7.                              Air-borne Noise

7.1                          Introduction

7.1.1.1              Potential construction air-borne noise impacts will be generated from activities including excavation, cut-and-cover, tunnelling, retaining wall construction, piling, backfilling, road reinstatement and construction of above ground structures, which are anticipated to be in the immediate vicinity of the noise sensitive receivers (NSRs) especially the residential buildings in Whampoa and institutional uses in Yau Ma Tei.  In addition, loading / unloading of construction materials at the barging point at Hung Hom Finger Pier, will also be potential sources of noise impact affecting NSRs nearby.

7.1.1.2              During the operation of railway systems, operational air-borne noise impacts will be generated from the fixed plant noise sources associated with the stations and ventilation shafts etc.  All of these fixed plant noise sources (as well as other similar noise sources) have been identified and assessed; including potential cumulative impacts.  This has allowed the fixed plant noise levels (and maximum sound power levels) to be determined and mitigated where necessary.

7.2                          Project Background

7.2.1.1              A description of the KTE project can be found in Section 3 of this EIA report with the layout of the proposed railway alignment, stations, and the associated structures.  During the construction phase, air-borne noise issues may arise due to the use of powered mechanical equipment (PME) for various works activities including the establishment and reinstatement works with respect to the works items listed in Table 3.1:

·                YMT Station Interface (works site for Item 1A);

·                Running Tunnels from YMT Station to HOM Station (works sites for Items 2A, 2C and 2D);

·                HOM Station (works sites for Items 3A-3C, 3E-3G and 3I-3K);

·                Running Tunnels from HOM Station to WHA Station (works sites for Item 4A);

·                WHA Station (works sites for Items 5A-5E); and

·                Hung Hom Finger Pier Barging Point (works areas for Item 6A).

7.2.1.2              Rock crushing facilities will also be in operation during the construction phase.  One rock crushing facility would be located at the work site for HOM Station (Item 3A) for a period of 19 months and two others would be located at the barging point (Item 6A) for 29.5 months of the construction period.  The rock crushing facilities are Designated Projects under Schedule 2, Part 1, Section G.5 of the EIAO. 

7.2.1.3              Construction noise may also arise from site formation works at the temporary magazine site at TKO Area 137.  There are no noise sensitive receivers within 300m of the temporary magazine, and therefore it is not included in the assessment.

7.2.1.4              During the operational phase, there would be no air-borne railway noise impacts as the entire KTE alignment would be underground.  Only fixed plant noise sources would arise from the tunnel ventilation building at Club de Recreio, and ventilation shafts and station facilities at HOM Station and WHA Station.

7.3                          Environmental Legislation, Standards and Guidelines

7.3.1                    Background

7.3.1.1              The Noise Control Ordinance (NCO) and the EIAO provide the statutory framework for noise control.  Assessment procedures and standards are set out in the technical memoranda (TM) given below.

·                The TM on EIA process (EIAO-TM);

·                The TM on Noise from Construction Work other than Percussive Piling; (GW-TM);

·                The TM on Noise from Percussive Piling (PP-TM);

·                The TM on Noise from Construction Work in Designated Areas; (DA- TM); and

·                The TM for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (IND-TM).

7.3.1.2              Any noise from percussive piling is controlled by the PP-TM and an application to EPD for a Construction Noise Permit (CNP) would be required.

7.3.2                    Construction Phase

Noise Standards for Non-restricted Hours

7.3.2.1              Daytime construction noise excluding percussive piling between the hours 0700 and 1900 on weekdays, i.e. non-restricted hours, is controlled under the EIAO.  Annex 5 of the EIAO sets out the construction noise assessment limits, which are Leq(30 min) 75dB(A) for domestic premises and hotels, and Leq(30 min) 70dB(A) during normal hours for educational institutions including kindergartens (65dB(A) during examination periods), nurseries and all other places where unaided voice communication is required.  The recommended noise standards are summarised in Table 7.1 below.

Table 7.1:    Daytime Construction Noise Limit

Uses

Noise Standard

(Leq, 30 min dB(A))

Domestic premises, hotels and hostels

75

Educational institutions, kindergartens, nurseries and all others where voice communication is required

70

(65 during examination period)

Note:      The above criteria apply to noise sensitive uses which rely on open window for ventilation and should be viewed as the maximum permissible noise levels assessed at 1m from the external façade.

Noise Standards for Restricted Hours

7.3.2.2              Between 1900 and 0700 hours and all day on Sundays and public holidays, activities involving the use of PME for the purpose of carrying out construction work is prohibited unless a CNP has been obtained.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the NSRs.  ANLs are assigned depending on the Area Sensitivity Ratings (ASRs).  The ASRs are determined based on the best available information at this stage and are unlikely to be significantly different at the time of project implementation unless there are substantial changes such as building redevelopment or land use changes in the near vicinity of the NSRs.  However, nothing in this report shall bind the Noise Control Authority in the context of law enforcement against any noise sources being assessed.  The corresponding basic noise levels (BNLs) for evening and night-time periods are given in Table 7.2.

Table 7.2:    Construction Noise Criteria for Activity other than Percussive Piling

Time Period

Basic Noise Levels (BNLs), dB(A)

ASR ‘A’

ASR ‘B’

ASR ‘C’

Evening (1900 to 2300 hrs)[a]

 

60 (45)

65 (50)

70 (55)

Night-time (2300 to 0700 hrs)

45 (30)

50 (35)

55 (40)

 

                        [a] Includes Sunday and Public Holidays during daytime and evening.

                        Figures in brackets are BNLs for Specified Powered Mechanical Equipment (SPME) construction       work in designated areas.

7.3.2.3              As noise in restricted periods is covered by the NCO, it is not assessed further in this EIA under the EIAO and despite any reference made in this EIA Report on construction noise aspects during restricted periods, there is no guarantee that a CNP will be issued for the project construction.  The Noise Control Authority will consider a well justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TM issued under the Noise Control Ordinance.  The Noise Control Authority will take into account contemporary conditions/situation of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in the EIA Report shall bind the Noise Control Authority in making his decision.  If a CNP is to be issued, the Noise Control Authority shall include in it any condition seen fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

7.3.2.4              Under the DA-TM, the use of five types of SPME and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours would require a valid CNP.  The SPME includes a hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker.  The PCW are:

·                Erecting or dismantling of formwork or scaffolding;

·                Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and

·                Hammering.

7.3.2.5              In general, it cannot be presumed that a CNP would be granted for carrying out PCW within a designated area during restricted hours but it may be granted if the relevant ANLs and criteria stipulated in the GW-TM and DA-TM can be met.

7.3.2.6              As defined in the Noise Control Designated Area Plan, the whole KTE alignment and works areas are within the Designated Area.

7.3.2.7              According to the construction programme, all the proposed construction works will be carried out during non-restricted hours.  In case of any construction activities during restricted hours, it is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs.  The Contractor will be required to submit a CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.

Blasting

7.3.2.8              While air-borne (and ground-borne) noise due to blasting is not required to be assessed, if it is unavoidable to undertake blasting during sensitive hours (1900 to 0700 from Monday to Saturday and any time on a public holiday, including Sunday), then noise impacts associated with the removal of debris and rocks have been assessed and mitigation measures recommended to reduce the impact as required.

7.3.2.9              Notwithstanding, the administrative and procedural control of all blasting operations in Hong Kong is vested in the Mines Division of the Civil Engineering and Development Department (CEDD).  The Dangerous Goods (General) Regulations also stipulates that no person shall carry out blasting unless he possesses a valid mine blasting certificate to be issued by the Mines Division of CEDD.  The Superintendent of Mines will review the application on a case-by-case basis before issuing the Mine Blasting Certificate.

7.3.3                    Operational Phase

Fixed Sources

7.3.3.1              The NCO and IND-TM control noise from fixed noise sources such as ventilation shafts, chillers and cooling towers.  For the assessment of impacts from these fixed noise sources, the ASR of the NSRs must be determined in accordance with the IND-TM, and then based on the ASR, the appropriate ANL can be determined.  The ASRs are determined based on the best available information at this stage and are unlikely to be significantly different at the time of project implementation unless there are substantial changes such as building redevelopment or land use changes in the near vicinity of the NSRs.  However, nothing in this report shall bind the Noise Control Authority in the context of law enforcement against any fixed noise sources being assessed.  The ANL is shown in Table 7.3.

Table 7.3:    Acceptable Noise Level for Fixed Plant Noise

Time Period

NCO Criteria

EIAO-TM

ASR ‘A’

ASR ‘B’

ASR ‘C’

ASR

‘A’

ASR

‘B’

ASR ‘C’

Daytime and Evening

(0700-2300 hrs)

60

65

70

55

60

65

Night-time

(2300-0700 hrs)

50

55

60

45

50

55

                        Source – IND-TM

7.3.3.2              It is anticipated that, due to the urban nature of the KTE project, most of the study areas will be significantly affected by traffic activities and as such an ASR of ‘C’ will be mostly allocated.  However, in areas where a lesser traffic influence is anticipated, an ASR of B would be allocated.

