Contents:
2.1 Scope and Nature of the Project
2.2 Selection of the Project Scheme
2.3 Construction Works
2.4
Preliminary Construction Programme
3. Environmental Impact Assessment
3.2 Cultural Heritage
3.3 Landscape and Visual
3.4 Air Quality
3.5 Air-borne Noise
3.6 Ground-borne Noise
3.7 Water Quality
3.8 Waste Management
3.9 Land Contamination
3.10 Hazard to Life
4. Environmental Monitoring and Audit
Table
Table 3.1 Impact Summary
Figures
Figure 2.2 Revised Preferred Scheme
1.1.1.1
The
Kwun Tong Line Extension (KTE), otherwise referred to as ‘the Project’, is the
proposed extension of the existing Kwun Tong Line (KTL) from Yau Ma Tei (YMT)
Station to a new Whampoa (WHA) Station with an interchange with the Shatin to
Central Link (SCL) at the proposed Ho Man Tin (HOM) Station.
1.1.1.2
The
MTR Corporation has completed feasibility studies for the proposed extension
and submitted a proposal to Government in February 2004. The proposed scheme was subsequently modified
to incorporate improved interchange arrangements with the proposed SCL and a
revised proposal was submitted to Government in July 2005. Positive responses from the public, relevant
stakeholders and the Government have been received for the KTE and Government
has requested the MTR Corporation to proceed with further planning and implementation
of the extension. The target completion
date is 2015, subject to obtaining government and statutory approvals.
1.1.1.3
This
Executive Summary highlights the key findings of the Environmental Impact
Assessment (EIA) for the Project to comply with the EIA Ordinance (EIAO).
2.1
Scope and Nature of the Project
2.1.1.1
The
Project comprises the following key elements:
· Running tunnels from YMT Station (existing overrun tunnels) to HOM Station;
· Running tunnels from HOM Station to WHA Station;
· HOM Station with associated structures and provisions including station structures and provisions for interchange with the SCL;
· WHA Station with associated structures and provisions;
· The Wylie Road Ancillary Building (WAB) and ventilation structure at Club de Recreio; and
· A purpose designed and built temporary explosives storage magazine at Tseung Kwan O Area 137 (The decommissioning of the temporary explosives storage magazine will not be part of the KTE project).
2.1.1.2
The
KTE is a single project and as an extension of the MTR Corporation’s KTL it is
a Designated Project under the EIAO falling into the following categories:
· A railway and its associated stations (Item A.2 of Part 1 of Schedule 2 of the EIAO);
· A railway tunnel more than 800m in length between portals (Item A.7 of Part 1 of Schedule 2 of the EIAO);
· Underground rock caverns (Item Q.2 of Part 1 of Schedule 2 of the EIAO). (Referred to in this report as Station Platform);
· Rock crushing equipment which is a facility for the treatment of construction waste (a) with a designed capacity of not less than 500 tonnes per day; and (b) a boundary of which is less than 200m from an existing or planned (i) residential area; (ii) place of worship; (iii) educational institution; or (iv) health care institution (Item G.5 of Part 1 of Schedule 2 of the EIAO); and
· An explosives depot in a stand-alone, purpose built building (Item K.10, Part 1 of Schedule 2 of the EIAO). (Referred to in this report as an explosives storage magazine). Given that this explosives storage magazine is a temporary structure it will need to be decommissioned. The decommissioning will itself be a designated project (under Item 11, Part II – Decommissioning Projects of Schedule 2 of the EIAO). The date of the decommissioning is uncertain at this stage but the decommissioning of the temporary explosives storage magazine will not be part of the KTE project.
2.2
Selection of the Project Scheme
2.2.1.1
The
KTE alignment options as shown in Figure 2.1 included:
·
The
Base Scheme: developed in the previous Feasibility Study. This was the originally proposed KTE
alignment as shown in the EIA Study Brief;
·
Option
A: the YMT Station to HOM Station to
·
Option
B: the YMT Station to HOM Station to
2.2.1.2
The
Base Scheme incorporated the preferred Tak On Street Alignment for WHA Station
but also includes less favourable design elements, namely the longer tunnel
alignment (with associated greater usage of materials, resources and energy),
with a crossover further away from the HOM Station, the joint longest
construction programme and affects the greatest number of private land lots.
2.2.1.3
Option
A incorporated the shorter tunnel alignment and the closer crossover location
(to HOM Station) but also incorporates the Dyer Avenue Alignment which is not
preferred for reasons such as, a deeper WHA Station with greater associated
excavation, spoil arisings, materials usage, inconvenience to the passengers
and the joint longest construction programme.
The Option A alignment was also considered slightly less favourable than
Option B in terms of its effects on private land lots.
