6.1.1.1
During
the construction phase of the project, potential air quality issues may arise
from fugitive dust emissions generated by construction activities such as
excavation, backfilling, rock breaking and crushing, stockpiling and
construction vehicle movement. During
the operation phase, as trains to be operated on the project will be
electrically powered, there would be minimal dust emissions. Tunnel ventilation exhausts and emergency
smoke extraction facilities would be carefully positioned to avoid adverse air quality
impacts. Air quality impacts during
operational phase are, therefore, envisaged to be insignificant.
6.2.1.1
A description of the works items of the KTE project
is included in Section
3 of this EIA report, including a summary of works
items in Table 3.1 and details of works sites
and works areas in Table
3.2. The layout
of the proposed railway alignment, stations, and the associated structures are
also provided with
respect to the main works items, which will potentially generate dust to the
environment as summarised below and in Figures 3.1 to 3.10.
·
Excavation and backfilling activities at the
above-ground works sites for YMT Station interfacing (Item 1A), running tunnels
between YMT Station and HOM Station (Items 2A and 2C), HOM Station (Items 3A,
3D, 3I and 3J), and WHA Station (Items 5A, 5C and 5D);
· Blasting activities (at the above ground works sites for HOM Station (Item 3A);
· Loading and unloading of C&D materials at the barging point (works area for Item 6A);
· Wind erosion (all above ground works sites of Items 1A, 2A, 2C, 3A, 3S, 3I, 3J, 5A, 5C and 5D); and
· Rock crushing facilities (One rock crushing facility would be located at the work site for HOM Station (Item 3A) and two others would be located at the barging point (Item 6A)). The rock crushing facilities are Designated Projects under Schedule 2, Part 1, Section G.5 of the EIAO. The rock materials would be transported by trucks to the receiving point of the respective rock crushing facilities for processing. There would be no temporary storage of C&D material at the crushing facilities locations and the material will be processed directly. The crushed rock materials would be transported by trucks to barges for loading and transportation.
6.2.1.2 It should be noted that there would be 2 works areas (above ground works sites for Item 7A) for the formation of the temporary magazine site in TKO Area 137. As no valid Air Sensitive Receives (ASRs) (refer to Section 6.5 for the locations of ASRs) were identified within 500m from the boundary of the temporary magazine site, these works areas have not been covered in the air quality impact assessment. However, watering will be the dust mitigation measure during the site formation of the magazine site. Nevertheless, hard surface will be formed at the temporary magazine site after the site formation so that dust generation is minimised, and no mitigation measure will be required.
6.2.1.3
In addition to the above main works sites, the
barging point and temporary magazine site, there would be off-site works areas
proposed for use as site offices and material storage yards during the
construction period (Table 3.1). As the activities at these works areas would
be minor works during the construction phase, namely for site clearance,
erection of site office structures, open storage of equipment, reinstatement,
etc, no significant dust impacts would be anticipated in these works areas and
they are not covered by the air quality impact assessment.
6.3
Environmental Legislation, Policies, Plans,
Standards and Criteria
6.3.1
Environmental Impact Assessment Ordinance (Cap 499)
6.3.1.1
Reference to the EIAO and the associated EIAO-TM has
been made for the assessment of air quality impacts. Annexes 4 and 12 of the EIAO-TM set out the
criteria and guidelines for evaluating air quality impacts, which requires that
for construction dust impact an hourly averaged Total
Suspended Particulates (TSP) concentration of 500mgm-3 shall not
be exceeded.
6.3.2
Air Pollution Control Ordinance (Cap 311)
6.3.2.1
The principal legislation for controlling air
pollutants is the Air Pollution Control Ordinance (APCO) (Cap 311) and its
subsidiary regulations, which defines the statutory Air Quality Objectives
(AQOs) for 7 air pollutants as shown in Table 6.1. Notifiable
and regulatory works are under the control of the Air Pollution Control
(Construction Dust) Regulation.
Notifiable Works include site formation, reclamation, demolition,
foundation works and superstructure construction for buildings and road
construction.
6.3.2.2
Regulatory works are building renovation, road
opening and resurfacing, slope stabilisation, and other activities including
stockpiling, dusty material handling, excavation, concrete works, etc. The KTE project is expected to include both
notifiable and regulatory works.
Contractors will be required to inform the EPD prior to carrying out the
construction works and implement dust control measures to reduce potential
impacts to the acceptable level.
Table 6.1: Hong Kong
Air Quality Objectives
Pollutant |
Concentration in mg m-3 [1] (ppm) |
||||
1 Hour [2] |
8 Hours [3] |
24 Hours [3] |
3 Months [4] |
1 Year [4] |
|
|
800 (0.3) |
|
350 (0.13) |
|
80 (0.03) |
Total Suspended Particulates
(TSP) |
|
|
260 |
|
80 |
Respirable
Suspended Particulates (RSP) [5] |
|
|
180 |
|
55 |
Carbon Monoxide
(CO) |
30,000 (26.2) |
10,000 (8.7) |
|
|
|
Nitrogen Dioxide
(NO2) |
300 (0.16) |
|
150 (0.08) |
|
80 (0.04) |
Photochemical Oxidants (as
Ozone, O3) [6] |
240 |
|
|
|
|
Lead (Pb) |
|
|
|
1.5 |
|
Notes:
[1] Measured
at 298K (25°C)
and 101.325kPa (one atmosphere).
[2] Not
to be exceeded more than three times per year.
[3] Not
to be exceeded more than once per year.
[4] Arithmetic
means.
[5] Respirable
suspended particulates mean suspended particles in air with nominal aerodynamic
diameter of 10 micrometres or smaller.
[6] Photochemical oxidants are determined by
measurement of ozone only.
6.3.3
Air Pollution Control Ordinance – Control of Emission from Specified
Processes
6.3.3.1
Major stationary air polluters such as power plant,
incinerator and rock crushing plants, which are classified as Specified
Processes (SP) under the APCO, are subject to a more stringent emission
control, as follows:
·
Operation of Stone Crushing Plant in which the processing capacity
exceeds 5000 tonnes per annum and in which stones are subjected to any size
reduction or grading by a process giving rise to dust, not being any works
described in any other specified process.
6.3.3.2
A
license is required for the operation of these processes under Part IV of the ordinance
and the application for a license should be made to EPD. EPD may either grant
or refuse to grant a license subject to whether the applicant can fulfill the
environmental standards to avoid causing air pollution. If EPD decides to grant
the license, a set of conditions will be imposed to ensure the adequate
prevention of the discharge of air pollutant emissions.
6.4.1.1
The KTE project is located in the
6.4.1.2
The 5 year average annual TSP levels of 5 EPD
stations (namely Sham Shui Po, Kwun Tong, Central/Western, Kwai Chung and Tsuen
Wan) as the background level (77.4 ug/m3) and criterion for our
construction dust assessment in the revised EIA report. These stations are considered to represent
the full range of landuses in the KTE project study area, given their built-up
nature, similarity of population characteristics and mix of residential developments
with commercial properties and open space areas, and, therefore, combined,
present a reasonable representation of the background conditions of the study
area.
6.4.1.3
The recent annual average concentrations of air
pollutants (in mg/m3) monitored at these stations are
summarised in Table
6.2 below.
