1.                              INTRODUCTION

1.1                          Project Description

1.1.1.1              The Kwun Tong Line Extension (KTE), otherwise referred to as ‘the Project’, is the proposed extension of the existing Kwun Tong Line (KTL) from Yau Ma Tei (YMT) Station to a new Whampoa (WHA) Station and with an interchange with the Shatin to Central Link (SCL) at the proposed Ho Man Tin (HOM) Station. 

1.1.1.2              The existing KTL was Hong Kong’s first mass transit line opened in 1979, initially running from Kwun Tong Station through to YMT Station before being extended to connect with the Eastern Harbour Crossing Link to Quarry Bay in 1985 and, more recently, the Tseung Kwan O (TKO) Extension in 2002. The current KTL runs from Tiu Keng Leng Station to YMT Station and is serviced by a depot at Kowloon Bay.

1.1.1.3              The MTR Corporation has completed feasibility studies for the proposed extension and submitted a proposal to Government in February 2004.  The proposed scheme was subsequently modified to incorporate improved interchange arrangements with the proposed SCL and a revised proposal was submitted to Government in July 2005.  Positive responses from the public, relevant stakeholders and the Government have been received for the KTE and Government has requested the MTR Corporation to proceed with further planning and implementation of the extension. The target completion date is 2015, subject to obtaining government and statutory approvals.  Meinhardt Infrastructure and Environment Limited (MIEL) was commissioned by the MTR Corporation in August 2008 to undertake an Environmental Impact Assessment (EIA) study, pursuant to section 5(7)(a) of the EIA Ordinance (EIAO), for the proposed KTE which is planned for completion in 2015.

1.1.1.4              The KTE project comprises a new railway extension, approximately 2.6km long, running from the end of the existing KTL twin overrun/refuge siding tunnels south of YMT Station to the end of the overrun/refuge siding beyond the new terminus station at Whampoa. An intermediate station (HOM Station) will provide an interchange with the SCL.  A crossover is located immediately east of HOM Station with a turnback siding immediately beyond the crossover. This allows every second train to turnback through HOM Station to maintain the current peak headway of 128 seconds. At WHA Station a single refuge siding will be provided immediately beyond the end of the platform.

1.1.1.5              An application for an EIA Study Brief was made to the Environmental Protection Department (EPD) dated 24 April 2008 with an associated Project Profile (No. PP-352/2008).  In accordance with Section 5/(7)(a) of the EIAO, an EIA Study Brief was issued (No. ESB-188/2008) for the undertaking of an EIA Study and preparation of an EIA Study Report.  This Assignment comprises the preparation of an EIA Report and associated Executive Summary and Environmental Monitoring and Audit (EM&A) Manual. 

1.2                          Purpose of this EM&A Manual

1.2.1.1              The purpose of this EM&A Manual is to guide the set-up of an EM&A programme to check the compliance with the recommendations of the EIA study for the KTE project, to assess the effectiveness of the mitigation measures recommended in the EIA report (the Implementation Schedule for Environmental Mitigation Measures (EMIS) is also included in Appendix 1.1 of this EM&A Manual), and to identify any further requirements for additional mitigation measures and remedial action.  This EM&A Manual outlines the monitoring and audit programme for the KTE project.  It aims to provide systematic procedures for the monitoring, auditing and minimising of environmental impacts associated with the activities of the KTE project.

1.2.1.2              All the environmental legislation of Hong Kong and the Hong Kong Planning Standards and Guidelines serve as the environmental standards and guidelines for the preparation of this EM&A Manual.  In addition, this EM&A Manual has been prepared in accordance with the requirements as stipulated in Annex 21 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

1.2.1.3              This EM&A Manual contains the following information:

·               The responsibilities of the Contractor, Engineer or Engineer’s Representative (ER), Environmental Team (ET), and the Independent Environmental Checker (IEC) with respect to the EM&A requirements during the course of the KTE project;

·               The organisation for the KTE project;

·               The requirements with respect to the construction schedule and the EM&A programme to track the varying environmental impacts;

·               The details of methodologies to be adopted, including all field laboratories and analytical procedures, and details on the quality assurance and quality control (QA/QC) programme;

·               The rationale on which the environmental monitoring data will be evaluated and interpreted;

·               The definition of Action and Limit levels;

·               The establishment of Event and Action plans;

·               The requirements for reviewing the pollution sources and working procedures required in the event of the non-compliance with environmental criteria and complaints;

·               The requirements for the presentation of EM&A data and appropriate reporting procedures; and

·               The requirements for reviewing the EIA predictions and effectiveness of mitigation measures/environmental management systems and the EM&A programme. 