2.2.1.4
Option
B was determined to have minimised environmental effects and provides overall
environmental benefits over the other two options such as, a shorter tunnel
alignment, shortest construction program, and reduced impacts associated with a
shallower WHA Station. It presents the
optimum scheme from an operational and environmental perspective. As such, Option B was selected as the
preferred alignment.
2.2.1.5
Since
the selection of the preferred alignment option (Option B), the alignment
design has continued to be modified in order to avoid potential problems and to
improve the alignment. This process has
involved relatively small modifications to the alignment and the associated
facilities. This Revised Preferred
Scheme is shown in Figure 2.2. The EAP /
2.3
Construction Works
2.3.1.1
As the
Project is an underground railway, major construction works are tunnelling
works and cut-and-cover works at shafts, WAB, HOM and WHA Stations. Drill-and-blast, cut-and-cover, and
mechanical breaking construction method will be adopted for rock tunnels and
mixed soft ground tunnels. There would
be no marine works and dredging works in the Project.
2.4
Preliminary Construction Programme
2.4.1.1
The
construction works would be scheduled to commence in early 2011 for completion
in 2015.
3.1.1.1
The
EIA Study was conducted in accordance with the EIAO Study Brief No.
ESB-188/2008, following the guidelines on assessment methodologies in the
Technical Memorandum on Environmental Impact Assessment (EIAO-TM). The major findings of the EIA study are summarised
below and an impact summary is shown in Table 3.1.
3.2.1.1
There
are no Declared Monuments within the KTE project study area. No impacts on Sites of Cultural Heritage are
expected during the construction or operational phases under the EIAO and no
specific mitigation measures for archaeological resources will be required.
Construction Phase
3.3.1.1
Approximately 1,000
existing trees will be affected by the proposed works, of which 69 trees (6%)
are intended to be transplanted and 931 proposed to be felled. None of these
are Registered Old and Valuable Trees.
3.3.1.2
Open
cut excavation at HOM Station will create the most significant impacts, most
importantly with the loss of mature mixed and plantation woodland including
almost 800 trees on the Slopes adjacent
to
3.3.1.3
The
large works site at HOM Station will be
particularly visually prominent in the surrounding areas and large enough to
modify the nature of the existing landscape framework (LCA06), low in quality
as it is. Mitigation measures will have
little effect and in fact the existing character of the site is one that is
undergoing change. Impacts are
considered Moderate and Reversible.
3.3.1.4
The
most significantly affected visual receivers will be those residents in close
proximity to the works at HOM station
and WHA station. These include Residents on the south side of
3.3.1.5
Construction
of the WAB, whilst a small structure, will occupy a reasonably large
construction space during the works. It
is relatively overlooked and close by receivers will not be suitably mitigated
during the construction. Members and Visitors of Club de Recreio
(VSR-L4) and Visitors of Chinese Civil
Servants Recreation Club and Philipino Club (VSR-L6) will be adversely
affected Significantly.
Operational Phase
3.3.1.6
Compensatory tree
planting and greening shall be provided to compensate for felled trees and loss
of visual amenity with reference to the requirement in ETWB TCW No.
3/2006. A minimum of 224 heavy standard trees will be provided within the
site areas of the project and 1,800 seedling trees planted on slopes
surrounding HOM Station. Furthermore an approximate total of 55m2 of vertical greening / climbers shall be provided at the WAB and HOM
Station.
3.3.1.7
No
long term Significant Adverse
Landscape Impacts are anticipated at Operation Stage. New tree planting proposals for the HOM
Station will include some 150 new trees of various size and go some way to
mitigating against the loss to the vegetated areas of this extensive green
urban lung. The establishment of other
slope greening measures including the planting of 1800 seedling trees along
with the potential for invasive tree seeding should see an ongoing reduction in
the net loss of landscape resources.
Whilst at Day 1 of Operation Significant
residual impacts will occur at Slopes
adjacent to Chatham Road North (LDR-3.2), in the longer term residual
impacts will continue to reduce and some of the original size and scale of
trees in the area may be achieved by year 30, however at year 10 impacts to
landscape resources are considered to remain Moderate Adverse.
3.3.1.8
LCA-06
is an area currently exhibiting qualities of transition. With the implementation of the project along
with other scheduled redevelopments within the Character Area the underlying
character may be said to have actually changed and the area may need to be
redefined to one showing a more defined and valued urban characteristic. The project itself will be largely
responsible for this change and the residual impacts of the project on the
Character Area can be considered to be Slight Beneficial by Year 10.
3.3.1.9
With
the removal of the visual impacts caused by construction works the majority of
adverse visual impacts from the project are significantly reduced. No Significant Adverse Visual Impacts are
anticipated at Operation Stage.
