4.1.1.1
Potential air quality impacts arising from the construction works would mainly be
related to the
construction dust from
excavation, materials handling, spoil removal and wind erosion, as well as
operation of the
temporary stockpiles and barging points. The construction dust monitoring and site audit are recommended to confirm that the mitigation measures recommended in the EIA
report are properly implemented. During the operational phase, there would be no adverse air quality impact anticipated and, therefore, no specific EM&A requirements are recommended during the
operational phase
of the KTE project.
4.2
Monitoring Requirements
4.2.1
Monitoring Parameters and
Equipment
4.2.1.1
The levels
of total suspended particulate (TSP)
should be measured by following the standard method as set out in the High Volume Method for Total Suspended Particulates,
Part 50 Chapter 1 Appendix B, Title 40 of the Code of Federal Regulations of
the USEPA (the
HVS method) or by direct reading
methods which are capable of producing comparable results as that by the high
volume sampling method.
4.2.1.2
Dust laden in air should be drawn through a high volume sampler (HVS) fitted
with a conditioned, pre-weighed filter paper, at a controlled rate. After sampling for 24-hours, the filter paper
with the retained dust particles should be collected and returned to the laboratory for drying
in a desiccator followed by weighing. The
24-hour average TSP levels should be calculated from the ratio of the mass of
particulates retained on the filter paper to the total volume of air sampled.
4.2.1.3
All the
relevant data including the temperature, pressure, weather conditions,
elapsed-time meter reading for the start and stop of HVS, identification and weight of the filter paper, and
other specific phenomena and works progress of the concerned works sites, etc, should
be recorded in detail. A sample
data sheet is shown in Appendix 4.1 of this
EM&A Manual.
4.2.1.4
The HVS in compliance with the following specifications
should be used for carrying out the 1-hour and 24-hour monitoring for TSP levels:
(i)
0.6-1.7 m3 per minute (20-60 standard cubic
feet per minute) adjustable flow range;
(ii)
Equipped with a timing/control device with ± 5
minutes accuracy for 24 hours operation;
(iii)
Installed with elapsed-time meter with ± 2 minutes
accuracy for 24 hours operation;
(iv)
Capable of providing a minimum exposed area of 406 cm2
(63 square
inch);
(v)
Flow control accuracy: ± 2.5% deviation over 24-hour
sampling period;
(vi)
Incorporated with an electronic mass flow rate
controller or other equivalent devices;
(vii)
Equipped with a flow recorder for continuous
monitoring;
(viii)
Provided with a peaked roof inlet;
(ix)
Incorporated with a manometer;
(x)
Capable of holding and sealing the filter paper to the
sampler housing at horizontal position;
(xi)
Easy to change the filter; and
(xii)
Capable of operating continuously for 24-hour periods.
4.2.1.5
The ET should be responsible for providing the monitoring equipment and should ensure that sufficient HVSs with the appropriate calibration kit
are available for carrying out the baseline monitoring,
regular impact monitoring and ad-hoc
monitoring
as required. The HVSs should be equipped with an
electronic mass flow controller and be calibrated against a traceable standard
at regular intervals, in accordance with the requirements in the
manufacturer’s operating manual and as described below. All the equipment, calibration kit, filter
papers, etc, should be clearly labelled.
4.2.1.6
The initial calibration of the HVSs with mass flow controller should be conducted
upon the installation and thereafter in every 6 months. The calibration should be conducted using an orifice calibrator and the calibration data should be properly documented for the future reference by the IEC. The flow rates of the sampler before and after the sampling with
the filter in position should be verified to be constant and be recorded on the
data sheet as shown in Appendix 4.1.
4.2.2
Monitoring Stations
4.2.2.1
The worst affected locations in the vicinity of the
construction works
sites and works areas identified for the construction dust monitoring are listed in Table 4.1 and depicted in Figures 4.1-4.4.
