This chapter presents the implementation schedule of the proposed mitigation measures for the Project. Table 14.1 summarises the details of the mitigation measures for all works areas. For each recommended mitigation measure, both the location and timing for the measure have been clearly identified. As well, the parties responsible for implementing the measure and for maintenance (where applicable) have also been clearly identified.
Table 14.1: Implementation Schedule of Mitigation Measures
EIA Ref. |
EM&A Ref. |
Recommended Mitigation Measures |
Objectives of the Recommended Measure & |
Who to implement the measure? |
Location of the measure |
When to implement the measure? |
What requirements or standards for the measure to achieve? |
Noise Impact (Construction Phase) |
|||||||
|
|
Airborne |
|
|
|
|
|
3.4.1.4 |
2 |
Adoption of Quieter PME The
recommended quieter |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.1.4 |
2 |
Use of Movable Noise Barrier The
use of movable barrier for certain PME can further alleviate the construction
noise impacts. In general, a 5 dB(A) reduction for movable PME and 10 dB(A)
for stationary PME can be achieved depending on the actual design of the
movable noise barrier. The Contractor shall be responsible for design of the
movable noise barrier with due consideration given to the size of the PME and
the requirement for intercepting the line of sight between the NSRs and PME.
Barrier material with surface mass in excess of 7 kg/m2 is
recommended to achieve the predicted screening effect. |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.1.4 |
2 |
Use of Noise Enclosure/ Acoustic Shed The
use of noise enclosure or acoustic shed is to cover stationary PME such as
air compressor and concrete pump. With
the adoption of the noise enclosure, the PME could be completely screened,
and noise reduction of 15 dB(A) can be achieved according to the GW-TM. |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.1.4 |
2 |
Use of Silencer To
reduce noise emission from the ventilation fans, silencers are also recommended
to be used in fan ventilation system to attenuate noise generated during fan
operation to achieve a noise reduction of 15 dB(A). |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.1.4 |
2 |
Use of Noise Insulating Fabric Noise
insulating fabric (the Fabric) can also be adopted for certain PME (e.g.
drill rig, pilling auger etc). The
Fabric should be lapped such that there are no openings or gaps on the joints.
Technical data from manufacturers state that by using the Fabric, a noise
reduction of over 10 dB(A) can be achieved on noise level. |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.1.4 |
2 |
Good Site Practice The good site practices listed below should be followed during each phase of construction: ·
Only well-maintained plant should be operated on-site
and plant should be serviced regularly during the construction programme; ·
Silencers or mufflers on construction
equipment should be utilized and properly maintained during the construction
programme; ·
Mobile plant, if any, should be sited as far
from NSRs as possible; ·
Machines and plant (such as trucks) that may
be in intermittent use should be shut down between work periods or should be
throttled down to a minimum; ·
Plant known to emit noise strongly in one
direction should, wherever possible, be orientated so that the noise is
directed away from the nearby NSRs; and ·
Material stockpiles and other structures
should be effectively utilized, wherever practicable, in screening noise from
on-site construction activities. |
To minimize the construction air-borne noise impact |
Contractors |
Construction Work Sites |
During Construction |
EIAO and NCO |
3.4.2.5 |
|
Ground-borne |
|
|
|
|
|
|
2 |
PME that is in intermittent use should be shut down between work periods or should be throttled down to a minimum. |
To minimize the construction ground-borne noise impact |
Contractors |
Tunnel site
near Lei Tung Station |
During Construction |
NCO |
Noise Impact (Operation Phase) |
|||||||
|
|
Airborne |
|
|
|
|
|
|
|
Railway
Noise |
|
|
|
|
|
3.5.1.1 |
2 |
Erection of noise barrier/ enclosure along the viaduct section as shown in Table 3.52 and illustrated in Figures 3.25 to 3.27. For the ‘Further Mitigation Measures for Existing and Planned NSRs’, additional noise barriers/semi-enclosures have been recommended for viaduct sections shown in Table 3.57 and illustrated in Figure 3.28 to 3.30. The viaduct structure should allow further installation of noise barrier or enclosure at the later commissioning stage, if required. |
To minimize the railway airborne noise along the viaduct section of SIL(E) |
MTRC / Contractor |
West of ex-Canadian Hospital site, West of Ocean Park G/IC site, East and West of Wong Chuk Hang Residential Zone, along Wong Chuk Hang Nullah and along Ap Lei Chau Bridge as shown in Figure 3.25 to Figure 3.30. |
Before Operation |
EIAO and NCO |
|
|
Fixed Plant Noise |
|
|
|
|
|
3.5.1.2 |
2 |
The following noise reduction measures shall be considered as far as practicable during construction: · Choose quieter plant such as those which have been effectively silenced; · Include noise levels specification when ordering new plant (including chillier and E/M equipment); · Locate fixed plant/louver away from any NSRs as far as practicable; · Locate fixed plant in walled plant rooms or in specially designed enclosures; · Locate noisy machines in a basement or a completely separate building; · Install direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosure where necessary; and · Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain a controlled level of noise. |
To minimize the fixed plant noise impact |
MTRC |
All stations, entrances, and ventilation buildings |
Before Operation |
EIAO and NCO |
|
|
Ground-borne |
|
|
|
|
|
3.5.2.3 |
2 |
Using of incline turnout (a 5 dB(A) reduction in turnout and crossing vibration) and Type 1a resilient baseplated trackform within the SOH station. |
To minimize the railway ground-borne noise impact |
MTRC / Contractor |
South Horizons Station |
Before Operation |
EIAO and NCO |
Ecological
Impact (Construction Phase) |
|||||||
|
|
Habitat
Loss |
|
|
|
|
|
4.7.1 |
3 |
Minimise habitat loss particularly woodland as far as possible. |
Minimize habitat loss |
Contractors |
Construction Work Sites |
During Construction |
Annex 16 of EIAO-TM |
4.7.1 |
3 |
Temporary disturbed woodland should be reinstated in full after the completion of works |
To reinstate disturbed woodland habitats |
Contractors |
Construction Work Sites |
After completion of construction works |
Annex 16 of EIAO-TM; ETWB TCW No. 2/2004 (for maintenance arrangement of vegetation) |
4.7.1 |
3 |
Degraded woodland and shrubland should be reinstated after the completion of works as far as possible. |
To reinstate disturbed habitats |
Contractors |
Construction Work Sites |
After completion of construction works |
Annex 16 of EIAO-TM; ETWB TCW No. 2/2004 (for maintenance arrangement of vegetation) |
4.7.1 |
3 |
Habitat Compensation of permanent loss of woodland in full in terms of area. |
To compensate permanent loss of woodland |
Contractors |
Construction Work Sites |
After completion of construction works |
Annex 16 of EIAO-TM; ETWB TCW No. 2/2004 (for maintenance arrangement of vegetation) |
|
|
Ardeid
Night Roost |
|
|
|
|
|
4.7.2.1 |
3 |
Avoidance of Site Clearance and Tree
Felling Works at Wintering Season Site
clearance and tree felling works at the existing ardeid night roost (location
described in Figure 4.15) should only be carried out at non-wintering
season (March to November inclusive). Demarcating clearly the works area and
ensuring good site practise to avoid unnecessary disturbance to the ardeids
during construction phase. |
Avoid and minimize impact on peak period of ardeid roosting |
Contractor |
Construction Work Sites |
During Construction |
Annex 16 of EIAO-TM |
4.7.2.1 and 4.7.2.4 |
3 |
Compensate for loss of roosting trees
with replanting of suitable trees The compensatory planting with suitable, heavy
standard trees should be located at the lower course of the WCH Nullah
approximately 200m west of the existing night roost (location shown in Figure 4.15). Trees should be