Potential residual adverse impacts will result primarily from the
permanent loss of open space and greening at both HOM and WHA Stations (LDR3.2
and LDR4.2) as well as the above-ground structures developed under the
project. These include the new station
at HOM, the ventilation structures at WHA Station, new walls, slopes, and entrances
as well as the WAB at Club de Recreio.
The final appearance if these is critical in ensuring minimal visual
impacts in the Operation Stage. At Year
10 of Operation worst case situation has Residents
with north views on the south side of
Construction Phase
3.4.1.1
Potential
air quality impacts from the construction works for the Project would mainly be
due to construction dust, which would be anticipated to be generated from
activities, such as soil excavation, backfilling, wind erosion,
transportation/handling of C&D materials, loading and unloading of
excavated materials at the barging point, construction of access shafts and
tunnel mucking out areas, rock crushing equipment, etc.
3.4.1.2
Mitigation
measures specified in the Air Pollution Control (Construction Dust) Regulation
have been recommended, such as regular watering of the exposed spoil and
covering dusty material storage areas.
With the implementation of the dust mitigation measures, the dust
impacts can be generally reduced to acceptable levels, which are less than the
AQO criteria, except some exceedances for the annual dust results at the areas
adjacent to the HOM Station works site and Finger Pier works area. However, the exceedances are marginal,
short-term and in most cases transient and have been based upon worst case
assumptions. It is, also considered that
the maximum practicable mitigation measures have been applied to reduce the
residual impacts to a minimum. Based upon these factors, the residual impacts
associated with the annual dust exceedances for the KTE project within the
study area would be considered minor and acceptable.
Operation Phase
3.4.1.3
As
KTE trains are electrically powered, there would be minimal dust
emissions. Tunnel ventilation exhausts
and emergency smoke extraction facilities would be carefully positioned to
avoid adverse air quality impacts. Air
quality impacts during operational phase are, therefore, envisaged to be insignificant.
Construction Phase
3.5.1.1
The
potential source of noise impact during the construction phase of the Project
would mainly be the use of powered mechanical equipment (PME) for various
construction activities, including site establishment, excavation, station
construction, tunnel construction, backfilling and reinstatement works. As the area is densely populated at WHA
Station, in the absence of any control measures, construction noise levels
exceeding the EIAO-TM air-borne construction noise criteria would be expected
at a number of noise sensitive receivers (NSRs) in the vicinity of the works
areas.
3.5.1.2
Construction
noise control measures have been incorporated into the construction method
design, such as use of quieter construction methods and equipment, movable and
temporary noise barriers, full enclosure, noise insulating fabric, silencer for
ventilation fans and decking over excavation areas. With these measures in place, there would be
compliance with the noise criteria at most NSRs.
3.5.1.3
There
would nevertheless be some exceedance of the noise criteria at some NSRs in
close proximity to the works areas for WHA Station, and some institutional NSRs
in close proximity to the works areas for HOM and WHA Stations. Residual impacts range from 2-8dB(A) for
residential NSRs. For institutional
NSRs, residual impact of up to 8dB(A) during normal periods would be
expected. Careful planning of the
construction schedule would be able to reduce the noise impact at these NSRs.
3.5.1.4
Noise enclosures are proposed to be installed for
all rock crushers to mitigate the noise generation during the construction
phase. It is anticipated that the
enclosure would perform in a similar manner to the noise closure suggested for
the PMEs and would be capable of a 15dB(A) reduction in noise.
Operation Phase
3.5.1.5
The
main source of operational air-borne noise impact would be the fixed plant used
for tunnel ventilation and cooling systems for stations and adits. The maximum allowable Sound Power Levels
(SWLs) have been incorporated into the fixed plant design specification to
comply with the SWL criteria. No adverse
operational noise impact at NSRs would therefore be envisaged.
Construction Phase
3.6.1.1 During construction, ground-borne noise could mainly arise from hydraulic breakers, pipe pile rigs and drilling rigs during excavation. No exceedances of the relevant ground-borne noise criteria are predicted and no further mitigation measures are required.
Operation Phase
3.6.1.2 Representative NSRs have been identified to assess ground-borne noise and the levels of operational ground-borne noise predicted. Operational ground-borne noise levels have been predicted at representative NSRs along the route with no exceedances of the relevant ground-borne noise criteria. No noise mitigation is necessary.
Construction Phase
3.7.1.1 Potential water pollution sources have been identified as construction runoff, sewage from workforce, wastewater discharge from tunnelling and excavation, change of the groundwater table, and groundwater contamination. Mitigation measures including covering of excavated construction materials and provision of sedimentation tanks etc., are recommended to mitigate any adverse water quality impacts. The sites should be regularly inspected and audited.
