11.1.1.1
The objectives of this section
are to summarise
the findings of the land contamination assessment which includes a desktop review
of the existing
information related to the development, findings of the site investigation
(SI) works,
interpretation of the extent of land contamination based
on the findings, recommendation of any necessary remediation action
and the way
forward on detailed site investigations to ascertain the extent of land
contamination. Section 3.4.5 of the EIA
Study Brief No: ESB-188/2008 specified that a land contamination assessment
shall be undertaken and that a Contamination Assessment Plan (CAP),
Contamination Assessment Report (CAR) and Remediation Action Plan (RAP) (if
confirmed necessary) shall be endorsed by the EPD. These documents, including a Supplementary
CAP addressing the potential land
contamination issues due to the addition of works sites and works areas for
the KTE project, are included in Appendices 11.1 and 11.2 of this EIA report.
11.2
Environmental Standards and Criteria
11.2.1.1
Relevant legislation to the land contamination
issues as a result of handling, treatment and disposal of contaminated
materials are as follows:
· Environmental Impact Assessment Ordinance (Cap 499);
· Waste Disposal Ordinance (Cap 354);
· Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C); and
·
Code of Practice of the
Packaging, Labelling and Storage of Chemical Waste, EPD (1992).
11.2.1.2
The following EPD publications also provide guidance
on the land contamination assessment relevant to this study:
· Guidance Note for Contaminated Land Assessment and Remediation;
· Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management; and
· Guidance Notes for Investigation Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repair/Dismantling Workshops.
11.3.1.1
The contaminated land assessment methodology
comprises the following key survey tasks in order to identify and evaluate the
potential of land contamination within the study area:
(a) A desktop review to appraise the current and historical land uses within the study area in connection with land uses and potential activities leading to land contamination with the aid of aerial photographs, survey maps and the geological map as have been addressed in the endorsed CAP and supplementary CAP;
(b) A site reconnaissance to identify any visual contamination hotspots, as have been addressed in the endorsed CAP and supplementary CAP;
(c) Definition of field sampling and laboratory testing regimes and supervision of the field and laboratory testing works based on the Risk-Based Remediation Goals (RBRGs) promulgated since August 2007 in Hong Kong, if contaminated land hotspots were identified;
(d) Interpretation and assessment of the findings of the site investigation (if required) for soil and groundwater samples following the philosophy of the RBRGs which estimate the extent of remediation required to the level of risk under certain land uses for the protection of human health; and
(e) Recommendation of any necessary contamination remediation works for the future KTE operation based on the conclusion of the land contamination assessment.
11.3.1.2
The
proposed construction scheme for the tunnel from YMT to WHA comprises the
construction of access shafts followed by drill-and-blast and mechanical
breaking along the alignment, and excavated materials will be mucked out at
designated locations near the potentially contaminated sites. As such, excavation workers at these
locations would be potentially prone to the risk of land contamination impact.
11.3.1.3
Soil
bore logs with the description of sub-soil strata were prepared for all
sampling locations. All sampling
equipment and apparatus were thoroughly cleaned and decontaminated before and
after drilling and sampling at each sampling location. All necessary measures will be provided to
comply with statutory requirements in respect of environmental, health and
safety aspects.
11.3.1.4
Details of the methodology for
the field sampling and laboratory analyses in the SI are provided in the
endorsed CAP in Appendix 11.1. The
results of the laboratory analyses were interpreted in accordance with the Guidance Note for Contaminated Land Assessment and Remediation, and
Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land
Management. Reference was made to the RBRG criteria
for assessing the degree of land contamination in the site based on the
proposed future land use as tabulated in Tables 11.1 and 11.2.
