facilities at the two
depots, it is not possible to directly model consequence distances from
petroleum product release scenarios from the SINOPEC Depot. A comparison between release consequence
distances from an oil storage facility of a larger scale, and the distances
from the dredging workers to the depot facilities was used to demonstrate the
risk impact posed by the depot on the dredging workers. This is because the
change in risk levels of the depots due to the dredging works, i.e. the
presence of dredging workers within the Consultation Zone of the PHIs, is the
main concern of this study.
Release consequence
distances from the Permanent Aviation Fuel Facility (PAFF) EIA study [8],
are used for comparison in this regard. That project related to a gross
aviation fuel capacity of
Table
7.15: Maximum Representative Consequence Distances
in the PAFF EIA [8]
Petroleum Product Release Scenario |
Hazard Distance
(m) |
Jetty Transfer |
|
Fire due to rupture/ leak of
oil products from loaded vessel |
236 |
Fire due to rupture/ leak of
loading arm during unloading |
69 |
Fire due to rupture/ leak of
jetty equipment |
236 |
Fire due to rupture/ leak of
jetty riser |
69 |
Fire due to rupture/ leak of
submarine pipeline from jetty to tank farm ESD valve |
148 |
Tank Farm Storage |
|
Fire due to discharge from tank vent |
Not significant |
Tank head fire or explosion
in tank head space |
Not significant |
Multiple tank head fires |
Not significant |
Tank failure due to overpressure |
Not significant |
Explosion in empty tank (under maintenance) |
Not significant |
Bund fire |
18 |
Fire outside bund due to rupture/ leak of
pumps, pipework and fittings |
4 |
Fire on sea due to release through drainage |
219 |
Fire due to instantaneous tank wall
failure, bottom seam failure |
< 399 |
Fire due to instantaneous tank wall
failure, unzipping |
< 399 |
Aircraft impact |
< 399 |
Fire due to multiple tank failure |
399 |
Tank boilover |
Not significant |
Fire due to release from top of tank due to
overfilling |
Not significant |
Vapour cloud explosion or flash
fire |
Not significant |
Fire due to 10% instantaneous release from
the top of a tank |
39 |
The nearest
distances from the dredging works area to the SINOPEC Depot jetty and storage
area are 257 and 494 metres respectively. It can be seen that the consequence
distances under Jetty Transfer scenarios in PAFF EIA are less than
Therefore, hazard
scenarios from the petroleum product storage facilities at the SINOPEC Depot
will give no (zero) risk impacts to the dredging workers of the Project. Therefore, risks are quantified as zero.
7.5.3.2 ExxonMobil LPG/ Oil Depot
LPG Release
Table 7‑16: List of Consequences of Hazardous Events for the ExxonMobil Depot (N6)
Facility |
ID |
Sub ID |
Containment |
P (barg) |
T (oC) |
Amount (kg) |
Release Scenario |
Jet Fire |
Fireball |
Flash Fire |
VCE |
||
|
|
|
|
|
|
|
|
Max Jet length (m) |
Radius (m) |
Duration (s) |
Max Downwind Distance (m) |
|
|
LPG import |
A |
1.1 |
ship tank |
3.75 |
23 |
850000 |
rupture |
|
249 |
28 |
920 |
|
|
LPG import |
A |
2.1 |
ship tank |
3.75 |
23 |
425000 |
rupture |
|
201 |
23 |
710 |
|
|
LPG import |
A |
3.1 |
ship tank |
3.75 |
23 |
850000 |