7.3.3.3              The ASR is indicative only and the noise from the fixed sources is controlled under Section 13 of the NCO.  The prevailing legislation, practices contemporary conditions and situation of adjoining land use should all be considered in determining noise impact.

7.3.3.4              More stringent criteria for assessing fixed plant are recommended in the EIAO-TM for planning purposes.  The recommended assessment criteria are:

·                Criteria (1): 5dB(A) below the appropriate ANL set out in the IND-TM; and

·                Criteria (2): The prevailing background noise level where this is 5dB(A) below the appropriate ANL (i.e. ANL -5dB(A)).

7.3.3.5              Criteria (2) would be more stringent than Criteria (1) and would generally apply to areas with low ambient noise levels such as rural areas and suburban areas.  The Project areas are densely populated areas strongly influenced by traffic and as noted from site inspections, the prevailing noise levels are unlikely to be 5dB(A) lower than the appropriate ANL.  Thus Criteria 1 has been adopted for this urban Study Area and this will be confirmed during the assessment.

Air-borne Railway Noise

7.3.3.6              During the operational phase, there would be no air-borne railway noise as the entire KTE alignment would be underground.

7.4                          Noise Sensitive Receivers

7.4.1.1              The whole alignment is located within a densely populated urban area with residential buildings and schools, and, therefore, there are a relatively large number of NSRs in the vicinity of the KTE project area.  The existing and future NSRs selected for both construction and operation noise assessment are listed in Table 7.4 and illustrated in Figures 7.1-7.9.  Details of the NSRs are presented in Appendix 7.1.  For specific NSRs, more than one direction will be evaluated.  However, they will be discussed collectively as a single NSR.

Table 7.4:    Representative Air-borne Noise Sensitive Receivers

Ref

Noise Sensitive Receiver

Construction

Operation

5

Alhambra Building

Y

 

6

Methodist College

Y

 

11

Queen Elizabeth Hospital – Specialist Clinic

Y

Y

12

Primary School at 10-12 Wylie Road (Planned Future NSR)#

Y

Y

13a

Parc Palais Block 1

Y

 

13b

Parc Palais Block 3

Y

 

13c

Parc Palais Block 6

Y

 

16

Carmel Secondary School

Y

 

18-1

1/F, Yee Fu Building

Y

Y

18-7

7/F, Yee Fu Building

Y

Y

19

Marigold Mansion

Y

Y

20

Caritas Bianchi College of Careers

Y

Y

21

Lok Ka House

Y

Y

22

Lok Do Building

Y

 

23

Hung Hom Government Primary School

Y

 

27

Block Y, Ki Fu Building, Whampoa Estate

Y

 

28

Block H, On Wah Building, Whampoa Estate

Y

Y

29

Block 9, Bauhinia Mansions, Whampoa Garden Site 11

Y

Y

30

Block 1, Cherry Mansions, Whampoa Garden Site 2

Y

 

31

Block 5, Cherry Mansions, Whampoa Garden Site 2

Y

 

32

Block 13, Bauhinia Mansions, Whampoa Garden Site 11

Y

Y

33

Block 1, Oak Mansions, Whampoa Garden Site 5

Y

Y

34

Fung Kei Millennium Primary School

Y

Y

35

GCEPSA Whampoa Primary School

Y

Y

36

Harbourfront Landmark

Y

 

39

Harbourfront Horizon

Y

 

40

Residential Building, Ho Man Tin Station Development (Planned Future NSR)

 

Y

41

Residential Building, Dormitory for The Hong Kong Polytechnic University (Planned Future NSR)

 

Y

44

Yue Sun Mansion 191A Wuhu Street

Y

 

45

211 Chatham Road North

 

Y

46

Block Q, Ho Wing Building, Whampoa Estate

 

Y

47

Block 7, Bauhinia Mansions, Whampoa Garden Site 11

 

Y

48

Block I, Lok Wah Building, Whampoa Estate

Y

Y

49

Fung Kei Primary School

Y

Y

50

Block 2, Oak Mansions, Whampoa Garden Site 5

Y

Y

51

Block 5, Cotton Tree Mansions, Whampoa Garden Site 7

Y

Y

52

Block 4, Cotton Tree Mansions, Whampoa Garden Site 7

Y

Y

53

Block 8, Bauhinia Mansions, Whampoa Garden Site 11

 

Y

61

Block A, Wylie Court

 

Y

62

Wing Fung Building

Y

 

63

Queen Elizabeth HospitalSchool of General Nursing

Y

 

*          Both 1/F and 7/F of NSR 18 are assessed.  7/F is the lowest level within the Line of Sight of the HOM Station construction site (WS15a) at the start of excavation, while 1/F will be exposed to the HOM Station excavation works only after the slope at Yan Fung Street has been trimmed back.

#          NSR 12 is included in the construction noise assessment as the planned school is anticipated to be completed by 2010 and thus it could be affected by the construction of the KTE.

7.5                          Baseline Conditions

7.5.1.1              The proposed KTE is an extension of the KTL from Yau Mei Tei to Whampoa via Ho Man Tin.  The project site is located in the urban district of Kowloon.  The surrounding land uses mainly comprise a mixture of commercial and residential uses.  Site visits conducted from September 2008 to July 2009 revealed that the NSRs identified within the study area are exposed to the traffic noise along the existing road networks including Gascoigne Road Flyer, Princess Margaret Road and Chatham Road North.  Details of the key noise sources are included in Appendix 7.1.

7.6                          Identification of Environmental Impact

7.6.1                    Construction Phase

Overview

7.6.1.1              The potential source of noise impact during the construction phase of the KTE project would be the use of PME for various construction activities.  As broadly indicated in the construction programme in Appendix 3.2, the construction of the KTE project would be tentatively undertaken from 2010/2011 to 2015.  The key elements involving construction activities to be carried out at ground surface relevant to the construction air-borne noise assessment include:

·                Open-cut station boxes at HOM Station;

·                Cut-and-cover station boxes at WHA Station;

·                Tunnel ventilation building in combination with the WAB at Club de Recreio;

·                Entrance structures/lift entrances of stations;

·                Ventilation shafts of stations; and

·                Entrance adits of stations.

7.6.1.2              Besides the main works sites shown in Figures 7.1-7.9 where major works activities will be undertaken, there are also six works areas as summarised in Section 3 (refer to Table 3.1 and Appendix 3.1).  It should be noted that three of these works areas (WA2a, WA6 and WA15; Figures 7.4, 7.5, 7.6 and 7.9 refers) would be designated for use as site offices and storage of materials only and there would be no use of PME anticipated, except for the initial establishment works.  One of the remaining works areas is designated for use as a barging point in Figure 7.8 (WA14), at which initial site establishment works and loading/unloading of C&D materials would occur.  The last works area is a temporary magazine site shown in Figure 3.10 (WA12a and WA13) which will be used for storage/delivery of explosives.  Since there are no NSRs within 300m from the temporary magazine site, the construction air-borne noise impact was not assessed.

Muckout Points

7.6.1.3              There would be 5 groups of works sites with construction shafts or haul roads through which excavated spoil from tunnelling works would be removed or mucked out (Table 3.2 in Section 3):

·                WS1 (Gascoigne Road Rest Garden) (Figure 7.10);

·                WS7a1 (WAB at Club de Recreio) (Figure 7.11);

·                WS15a (HOM Station) (no dedicated muckout point is assigned);

·                WS26a (Fat Kwong Street Playground) (Figure 7.12); and

·                WS30 and WS33 (WHA Station) (no dedicated muckout points are assigned).

7.6.1.4              Due to the intensity of the construction activities at these locations, specific attention to the construction noise mitigation measures has been made and at all dedicated muckout points enclosures will be installed to mitigate the air-borne noise impact during construction phase which will be discussed in Section 7.9.2.  However, it should be noted that not all NSRs would be shielded by the enclosures due to the existence of openings for the access of trucks.

Station Construction

7.6.1.5              HOM Station and WHA Station will be constructed mainly using the open-cut method and cut-and-cover method, respectively.  No dedicated haul roads or muckout points will be assigned at the station works areas as spoil will be removed through access points which will change in location depending on the process of the works throughout the construction phase.

Tunnel Construction

7.6.1.6              As the tunnel construction would be carried out underground, it would be considered to be fully enclosed and would not induce any air-borne construction noise impacts on the NSRs.

Barging Point

7.6.1.7              The barging point located at Hung Hom Finger Pier would potentially induce noise impacts to the nearby NSRs during delivery and loading of construction and demolition materials throughout the construction phase.

7.6.1.8              The barging point will be used by both KTE and SCL projects and therefore cumulative impact at the barging point will be assessed.