Operation Phase
3.7.1.2
During the operational phase,
there would be no direct discharge of wastewater into
Construction Phase
3.8.1.1
Construction
waste of the Project would include construction and demolition (C&D)
materials including excavated C&D materials suitable for public fill,
C&D waste including cleared vegetation which is not suitable for public
fill, chemical waste, and general refuse.
3.8.1.2
Measures
have been adopted to minimise the generation of C&D materials at the outset
during the design stage. As excavation
cannot be avoided, only a few measures can be taken to minimise the quantity of
C&D materials. Owing to the urban
setting constraints, the available schemes for construction of railway
facilities and tunnels are limited, hindering the minimisation of waste
generation. Alternative methods for
construction and measures to minimise the generation of C&D materials at
the preliminary design stage have been investigated for the key works sites.
3.8.1.3
Opportunities
to re-use materials have also been fully considered. Approximately 930,000m3 of C&D
materials will be considered for the reuse/recycling in other
projects/facilities, e.g. Hong Kong-Zhuhai-Macao Bridge Hong Kong Boundary Crossing
Facilities, etc. There would be
approximately 5,900m3 of C&D waste that needs to be disposed of
at landfills.
Operation Phase
3.8.1.4
The
main types of waste generated during the operation of the Project would be the
general refuse from the public, station employees and commercial operators
within the HOM and WHA Stations, industrial waste from maintenance activities
and chemical waste from operational activities.
The handling, collection, transportation and disposal practices of the
identified waste generated will follow the current practices at other operating
railway lines.
3.9.1.1
The
land contamination assessment examined the potential contaminated landuse
within the Project boundary and their potential impacts to the future landuse
in the Project. A Contamination
Assessment Plan (CAP) (and a Supplementary CAP) and Contamination Assessment
Report (CAR) were prepared in accordance with Section 3.4.5 of the EIA Study
Brief No: ESB-188/2008.
3.9.1.2
The
findings of the land contamination assessment indicated that there was no
exceedance of the relevant Risk-based Remediation Goals (RBRGs) of the soil and
groundwater samples collected in this study.
3.9.1.3
As there is an existing kerosene store at
3.10.1.1
It is recognised that, from a
risk point of view, blasting is not a desirable construction method. However, due to foreseen ground conditions
and the impracticability in using other techniques, drill and blasting for rock
excavation is required for some sections along the alignment. To enable a timely delivery of explosives to site and in order to meet
the proposed construction work programme, a temporary Explosives Storage
Magazine (Magazine) is required.
3.10.1.2
A
Quantitative Risk Assessment (QRA) for the storage and transport of explosives
has been carried out as per the EIA Study Brief No. ESB-188/2008 (EIA Study
Brief). A robust site selection process
has been undertaken for the proposed temporary magazine and Tseung Kwan O (TKO)
Area 137 has been identified as the only practicable site. The criterion of the EIAO-TM for Individual
Risk has been met. The assessment
results show that the societal risk lies within the As Low As Reasonably Practicable
(ALARP) region when compared to the criteria stipulated in Annex 4 of the
EIAO-TM. An ALARP assessment has been
carried out by identifying all practicable mitigation measures and assessing
the cost effectiveness of each measure in terms of the risk reduction achieved
and the cost of implementing the measures.
As part of the ALARP assessment, TKO Area 137 has been confirmed as the
only practicable site.
4.1.1.1
An
environmental monitoring and audit (EM&A) programme will be implemented
during the construction and operation of the Project, to check effectiveness of
the recommended mitigation measures and compliance with relevant statutory
criteria.
5.1.1.1
This
EIA study has identified and assessed potential environmental impacts of the
Project, in accordance with the EIA study brief and EIAO-TM guidelines. Overall, the EIA study has concluded that the
Project would be environmentally acceptable, in compliance with environmental
legislation and standards. With the implementation
of environmental control measures during construction and operation phases,
there would be no adverse residual impacts from the Project. This will be checked by a comprehensive
environmental monitoring and audit programme.