Table 6.2: Recent EPD Air Quality
Monitoring Data at Sham Shui Po, Kwun Tong, Central/Western, Kwai Chung and Tsuen
Wan Stations (2005 to 2009)
EPD Monitoring
Station |
Annual Average (mg/m3) |
|||||
2005 |
2006 |
2007 |
2008 |
2009 |
5-year Average |
|
Sham Shui Po |
83 |
79 |
79 |
81 |
77 |
79.8 |
Kwun Tong |
81 |
75 |
82 |
72 |
70 |
76.0 |
Central/Western |
81 |
78 |
77 |
78 |
73 |
77.4 |
Kwai Chung |
79 |
81 |
85 |
79 |
70 |
78.8 |
Tsuen Wan |
83 |
82 |
79 |
67 |
63 |
74.8 |
Overall Average: |
|
|
|
|
|
77.4 |
TSP
(AQO: 80 mg/m3)
Underlined value denotes exceedance of AQO
6.4.1.4
The average annual TSP concentration of the
monitoring stations between the years 2005 and 2009 has been calculated as 77.4
mg/m3
and this has been used as the background value for assessment.
6.5.1.1
The landuse in the vicinity of the preferred KTE
alignment consists of commercial buildings, hotels, residential premises,
hospitals, educational institutions and open space. Site surveys have been carried out to identify
ASRs within 500m from the site boundary in accordance with Annex 12 of the
EIAO-TM, and the worst affected representative ASRs during the construction
phase will be assessed. The nearest existing ASRs have been
identified and are given in Table
6.3, together
with the proposed assessment heights above ground, and depicted
in Figures 6.1-6.9. All the ASRs
are relevant to the construction phase only.
Table 6.3: Nearest Air Sensitive Receivers
in the Study Area
Ref |
Air Sensitive Receiver |
No. of Storeys |
Assessment Height in mPD |
Distance from Closest Site Boundary (m) |
1 |
|
1 |
7,
10, 15, 20, 25 |
80 |
2 |
Tang’s Mansion |
9 |
8,
11, 16, 21, 26 |
32 |
3 |
|
14 |
7,
11, 16, 21, 26 |
30 |
4 |
|
5 |
17,
20, 25, 30, 35 |
1 |
5 |
Eaton Hotel |
19 |
8,
12, 17, 22, 27 |
50 |
6a |
Diocesan Girls’ |
7 |
9,
12, 17, 22, 27 |
139 |
6b |
Diocesan Girls’ School# |
7 |
10,
13, 18, 23, 28 |
76 |
7a |
|
12 |
17,
21, 26, 31, 36 |
5 |
7b |
|
14 |
17,
21, 26, 31, 36 |
47 |
8b |
Parc Palais Block 3 |
24 |
41,
44, 49, 54, 59 |
151 |
8c |
Parc Palais Block 6 |
24 |
41,
44, 49, 54, 59 |
224 |
9 |
Filipino Club |
2 |
20,
24, 29, 34, 39 |
3 |
10 |
|
2 |
16,
20, 25, 30, 35 |
4 |
11 |
Shun Man House, Oi Man Estate |
20 |
35,
39, 44, 49, 54 |
180 |
12 |
|
6 |
55,
59, 64, 69, 74 |
105 |
13 |
|
4 |
53,
56, 61, 66, 71 |
29 |
14 |
Yee Fu Building |
25 |
16,
19, 24, 29, 34 |
22 |
15 |
|
5 |
10,
13, 18, 23, 28 |
28 |
16 |
Caritas Bianchi |
15 |
7,
11, 16, 21, 26 |
44 |
17 |
Lok Ka House |
7 |
6,
10, 15, 20, 25 |
47 |
18 |
|
8 |
6,
10, 15, 20, 25 |
63 |
19 |
|
20 |
23,
27, 32, 37, 42 |
85 |
20 |
Lok Do Building |
13 |
6,
9, 14, 19, 24 |
10 |
21 |
|
4 |
7,
11, 16, 21, 26 |
50 |
22 |
Hung Hom Government Clinic |
3 |
7,
10, 15, 20, 25 |
76 |
23 |
Block Z, Ka Fu Building, Whampoa Estate |
15 |
6,
9, 14, 19, 24 |
5 |
24 |
Block Y, Ki Fu Building, Whampoa Estate |
15 |
6,
9, 14, 19, 24 |
5 |
25 |
Block I, |
15 |
6,
9, 14, 19, 24 |
8 |
26 |
Block H, On |
15 |
7,
10, 15, 20, 25 |
7 |
27 |
Block 9, Bauhinia Mansions,
Whampoa Garden Site 11 |
14 |
6,
9, 14, 19, 24 |
4 |
28 |
Block 1, |
15 |
6,
9, 14, 19, 24 |
5 |
29 |
Block 13, Bauhinia Mansions, Whampoa
Garden Site 11 |
15 |
6,
9, 14, 19, 24 |
6 |
30 |
Block 5, |
15 |
6,
9, 14, 19, 24 |
5 |
31 |
Block 7, |
15 |
5,
9, 14, 19, 24 |
4 |
32 |
Block 1, Oak Mansions, Whampoa
Garden Site 5 |
15 |
5,
9, 14, 19, 24 |
3 |
33 |
Block 2, Oak Mansions, Whampoa
Garden Site 5 |
15 |
5,
9, 14, 19, 24 |
3 |
34 |
|
7 |
5,
9, 14, 19, 24 |
6 |
35 |
|
7 |
5,
9, 14, 19, 24 |
13 |
36 |
|
6 |
6,
9, 14, 19, 24 |
52 |
37 |
|
6 |
6,
9, 14, 19, 24 |
0 |
38 |
Block 5, |
15 |
6,
9, 14, 19, 24 |
12 |
39 |
Harbourfront Landmark |
57 |
6,
9, 14, 19, 24 |
46 |
46 |
Harbourfront Horizon |
18 |
6,
9, 14, 19, 24 |
14 |
47 |
|
11 |
24,
28, 33, 38, 43 |
41 |
48 |
Metropolis Residence |
11 |
16,
20, 25, 30, 35 |
170 |
49 |
|
1 |
15,
19, 24, 29, 34 |
44 |
52 |
Fire Service Headquarters |
13 |
6,
10, 15, 20, 25 |
164 |
Note: * Reference to Ho Man Tin OZP (S/K7/19)
# The School Redevelopment Project of
Diocesan Girls’
6.6.1.1 Construction of the KTE project would be on-going between 2011 and 2015, with its commissioning in 2015. In addition to the KTE project itself, there are various other projects that are planned to be constructed concurrently and these have been taken into account in the air quality assessment. Details of the KTE project construction programme and the concurrent projects are provided in Section 3 of this EIA Report and summarised below.
