12.                          hazard to life (erm)

 

12.1                      Introduction

 

12.1.1                Background

 

12.1.1.1          This section of the EIA presents a summary of the analysis and findings of the Hazard to Life Assessment (also referred as Quantitative Risk Assessment (QRA)) undertaken for the proposed Kwun Tong Line Extension (KTE) project.

 

12.1.1.2          The railway project consists of an approximately 2.5 km long extension from the overrun tunnels at Yau Ma Tei Station (YMT) to a new terminal station at Whampoa (WHA) via a station at Ho Man Tin (HOM) will become an interchange station with the proposed Shatin to Central Link (SCL) beneath a future property development at the site of the demolished Valley Road Estate.

 

12.1.1.3          The selection of construction methods has been optimised to minimise, as far as possible, the use of explosives depending on the type of material to be excavated. However, a significant amount of explosives will be required for the construction of tunnels, station and adits. It is envisaged that the following items of works for KTE will involve blasting:

 

·                A 2.6 km long underground tunnel connecting the overrun tunnels at Yau Ma Tei Station (YMT) to a new terminal station at Whampoa (WHA); the alignment is chosen to avoid all existing highway and building foundations.

·                Ho Man Tin Station – an intermediate station to interchange with the proposed Shatin to Central Link (SCL).

12.1.1.4          Excavation by blasting will be generally ongoing from the beginning of November 2011 to the end of December 2012.

 

12.1.1.5          To enable a timely delivery of explosives to site and in order to meet the proposed construction work programme, one temporary Explosives Storage Magazine (Magazine) is required. It will be located at Tseung Kwon O Area 137. The site was selected considering the distance to the work areas as well as other constraints such as land availability, minimum separation distances from temporary magazine to populated area, accessibility by Mines Division, etc. (ref.1, ref. 21).

 

12.1.1.6          With reference to the EIA Study Brief (ESB-188/2008), if there is use of explosives for the construction activities and the storage or blasting location is in close vicinity to populated areas and/or Potentially Hazardous Installation site(s) along the Project alignment a hazard to life assessment is required.

 

12.1.1.7          The QRA for the storage and transport of explosives relates to the construction phase of the project, in which blasting activities are expected. There will be no explosives handled during the operational phase.

 

12.1.1.8          The Hazard to Life assessment under this section of the EIA, addresses, in particular, the following:

·                Storage of explosives at the proposed temporary magazine (cartridged emulsion, cast boosters, detonating cord and detonators) including handling of explosives within the temporary magazine site; and

·                Transport of explosives to the delivery points.

12.1.1.9          Further details of the QRA for the Project are presented in the Appendix 12.1.

 

12.2                      Legislation Requirement and Evaluation Criteria

 

12.2.1.1          The key legislation and guidelines that are considered relevant to the development of the proposed Kwun Tong Line Extension (KTE) project are as follows:

 

·                Dangerous Goods Ordinance, Chapter 295;

·                Environmental Impact Assessment Ordinance (EIAO), Chapter 499; and

·                The EIA Study Brief (ESB-188/2008), Section 3.4.6.

12.2.3                EIAO Technical Memorandum (EIAO-TM)

 

12.2.3.1          The requirement for a QRA of projects that involve the storage and transport of dangerous goods where a risk to life is a key issue with respect to the Hong Kong Government Risk Guidelines (HKRG) is specified in Section 12 of the Environmental Impact Assessment Ordinance Technical Memorandum (EIAO-TM).

 

12.2.3.2          The relevant authority for a QRA study relating to a temporary explosives magazine storage facility and the transport of the explosives is the Environmental Protection Department (EPD), as specified in Annex 22 of the EIAO-TM.

 

12.2.3.3          Annex 4 of the EIAO-TM specifies the Individual and Societal Risk Guidelines.

 

12.2.4                Hong Kong Government Risk Guidelines (HKRG), EIAO TM Annex 4

 

12.2.4.1          Individual risk is the predicted increase in the chance of fatality per year to an individual due to a potential hazard. The individual risk guidelines require that the maximum level of individual risk should not exceed 1 in 100,000 per year i.e. 1 x10-5 per year.

 

12.2.4.2          Societal risk expresses the risks to the whole population. The HKRG is presented graphically in Figure 12.1. It is expressed in terms of lines plotting the frequency (F) of N or more deaths in the population from incidents at the installation. Two F-N risk lines are used in the HKRG that demark “acceptable” or “unacceptable” societal risks. The intermediate region indicates the acceptability of societal risk is borderline and should be reduced to a level which is “as low as is reasonably practicable” (ALARP). It seeks to ensure that all practicable and cost effective measures that can reduce risk will be considered.

 

12.3                      Study Objectives and Methodology

 

12.3.1.1          The objective of the QRA study is to assess the risk to life of the general public from the hazards that arise from the storage and transport of the explosives that are required to facilitate the construction of the Project. The results of the QRA should then be compared with the HKRG.

 

12.3.1.2          The detailed requirements of the study are given in Section 3.4.6 of the EIA study brief. The main requirements are:

 

·                To identify hazardous scenarios associated with the storage and transport of explosives; and then determine a set of relevant scenarios to be included in a QRA;

·                To execute a QRA of the set of hazardous scenarios determined, expressing population risks in both individual and societal terms;

·                To compare the individual and societal risks with the Criteria for Evaluating Hazard to Life stipulated in Annex 4 of the EIAO-TM; and

·                To identify and assess practicable and cost-effective risk mitigation measures (e.g. selection of the shortest practicable road transport routes to and from the storage facility).

12.3.1.3          The methodology of the hazard assessment should be consistent with previous studies having similar issues.

 

12.3.1.4          The elements of the QRA are shown schematically in Figure 12.2. It includes the following:

 

·                Collection and review of relevant data for the proposed temporary Magazine, the transport from the temporary Magazine, and the use of explosives at the works area, as well as population and vulnerable receptors, such as slopes, retaining walls etc., in the vicinity of the storage, the tunnel construction and proposed transport routes;

·                Hazard identification. A review of literature and accident databases were undertaken and updated. These formed the basis for identifying all the hazardous scenarios for the QRA study;

·                Frequency estimation. The frequencies, or the likelihood, of the various outcomes that result from the hazards associated with the storage and transport of explosives was taken primarily from the XRL study (ref. 2), which has been accepted by the relevant authorities. Where necessary, to consider specific factors applicable for the Project, recent accident statistics, and to reflect the current knowledge on the explosives’ properties, these frequencies were modified or updated making reference, as far as possible to published references; such as the previous Hong Kong studies , UK HSE, US DoD, Dutch TNO, latest accident statistics from the Transport Department and Fire Service Department, etc.;

·                For all identified hazards, the frequency assessment has been documented and the consequences were modelled;

·                The frequency model related to the transport and storage of explosives was taken from the ERM 2009 study (ref. 2);

·                The consequence model employed in this study is the ESTC model (ref.3), developed by the UK Health and Safety Commission (HSC). Although, there have been a number of recent studies suggesting that the ESTC (2000) models should be reviewed for applicability to explosive stores and transport, these models are still the recommended models in the UK and adopted in the WIL (ref. 4) and XRL (ref. 2) studies;

·                The consequence and frequency data were subsequently combined using ERM’s in-house proprietary software Riskplot TM to produce the required risk estimates. The transport part of the risk assessment, consistently with the XRL study (ref. 2), uses an in-house Explosive Transport GIS Risk Assessment tool (E-TRA) developed to account for three-dimensional blast effects on buildings and the effect of accidental explosions on elevated roads. It also accounts for traffic jam scenarios which could occur in some accidental scenarios as reported in ref. 5. The E-TRA model is summarised in Section 3.2 of Appendix 12.1 and has been validated against Riskplot TM.