Table 3.1: Impact
Summary
Assessment Points (e.g. ASRs, NSRs) |
Results of Impact Predictions and Relevant
Standards or Criteria |
Extent of Exceedance Predicted |
Impact Avoidance Measures Considered and Mitigation
Measures Proposed |
Residual Impacts after Mitigation |
Cultural
Heritage |
||||
There are no Sites of Cultural Heritage in
the study area of the Project |
The assessment followed the EIAO-TM. |
No identified impacts to Sites of Cultural
Heritage would be predicted. |
No mitigation would be required. |
Not applicable. |
Landscape
and Visual |
||||
LANDSCAPE RESOURCES Gascoigne Road Rest Garden, Yan Fung Street
Rest Garden, Fat Kwong Street Garden, Ping Chi Street Sitting Out Area, Lee Kung
Street Garden, Ko Shan Road Park, Hutchison Park, The Whampoa Garden, Whampoa
Garden Amenity Areas, Sports Pitches in the vicinity of Wylie Road,
Wuhu Street Temporary Playground, Fat Kwong Street Playground, King’s Park
High Level Service Reservoir Playground , Ho Man Tin Park and Leisure Centre,
Ho Man Tin East Service Reservoir Playground, Whampoa Garden Podium
Recreation Areas, Primary School Play Areas on Tak On Street, Tai Wan Shan
Swimming Pool, Slopes in the area of Chinese Methodist College, Slopes
adjacent to Chatham Road North, Slopes surrounding King’s Park High Level
Service Reservoir , Slopes surrounding Ho Man Tin East Service Reservoir,
Slopes surrounding Fat Kwong Street Playground, Street Planting at Gascoigne
Road, Street planting in the vicinity of Hung Hom Road, Tree planting on Tak
Man / Tak On Streets, Street planting in the vicinity of Hung Luen Road,
Roadside planting in the Princess Margaret Road Interchange, Planting at
Recreation Clubs around Gascoigne / Wylie Roads, Edge landscape at Harbour
Front Landmark, Landscape Gardens at Harbour Front Horizon, Slopes adjacent
to Yan Fung Street, Slopes surrounding Chung Hau Street, Slopes surrounding
Ho Man West Service Reservoir, Slopes surrounding Ho Man Tin East Service
Reservoir, Site formation levels for use by HOM Station, Future Poly U site
formation area, Residual Valley Road Estate site formations, Formation levels at King’s Park High Level Service Reservoir, Open
Space sites at LANDSCAPE
CHARACTER Area surrounding West of Ma Tau Wai Road -
Ho Man Tin, Hung Hom - Cross Harbour Links, Ho Man Tin - Valley Road Estate,
Yau Ma Tei and Jordan, Hung Hom around Wuhu Street, Whampoa and Hung Hom
Reclamations, Ho Man Tin Estate, Victoria Harbour Reclamation at TKO, VISUALLY SENSITIVE RECEIVERS Residents of towers on the west of Nathan Road, Residents of Parc
Palais, East facing units of Wylie Court, Residents on the south side of
Chatham Road North, Residents grouped at Wuhu Street and Gillies Avenue,
Residents at Ka Wai Chuen, Residents at Tsing Chau Street, Residents at Shun
Yung Street, Future residents of HK PolyU planned student dormitory,
Residents with surrounding views at Valley Road, Residents at Ho Man Tin
Estate South, Residents at Ko Shan Road, Residents of Whampoa Estate,
Residents of Harbourfront Landmark, Residents at Poly U Student Dormitory,
Residents of Harbour Place, Residents of Royal Peninsula, Future residents of
property development above HMT Station, Future residents of Valley Road
Estate development site, Users of Gascoigne Road
Rest Garden, Pedestrians and Shoppers in the vicinity of Gascoigne Road Rest
Garden Members and Visitors of India Club and
YMCA, Members and Visitors of Club de Recreio, Visitors of Kings Park Hockey
Ground, Visitors of Chinese Civil Servants Recreation Club and Philipino
Club, Recreation visitors at King’s Park Fresh Water Service Reservoir,
Recreation visitors at Ho Man Tin Park and Leisure Centre, Recreation users
at Ho Man Tin East Service Reservoir Playground, Users of Yan Fung Street
Rest Garden, Pedestrians around Fat Kwong Street Playground and Sitting Out
Area, Recreational users of Fat Kwong Street Playground, Pedestrians in and
around Fat Kwong Street Garden, Pedestrians and Shoppers in Whampoa Garden,
Pedestrians at Hong Kong Coliseum, Pedestrians on TST East Promenade, Hikers
at Clear Water Bay Country Park, Workers in commercial buildings on Nathan
Road, Staff and Guests of Eaton Hotel, Staff and students of Methodist
College, Staff of Queen Elizabeth Hospital Buildings, Staff of India Club and
YMCA, Staff of Club de Recreio Staff of Kings Park Hockey Ground, Staff of Chinese Civil Servants