replanted after construction
alongside the nullah to provide a substrate for roosting. |
To compensate for permanent loss of roosting trees |
Contractors, advised by Ecologist |
Construction Work Site at Wong Chuk Hang |
After completion of construction works |
Annex 16 of EIAO-TM; ETWB TCW No. 2/2004 (for maintenance arrangement of vegetation) |
4.7.2.1 |
3 |
Inspection of ardeid night roost for
active ardeid nests When
conducting site clearance works at the existing ardeid night roost, the area
should be inspected to confirm no active ardeid nest are present. If any active bird nest is observed,
suitably sized buffer area should be established to minimize human or
machinery disturbance until the nest is abandoned. Also
the site should be monitored monthly to check the updated status. |
Ensure no impact on active ardeid nests |
Contractors, advised by Ecologist |
Construction Work Site at Wong Chuk Hang |
During Construction |
Wild Animals Protection Ordinance (Cap. 170) |
4.7.2.2 |
3 |
Avoidance of Construction Activities at
Sunset Time Construction activities using PME at the potential ardeid night roost (location shown in Figure 4.13) should be ceased at 18:00 – 06:00 to avoid disturbance to the night roost ardeids. |
Minimize noise impact on ardeid roosting and foraging |
Contractor |
Construction Work Sites |
During Construction |
Annex 16 of EIAO-TM |
4.7.2.4 |
3 |
Coloured Panels on Noise Barriers The acoustic enclosure/ barrier should be designed with coloured panels to minimize the chance of bird collision. |
To minimise the potential for bird strike |
Contractors |
Construction Work Sites |
During Construction |
Annex 16 of EIAO-TM; |
4.7.3 |
3 |
Magazine Site Implement good site practice including
containment of silt runoff within the site boundary, containment of contaminated
soils, appropriate storage of chemicals and wastes. |
Avoid impacts to fauna species and water pollution |
Contractor |
Chung Hom Shan Magazine Site |
During Construction |
ProPECC Note PN 1/94 Waste Disposal Ordinance (Cap.354) |
4.7.4 |
3 |
Coral Community at A bridge pier construction method in which a cofferdam would be installed to create a confined dredging environment should be implemented to minimise potential impacts from suspended solid release. Good site practices should be applied to land-based construction works including containment of silt runoff within the site boundary, the containment of contaminated soils for removal from the site and appropriate storage of chemicals and chemical waste. |
Avoid release of suspended solid and contaminated runoff to Aberdeen Channel |
Contractors |
Dredging/ excavation area required for installation of the pier/pier foundations of bridge in Aberdeen Channel |
During marine construction works |
WQOs & ProPECC Note PN 1/94 |
4.7.5 |
3 |
Floral Species of Conservation Interest Transplanting all affected floral species of conservation interest identified in the EcoIA. In-situ preservation should be re-considered throughout all stages of the project. |
Mitigate the removal impact on floral species of conservation interest |
Contractors |
Construction Work Sites |
During Construction |
Annex 16 of EIAO-TM; |
Water
Quality Impact (Construction) |
|||||||
5.7.1.1 |
4 |
Dredging/ Excavation and Seawall modification
for construction of piers/pier foundations of bridge in To minimise the loss of fine sediment to suspension, steel pile casing and watertight cofferdam should be installed and seawater trapped inside the casing and cofferdam should be pumped out to generate a dry working environment prior to carrying out sediment dredging/ excavation. The water from the dewatering should be appropriately treated with desilting or sedimentation device before discharge. Silt curtains should be deployed to completely enclose the cofferdam installation and removal works and the seawall modification and pile installation works respectively. |
Avoid spillage of sediment |
MTRC / Contractor |
Dredging/ excavation area required for installation of the pier/pier foundations of bridge in Aberdeen Channel |
During marine construction works |
WQOs & ProPECC Note PN 1/94 |
5.7.1.2 |
4 |
Barging
Facilities and Activities To minimise the release of suspended solids to marine waters, silt curtain should be deployed to completely enclose the marine piles works during installation and decommissioning. Good site practices for operation of barging points should be followed, including appropriate sizing of vessels to ensure adequate clearance between the vessel and the seabed, controlled loading and unloading of barges and hoppers to prevent splash, installing tight fitting seals to the bottom openings to prevent leakage, and measures to prevent foam, oil, grease, scum or litter on the water within the site. |
To minimize suspended solids and water quality impacts |
MTRC / Contractor |
Barging point marine works area |
During marine construction works |
WQOs & ProPECC Note PN 1/94 |
5.7.1.3 |
4 |
Sewage
Effluent from Construction Workforce Temporary sanitary facilities, such as portable chemical toilets, should be employed on-site where necessary to handle sewage from the workforce. A licensed contractor should be employed to provide appropriate and adequate portable toilets and be responsible for appropriate disposal and maintenance. |
To minimize water quality impacts |
MTRC / Contractor |
All works areas with on-site sanitary facilities |
During Construction |
Water Pollution Control Ordinance |
5.7.1.4 |
4 |
Wastewater
Discharge from Tunnelling
and Open Cut Excavation Wastewater with a high level of suspended solids should be treated before discharge by settlement in tanks with sufficient retention time. Oil interceptors would be required to remove the oil, lubricants and grease from wastewater. Should the level of suspended solids be very high, an on-site pre-packaged treatment plant might be required with the addition of flocculants to improve the settlement of solids. A discharge licence under the WPCO would be required for discharge to stormwater drain. |
To minimize water quality impacts |
MTRC / Contractor |
All works areas |
During Construction |
Water Pollution Control Ordinance |
5.7.1.5 |
4 |
Construction
Site Runoff and Drainage The site practices outlined in ProPECC Note PN 1/94 should be followed as far as practicable in order to minimise surface runoff and the chance of erosion. The following measures are recommended to protect water quality and sensitive uses of the coastal area i.e. WSD seawater intakes along the Aberdeen Channel: |
To minimize water quality impacts |
MTRC / Contractor |
All works areas |
During Construction |
ProPECC Note PN 1/94 |
|
|
· At the start of site establishment (including the barging facilities), perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works and erosion and sedimentation control facilities implemented. Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities. The design of the temporary on-site drainage system should be undertaken by the Contractor prior to the commencement of construction. |
|
|
|
|
|
|
|
· The dikes or embankments for flood protection should be implemented around the boundaries of earthwork areas. Temporary ditches should be provided to facilitate the runoff discharge into stormwater drainage system through a sediment/silt trap. The sediment/silt traps should be incorporated in the permanent drainage channels to enhance deposition rates, if practical. |
|
|
|
|
|
|
|
· Sand/silt removal facilities such as sand/silt traps and sediment basins should be provided to remove sand/silt particles from runoff to meet the requirements of the TM standards under the WPCO. The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC Note PN 1/94. Sizes may vary depending upon the flow rate. The detailed design of the sand/silt traps should be undertaken by the Contractor prior to the commencement of construction. |
|
|
|
|
|
|
|
· All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly during rainstorms. Deposited silt and grit should be regularly removed, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times. |
|
|
|
|
|
|
|