Table 4.1: Construction
Dust Monitoring Locations
ID No. |
ASRs |
Monitoring
Location |
CD1 |
ASR7a |
|
CD2 |
ASR14 |
Yee
Fu Building |
CD3 |
ASR17 |
Lok
Ka House |
CD4 |
ASR28 |
Block
1, |
CD5 |
ASR34 |
|
CD6 |
ASR46 |
Harbourfront
Horizon |
* ASRs = Air Sensitive
Receivers
4.2.2.2
It should be noted that there are no monitoring
stations proposed for the access shafts at
4.2.2.3
The status and locations of the air sensitive receivers (ASRs) may change after this EM&A Manual has
been issued. In such cases, the ET
should propose the
updated monitoring locations and
seek approval from the
ER and agreement from the IEC and
EPD. If alternative
monitoring locations are proposed, they should be chosen based on
the following criteria:
(i)
The monitoring at the ASRs close to
the major construction
site activities which are likely
to be
subjected to construction dust impacts due to the KTE project;
(ii)
The monitoring at the ASRs as defined in the EIAO-TM; and
(iii)
The assurance of the
minimal disturbance to the occupants and working under a safety condition
during monitoring.
4.2.2.4
When positioning the HVSs, the following aspects should be noted:
(i)
A horizontal platform with the appropriate support to secure the HVSs against the gusty wind should be
provided;
(iv)
No two HVSs should be placed less than 2m apart;
(v)
The distance between the HVSs and an obstacle, e.g. buildings, must be at least twice
the height of
the obstacle protruding above the HVSs;
(vi)
A minimum of 2m separation from the walls, parapets and penthouses is required for
rooftops HVSs;
(vii)
A minimum of 2m separation from any supporting
structures measured horizontally is required;
(viii)
No nearby
furnace or incinerator flue is allowed;
(ix)
The airflow around the HVSs is unrestricted;
(x)
The HVSs are more than 20m from the dripline;
(xi)
Any wire fences and gates to protect the HVSs should not cause obstructions during the monitoring;
(xii)
The permission must be obtained to set up the HVSs and to obtain access to the monitoring stations;
and
(xiii)
A secured supply of electricity is needed to operate
the HVSs.
4.2.3
Baseline Monitoring
4.2.3.1
The baseline monitoring should be carried out to determine
the ambient 1-hour and 24‑hour TSP levels at the monitoring locations
prior to the commencement of the main construction works for the KTE project. Prior to commencing
the baseline monitoring, the ETL should inform the IEC of the baseline monitoring
programme such that the IEC can conduct the on-site audit to ensure the accuracy of the baseline monitoring results.
4.2.3.2
The baseline monitoring of TSP levels should be carried out for a continuous period of at least
two weeks with the 24-hour and three sets of 1-hour ambient measurements taken
daily at each monitoring location.
During the baseline monitoring, there should not be any construction or
dust generating activities in the vicinity of the monitoring stations. The general
meteorological conditions (e.g.
wind speed, direction and
precipitation) and notes regarding any significant adjacent dust producing
sources should be recorded throughout the baseline monitoring. A summary of the requirements for the baseline monitoring is shown in Table 4.2.
Table 4.2: Summary of
Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Parameter |
Frequency |
Baseline Monitoring |
Consecutive
days of at least 2 weeks before commencement of construction works |
1
hour TSP |
3 times per day |
Continuous
24-hour TSP |
Daily |
||
Impact Monitoring |
Throughout
the construction phase* |
1
hour TSP |
3
times per
6 days (as required in case of complaints) |
Continuous
24-hour TSP |
Once per 6 days |
*
Impact monitoring should be conducted at the monitoring stations for 24-hour
TSP monitoring when there are project-related construction activities being undertaken
within a radius of 500m from these monitoring stations.
4.2.3.3
The baseline monitoring will provide environmental data for the determination of the appropriate Action
levels for
the air quality monitoring, whilst the Limit
levels will
be set against the statutory or otherwise agreed limits. If the ET considers that
significant changes in the ambient conditions have arisen, a repeat of the
baseline monitoring may be carried out to update the baseline levels and Action levels, upon
the consultation and agreement with
the ER, IEC and EPD.
4.2.4
Impact Monitoring
4.2.4.1
The monthly schedule of the impact construction dust monitoring programme should be drawn up by the ET
one month prior to the commencement of the scheduled construction period.
4.2.4.2
For the
regular 24-hour TSP impact
monitoring, a sampling frequency of at least once per 6 days should be strictly conducted at the monitoring stations when there are main project related construction activities being conducted within a radius of 500m from these monitoring stations. In case of complaints, the 1-hour TSP monitoring should be conducted at least
three times per 6 days when the highest dust impacts are likely to
occur. The impact monitoring programme
is also summarised in Table 4.2.