Recreation Club and Philipino Club, Staff and Students of future Primary
School (under construction) at Staff of Ho Man Tin Leisure Centre, Staff of small businesses at
Valley Road, Workers at short term tenancy on Fat Kwong Street (Planned
dormitory of the Hong Kong Polytechnic University), Staff at Hung Hom Fire
Station, Staff and Students of Hung Hom Government Primary School, Staff at
Caritas College of Careers and Businesses on Wuhu Street, Staff of businesses
in Whampoa Garden, Staff and Students of S.K.H. Fung Kei Primary Schools,
Staff and Students of GCEPSA Whampoa Primary School, Office workers at Two
Harbourfront, Staff and Students at HK Poly U – Community College Campus,
Staff and Guests at Harbour View Horizon Hotel, Staff and Guests at Harbour
Front Horizon Hotel, Staff and Guests of Harbour Plaza Metropolis, Office
workers at International Mail Centre, Office/Hotel workers and guests at TST
East, Office workers at The Metropolis Tower, Staff and Students at HK Poly U
Lee Shau Kee Building, Circulating Traffic on Nathan and Gascoigne Roads Fast moving vehicles on Gascoigne Road, Road users on Wylie Road and
Wylie Path, Fast moving vehicles at Queen Margaret Road Interchange, Fast
moving vehicles on Chatham Road North, Road users on Chung Hau Street,
Temporary parking users on future development site, Road users on Fat Kwong
Street, Road users on Yan Fung Street, Road users on Tak Man / Tak On Street,
Road users on Hung Hom Road (east section), Road users on Whampoa Estate side
streets, Road users on Hung Lok Road and Yan Yung Street, Road users on Hung
Hom Road (west section), Road users on Salisbury Road, Travellers on Victoria
Harbour, Recreational boat traffic at Tai Mui Wan. |
The assessment followed the EIAO-TM and EIAO Guidance Note No. 8/2002 LANDSCAPE RESOURCES During both the Construction and Operational Phases Significant Adverse Landscape Impacts are
anticipated at Slopes adjacent to LANDSCAPE
CHARACTER Approximately
1,000 existing trees affected. During
both the Construction and Operational Phases Moderate Adverse Impacts to Landscape Character are anticipated
at Ho Man Tin - Valley Road Estate (LCA-6). VISUALLY SENSITIVE RECEIVERS A total of 77 VSRs are
identified within the project. During
the Construction Phase Significant
Visual Impacts are anticipated to 22 of these VSR's. During Operational Phase Significant Impacts would
remain only to Residents on the south side of |
N/A |
Construction
Phase Reuse
of Existing Topsoil; Tree
Transplantation; Control
of night-time lighting glare, however, currently no night-time working is
proposed and Decoration
of Hoarding. Operation
Phase Re-provision
of Public Open Spaces; Compensatory
Tree Planting of approximately 224 trees; Vertical
Greening; Horizontal
and Slope Greening; Design
Aesthetics for Above-Ground Structures for the WAB at Club de Recreio; Design
Aesthetics for Above-Ground Structures at HOM Station; Design
Aesthetics for Above-Ground Structures at WHA Station; |
LANDSCAPE RESOURCES Significant Adverse
Residual Landscape Impacts are anticipated at Slopes adjacent to Significant Adverse Residual Impacts are recorded at: Slopes adjacent to Slopes adjacent to LANDSCAPE
CHARACTER Moderate Adverse Impacts to
Landscape Character at Ho Man Tin
- Valley Road Estate (LCA-06)
are anticipated . At Day 1 of
Operation Negligible Character
Impacts prevail at Ho
Man Tin - Valley Road Estate (LCA-06).
By Year 10 of Operation Slight
Beneficial Landscape Character Impacts will be evidenced. VISUALLY SENSITIVE RECEIVERS Significant Adverse Residual Visual Impacts are anticipated during Construction Phase to Residents on the south side
of Chatham Road North (VSR-R4), Residents
grouped at Wuhu Street and Gillies Avenue (VSR-R5), Residents at Ka Wai Chuen (VSR-R6), Residents at Shun Yung
Street (VSR-R8), ), Future
Residents of HK PolyU Planned Student Dormitory (SVR-R9); Residents
at Valley Road
(VSR-R10); Residents of Whampoa Garden
(VSR-R13) Members and Visitors of Club de Recreio (VSR-L4), Visitors of Chinese Civil Servants Recreation Club and Philipino Club
(VSR-L6) and Shoppers in Whampoa
Garden (VSR-L14). At Day 1 of Operation no Significant
Impacts prevail. By Year 10 of Operation the most significant
visual impacts envisaged are Moderate Adverse at
Residents on the south side of |
Air
Quality |
||||