· Measures should be taken to minimize the ingress of site drainage into excavations. If excavation of trenches in wet periods is necessary, they should be dug and backfilled in short sections wherever practicable. Water pumped out from foundation excavations should be discharged into storm drains via silt removal facilities. |
|
|
|
|
|
|
|
· If surface excavation works cannot be avoided during the wet season (April to September), temporarily exposed slope/soil surfaces should be covered by tarpaulin or other means, as far as practicable, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds. Interception channels should be provided (e.g. along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces. |
|
|
|
|
|
|
|
· The overall slope of the site should be kept to a minimum to reduce the erosive potential of surface water flows. |
|
|
|
|
|
|
|
· All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads. An adequately designed and sited wheel washing facility should be provided at construction site exit where practicable. Wash-water should have sand and silt settled out and removed regularly to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains. |
|
|
|
|
|
|
|
· Open stockpiles of construction materials or construction wastes on-site should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system. |
|
|
|
|
|
|
|
· Manholes (including newly constructed ones) should be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and stormwater runoff being directed into foul sewers. |
|
|
|
|
|
|
|
· Precautions should be taken at any time of the year when rainstorms are likely. Actions should be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarized in Appendix A2 of ProPECC Note PN 1/94. Particular attention should be paid to the control of silty surface runoff during storm events, especially for areas located near steep slopes. |
|
|
|
|
|
|
|
· Bentonite slurries used in piling or slurry walling should be reconditioned and reused wherever practicable. Temporary enclosed storage locations should be provided on-site for any unused bentonite that needs to be transported away after all the related construction activities are completed. The requirements in ProPECC Note PN 1/94 should be adhered to in the handling and disposal of bentonite slurries. |
|
|
|
|
|
5.7.1.6 |
4 |
General
Construction Activities Construction solid waste, debris and refuse generated on-site should be collected, handled and disposed of properly to avoid entering any nearby stormwater drain. Stockpiles of cement and other construction materials should be kept covered when not being used. Oils and fuels should only be stored in designated areas which have pollution prevention facilities. To prevent spillage of fuels and solvents to any nearby stormwater drain, all fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank. The bund should be drained of rainwater after a rain event. |
To minimize water quality impacts |
MTRC / Contractor |
All works areas |
During Construction |
EIA Recommendation |
Water
Quality Impact (Operation) |
|||||||
5.7.2.1 |
4 |
Change
in flow regime and hydrology in Streamline shaped bridge pier to reduce friction to the tidal flows across the Aberdeen Channel should been considered in the conceptual design of the bridge form. |
To minimize water quality impacts |
MTRC / Detailed Design Consultant |
Pier/pier foundations of bridge in Aberdeen Channel |
During Detailed Design |
EIA Recommendation |
5.7.2.3 |
4 |
Sewage
and wastewater effluents from stations and depot · Runoff and spillage prevention measures should conform to relevant engineering and design standards. Any opportunities for the recycling of water within the automatic washing facilities should be sought to minimise discharge requirements. Bio-degradable detergents should be selected to minimise the impact on water quality and associated ecosystems of the receiving water bodies. |
To minimize water quality impacts |
MTRC |
SIL(E) Stations & WCH Depot |
During Operation |
WPCO |
|
|
· Plant maintenance areas should be bunded and constructed on an impermeable floor, and provided with petrol interceptors. Traps and interceptors should be regularly cleaned and maintained, especially after any accidental spillages. Layers of sawdust, sand or equivalent material should be laid underneath and around any plant and equipment that may possibly leak oil. |
|
|
|
|
|
|
|
· An emergency spillage action plan should be developed for the Depot to ensure that any accidental spillage event is treated immediately and does not impact on any water bodies. |
|
|
|
|
|
|
|
· All fuel tanks and storage areas within the Depot should be provided with locks and be located on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank, to prevent the escape of spilled fuel oils. |
|
|
|
|
|
|
|
· Waste oil and other chemicals must be disposed by a licensed contractor to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation (Cap 354). |
|
|
|
|
|
5.7.2.4 |
4 |
Runoff
from rail tracks · Track drainage channels discharge should pass through oil/grit interceptors/chambers to remove oil, grease and sediment before being pumped to the public stormwater drainage system. |
To minimize water quality impacts |
MTRC |
Along the SIL(E) tracks |
During Operation |
WPCO |
|
|
· Silt traps and oil interceptors should be cleaned and maintained regularly. |
|
|
|
|
|
|
|
· Oily contents of the oil interceptors should be transferred to an appropriate disposal facility, or to be collected for reuse, if possible. |
|
|
|
|
|
Landscape
and Visual Impact (Construction Phase) |
|||||||
Table 6-13 |
Preservation of Existing Vegetation |
|
|
|
|
|
|
CP1.1 |
5 |
To retain trees, which
have high amenity or ecology value and contribute most to the landscape and
visual amenity of the site and its immediate environs. |
To minimise the disturbance to the existing landscape resources. |
Project Landscape Architect (Detailed Design Consultants)/ Contractor |
Site |
Throughout design phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.2 |
5 |
Creation
of precautionary area around trees to be retained equal to half of the trees canopy
diameter. Precautionary area to be fenced. |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Before construction phase commence |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.3 |
5 |
Prohibition
of the storage of materials including fuel, the movement of construction
vehicles, and the refuelling and washing of equipment including concrete
mixers within the precautionary area. |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.4 |
5 |
Phased
segmental root pruning for trees to be retained and transplanted over a suitable
period (determined by species and size) prior to lifting or site formation
works which affect the existing rootball of trees identified for retention.
The extent of the pruning will be based on the size and the species of the
tree in each case. |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.5 |
5 |
Pruning
of the branches of existing trees identified for transplantation and
retention to be based on the principle of crown thinning maintaining their
form and amenity value. |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.6 |
5 |
The
watering of existing vegetation particularly during periods of excavation
when the water table beneath the existing vegetation is lowered. |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.7 |
5 |
The
rectification and repair of damaged vegetation following the construction phase
to it’s original condition prior to the commencement of the works or
replacement using specimens of the same species, size and form where
appropriate to the design intention of the area affected |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.8 |
5 |
All
works affecting the trees identified for retention and transplantation will
be carefully monitored. This includes the
key stages in the preparation of the trees, the implementation of protection
measures and health monitoring through out the construction period |
To ensure the success of the tree
preservation proposals. |
Contractor |
Site |
Throughout construction phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.9 |
5 |
Detailed landscape and tree preservation
proposals will be submitted to the relevant government departments for
approval under the lease conditions and in accordance with ETWB TCW No.