Table 11.1: Risk-Based
Remediation Goals for Soil and Soil Saturation Limit
Chemical |
Risk-Based Remediation Goals for Soil |
Soil Saturation Limit (Csat) (mg/kg) |
||
Urban Residential (mg/kg) |
Industrial (mg/kg) |
Public Parks (mg/kg) |
||
VOCs |
|
|
|
|
Benzene |
7.04E-01 |
3.21E+00 |
4.22E+01 |
3.36E+02 |
Ethylbenzene |
7.09E+02 |
8.24E+03 |
1.00E+04* |
1.38E+02 |
Toluene |
1.44E+03 |
1.00E+04* |
1.00E+04* |
2.35E+02 |
Xylenes (Total) |
9.50E+01 |
1.23E+03 |
1.00E+04* |
1.50E+02 |
SVOCs |
|
|
|
|
Acenaphthene |
3.51E+03 |
1.00E+04* |
1.00E+04* |
6.02E+01 |
Acenaphthylene |
2.34E+03 |
1.00E+04* |
1.00E+04* |
1.98E+01 |
Anthracene |
1.00E+04* |
1.00E+04* |
1.00E+04* |
2.56E+00 |
Benzo(a)anthracene |
1.20E+01 |
9.18E+01 |
3.83E+01 |
- |
Benzo(a)pyrene |
1.20E+00 |
9.18E+00 |
3.83E+00 |
- |
Benzo(b)fluoranthene |
9.88E+00 |
1.78E+01 |
2.04E+01 |
- |
Benzo(g,h,i)perylene |
1.80E+03 |
1.00E+04* |
5.74E+03 |
- |
Benzo(k)fluoranthene |
1.20E+02 |
9.18E+02 |
3.83E+02 |
- |
Chrysene |
8.71E+02 |
1.14E+03 |
1.54E+03 |
- |
Dibenzo(a,h)anthracene |
1.20E+00 |
9.18E+00 |
3.83E+00 |
- |
Fluoranthene |
2.40E+03 |
1.00E+04* |
7.62E+03 |
- |
Fluorene |
2.38E+03 |
1.00E+04* |
7.45E+03 |
5.47E+01 |
Indeno(1,2,3-cd)pyrene |
1.20E+01 |
9.18E+01 |
3.83E+01 |
- |
Naphthalene |
1.82E+02 |
4.53E+02 |
9.14E+02 |
1.25E+02 |
Phenanthrene |
1.00E+04* |
1.00E+04* |
1.00E+04* |
2.80E+01 |
Pyrene |
1.80E+03 |
1.00E+04* |
5.72E+03 |
- |
Metals |
|
|
|
|
Antimony |
2.95E+01 |
2.61E+02 |
9.79E+01 |
- |
Arsenic |
2.21E+01 |
1.96E+02 |
7.35E+01 |
- |
Barium |
1.00E+04* |
1.00E+04* |
1.00E+04* |
- |
Cadmium |
7.38E+01 |
6.53E+02 |
2.45E+02 |
- |
Chromium III |
1.00E+04* |
1.00E+04* |
1.00E+04* |
- |
Chromium VI |
2.21E+02 |
2.18E+02 |
7.35E+02 |
- |
Cobalt |
1.48E+03 |
1.00E+04* |
4.90E+03 |
- |
Copper |
2.95E+03 |
1.00E+04* |
9.79E+03 |
- |
Lead |
2.58E+02 |
2.29E+03 |
8.57E+02 |
- |
Manganese |
1.00E+04* |
1.00E+04* |
1.00E+04* |
- |
Mercury |
1.10E+01 |
3.84E+01 |
4.56E+01 |
- |
Molybdenum |
3.69E+02 |
3.26E+03 |
1.22E+03 |
- |
Nickel |
1.48E+03 |
1.00E+04* |
4.90E+03 |
- |
Tin |
1.00E+04* |
1.00E+04* |
1.00E+04* |
- |
Zinc |
1.00E+04* |
1.00E+04* |
1.00E+04* |
- |
Dioxins/PCBs |
|
|
|
|
PCBs |
2.36E-01 |
7.48E-01 |
7.56E-01 |
- |
|
|
|
|
|
C6 - C8 |
1.41E+03 |
1.00E+04* |
1.00E+04* |
1.00E+03 |
C9 - C16 |
2.24E+03 |
1.00E+04* |
1.00E+04* |
3.00E+03 |
C17 - C35 |
1.00E+04* |
1.00E+04* |
1.00E+04* |
5.00E+03 |
Other Inorganic
Compounds |
|
|
|
|
Cyanide, free |
1.48E+03 |
1.00E+04* |
4.90E+03 |
- |
Organometallics |
|
|
|
|
TBTO |
2.21E+01 |
1.96E+02 |
7.35E+01 |
- |
Soil saturation limits for petroleum carbon
ranges taken from the Canada-Wide Standards for Petroleum Hydrocarbons in Soil,
CCME 2000; * denotes a ‘ceiling limit’ concentration.
