3.                              LANDSCAPE AND VISUAL

3.1                          Introduction

3.1.1.1              The EIA report has recommended that EM&A for landscape and visual resources is undertaken during the design, construction and operational phases of the project.  This is particularly important at detail design stage since some residual landscape and visual impacts were considered to remain Significant and the adverse effects were considered too excessive to be able to mitigate fully at construction. The further design, implementation and maintenance of landscape mitigation measures needs to be checked to ensure that they are fully realised and that potential conflicts between the proposed landscape measures and any other project works and operational requirements are resolved at the earliest possible date and without compromise to the intention of the mitigation measures. In addition, implementation of the mitigation measures recommended by the EIA report will be monitored through the site audit programme.

3.2                          Audit Requirements

3.2.1.1              The design, implementation and maintenance of mitigation measures should be checked regularly to ensure that they are fully realised and compliant with the intended aims of the measures.  Any potential conflicts among the proposed mitigation measures, the project works, and operational requirements should also be identified and resolved early.

3.3                          Construction and Operational Phase Audit

3.3.1.1              A specialist landscape contractor should be employed by the Project Proponent prior to the undertaking of the main contract in order to facilitate the advance preparation and relocation of mature trees in conflict with the proposed works. A lead in time of up to 18 months may be necessary in this advance works period in order to prepare trees suitably for transplantation.

 

3.3.1.2              A specialist landscape sub-contractor should be employed by the works contractor for the implementation of further soft landscape works and subsequent maintenance operations during the establishment period.  The planting should commence during the construction contract and extend throughout the Contractor’s one-year maintenance period, which will be within the first operational year of the project.  The intention is to provide at least 24 months establishment period for the majority of the planting works.

 

3.3.1.3              All measures undertaken by the advance works specialist contractor as well as those by the works contractor and the specialist landscape sub-contractor during the construction phase and first year of the operational phase shall be audited by a Registered Landscape Architect, as a member of the Environmental Team (ET), on a regular basis to ensure compliance with the intended aims of the measures.  Site inspections should be undertaken once every two weeks throughout the construction period and once every two months during the operational phase.  The broad scope of the audit is detailed below but should also be undertaken with reference to the more specific checklist provided in Table 3.1. Operational phase auditing will be restricted to the last 12 months of the establishment of the landscape works and thus only the items below concerning this period are relevant to the operational phase.

 

·        the extent of the agreed works areas should be regularly checked during the construction phase. Any trespass by the contractor outside the limit of the works, including any damage to existing trees and woodland shall be prohibited;

 

·        the progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken;

 

·        all existing trees and vegetation within the study area which are not directly affected by the works are retained and protected;

 

·        the methods of protecting existing vegetation proposed by the contractor are acceptable and enforced;

 

·        the preparation, lifting transport and re-planting operations for any transplanted trees;

 

·        all landscape works are carried out in accordance with the specifications;

 

·        the planting of new trees, shrubs, groundcover, climbers, ferns, grasses and other plants, together with the replanting of any transplanted trees are carried out properly and during the appropriate season; and

 

·        all necessary horticultural operations and replacement planting are undertaken at the earliest possible opportunity throughout the Establishment Period, to ensure the healthy establishment and growth of both transplanted trees and all newly established plants.

 

Table 3.1: Construction/Operational Phase Audit Checklist

Area of Works

Items to be Monitored

Advance planting

monitoring of implementation and maintenance of planting, and against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Protection of all trees and woodland blocks to be retained

identification and demarcation of trees / vegetation to be retained, erection of physical protection (e.g. fencing), monitoring against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Clearance of existing vegetation

identification and demarcation of trees / vegetation to be cleared, checking of extent of works to minimise damage, monitoring of adjacent areas against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Transplanting of trees

identification and demarcation of trees / vegetation to be transplanted, monitoring of extent of pruning / lifting works to minimise damage, timing of operations, implementation of all stages of preparatory and translocation works, and maintenance of transplanted vegetation, etc.

Plant supply

monitoring of operations relating to the supply of specialist plant material (including the collecting, germination and growth of plants from seed) to ensure that plants will be available in time to be used within the construction works.