2/2004 and 3/2006. |
To
ensure the tree preservation and planting proposals are integrated with the
existing landscape context and that the landscape resources are preserved
where appropriate. |
Project Landscape Architect (Detailed Design Consultants) |
Site |
Throughout
design phase |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP1.10 |
5 |
The
tree preservation works should be implemented. A tree protection specification
would be included within the contract documents. |
To ensure the tree preservation and planting
proposals are integrated with the existing landscape context and that the
landscape resources are preserved where appropriate. |
Project Proponent |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
Table 6-13 |
Works Area and Temporary Works Areas |
|
|
|
|
|
|
CP2.1 |
5 |
Where
appropriate to the final design the landscape of these works areas should be
restored following the completion of the construction phase. |
To minimise the disturbance to existing
landscape resources and change of visual amenity. |
Contractor |
Site |
Through out construction phase |
TM-EIA Annex 18 |
CP2.2 |
5 |
Construction
site controls should be enforced including the storage of materials, the
location and appearance of site accommodation and the careful design of site lighting
to prevent light spillage. |
To minimise the disturbance to existing
landscape resources and change of visual amenity. |
Contractor |
Site |
Through out construction phase |
TM-EIA Annex 18 |
CP2.3 |
5 |
Screen
the works area during the construction phase through the use of decorative
hoarding along the site boundary facing adjacent VSRs |
To minimise the disturbance to existing
landscape resources and change of visual amenity. |
Contractor |
Site |
Through out construction phase |
TM-EIA Annex 18 |
Table 6-13 |
Implementation of Mitigation Planting and planting species selection
|
|
|
|
|
|
|
CP3.1 |
5 |
Replanting
of disturbed vegetation should be undertaken at the earliest possible stage of
the construction phase. |
To minimise the disturbance to existing
landscape resources and minimize the impacts on the visual amenity of the
area. |
Contractor |
Site |
After the site formation and on completion
of planting area. |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP3.2 |
5 |
Use
of native plant species predominantly in the planting design for the buffer
areas. |
To enhance the local landscape and
ecological value. |
Project Landscape Architect (Detailed Design
Consultants) |
Site |
After the site formation and on completion
of planting area. |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP3.3 |
5 |
Proposed
mitigation planting shall not only limit to conventional amenity planting, but
also considered alternative greening measures such as vertical greening for
screening or soften the built structures. Small shrubs, climbing plants,
grass and groundcovers shall be used in specific locations according to site
condition and at where would not interfere the operation of railway and its
associated facilities. |
To maximise the planting opportunities |
Project Landscape Architect (Detailed Design
Consultants) |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP3.4 |
5 |
The
tree planting works should be implemented by approved Landscape Contractors
and inspected and approved on site by a qualified Landscape Architect. A tree
planting specification would be included within the contract documents. |
To ensure the tree preservation and planting
proposals are integrated with the existing landscape context and that
valuable landscape |
Project Proponent |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
Table 6-13 |
Transplantation of Existing Trees |
|
|
|
|
|
|
CP4.1 |
5 |
The
tree transplanting works should be implemented by approved Landscape Contractors
and inspected and approved on site by a qualified Landscape Architect. A tree
protection / transplanting specification would be included within the
contract documents. |
To ensure the tree preservation and planting
proposals are integrated with the existing landscape context and that
valuable landscape resources are preserved where appropriate to the final
design. |
Project Proponent / Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.2 |
5 |
Approximately
437 existing trees to be transplanted, majority of them shall be relocated to
off-site planting areas. The final recipient sites should be, as far as space
allows, adjacent to their current locations alongside of the alignment. |
To retain their contribution to the local
landscape context. |
Project Landscape Architect (Detailed Design
Consultants)/ Contractor / Project
Proponent (planting areas associated with station and alignment)/ LCSD
(roadside and park areas) |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.3 |
5 |
Tree
to be transplanted to planting areas identified in the “Southern District Greening
Master Plan” shall be, as far as programme allows, directly relocated to
their final recipient sites. |
To minimise the disturbance to the landscape
resources. |
Project Landscape Architect (Detailed Design
Consultants)/ Contractor / Project
Proponent (planting areas associated with station and alignment)/ LCSD
(roadside and park areas) |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.4 |
5 |
Tree
to be replanted along the alignment shall be kept in the temporary holding
nurseries which closely monitoring by landscape contractor. |
To enhance the survivals of the transplanted
trees |
Project Landscape Architect (Detailed Design
Consultants)/ Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.5 |
5 |
The
implementation programme for the proposed works should reserve enough time
for the advance tree transplanting preparation works. |
To
enhance the survivals of the transplanted trees |
Project Proponent/ Project Landscape
Architect (Detailed Design Consultants)/
Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.6 |
5 |
The
implementation programme for the proposed works should reserve enough time
for the advance tree transplanting preparation works. |
To enhance the survivals of the transplanted
trees |
Project Proponent/ Project Landscape
Architect (Detailed Design Consultants)/
Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
CP4.7 |
5 |
The
tree transplanting works should be implemented by approved Landscape Contractors
and inspected and approved on site by a qualified Landscape Architect. A tree
protection specification would be included within the contract documents. |
To enhance the survivals of the transplanted
trees |
Project Proponent/ Project Landscape Architect
(Detailed Design Consultants)/
Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18, ETWB TCW No.
3/2006 & 2/2004 |
Table 6-13 |
Coordination with Concurrent Projects |
|
|
|
|
|
|
CP5.1 |
5 |
Coordinated
implementation programme with concurrent projects |
To minimise potential impact where possible reduce the period of disturbance. |
Project Proponent / Project Landscape Architect (Detailed Design Consultants)/ Contractor |
Site |
Throughout design and construction phases |
TM-EIA Annex 18. |
Landscape
and Visual Impact (Operation Phase) |
|||||||
Table 6-14 |
Design of Engineering and Building
Structures |
|
|
|
|
|
|
OP1.1 |
5 |
Where
possible integrate the engineering and building structures, as far as
technically feasible, with existing built structures. Select responsive The
locations for the associated facilities away from landscape and visually
sensitive areas. |
To ensure the proposals are integrated with
the existing landscape and visual context, and avoid cluster effect. |
Project Engineer and Architect (Detailed Design Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP1.2 |
5 |
Use
of a responsive design for the disposition of the main elements including the
locations of the proposed above ground structures. |
To ensure the proposals are integrated with
the existing landscape and visual context, and avoid cluster effect. |
Project Engineer and Architect (Detailed Design Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP1.3 |
5 |
The
disposition and height profile of the proposed ground structures should
respond to the existing context. |
To enhance the sense
of visual integration with the existing context, avoid abrupt transitions
between the existing and proposed built environment and reduce the apparent
visual mass of the proposed developments.
|
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP1.4 |
5 |
Creation
of setbacks, articulating the development frontage, maintenance of view
corridors and the utilisation of stepped or articulated height profile. |
To enhance the sense
of visual integration with the existing context, avoid abrupt transitions
between the existing and proposed built environment and reduce the apparent
visual mass of the proposed developments.
|
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP1.5 |
5 |
Use
of natural materials such as colour blocking, innovative surface treatments
and vertical greening. |
To reduce the
apparent visual mass of the facilities. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18, HKPSG and
BD |
OP1.6 |
5 |
Use
of natural materials such as colour blocking, innovative surface treatments
and vertical greening. |
To reduce the
apparent visual mass of the facilities. |
Project Engineer and
Architect (Detailed Design
Consultants)/ Project Proponent |
Site |
Throughout design phase |
TM-EIA Annex 18, HKPSG and
BD |
OP1.7 |
5 |
Use
of natural tones colour palette and non-reflective materials for outward
facing building facades finishes. |
To reduce the
potential glare effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18, HKPSG and
BD |
OP1.8 |
5 |
Incorporation
of landscaped terraced edges where conditions allow particularly those
fronting the public realm. |
To reduce the
apparent visual mass of the structure and create a more subtle transition
with the pedestrian level streetscape.