Rock Crushing Activities

7.6.1.9              There will be rock crushing activities to be carried out as part to the KTE project and one rock crushing facilities will be located at WS15a and two at WA14.  The capacity of each rock crusher is anticipated to be about 800ton/hr.  Two of the rock crushers will be located within the barging point in Hung Hom Finger Pier and used by both KTE and SCL projects.  Therefore, cumulative impacts of the rock crushers at the barging point will be assessed.

7.6.1.10          These rock crushing facilities are designated projects under Section G.2 of Part I, Schedule 2 of the EIAO and as such, specific attention to construction noise mitigation measures has been made at these locations to mitigate the potential air-borne noise impacts during their use.  In each case, a full enclosure of the rock crushing activities will be provided (see Figure 3.38).

Drill and Blast Operation and Spoil Removal

7.6.1.11          The tunnel sections of the KTE alignment will largely be excavated by the drill-and-blast method (WS3, WS10, WS28 and WS29 in Table 3.2).  The blasting, as well as the removal of debris and rocks after blasting, would be carried out during non-restricted hours.  The broken rock would be removed from the underground by dump trucks and subsequently transported to the designated barging point at the Hung Hom Finger Pier (WA14).  Nonetheless, it should be noted that no noise assessment would be required for blasting works in this EIA Study.

Key PMEs Identified as Major Noise Sources

7.6.1.12          The key PMEs that would result in elevation of construction noise impact at various works sites are shown in Table 7.5, and these are considered to be the dominant noise sources.

Table 7.5:    PMEs Identified as Major Noise Sources

Name of PMEs

SWL of the PME, dB(A)

Rock Drill

123

Breaker

122

Scraper

119

Rock Crusher †

118

Tractor

118

Dump Truck

117

Bulldozer

115

Breaker, mini-robot mounted

115

Piling, vibrating hammer

115

Saw/groover, concrete (petrol)

115

Compressor and Pneumatic Drilling Rig

114

      SWL for Rock Crusher is made with reference to the approved EIA Report for West Island Line

7.6.2                    Operational Phase

7.6.2.1              Air-borne operational noise will be generated by fixed plant sources such as the ventilation shafts, chillers and coolers.  Other building services equipment, such as pumps, transformers, emergency generators will be located within plant rooms which would be located underground or at least fully enclosed.

7.6.2.2              There are 5 groups of ventilation shafts for HOM Station, 5 groups for WHA Station and 1 group combined with the WAB at Club de Recreio.  Detailed locations are shown in Figures 7.13 – 7.19 and are listed as follows:

·                VSH-1a, VSH-1a-1 and VSH-1b – Tunnel Ventilation Shaft located at Entrance of HOM Station at Yan Fung Street.  VSH-1a and VSH-1b are two ventilation shafts for Tunnel Ventilation.  VSH-1a has an addition louver facing Yan Fung Street.  Both ventilation shafts are oriented towards the same direction and their cumulative impacts were considered separately;

·                VSH-2 – Cooling Tower Intake & Exhaust located at Entrance D of HOM Station at Yan Fung Street.  VSH-2 comprises two groups of louvers, the intake and exhaust for the cooling tower.  As both groups of louvers are oriented towards the same direction, their cumulative impacts were considered and assessed as one single group;

·                VSH-3 – Ventilation Shaft located at Entrance C of HOM Station facing Chatham Road North.  VSH-3 is the Station Ventilation Shaft located next to the cooling tower intake and exhaust.  The louver follows the station outline and resulting in facing three directions.  Their cumulative impacts were considered separately;

·                VSH-4 – Ventilation Shaft next to VSH-3.  VSH-4 is a ventilation shaft between VSH-3 and VSH-5 facing Chatham Road North;

·                VSH-5 – Tunnel Ventilation Shaft located at the south end of the station.  VSH-5 is a ventilation shaft facing Chatham Road North;

·                VSH-6 – Elevated Ventilation Shaft located at Entrance B of the station.  VSH-6 is a ventilation shaft facing Chatham Road North located above VSH-5;

·                VSH-7 – Station Ventilation Shaft located under Entrance B of the station.  VSH-7 is a ventilation shaft under the footbridge of Entrance B facing north in an opposite direction to VSH-8.

·                VSH-8 – Station Ventilation Shaft located under Entrance B of the station.  VSH-8 is a ventilation shaft under the footbridge of Entrance B facing south towards Winslow Street & underpass.

·                VSH-9 – Station Ventilation Shaft located at the south end of the station.  VSH-9 is a ventilation shaft facing south towards Winslow Street & underpass.

·                VSH-10 – Station Ventilation Shaft located at the south end of the station.  VSH-10 is a ventilation shaft facing south towards Winslow Street & underpass.

·                VSH-11 – Station Ventilation Shaft located at the south end of the station.  VSH-11 is a ventilation shaft facing south towards Winslow Street & underpass.

·                VSW-1 – Integrated with Entrance A at Hung Hom Road adjacent to On Wah Building.  VSW-1 is a ventilation shaft with multiple louvers facing South-eastward and North-westward affecting On Wah Building and Bauhinia Mansions.

·                VSW-2 – Integrated with designated emergency entrance at Shung King Street adjacent to Whampoa Plaza.  VSW-2 is a ventilation shaft with multiple louvers facing North-eastward and North-westward affecting Block 8 and 13 of Bauhinia Mansions.

·                VSW-3 –Standalone ventilation shaft at Tak Ting Street between Whampoa Plaza and SKH Fung Kei Millennium Primary School.  VSW-3 is a standalone ventilation shaft construction with multiple louvers in North-eastward and South-eastward facing SKH Fung Kei Millennium Primary School.

·                VSW-4 – Integrated with Entrance B2 at Tak On Street outside GCE Past Student’s Association Whampoa Primary School.  VSW-4 is a ventilation shaft integrated with Entrance B2 with a louver facing north-westward affecting Block 1 and Block 2 of Oak Mansions.

·                VSW-5a and VSW-5b – A pair of standalone ventilation shafts outside Harbourfront Landmark.  VSW-5 is a pair of ventilation shafts located outside Harbourfront Landmark next to the southern end of Wan Hoi Street with louvers in all directions affecting Block 5 of Cotton Tree Mansions.  As Harbourfront Landmark is likely to be out of the line of sight of the ventilation shaft, it is not considered affected by the vent shaft and thus not included in the assessment.

·                VSWAB-1 to VSWAB-10 – Integrated with the WAB in Club de Recreio.  VSWAB is a group of ventilation shafts integrated with the WAB at Club de Recreio with multiple louvers in all directions.

7.7                          Concurrent Projects

7.7.1.1              Construction of the KTE project would be on-going between early 2011 and 2015 with its commissioning in 2015.  In addition to the KTE project itself, there are various other projects that are planned to be constructed concurrently and these have been taken into account in the construction air-borne noise assessment.

7.7.1.2              The assessment of the cumulative impacts has been based on the best available information during the time of submission and any changes to the programmes of the concurrent projects will be reflected in the subsequent submissions for those projects.  Details of the KTE project construction programme and the concurrent projects have been provided in Section 3 of this EIA Report and summarised below:

·               The planned dormitory of the Hong Kong Polytechnic University (construction period: 2009-2012) – There is currently no detailed information on the construction works available for the assessment and, as such, this concurrent project has not been assessed for any cumulative impacts with the KTE project (Figure 3.19);

·               Central Kowloon Route (CKR) – According to the HyD (refer to Appendix 3.3), the construction programme and commissioning time of CKR are under review, and the types of construction works and the respective construction plant inventories within the construction period are not available yet;

·               Shatin to Central Link (SCL) – Tai Wai to Hung Hom Section (tentative construction period: 2011-2017) – There are proposed works sites for the cut-and-cover tunnel for the construction of SCL – Tai Wai to Hung Hom Section near Chatham Road North which are in the immediate neighbourhood of the southern end of the works sites for HOM Station of the KTE project as shown in Figures 3.21 and 3.22.  The assessment of the cumulative impacts for SCL has been based on the best available information during the time of submission and any changes to the programme will be reflected in the subsequent submissions for this project.  In addition, as SCL – Tai Wai to Hung Hom Section will also share the same barging point at Hung Hom Finger Pier cumulative construction air-borne noise impact at Harbourfront Horizon has also been assessed;

·               Shatin to Central Link – Mongkok East to Hung Hom Section (tentative construction period: 2011-2020) – There would be some works sites proposed for the cut-and-cover tunnel of the SCL – Mongkok East to Hung Hom Section near the existing East Rail Line (EAL) adjacent to Princess Margaret Road and Oi Man Estate which are close to the works sites of the KTE project for HOM Station as shown in Figure 3.23.  The assessment of the cumulative impacts for SCL has been based on the best available information during the time of submission and any changes to the programme will be reflected in the subsequent submission for this project.  In addition, as SCL – Mongkok East to Hung Hom Section will also share the same barging point at Hung Hom Finger Pier cumulative construction air-borne noise impact at Harbourfront Horizon has also been assessed; and

·               Essential Public Infrastructure Works (EPIW) for the KTE project (tentative construction period: 2011-2015) – There would be some works sites allocated for the construction of the EPIW including subways and footbridges connecting HOM Station and Oi Man Estate and Ho Man Tin Estate, Public Transport Facilities along Chung Hau Street at the northwest of HOM Station and a covered footbridge stretching from HOM Station over Yan Fung Street, Chatham Road North and above the existing footbridge as shown in Figure 3.24.