1.2.1.4              This EM&A Manual is a dynamic document that should be reviewed regularly and updated as necessary during the construction and operation of the KTE project.

1.3                          Project Organisation

1.3.1.1              The roles and responsibilities of various parties involved in the EM&A process and the organisational structure of the parties responsible for implementing the EM&A programme are outlined below.  The project organisation and lines of communication with respect to environmental protection works are shown in Figure 1.1.

The Engineer or Engineer’s Representative (ER)

1.3.1.2              The Engineer is responsible for overseeing the construction works and ensuring the works to be undertaken by the Contractor in accordance with the specifications and contractual requirements.  The duties and responsibilities of the Engineer with respect to the EM&A programme include:

·               To supervise the Contractor’s activities and ensure the requirements in the EM&A Manual to be fully complied with;

·               To inform the Contractor when action is required to reduce the environmental impacts in accordance with the Event and Action Plans;

·               To lead the regular site inspections and audits attended by the Contractor and the ET; and

·               To adhere to the procedures for carrying out the complaint investigation.

Contractor

1.3.1.3              The Contractor should report to the Engineer.  The duties and responsibilities of the Contractor are:

·               To implement the recommendations and requirements of the EIA study;

·               To provide assistance to the ET in carrying out the relevant environmental monitoring;

·               To submit the proposals of mitigation measures in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans;

·               To implement the mitigation measures to reduce the environmental impacts where the Action and Limit levels are exceeded until the events are resolved; and

·               To adhere to the procedures for carrying out the complaint investigation as required in the EM&A Manual. 


Environmental Team (ET)

1.3.1.4              The ET will be set up by MTR Corporation and will conduct the EM&A programme to ensure the Contractor’s compliance with the KTE project’s environmental requirements during the construction phase. 

1.3.1.5              The ET should be led and managed by the Environmental Team Leader (ETL).  The ETL should possess at least 7 years of experience in EM&A.  The ET should monitor the mitigation measures implemented by the Contractor on a regular basis to ensure the compliance with the intended aims of the mitigation measures.  The duties and responsibilities of the ET are:

·               To monitor various environmental parameters as required in the EM&A Manual;

·               To carry out site inspections to investigate and audit the Contractor’s site practices, equipment and work methodologies with respect to the pollution control and environmental mitigation, and anticipate the environmental issues for the proactive and practicable action before problems arising;

·               To analyse the EM&A data, review the success of EM&A programme to confirm the adequacy of mitigation measures implemented, and the validity of the EIA predictions and to identify any adverse environmental impacts arising and report the EM&A results to the IEC, Contractor, and ER;

·               To prepare the reports of environmental monitoring data and site environmental conditions; and

·               To review the proposals of mitigation measures by the Contractor in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans.

Independent Environmental Checker (IEC)

1.3.1.6              The IEC should advise the ER on the environmental issues related to the KTE project.  The IEC should possess at least 7 years of experience in EM&A.  The duties and responsibilities of the IEC are:

·               To review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;

·               To validate and confirm the accuracy of the monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

·               To carry out random sample checking and audit of the environmental monitoring data and sampling procedures, etc;

·               To conduct random site inspections during construction;

·               To audit the recommendations and requirements of the EIA study against the status of the implementation of environmental protection measures on-site;

·               To review the effectiveness of the environmental mitigation measures and environmental performance of the KTE project;

·               On as-needed basis, to verify and certify the environmental acceptability of the Environmental Permit (EP) holder’s construction methodology (both temporary and permanent works), relevant design plans and submissions under the EP;

·               To verify the investigation results of the environmental complaints and the effectiveness of corrective measures;

·               To verify the EM&A reports that have been certified by the ETL; and

·               To provide feedback of the audit results to the ET/EP holder according to the Event and Action Plans in the EM&A manual.

1.4                          Structure of this EM&A Manual

1.4.1.1              Following this introductory section, the remainder of the EM&A Manual is set out as follows:

·               Section 2 sets out EM&A requirements for cultural heritage;

·               Section 3 details auditing requirements for landscape and visual impact;

·               Section 4 sets out EM&A requirements for air quality;

·               Section 5 sets out EM&A requirements for air-borne noise;

·               Section 6 sets out EM&A requirements for ground-borne noise;

·               Section 7 sets out EM&A requirements for water quality;

·               Section 8 details auditing requirements for waste management;

·               Section 9 details auditing requirements for hazard to life;

·               Section 10 describes the scope and frequency of the environmental site audits and sets out the general requirements of the EM&A programme; and

·               Section 11 details the EM&A reporting requirements; and

·               Section 12 describes the termination of the EM&A programme.