|
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18, HKPSG and BD |
OP1.9 |
5 |
Aesthetic
design of architectural and track lighting sign shall follow the following
design intention. -
Directional and full cut off lighting is recommended particularly for
recreation and roadside areas; - Minimize
geographical spread of lighting, only applied for safety at the key access
points and staircases; -
Limited lighting intensity to meet the minimum safety and operational
requirement; and -
High-pressure sodium road lighting is recommended for more stringent light
control. |
To reduce the
night-time glare effect to the surrounding environs, reducing spillage and
thus visual impacts. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Through out operation phase |
TM-EIA Annex 18 |
Table 6-14 |
Roadside and Amenity Planting |
|
|
|
|
|
|
OP2.1 |
5 |
Utilise large ornamental trees to maximise
the area of visible greenery, soften the interface between the proposed scheme
and adjacent urban fabric and enhance the thermal comfort of adjacent spaces. |
Provide a linkage
with the existing landscape creating a more coherent landscape framework. |
Project Landscape
Architect(Detailed Design Consultants)/ Project Proponent |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG
and BD |
OP2.2 |
5 |
Planting
proposals should respond to the need for visual access in the views from the adjacent
neighbourhoods to the roadside or rural landscape. Whereas dense foliage
plants shall be provided at other locations to screen and frame views,
provide a more shaded environment for pedestrians and provide accents within
the existing roadside planting. |
Conserve and enhance
the landscape interest. |
Project Landscape
Architect(Detailed Design Consultants)/ Project Proponent |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG
and BD |
OP2.3 |
5 |
The
planting on sloping ground and areas adjacent to existing woodland shall
utilise native species. |
Improving the
ecological connectivity between existing woodland habitats and creating a
more unified and coherent landscape framework. |
Project Landscape Architect(Detailed
Design Consultants)/ Project Proponent |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG
and BD |
Table 6-14 |
Compensatory Planting Proposals |
|
|
|
|
|
|
OP3.1 |
5 |
Utilise
all available spaces for new tree and shrub planting to screen views of the
proposals and where this is not possible soften their architectural form. |
To soften the
architectural form and enhance their visual integration within the future
landscape context. |
Project Landscape
Architect (IDC Consultants) / LCSD |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG
and BD |
OP3.2 |
5 |
New tree
planting will be concentrated in the proposed amenity areas along the alignment
and surrounding the stations, and providing infill planting between the
retained and transplanted trees; and on the disturbed slope areas. |
To restore and
enhance existing landscape context. |
Project Proponent /
NA |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG
and BD |
OP3.3 |
5 |
The
preliminary planting proposals for the proposed works shall adopt a
compensatory planting ratio of 1:1 (new planting: trees recommended for felling)
utilising a combination of mature to light standard sized stock in general
roadside and planting areas adjacent to proposed stations and above ground
structures. |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG |
OP3.4 |
5 |
The
retention of existing trees through their preservation in-situ, the transplantation
of trees found to be in conflict with the proposed works and the successful
establishment of the newly planted trees will form part of the roadside and
slope planting enhancing the amenity of the local areas and providing for the
thermal comfort of pedestrians. |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG |
OP3.5 |
5 |
The
proposed compensatory and new tree planting will utilise a combination of
species native to |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG |
OP3.6 |
5 |
The
preliminary planting proposals for the proposed works shall adopt a compensatory
planting ratio of 1:1 (new planting: trees recommended for felling) utilising
a combination of mature to light standard sized stock in general roadside and
planting areas adjacent to proposed stations and above ground structures. . |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG |
OP3.7 |
5 |
The retention
of existing trees through their preservation in-situ, the transplantation of
trees found to be in conflict with the proposed works and the successful
establishment of the newly planted trees will form part of the roadside and
slope planting enhancing the amenity of the local areas and providing for the
thermal comfort of pedestrians. |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB
TCW No. 3/2006 & 2/2004, HKPSG |
OP3.8 |
5 |
The
proposed compensatory and new tree planting will utilise a combination of
species native to |
To compensate the
loss of existing trees. |
Project Proponent /
Project Landscape Architect (IDC Consultants) |
Site |
Through out design phase |
TM-EIA Annex 18, ETWB TCW No. 3/2006 & 2/2004, HKPSG |
Table 6-14 |
Treatment of Retaining Wall and Slopes |
|
|
|
|
|
|
OP4.1 |
5 |
The proposed treatment of Retaining
Wall and Slopes should be
aesthetically enhanced through the use of soft landscape works including tree
and shrub planting to give man-made slopes a more natural appearance blending
into the local rural landscape. |
The design seeks to
visually integrate the engineered slope feature within the local landscape
context. |
Project Landscape
Architect(Detailed Design Consultants)/ / LCSD or HyD |
Site |
Through out design phase |
TM-EIA Annex 18, HKPSG and
BD GEO Publication No.
1/2000 "Technical Guidelines on Landscape Treatment and Bio-engineering
for Man-made Slopes and Retaining Walls" For HyD SIMAR slopes
refer to Standard Requirements for Handover of Vegetation on to Highways
Department (Rev.B). |
OP4.2 |
5 |
Whip sized tree planting is preferred
on the face of soil cut slopes and at the crest and toe of the slope, and
within berm planters. The smaller, younger plant stock will adapt to their
new growing conditions more quickly than larger sized stock and establish a
naturalistic effect more rapidly. |
The design seeks to
visually integrate the engineered slope feature within the local landscape
context. |
Project Landscape
Architect(Detailed Design Consultants)/ / LCSD or HyD |
Site |
Through out design phase |
TM-EIA Annex 18, HKPSG and
BD GEO Publication No.
1/2000 "Technical Guidelines on Landscape Treatment and Bio-engineering
for Man-made Slopes and Retaining Walls" For HyD SIMAR slopes refer to Standard
Requirements for Handover of Vegetation on to Highways Department (Rev.B). |
Table 6-14 |
Design of Noise Mitigation Structures |
|
|
|
|
|
|
OP5.1 |
5 |
Noise mitigation structures installed along the
trackside should not be limited to the functional requirements of mitigating
train noise. It should also include a requirement that these structures make
a positive contribution to the urban / semi-rural landscape character of this
area and by doing so improve the perceived landscape quality of the area.