7.7.1.3              The EPIW involves 4 main components:

·               Two connections to both Oi Man Estate and Ho Man Tin Estate (including the subway from HOM Station across Chung Hau Street and the covered walkway along Chung Hau Street, Chung Yi Street and Fat Kwong Street) and the associated slope stabilisation works;

·               Public transport facility and lay-bys at Chung Hau Street; and

·               Passageway and covered footbridge over Chatham Road North and connection to Wuhu Street.

7.7.1.4              However, as there are no NSRs identified for construction air-borne noise assessment in the close proximity of the works site, the EPIW for Connections to Oi man Estate and Ho Man Tin Estate have not been included in the assessment for cumulative construction air-borne noise impacts.

7.8                          Assessment Approach

7.8.1                    Construction Phase

7.8.1.1              In accordance with the EIAO-TM, the methodology outlined in the GW-TM has been used for the construction noise assessment.  The general approach is summarised below:

·                Locate the NSRs which would most likely be affected by the noise from construction works;

·                Determine the items of PME for each discrete construction activity, based on the available information or agreed plant inventories;

·                Assign sound power levels (SWLs) to the proposed PME according to the GW-TM or other sources;

·                Calculate the distance attenuation and screening effects to NSRs from the notional noise source;

·                Predict the construction noise levels at NSRs in the absence of any mitigation measures; and

·                Include a 3dB(A) façade correction to the predicted noise levels in order to account for the façade effect at each NSR.

7.8.1.2              At WHA Station, construction is proposed to be carried out by the cut-and-cover method and is divided into up to 6 phases.  In each phase, construction is divided into a number of sub-zones where construction activities would be on-going.  PMEs are assumed to be spread among the sub-zones.  The details of sub-zoning of works sites, distances between notional sources and all NSRs adopted for calculation are shown in Appendix 7.2.

7.8.1.3              The SWLs of the PME were taken from Table 3 of the GW-TM.  Where no SWL is given in the GW-TM, reference was made to the British Standard 5228: Part 1:2009 Noise Control on Construction and Open Sites and previous similar studies or from other EIA reports or measurements taken in other relevant studies.

7.8.1.4              Groups of PME were assigned for various construction activities of the KTE project and the plant inventory is presented in Appendix 7.3.  The design consultant of the KTE project has confirmed this plant inventory as being practical and adequate for completing the construction works within the scheduled timeframe.  The plant inventory has been provided as one option which is considered technically feasible, and would represent a realistic worst-case scenario for assessment purposes.  In the detailed design stage, the Contractor may propose an alternative plant schedule(s), should it be considered appropriate.  However, the alternative plant inventory should be reviewed and verified by the Environmental Team and Independent Environmental Checker respectively.

7.8.1.5              During excavation for HOM Station and WHA Station, PMEs will be located below station shafts / boxes and be shielded by the pipe pile wall.  Assessment will not consider the change of elevation during excavation and PMEs are assumed to stay at the level where construction works starts.  The typical station shafts / boxes to illustrate the noise reduction of the shielding can be seen in Figure 7.20.  It is anticipated that due to the shielding effect from the pipe pile walls, a -10dB(A) attenuation would be achievable.

7.8.1.6              As the tunnel construction would be carried out underground, it would be considered to be fully enclosed and would induce no air-borne construction noise impact to the NSRs.

7.8.1.7              For NSR 18, as the slope at Yan Fung Street will be trimmed to about 15mPD, no floor at NSR 18 would be permanently shielded by the slope.  The 7/F will be the lowest floor within the line of sight (LOS) of all construction works at HOM Station at the beginning of the construction phase while 1/F would only be exposed after the trimming of the slope was completed.  Thus, both 1/F and 7/F have been assessed to take into account these phases.

7.8.1.8              The WS27 is a ring shaped works site surrounding WS26a and WA15 and in accordance with GW-TM, the notional source shall not consider the whole work site and instead the closest portion to the NSR being assessed has been considered.

7.8.2                    Operational Phase

7.8.2.1              Operation air-borne noise levels were determined by adopting standard acoustic principles.  The formula for calculating the maximum permissible SWLs for the fixed plant is:

SPL = Max SWL - DC + FC - BC

Where:

SPL             = Sound Pressure Level in dB(A)

Max SWL   = Maximum Permissible Sound Power Level in dB(A)

DC              = Distance Attenuation in dB(A) and = 20 log D + 8

FC               = Façade Correction in dB(A) and = 3dB(A)

BC              = Barrier Correction in dB(A)

D                 = Distance in metres

7.8.2.2              A worst-case scenario was assumed where all the fixed plant positioned within the same area are assumed to be operated at the same time using the back-calculation of the maximum SWL.  In addition, the plant was assessed individually where it is not situated close to others.

7.8.2.3              Screening corrections from buildings or other structures and prevailing noise levels obtained by measurements (daytime, evening and night-time) were taken into account in the noise calculations.  For instance, according to the GW-TM, effective barriers could result in noise reduction of 5/10dB(A) for the fixed plant depending on the line of sight of the representative NSRs.  A positive 3dB(A) correction would be added to predicted noise levels at the NSRs due to the façade effect.

7.8.2.4              No corrections have been applied for tonality, intermittency or impulsiveness.  If the noise exhibits any of these characteristics during the operation of the plant, the noise limit should be reduced in accordance with the recommendation given in Section 3.3 of IND-TM.

7.9                          Air-borne Construction Noise Assessment

7.9.1                    Results

7.9.1.1              As illustrated in the construction programme (see Section 3.7), various works activities for KTE would be carried out concurrently during a particular period.  The unmitigated construction noise levels at representative NSRs have been predicted as summarised in Table 7.6.  Detailed results are presented in Appendix 7.4 and the predicted SPL for difference directions of NSRs (if any) are also shown, although they are discussed collectively as a single NSR.

Table 7.6:    Predicted Unmitigated Air-borne Construction Noise Levels for Selected NSRs

NSR

Name

Maximum Predicted Construction Noise Level, dB(A)

EIAO -TM Noise Criteria, dB(A)

NSR 5

Alhambra Building

82

75

NSR 6

Methodist College

86

70/65

NSR 11

Queen Elizabeth Hospital - Specialist Clinic

84

75

NSR 12

Primary School at 10-12 Wylie Road (Planned Future NSR)

83

70/65

NSR 13a

Parc Palais Block 1

76

75

NSR 13b

Parc Palais Block 3

72

75

NSR 13c

Parc Palais Block 6

65

75

NSR 16

Carmel Secondary School

79

70/65

NSR 18-1

Yee Fu Building (1/F)

90

75

NSR 18-7

Yee Fu Building (7/F)

91

75

NSR 19

Marigold Mansion

81

75

NSR 20

Caritas Bianchi College of Careers

85

70/65

NSR 21

Lok Ka House

84

75

NSR 22a-1

Flat A, Lok Do Building

86

75

NSR 22b-1

Flat B, Lok Do Building

NSR 23

Hung Hom Government Primary School

83

70/65

NSR 27a

Block Y, Ki Fu Building, Whampoa Estate

94

75

NSR 27b

NSR 28

Block H, On Wah Building, Whampoa Estate

95

75

NSR 29a

Block 9, Bauhinia Mansions, Whampoa Garden Site 11

90

75

NSR 29b

NSR 30a

Block 1, Cherry Mansions, Whampoa Garden Site 2

91

75

NSR 30b

NSR 31a

Block 5, Cherry Mansions, Whampoa Garden Site 2

91

75

NSR 31b

NSR 31c

NSR 32

Block 13, Bauhinia Mansions, Whampoa Garden Site 11

89

75

NSR 33

Block 1, Oak Mansions, Whampoa Garden Site 5

92

75

NSR 34a

Fung Kei Millennium Primary School

89

70/65

NSR 34b

NSR 35a

GCEPSA Whampoa Primary School

88

70/65

NSR 35b

NSR 35c

NSR 36

Harbourfront Landmark

82

75

NSR 39

Harbourfront Horizon

88

75

NSR 44

Yue Sun Mansion 191A Wuhu Street

77

75

NSR 48a

Block I, Lok Wah Building, Whampoa Estate

97

75

NSR 48b

NSR 49

Fung Kei Primary School

85

70/65

NSR 50

Block 2, Oak Mansions, Whampoa Garden Site 5

92

75

NSR 51a

Block 5, Cotton Tree Mansions, Whampoa Garden Site 7

91

75

NSR 51b

NSR 52

Block 4, Cotton Tree Mansions, Whampoa Garden Site 7

83

75

NSR 62

Wing Fung Building

81

75

NSR 63

Queen Elizabeth HospitalSchool of General Nursing

77

70/65

Notes:    Noise Limits of Leq(30min) for Schools is 70dB(A) for normal periods; 65dB(A) during exam periods.