Table 11.2: Risk-Based
Remediation Goals for Groundwater and Solubility Limit
Chemical |
Risk-Based Remediation Goals for Groundwater: |
Solubility Limit (mg/L) |
|
Urban Residential (mg/L) |
Industrial (mg/L) |
||
VOCs |
|
|
|
Benzene |
3.86E+00 |
5.40E+01 |
1.75E+03 |
Ethylbenzene |
1.02E+03 |
1.00E+04* |
1.69E+02 |
Toluene |
5.11E+03 |
1.00E+04* |
5.26E+02 |
Xylenes (Total) |
1.12E+02 |
1.57E+03 |
1.75E+02 |
SVOCs |
|
|
|
Acenaphthene |
1.00E+04* |
1.00E+04* |
4.24E+00 |
Acenaphthylene |
1.41E+03 |
1.00E+04* |
3.93E+00 |
Anthracene |
1.00E+04* |
1.00E+04* |
4.34E-02 |
Benzo(a)anthracene |
- |
- |
- |
Benzo(a)pyrene |
- |
- |
- |
Benzo(b)fluoranthene |
5.39E-01 |
7.53E+00 |
1.50E-03 |
Benzo(g,h,i)perylene |
- |
- |
- |
Benzo(k)fluoranthene |
- |
- |
- |
Chrysene |
5.81E+01 |
8.12E+02 |
1.60E-03 |
Dibenzo(a,h)anthracene |
- |
- |
- |
Fluoranthene |
1.00E+04* |
1.00E+04* |
2.06E-01 |
Fluorene |
1.00E+04* |
1.00E+04* |
1.98E+00 |
Indeno(1,2,3-cd)pyrene |
- |
- |
- |
Naphthalene |
6.17E+01 |
8.62E+02 |
3.10E+01 |
Phenanthrene |
1.00E+04* |
1.00E+04* |
1.00E+00 |
Pyrene |
1.00E+04* |
1.00E+04* |
1.35E-01 |
Metals |
|
|
|
Antimony |
- |
- |
- |
Arsenic |
- |
- |
- |
Barium |
- |
- |
- |
Cadmium |
- |
- |
- |
Chromium III |
- |
- |
- |
Chromium VI |
- |
- |
- |
Cobalt |
- |
- |
- |
Copper |
- |
- |
- |
Lead |
- |
- |
- |
Manganese |
- |
- |
- |
Mercury |
4.86E-01 |
6.79E+00 |
- |
Molybdenum |
- |
- |
- |
Nickel |
- |
- |
- |
Tin |
- |
- |
- |
Zinc |
- |
- |
- |
Dioxins/PCBs |
|
|
|
PCBs |
4.33E-01 |
5.11E+00 |
3.10E-02 |
|
|
|
|
C6 - C8 |
8.22E+01 |
1.15E+03 |
5.23E+00 |
C9 - C16 |
7.14E+02 |
9.98E+03 |
2.80E+00 |
C17 - C35 |
1.28E+01 |
1.78E+02 |
2.80E+00 |
Other Inorganic
Compounds |
|
|
|
Cyanide, free |
- |
- |
- |
Organometallics |
|
|
|
TBTO |
- |
- |
- |
- denotes
that RBRG could not be calculated because the toxicity or physical/chemical
values were unavailable, or the condition of Henry’s Law Constant>1.00E-05
was not met for the inhalation pathway;
* denotes
a ‘ceiling limit’ concentration;
Water
solubilities for
11.4
Identification of Potential
Impacts
11.4.1
Identification of Contamination
Sources
11.4.1.1 Based on the initial site appraisal, reconnaissance site visit, review of previous SI and other relevant information as summarised in the endorsed CAP (Appendix 11.1), the potential sources of land contamination relevant to the KTE development have been identified. The contaminants of concern (COCs) for the site have been selected based on the historical land use information collected during the above initial site appraisal with reference to the Guidance Note for Contaminated Land Assessment and Remediation, Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management. With respect to the historic land use information, the broad groups of selected COCs for this investigation include volatile organic compounds (BTEX: Benzene, Toluene, Ethylbenzene, Xylene), semi-volatile organic compounds (PAHs: Polycyclic Aromatic Hydrocarbons), metals, petroleum hydrocarbon, PCBs, cyanide, and organometallic compound (TBTO: Tributyltin Oxide).