These barriers would be visible from some VSRs identified in the study. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP5.2 |
5 |
Promote the innovative use of materials, such as Plexiglas, fibreglass,
reinforced concrete etc, whilst remaining aware of the design life span of
each of the elements incorporated in the design. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP5.3 |
5 |
Reduce the visual effect of the structure through the use of form,
materials, textures colours and tones. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP5.4 |
5 |
Incorporation of articulation in the façade of the noise barriers /
enclosures through the use of some transparent sections near the upper
portion of the proposed structure. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP5.5 |
5 |
Reflect the chromatic context of the surrounding urban landscape through
the use of colour panels in the proposed noise barrier. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
OP5.6 |
5 |
Utilise materials, which are non-reflective avoiding glare from
incident sunlight. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD |
Table 6-14 |
Design of Engineering Structures |
|
|
|
|
|
|
OP6.1 |
5 |
The landscape consultants have worked in unison with the engineers on the aesthetic aspects of the structures and their relationship with the landscape. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect and Landscape Architects
(Detailed Design Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.2 |
5 |
The structures shall aim to “touch” the ground as lightly as
possible in order to minimise disturbance to the existing landscape and
vegetation below the structures. This would be achieved by designing slender,
rounded columns spaced the maximum distance apart. The viaducts would be
constructed using pre-cast methods and launched from columns rather than
scaffolding. The viaduct should be designed to achieve where appropriate a
graceful, curving alignment. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.3 |
5 |
Landform and vegetation in areas disturbed by construction works would be reinstated to blend with the existing landscape patterns or as discussed above. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.4 |
5 |
Wherever light levels, the water regime and the requirements of the ecological mitigation measures permit, vegetation would be reinstated below the structures. Irrigation may be required in some locations and hard landscape solutions considered where the clearance is low. Planting would be used wherever possible to minimise the apparent height of structures and to soften their appearance in medium and long distance views. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.2 |
5 |
The design of the proposed structures should avoid unnecessary visual clutter, this would be achieved through the co-ordination of the various engineering disciplines involved to arrive at innovative design solutions. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.5 |
5 |
Fair faced concrete would not be used for parapets to minimise glare from the structure and to avoid the visually detracting effect of staining. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
OP6.6 |
5 |
Drainage structures would where possible be concealed
within the structure of the proposed viaducts. |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect (Detailed Design
Consultants)/ NA |
Site |
Throughout design phase |
TM-EIA Annex 18 and BD,
ACABAS |
Table 6-14 |
Reinstatement and
Creation of Open Spaces and Gardens |
|
|
|
|
|
|
OP7.1 |
5 |
The landscape consultants have worked in unison with the engineers on the aesthetic aspects for Reinstatement and Creation of Open Spaces and Gardens |
To ensure the
proposals are integrated with the existing landscape and visual context, and
avoid cluster effect. |
Project Engineer and
Architect and Landscape Architects
(Detailed Design Consultants)/ NA |
Site |
Throughout Design and
Construction phases |
TM-EIA Annex 18 and BD,
ACABAS |
Hazard
to Life |
|||||||
A7A |
6 |
Improved
truck design to reduce the amount of combustibles in, front exhaust spark
arrester, 1 x 9 kg water based and 1 x 9 kg dry chemical powder fire
extinguishers for a vehicle with gross weight up to 9 tonnes, and 2 x 2.5kg
dry powder and 2 x 10-litre foam fire extinguishers to be provided for a
vehicle of 9 tonnes and above, and a hand-held lightning detector to be
provided in the vehicle. This should be combined with monthly vehicle
inspection. |
To meet the ALARP requirement |
MTRC/ Contractor |
Explosive Magazine |
Construction phase |
|
A7A |
6 |
Blasting activities including storage and transport of explosives should be supervised and audited by competent site staff to ensure strict compliance with the blasting permit conditions. |
To ensure that the risks from the proposed explosives storage and transport would not be unacceptable |
MTRC / Contractor |
Works areas at which explosives would be stored and/or
used |
Construction phase |
Dangerous Goods Ordinance |
A7A |
6 |
Only the required quantity of explosives for a particular blast should be transported to avoid the return of unused explosives to the magazine. The number of return trips to the magazine with the full load of explosives or partial load should be minimised by proper co-ordination between blasting and delivery. If disposal is required for small quantities, disposal should be made in a controlled and safe manner by a Registered Shotfirer. |
To reduce the risk during explosives transport |
MTRC/ Contractor |
Works areas at which explosives would be stored and/
or used |
Construction phase |
|
A7A |
6 |
The explosive truck accident frequency should be minimized by implementing a dedicated training programme for both the driver and his attendants, including regular briefing sessions, implementation of a defensive driving attitude. In addition, drivers should be selected based on good safety record, and medical checks. |
To meet the ALARP requirement. |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
The contractor should as far as practicable combine the explosive deliveries for a given work area. |
To meet the ALARP requirement. |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
The explosive truck fire involvement frequency should be minimized by implementing a better emergency response and training to make sure the adequate fire extinguishers are used and attempt is made to evacuate the area of the incident or securing the explosive load if possible. All explosive vehicles should also be equipped with bigger capacity AFFF-type extinguishers. |
To meet the ALARP requirement. |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
A
minimum headway between two consecutive trucks conveys of at least 10 min is recommended. |
To ensure that the risk from the proposed explosives transport would not be unacceptable |
MTRC/ Contractor |
Along explosives transport route |
Construction phase |
|
A7A |
6 |
Use
only experienced driver(s) with good safety record for explosive vehicle(s).
Training should be provided to ensure it covers all major safety subjects. |
To ensure safe transport of explosives |
MTRC/ Contractor |
At suitable location |
Construction phase |
|
A7A |
6 |
Develop procedure to ensure that parking space on the site is available for the explosive truck. Confirmation of parking space should be communicated to truck drivers before delivery. |
To ensure that the risks from the proposed explosives storage and transport would not be unacceptable |
MTRC/ Contractor |
Explosive magazine |
Construction phase |
|
|
6 |
Delivery vehicles shall not be permitted to remain unattended within the magazine site (or appropriately wheel-locked). |
To reduce the risk of fire within the magazine |
MTRC / Contractor |
Explosive Magazine |
Construction phase |
|
|
6 |
Good house-keeping within and outside of the magazine to ensure that combustible materials (including vegetation) are removed and not allowed to accumulate. |
To reduce the risk of fire within the magazine |
MTRC / Contractor |
Explosive Magazine |
Construction phase |
|
|
6 |
Detonators shall not be transported in the same vehicle with other Class 1 explosives. |
To reduce the risk of explosion during the transport of cartridged emulsion |
MTRC / Contractor |
|
Construction phase |
|
A7A |
6 |
Emergency plan (i.e. magazine operational manual) shall be developed to address uncontrolled fire in magazine area. The case of fire near an explosive carrying truck in jammed traffic should also be covered. Drill of the emergency plan should be carried out at regular intervals. |
To reduce the risk of fire |
MTRC/ Contractor |
Explosive Magazine and along explosives transport
route |
Construction phase |
|
A7A |
6 |
Adverse weather working guideline should be developed to clearly define procedure for transport explosives during thunderstorm. |
To ensure safe transport of explosives |
MTRC/ Contractor |
Along explosives transport route |
Construction phase |
|
A7A |
6 |
During transport of the explosives within the tunnel, hot work should not be permitted. |
To ensure safe transport of explosives |
MTRC/ Contractor |
Along explosives transport route |
Construction phase |
|
A7A |
6 |
Ensure that UN 1.4B packaging of detonators remains intact until handed over at blasting site. |
To reduce the risk of explosion during the transport of detonator |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
Contractor to ensure that any electro-explosive devices are sufficiently shielded from radio frequency radiation hazards. |
To reduce the risk of explosion during the transport of detonators |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
Steel
vehicle tray welded to a steel vertical fire screen should be mounted at least
150 mm behind the drivers cab and 100 mm from the steel cargo compartment,
the vertical screen shall protrude 150 mm in excess of all three (3) sides of
the steel cargo compartment. |
To reduce the risk during explosives transport. |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
Ensure cartridged emulsion with high water content should be preferred. Also, the emulsion with perchlorate formulation should be avoided. |
To ensure safe explosives to be used |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
Traffic Management should be implemented within the temporary magazine site, to ensure that no more than 1 vehicle will be loaded at any time, in order to avoid accidents involving multiple vehicles within the site boundary. Based on the construction programme, considering that 6 trucks could be loaded over a peak 2 hour period, this is considered feasible. |
To ensure that the risks from the proposed explosives storage and transport would not be unacceptable |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
The design of the fill slope close to the temporary magazine site should consider potential washout failures and incorporate engineering measures to prevent a washout causing damage to the temporary magazine stores |
To ensure that the risks from the proposed explosives storage would not be unacceptable |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