                Numbers in bold underline (e.g. 80) signify an exceedance of the noise criteria.

                Numbers in italic (e.g. 68) signify an exceedance of the noise criteria during examination periods only.

 

7.9.1.2              Without mitigation, impacts of up to 22dB(A) exceeding the relevant criteria would be anticipated.  The high level of construction noise impacts would be due to the limited separation distance between NSRs and works sites.  The feasibility of providing noise reduction measures to further reduce the noise impacts has been examined and discussed below.

7.9.2                    Mitigation Measures

PMEs Used in Construction Works

7.9.2.1              The results in Table 7.7 above indicate that significant construction noise impacts would be anticipated at most of the NSRs under the unmitigated scenario.  Suitable noise mitigation measures are, therefore, required to minimise the construction noise impact.  The measures applied are presented in Appendix 7.5 which include:

·                Use of quiet plant as per the following list.  These are capable of a 3-14dB(A) reduction of noise;

PME

Reference

SWL, dB(A)

Air Compressor

CNP 003

104

Asphalt Paver

BS D8/24

101

Breaker

BS D8/13

110

Bulldozer

BS D3/27

109

Concrete lorry mixer

BS D6/33

96

Concrete Pump / Grout Pump

BS D6/36

106

Crane

BS D7/114

101

Cutter, circular, steel (electric)

BS D7/78

106

Dump Truck

BS D9/39

103

Backhoe

BS D3/79

101

Generator

CNP 103

95

Vibrating Poker, hand-held (electric)

BS D6/40

98

Rock Drill †

Ref 1

108

Roller, vibratory

BS D8/30

101

Scraper

BS D9/16

108

Water pump (electric)

CNP 283

85

    SWL for Rock Drill is made with reference to the approved EIA Report for Tsim Sha Tsui Station Northern Subway

·                Use of temporary or fixed noise barriers with a surface density of at least 10kg/m2 to screen noise from movable and stationary plant.  With reference to EIAO Guidance Note No.9/2004, noise reduction of 5dB(A) and 10dB(A) can be achieved by noise barriers for movable and stationary plant respectively;

·                Use of enclosures with covers at top and three sides and a surface density of at least 10kg/m2 to screen noise from generally static noisy plant such as air compressors.  With reference to EIA Guidance Note No.9/2004 this is capable of a 15dB(A) reduction of noise;

·                Use of acoustic fabric for the silent piling system, drill rigs, rock drills etc.  Experience from approved EIA Report for Tsim Sha Tsui Station Northern Subway (EIA 154/2008) showed that this is capable of a 10dB(A) reduction of noise;

·                Proper fitting of silencers and mufflers on the ventilation fans.  Experience from approved EIA Report for Tsim Sha Tsui Station Northern Subway (EIA 154/2008) showed that this is capable of a 15dB(A) reduction of noise; and

·                Utilisation of decking for WHA Station where PMEs would be operating under temporary traffic decking.  The area where traffic decking is feasible is shown in Figure 7.21.  Experience from approved EIA Report for West Island Line (EIA153/2008) showed that this is capable of a 20dB(A) reduction of noise.

Muckout Activities

7.9.2.2              Noise enclosures are proposed for all muckout points to mitigate the noise generated during the construction phase.  The typical setup of an enclosure at a mucking out point is presented in Figure 7.22.  It is anticipated that the enclosure would perform in a similar manner to the noise closure suggested for the PMEs above and, therefore, a 15dB(A) reduction of noise has been assumed for this assessment.

Rock Crushing Activities

7.9.2.3              Noise enclosures are proposed to be installed for all rock crushers to mitigate the noise generation during the construction phase.  The typical setup of an enclosure has been given in Figure 3.38.  It is anticipated that the enclosure would perform in a similar manner to the noise closure suggested for the PMEs above and, therefore, would be capable of a 15dB(A) reduction in noise.

7.9.2.4              Table 7.7 summarises all mitigation measures to be adopted for PMEs and their respective reduction in noise levels during the construction noise assessment.

Table 7.7:    Mitigation Measures and Assumed Effectiveness for PMEs

PME

Mitigation Measures

Reduction Level

Compressor and Pneumatic Drilling Rig

Acoustic Fabric

15

Piling, vibrating hammer

Acoustic Fabric

15

Rock Drill

Acoustic Fabric

15

Silent Piling System

Acoustic Fabric

15

Air Compressor

Enclosure Type Noise Barrier

15

Rock Crusher

Enclosure Type Noise Barrier

15

Concrete pump

Fixed Noise Barrier

10

Circular Saw, bench mounted

Fixed Noise Barrier

10

Truck

Fixed Noise Barrier

10

Bar bender and cutter (electric)

Fixed Noise Barrier

10

Conveyor belt

Fixed Noise Barrier

10

Generator, Super Silenced

Fixed Noise Barrier

10

Grout Pump

Fixed Noise Barrier

10

Saw, wire

Fixed Noise Barrier

10

Water Pump, Submersible (Electric)

Fixed Noise Barrier

10

Hydraulic Jack with Pump

Fixed Noise Barrier

10

Ventilation Fan

Silencer

15

Wheeled Excavator/Loader

Temporary Noise Barrier

5

Crane

Temporary Noise Barrier

5

Hydraulic Breaker

Temporary Noise Barrier

5

Scraper

Temporary Noise Barrier

5

Breaker, hand-held, mass > 10kg and < 20kg

Temporary Noise Barrier

5

Breaker, hand-held, mass >= 20kg and <= 35kg

Temporary Noise Barrier

5

Compactor, vibratory

Temporary Noise Barrier

5

Drill, percussive, hand-held (electric)

Temporary Noise Barrier

5

 

7.9.2.5              Due to the necessity of access entrances, not all NSRs would be shielded by the the enclosures.  Table 7.8 below shows the NSRs which will be shielded by the enclosure and receive an additional 15dB(A) attenuation of the predicted SWL for the PMEs used in the mucking out operations.

Table 7.8:    NSRs to be Shielded by Noise Enclosures at Muckout Points

NSR

Muckout Operation and Location

Noise Level Reduction (dB(A))

NSR 5

1.6 Remove spoil through existing GAR substation hatch

15

NSR 6

1.6 Remove spoil through existing GAR substation hatch

15

NSR 12

4.10 Remove spoil from YMT to HMT tunnels including KTE east station platform via WAB shaft

15

NSR 13a

4.10 Remove spoil from YMT to HMT tunnels including KTE east station platform via WAB shaft

15

NSR 13b

4.10 Remove spoil from YMT to HMT tunnels including KTE east station platform via WAB shaft

15

NSR 19

7.12 Remove spoil from HMT to WHA tunnel including KTE station platform via FKSP shaft

15

NSR 22

7.12 Remove spoil from HMT to WHA tunnel including KTE east station platform via FKSP shaft

15

NSR 23

7.12 Remove spoil from HMT to WHA tunnel including KTE east station platform via FKSP shaft

15

 

7.9.2.6              In addition to the mitigation measures listed above, there are also some good site practices that can further reduce the noise levels at NSRs.  However, they are non-quantifiable and, thus, not included in the noise level calculations.  These include:

·                Only well-maintained plant should be operated on-site and plants should be serviced regularly during the construction period;

·                Mobile plant, if any, should be sited as far from NSRs as possible;

·                Plant known to emit noise strongly in one direction should, wherever possible, be properly orientated so that the noise is directed away from the nearby NSRs;

·                Use of site hoarding as a noise barrier to screen noise at low level NSRs;

·                Machines and plant that may be in intermittent use should be shut down between works periods or should be throttled down to a minimum; and

·                Any material stockpiles and other structures should be effectively utilised, wherever practicable, to screen the noise from on-site construction activities.

7.9.2.7              Thus, the construction works have been mitigated using the above mentioned measures, and the mitigated construction noise levels at representative NSRs have been predicted and summarized in Table 7.9 below.  Detailed results are presented in Appendix 7.6.