rupture |
|
249 |
28 |
920 |
|
|
LPG import |
A |
4.1 |
ship tank |
3.75 |
23 |
850000 |
|
108 |
|
|
270 |
|
|
LPG import |
B |
1.1 |
marine loading arm |
5.55 |
23 |
850000 |
|
108 |
|
|
270 |
|
|
LPG import |
B |
2.1 |
marine loading arm |
5.55 |
23 |
850000 |
|
62 |
|
|
140 |
|
|
LPG import |
B |
3.1 |
pipeline |
5.55 |
23 |
850000 |
|
149 |
|
|
380 |
|
|
LPG storage |
C |
1.1 |
tank |
3.75 |
23 |
850000 |
rupture |
|
249 |
28 |
920 |
432 |
864 |
LPG storage |
C |
1.2 |
tank |
3.75 |
23 |
425000 |
rupture |
|
201 |
23 |
710 |
432 |
864 |
LPG storage |
C |
1.3 |
tank |
3.75 |
23 |
170000 |
rupture |
|
149 |
18 |
500 |
244 |
488 |
LPG storage |
C |
2.1 |
tank |
4.04 |
23 |
850000 |
|
108 |
|
|
270 |
432 |
864 |
LPG storage |
C |
2.2 |
tank |
4.04 |
23 |
425000 |
|
108 |
|
|
270 |
432 |
864 |
LPG storage |
C |
2.3 |
tank |
4.04 |
23 |
170000 |
|
108 |
|
|
270 |
244 |
488 |
LPG storage |
C |
3.1 |
tank |
4.04 |
23 |
850000 |
|
33 |
|
|
62 |
432 |
864 |
LPG storage |
C |
4.1 |
tank |
4.04 |
23 |
850000 |
|
10 |
|
|
8 |
|
|
LPG export |
D |
1.1 |
pipeline |
5.55 |
23 |
850000 |
|
149 |
|
|
380 |
432 |
864 |
LPG export |
D |
2.1 |
cylinder |
5.55 |
23 |
50 |
|
|
|
|
2 |
|
|
LPG road tanker |
D |
3.1 |
road tanker |
5.55 |
23 |
8000 |
|
108 |
|
|
270 |
91 |
182 |
LPG road tanker |
D |
4.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
LPG road tanker |
D |
5.1 |
road tanker |
5.55 |
23 |
8000 |
|
108 |
|
|
270 |
91 |
182 |
LPG road tanker |
D |
6.1 |
road tanker |
5.55 |
23 |
8000 |
|
10 |
|
|
8 |
|
|
LPG road tanker |
D |
7.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
LPG road tanker |
D |
8.1 |
road tanker |
5.55 |
23 |
8000 |
rupture |
|
55 |
8 |
165 |
91 |
182 |
Petroleum Product Release
The nearest
distances from the dredging works area to the ExxonMobil Depot jetty and
storage area are 699 and 968 metres respectively. Based on similar arguments as
the petroleum product storage facilities at the SINOPEC Depot, hazard scenarios
from the petroleum product storage facilities at the ExxonMobil Depot will give
no (zero) risk impacts to the dredging workers of the Project. Therefore, the risks are quantified as zero.
7.6.1 Frequencies of Accidental Release Scenarios
After the
consequence assessment of the
Table 7.17: Frequencies of Failure Events at SINOPEC Depot
Case |
Facility |
Failure Description |
Event Frequency, per year |
A1.1 |
LPG import |
Tank rupture (full inventory) |
6.9E-8 |
A2.1 |
LPG import |
Tank rupture (half inventory) |
2.8E-7 |
A3.1 |
LPG import |
Catastrophic tank leak due to collision |
6.8E-6 |
A4.1 |
LPG import |
|
6.1E-5 |
B1.1 |
LPG import |
Full bore rupture of marine loading arms |
6.8E-4 |
B2.1 |
LPG import |
|
6.2E-3 |
B3.1 |
LPG import |
|
7.7E-5 |
C1.1 |
LPG storage |
Catastrophic tank leak |
2.0E-5 |
C2.1 |
LPG storage |
|
2.9E-5 |
C3.1 |
LPG storage |
|
1.6E-4 |
C4.1 |
LPG storage |
|
2.4E-4 |
D1.1 |
LPG export |
|
7.7E-5 |
D2.1 |
LPG export |
Leak of LPG cylinders |
2.8E-1 |
D3.1 |
LPG road tanker |
|
2.7E-5 |
D4.1 |
LPG road tanker |
Rupture of road tanker on road |
3.3E-6 |
D5.1 |
LPG road tanker |
|
7.9E-6 |
D6.1 |
LPG road tanker |
|
1.6E-5 |
D7.1 |
LPG road tanker |
BLEVE during road tanker on road |