The security plan should address different alert security level to reduce opportunity for arson / deliberate initiation of explosives. The corresponding security procedure should be implemented with respect to prevailing security alert status announced by the Government. |
To ensure that the risks from the proposed explosives storage would not be unacceptable |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
A suitable work control system should be introduced, such as an operational manual including Permit-to-Work system. |
To ensure that the risks from the proposed explosives storage would not be unacceptable |
MTRC/ Contractor |
- |
Construction phase |
|
A7A |
6 |
The magazine building shall be regularly checked for water seepage through the roof, walls or floor. |
To ensure that the risks from the proposed explosives storage would not be unacceptable |
MTRC/ Contractor |
- |
Construction phase |
|
Waste
Management (Construction Phase) |
|||||||
8.5.1.1 |
7 |
Good Site Practices Recommendations for good
site practices during the construction activities include: ·
Nomination of an approved person, such as a site manager, to be responsible
for good site practices, arrangements for collection and effective disposal
to an appropriate facility, of all wastes generated at the site ·
Training of site personnel in proper waste management and chemical
handling procedures ·
Provision of sufficient waste disposal points and regular collection
of waste ·
Appropriate measures to minimise windblown litter and dust/odour
during transportation of waste by either covering trucks or by transporting
wastes in enclosed containers ·
Provision of wheel washing facilities before the trucks leaving the
works area so as to minimise dust introduction from public road ·
Well planned delivery programme for offsite disposal such that
adverse environmental impact from transporting the C&D material is not
anticipated ·
Provision of cover for the stockpile material, sand bag or earth bund
as barrier to prevent material from washing away and entering the drains |
To reduce waste generation |
MTRC / Contractor |
Construction Work Sites (General) |
During Construction |
Waste Disposal Ordinance (Cap.354); Waste Disposal (Chemical Wastes) (General) Regulation (Cap 354) and ETWBTC No. 15/2003, Waste Management on Construction Site |
8.5.1.2 |
7 |
Waste Reduction Measures Recommendations to achieve waste reduction include: · Sort C&D material from demolition and decommissioning of the existing facilities to recover recyclable portions such as metals · Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal · Encourage collection of aluminium cans by providing separate labelled bins to enable this waste to be segregated from other general refuse generated by the work force · Proper storage and site practices to minimise the potential for damage or contamination of construction materials · Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste. |
For perform waste reduction |
MTRC / Contractor |
Construction Work Sites (General) |
During Construction |
Waste Disposal Ordinance (Cap.354); Waste Disposal (Chemical Wastes) (General) Regulation; Land (Miscellaneous Provisions) Ordinance (Cap. 28) |
8.5..1.3 |
7 |
C&D
Material In
order to minimise impacts resulting from collection and transportation of
C&D material for off-site disposal, the excavated materials should be
reused on-site as backfilling material as far as practicable. In addition, C&D material generated
from excavation works could be reused as rock material in local projects that require public fill for reclamation and earth
filling purposes, say, ‘Hong Kong – Zhuhai – Macao Bridge’ in association with Hong Kong Boundary
Crossing Facilities and Hong Kong Link Road, Central-Wanchai Bypass and Wanchai Development Phase II project
(subject to further coordination). The
surplus rock and other inert C&D material should be disposed of at the
Government’s Public Fill Reception Facilities (PFRFs), for beneficial use by
other projects in the HKSAR, or transported to Mainland · A Waste Management Plan should be prepared and · In order to monitor the disposal of C&D material and solid wastes at public filling facilities and landfills, and to control fly-tipping, a trip-ticket system (e.g. ETWB TCW No. 31/2004) should be included. |
To minimize impacts resulting from collection and transportation of C&D material for off-site disposal |
MTRC / Contractor |
Construction Work Sites (General) |
During Construction |
ETWB TCW No. 31/2004 |
8.5.1.4 |
7 |
General
Refuse General refuse should be stored in enclosed bins or compaction units separate from C&D material. A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D material. Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material. |
To minimize impacts resulting from collection and transportation of general refuse for off-site disposal |
MTRC / Contractor |
Construction Work Sites (General) |
During Construction |
Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation |
8.5.1.5 |
7 |
Chemical
Waste If chemical wastes are produced at the construction site, the Contractor would be required to register with the EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor should use a licensed collector to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. |
To minimize impacts resulting from collection and transportation of chemical waste for off-site disposal |
MTRC / Contractor |
Construction Work Sites (General) |
During Construction |
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, Waste Disposal (Chemical Waste) (General) Regulation |
8.5.1.6 |
7 |
Marine
Dredged Sediment The sediment at the pier site would be dredged and transferred to barges for subsequent disposal. Release of dredged sediment into the surrounding water should be avoided. It is recommended that the distance between the barge and the dredging point be shortened as far as possible to avoid dropping of sediment from the close grab to the seawater. |
To minimise potential impacts on water quality |
MTRC/ Contractor |
Dredging/ excavation area required for installation of the pier/pier structure in Aberdeen Channel |
During marine construction works |
ETWB TCW No. 34/2002 |
8.5.1.6 |
7 |
Category H material was identified at the grab sampling location at the dredging/excavation site. As there was no exceedance of 10xLCEL for the tested parameters, the sediment to be dredged at this location should be disposed of at a confined marine disposal site. The Project Proponent should agree with MFC on the allocation of disposal site and the Contractor should apply a dumping permit from EPD prior to the dredging / excavation works. |
To prevent cross contamination of waste. |
MTRC/ Contractor |
Dredging/ excavation area with Category H material |
During marine construction works |
ETWB TCW No. 34/2002 |
Waste
Management (Operation Phase) |
|||||||
8.5.2.1 |
7 |
General
Refuse General refuse should be collected on daily basis and delivered to the refuse collection point accordingly. A reputable waste collector should be employed to remove general refuse regularly to avoid odour nuisance or pest and vermin problem. Recycling containers are recommended to be provided to encourage recycling aluminium cans and waste paper. |
To minimize impacts resulting from collection and transportation of general refuse for off-site disposal |
MTRC |
Stations and depot |
During Operation |
Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation |
8.5.2.2 |
7 |
Industrial
Waste Similar to general refuse, a reputable waste collector should be employed to remove industrial waste regularly to avoid accumulation. Scrap materials such as metals can be recycled if uncontaminated. |
To minimize impacts resulting from collection and transportation of industrial waste for off-site disposal |
MTRC |
Stations and depot |
During Operation |
Public Health and Municipal Services Ordinance (Cap. 132) - Public Cleansing and Prevention of Nuisances Regulation |
8.5.2.3 |
7 |
Chemical
Waste · Register with the EPD as a chemical waste producer should be obtained and guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes should be followed. · Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. Licensed collector should be deployed to transport and dispose of the chemical wastes, to either the approved Chemical Waste Treatment Centre, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. |
To minimize impacts resulting from collection and transportation of chemical waste for off-site disposal |
MTRC |
Stations and depot |
During Operation |
Waste Disposal (Chemical Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical Waste |
Land
Contamination (Construction Phase) |
|||||||
9.7.1 |
8 |
The following measures should be implemented for contaminated material excavation and transportation (if any): · To minimize the chance for construction workers’ to come into contact with contaminated materials, bulk earth-moving excavation equipment should be employed; · Contact with contaminated materials can be minimised by wearing appropriate clothing and personal protective equipment such as gloves and masks (especially when interacting directly with contaminated material), provision of washing facilities and prohibition of smoking and eating on site; · Stockpiling of contaminated excavated materials on site should be avoided as far as possible; · The use of contaminated soil for landscaping purpose should be avoided unless pre-treatment was carried out; · Vehicles containing any excavated materials should be suitably covered to reduce dust emissions and/or release of contaminated wastewater; · Truck bodies and tailgates should be sealed to stop any discharge; · Only licensed waste haulers should be used to collect and transport contaminated material to treatment/disposal site and with the implementation of tracking system to avoid fly tipping; · Speed control for trucks carrying contaminated materials should be carried out; · Observe all relevant regulations in relation to waste handling, such as Waste Disposal Ordinance (Cap 354), Waste Disposal (Chemical Waste) (General) Regulation (Cap 354) and obtain all necessary permits where required; and · Maintain records of waste generation and disposal quantities and disposal arrangements. |
To minimize as much as possible any nuisance generated in relation to land remediation activities. At the same time, to protect all personnel from possible risk associated with land remediation activities. |
MTRC / Contractor |
All site areas |
During Construction |
EIA Recommendations |
Land
Contamination (Operation Phase) |
|||||||
9.7.2 |
8 |
Defined procedures in handling chemicals should be implemented as part of MTRCL company policy. All relevant operational procedures should be strictly followed to avoid land contamination. |
To minimize as much as possible any risk in association with land contamination during operation of the Project |
MTRC |
All areas within the Project |
During Operation |
EIA Recommendations |
Air
Quality Impact (Construction Phase) |
|||||||
10.6.2 |
9 |
Specific Dust Control Measures Dust
emissions should be suppressed by regular water spraying on site. In general,
water spraying twice a day could reduce dust emission to active area by 50%.