Table 7.9:    Predicted Mitigated Air-borne Construction Noise Levels for Selected NSRs

NSR

Name

Maximum Predicted Construction Noise Level, dB(A)

EIAO-TM Noise Criteria, dB(A)

NSR 5

Alhambra Building

74

75

NSR 6

Methodist College

75

70/65

NSR 11

Queen Elizabeth Hospital – Specialist Clinic

73

75

NSR 12

Primary School at 10-12 Wylie Road (Planned Future NSR)

70

70/65

NSR 13a

Parc Palais Block 1

62

75

NSR 13b

Parc Palais Block 3

59

75

NSR 13c

Parc Palais Block 6

53

75

NSR 16

Carmel Secondary School

65

70/65

NSR 18-1

Yee Fu Building (1/F)

77

75

NSR 18-7

Yee Fu Building (7/F)

77

75

NSR 19

Marigold Mansion

69

75

NSR 20

Caritas Bianchi College of Careers

72

70/65

NSR 21

Lok Ka House

70

75

NSR 22a

Lok Do Building

72

75

NSR 22b

NSR 23

Hung Hom Government Primary School

70

70/65

NSR 27a

Block Y, Ki Fu Building, Whampoa Estate

83

75

NSR 27b

NSR 28

Block H, On Wah Building, Whampoa Estate

78

75

NSR 29a

Block 9, Bauhinia Mansions, Whampoa Garden Site 11

79

75

NSR 29b

NSR 30a

Block 1, Cherry Mansions, Whampoa Garden Site 2

78

75

NSR 30b

NSR 31a

Block 5, Cherry Mansions, Whampoa Garden Site 2

80

75

NSR 31b

NSR 31c

NSR 32

Block 13, Bauhinia Mansions, Whampoa Garden Site 11

79

75

NSR 33

Block 1, Oak Mansions, Whampoa Garden Site 5

82

75

NSR 34a

Fung Kei Millennium Primary School

78

70/65

NSR 34b

NSR 35a

GCEPSA Whampoa Primary School

76

70/65

NSR 35b

NSR 35c

NSR 36

Harbourfront Landmark

74

75

NSR 39

Harbourfront Horizon

75

75

NSR 44

Yue Sun Mansion 191A Wuhu Street

65

75

NSR 48a

Block I, Lok Wah Building, Whampoa Estate

81

75

NSR 48b

NSR 49

Fung Kei Primary School

71

70/65

NSR 50

Block 2, Oak Mansions, Whampoa Garden Site 5

83

75

NSR 51a

Block 5, Cotton Tree Mansions, Whampoa Garden Site 7

82

75

NSR 51b

NSR 52

Block 4, Cotton Tree Mansions, Whampoa Garden Site 7

75

75

NSR 62

Wing Fung Building

67

75

NSR 63

School of General Nursing, Block S, Queen Elizabeth Hospital

63

70/65

Notes:    Noise Limits of Leq(30min) for Schools is 70dB(A) for normal periods; 65dB(A) during exam periods.

                Numbers in bold underline ( e.g. 77) signify an exceedance of the noise criteria.

                Numbers in italic (e.g. 68) signify an exceedance of the noise criteria during examination periods only.

 

7.9.2.8              With the implementation of the above recommended mitigation measures, the predicted construction noise level could be reduced by up to 17dB(A).  However, the construction noise levels for the NSRs near HOM Station and WHA Station are still predicted to exceed the criteria. The NSRs for which exceedances are predicted to occur are summarised in Table 7.10.

Table 7.10:  Summary of Exceedances at Representative NSRs

NSR

Name

Maximum Predicted Residual Impact, dB(A)

EIAO-TM Noise Criteria, dB(A)

Duration, months

NSR 6

Methodist College

5 (10)

70 / 65

4(12.5)#

NSR 12

Primary School at 10-12 Wylie Road (Planned Future NSR)

0 (5)

70 / 65

0(19.5) #

NSR 18-1

Yee Fu Building (1/F)

2

75

6.5

NSR 18-7

Yee Fu Building (7/F)

2

75

6.5

NSR 20

Caritas Bianchi College of Careers

2 (7)

70 / 65

7(31) #

NSR 23

Hung Hom Government Primary School

0 (5)

70 / 65

0(15.5) #

NSR 27

Block Y, Ki Fu Building, Whampoa Estate

8

75

16

NSR 28

Block H, On Wah Building, Whampoa Estate

3

75

7.5

NSR 29

Block 9, Bauhinia Mansions, Whampoa Garden Site 11

4

75

9.5

NSR 30

Block 1, Cherry Mansions, Whampoa Garden Site 2

3

75

12.5

NSR 31c

Block 5, Cherry Mansions, Whampoa Garden Site 2

5

75

20

NSR 32

Block 13, Bauhinia Mansions, Whampoa Garden Site 11

4

75

22

NSR 33

Block 1, Oak Mansions, Whampoa Garden Site 5

7

75

13

NSR 34

Fung Kei Millennium Primary School

8 (13)

70 / 65

28(43) #

NSR 35

GCEPSA Whampoa Primary School

6 (11)

70 / 65

20(31.5) #

NSR 48

Block I, Lok Wah Building, Whampoa Estate

6

75

13

NSR 49

Fung Kei Primary School

1 (6)

70 / 65

10(20.5) #

NSR 50

Block 2, Oak Mansions, Whampoa Garden Site 5

8

75

24

NSR 51

Block 5, Cotton Tree Mansions, Whampoa Garden Site 7

7

75

24

Notes:    Noise Limits of Leq(30min) for Schools is 70dB(A) for normal periods; 65dB(A) during exam periods.

                Numbers in parentheses signify residual impacts during examination periods.

                NSRs with more than one façade (e.g. NSR 29a and 29b) are only counted as one NSR.

      #        Denotes maximum construction period where exceedances could occur but only if an exam is being undertaken during this period.

 

7.9.2.9              Two schools (NSR 12 and NSR 23) will show exceedances during examination periods only.  Scheduling of noisy construction works outside school examination periods would reduce the noise impacts on the NSRs and this is proposed.  This measure relieves the need to incorporate more stringent noise mitigation measures required to ensure compliance with the construction noise criterion and would avoid residual impacts.

7.9.2.10          There are a total of seventeen NSRs that show exceedances of the relevant construction noise criteria of 1dB(A) – 8dB(A).  Five of them are schools (NSR 6, NSR 20, NSR 34, NSR 35 and NSR 49) which would be subject to residual impacts of 1dB(A) – 7dB(A).  The other twelve NSRs are residential which will be subject to residual impacts of 2dB(A) – 8dB(A).

7.9.2.11          Additional barriers are not considered practical for most of the works sites.  For example, for the slope stabilization works at WS2 and WS27, substantial noise barriers would be impractical due to site constraints as well as potential secondary impacts as a consequence of building such barriers with a large footing.  For works sites at HOM Station, the open cut area at WS15a is more than 250m in length with slope ranges from 30° to 80°.  These site conditions make the erection of tall noise barriers infeasible due to lack of suitable area for foundations.  As short noise barriers will not be able to provide sufficient shielding for the PMEs at the centre of the work site, fixed noise barriers would not be considered practical at WS15a.

7.9.2.12          For the works sites at WHA, due to the lack of space between the works sites and the pedestrian walkway at Tak On Street, substantial noise barriers with large footings are also considered not practical.

7.9.2.13          Utilisation of temporary construction facilities including site offices would also be limited by the location of works areas.  For Fat Kwong Street Playground, works area is divided into WA15 at the northwest side where the site offices and storage area will be located.  The mucking out point is located in WS26a to the south and is close to the edge of the works site.  As such, there is limited space for any site offices to be located around the mucking out point in order to provide additional attenuation to the NSRs near by.  Figure 7.12 showed the site layout of WS26a and WA15.

7.9.2.14          All reasonably practicable mitigation measures have, therefore, been proposed but some residual impacts will still remain.  Residual impacts are further discussed in Section 7.11.

7.9.3                    Cumulative Construction Noise Assessment

7.9.3.1              All concurrent projects which may contribute to air-borne noise impacts on NSRs during its construction and operational phases have been identified in Section 3.  Referring to the respective draft EIA Reports, cumulative impacts have been presented in Appendix 7.6.  A summary of the results is presented in Table 7.11 below.

Table 7.11:  Cumulative Construction Noise Assessment with Concurrent Projects

NSR

Source of Cumulative Impact

Maximum Cumulative Construction Noise Level, dB(A)

Exceedance, dB(A)

EPIW

SCL-

THS

SCL-

MHS

13a

--

--

ü

63

--

13c

--

--

ü

68

--

16

ü

--

ü

73

3

19

ü

--

--

69

--

20

ü

ü

--

78

8

21

ü

ü

--

76

1

22

ü

--

--

77

2

39

--

ü

ü

75

--

62

ü

ü

ü

80

5

                  Note:    EPIW          =    Essential Public Infrastructure Works associated with the Project

                                      SCL-THS   =    SCL – Tai Wai to Hung Hom Section

                                      SCL-MHS  =    SCL – Mongkok East to Hung Hom Section

 

7.9.3.2              The cumulative impact with concurrent projects shows exceedances of 1dB(A) to 8dB(A).  However, the dominant noise sources for them are:

·                NSR 16 (due to SCL – Mongkok East to Hung Hom Section at 73dB(A));

·                NSR 20 (due to EPIW at 77dB(A));

·                NSR 21 (due to SCL – Tai Wai to Hung Hom Section at 75dB(A));

·                NSR 22 (due to EPIW at 76dB(A)); and

·                NSR 62 (due to SCL – Tai Wai to Hung Hom Section at 79dB(A)).