Soiling, planting, etc.

monitoring of implementation and maintenance of soiling and planting works and against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Decorative treatment of site hoarding

implementation and maintenance, to ensure compliance with agreed designs and check that it matches the surrounding environment and does not cause visual intrusion.

Architectural treatment of structures, retaining walls, elevated road structures and other engineering works.

implementation and maintenance of mitigation measures, to ensure compliance with agreed designs.

Establishment Works

monitoring of implementation of maintenance operations during Establishment Period

 

3.3.1.4              In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event /Action plan provided on Table 3.2.

 


Table 3.2:       Event / Action Plan for Construction/Operational Phase

Action Level

ET

IEC

ER

Contractor

Non-conformity on one occasion

1.   Identify Source

2.   Inform the IEC and the ER

3.   Discuss remedial actions with the IEC, the ER and the Contractor

4.   Monitor remedial actions until rectification has been completed

1.   Check report

2.   Check the Contractor's working method

3.   Discuss with the ET and the Contractor on possible remedial measures

4.   Advise the ER on effectiveness of proposed remedial measures.

5.   Check implementation of remedial measures.

1.   Notify Contractor

2.   Ensure remedial measures are properly implemented

1.   Amend working methods

2.   Rectify damage and undertake any necessary replacement

Repeated Non-conformity

1.   Identify Source

2.   Inform the IEC and the ER

3.   Increase monitoring frequency

4.   Discuss remedial actions with the IEC, the ER and the Contractor

5.   Monitor remedial actions until rectification has been completed

6.   If exceedance stops, cease additional monitoring

1.   Check monitoring report

2.   Check the Contractor's working method

3.   Discuss with the ET and the Contractor on possible remedial measures

4.   Advise the ER on effectiveness of proposed remedial measures

5.   Supervise implementation of remedial measures.

1.   Notify the Contractor

2.   Ensure remedial measures are properly implemented

1.   Amend working methods

2.   Rectify damage and undertake any necessary replacement

Note: 

ET –           Environmental Team

IEC –         Independent Environmental Checker

ER –           Engineer’s Representative

 


3.4                          Mitigation Measures

3.4.1.1              The Landscape and Visual Assessment of the EIA report recommended a series of mitigation measures to ameliorate the landscape and visual impacts of the project. These measures are summarised in Table 3.3. 

Table 3.3:       Recommended Construction and Operational Phase Landscape and Visual Mitigation Measures

ID

No.

Type

Landscape / Visual Mitigation Measure

Funding / Implement-ation

Management / Maintenance

Construction Phase

CM1

Site Practice –

 

Landscape

Reuse of Existing Topsoil

Existing topsoil shall be re-used for new planting areas within the project. Potential topsoil resources are located at:- a) Gascoigne Road Rest Garden, b) slopes above Chatham Road North, c) roadside planters in Whampoa Garden. The construction program shall consider using the soil removed from one phase for backfilling another. Suitable storage ground, gathering ground and mixing ground shall be set up as necessary.

MTR Corporation

MTR Corporation / LandsD, LCSD / HyD

CM2

Design / Planning –

 

Landscape

 

Tree Transplantation

Transplantation is proposed for a number of trees generally able to provide high amenity value and which are likely to survive the transplantation process. All transplantation will be carried out in accordance with ETWB TCW No. 3/2006 and undertaken under separate submission process. 

MTR Corporation

MTR Corporation / LandsD / HyD / LCSD / AFCD

CM3

Site Practice –

 

Visual

Control of night-time lighting glare

All security floodlights for construction sites and temporary works areas shall be equipped with adjustable shield, frosted diffusers and reflective covers, and be carefully controlled to minimize light pollution and night-time glare to nearby receivers.

MTR Corporation

Contractor

CM4

 

Site Practice –

 

Visual

Erection of Decorative Hoardings

Temporary decorative screen hoardings shall be designed and erected to be compatible with the existing urban context, either brightly and imaginatively or with visually unobtrusive design and colours where more appropriate. All works sites and works areas shall be surrounded by such hoardings, which shall be removed at project completion.

