14.1.1.1
This EIA study predicted
that, with the implementation of the recommended mitigation measures, the KTE
project would be environmentally acceptable with no adverse residual impacts on
the population and environmentally sensitive resources. Table 14.1 summarises
the environmental outcomes and benefits that accrued from the environmental considerations
and analysis during the EIA process and the implementation of environmental
control measures of the KTE project. The
requirements for the EM&A programme have been recommended, where necessary,
to check on project compliance with environmental legislation and standards.
Table 14.1: Summary of Key
Environmental Outcomes
Area/Issue |
Environmental Outcomes and Mitigation
Measures |
The KTE Project |
The KTE project is an
extension of the KTL and comprises a new railway extension, approximately 2.6km
long, running from the end of the existing KTL twin overrun/ refuge siding
tunnels south of YMT Station to the end of the overrun/ refuge siding beyond
the new terminus station at Whampoa. A
crossover is located immediately east of HOM Station with a turnback siding
immediately beyond the crossover. This allows every second train to turnback
through HOM Station to maintain the current peak headway. At WHA Station a single refuge siding will
be provided immediately beyond the end of the platform. The existing terminus at YMT Station will
revert to a through station. The
distance between centrelines of YMT Station and HOM Station platforms is
approximately 1,750m and between HOM Station and WHA Station platforms is
approximately 830m. As the spacing
between YMT Station and HOM Station is greater than the normal established
principle of 1km, a mid-point Emergency Access Point (EAP) and ventilation
building is proposed. The major components of
the project will include the following: ·
Running tunnels from
YMT Station (existing overrun tunnels) to HOM Station; ·
Running tunnels from HOM
Station to WHA Station; ·
HOM Station with
associated structures and provisions including station structures and
provisions for interchange with the SCL; ·
WHA Station with
associated structures and provisions; and ·
The WAB and ventilation
structure at Club de Recreio; and ·
A purpose designed and
built temporary explosives storage magazine at Tseung Kwan O Area 137. |
Environmentally
Friendly Design Recommended |
There are no Declared
Monuments within the KTE project area, and all areas with archaeological
potential and graded historical buildings within the project boundary have
been identified in an early stage of the preliminary design. The KTE project has been designed to avoid
causing direct physical impacts on these heritage resources. Different types of
ventilation buildings and shafts have been designed for provision in different
areas. Low-height ventilation buildings and shafts have been assigned to the
areas which are considered to be visually sensitive. Their locations have been carefully selected
in order to minimise the impacts to the nearby environmental sensitive
receivers. The entire KTE alignment
will be operated underground and will avoid air-borne noise impacts. Suitable trackform have been provided in
the design to minimise the ground-borne train noise impacts on the adjacent
NSRs. The selection of a shortest
practicable tunnel KTE alignment will minimise the generation of excessive
excavated C&D materials and tunnel wastewater during the design stage,
e.g. limited construction works sites in urban area approved for the project
construction and related secondary air and visual impacts, reuse in other
external projects etc. These C&D
materials will be arranged to be re-used on-site and off-site at other
concurrent projects in Hong Kong, e.g. the reclamation for the Hong Kong –
Zhuhai – Macao Bridge Border Crossing Facility in north Lantau, etc., to
minimise the potential impact to the existing public fills and landfills in No modification of the
existing seawall structures and marine works including piling are required
for the construction and use of the barging point or the purpose designed and
built temporary magazine site, hence avoiding possible water quality and
marine ecological impacts. A fast-track
construction programme has been designed to shorten the duration of
construction works and hence minimise the possible environmental impacts posed
on the nearby environmental sensitive receivers. |
Population and Environmentally Sensitive Areas
Protected |
With the adoption of environmentally
sensitive design, the major environmental sensitive receivers will be protected.
Most of the site locations of ventilation shafts and buildings will be used
as work sites and/or construction shafts/muck-out points during construction in
order to minimise the works areas required as well as disturbance to the
public and environment. As all of the railway
running tracks of the project are underground, there would be no air-borne
train noise impacts on the noise sensitive uses along the KTE alignment. |
Cultural Heritage |
As there are no
Declared Monuments in the study area, no impacts to any Sites of Cultural
Heritage covered by the EIAO are expected during the construction and operational
phases and no specific mitigation measures will be required. |
Landscape and Visual |
Potentially Significant Adverse impacts
to landscape resources during Construction Phase are anticipated at HOM
Station (Slopes adjacent to Following introduction of the above
mitigation measures only one Landscape Character Area demonstrates Impacts
during Construction Phase. Moderate Adverse
impacts to landscape character at Ho Man Tin - Valley Road Estate (LCA-06)
are anticipated. At
Day 1 of Operation Slight Adverse impacts prevail. By Year 10 of Operation Slight Beneficial landscape character impacts
will be evidenced. Despite mitigation measures Significant
Adverse Residual Visual Impacts are anticipated during Construction Phase to
Residents on the south side of Chatham Road North (VSR-R4), Residents grouped
at Wuhu Street and Gillies Avenue (VSR-R5), Residents at Ka Wai Chuen
(VSR-R6), Residents at Shun Yung Street (VSR-R8), Future Residents of HK
PolyU Planned Student Dormitory (VSR-R9), Residents at Valley Road (VSR-R10),
Residents of Whampoa Estate and Garden (VSR-R13), Members and Visitors of
Club de Recreio (VSR-L4), Visitors of Chinese Civil Servants Recreation Club
and Philipino Club (VSR-L6) and Shoppers in Whampoa Garden (VSR-L14).