·
· Shatin to Central Link – Tai Wai to Hung Hom Section (tentative construction period: 2011-2017) – There are proposed to be the works sites for the cut-and-cover tunnel for the construction of SCL – Tai Wai to Hung Hom Section near Chatham Road North which are in the immediate neighbourhood of the southern end of the works sites for HOM Station of the KTE project as shown in Figures 3.21 and 3.22. Details of the modelling assumptions for the SCL – Tai Wai to Hung Hom Section are provided in Appendix 6.1, including the size of works sites, emission rates, mitigation measures, etc. As a full overlap of construction activities for KTE and Shatin to Central Link – Tai Wai to Hung Hom Section has been assumed, worst case cumulative impacts have been predicted. It should be noted that, in this EIA report, all details in relation to the proposed SCL project are tentative only as it is subject to obtaining government and statutory approvals. The assessments related to the SCL project are based upon the best available information at the time of the submission of this EIA report. SCL is under a separate EIA study and subject to the study requirements of a separate EIA study brief under the statutory processes of the EIAO;
· Shatin to Central Link – Mongkok East to Hung Hom Section (tentative construction period: 2011-2020) – There would be some works sites proposed for the cut-and-cover tunnel of the SCL – Mongkok East to Hung Hom Section near the existing East Rail Line (EAL) adjacent to Princess Margaret Road and Oi Man Estate which are close to the works sites of the KTE project for HOM Station as shown in Figure 3.23. Details of the modelling assumptions for SCL – Mongkok East to Hung Hom Section are provided in Appendix 6.1, including the size of works sites, emission rates, mitigation measures, etc. As a full overlap of construction activities for KTE and Shatin to Central Link – Mongkok East to Hung Hom Section has been assumed, worst case cumulative impacts have been predicted. It should be noted that, in this EIA report, all details in relation to the proposed SCL project are tentative only as it is subject to obtaining government and statutory approvals. The assessments related to the SCL project are based upon the best available information at the time of the submission of this EIA report. SCL is under a separate EIA study and subject to the study requirements of a separate EIA study brief under the statutory processes of the EIAO;
· The planned dormitory of the Hong Kong Polytechnic University (construction period: 2009-2012) – There is currently no detailed information on the construction works available for the assessment and, as such, this concurrent project has not been assessed for any cumulative impacts with the KTE project (Figure 3.19); and
· Essential Public Infrastructure Works (EPIW) for the KTE project (tentative construction period: 2011-2015) – There would be some works sites allocated for the construction of the EPIW including subways and footbridges connecting HOM Station and Oi Man Estate and Ho Man Tin Estate, Public Transport Facilities along Chung Hau Street at the northwest of HOM Station and a covered footbridge stretching from HOM Station over Yan Fung Street, Chatham Road North and above the existing footbridge as shown in Figure 3.24. Details of the modelling assumptions for the EPIW are provided in Appendix 6.1, including the size of works sites, emission rates, mitigation measures, etc.
6.7
Identification of Pollution Sources and
Emission Inventory
6.7.1.1
The running tunnels and station boxes would be
constructed by drill-and-blast, soft ground tunnelling and mechanical
excavation methods along the KTE alignment.
Locations of work sites and works areas for the assessment are shown in Figures 6.1-6.9.
Construction dust would be anticipated to be generated from activities,
such as soil excavation, backfilling, wind erosion, transportation/handling of
C&D materials, blasting, loading and unloading of excavated materials at
barging point, construction of access shafts and tunnel mucking out areas,
etc. It should be noted that C&D
materials will not be stored temporarily at barging point.
6.7.1.2
It would be anticipated that the excavation and
backfilling activities would involve significant quantity of earthworks and
silty material handling, and hence significant dust impacts would be
anticipated at the adjacent ASRs if no appropriate mitigation measures are implemented. The ASRs nearest to the proposed barging
point have also be included in the assessment, which have included ASRs 46, 47,
48, 49 and 52.
6.7.1.3
There would be access shafts at
6.7.1.4
The potential emission sources at the rock crushing
facilities would be the unloading activities (from trucks to receiving point of
the rock crushing facilities) and the discharge point of the dust extraction
systems.
6.7.1.5
The assessment of construction dust impacts has been
carried out based on the following assumptions of the general construction
activities:
· All construction activities at all work sites and areas would be undertaken concurrently in order to assess the worst case situation;
· Heavy construction activities will include site clearance, ground excavation, cut and fill operations, construction of the associated facilities, drill-and-blast, and construction traffic and hauling over the sites;
· For the blasting at HOM Station, tarpaulin covers would be provided on wire mesh covered steel cages to contain the dust. Therefore, the heavy construction emission factor is considered adequate for the Fugitive Dust Model (FDM) in the air quality assessment to address the dust generated from this activity (refer to Section 6.8);
· Wind erosion area of 30% has been assumed at any time for the hourly and daily TSP prediction and 6% at any time for annual TSP. However, to be conservative a 100% active area screening test has been undertaken initially for the short term hourly and daily TSP assessment as detailed in the methodology section below;
· Active operating areas of 30% have been assumed at any time for the hourly and daily TSP predictions and 6% active operating area at any time for annual TSP predictions for all sites other than the barging point where the area of the fixed haul road surface has been assumed. However, to be conservative a 100% active area screening test has been undertaken initially for the short term hourly and daily TSP assessment as detailed in the methodology section below;
· Haul roads within the work sites would be paved and water spraying would be provided to keep the wet condition;
· A three-sided and top cover with water spraying would be provided at the receiving point of the barging point loading and unloading locations;
· The rock crushing facilities including haul road and unloading locations would be enclosed and a fabric baghouse/cartridge filter type dust extraction and collection system or equivalent system with 99% or more dust removal efficiency installed for the treatment of the emissions from rock crushing and screening processes; and
· Construction periods are assumed to be 30 days per month, 6 working days per week and 12 operation hours per day from 0700 to 1900. An addition of 17 public holidays per year with no construction works has also been assumed for the assessment.
6.7.1.6
Dust emission factors for different construction
activities would be extracted from the USEPA “Compilation of Air Pollution Emission
Factors (AP-42)”, 5th edition.
The key assumptions for the calculation of dust emission factors are
summarised in Table 6.4 below.
Table 6.4: Assumptions
for Calculation of Dust Emission Factors
Activities |
Reference
[1] |
Operating Sites (Figures 3.2 – 3.9) |
Equations and Assumptions [1] |
Heavy construction activities including land clearing, ground
excavation, cut and fill operations, construction of facilities, drill-and-blast, mucking out areas, equipment traffic and
hauling over the site areas[2] |
S.13.2.3.3 |
All above ground and open construction and excavation sites |
E = 1.2 tons/acre/month of activity or 2.69Mg/hectare/month of activity |
Wind erosion |
S.11.9, Table
11.9.4 |
Area of 30% for
the hourly and daily TSP prediction and 6% for annual TSP |
E = 0.85
Mg/hectare/yr (24 hour emission) |
Loading and unloading at barging point |
S.13.2.4 |
Barging point |
k is particle
size multiplier U is average wind
speed M is material
moisture content |
Unloading of rock
materials at the receiving point of rock crushing facilities |
S.11.19.2, Table 11.19.2-1 |
Rock crushing
facilities |
E = 0.000008
kg/Mg |
Crushing at rock
crushing facilities |
S.11.19.2, Table 11.19.2-1 |
Rock crushing
facilities |
E = 0.0027 kg/Mg |
Screening at rock
crushing facilities |
S.11.19.2, Table
11.19.2-1 |
Rock crushing
facilities |
E = 0.0125 kg/Mg |
Note:
[1] USEPA Compilation of Air
Pollution Emission Factors (AP-42)
[2] For
blasting at HOM Station, tarpaulin covers would be provided on wire mesh
covered steel cages to contain the dust and therefore, the emission factors
associated with heavy construction has been used for the modelling.