7.10                      Operational Air-borne Noise Assessment

7.10.1                Assessment Results

7.10.1.1          As all the rail tracks in the KTE project will be underground, hence adverse operational air-borne train noise impacts would not be anticipated.  However, operational noise will emanate from tunnel ventilation shafts.  This EIA Study has established the maximum allowable SWL for all above ground louvers and ventilation plant, with regard to the separation distances and orientation from the nearest NSRs, as well as cumulative noise impacts from other fixed noise sources.  The detailed calculation is presented in Appendix 7.7.

7.10.1.2          These predicted maximum allowable SWLs which are summarised in Table 7.12 should be implemented during the detailed design stage to meet the relevant legislative requirements.

Table 7.12:  Summary of Maximum Allowable SWLs for Fixed Plant at Representative NSRs

Plant Item

Distance to nearest NSR, (m)

Maximum Allowable Sound Power Level, dB(A)

Daytime

Night-time

Running Tunnel from YMT to HMT

VSWAB (VSWAB-1)

66

87

77

VSWAB (VSWAB-2)

80

99

89

VSWAB (VSWAB-3)

83

99

89

VSWAB (VSWAB-4)

82

99

89

VSWAB (VSWAB-5)

82

100

90

VSWAB (VSWAB-6)

74

89

79

VSWAB (VSWAB-7)

76

89

79

VSWAB (VSWAB-8)

67

88

78

VSWAB (VSWAB-9)

67

88

78

VSWAB (VSWAB-10)

62

87

77

HOM Station

VSH-1a

15

81

71

VSH-1a-1

14

81

71

VSH-1b

23

85

75

VSH-2

36

89

79

VSH-3 (East Elevation)

47

91

81

VSH-3 (South East Elevation)

63

99

89

VSH-3 (South Elevation)

86

100

92

VSH-4

96

100

90

VSH-5

97

100

90

VSH-6a

38

92

82

VSH-6b

38

92

82

VSH-7

118

90

80

VSH-8

113

101

92

VSH-9

103

100

90

VSH-10

114

101

92

VSH-11

88

99

89

WHA Station

VSW-1 (East Elevation)

25

92

82

VSW-1 (West Elevation)

15

86

76

VSW-2 (North Elevation)

21

88

78

VSW-2 (West Elevation)

21

88

78

VSW-3 (North Elevation)

32

94

93

VSW-3 (East Elevation)

27

91

82

VSW-4 (West Elevation)

9e

79

69

VSW-5a

25

90

80

VSW-5b

28

91

81

 

7.10.1.3          Whilst it is generally considered too restrictive to specify that the contractor has to use specific models of items of equipment/plant, it is reasonable and practicable to set the noise performance specifications for specific equipment/plant so that flexibility in the selection of equipment is allowed.  A pragmatic approach would be to request that the contractors should independently verify the noise levels of the equipment/plant to be used and demonstrate through furnishing these results, that the equipment/plant to be used should meet the requirements.  The preference for adopting quieter equipment/plant will be stipulated in the contract specifications.  It should be applied whenever practicable to further eliminate the potential of noise impact from ventilation buildings.

7.10.1.4          Cumulative SPL from all ventilation shafts at representative NSRs are presented in Table 7.13 and detailed calculation is presented in Appendix 7.7.

Table 7.13:  Cumulative SPL from all Ventilation Shafts at Representative NSRs

NSR

Louver

Cumulative SPL from all Ventilation Shafts, dB(A)

Specific ANL

Daytime (Night-time)

Daytime

Night-time

NSR 11

VSWAB (VSWAB-1)

56

42

60 (50)

 

VSWAB (VSWAB-2)

 

 

 

 

VSWAB (VSWAB-3)

 

 

 

 

VSWAB (VSWAB-4)

 

 

 

 

VSWAB (VSWAB-5)

 

 

 

 

VSWAB (VSWAB-6)

 

 

 

 

VSWAB (VSWAB-7)

 

 

 

 

VSWAB (VSWAB-8)

 

 

 

 

VSWAB (VSWAB-9)

 

 

 

 

VSWAB (VSWAB-10)

 

 

 

NSR 12

VSWAB (VSWAB-1)

55

41

55 (45)

 

VSWAB (VSWAB-2)

 

 

 

 

VSWAB (VSWAB-3)

 

 

 

 

VSWAB (VSWAB-4)

 

 

 

 

VSWAB (VSWAB-5)

 

 

 

 

VSWAB (VSWAB-6)

 

 

 

 

VSWAB (VSWAB-7)

 

 

 

 

VSWAB (VSWAB-8)

 

 

 

 

VSWAB (VSWAB-9)

 

 

 

 

VSWAB (VSWAB-10)

 

 

 

NSR 61

VSWAB (VSWAB-1)

55

44

60 (50)

 

VSWAB (VSWAB-2)

 

 

 

 

VSWAB (VSWAB-3)

 

 

 

 

VSWAB (VSWAB-4)

 

 

 

 

VSWAB (VSWAB-5)

 

 

 

 

VSWAB (VSWAB-6)

 

 

 

 

VSWAB (VSWAB-7)

 

 

 

 

VSWAB (VSWAB-8)

 

 

 

 

VSWAB (VSWAB-9)

 

 

 

 

VSWAB (VSWAB-10)

 

 

 

NSR 18-1

VSH-1a

56

46

60 (50)

 

VSH-1a-1

 

 

 

 

VSH-1b

 

 

 

 

VSH-2

 

 

 

 

VSH-3 (East Elevation)

 

 

 

NSR 19

VSH-1a

43

33

65 (55)

 

VSH-1a-1

 

 

 

 

VSH-1b

 

 

 

 

VSH-2

 

 

 

NSR 41

VSH-1a

51

41

65 (55)

 

VSH-1a-1

 

 

 

 

VSH-1b

 

 

 

 

VSH-2

 

 

 

NSR 20

VSH-3 (East Elevation)

62

--

65 (--)

 

VSH-3 (South East Elevation)

 

 

 

 

VSH-3 (South Elevation)

 

 

 

 

VSH-4

 

 

 

 

VSH-5

 

 

 

 

VSH-6a

 

 

 

 

VSH-7

 

 

 

NSR 21

VSH-3 (East Elevation)

64

54

65 (55)

 

VSH-3 (South East Elevation)

 

 

 

 

VSH-3 (South Elevation)

 

 

 

 

VSH-4

 

 

 

 

VSH-5

 

 

 

 

VSH-6a

 

 

 

 

VSH-8

 

 

 

 

VSH-9

 

 

 

 

VSH-10

 

 

 

 

VSH-11

 

 

 

NSR 40a

VSH-6a

56

46

60 (50)

 

VSH-6b

 

 

 

 

VSH-7

 

 

 

NSR 40b

VSH-1a

58

48

60 (50)

 

VSH-1a-1

 

 

 

 

VSH-1b

 

 

 

 

VSH-2

 

 

 

 

VSH-3 (East Elevation)

 

 

 

NSR 40c

VSH-6a

60

50

60 (50)

 

VSH-6b

 

 

 

 

VSH-7

 

 

 

NSR 45

VSH-3 (East Elevation)

61

51

65 (55)

 

VSH-3 (South East Elevation)

 

 

 

 

VSH-3 (South Elevation)

 

 

 

 

VSH-4

 

 

 

 

VSH-5

 

 

 

NSR 62

VSH-6a

58

49

60 (50)

 

VSH-8

 

 

 

 

VSH-9

 

 

 

 

VSH-10

 

 

 

 

VSH-11

 

 

 

NSR 28

VSW-1 (East Elevation)

58

48

60 (50)

 

VSW-1 (West Elevation)

 

 

 

NSR 29a

VSW-1 (East Elevation)

55

45

60 (50)

 

VSW-1 (West Elevation)

 

 

 

NSR 46

VSW-1 (East Elevation)

52

42

60 (50)

 

VSW-1 (West Elevation)

 

 

 

NSR 47

VSW-1 (East Elevation)

58

48

60 (50)

 

VSW-1 (West Elevation)

 

 

 

NSR 48a

VSW-1 (East Elevation)

52

42

60 (50)

 

VSW-1 (West Elevation)

 

 

 

NSR 32

VSW-2 (North Elevation)

57

47

60 (50)

 

VSW-2 (West Elevation)

 

 

 

NSR 53

VSW-2 (North Elevation)

60

50

60 (50)

 

VSW-2 (West Elevation)

 

 

 

NSR 33

VSW-3 (North Elevation)

56

48

60 (50)

 

VSW-3 (East Elevation)

 

 

 

 

VSW-4 (West Elevation)

 

 

 

NSR 34b

VSW-3 (North Elevation)

58

--

60 (--)

 

VSW-3 (East Elevation)

 

 

 

NSR 49

VSW-3 (North Elevation)

58

--

60 (--)

 

VSW-3 (East Elevation)

 

 

 

NSR 50

VSW-3 (North Elevation)

55

48

60 (50)

 

VSW-3 (East Elevation)

 

 

 

 

VSW-4 (West Elevation)

 

 

 

NSR 35a

VSW-5a

55

--

60 (--)

 

VSW-5b

 

 

 

NSR 35b

VSW-5a

55

--

60 (--)

 

VSW-5b

 

 

 

NSR 51a

VSW-5a

60

50

60 (50)

 

VSW-5b

 

 

 

 

7.10.2                Mitigation Measures

7.10.2.1          Provided the fixed plant are designed to meet the maximum allowable SWLs as indicated in Table 7.12, no adverse noise impacts on the NSRs would be expected.  However, it is still recommended that the following good practice should be considered during detailed design:

·                Louvers should be orientated away from adjacent NSRs whenever practicable;

·                Adequate direct noise mitigation measures including silencers, acoustic louvers or acoustic enclosures should be adopted where necessary; and

·                Quieter plant should be chosen as far as practical.