11.4.2
Identification of Sensitive
Receivers
11.4.2.1 Construction workers would be prone to exposure to any potential contaminated materials during the construction phase during excavation of the identified contaminated sites. The principle exposure routes would include:
· Direct ingestion of contaminated materials through eating or drinking on-site; and
· Dermal contact with contaminated materials.
11.4.2.2 There would be no sensitive receivers during the operational phase of the KTE project provided that remediation action and measures have been fully implemented. Potential environmental impacts could, also, arise from any remediation works, if required (e.g. air emissions and water discharges, etc), that may affect the surrounding sensitive receivers e.g. human receivers and water bodies. Proper mitigation measures should, therefore, be implemented as necessary.
11.4.3
Conceptual Site Model and Site
Investigation
11.4.3.1 The conceptual site model is summarised in Table 11.3 below and based on this, the sampling locations were devised as shown in Table 11.4 and Figures 11.1 and 11.2.
11.4.3.2
As stated in the endorsed CAP, the historic and existing landuse and
geological information suggest that the operation of
11.5
Prediction of Environmental Impacts
11.5.1
Potential Soil Contamination
11.5.1.1
A total of 19 soil samples were
collected from 4 boreholes at BH1, BH2, BH3 and BH4 and 1 trial pit at TP1, as
shown in Figures 11.1 and 11.2.
11.5.1.2 A summary of laboratory testing results and the laboratory reports are included in the CAR in Appendix 11.2. For the soil samples collected, antimony, cadmium, chromium VI and mercury were mostly determined to be below the reporting limits of the laboratory, whilst arsenic, chromium III, copper, molybdenum, nickel, tin and zinc also exhibited low levels. Although the concentrations of barium, cobalt, lead and manganese for soil samples collected at 1.5m and 3.0m at TP1 showed elevated levels, all of them comply with the RBRGs for “Industrial” landuse where the railway inside HOM and WHA Stations would be located. The concentrations of petroleum hydrocarbon, VOCs, SVOC, PCBs, cyanide and TBTO were all below the reporting limits of the laboratory. There were no exceedances of the RBRGs determined for all the soil samples collected in the SI.
Table
11.3: Conceptual Site Model of KTE
Project
Potential Sources of Contamination |
Potential Human Receptors |
Potential Pathways |
Preliminary Appraisal of Potential Impact |
Tunnels from YMT to HOM |
|||
Esso filling station and LPG store at |
Construction Phase: Construction workers inside the tunnels |
The tunnels would be situated deep in
rock with no major fault lines identified and physically separated from any
potential contamination sources, hence unlikely forming pathways for
migration of contaminants |
Not anticipated, as no direct/indirect pathways
for the exposure of human receptors to the possible source of contaminants |
Operational Phase: Passengers and staff of KTE project |
The tunnels would be situated deep in rock
with no major fault lines identified and physically separated from any
potential contamination sources, hence unlikely forming pathways for
migration of contaminants |
Not anticipated, as no direct/indirect
pathways for the exposure of human receptors to the possible source of
contaminants |
|
HOM Station |
|||
|
Construction Phase: Construction workers for construction of the station entrance at |
Rock nature of site geology and existence
of concrete floor of the premises, but uncertain for any other pathways
inside the premises leading to spillage and leakage, hence migration of
contaminants uncertain, due to restriction of site access |
Potential
contamination anticipated. There
are 3 kerosene storage tanks beneath the building of the kerosene store. Also, the owner would be unlikely to permit
any proposed GI works to be undertaken within their premises, especially near
or underneath the 3 kerosene tanks.