6.7.1.7
The dust emission from construction vehicles and the
loaded/unloaded vehicles movements would be limited to within the confined
works sites and barging point respectively and the equation for Heavy
Construction (as in AP-42 S.13.2.3.3) would take this factor into account. The major dust generating activities at the
barging point would be assumed to mainly originate from the loading/unloading
of C&D materials, which would be controlled with the following measures:
· Road surfaces within barging point areas would be paved;
· Installation of 3-sided screen with top and the provision of water sprays at the discharge points of the barging point;
· Vehicles would be required to pass through designated wheel washing facilities before leaving the barging point; and
· Regular watering would be imposed on exposed surfaces and activities (the amount of water to be used would be 1.8L/m2).
6.7.1.8
The major dust generating activities at the rock
crushing facilities at HOM Station and the
barging point would be assumed to mainly originate
from the unloading of rock materials, crushing and screening processes. The rock crushing facilities would be assumed
to be equipped with the following measures:
·
A dust enclosure with fabric baghouse/cartridge filter type dust
extraction and collection system or equivalent system with 99% or more dust
removal efficiency for the
rock crushing facilities including haul road
and unloading location; and
·
Watering of paved road surfaces
within the area of the rock crushing facilities as good site practice.
6.8.1.1
The assessment approach has been based on the
requirements as specified in the EIA Study Brief (ESB-188/2008). The criteria and guidelines for assessing air
quality impacts as stated in Annexes 4 and 12 of the EIAO-TM have been
followed. The requirements as stipulated
under the Air Pollution Control (Construction Dust) Regulation would be
followed to ensure that construction dust impacts would also be controlled
within the relevant standards as stipulated in the EIAO-TM.
6.8.1.2
The quantitative assessment of construction dust
impacts has been conducted using the Fugitive Dust Model (FDM) as approved by
the EPD, which is a Gaussian Plume model designed for computing air dispersion
model for fugitive dust sources.
Modelling parameters including the dust emission factors, particle size
distribution, surface roughness, etc., are specified in the EPD’s Guideline on
choice of models and model parameters and USEPA AP-42.
6.8.1.3
The density of dust would be assumed to be 2.5g/m3. According to S13.2.4.3 of USEPA AP-42, the
particle size distribution is assumed as 1.25mm, 3.75mm, 7.5mm, 12.5mm and 22.5mm with 7%, 20%, 20%, 18% and 35% respectively. Based upon the nature of the study area of
KTE which is urban but with frequent areas of open space, the average
monitoring data from the latest 5 years (i.e. 2005 to 2009) from EPD’s air
quality monitoring stations in Sham Shui Po, Kwun Tong, Central/Western,
Kwai Chung and Tsuen Wan (Table 6.2) has been adopted as a
representative background concentration.
Based on this, the average TSP background concentration has been
calculated as being 77.4 µg/m3.
A surface roughness of 100cm has been assumed in the model to represent
the terrain where applicable.
6.8.1.4
The latest available sequential meteorological data
for 2008 with at least 90% valid data recorded at King’s Park and Hong Kong
Observatory obtained from Hong Kong Observatory (HKO) will be used to predict
the 1-hour, 24-hour average and annual average TSP concentrations at
representative ASRs. The following
meteorological conditions have been adopted for the calculation of 1-hour,
24-hour and annual average TSP concentrations:
· Wind speed: hourly record of meteorological data from HKO;
· Wind direction: hourly record from meteorological data from HKO;
· Stability class: hourly record from meteorological data from HKO. It should be noted that stability classes A-F have been applied;
· Mixing height: daily record from meteorological data at King’s Park Meteorological Station in Year 2008. The minimum mixing height would be adopted for the mixing height which were undeterminable; and
· Temperature: hourly record of meteorological data from HKO in Year 2008.
6.8.1.5
Hourly, 24-hour and annual average TSP concentrations
at the representative ASRs near the works sites and barging point have been
predicted with the sequential meteorological data. For the unavailable hourly meteorological
data, the FDM has been run as usual but the corresponding modelled results will
be ignored in the assessment.
6.8.1.6
Fugitive dust modelling have been conducted for
heights 1.5m, 5m, 10m, 15m, 20m and 25m above local ground level. The maximum cumulative 1-hour, 24-hour and
annual average TSP concentrations at selected ASRs has been determined and
pollutant contours presented at the worst hit level. A 100x100m grid contour has been used to
investigate the pollutant distribution for the assessment period.
6.8.1.7
The
air quality impact assessment has been carried out in accordance with the
construction programme shown in Appendix 3.1. All the works sites (except those for the
construction of the WHA Station), and works areas would be expected to have
continuous works activities throughout the entire construction period. There will be a barging point at the Hung Hom
Finger Pier, comprising three loading and unloading locations, and it is
proposed that the waste disposal trucks from the KTE project would be directed
to this barging point.
6.8.1.8
As
the WHA Station is severely constrained by the existing infrastructure and
buildings, significant amounts of temporary traffic decking, temporary utility
support and associated temporary traffic management (TTM) schemes will be
required. However, in order to assess
the worst case scenario, the works activities of all stages of TTM have been
assessed at the same time. All works
activities of all stages of TTM for the construction of WHA Station and all
other works sites at Gascoigne Road Rest Garden, the WAB, HOM Station, Fat Kwong
Street Playground and the barging point, have been modelled for the KTE works
at the same time to represent the worst case situation. Detailed calculations
of emission rates are presented in Appendix
6.1.
6.8.1.9
In
terms of the construction programme, it should be noted that the sequencing of
works for each works activity over each works site or area will be determined
by the Contractor and is not known at this stage. However, due to the constrained size of the
works sites and areas and the tight construction programme constraints, it will
be necessary for active construction activities to be undertaken at moving
multiple work faces spread across each site.
Therefore, it is not feasible to identify the exact locations of
individual dust emission sources. As
such, for the long term annual predictions, the dust modelling assessment has
assumed that the dust emissions would be distributed across the whole area of
each site to reasonably represent this mode of working and the dust emissions
rates have been proportioned to produce the effect of 6% active works site. The
justification for the percentage of active works areas for the long terms
assessment is presented in Appendix 6.2.
6.8.1.10
However,
for the barging point at the Hung Hom Finger Pier, the annual 6% active area is
not applied in this case as it is more appropriate to apply the emission rates
detailed in Table 6.4
above to the whole area of the access haul road surface. Applying 100% emissions from the barging
point haul road areas represents a very conservative assumption, in that it
assumes a continuous use of the haul road by traffic for the full construction
period as would be expected if the barging point was being used to full
capacity. The barging point with two
unloading locations on the Finger Pier has been designed with capacity of 10,000
tonnes per day (5,000 tonnes for unloading point), equating to a capacity of
approximately 850 trucks/day.
6.8.1.11
In
terms of the short term hourly and 24-hour periods, it is assumed that a total
works area of 30% on each site would be active at any one time and again active
construction activities to be undertaken at moving multiple work faces spread
across each site. The justification for
the percentage of active works areas for the short is presented in Appendix 6.2.