The ASRs included Tin Hau Temple, Tang’s
Mansion, Alhambra Building, Methodist College, Eaton Hotel, Diocesan Girls’
Junior School, Diocesan Girls’ School, Queen Elizabeth Hospital, Parc Palais,
Filipino Club, Hong Kong Chinese Civil Servants’ Association, Oi Man Estate,
SKH Holy Trinity Church Secondary School, Carmel Secondary School, Yee Fu
Building, 271-273 Chatham Road North, Caritas Bianchi College of Careers, Lok
Ka House, Wing Fung Building, Marigold Mansion, Lok Do Building, Hung Hom
Government Primary School, Hung Hom Government Clinic, Whampoa Garden,
Whampoa Estate, Fung Kei Millennium Primary School, Fung Kei Primary School,
Alliance Primary School, GCEPSA Whampoa Primary School, Harbourfront
Landmark, Harbourfront Horizon, Harbour Plaza Metropolis, Metropolis
Residence, Hong Kong Coliseum, Fire Service Headquarters |
The assessment followed the EIAO-TM. Potential dust impacts would be generated
from the excavation activities, material handling, wind erosion, stockpiles,
spoil removal, material delivery, and operation of the barging point during
the construction phase. |
The predicted maximum hourly and 24-hour
average TSP levels at the representative ASRs would comply with the statutory
requirement. However, some marginal
exceedances for the annual average TSP levels at the areas adjacent to the
HOM Station works site and Finger Pier works area are predicted. |
Fugitive dust impacts would be controlled
by the implementation of dust suppression measures as stipulated in the Air
Pollution Control (Construction Dust) Regulation, good site practices and
proposed mitigation measures. |
The residual impacts are assessed and
concluded as marginal, short-term and in most cases transient and have been
based upon worst case assumptions. It
is, also considered that the maximum practicable mitigation measures have
been applied to reduce the residual impacts to a minimum. Based upon these
factors, the residual impacts associated with the annual dust exceedances for
the KTE project within the study area would be considered minor and
acceptable. |
Air-borne
Noise |
||||
The NSRs included Alhambra Building,
Methodist College, Queen Elizabeth Hospital – Specialist Clinic, Primary School
at 10-12 Wylie Road (Planned Future NSR), Parc Palais, Carmel Secondary
School, Yee Fu Building, Marigold Mansion, Caritas Bianchi College of
Careers, Lok Ka House, Lok Do Building, Hung Hom Government Primary School,
Ki Fu Building, On Wah Building, , Whampoa Garden, Fung Kei Millennium
Primary School, GCEPSA Whampoa Primary School, Harbourfront Landmark,
Harbourfront Horizon, Residential Building, Ho Man Tin Station Development
(Planned Future NSR), Residential Building, Dormitory for The Hong Kong
Polytechnic University (Planned Future NSR), Yue Sun Mansion, 211 Chatham
Road North, Fung Kei Primary School, Wylie Court, Wing Fung Building and
Queen Elizabeth Hospital – School of General Nursing |
The assessment followed the EIAO-TM. Without mitigation, exceedances of the
criteria were predicted at some NSRs for the construction air-borne noise due
to the use of powered mechanical equipment.
The predicted operational noise levels arising from the noisy fixed plant
of the project such as ventilation building and shafts at the NSRs are
carefully assessed to comply with the EIAO-TM criteria provided that the
designed maximum allowable SWLs of the fixed plants are met. |
Without mitigation, the construction
air-borne noise levels would be anticipated to exceed the relevant criteria
by up to about 22dB(A) at some NSRs. |
Mitigation measures for the construction
air-borne noise included provision of quieter plants, silencers, noise
barriers, enclosures and insulating fabric and temporary road deck
covers. After these mitigation
measures are adopted, the noise levels at 17 NSRs (5 schools, 12 residential)
would subject to residual impacts of between 1-8dB(A); while 1 additional NSR
would be subject to potential exceedances during examination periods only. As such, all practicable noise mitigation
measures will be exhausted as far as possible to minimise the residual
impacts, e.g. good site practices such as orientating the noisy plant away
from the nearby NSRs, intermittent use of plant, proper fitting of silencers
and mufflers on the construction equipment, avoidance of noisy construction
works during the examination period etc.