12.3.1.5          Finally, the results from the risk assessment were compared to the EIAO-TM Criteria. Recommendations have been made where required to ensure compliance with EIAO-TM Criteria, relevant best practice, and to reduce the overall risk levels.

 

12.3.1.6          The methodology used in this hazard assessment is consistent with previous studies. Details of the analysis can be found in Appendix 12.1.

 

12.4                      Facility Details

 

12.4.1                Project Overview

 

12.4.1.1          The Project comprises the following key elements (ref. 19):

 

·                The approximately 0.5 km tunnel from the Club de Recreio (CDR) Shaft to the Yau Ma Tei overrun tunnels;

·                The approximately 0.7 km tunnel from the Club de Recreio (CDR) Shaft to the west end of Ho Man Tin Station Platform;

·                The Ho Man Tin Station Platform(West - 0.13 km and East – 0.09 km);

·                The Ho Man Tin Station (Open Cut Scheme, ref. 20);

·                The approximately 0.05 km tunnel from the east end of Ho Man Tin Station Platform to Fat Kwong Street (FKS) Shaft;

·                The approximately 0.5 km tunnel from the FKS Shaft to Whampoa Station; and

·                Construction of a temporary above ground explosives magazine site at Tseung Kwon O Area 137.

12.4.1.2          The proposed Project alignment and work areas are shown in Figure 12.3.

 

12.4.1.3          Excavation in rock by blasting will be ongoing generally from November 2011 to December 2012 for a significant length of the tunnels, station and adits.

 

12.4.1.4          Two categories of explosives will be used for the construction of tunnels and adits by Drill and Blast methods. These are:

 

·                Initiating explosives: cartridged emulsion explosives, cast boosters, detonating cord and detonators; and

·                Blasting explosives: bulk emulsion explosives or ammonium nitrate-fuel oil (ANFO) manufactured at the blast site or, in close proximity to sensitive receivers (i.e. with MIC less than 2 kg), cartridged emulsion explosives.

12.4.1.5          Cartridged emulsion, cast boosters and detonating cord will be delivered from the temporary explosives magazine to the various construction sites by the appointed contractor using Mines Division licensed trucks. These explosives are classified as an explosive Class 1.1D under United Nations (UN) Classification (ref. 6) and as a Category 1 (Explosive and blasting agents) Dangerous Goods under the Hong Kong Dangerous Goods Ordinance.

 

12.4.1.6          Detonators will also be used to initiate the blast at the working face. As used in this project, they are classified as Class 1.4B or 1.4S explosives under the UN classification system and Category 1 (Explosives and Blasting Agents) under the Hong Kong Dangerous Goods Ordinance, and will be transported from temporary magazine to work areas by a dedicated truck, which is identical to, but independent of the truck carrying the emulsion explosives and detonating cord. Detonators approved for use in Hong Kong are of the Non-Electric Type, i.e. initiated by shock tube.

 

12.4.1.7          Explosives classified as Class 1.1 are defined as substances and articles which have a mass explosion hazard while Class 1.4 explosives present no significant hazard outside the packaging. To comply with the classification, it is required to ensure that the explosive is safe to transport, to pass a series of classification tests in accordance with the UN test manual, 2003 (ref.7). Due to different properties of explosives, a compatibility class is also assigned, as applicable to this Project. Type “B” is defined as “An article containing a primary explosive substance and not containing two or more protective features” and type “S” is defined as “The substance or article so packed or designed that any hazardous effects arising from accidental functioning are limited to the extent that they do not significantly hinder or prohibit fire fighting or other emergency response efforts in the immediate vicinity of the package”.

 

12.4.1.8          Bulk emulsion precursor will be transported to the blast sites by the appointed third party supplier. It is classified as an oxidising agent Class 5.1 under the UN Classification system and as Category 7, i.e. strong supporter of combustion under the Hong Kong Dangerous Goods Ordinance. Prior to sensitizing, it is not considered as an explosive, and hence outside the scope of this QRA. Bulk emulsion will not be stored within the temporary magazine.

 

12.4.1.9          Depending on blasting requirements, ANFO may be used in this Project. ANFO is classified as UN HD 1.1D under UN Classification. It consists of an oxidizing substance mixed with 6% by weight of diesel fuel oil. ANFO will be produced at the construction work area by using a mixing truck and hence outside the scope of this QRA.

 

12.4.2                Statutory/ Licensing Requirements

 

12.4.2.1          The statutory / licensing requirements with respect to the explosives (Cat. 1 Dangerous Goods) or the oxidizing substances (Cat. 7 Dangerous Goods) used to prepare explosives at the construction work area as well as relevant government departments/ authorities’ advice and practice on the proposed transport and storage of explosives for the blasting activities are summarized below.

 

Category 1 Explosives and Blasting Agents

 

·                Responsible authority: The Commissioner of Mines; and

·                Applicable regulations/ guidance notes:

-          Supply of detonators, cast boosters and cartridged emulsion explosives (under the Dangerous Goods (General) Regulations Cap. 295B);

 

-          Approved explosives for blasting in Hong Kong (under the Dangerous Goods (General) Regulations Cap. 295B);

 

-          Blast design (under the Dangerous Goods (General) Regulations Cap. 295B);

 

-          Blast loading and execution (under the Dangerous Goods (General) Regulations Cap. 295B);

 

-          Removal of explosives (under Regulation 4 of the Dangerous Goods (General) regulations Cap. 295B);

 

-          Approval of an explosives delivery vehicle (under CEDD’s “Guidance Note on Requirements for Approval of an Explosives Delivery Vehicle” (ref. 8));

 

-          Explosives delivery vehicle design features and safety requirements (under CEDD’s “Guidance Note on Requirements for Approval of an Explosive Delivery Vehicle” (ref. 8);

 

-          Temporary explosives magazine (under CEDD’s document “How to Apply for a Mode A Explosives Store Licence” (ref. 9)) including storage capacity;

 

-          Explosives produced at site (under Regulation 31A of the Dangerous Goods (General) Regulations Cap. 295B); and

 

-          Explosives load per truck (in accordance with the Removal Permit under the Dangerous Goods (General) Regulations Cap. 295B).