Based upon this, works activities and plant would
not cover the whole site area nor be concentrated in certain areas of the site
close to ASRs at any time during the construction period. However, notwithstanding that such a scenario
would not be expected to occur, for the short term TSP predictions, in order be
conservative, an initial screening test has been undertaken. The Tier 1 screening test is ultra
conservative and has simulated an absolute worst case situation, whereby the
whole area of each site (that is, 100%) would be active.
6.8.1.12
The
purpose of the absolute worst case Tier 1 screening assessment has been to
highlight areas where construction dust may accumulate and potentially become
an issue. The Tier 1 results have allowed a more focused Tier 2 assessment to
be undertaken at specific hot spot locations.
The focused Tier 2 assessments have been undertaken whereby the
projected actual 30% active works areas for the construction site in question,
is positioned closest to the potentially worst affected ASRs, while emission
from all the other sites remain at 100% as per Tier 1. As for the long term assessment, the
exception to this approach has been the barging point, where the emission rates
have been applied to the whole area of the access haul road surface and not a
30% area.
6.8.1.13
Thus,
the Tier 2 assessment is also very conservative as it assumes that all works
activities with the associated plant would be undertaken in the closest
proximity to the potentially affected ASRs at the same time, which as noted
above would not occur and assumes the barging point would be working at full
capacity throughout the construction period.
6.8.1.14
The
locations and dimensions of the emission sources for the short and long term
assessments of the KTE sites are shown in Appendix
6.1, including detailed calculations of emission rates.
6.8.1.15
For
the concurrent projects, similar assumptions have been made for the
calculations of the emission factors for both wind erosion and general
construction activities for short and long term predictions. The locations and dimensions of the emission
sources of the concurrent projects are shown in Appendix 6.1,
in which detailed calculations of emission rates are also presented. Practical and necessary mitigation measures
have been taken into consideration for the planning of the KTE project to abate
the air pollution impact and alternative construction methods/phasing
programmes have been considered to minimise the constructional air quality
impact. As such, measures such as
regular watering are considered the necessary mitigation for all construction
works, and the unmitigated scenario where no watering is applied has not been
considered.
6.9.1
Unmitigated Results
6.9.1.1
The
maximum predicted unmitigated 1-hour, 24 hour and annual average cumulative TSP
levels are presented in Table 6.5
below. The results show that exceedances
of the relevant Air Quality Objectives (AQOs) are predicted to occur with no
mitigation and, therefore, mitigation measures are required to control dust
impacts.
Table
6.5: 1-hour, 24-hour and Annual
Average Maximum Cumulative Unmitigated TSP Concentrations (µgm-3) at
ASRs (Including Background Level)
Receiver
Reference |
Predicted
Maximum 1-hour Concentration (Criterion:
500µgm-3) |
Predicted
Maximum 24-hour Concentration (Criterion:
260µgm-3) |
Predicted
Maximum Annual Concentration (Criterion:
80µgm-3) |
|
1 |
619 |
248 |
82.1 |
|
2 |
642 |
240 |
82.3 |
|
3 |
1933 |
570 |
86.7 |
|
4 |
542 |
195 |
82.2 |
|
5 |
790 |
246 |
83.1 |
|
6a |
1256 |
284 |
82.6 |
|
6b |
1613 |
298 |
82.7 |
|
7a |
787 |
263 |
83.5 |
|
7b |
737 |
248 |
83.9 |
|
8b |
395 |
161 |
83.1 |
|
8c |
408 |
159 |
84.9 |
|
9 |
1297 |
276 |
83.0 |
|
10 |
1041 |
236 |
83.4 |
|
11 |
1256 |
304 |
98.8 |
|
12 |
1250 |
316 |
102.1 |
|
13 |
1599 |
275 |
92.8 |
|
14 |
7134 |
1452 |
108.6 |
|
15 |
4573 |
1195 |
102.5 |
|
16 |
4212 |
1256 |
99.3 |
|
17 |
4073 |
1017 |
90.0 |
|
18 |
3261 |
740 |
87.6 |
|
19 |
4139 |
586 |
90.5 |
|
20 |
2622 |
775 |
90.4 |
|
21 |
2923 |
357 |
81.8 |
|
22 |
2234 |
369 |
81.6 |
|
23 |
2130 |
763 |
91.9 |
|
24 |
2278 |
1014 |
95.2 |
|
25 |
2288 |
800 |
90.4 |
|
26 |
1841 |
452 |
82.5 |
|
27 |
2452 |
782 |
86.4 |
|
28 |
2858 |
937 |
89.3 |
|
29 |
2516 |
528 |
84.7 |
|
30 |
2643 |
903 |
93.7 |
|
31 |
1641 |
543 |
88.8 |
|
32 |
3300 |
754 |
94.1 |
|
33 |
3499 |
641 |
89.5 |
|
34 |
3252 |
585 |
84.0 |
|
35 |
1690 |
480 |
81.9 |
|
36 |
1045 |
252 |
82.9 |
|
37 |
1885 |
268 |
82.3 |
|
38 |
1653 |
261 |
81.9 |
|
39 |
1293 |
227 |
81.6 |
|
46 |
7406 |
1804 |
123.6 |
|
47 |
5411 |
671 |
103.1 |
|
48 |
3917 |
439 |
85.0 |
|
49 |
16914 |
1009 |
99.4 |
|
52 |
4186 |
835 |
172.2 |
|
Note: |
|
denotes TSP level in excess of criterion |
||
6.9.2
Mitigation Measures
6.9.2.1
The
following specific mitigation measures (Appendix 6.1)
and the proposed dust removal efficiencies that have been assumed in the
modelling to reduce the dust generation from the KTE project
to within the 1-hour (500µgm-3), 24-hour (260µgm-3) and
Annual (80µgm-3) criteria at ASRs, and have been applied for both
short term Tier 1 and Tier 2 assessment and the annual TSP predictions:
(i)
For
the unloading of spoil from trucks at barging point, installation of 3-sided
screen with top and the provision of water sprays at the discharge point would
be provided for an assumed 50% dust suppression. This assumption is based upon USEPA AP-42
Control Techniques for Particulate Emissions form Stationary Sources Part 2
which states that watering alone would have 50% dust removal efficiency. This is, however, considered very
conservative as the barging point would also be provided with a 3 sided
enclosure, which would provide additional dust containment and control which
has not been allowed for in this assumption;
(ii) Watering every working hour for 12 hours a day on exposed soil areas on active works areas and paved haul roads to reduce dust emissions by 91.7%, which is with reference to the “Control of Open Fugitive Dust Sources” (USEPA AP-42). The amount of water to be applied would be 1.8L/m2; and
(iii) The dust removal efficiency of fabric baghouse/cartridge filter type dust extraction and collection system or equivalent for rock crushing activities within an enclosure is assumed to be 99%, with reference to USEPA AP-42.
6.9.2.2
In addition to the above, it is noted that tarpaulin
covers would be provided on wire mesh covered steel cages to contain the dust
generated by the blasting at HOM Station.
6.9.2.3
It should be noted that the three proposed rock
crushing plant facilities at HOM and the barging point are designated projects
under the EIAO as noted in Section 1, and the specific mitigation for these
facilities are as follows:
(i) A dust enclosure with fabric baghouse/cartridge filter type dust extraction and collection system or equivalent system with 99% or more dust removal efficiency for the rock crushing facilities including haul road and unloading location; and
(ii) Watering of paved roads within the area of the rock crushing facility as good site practice.