4.2.4.3
Before commencement of the monitoring, the ET should
inform the IEC of the impact monitoring programme such that the IEC can conduct
an on-site audit to ensure the accuracy of the impact monitoring results.
4.2.5
Compliance Assessment
4.2.5.1
The Action and Limit (A/L) levels that provide an
appropriate framework for the interpretation of monitoring results have to be
agreed between the
ET, IEC, EPD and ER before the commencement of the construction dust monitoring, and the monitoring data should be checked against these agreed A/L levels.
The recommended A/L levels are summarised in Table 4.3.
Table 4.3: Action and Limit (A/L) Levels for Construction Dust Impact Monitoring
Parameter |
Action Level* |
Limit Level |
TSP
(24 hour average) |
BL
£
200 μgm-3,
BL
> 200 μgm-3,
|
260
μgm-3 |
TSP
(1 hour average) |
BL
£
384 μgm-3,
BL
> 384 μgm-3,
|
500 μgm-3 |
*
BL = baseline level;
4.2.6
Event and Action Plan
4.2.6.1
The Event and Action Plan prescribes the
procedures and action associated
with the outcome of the comparison of the construction dust monitoring data recorded and the agreed A/L levels. In the cases where exceedances of these A/L levels occur, the ET, IEC, ER and
Contractor should strictly observe the relevant action of the respective Event
and Action Plan as
listed in Table 4.4.
Table 4.4: Event and Action Plan for Construction Dust Monitoring
EVENT |
ACTION |
|||||||||||
ET(1) |
IEC(1) |
ER(1) |
Contractor |
|||||||||
Action Level |
|
|
|
|
||||||||
1. Exceedance
for one sample |
1. Identify
sources, investigate the causes of complaint and propose remedial measures. 2. Inform
IEC and ER. 3. Repeat
measurement to confirm finding;. 4. Increase
monitoring frequency. |
1. Check
monitoring data submitted by the ET. 2. Check
the Contractor’s working methods. |
1. Notify
the Contractor. |
1. Rectify
any unacceptable practices. 2. Amend
working methods agreed with the ER as appropriate. |
||||||||
2. Exceedance
for two or more consecutive samples |
1. Identify
sources. 2. Inform
the IEC and ER. 3. Advise
the ER on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings. 5. Increase
monitoring frequency to daily. 6. Discuss
with the IEC, ER and Contractor on remedial action required. 7. If
exceedance continues, arrange meeting with the IEC, Contractor and ER. 8. If exceedance stops,
cease additional monitoring. |
1. Check
monitoring data submitted by the ET. 2. Check the Contractor’s working methods. 3. Discuss with the ET, ER and Contractor on possible remedial
measures if required. 4. Advise the ER on the effectiveness of proposed remedial measures
if required. |
1. Notify
the Contractor. 2. Ensure remedial
measures properly implemented. |
1. Submit
proposals for remedial action to the ER within 3 working days of
notification. 2. Implement
the agreed proposals. 3. Amend proposal as
appropriate. |
||||||||
|
|
|
|
|
||||||||
Limit Level |
|
|
|
|
|
|
||||||
1. Exceedance for one sample |
1. Identify
sources, investigate causes of exceedance and proposed remedial measures. 2. Inform
the IEC, ER, and Contractor. 3. Repeat
measurement to confirm finding. 4. Increase
monitoring frequency to daily. 5. Assess effectiveness
of the Contractor’s remedial action and keep the IEC and ER informed of the
results. |
1. Check monitoring data submitted by the ET. 2. Check the Contractor’s working methods. 3. Discuss with the ET, ER and Contractor on possible remedial
measures. 4. Advise the ER and ET on the effectiveness of the proposed
remedial measures. 5. Supervise the implementation of remedial measures. |
1. Confirm
receipt of the notification of exceedance in writing. 2. Notify
the Contractor. 3. Ensure remedial
measures are properly implemented. |
1. Take
immediate action to avoid further exceedance.