|
Residual impacts have been assessed and
concluded to be temporary, reversible and unlikely to induce public health
concern and as such, are considered to be acceptable. |
Ground-borne
Noise |
||||
The NSRs included Kam Wah Building, New
King's Hotel, Tin Hau Temple, Tang's Mansion, Alhambra Building, Methodist College,
Eaton Hotel, Labour Tribunal, Diocesan Girl's Junior School, School of
General Nursing, Queen Elizabeth Hospital - Specialist Clinic, Primary School
at 10-12 Wylie Road (Planned Future NSR), Parc Palais, Oi Man Estate, SKH
Holy Trinity Church Secondary School, Yee Fu Building, Caritas Bianchi
College of Careers, Lok Ka House, Top Growth Court, 36 Wuhu Street, Block R,
Wing Fu Building, Whampoa Estate, Whampoa Garden, Fung Kei Millennium Primary
School, GCEPSA Whampoa Primary School, Harbourfront Landmark, Residential
Building, Ho Man Tin Station Development (Planned Future NSR), Residential
Building, Dormitory for The Hong Kong Polytechnic University (Planned Future
NSR), Yue Sun Mansion 191A Wuhu Street, 271-273 Chatham Road North and Wing
Fung Building |
The assessment followed the EIAO-TM. No exceedance was predicted for the
construction and operational ground-borne noise at all NSRs. |
Not applicable. |
No particular mitigation measures were
recommended. |
Not applicable. |
Water
Quality |
||||
The WSRs included East Rail Extension
Cooling Water Intake, Tai Wan WSD Flushing Water Intake, Victoria Harbour
Water Control Zone, To Kwa Wan Typhoon Shelter, King’s Park High Level
Service Reservoir, Ho Man Tin East Service Reservoir |
The assessment followed the EIAO-TM. Construction phase impacts would be
generated form the construction run-off from general construction activities,
wastewater discharge from tunnelling and excavation, potential impacts on
groundwater hydrology, and sewage effluent from construction workforce. Operational phase impacts would include the
run-off from rail track and operational tunnel drainage, station run-off, and
sewage from the stations operation. |
No exceedance would be predicted. |
Water quality impacts from land-based
construction activities would be controlled by implementing the recommended
mitigation measures, e.g. control measures on site run-off and drainage from
the works sites and barging points to minimise construction run-off,
tunnelling wastewater, and particularly on-site treatment of any contaminated
wastewater prior to discharge. During
the operational phase, track run-off, tunnel seepage and effluent discharges
from stations, ventilation buildings and maintenance activities would have no
adverse water quality impact provided that mitigation measures are
incorporated in the design. |
Residual impacts are not anticipated,
provided that the recommended mitigation measures are implemented. |
Waste
Management |
||||
All works sites and works areas. |
Construction waste arisings have been
identified based on the proposed construction activities and would comprise
C&D materials (including excavated materials, materials from demolition works
and site formation), general refuse from workforce, chemical waste from
maintenance of construction plant and equipment and sewage from on-site staff
and workers. The types of waste generated during the
operation of the KTE project would be general refuse from the passengers,
staff and any commercial operators at HOM Station and WHA Station, general
refuse from the ventilation building and ventilation shafts, industrial waste
from the maintenance activities and chemical waste from operational activities. The handling, collection, transportation
and disposal practices of the identified waste generated should follow the
current practices at other operating railway lines and hence would pose no
impact. Provided that the identified waste arisings
are to be handled, transported and disposed of using approved methods and the
recommended good site practices are to be followed, adverse environmental
impacts would not be expected during the construction phase. |
No exceedance would be predicted. |
Methods to minimise the generation of waste
have been investigated which focus on the construction methods of tunnels,
ventilation building and shafts, and stations. Under the condition of limited works sites
approved for construction use of the project, delivery of soft materials for
reuse and stockpiling on-site would be considered and used as far as
practicable. The off-site reuse at
other projects has also been explored, e.g. Hong Kong-Zhuhai-Macao Bridge
(HZMB) Hong Kong Boundary Crossing Facilities and Tuen Mun Chek Lap Kok Link,
which would require a substantial amount of filling materials. With the implementation of the recommended
mitigation measures in Section 10
of this EIA Report, no adverse environment impacts would be expected. |
Not applicable. |
Land
Contamination |
||||
Sampling points were located at the
existing slope beneath Concord kerosene store at Chung Hau Street, pedestrian
parts of Hung Hom Road at Whampoa Estate adjacent to Ka Fu Building,
pedestrian area at Shung King Street adjacent to The Whampoa (the ship), and
pedestrian area at the junction of Tak On Street and Tak Ting Street at
Whampoa Garden. |
The assessment followed the EIAO-TM. There was no exceedance of the RBRGs for
all soil and groundwater samples tested.
There is an existing |
There was no exceedance of the RBRGs for
all soil and groundwater samples tested.
|
No remedial action would be required. |
Not applicable. |
Hazard
to Life |
||||
N/A |
The assessment followed the EIAO-TM. The criterion for Individual Risk has been
met. The assessment results show that
the societal risk lies within the As Low As Reasonably Practicable (ALARP)
region when compared to the criteria stipulated in Annex 4 of the
EIAO-TM. An ALARP assessment has been
carried out by identifying all practicable mitigation measures. |
N/A |
As part of the ALARP assessment, a list of
25 potential temporary magazine site candidates have been reviewed and the TKO
Area 137 has been confirmed as the only practicable site. |
N/A |