 

Category 7 Strong Supporters of Combustion

 

·                Responsible authority: Fire Services Department; and

·                Applicable regulations:

-          Storage of oxidizing agents (under Dangerous Goods (General) Regulations Cap. 295B)

 

12.4.2.2          This Project will use cartridged emulsion and cast booster explosives as initiating explosives. For blasting explosives, bulk emulsion or ANFO will be used; however, cartridged emulsion explosives may be used as blasting explosives in close proximity to sensitive receivers. Therefore, the storage and transport requirements for explosives are the minimum required quantities for the Project.

 

12.4.3                Temporary Storage Magazine Details

 

12.4.3.1          A temporary magazine site is proposed to be built at Tseung Kwan O (TKO) Area 137. The design, construction and operation of the temporary magazine will comply with the general requirements from the Commissioner of Mines (ref. 9).

 

12.4.3.2          The temporary magazine is generally designed to store sufficient quantities of explosives for two days so as to allow blasting to be carried out 24 hours per day and provide a buffer in the event of delivery interruption to the temporary magazine by Mines Division.

 

12.4.3.3          The temporary Magazine is required to serve the delivery points at Ho Man Tin (HOM) Station, Fat Kwong Street (FKS) and Club de Recreio (CDR) shafts. Potential magazine site locations in Hong Kong close to the blasting locations have been investigated. One site has been identified as the shortest practicable distance from the temporary Magazine site to the construction site, in compliance with the separation requirements of Mines Division. This is Tseung Kwan O (TKO) Area 137. The site is located in area of low population density. 

 

12.4.3.4          The proposed temporary Magazine will have five stores each containing 300 kg. All quantities of explosives are represented in gross weight, unless they are clearly specified as TNT eqv kg. A storage chamber for detonators equivalent to two days supply is provided next to each explosives chamber. The detonators have a very low explosive mass and contain less than 1 gram of high explosives per detonator. The net explosives quantity within each detonator chamber will be less than 2 to 3 kg.

 

12.4.3.5          The work areas and the associated explosives using contract packaging for the temporary magazine are shown in Table 12.1.

 

12.4.3.6          Each of the temporary magazine buildings is a single-storey, detached and bunded structure, which is fenced and secured in accordance with the Commissioner of Mines’ requirements. Details of the requirements are defined in the CEDD document “How to Apply for a Mode A Explosives Store Licence” (ref. 9). Surface road access suitable for 11-tonne trucks is also provided for the delivery of explosives.

 

Table 12.1:   Project Contracts and Work Areas (Blasting only)

Magazine Storage Requirement per contract

Works Area

Blast Faces

Delivery Point

1,500 kg      (300 kg x 5)

Ho Man Tin Station

- Open Cut Scheme

Ho Man Tin (Chung Hau Street)

Fat Kwong Street Shaft

- Single bore tunnel drives west to HOM – continues into the east end of Ho Man Tin Station Platform

- Single bore tunnel drives east to Whampoa Station

Fat Kwong Street

Club De Recreio Shaft

- Twin tunnels drive west to YMT

- Twin tunnels drive east to HOM – continues into the west end of Ho Man Tin Station Platform

Wiley Road

 

12.4.3.7          Mines Division will deliver explosives to the temporary Magazine on a daily basis (once per day), from where explosives will be transferred to the work areas by the contractor for the daily or twice-daily blasts depending on requirements for construction. Loads will be limited to a maximum of 200 kg per truck or less in accordance with the Removal Permit issued by Mines Division.

 

12.4.3.8          The explosives will be delivered to the various construction work areas using the public roads as shown in Figure 12.4. The proposed delivery points from the temporary Magazine are shown in Table 12.1.

 

12.4.3.9          According to the current construction programme, delivery of explosives to the three delivery points will be required from November 2011 to December 2012. The delivery programme to each work area will overlap significantly.

 

12.4.3.10      In addition to cartridged emulsion, cast boosters and detonating cord, detonators will also be transported. Detonators will be transported in a separate and dedicated licensed vehicle.

 

12.4.3.11      The licensed explosives delivery vehicles (LGV pick-up trucks) for delivery of explosives from the temporary site magazine to the worksites, used as the basis for this QRA, will have the following safety features:

 

·                Diesel powered;

·                Manual fuel isolation switch;

·                Forward mounted exhaust with spark arrestor;

·                All electrical wiring or electrical devices will be shrouded in fire resisting conduits;

·                Fuel tank will be protected from accidental damage, and designed to prevent accumulation of spilt fuel on any part of the vehicle;

·                Two fire extinguishers will be mounted on an easily accessible position on the vehicle;

·                Fire resistant material will be fitted between the wheel arches and the goods compartment;

·                Lockable wood lined steel or aluminium receptacles mounted on the vehicle tray; and

·                Fold down / up explosives warning signs and rotating flashing light.

12.4.3.12      In addition, a fire screen will be fitted between the cab and the load compartment and between the load compartment and the chassis.

 

12.4.4                Base Case and Worst Case for Quantitative Risk Assessment

 

12.4.4.1          The actual construction programme will depend on the detailed design and appointed contractor. It may also depend on the actual achievable progress rates which may vary due to specific site conditions (e.g. geology). To consider the uncertainty in the envisaged construction programme, a Base Case, which accounts for expected programme variations, and a Worst Case, which presents the worst programme scenario, have been considered for the assessment.

 

12.4.5                Base Case programme for Hazard to Life Assessment

 

12.4.5.1          Based on the envisaged construction programme and sequence of works, the annual travel distance by explosives vehicles, carrying cartridged emulsion and detonating cord, will reach a peak in the period between November 2011 and October 2012, with an annual number of deliveries of 1,232 and a travel distance of around 29,000 km. This period is referred to as the peak explosives delivery period which is taken to represent the Base Case scenario for the Hazard to Life Assessment. The delivery frequency has been estimated on the basis that, for a given delivery point, each delivery will be made to each blast face independently of the other blast faces even if the load could be transported on the same truck. This approach, although slightly conservative, accounts for expected delivery variations during the peak delivery period, within which, separate deliveries will be generally undertaken.

 

12.4.5.2          The explosives load has been estimated on the basis that, for a particular delivery point, when the blast time for various faces coincides in the construction programme within the peak delivery period, explosives will be transported on the same truck. The total number of trips has been estimated based on the typical licensing limit of 200 kg explosives per truck.

 

12.4.5.3          In the Base Case, it was considered that blasting could be carried out at predetermined times during the day following the envisaged construction programme. A distribution of delivery times has thus been considered based on the construction programme.