2. Submit
proposals for remedial action to the ER and copy to the ET and IEC within 3
working days of notification. 3. Implement
the agreed proposals. 4. Amend proposal as
appropriate. |
|
|
||||||
2. Exceedance
for two or more consecutive samples |
1. Notify
the IEC, ER and Contractor. 2. Identify
sources. 3. Repeat
measurements to confirm findings. 4. Increase
monitoring frequency to daily. 5. Carry
out analysis of the Contractor’s working procedures with the ER to determine
the possible mitigation to be implemented. 6. Arrange
meeting with the IEC and ER to discuss the remedial action to be taken. 7. Assess
the effectiveness of the Contractor’s remedial action and keep the IEC, EPD
and ER informed of the results. 8. If
exceedance stops, cease additional monitoring. |
1. Discuss
amongst the ER, ET and Contractor on the potential remedial action. 2. Review
the Contractor’s remedial action whenever necessary to assure their
effectiveness and advise the ER and ET accordingly. 3. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of the notification of exceedance in writing. 2. Notify
the Contractor. 3. In
consultation with the IEC and ET, agree with the Contractor on the remedial
measures to be implemented. 4. Ensure
remedial measures are properly implemented. 5. If
exceedance continues, consider what portion of works is responsible and
instruct the Contractor to stop that portion of works until the exceedance is
abated. |
1. Take
immediate action to avoid further exceedance. 2. Submit
proposals for remedial action to the ER and copy to the IEC and ET within 3
working days of notification. 3. Implement
the agreed proposals. 4. Resubmit
proposals if problems still not under control. 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
|
|
||||||
Note (1): ET – Environmental Team, IEC – Independent
Environmental Checker, ER – Engineer’s Representative
4.3
Mitigation Measures
4.3.1.1
The construction dust mitigation measures stipulated
in the Air Pollution Control (Construction Dust) Regulation should be
implemented to control dust emissions from all construction work sites. Details of the mitigation measures recommended
in the EIA report are presented in Appendix 1.1.
·
For the unloading of spoil from trucks at barging
point and crushing plant, installation of 3-sided screen with top and the
provision of water sprays at the discharge point would be provided for an
assumed 50% dust suppression. This
assumption is based upon USEPA AP-42 Control Techniques for Particulate
Emissions form Stationary Sources Part 2 which states that watering alone would
have 50% dust removal efficiency;
·
Watering every working hour for 12 hours a day on exposed
soil areas on active works areas and paved haul roads to reduce dust emissions
by 91.7%, which is with reference to the “Control of Open Fugitive Dust
Sources” (USEPA AP-42). The amount of
water to be applied would be 1.8L/m2;
·
The dust removal efficiency of fabric
baghouse/cartridge filter type dust extraction and collection system or
equivalent for rock crushing activities within an enclosure is assumed to be
99%, with reference to USEPA AP-42;
·
The use of regular watering, with complete coverage,
to reduce dust emissions from the exposed site surfaces and unpaved roads,
particularly during dry weather;
·
The use of the frequent watering for particularly
dusty construction works sites and works areas close to ASRs;
·
The use of side enclosure and covering of
aggregates and dusty material storage piles to reduce emissions. Where this is not practicable owing to the
frequent usage, watering shall be applied to the aggregate fines;
·
Open stockpiles should be avoided or covered. Prevent placing dusty material storage piles
near ASRs;
·
The tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations;
·
The establishment and use of vehicle wheel and body
washing facilities at the exit points of construction works sites practically;
·
The provision of wind shield and dust extraction
units or similar dust mitigation measures at the loading points, and use of
water sprinklers at the loading areas where dust generation is likely during
the loading process of loose materials, particularly in dry seasons / periods;
·
The imposition of speed control for vehicles on
unpaved haul road within construction sites – 8 km per hour is the recommended
limit;
·
Routing of vehicles and positioning of construction
plant should be at the maximum possible distance from ASRs;
·
Every stock of more than 20 bags of cement or dry
pulverised fuel ash (PFA) should be covered entirely by the impervious sheeting
or placed in an area sheltered on the top and 3 sides;
·
Cement and/or dry PFA delivered in bulk should be
stored in a closed silo fitted with an audible high level alarm which is
interlocked with the material filling line and no overfilling is allowed; and
·
The loading, unloading, transfer, handling or
storage of bulk cement or dry PFA should be carried out in a totally enclosed
system or facility, and any vent or exhaust should be fitted with an effective
fabric filter or equivalent air pollution control system.