7.10.2.2          With proper implementation of the above noise control measures, adverse operational noise impacts are not anticipated and residual impacts are not predicted.

7.11                      Residual Impacts

7.11.1.1          The assessment of construction noise has revealed that, even with the application of all feasible direct mitigation measures and scheduling of noisy construction works outside school examination periods, up to seventeen representative NSRs will be affected by the implementation of the project in excess of the stipulated standards.  Residual impacts of between 1dB(A) to 8dB(A) are predicted to occur.

7.11.1.2          The Methodist College (NSR 6), which will be predicted to be subject to residual impacts during normal school hours, is located on top of a slope where slope stabilisation is proposed.  While noise barriers and insulating fabric have been recommended as mitigation measures to alleviate the noise emissions from the PME, given the location of the NSR on top of the slope and in a very close proximity of the works site, installation of substantial noise barriers would be impractical due to site constraints as well as potential secondary impacts as a consequence of building a substantial noise barrier with a large footing.  NSR 6 is observed to have been installed with either split-type or window-type air conditioners, which will further alleviate the residual impacts.  Noisy construction works would also be avoided during the examination periods.

7.11.1.3          The Caritas Bianchi College of Careers (NSR 20) is predicted to be subject to the residual impacts during normal hours as a result of the excavation works at HOM Station (WS15a).  Noise barriers and insulating fabric have been recommended as mitigation measures to alleviate the noise emissions from PME.  However, installation of substantial noise barriers at the source of the exceedance (WS15a) would be impractical due to site constraints as discussed in Section 7.9.2.9, as well as potential secondary impact as a consequence of building a substantial noise barrier with a large footing.  However, NSR 20 has been observed to have been installed with either split-type or window-type air conditioners, which will further alleviate the residual impacts.  Noisy construction works would also be avoided during the examination periods.

7.11.1.4          The Fung Kei Primary School (NSR 49) is located at Tak Ting Street where it will be affected by the construction works for WHA Station.  Noise barriers and insulating fabric have been recommended as mitigation measures to alleviate the noise emissions from PME.  However, installation of additional noise barriers at WHA Station work sites would be impractical due to site constraints including the lack of separation distance between the works site and pedestrian walkways.  NSR 49 is largely shielded by NSR 34 and will experience a marginal 1dB(A) exceedance.  It is, also, observed to have been installed with either split-type or window-type air conditioners, which will further alleviate the residual impacts.  Noisy construction works would also be avoided during the examination periods.

7.11.1.5          For the two schools, (NSR 34 and NSR 35) where exceedances are predicted during normal hours, residual impacts are predicted during the construction of pipe pile and sheet pile cofferdam walls, rock support and station structures at WHA Station east concourse.  Due to the close proximity of the NSRs, installation of substantial noise barriers would be impractical due to the lack of space between the works sites and the pedestrian walkway at Tak On Street.  Both NSR 34 and NSR 35 are observed to have been installed with either split-type or window-type air conditioners, which will further alleviate the residual impacts.  Noisy construction works would also be avoided during the examination periods.

7.11.1.6          Seven residential NSRs, (NSR 18-1, NSR 18-7, NSR 28, NSR 29, NSR 30, NSR 31c and NSR 32) will be exposed to residual impacts of 5dB(A) or below, which is considered acceptable in view of the temporary nature of construction phase impact and the construction works will be carried out outside the sensitive hours, i.e. 7pm to 7am on Monday to Saturday and any time on a general holiday, including Sunday.

7.11.1.7          The other five NSRs (NSR 27, NSR 33, NSR 48, NSR 50 and NSR 51) will be exposed to residual impacts of 6dB(A) to 8dB(A).  All possible direct mitigation measures have been applied for the reduction of noise levels from the corresponding works sites and, therefore, they are considered exhaustive for the affected NSRs.

7.11.1.8          The magnitude of the residual impacts are assessed in accordance with Section 4.4.3 of the EIAO-TM in Table 7.14 below.

Table 7.14:  Assessment of Residual Impacts from Construction Noise

Criteria

Assessment

Effects on public health and health of biota or risk to life.

The extent of noise nuisance would be unlikely to induce public health concern.

Magnitude of the adverse environmental impacts.

Residual impacts of between 1-8dB(A) could occur at up to 17 NSRs during the construction phase based upon worse case scenarios.

Geographic extent of the adverse environmental impacts.

The geographic extent of the adverse impacts from noise will not be large and is anticipated to be limited to within about 50m from the KTE project works area.

Duration and frequency of the adverse environmental impacts.

The construction noise impacts of the KTE project will be from 1 to 28 months and are, therefore, temporary and reversible.

Likely size of the community or the environment that may be affected by the adverse impacts.

About 5000 students (Assuming 1000 students for each of the 5 schools) and 800 dwellers (assuming 4 dwellers in each of the 200 residential units) would be affected.  In addition, pedestrians within immediate vicinity will be temporarily affected.  The size of the community can therefore be considered acceptable.

Degree to which the adverse environmental impacts are reversible or irreversible.

Construction phase impacts should be reversible.

Ecological context.

Not Applicable

Degree of disruption to sites of cultural heritage.

Very minimal as there would be no important cultural heritage resources in the immediate vicinity of works sites

International and regional importance.

The impacts are localised and not of international and regional importance.

Likelihood and degree of uncertainty of adverse environmental impacts.

The impacts predicted are based upon worst case assumptions and as such, would not occur to the extent predicted on all occasions.  However, the assessment has been made using approved mathematical modelling techniques and the degree of certainty on the results is high.

 

7.11.1.9          Based upon the above, the following factors should be considered in determining the residual impacts:

·                The noise impacts are not predicted to significantly affect their health or cause loss of life;

·                The predicted impacts are temporary and reversible;

·                Impacts are localised and not of international and regional importance;

·                The geographic extent of the adverse impacts is confined to small areas around the HMT and WHA works sites;

·                The mitigation measures proposed will reduce the levels of impacts; and

·                The study area has not shown itself to be fragile or undisturbed.

7.11.1.10      The MTR Corporation will facilitate communications with the concerned parties with residual impacts during construction and review to consider other initiatives, such as indirect technical remedies (ITR), if required.

7.11.1.11      As such, the residual impacts associated with the construction phase exceedances for the KTE would be considered minor and acceptable.

7.11.2                Operation Phase

7.11.2.1          With the fixed plant designed to meet the SWL requirements, adverse operational noise impacts are not anticipated.

7.12                      Environmental Monitoring and Audit

7.12.1.1          The assessment has concluded that, despite the implementation of the maximum practicable extent of mitigation measures, residual impacts during the construction phase will occur as a result of the implementation of the project.  As such, it is recommended that construction phase environmental monitoring and audit (EMA) is undertaken to ensure that adverse impacts do not occur.  It is noted that during the construction process, episodes of noise higher levels may occur and it will be the function of the EM&A process to identify these events and take the necessary action such as, for example, temporarily adjustment of the number of plant to be used or an equivalent measure as necessary.  Further details of the specific EM&A requirements are detailed in Section 13 of this report and in the EM&A Manual, together with event action plans and procedures for complaints.  The procedure for complaints will include the provision of a hotline number for the public to use when required. 

7.13                      Summary and Conclusions

7.13.1.1          Construction noise assessment has been conducted.  Results indicate that the noise impacts after the implementation of all practical direct mitigation measures would still exceed the stipulated noise criteria.  Residual impacts have been assessed and concluded to be temporary, reversible and unlikely to induce public health concern and as such, are considered to be minor and acceptable.

7.13.1.2          For operation phase, it is anticipated that if the construction contractor complies with the specified allowable sound power levels from the respective louvers (which will be checked by the EM&A programme), the operational noise impact at the sensitive receivers would be within acceptable noise impact criteria.