6.9.2.4
In addition to those measures mentioned above, under
the auspices of the Air Pollution Control (Construction Dust) Regulation, the
Contractor will be required to ensure that dust control measures stipulated in
the Regulation should be implemented control dust emissions. The dust control measures detailed below
shall also be incorporated into the Contract Specification where practicable as
an integral part of good construction practice.
(i) Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather;
(ii) Use of frequent watering for particularly dusty construction areas and areas close to ASRs;
(iii) Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines;
(iv) Open stockpiles shall be avoided or covered. Prevent placing dusty material storage piles near ASRs;
(v) Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations;
(vi) Establishment and use of vehicle wheel and body washing facilities at the exit points of the site;
(vii) Imposition of speed controls for vehicles on unpaved site roads, 8 km per hour is the recommended limit;
(viii) Routing of vehicles and position of construction plant should be at the maximum possible distance from ASRs;
(ix) Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides;
(x) Cement or dry PFA delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line and no overfilling is allowed; and
(xi) Loading, unloading, transfer, handling or storage of bulk cement or dry PFA should be carried out in a totally enclosed system or facility, and any vent or exhaust should be fitted with an effective fabric filter or equivalent air pollution control system.
6.9.2.5
All the mitigation measures are also summarised in
the Environmental Mitigation Implementation Schedule (EMIS) in Section 16.
6.9.3
Mitigated Results
Short Term Dust
Predictions
6.9.3.1
The
maximum predicted 1-hour and 24-hour results of the Tier 1 screening at
representative ASRs in the study area with mitigation measures applied are
shown in Table
6.6 and the modelling results are included in Appendix 6.3. The mitigated Tier 1 screening test 1-hour and
24-hour cumulative (KTE + SCL + other concurrent projects + background)
contours at
1.5m above ground are summarised in Table 6.6 and shown in Figures 6.10-6.17.
6.9.3.2
According
to the predicted cumulative TSP levels at different heights, the predicted
maximum cumulative 1-hour and 24-hour average TSP levels would be at 10m or 15m
above ground for the ASRs near HOM Station because of the elevated work sites
at HOM Station. Therefore, Figures 6.18-6.21 also show the contour plots of the mitigated 1-hour
and 24-hour for cumulative (KTE + SCL + other concurrent projects + background)
at 10m or 15m above ground.
Table 6.6: Tier 1 Screening Test:
1-hour and 24-hour Maximum Cumulative TSP Concentrations (µg/m3) at
ASRs (Including Background Level)
Receiver Reference |
Predicted Maximum 1-hour Concentration (Criterion: 500µg/m3) |
Predicted Maximum 24-hour Concentration (Criterion: 260µg/m3) |
||
1 |
139 |
99 |
||
2 |
140 |
99 |
||
3 |
253 |
128 |
||
4 |
140 |
94 |
||
5 |
167 |
98 |
||
6a |
207 |
105 |
||
6b |
222 |
107 |
||
7a |
176 |
105 |
||
7b |
174 |
103 |
||
8b |
110 |
86 |
||
8c |
108 |
86 |
||
9 |
194 |
104 |
||
10 |
179 |
104 |
||
11 |
169 |
107 |
||
12 |
208 |
98 |
||
13 |
347 |
188 |
||
14 |
361 |
185 |
||
15 |
446 |
202 |
||
16 |
304 |
157 |
||
17 |
317 |
162 |
||
18 |
325 |
169 |
||
19 |
262 |
120 |
||
20 |
289 |
145 |
||
21 |
260 |
120 |
||
22 |
227 |
112 |
||
23 |
248 |
143 |
||
24 |
260 |
164 |
||
25 |
261 |
144 |
||
26 |
224 |
113 |
||
27 |
312 |
146 |
||
28 |
307 |
160 |
||
29 |
280 |
119 |
||
30 |
290 |
154 |
||
31 |
206 |
122 |
||
32 |
343 |
139 |
||
33 |
360 |
132 |
||
34 |
360 |
125 |
||
35 |
185 |
113 |
||
36 |
162 |
92 |
||
37 |
227 |
91 |
||
38 |
227 |
93 |
||
39 |
195 |
88 |
||
46 |
504 |
212 |
||
47 |
132 |
96 |
||
48 |
164 |
107 |
||
49 |
284 |
101 |
||
52 |
270 |
137 |
||
Note: |
|
denotes TSP level in excess of criterion |
|
|
6.9.3.3
The predicted Tier 1 screening test maximum
cumulative TSP levels are detailed in Table
6.6. Table
6.7 shows the predicted Tier 1
screening test maximum TSP levels only for projects under MTR Corporation (i.e.
KTE + SCL, but without other concurrent projects and background). The results indicate that, for the majority
of ASRs, no exceedances of the 1-hour and 24-hour TSP criteria are predicted to
occur at any of the assessed levels above ground would occur, even assuming the
absolute worst case situation where 100% of every works site would be active and
emitting dust. However, the Tier 1
assessment has highlighted that ASR 46, the Harbourfront Horizon, could be
subject to 1-hourly dust impacts. As the
Tier 1 assessment is for screening purposes only and would not represent the
actual on-site situation for the KTE project, a more focused Tier 2 assessment
has been undertaken at ASR 46 based upon the emissions from the Hung Hom Finger
Pier barging point. According to the
contour plots of the mitigated 1-hour and 24-hour TSP levels, there would be no
exceedances at any other locations.
Table 6.7: Tier 1 Screening Test:
1-hour and 24-hour Maximum TSP Concentrations (µg/m3) at ASRs for
Projects under MTR Corporation (KTE + SCL) Only (Not Including Background Level)
Receiver Reference |
Predicted Maximum 1-hour Concentration |
Predicted Maximum 24-hour Concentration |
1 |
51 |
20 |
2 |
53 |
20 |
3 |
173 |
49 |
4 |
51 |
15 |
5 |
81 |
19 |
6a |
113 |
24 |
6b |
127 |
27 |
7a |
82 |
23 |
7b |
70 |
22 |
8b |
24 |
7 |
8c |
23 |
7 |
9 |
93 |
21 |
10 |
83 |
22 |
11 |
30 |
11 |
12 |
18 |
6 |
13 |
19 |
7 |
14 |
257 |
102 |
15 |
314 |
108 |
16 |
199 |
74 |
17 |
238 |
84 |
18 |
248 |
89 |
19 |
166 |
40 |
20 |
211 |
67 |
21 |
166 |
37 |
22 |
138 |
31 |
23 |
170 |
65 |
24 |
183 |
86 |
25 |
183 |
67 |
26 |
146 |
35 |
27 |
222 |
69 |
28 |
219 |
82 |
29 |
202 |
42 |
30 |
213 |
76 |
31 |
129 |
45 |
32 |
255 |
62 |
33 |
272 |
55 |
34 |
272 |
48 |
35 |
108 |
36 |
36 |
74 |
15 |
37 |
140 |
13 |
38 |
139 |
15 |
39 |
108 |
10 |
46 |
426 |
135 |
47 |
54 |
15 |
48 |
83 |
25 |
49 |
207 |
22 |
52 |
192 |
60 |
6.9.3.4
The
focused Tier 2 assessment has assumed that dust emissions would occur from the haul
road only as opposed to the whole site and as such, emission rates have been
applied to the area of the haul road surface. As noted in Section 6.8.1.10
above, this would also represent a very conservative scenario and would be an
over prediction of what the actual dusts emissions that would be expected to
occur.