 

12.4.5.4          The Base Case programme is summarized in Table 12.2.

 

Table 12.2:   Summary of Explosives Deliveries and Transport Quantities (for Base Case)

Delivery Point

Explosive Deliveries in Peak Delivery Period (trips/year)

Peak Transport Quantity

(kg/trip)

Ho Man Tin Station

238

200

FKS Shaft

413

119

CDR Shaft

581

200

 

12.4.6                Worst Case programme for Hazard to Life Assessment

 

12.4.6.1          The Hazard to Life Assessment also covers the Worst Case scenario. It addresses the possibility that, due to construction uncertainties or contractors’ methods of working, the contractor proposes an actual construction programme which differs from the envisaged construction programme. Such a case may result in a higher number of delivery trips. Return trips loaded with explosives will generally be avoided; however, due to some construction uncertainties, a number of return trips could be made. Overall, in the worst case, a 20% increase in the number of deliveries compared to the base case scenario may result based on previous project experience.

 

12.4.6.2          In this project, for a particular delivery point, it is possible that the explosives load required for each delivery will be higher than that indicated in the envisaged programme due to particular site conditions and blasting requirements; however, the explosives load to be transported will be, as a worst case, the maximum explosives load for the site (sum of the loads for each blast face within the same work site). The delivery load, in the Worst Case Scenario, has been selected as the sum of the loads for each blast face within the same work site bearing in mind the licensing limit of 200 kg for the truck.

 

12.4.6.3          In this Worst Case Scenario, explosives could be delivered at peak day times.

 

12.4.6.4          The Worst Case programme is summarized in Table 12.3.

 

Table 12.3:   Summary of Explosives Deliveries and Transport Quantities (for Worst Case)

Delivery Point

Explosive Deliveries in Peak Delivery Period (trips/year)

Peak Transport Quantity

(kg/trip)

Ho Man Tin Station

286

200

FKS Shaft

496

200

CDR Shaft

697

200

 

12.5                      Population Data

 

12.5.1.1          Population within the vicinity of the temporary explosives magazine is estimated based on site surveys and information gathered from Geographic Information System (GIS) database 2008 data (ref. 10) and aerial maps. The site is a relatively remote location surrounded by woodland and is currently unoccupied.

 

12.5.1.2          Population data used for the transport risk assessment have been collected by a combination of site survey, Base District Traffic Model (BDTM) 2011, Annual Traffic Census 2007 (ref. 11), Road Traffic Accident Statistics 2007 (ref. 12 & 13), Centamap (2009) and GIS tools. For areas where information is not available, assumptions have been used consistently with the previously approved studies. Three types of population have been considered.

 

·                Pedestrian population on footpaths and pavements next to delivery routes;

·                Road population; and

·                Building population.

12.5.1.3          The approach to modelling the risks during the transport of explosives is fully 3-dimensional and GIS based. It also accounts for the potential increased risk when explosives trucks travel on elevated roads.

 

12.5.1.4          The population data adopted in the QRA is detailed in Appendix 12.1.

 

12.6                      Hazard Identification

 

12.6.1                Background

 

12.6.1.1          Hazard identification consisted of a review of the following:

 

·                Explosives properties;

·                Scenarios presented in previous relevant studies;

·                Historical accidents; and

·                Discussions with explosives and blasting specialists.

12.6.2                Hazards of Explosives

 

12.6.2.1          Explosives present a hazard to both property and people. This hazard manifests itself in the following ways:

 

·                Blast and pressure wave;

·                Flying fragments or missiles;

·                Thermal radiation; and

·                Cratering and Ground shock.

12.6.2.2          In the case of explosions, the biggest damage is usually caused by the blast effects. The blast and pressure waves can cause injury to sensitive human organs such as the ears and lungs. However, considerable overpressures are required for fatalities to occur, and consequently people need to be fairly close to the scene for the direct explosion effects to b significant.

 

12.6.2.3          Other effects due to the blast or overpressure are associated with damage to buildings and other structures/ objects or the impact of debris and fragments from the damaged building structure, and the vehicle or container in which the explosives are held. Moreover, injury may occur when people are displaced or swept away, or due to the violent movement of internal organs within the body.

 

12.6.2.4          An explosion may result in the formation of a short duration fireball since the fuel content of the emulsion is oxidised. However, it is generally the case that the thermal hazards from an explosives detonation event are of less concern than the blast and fragment hazards.

 

12.6.3                Review of Incidents

 

12.6.3.1          A review of reported safety incidents involving storage, transport and disposal of explosives (in industrial applications) was carried out. Records were retrieved mainly from the UK Health and Safety Executive (UK HSE)’s Explosives Incidents Database Advisory Service (EIDAS) (ref. 14), US Mine Safety and Health Administration (MHSA) (ref. 15) and Western Australia’s Department of Consumer and Employment Protection (DOCEP) (ref. 16). The records provided are also supplemented with information obtained from various sources. An analysis of accident data is provided in Section 5 and Section 6 of Appendix 12.1.

 

12.6.4                Scenarios for Hazard Assessment

 

12.6.4.1          The following table (Table 12.4) provides a summary of the scenarios considered in this QRA.

 

Table 12.4:   Scenarios Considered in the QRA Study

Tag

Scenario

Storage of Explosives

01

Detonation of full load of explosives in 1 store in TKO Area 137

02

Detonation of full load of explosives in one contractor truck on the access road within TKO Area 137 magazine site boundary

Transport of Explosives

03

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Ho Man Tin delivery point

04

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Fat Kwong Street delivery point

05

Detonation of full load of explosives in one contractor truck on public roads– from TKO Area 137 site to Club De Recreio delivery point

 

12.7                      Frequency Analysis

 

12.7.1                Background

 

12.7.1.1          Deflagration or detonation explosion may occur during the transportation of explosives from the temporary magazine to the construction sites. This accidental explosion can be caused by spontaneous fire (non-crash fire), fire after a vehicle crash (crash fire), impact initiation in crash (crash impact) or spontaneous explosion during the normal condition of transport which may occur if the cargo load contains ‘unsafe explosives’.

 

12.7.1.2          In this study, a fault tree has been developed to assess the overall explosion frequency as applicable to the Project contractors’ trucks based on the latest information available on the explosives properties, vehicle incident frequencies provided by the Transport Department and Fire Services Department, and the specific explosives transport vehicle design and operation to be used as part of the Project. This is consistent with the previous XRL study (ref. 2)). The details of the frequency assessment are provided in Section 6 of Appendix 12.1.

 

12.7.2                Frequency Analysis for Transport of Explosives

 

12.7.2.1          Based on Hong Kong vehicle accident data, the frequencies of explosives initiation during road transport are estimated as 7.69 x 10-10/km for the truck on non-expressway and 6.87 x 10-10/km on expressway, using a fault tree approach. The fault tree model has considered the frequencies of non-crash fire, crash fire, crash impact and unsafe explosives. Adjustment factors were applied to the model to account for the probabilities of explosives initiation due to thermal stimulus or crash impact

 

12.7.3                Frequency Analysis for Storage of Explosives

 

12.7.3.1          The overall initiating event frequency within the temporary storage magazine is based upon the UK HSE recommended value of 1 x 10-4 per storehouse year. Additional risk due to manual transfer of explosives, lightning strike, aircraft crash, hill/ vegetation fire, earthquake and other site specific considerations to the KTE project were also considered but their contribution was negligible (see Section 6 of Appendix 12.1).