5.8E-8 |
D8.1 |
LPG road tanker |
BLEVE during road tanker loading |
1.5E-5 |
Table 7.18: Frequencies of Failure Events at ExxonMobil Depot
Case |
Facility |
Failure Description |
Event Frequency, per year |
A1.1 |
LPG import |
Tank rupture (full inventory) |
3.0E-8 |
A2.1 |
LPG import |
Tank rupture (half inventory) |
1.2E-7 |
A3.1 |
LPG import |
Catastrophic tank leak due to collision |
3.3E-7 |
A4.1 |
LPG import |
|
3.0E-6 |
B1.1 |
LPG import |
Full bore rupture of marine loading arms |
3.8E-4 |
B2.1 |
LPG import |
|
3.4E-3 |
B3.1 |
LPG import |
|
4.3E-5 |
C1.1 C1.2 C1.3 C1.4 |
LPG storage |
Catastrophic tank leak 100% inventory 50% inventory 20% inventory |
2.7E-6 1.4E-6 2.7E-6 |
C2.1 C2.2 C2.3 C2.4 |
LPG storage |
100% inventory 50% inventory 20% inventory |
4.1E-6 1.5E-6 4.1E-6 |
C3.1 |
LPG storage |
|
1.6E-4 |
C4.1 |
LPG storage |
|
2.4E-4 |
D1.1 |
LPG export |
|
4.3E-5 |
D2.1 |
LPG export |
Leak of LPG cylinders |
2.8E-1 |
D3.1 |
LPG road tanker |
|
2.7E-5 |
D4.1 |
LPG road tanker |
Rupture of road tanker on road |
4.6E-6 |
D5.1 |
LPG road tanker |
|
1.1E-5 |
D6.1 |
LPG road tanker |
|
2.3E-5 |
D7.1 |
LPG road tanker |
BLEVE during road tanker on road |
8.2E-8 |
D8.1 |
LPG road tanker |
BLEVE during road tanker loading |
2.1E-5 |
Event tree analysis (ETA) is used to develop the evolution
of a failure event from its initial release to the final outcome scenarios,
namely, jet fire, flash fire, fireball, etc. It depends on various factors such
as release type (instantaneous or continuous), ignition sources and
probabilities, and degree of congestion to cause a vapour cloud explosion.
The event
tree for the LPG release scenarios in
this assessment is shown in Figure
7.7. It has been adopted from
the Route 9 EIA study [2]. The
probabilities used are also shown in the event tree.
The event trees for the 3 above ground LPG storage vessels in ExxonMobil Depot N6 are further refined to include the possibility of BLEVE events upon flame jet impingement and unsuccessful fire protection considering they are installed aboveground. The outcome event tree is shown in Figure 7.8.
Risk summation combines the estimation of the likelihood and consequences of hazardous events, as well as the meteorological data and population in the hazard effect zones, to give a numerical measure of the fatalities. The risk analysis is conducted by the SAFETI package and the outcome results are presented in terms of individual risk (as individual risk contours), and societal risk (as F-N curves or potential loss of life). The risk outcome will be compared with the Hong Kong Government Risk Guidelines set out in Annex 4 of the EIAO-TM, as specified in Section 7.1.4.
The
individual risk contours of the SINOPEC
and ExxonMobil Depots are presented in Figures
7.9 and 7.10
respectively. The 1×10-5 per year risk contours extend slightly outside the PHI boundaries, but are mostly close to the site boundary and does not go into the proposed dredging works
area. Further away from the depot
and jetty, the risk gradually diminishes to lower risk levels. The
individual risk levels of the
two PHIs therefore marginally satisfy
the Hong Kong Government Risk Guidelines
for individual risk.
