(i)
Completion of construction activities and
insignificant environmental impacts of the remaining outstanding construction
works;
(ii)
Trends analysis to demonstrate the narrow down of monitoring
exceedances due to construction activities and, return of ambient environmental
conditions in comparison with baseline data; and
(iii)
No environmental complaint and prosecution
involved.
12.1.1.2
The EM&A programme of the KTE project will be
ceased based on the above conditions.