 

12.8                      Consequence Analysis

 

12.8.1.1          The probability of fatality due to blast over-pressure, have been estimated using the method detailed by the UK HSE Explosives Storage and Transport Committee (ref. 3). The fatality contours are calculated at 90%, 50%, 10%, 3% and 1% fatality. Details of the model and the results are given in Section 7 of Appendix 12.1.

 

12.8.1.2          Special features such as slopes and service reservoirs along the transport routes or near the temporary magazine site were identified with respect to the potential secondary hazards. These aspects of risk were evaluated separately, and were found either insignificant or already covered by applying the blast overpressure-fatality model (i.e. ESTC model (ref. 3)).

 

12.9                      Risk Summation

 

12.9.1                Individual Risk Results

 

12.9.2                The individual risk (IR) contours associated with the Project are shown in Figure 12.5 and Figure 12.6. In Figure 12.6 the ‘indoor’ refers to the population located inside buildings, and the ‘outdoor’ refers to the population located outside buildings i.e. in open areas. At the same distance from a potential explosion, persons located inside buildings are more vulnerable to explosion than persons located outside buildings as they are exposed to more hazards such as debris from broken windows, etc. This explains a higher individual risk for indoor population.

 

12.9.3                For the delivery routes, the IR data represent the highest individual risk, occurring on the road in the same lane as the explosives delivery truck. It is observed that the maximum IR is about 8.2´10-8 per year. This is a low risk when compared to Hong Kong Risk Guidelines which require the offsite IR from a fixed installation to be below 10-5 per year.

 

12.9.4                The temporary magazine site is in a remote area and the 10-5 per year contour does not extend offsite in both indoor/outdoor cases. There is no continuous presence of people nearby. The presence of people in these areas will be rare and only temporary leading to a very small presence factor. The most exposed population group will be Mines Delivery personnel who will be making/ receiving deliveries at the jetty. Such persons are not expected to be present more than 8% of the time. Therefore, no member of the public will be exposed to an IR of 10-5 per year. The actual risk to any individual will be much smaller than 10-5 per year and is deemed to be acceptable.

 

12.9.5                Societal Risk Results

 

12.9.6                The societal risk results for explosives storage and transport for the KTE project have been combined to produce the overall societal risk results for the base case and the worst case (Figure 12.7).

 

12.9.7                The Base Case represents the risks associated with the envisaged blasting programme. It can be seen that the risks lie in the ALARP region.

12.9.8                The Worst Case represents the maximum risks associated with the worst blasting scenario. The risks, as expected, are higher than the base case but still within the ALARP region.

 

12.9.9                Figure 12.8 shows the F-N curve for the Base Case with a breakdown by storage and transport. It is observed that risks from the temporary magazine are negligible compared to the transport risks. Indeed, the temporary magazine is located in a remote area with very low population density nearby.

 

12.9.10            The F-N curves for both base case and worst case are within the As Low as Reasonably Practicable (ALARP) Region as per HK EIAO-TM. Therefore, mitigation measures need to be considered to reduce the risk. The ALARP assessment is provided in Section 9 of Appendix 12.1.

 

12.9.11            The Potential Loss of Life (PLL) for the base case and the worst case are given in Table 12.5 and Table 12.6 respectively. The PLL for this Project has been evaluated at 5.66 x 10-4 per year. The maximum PLL value for the Project is estimated at 7.91 x 10-4 per year, which is obtained from the worst case.

 

Table 12.5:   Potential Loss of Life for Base Case

Base Case

PLL (per year)

Percentage

Contribution (%)

Storage of Explosives

TKO Area 137 Magazine

9.17E-07

0.16%

Transport of Explosives

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Ho Man Tin delivery point

9.55E-05

16.9%

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Fat Kwong Street delivery point

1.46E-04

25.8%

Detonation of full load of explosives in one contractor truck on public – from TKO Area 137 site to Club De Recreio delivery point

3.24E-04

57.2%

Total

5.66E-04

 

 

Table 12.6:   Potential Loss of Life for Worst Case

Worst Case

PLL (per year)

Percentage

Contribution (%)

Storage of Explosives

TKO Area 137 Magazine

9.17E-07

0.12%

Transport of Explosives

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Ho Man Tin delivery point

1.25E-04

15.9%

Detonation of full load of explosives in one contractor truck on public roads from TKO Area 137 site to Fat Kwong Street delivery point

2.53E-04

32.0%

Detonation of full load of explosives in one contractor truck on public – from TKO Area 137 site to Club De Recreio delivery point

4.12E-04

52.1%

Total

7.91E-04

 

 

12.9.12            ALARP Assessment

 

12.9.13            Since the risks posed by the Project, for both cases considered, are within the ALARP region specified in EIAO-TM Annex 4, this implies that risk reduction measures and / or alternate options should be explored for the Project.

 

12.9.14            It was found that the risks arising from explosives transport are much more significant than that of the explosives storage; hence the ALARP assessment focuses on the transportation aspects of explosives.

 

12.9.15            Where the risk falls into the ALARP region, the risks associated with each probable hazardous event should be reduced to a level ‘as low as reasonably practicable’. This firstly requires the identification of any ‘practicable’ options regardless of their cost. A mitigation option is considered ‘practicable’ if an engineering solution exists and can be implemented on the KTE project regardless of the cost without affecting the project construction programme. Secondly, the extent to which the risk should be reduced is usually measured as a trade off between the risk reduction, i.e. the safety benefits and the cost of the risk reduction measure. A mitigation option is considered ‘reasonable’ if the cost of implementing the option is not grossly disproportionate to the achieved safety benefits.

 

12.9.16            Risk mitigation measures may take the form of engineered measures, controls in the zones most impacted by the hazardous scenarios presented by this project, or operation and procedural controls

 

Approach to ALARP Assessment

 

12.9.17            The approach consists of identifying potential justifiable mitigation measures, assessing their practicability for this Project and evaluating their cost and comparing with the safety benefits of implementing the measures. Combinations of mitigation measures are also considered.

 

12.9.18            The safety benefits are evaluated as follows:

 

Safety Benefits = Value of Preventing a Fatality x Aversion Factor x Reduction in PLL value x Design life of mitigation measure.

 

12.9.19            The Value of Preventing a Fatality (VPF) reflects the tolerability of risk by the society and therefore the monetary value that the society is ready to invest to prevent a fatality. For the purpose of this assessment and for consistency with previous studies, the Value of Preventing a Fatality is taken as HK$33M per person, which is the same figure as used in previous Hazard Assessment studies (derived from ref. 17 but updated to current prices).

 

12.9.20            Depending on the level of risk, the value of preventing a fatality may be adjusted to reflect people’s aversion to high risks or scenarios with potential for multiple fatalities. The methodology for application of the ‘aversion factor’ follows that developed by EPD (ref. 18), in which the aversion factor is calculated on a sliding scale from 1 (risks at the lower boundary of the ALARP region of the Risk Guidelines) up to a maximum of 20 (risks at the upper boundary of the ALARP region). The adjusted VPF using the aversion factor of 20 is HK$660M. This value is a measure of how much the society is willing to invest to prevent a fatality, where there is potential for an event to cause multiple fatalities.