Also, the inspection and identification of any hotspots at the
kerosene filling area was not permitted by the owner. As such, a borehole was proposed on the
existing slope adjacent to the storage tanks. It is suggested that a
reconnaissance site visit should be carried out upon the resumption of the
land area when the STT KX1484 land lease expired after
2010 to review whether further SI would be required (details refer to Table 11.5 below). |
|
Operational Phase: Passengers and staff using the station
Entrances B1 and B2 and adits |
The above ground station entrance and
adit would be physically separated from any potential underground contamination
sources, hence unlikely forming pathways for migration of contaminants |
Not anticipated, as no direct/indirect
pathways for the exposure of human receptors to the possible source of
contaminants |
Esso filling
station at No.157-171, |
Construction Phase: Workers for the construction of the access shaft at Wuhu Street Temporary Playground and HOM Station Entrance C2 |
The station entrance would be physically separated at long distance (>40m)
from any potential contamination sources, hence unlikely forming pathways for
migration of contaminants |
Unlikely at the access shaft, as the potential pathway would be too long
for the direct and indirect exposure of human receptors to the possible
source of contaminants |
Operational Phase: Passengers and staff using the station
Entrance C2 |
The station entrance would be physically separated at long distance (>40m) from
any potential contamination sources, hence unlikely forming pathways for
migration of contaminants |
Unlikely at the access shaft, as the potential pathway would be too
long for the direct and indirect exposure of human receptors to the possible
source of contaminants |
|
Tunnels from HOM to WHA |
|||
Esso filling
station at No.157-171, |
Construction Phase: Construction workers inside the tunnels |
The tunnels would be situated beneath the rock head with no major fault lines identified and
physically separated from any potential contamination sources, hence unlikely
forming pathways for migration of contaminants |
Not anticipated, as no direct/indirect
pathways for the exposure of human receptors to the possible source of
contaminants |
Operational Phase: Passengers and staff of KTE project |
The tunnels would be situated beneath the rock head with no major fault lines identified and
physically separated from any potential contamination sources, hence unlikely
forming pathways for migration of contaminants |
Not anticipated, as no direct/indirect
pathways for the exposure of human receptors to the possible source of
contaminants |
|
Historic
operation of dockyards at the existing Tak On Street along the KTE alignment,
and possible contamination due to previous landuse e.g. metal workshop, ship
repairing, etc |
Construction Phase: Construction workers inside the tunnels |
The construction works would be
physically separated at long distance (~100m) from any potential
contamination sources, hence unlikely forming pathways for migration of
contaminants |
Unlikely, as the potential pathway would be
too long for the direct and indirect exposure of human receptors to the
possible source of contaminants |
Operational Phase: Passengers and staff of KTE project |
The tunnels would be physically separated
from any potential underground contamination sources, hence unlikely forming
pathways for migration of contaminants |
Not anticipated, as no direct/indirect
pathways for the exposure of human receptors to the possible source of
contaminants |
|
WHA Station |
|||
Historic operation
of dockyards at the southern side of Tak On Street to the proposed WHA
Station, and possible contamination due to previous landuse, e.g. metal
workshop, ship repairing, etc |
Construction Phase: Workers for the construction of station entrance and adits at the
southern side of WHA Station to be built along Hung Hom Road and Shung King
Street |
Potential direct and indirect contacts
with contaminants in soil and/or groundwater |
Potential
contamination anticipated,
as direct and indirect pathways for the
exposure of human receptors to the possible source of contaminants exist |
Operation Phase: Passengers and staff using the station entrance and adit to be built