It should also be noted that individual risk is solely determined by the LPG/ oil depots (N6, N11) and is not related to the actual population. Therefore, individual risk is not affected by the presence of the dredging workers of the Project.
F-N curves
for the SINOPEC and ExxonMobil Depots
before, during and after the dredging
works project (at Years 2009, 2012 and 2014 respectively) are presented
in Figures
7.11 and 7.12.
The societal risk levels for “all
neighbouring population” (including
dredging workers) for both
depots have only insignificant changes from Year 2009 to 2012 to 2014. The
reason for the change is due to changes in land, road and marine population
nearby the PHIs. The F-N curves of the two PHIs all lie in the ALARP region,
which is consistent with the previous Route 9 EIA study [2].
It should be noted that the proposed dredging project does not cause the societal risk levels of the two PHIs to go into the ALARP region. Comparing to the overall societal risk from the two depots, the presence of dredging workers of the proposed project is marginal. Therefore it can be concluded that with the dredging works project taking place, the societal risk levels of the LPG/ oil depots still satisfy the Hong Kong Government Risk Guidelines for societal risk.
7.8 Conclusion and Recommendations
This QRA study examined the effect from the proposed dredging work near Tsing Yi Island on risk levels posed by the SINOPEC N11 and
ExxonMobil N6 LPG/ oil depots. Major hazardous incidents which could
potentially impact on the
dredging area were evaluated in terms of their hazard consequences and
occurring frequencies. The overall risk levels show that the two depots marginally meet the Hong Kong
Government Risk Guidelines, which is consistent with previous studies. The increase in societal risk caused by the presence
of dredging workers is minimal comparing to the overall risk level,
and is not permanent. Therefore it can be concluded that the risks posed by two PHIs on
the neighbouring population and the
dredging workers satisfy the Hong Kong
Government Risk Guidelines.
The risks
associated with operational phase activities relate to the infrequent need for
maintenance dredging. Maintenance
dredging activities will be less frequent and involve smaller volumes of
material compared to the capital works dredging and thus, it may be surmised
that risks associated with maintenance dredging will similarly satisfy Hong
Kong Government Risk Guidelines.
7.8.2 Further Mitigation Measures
In spite of the negligible additional risk, mitigation measures are recommended to further reduce the risks as low as reasonably practicable.
Sound communication channel should be established with the oil companies, Marine Department, and Fire Services Department for effective notification and emergency evacuation in case of accidents.
Proper safety and emergency training should be given to the relevant operation staff at the dredging site. Emergency plans and procedures should be prepared and drills should be performed periodically.
1. EIA Study Brief No. ESB-198/2008 –
Providing Sufficient Water Depth for
2. Route 9 between Tsing Yi and Cheung Sha Wan Detailed Feasibility Study EIA (Atkins China Ltd.), Highways Department, August 1999.
3. Comprehensive Feasibility Study for the Revised Scheme of South East Kowloon Development EIA (Ove Arup & Partners HK Ltd.), Territory Development Department, July 2001.
4. Harbour Area Treatment Scheme Stage
5. Ministerie van VROM (TNO), Guidelines for Quantitative Risk Assessment, PGS3 “Purple Book”, 2005.
6. Reeves, A.B., Minah, F.C. and Chow, V.H.K., ‘Quantitative Risk Assessment Methodology for LPG Installations’, Conference on Risk & Safety Management in the Gas Industry, EMSD & HKIE, Hong Kong, 1997.
7. Code of Practice for Oil Storage
Installations 1992, Building Authority,
8. Permanent Aviation Fuel Facility for
Hong Kong International Airport EIA (ESR Technology Ltd.), Airport Authority
9. Annual Traffic Census 2008, Transport Department, HKSAR Government.
10. Committee for the Prevention of Disasters, Guidelines for Quantitative Risk Assessment “Purple Book”, CPR 18E, 2005.
11. Projections of Population Distribution 2009-2018, Planning Department, HKSAR Government.