 

12.9.21            With reference to Appendix 12, the maximum justifiable expenditure for this Project is calculated as HK$ 0.61M assuming the design life of the mitigation measure is 1.17 years based on the construction phase of the KTE project during which storage and transport of explosives will be involved, with the PLL of 7.91 x 10-4 per year, which is obtained from the Worst Case.

 

12.9.22            For an ‘achievable’ mitigation measure to be potentially justifiable, its cost should be less than the Maximum Justifiable Expenditure.

 

Potential Justifiable Mitigation Measures

 

12.9.23            The potential options that have been examined in the ALARP assessment include the following categories.

 

·                Options eliminating the need for a temporary Magazine or eliminating the risk (e.g. Use of alternative methods of construction (‘hard rock’ TBMs));

·                Options reducing significantly the distance run by contractors’ explosive trucks such as closer temporary magazine sites and alternative routes. The temporary magazine and route options considered are summarised below:

-          A list of 24 alternative temporary magazine sites to TKO Area 137 were considered. (Appendix 12).

 

However, none of the alternative candidate sites could meet the Commissioner of Mines’ external separation requirements. Therefore, no alternative temporary magazine site option has been considered for the ALARP assessment.

 

-          Based on a review of the possible transport routes for this project, Po Lam Road has been presented as an alternative route.

 

The possibility of using Po Lam Road instead of Clear Water bay Road for road transport to the three work sites is explored in the context of risk. This option has been selected for further cost benefit evaluation.

 

-          The combined Road/Marine transport option from the temporary magazine site to the KTE construction sites was not considered practicable.

 

·                Options reducing significantly the quantities of explosives to be used such as use of ‘hard rock’ TBM or alternatives to cartridged emulsion.

-          It is possible to use smaller explosive charges for initiating explosives such as ‘cast boosters’. The main explosive component of ‘cast boosters’ is PETN. Using such explosives will reduce the weight of explosives to be transported. However, PETN has a higher TNT equivalency. This will also not eliminate the need for detonating cord. This option has been selected for further cost benefit evaluation.

 

·                Options considering improved explosives truck design; and

·                Options considering better risk management systems and procedures.

12.9.24            In summary, the following options have been considered for cost-benefit analysis.

 

·                Option 1: Use of Alternative RoutePo Lam Road; and

·                Option 2: Use of Smaller Quantities of Explosives.

12.9.25            The PLL for Options 1 and 2 is compared to the PLL for the Worst Case in Table 12.7. This was used as the basis for the cost-benefit analysis/ ALARP assessment presented in Table 12.8.

 

12.9.26            Other options considered practicable have been either recommended for implementation or assessed comparing the implementation cost with the maximum justifiable expenditure. The evaluation for each option is shown in Table 12.8. More details are available in Section 9 of Appendix 12.

 

Table 12.7:   Potential Loss of Life for Worst Case, Option 1 and Option 2

Case

PLL (per year)

Worst Case

7.91E-04

Option 1: Use of Alternative RoutePo Lam Road

8.94E-04

Option 2: Use of Smaller Quantities of Explosives

5.37E-04

 

Table 12.8:   ALARP Assessment Results

Option Description

Practicability

Implementation Cost

Safety Benefits or Justifiable Expenditure

ALARP Assessment

Result

Use of alternative methods of construction (TBMs)

 

Not Practicable

> HK$ 100M

HK$ 0.61M

Not Justified

Use of Magazines Closer to the Construction Sites

 

Not Practicable

-

 

Closest practicable magazine site to the construction sites has been selected

 

Use of different explosive types (different types of detonating cord)

Pose some limitations

HK$ 1M

No safety benefit

Not Justified

Alternative Route (Option Case 1)

Practicable for Road Transport.

 

Not practicable for the combined Road/Marine Transport Option.

-

Negative

Clear Water Bay Road preferred

Use of Smaller Quantities of Explosives (Option Case 2)

Practicable

> HK$ 0.50M

HK$ 0.20M

Use of cast boosters is not justifiable on risk grounds. The cast booster option will be explored further in line with the use of best practice in explosives selection. [1]

Safer explosive truck (reduced fire load)

Practicable

-

-

Based on low implementation costs, this option has been directly incorporated in recommendations

Reduction of Accident Involvement Frequency (training programme etc.)

Practicable

-

-

Based on low implementation costs, this option has been directly incorporated in recommendations

Reduction of Fire Involvement Frequency (better emergency response, extinguisher types etc.)

Practicable

-

-

Based on low implementation costs, this option has been directly incorporated in recommendations

Note: [1] Please refer to Hazard to Life Assessment Final Draft Report, Section 9.6.3, paragraph 5 at page A12-146

 

12.10                  Cumulative Risk Assessment

 

12.10.1.1      Cumulative risk assessment analyses the combined risks of fatality arising from exposure to hazards due to storage and transport of dangerous goods in various projects being undertaken concurrently.

 

12.10.1.2      The projects that interface with the KTE Project are: the Shatin to Central Link (SCL) Tai Wai to Hung Hom Section (SCL-EWL), the SCL Cross Harbour Section (SCL-NSL), the Central Kowloon Route (CKR) and the widening of the Gascoigne Road Flyover. The projects are either not geographically aligned with the KTE placement (alignment, worksites, magazine site or transport routes) or not chronologically aligned with the blasting programme. Not only is the CKR Project use of explosives planned for the period from Oct 2013 to April 2015, a non-blasting zone is already proposed within the CKR blasting design to avoid impact on both KTE and SCL-EWL.

 

12.10.1.3      Therefore, there is no cumulative risk to be considered according to the current blasting programmes.

 

12.10.1.4      In a worst case scenario the tunnel alignment may encounter potential faults and zones of local soft ground requiring particular construction methods resulting in a slower advance rate possibly prolonging the KTE tunnel blasting programme leading to a potential overlap with the SCL-EWL blasting programme. The maximum cumulative societal risk for a full overlap of the peak year of KTE and peak year of SCL-EWL along the common transport route remains within the ALARP region (as shown in Figure 12.11), and the presented conclusions would still apply. In this worst case the maximum individual risk (IR) for the adjacent magazine sites in TKO Area 137 and the common route has been aggregated. The pier in TKO Area 137 is used for delivery of explosives for other projects however the transport of explosives by Mines Division is out of scope of this assessment, and only the transport of explosives by the appointed contractors of MTR as part of the KTE and SCL-EWL Projects is considered in the cumulative risk assessment.

 

12.10.1.5      As can be seen from Figures 12.9 and 12.10, in a worst case scenario the cumulative individual risk is less than <1E-05, and therefore acceptable according to the risk criterion.