6.9.3.5
The
maximum predicted 1-hour and 24-hour results for the
representative ASRs for the Tier 2 focused barging point assessment
are presented in Table 6.8 and those contributed only by projects under
MTR Corporation (i.e. KTE + SCL, but
without other concurrent projects and background)
are shown in Table 6.9 below.
The modelling results at the ASRs in the focused study
area are included in Appendix 6.3.
6.9.3.6
In
respect of Tier 2, according to the predicted cumulative TSP levels at
different heights, the predicted maximum cumulative 1-hour average TSP levels
would be at 1.5m above ground for the ASRs near the barging point. Figure 6.22
shows the contour plots of the mitigated 1-hour for cumulative (KTE + SCL +
other concurrent projects + background) at 1.5m above ground.
Table 6.8: Tier 2 Focused Barging
Point Assessment: 1-hour and 24-hour Maximum Cumulative TSP Concentrations
(µg/m3) at ASRs (Including Background Level)
Receiver Reference |
Predicted Maximum 1-hour Concentration (Criterion: 500µg/m3) |
Predicted Maximum 24-hour Concentration (Criterion: 260µg/m3) |
||
46 |
209 |
113 |
||
47 |
131 |
96 |
||
48 |
164 |
107 |
||
49 |
314 |
101 |
||
52 |
184 |
111 |
||
Note: |
|
denotes TSP level in excess of criterion |
|
|
Table 6.9: Tier 2 Focused Barging
Point Assessment: 1-hour and 24-hour Maximum Cumulative TSP Concentrations
(µg/m3) at ASRs for Projects under MTR Corporation Only (KTE + SCL)
(Not Including Background Level)
Receiver Reference |
Predicted Maximum 1-hour Concentration |
Predicted Maximum 24-hour Concentration |
46 |
132 |
32 |
47 |
43 |
15 |
48 |
71 |
25 |
49 |
237 |
21 |
52 |
107 |
34 |
6.9.3.7
As
detailed in Table
6.8 above, the maximum predicted 1-hourly TSP results at
ASR 46 would not be in excess of the criteria and as such, adverse impacts
would not be predicted.
Annual Dust Predictions
6.9.3.8
The maximum predicted annual average
TSP concentrations at representative ASRs in the study area with mitigation
measures applied are shown in Table
6.10 and the modelling results are included in Appendix 6.3. The mitigated annual cumulative (KTE + SCL +
other concurrent projects + background) contours at 1.5m above ground are
provided in Figures
6.23-6.26 at which the predicted cumulative
annual average TSP levels would be at their maximum.
6.9.3.9
According to the predicted TSP levels at different
heights, the predicted maximum annual average TSP levels would be at 10m and
15m above ground for the ASRs near HOM Station due to the elevated work sites
at HOM Station. As such, the contour plots of the mitigated cumulative annual
average TSP levels (KTE + SCL + other concurrent projects + background) at
10m and 15m above ground near HOM Station are
presented in Figures 6.27 and 6.28 respectively.
Table 6.10: Annual Average Maximum Cumulative
TSP Concentrations (µg/m3) at ASRs (Including Background Level)
Receiver
Reference |
Predicted
Maximum Annual Average Concentration |
||
1 |
77.7 |
||
2 |
77.7 |
||
3 |
78.2 |
||
4 |
77.7 |
||
5 |
77.8 |
||
6a |
77.8 |
||
6b |
77.9 |
||
7a |
77.9 |
||
7b |
77.9 |
||
8b |
77.6 |
||
8c |
77.7 |
||
9 |
77.9 |
||
10 |
78.0 |
||
11 |
78.0 |
||
12 |
77.9 |
||
13 |
78.4 |
||
14 |
78.7 |
||
15 |
78.9 |
||
16 |
78.4 |
||
17 |
78.6 |
||
18 |
78.8 |
||
19 |
77.9 |
||
20 |
78.4 |
||
21 |
77.8 |
||
22 |
77.7 |
||
23 |
78.9 |
||
24 |
79.2 |
||
25 |
78.7 |
||
26 |
77.9 |
||
27 |
78.2 |
||
28 |
78.5 |
||
29 |
78.0 |
||
30 |
79.0 |
||
31 |
78.5 |
||
32 |
79.0 |
||
33 |
78.4 |
||
34 |
77.9 |
||
35 |
77.7 |
||
36 |
77.6 |
||
37 |
77.6 |
||
38 |
77.6 |
||
39 |
77.5 |
||
46 |
79.5 |
||
47 |
77.8 |
||
48 |
77.7 |
||
49 |
78.0 |
||
52 |
79.8 |
||
Note: |
|
denotes TSP level in excess of criterion |
|
6.9.3.10
The
predicted maximum cumulative annual average TSP concentrations at
representative ASRs detailed in Table
6.10 indicate that all ASRs are in full
compliance with the criteria. However,
the contour plots shown in Figures 6.25 and 6.26 for HOM Station works sites and
Finger Pier works area, respectively show that exceedances of the cumulative
annual average TSP levels at 1.5m above ground level compared with the AQO
would occur in some locations.
6.9.3.11
Based on the existing landuse at the concerned HOM
Station works sites and the approved Ho Man Tin OZP No. S/K7/20, the concerned
zones of exceedance would cover:
(i)
Green Belt “GB” zone at east of King’s Park High
Level Service Reservoir – as “Green Belt” is not classified as an ASRs, the
dust level above the AQO would not be considered as an exceedance;
(ii)
North of King’s Park High Level Service Reservoir –
this is not classified as ASRs and, as such, the dust level above the AQO would
not be considered as an exceedance;
(iii)
King’s Park High Level Service Reservoir Playground
– this would be an ASR as the people using this area would be sensitive to
potential dust impacts. However, the
dust assessment has been based upon worst case assumptions and the predicted
dust exceedances would be marginal only (approximately 81 µg/m3). In addition, such impacts during the
construction period of the KTE project would be transient as the users would
not be permanently there and only occur when the playground was in use; and
(iv)
Area at the junction of Chung Hau Street and Fat
Kwong Street (ex-Valley Road Estate site) zoned as “R(B)2” Residential (Group
B) – while this is classified as an ASR, there is no known programme for the
development in this area. In addition,
the predicted dust exceedances would be marginal only (approximately 81 µg/m3) and
would not be expected to impose any landuse constraints in this area as any
development is unlikely to be completed and occupied before the end of the KTE
construction period.
6.9.3.12
Based on the existing landuse at the concerned Hung
Hom Finger Pier works areas and the draft Tsim Sha Tsui OZP No. S/K1/25, the
concerned zones of exceedance would cover:
(i)
Portal of
(ii)
Podium of
(iii)
International Mail Centre – this is classified as an
ASR. However, the potential dust impacts during the construction period of the
KTE project the predicted dust exceedances would be marginal only
(approximately 81 µg/m3) and would be
short-term.