at that location |
The above ground station entrance and
underground adits would be physically separated from any potential
underground contamination sources, hence unlikely forming pathways for
migration of contaminants |
Not anticipated, as no direct/indirect pathways
for the exposure of human receptors to the possible source of contaminants |
Table 11.4: Details of Sampling Locations
ID |
Type of Investigation |
Location |
Characteristics |
BH1 |
Borehole |
Existing slope beneath |
Potential contamination of soil and groundwater due to the historic
operation of the kerosene store |
TP1 |
Trial Pit |
||
BH2 |
Borehole |
Existing pedestrian parts of |
Potential contamination of soil and groundwater due to the historic
landuse, e.g. metal workshop, ship repairing, etc |
BH3 |
Borehole |
Existing pedestrian area at |
Potential contamination of soil and groundwater due to the historic
landuse, e.g. metal workshop, ship repairing, etc |
BH4 |
Borehole |
Existing pedestrian area at the junction of Tak On Street and |
Potential contamination of soil and groundwater due to the historic
landuse, e.g. metal workshop, ship repairing, etc |
Table 11.5: Information for Contamination Assessment at
Stage |
Details |
1.Review of
Available Information |
Historic and existing
landuse and geological information reviewed in the endorsed CAP suggest that
the operation of the |
2.Initial
Contamination Evaluation and Possible Remediation Method |
According to the Fire
Services Department (refer to Appendix 5.4 of the endorsed CAP), there was no
record of spillage incidents reported at this kerosene store. A sampling point at BH1, which was carried
out in accordance to the endorsed CAP, has also revealed that there was no
contamination and hence any potential migration of contaminant would be
unlikely. Nevertheless, as stated in
the endorsed CAP, the historic and existing landuse and geological
information reviewed suggest that the operation of |
3.Confirmation of
whether the contamination problem at this site would be surmountable |
Based on the available
information in the desktop review of the existing Concord kerosene store, if
land contamination were discovered, it would be unlikely that the
contamination would be insurmountable and that the methods for the
remediation of oil contaminated sites as recommended in the above Guidance
Notes for Investigation and Remediation of Contaminated Sites of Petrol
Filling Stations, Boat Yards, and Car Repair/Dismantling Workshops would be
applicable, e.g. biopiling, etc. It is
recommended that when the permission for access is granted when the land is
resumed, a reconnaissance site visit should be carried out to review whether
contamination hotspots could be identified in the premises and hence whether
further SI would be required. |
4.Sampling and
Analysis Proposal |
Upon the completion of the
reconnaissance site visit, if further SI would be required, the approach to
sampling and analysis would follow the requirements of the EPD’s Guidance
Notes for Investigation Remediation of Contaminated Sites of Petrol Filling
Stations, Boatyards, and Car Repair/Dismantling Workshops. |
5.Schedule of
Submissions |
If further land
contamination SI would be required, the following schedule of submissions to
the EPD for endorsement is anticipated:
·
Supplementary CAP – approximately 1 month upon the
completion of the reconnaissance site visit; ·
Supplementary CAR (and RAP if contamination is
confirmed) – approximately 6 months upon endorsement of the supplementary CAP
by the EPD as well as successful granting of site access for the land
contamination SI; and ·
Remediation Report – to be confirmed in the
Supplementary CAR. |
11.5.2
Potential Groundwater Contamination
11.5.2.1 One groundwater sample was collected at each of BH2 and BH3. A summary of laboratory testing results and the laboratory reports are included in the CAR in Appendix 11.2. It should be noted that no groundwater was encountered at BH1, TP1 and BH4. All of the tested COCs in the groundwater sample were below the reporting limits of the laboratory or at very low levels, and there was no exceedance of the RBRGs.
11.6.1.1
There were no exceedances of the RBRGs determined for any of the soil
and groundwater samples collected in the SI.
11.6.1.2
In addition, as the operation of