 

12.10.1.6      As can be seen the risk from the combined projects remains within the ALARP region. ALARP assessment has been described for the KTE project in Appendix 12. Similar ALARP assessment is included for the SCL-EWL project for the storage and transport of explosives. Combined ALARP assessment also results in the same conclusion as the individual ALARP assessment.

 

12.11                  Conclusions

 

12.11.1.1      A QRA has been carried out to assess the hazard to life issues arising from the storage and transport of explosives during the construction of the KTE Project.

 

12.11.1.2      The criterion of Annex 4 of the EIAO-TM for Individual Risk is met with regards to the hazards to life posed by the storage and transport of explosives. The assessment results show that the societal risk lies within the ALARP region when compared to the criteria stipulated in the EIAO-TM. A detailed ALARP assessment has been undertaken considering a wide range of mitigation measures and the results show compliance with the ALARP principles provided that the following recommendations are followed.

 

12.12                  Recommendations

 

12.12.1            Specific Recommendations

 

12.12.1.1      Following the ALARP principles, the following recommendations are justified and should be implemented to meet the EIAO-TM requirements:

 

·                The truck design should be improved to reduce the amount of combustibles in the cabin. The fuel carried in the fuel tank should also be minimised to reduce the duration of any fire;

·                The explosive truck accident frequency should be minimized by implementing a dedicated training programme for both the driver and his attendants, including regular briefing sessions, implementation of a defensive driving attitude. In addition, drivers should be selected based on good safety record, and medical checks;

·                The contractor should as far as practicable combine the explosives deliveries for a given work area;

·                Only the required quantity of explosives for a particular blast should be transported to avoid the return of unused explosives to the magazines.  

·                Whenever practicable, a minimum headway between two consecutive truck convoys of 10 min is recommended; and

·                The explosives truck fire involvement frequency should be minimized by implementing a better emergency response and training to make sure the adequate fire extinguishers are used and attempt is made to evacuate the area of the incident or securing the explosive load if possible. All explosive vehicles should also be equipped with bigger capacity AFFF-type extinguishers.

12.12.2            General Recommendations

 

12.12.1            Blasting activities including storage and transport of explosives should be supervised and audited by competent site staff to ensure strict compliance with the blasting permit conditions. The following general recommendation should also be considered for the storage and transport of explosives:

 

·                The security plan should address different alert security level to reduce opportunity for arson / deliberate initiation of explosives. The corresponding security procedure should be implemented with respect to prevailing security alert status announced by the Government; 

·                Emergency plan (i.e. magazine operational manual) shall be developed to address uncontrolled fire in magazine area and transport. The case of fire near an explosives carrying truck in jammed traffic should also be covered. Drill of the emergency plan should be carried out at regular intervals;

·                Adverse weather working guideline should be developed to clearly define procedure for transport explosives during thunderstorm; and

·                The magazine storage quantities need to be reported on a monthly basis to ensure that the two day storage capacity is not exceeded.

12.12.3            Storage of Explosives in Magazine Store

 

12.12.3.1      The magazine should be designed, operated and maintained in accordance with Mines Division guidelines and appropriate industry best practice. In addition, the following recommendations should be implemented:

 

·                A suitable work control system should be introduced, such as an operational manual including Permit-to-Work system, to ensure that work activities undertaken during the operation of the magazine are properly controlled;

·                There should be good house-keeping within the magazine to ensure that combustible materials are not allowed to accumulate;

·                The magazine shall be without open drains, traps, pits or pockets into which any molten ammonium nitrate could flow and be confined in the event of a fire;

·                The magazine building shall be regularly checked for water seepage through the roof, walls or floor;

·                Caked explosives shall be disposed of in an appropriate manner;

·                Delivery vehicles shall not be permitted to remain within the secured fenced off magazine store area;

·                Good housekeeping outside the magazine stores to be followed to ensure combustibles (including vegetation) are removed;

·                A speed limit within the magazine area should be enforced to reduce the risk of a vehicle impact or incident within the magazine area;

·                Traffic Management should be implemented within the magazine site, to ensure that no more than 1 vehicle will be loaded at any time, in order to avoid accidents involving multiple vehicles within the site boundary. Based on the construction programme, considering that 6 trucks could be loaded over a peak 2 hour period, this is considered feasible; and

·                The design of the fill slope close to the magazine site should consider potential washout failures and incorporate engineering measures to prevent a washout causing damage to the magazine stores.

12.12.4            Transport of Explosives

 

General Recommendations

 

12.12.4.1      The following measures should be considered for safe transport of explosives:

 

·                Detonators shall not be transported in the same vehicle with other Class 1 explosives. Separation of vehicles should be maintained during the whole trip;

·                Location for stopping and unloading from truck to be provided as close as possible to shaft, free from dropped loads, hot work, etc. during time of unloading;

·                Develop procedure to ensure that parking space on the site is available for the explosives truck. Confirmation of parking space should be communicated to truck drivers before delivery. If parking space on site cannot be secure, delivery should not commence;

·                During transport of the explosives within the tunnel, hot work or other activities should not be permitted in the vicinity of the explosives offloading or charging activities;

·                Ensure lining is provided within the transportation box on the vehicle and in good condition before transportation;

·                Ensure that packaging of detonators remains intact until handed over at blasting site;

·                Emergency plan to include activation of fuel and battery isolation switches on vehicle when fire breaks out to prevent fire spreading and reducing likelihood of prolonged fire leading to explosion;

·                Use only experienced driver(s) with good safety record; and

·                Ensure that cartridged emulsion packages are damage free before every trip.

Contractors Licensed Vehicle Recommended Safety Requirements

 

12.12.4.2      The following measures are recommended:

 

·                Battery isolation switch;

·                Front mounted exhaust with spark arrestor;

·                Fuel level should be kept as far as possible to the minimum level required for the transport of explosives;

·                Minimum 1 x 9 kg water based AFFF fire extinguisher to be provided;

·                Minimum 1 x 9 kg dry chemical powder fire extinguisher to be provided;

·                Horizontal fire screen on cargo deck and vertical fire screen mounted at least 150mm behind the drivers cab and 100mm from the steel cargo compartment, the vertical screen shall protrude 150mm in excess of all three (3) sides of the steel cargo compartment;

·                Cigarette lighter removed;

·                Two (2) battery powered torches for night deliveries;

·                Vehicles shall be brand new, dedicated explosives transport vehicles and should be maintained in good operating condition;

·                Daily checks on tyres and vehicle integrity;

·                Regular monthly vehicle inspections;

-          Fuel system;

-          Exhaust system;

-          Brakes;

-          Electrics;

-          Battery;

-          Cooling system; and

-          Engine oil leaks.

·                Vehicle log book in which monthly inspections and maintenance requirements are recorded; and

·                Mobile telephone equipped.

Recommended Requirements for the Driver of the Explosives Vehicle:

 

12.12.4.3      The driver shall:

 

·                be registered by the Commissioner of Mines and must be over the age of 25 years with proven accident free records and more than 7 year driving experience without suspension.