MTR Corporation

Contractor

Operational Phase

OM1

 

Design / Planning –

 

Landscape

 

Re-provision of Public Open Spaces

Every effort should be made to minimise use of public open spaces, however if affected by the Project they shall be re-provisioned to an equal or improved standard at completion of the project.  Sensitive design and reinstatement of the affected Public Open Spaces (Gascoigne Road Rest Garden, Yan Fung Street Rest Garden, Fat Kwong Street Playground) shall be made, incorporating replacement facilities to those currently provided and using materials of quality suitable for long term use and acceptable to the relevant government departments including LCSD and PlanD, who shall be consulted on the design of the reinstated public open spaces at an early stage of the design process.

MTR Corporation

LCSD

 

OM2

 

Design / Planning –

 

Landscape

/ Visual

Compensatory Tree Planting

Suitable land pockets within the project area will be used for the implementation of compensatory mitigation to offset the net loss of key landscape resources and improve visual amenity.

A compensatory tree planting proposal including locations of tree compensation will be submitted separately to seek relevant government department’s approval, in accordance with ETWB TCW No. 3/2006.

MTR Corporation

MTR Corporation /

LandsD/

HyD/

LCSD/

AFCD

 

OM3

Design / Planning –

 

Landscape

/ Visual

 

Horizontal and Slope Greening

Shotcreting of cut rock slopes shall be avoided and greening applications employed throughout the project.

 

At HOM Station the backfill slopes shall be hydroseeded and native seedling trees planted. The station roof shall be temporarily greened should there be no further on-site development within 1 year of the completion of the KTE, until permanent measures are undertaken under the proposed property development stage.

 

Parapets at WAB and HOM Station shall be provided with internal permanent planter boxes.

 

The roof at WAB shall be greened to improve visual amelioration from surrounding high level viewers

 

Station entrances at HOM and WHA shall utilise shrub planting areas to provide localised greening

MTR Corporation

MTR Corporation / LandsD

 

OM4

Landscape

/ Visual

 

Vertical Greening

Vertical greening / climbers shall be applied to all above ground structures against exposed walls as far as possible subject to technical operational and maintenance constraints. Such planting shall be employed at WAB, HOM Station and WHA Station.

MTR Corporation

MTR Corporation

 

OM5

Design / Planning –

 

Visual

 

Architectural Design Aesthetics for the WAB at Club de Recreio

The emergency access and ventilation building shall be designed in a way so as to ensure the form, material and surface detailing of this structure can fit sympathetically into the local context. The form shall consider the Cultural Heritage of the Club de Recreio site as well as other proximate buildings. The structure shall incorporate vertical greening / climbers where possible subject to technical operational and maintenance constraints. Detail Design Intent for the structures can be noted below.

MTR Corporation

MTR Corporation

 

OM6

Design / Planning –

 

Visual

 

Architectural Design Aesthetics for Above-Ground Structures at HOM Station

All station entrances, vent shafts, chillers and other above-ground structures shall be designed in accordance with the standardised MTR architectural theme for the KTE and other current rail projects. However specific attention shall be undertaken to ensure the form, material and surface detailing of these structures is considered to fit into the local context in terms of the architectural character of the site. Detail Design Intent for the structures can be noted below.

MTR Corporation

MTR Corporation

 

OM7

Design / Planning –

 

Visual

 

Architectural Design Aesthetics for Above-Ground Structures at WHA Station

These shall be designed in accordance with the standardised MTR architectural theme for the KTE and other current rail projects. However specific attention shall be undertaken to ensure the form, material and surface detailing of these structures is considered to fit into the local context in terms of the architectural character of the site. Detail Design Intent for the structures can be noted below.

MTR Corporation

MTR Corporation

 

(1)      Agreement and approval, including precise delineation of boundaries, etc., of the implementation, management and maintenance agencies of the project will be sought from all relevant authorities during the detail design stages of the project.

 

(2)    MTR Corporation would be responsible for maintenance and management of trees within the permanent site boundary. The maintenance matrix and responsible parties for trees outside the permanent site boundary are to be confirmed during detailed design stage. To facilitate with the confirmation process, MTR Corporation would be responsible for the maintenance works before any agreement is made.

 

(3)    Reinstatement of the Public Open Spaces and other disturbed areas is subject to the land status after project completion. Reinstatement of the land back to the previous state may not be practical and thus the reinstatement may take in other appropriate form.