6.9.3.13
The maximum predicted annual average TSP
concentrations at representative ASRs in the study area for the MTR Corporation projects (KTE + SCL) (without the background) with mitigation measures applied are shown in Table
6.11 and the modelling results are also included in Appendix 6.3. The annual TSP contours for the MTR
Corporation projects (KTE + SCL) at
1.5m above ground are provided in Figures 6.29-6.32.
6.9.3.14
According to the predicted TSP levels at different
heights, the predicted maximum annual average TSP levels would be at 10m or 15m
above ground for the ASRs near HOM Station due to the elevated work sites at
HOM Station. Figures 6.33-6.34 also show the annual TSP contours for the MTR
Corporation projects (KTE + SCL) at 10m and 15m above ground near HOM Station.
The results show that the contribution from the projects would be small
overall.
Table 6.11: Annual Average Maximum TSP
Concentrations (µg/m3) at ASRs Contributed by the Projects under MTR
Corporation (KTE + SCL) (Not Including Background Level)
Receiver
Reference |
Predicted
Maximum Annual Concentration Projects Contribution |
1 |
0.3 |
2 |
0.3 |
3 |
0.8 |
4 |
0.3 |
5 |
0.4 |
6a |
0.4 |
6b |
0.4 |
7a |
0.5 |
7b |
0.4 |
8b |
0.2 |
8c |
0.2 |
9 |
0.4 |
10 |
0.5 |
11 |
0.4 |
12 |
0.3 |
13 |
0.2 |
14 |
1.3 |
15 |
1.4 |
16 |
0.9 |
17 |
1.2 |
18 |
1.4 |
19 |
0.4 |
20 |
1.0 |
21 |
0.3 |
22 |
0.3 |
23 |
1.5 |
24 |
1.8 |
25 |
1.3 |
26 |
0.5 |
27 |
0.8 |
28 |
1.1 |
29 |
0.6 |
30 |
1.6 |
31 |
1.1 |
32 |
1.6 |
33 |
1.0 |
34 |
0.5 |
35 |
0.3 |
36 |
0.2 |
37 |
0.2 |
38 |
0.2 |
39 |
0.1 |
46 |
2.1 |
47 |
0.4 |
48 |
0.3 |
49 |
0.6 |
52 |
2.4 |
6.10.1.1 No exceedances of the 1-hour and 24-hour TSP levels are predicted to occur at any of the ASRs in the study area with the recommended mitigation measures applied.
6.10.1.2
However, there are some marginal exceedances of the AQO for the
cumulative annual average TSP levels for the areas adjacent to the HOM Station
works site and Finger Pier works area would occur according to the respective
contour plots.
6.10.1.3
The exceedances are marginal, short-term and in most cases transient and
based upon worst case assumptions. In
addition, based upon the trend of decreasing background TSP levels being
recorded at the EPD monitoring station, it is reasonable to assume that when
construction of the KTE project commences in 2011, the total predicted TSP
levels (project plus background) could be lower than predicted as the
background levels reduce and compliance with the AQO could occur at that
time. However, it is considered that the
maximum practicable measures to reduce residual impacts have been made that
such residual impacts may only occur on some occasions and for the short term
only.
6.10.1.4
The magnitude of the residual impacts have been assessed in accordance
with Section 4.4.3 of the EIAO-TM and detailed in Table
6.12 below.
Table 6.12: Assessment of Residual Impacts
from Annual Construction Dust
Criteria |
Assessment |
Effects on public health and
health of biota or risk to life. |
The dust generated during the
construction works are unlikely to contain a significant proportion of fine
particulates (less than 10 µm) which are deemed to the respirable and
therefore will have negligible potential to affect health if breathed
in. In addition, about 99% of inhaled
particulate matter is considered to be either exhaled or trapped in the upper
areas of the respiratory system and expelled and as such, would be deemed to
be more of a nuisance than a health risk. |
Magnitude of the adverse
environmental impacts. |
The contribution of the project to
dust levels in the area is relatively minor, being <3% based on the AQO
for annual average TSP level at all ASRs.
As such, the KTE project is not anticipated to contribute to cumulative construction dust impacts with other projects. |
Geographic extent of the adverse
environmental impacts. |
The geographic extent of the
adverse impacts from dust will not be large and is anticipated to be limited to within about 150m
from the KTE barging
point works
area. |
Duration and frequency of the
adverse environmental impacts. |
The construction dust impacts of the KTE
project will
be of short to moderate duration and, therefore, temporary and
reversible. |
Likely size of the community or
the environment that may be affected by the adverse impacts. |
As the impacts will be confined to
a relatively small area, only a few ASRs in the immediate vicinity will be
temporarily affected. |
Degree to which the adverse
environmental impacts are reversible or irreversible. |
Construction phase
impacts should be reversible. |
Ecological context. |
Not applicable |
Degree of disruption to sites of
cultural heritage. |
Not applicable |
International and regional
importance. |
The impacts are localised and not
of international and regional importance. |
Likelihood and degree of
uncertainty of adverse environmental impacts. |
The impacts predicted are based
upon worst case assumptions and modelling parameters and as such, would not
occur to the extent predicted on all occasions. However, the assessment has been made using
approved mathematical modelling techniques and the degree of certainty on the
results is high. |
6.10.1.5
Based
upon the above, the following factors should be considered in determining the residual
impacts associated with the annual average dust levels:
· Dust impacts are not predicted to significantly affect health or cause loss of life;
· Predicted impacts are temporary and reversible;
· Impacts are localised and not of international and regional importance;
· The geographic extent of the adverse impacts is confided to a small area around the barging point works site;
· Mitigation measures proposed will reduce the levels of impacts;
· The study area has not shown itself to be fragile or undisturbed;
· The KTE project itself will not trigger cumulative impacts; and
· The contribution from the KTE project to the background levels would be small overall, based upon the worst case assumptions and modelling.
6.10.1.6
Based
upon these factors, the residual impacts associated with the annual dust
exceedances for the KTE project within the study area would be considered minor
and acceptable.
6.11
Environmental Monitoring and Audit
6.11.1.1
The assessment has concluded that mitigated
construction dust impacts are within the acceptable levels and no adverse
residual impacts will occur. However, it
is recommended that, given the close proximity of the ASRs to the works site,
that construction phase environmental monitoring and audit (EM&A) is
undertaken to ensure that there are no adverse impacts during the
implementation of the construction activities and ensure that recommended
mitigation measures are implemented.
Further details of the specific EM&A requirements are detailed in Section 13 of this report and in the
EM&A Manual under separate cover.
6.12.1.1
Potential air quality impacts from the construction works for the KTE
project would mainly be related to construction dust from excavation, materials
handling, spoil removal and wind erosion, as well as operation of the rock
crushing facilities and the barging point.
With the implementation of mitigation measures in the Air Pollution
Control (Construction Dust) Regulation, proposed dust suppression measures, and
good site practices, no 1-hour and 24-hour residual impacts would occur. However, some marginal annual average TSP
exceedances would occur at locations around the HOM Station works sites and
Finger Pier works area. The exceedances are marginal, short-term and in most cases transient and
based upon worst case assumptions. Based upon these factors, the residual impacts associated with the
annual dust exceedances for the KTE project within the study area would be
considered minor and acceptable.