Operation Phase impacts resulting from resulting above-ground structures and
loss of visual amenity can be effectively mitigated and at Day 1 of Operation
no Significant Impacts prevail. By Year 10 of Operation the most significant
visual impacts envisaged are Moderate Adverse at Residents on the south side
of |
Air Quality |
Potential dust impacts
would be generated from excavation activities, material handling, wind
erosion, spoil removal, material delivery, rock crushing facilities and operation
of the barging point during the construction phase. Fugitive dust impacts
would be controlled by the implementation of dust suppression measures as stipulated
in the Air Pollution Control (Construction Dust) Regulation, good site
practices and proposed mitigation measures. With the implementation of
mitigation measures in the Air Pollution Control (Construction Dust)
Regulation, proposed dust suppression measures, and good site practices, no
1-hour and 24 hour residual impacts would occur. However, some marginal annual average TSP
exceedances would occur at locations around the HOM Station works sites and
Finger Pier works area. The exceedances are marginal,
short-term and in most cases transient and based upon worst case
assumptions. Based upon these factors, the residual
impacts associated with the annual dust exceedances for the KTE project
within the study area would be considered minor and acceptable. |
Air-borne Noise |
Without mitigation, the
air-borne noise levels would be anticipated to exceed the relevant criteria by
up to about 22dB(A) at some NSRs. Mitigation
measures are therefore recommended to reduce the noise levels to within the
EIAO-TM noise criterion, including provision of quieter plants, silencers,
noise barriers, enclosures and insulating fabric and temporary road deck
covers. After these mitigation
measures are adopted, the noise levels at 17 NSRs (5 schools, 12 residential)
would subject to residual impacts of between 1-7dB(A) (or up to 12dB(A) if
criterion during examination is considered); while 1 more school NSR would be
subject to potential exceedances during examination periods only. As such, all practicable noise mitigation
measures will be exhausted to minimise the residual impacts, e.g. good site
practices such as orientating the noisy plant away from the nearby NSRs,
intermittent use of plant, proper fitting of silencers and mufflers on the
construction equipment, avoidance of noisy construction works during the
examination period etc. Residual
impacts have been assessed and concluded to be temporary, reversible and
unlikely to induce public health concern and as such, are considered to be
acceptable. Noise enclosures are
also recommended to be installed at muckout points and rock crushing
equipments. The predicted noise
levels arising from the noisy fixed plant of the project such as ventilation
building and shafts at the NSRs are carefully assessed to comply with the
EIAO-TM criteria provided that the designed maximum allowable SWLs of the
fixed plants are met. Good practices should be considered, such as
orientating louvers away from adjacent NSRs whenever practicable, adopting
silencers, acoustic louvers or enclosures where necessary, etc. |
Ground-borne Noise |
The proposed mitigation
measures for operational ground-borne noise would be reviewed during the
construction stage after the tunnel boring. |
Water Quality |
Water quality impacts
from land-based construction activities would be controlled by implementing
the recommended mitigation measures, such as control measures on site run-off
and drainage from the works sites and barging points to minimise construction
run-off, tunnelling wastewater, and particularly on-site treatment of any
contaminated wastewater prior to discharge.
During the operational
phase, track run-off, tunnel seepage and effluent discharges from stations,
ventilation buildings and maintenance activities would have no adverse water
quality impact provided that mitigation measures are incorporated in the
design. |
Waste Management Implications |
Construction waste
arisings have been identified based on the proposed construction activities
and would comprise C&D materials (including excavated materials,
materials from demolition works and site formation), general refuse from
workforce, chemical waste from maintenance of construction plant and
equipment and sewage from on-site staff and workers. Provided that the identified waste arisings
are to be handled, transported and disposed of using approved methods and the
recommended good site practices are to be followed, adverse environmental
impacts would not be expected during the construction phase. Methods to minimise the
generation of waste have been investigated which focus on the construction
methods of tunnels, ventilation building and shafts, and stations. Under the
condition of limited works sites approved for construction use of the
project, delivery of soft materials for reuse off-site would be considered
and used. Off-site reuse at other projects has been explored, e.g. Hong
Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Boundary Crossing Facilities and
Tuen Mun Chek Lap Kok Link, which would require a substantial amount of
filling materials. With the
implementation of the recommended mitigation measures in Section 10 of this
EIA Report, no adverse environment impacts would be expected. The types of waste
generated during the operation of the KTE project would be general refuse
from the passengers, staff and any commercial operators at HOM Station and
WHA Station, general refuse from the ventilation building and ventilation shafts,
industrial waste from the maintenance activities and chemical waste from
operational activities. The handling,
collection, transportation and disposal practices of the identified waste
generated should follow the current practices at other operating railway
lines and hence would pose no impact. |
Land Contamination |
There was no exceedance
of the RBRGs for all soil and groundwater samples tested and, therefore, no remedial
action would be required. In
accordance with Clause 3.4.5.6 of the EIA Study Brief, if there is potential
contaminated site which is inaccessible for preparing sampling and analysis
during the course of the EIA study, e.g. due to site access problem, the
information summarised in Table 11.5 were provided. |
Hazard to Life |
A QRA has been carried
out to assess the hazard to life issues arising from the storage and
transport of explosives during construction of the KTE project. The assessment results
show that the societal risk lies within the ALARP region when compared to the
criteria stipulated in Annex 4 of the EIAO-TM. The criterion of the EIAO-TM
for Individual Risk is met. An ALARP assessment has been carried out by
identifying all practicable mitigation measures and assessing the cost
effectiveness of each measure in terms of the risk reduction achieved and the
cost of implementing the measures. The location of all
relevant Potentially Hazardous Installations (PHIs) have been reviewed with
regards to the KTE alignment, temporary explosives magazine and other works
areas for both the construction phase and the operation phase of the project.
As neither the overnight storage nor use of explosives for rock blasting is
in close vicinity to a PHI, and no PHI lies within the “hazard zone” of the
transport routes, no PHI requires assessment under the conditions of the
EIA Study Brief. |