More frequent wetting or watering is recommended in case of any construction
activities that are critical to the sensitive receivers. Paved haul roads in
the construction sites near |
To minimize adverse dust emission generated from various construction activities of the works sites |
Contractor |
Construction Works Sites |
During Construction |
EIA Recommendat-ions |
|
|
· For the unloading of spoil from trucks at barging point, installation of 3-sided screen with top and the provision of water sprays at the discharge point should be provided |
|
|
|
|
|
|
|
· Watering every working hour for 12 hours a day on exposed soil areas on active works areas and paved haul roads to reduce dust emissions |
|
|
|
|
|
|
|
· The rock crushing facilities with maximum daily output of over 1000m3 per day should be enclosed including unloading locations and a fabric baghouse/cartridge filter type dust extraction and collection system or equivalent system with 99% or more dust removal efficiency should be installed for the treatment of the emissions from rock crushing and screening processes. |
|
|
|
|
|
10.6.2 |
9 |
Best practices for dust control are required. A control programme can be instigated to monitor the construction process in order to enforce dust controls and modify methods of works where feasible to reduce the dust emission down to acceptable levels. The following best practices for dust control should be implemented throughout the construction period: |
To minimize adverse dust emission generated from various construction activities of the works sites |
Contractor |
Construction Works Sites |
During Construction |
Air Pollution Control (Construction Dust) Regulation, EPD’s Best Practicable Means and EIA Recommendat-ions |
|
|
Disturbed
Parts of the Roads |
|
|
|
|
|
|
|
· Each and every main temporary access should be paved with concrete, bituminous hardcore materials or metal plates and kept clear of dusty materials; or |
|
|
|
|
|
|
|
· Unpaved parts of the road would be sprayed with water or a dust suppression chemical so as to keep the entire road surface wet. |
|
|
|
|
|
|
|
Exposed
Earth |
|
|
|
|
|
|
|
· Exposed earth should be properly treated by compaction, hydroseeding, vegetation planting or seating with latex, vinyl, bitumen within six months after the last construction activity on the site or part of the site where the exposed earth lies. |
|
|
|
|
|
|
|
Loading,
Unloading or Transfer of Dusty Materials |
|
|
|
|
|
|
|
· All dusty materials should be sprayed with water immediately prior to any loading or transfer operation so as to keep the dusty material wet. |
|
|
|
|
|
|
|
Debris
Handling |
|
|
|
|
|
|
|
· Any debris should be covered entirely by impervious sheeting or stored in a debris collection area sheltered on the top and the three sides. |
|
|
|
|
|
|
|
· Before debris is dumped into a chute, water should be sprayed so that it remains wet when it is dumped. |
|
|
|
|
|
|
|
§
For the minor blasting at WCH Depot, tarpaulin
covers would be provided on the steel screens to prevent the dust from spreading
out, and the whole blasting area would be watered before and after each blast
in order to help contain the dust and fumes. |
|
|
|
|
|
|
|
Transport
of Dusty Materials |
|
|
|
|
|
|
|
· Vehicle used for transporting dusty materials/ spoil should be covered with tarpaulin or similar material. The cover should extend over the edges of the sides and tailboards. |
|
|
|
|
|
|
|
Wheel
Washing |
|
|
|
|
|
|
|
· Vehicle wheel washing facilities should be provided at each construction site exit. |
|
|
|
|
|
|
|
Stone Crushing Plant |
|
|
|
|
|
|
|
· The control measures listed in EPD’s A Guidance Note on the Best Practicable Means for Mineral Works (Stone Crushing Plants) BPM 11/1) should be followed, where appropriate. |
|
|
|
|
|
|
|
Concrete
Batching Plant |
|
|
|
|
|
|
|
· The loading, unloading, handling, transfer or storage of dusty materials should be carried in a totally enclosed system. All dust-laden air or waste gas generated by the process operations should be properly extracted and vented to fabric filtering system. The control measures listed in EPD’s A guidance note on the best practicable means for cement works (concrete batching plant) (BPM 3/2) should be followed, where appropriate. |
|
|
|
|
|
|
|
Good Site Management |
|
|
|
|
|
|
|
· The Contractor should maintain high standard of housekeeping to prevent emission of fugitive dust emission. Loading, unloading, handling and storage of raw materials, wastes or by-products should be carried out in a manner so as to minimize the release of visible dust emission. Any piles of materials accumulated on or around the work areas should be cleaned up regularly. Cleaning, repair and maintenance of all plant facilities within the work areas should be carried out in a manner minimizing generation of fugitive dust emissions. The material should be handled properly to prevent fugitive dust emission before cleaning. |
|
|
|
|
|
Cultural
Heritage Impact (Construction Phase) |
|||||||
11.7.1.1 |
10 |
Archaeological watching brief during the
construction phase is recommended for areas highlighted as having some archaeological
potential (The works sites that will require archaeological watching brief
can be found in the following figures
in the main report: Harcourt Garden (Figure 11.22), Wong Chuk Hang San Wai
(WS10) in Figure 11.35 and Works Sites S7, S7c, S7d and S7e (Figure 11.28). |
To identify and record any archaeological material or features revealed during the excavation phase of the works schedule |
MTRC/ Contractor |
Admiralty: Wong Chuk Hang: Works Sites S7c,d,e, Works Site S7, Pier Columns within Works Site S10 |
During Construction |
Antiquities and Monuments Ordinance |