·                hold a Driving License for the class of vehicle for at least one (1) year;

·                adopt a safe driving practice including having attended a defensive driving course;

·                pass a medical check and is assessed as fit to drive explosives vehicles; and

·                not be dependent on banned substances.

12.12.4.4      Some of the following requirements may also apply to the vehicle attendant(s).

 

·                The driver is required to attend relevant training courses recognized by the Commissioner of Mines. The training courses should include the following major subjects, but not limited to:

-          the laws and Regulations relating to the transport of explosives; and

-          security and safe handling during the transport of explosives.

·                Attend training courses provided by the explosives manufacturer or distributor, covering the following:

-          explosives identification;

-          explosion hazards; and

-          explosives sensitivity;

-          the dangers which could be caused by the types of explosives;

-          the packaging, labelling and characteristics of the types of explosives;

-          the use of fire extinguishers and fire fighting procedures; and

-          emergency response procedures in case of accidents.

12.12.4.5      The driver should additionally be responsible for the following:

 

·                The driver shall have a full set of Material Safety Data Sheets ( MSDS ) for each individual explosive aboard the vehicle for the particular journey;

·                The MSDS and Removal Permit ( where applicable ) shall be produced to any officer of the Mines Division of CEDD upon request;

·                A card detailing emergency procedures shall be kept on board and displayed in a prominent place on the drivers door;

·                Before leaving the magazine the driver together with and/or assisted by the shotfirer shall check the following:

-          Packaging integrity and labelling;

-          Check that the types and quantities of explosives loaded onto the vehicle are as stipulated in the Removal Permit(s);

-          Check that the explosive load does not exceed the quantities stated in the removal permit;

-          Check the condition and integrity of the cargo compartment or box;

-          Check that detonators are not loaded in the explosives cargo compartment and vice versa;

-          Check that the cargo is secured and cannot be damaged during the delivery;

-          Ensure that the appropriate placards and a red flag are displayed before leaving the magazine;

-          Be competent to operate all equipment onboard the vehicle including fire extinguishers and the vehicle emergency cut-off switches;

-          Prohibit smoking when the vehicle is loaded with explosives;

-          When explosives are loaded, ensure the vehicle is not left unattended;

-          Be conversant with emergency response procedures.

Specific Recommended Requirements for the Explosives Vehicle Attendants:

 

·                When the vehicle is loaded with explosives, it shall be attended by the driver and at least one (1) other person authorized by the Commissioner of Mines. The vehicle attendant shall:

-          Be the assistant to the driver in normal working conditions and in case of any emergency;

-          Be conversant with the emergency response procedures; and

-          Be competent to use the fire extinguishers and the vehicle emergency cut-off switches.

·                One of the vehicle attendant(s) should be equipped with mobile phones and the relevant MSDS and emergency response plan.

12.12.5            Type of Explosives & their Disposal

 

12.12.5.1      For explosives selection, the following should be considered

 

·                Cartridged Emulsions with perchlorate formulation should be avoided; and

·                Cartridged Emulsions with high water content should be preferred.

12.12.5.2      If disposal is required for small quantities, disposal should be made in a controlled and safe manner by a Registered Shotfirer.

 

12.13                  References

 

[1]        MTR, Consultancy Agreement No. NEX/2203, Kwun Tong Line Extension Preliminary Design, “Deliverable 3.25 – Final Preliminary Design Report”, April 2009. (MTR 1)

 

[2]        ERM, Express Rail Link: Hazard to Life Assessment for the Transport and Storage of Explosives, 2009 (ESB-197/2008) (ERM, 2009)

 

[3]        HSC, Selection and Use of Explosion Effects and Consequence Models for Explosives, Advisory Committee on Dangerous Substances, 2000 (ESTC, 2000)

 

[4]        ERM, West Island Line: Hazard to Life Assessment for the Transport Storage and Use of Explosives, 2008 (EIA153/2008) (ERM, 2008)

 

[5]        DNV, The Risk Assessment of the Transport of Explosives in Hong Kong QRA Report, Environmental Protection Department Hong Kong Government, 1997, EPD CE63/94 (DNV, 1997)

 

[6]        United Nations, Recommendations on the Transport of Dangerous Goods – Manual of Tests and Criteria, 4th Revised Edition, 2003 (TDG-Test Manual, 2003)

 

[7]        United Nations, Recommendations on the Transport of Dangerous Goods – Model Regulations, 15th Revised Edition, 2007 (TDG-Model Regulation, 2007)

 

[8]        CEDD, Guidance Note on Requirements for Approval of an Explosives Delivery Vehicle, http://www.cedd.gov.hk/eng/services/mines_quarries/doc/gn_03_edv.pdf (CEDD 2)

 

[9]        CEDD, How to apply for a Mode A Explosives Store Licence, http://www.cedd.gov.hk/eng/services/mines_quarries/doc/mode_a_store.pdf (CEDD 3)

 

[10]      Lands Department, Geographic Information System (GIS) database, http://www.landsd.gov.hk/mapping/en/digital_map/mapprod.htm The latest information on the GIS map of buildings from the Lands Department used in this study comes from 2008 (LD, 2008)

 

[11]      Transport Department, Annual Traffic Census 2007 (ATC, 2007)

 

[12]      Transport Department, "Road Traffic Accident Statistics”, Government of Hong Kong S.A.R, 2007 (and previous years) (TD, 2007a)

 

[13]      Transport Department, Road Traffic Accidents at Junction by Junction Type, Junction Control and Severity 2007, http://www.td.gov.hk/FileManager/EN/Content_1943/07fig2.12e.pdf (TD, 2007b)

 

[14]      UK Health and Safety Executive (UK HSE)’s Explosives Incidents Database Advisory Service (EIDAS)

 

[15]      Incident database retrieved from US Mine Safety and Health Administration (MHSA)

 

[16]      DOCEP, Incident Log Reports retrieved from http://www.docep.wa.gov.au/resourcesSafety/Content/Dangerous_Goods/Incident_log_reports/index.htm (DOCEP)

 

[17]      ACDS, Risk from Handling Explosives in Ports, HSC Advisory Committee on Dangerous Substances, HMSO, UK, 1995 (ACDS, 1995)

 

[18]      EPD, Technical Note: Cost Benefit Analysis in Hazard Assessment, Environmental Protection Department, Rev. January 1996. (EPD, 1996)

 

[19]      MTR, Consultancy Agreement No. NEX/2203, Kwun Tong Line Extension Preliminary Design, “Deliverable 3.7 – Final Blast Risk Report”, March 2009. (MTR 2)

 

[20]      MTR, Consultancy Agreement No. NEX/2203, Kwun Tong Line Extension Preliminary Design, “Working Paper 18 – Ho Man Tin Station Open Cut Scheme”, April 2009. (MTR 3)

 

[21]      MTR, Consultancy Agreement No. NEX/2203, Kwun Tong Line Extension Preliminary Design, “Shatin to Central Link (East West Link) and Kwun Tong Line Extension – Location Study for Explosives Magazine”, 19 April 2010. (MTR 4)


 

 

 

   26