5               Construction Dust IMPACT

Introduction

5.1          Potential dust impacts associated with the construction phase of the Shatin to Central Link (SCL) protection works at Causeway Bay Typhoon Shelter (CBTS) are presented in this section.  Representative Air Sensitive Receivers (ASRs) are identified.  Potential dust impacts on these receivers arising from dust emission from the construction activities associated with the Project have been assessed and appropriate mitigation measures are proposed to alleviate the impacts.

Environmental Legislation, Standards and Guidelines

5.2          The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the requirements set out under Clause 3.4.4 of the EIA Study Brief (No. ESB-213/2010).

Air Quality Objective & EIAO-TM

5.3          The Air Pollution Control Ordinance (APCO) provides the statutory authority for controlling air pollutants from a variety of sources.  The Hong Kong Air Quality Objectives (AQOs), which stipulate the maximum allowable concentrations over specific periods for a number of criteria air pollutants, should be met. The relevant AQOs are listed in Table 5.1.

 

Table 5.1           Hong Kong Air Quality Objectives

Pollutant

Maximum Concentration (µg m-3) (1)

Averaging Time

Daily (2)

Annual (3)

Total Suspended Particulates (TSP)

260

80

Note:

(1)         Measured at 298 K and 101.325 kPa.

(2)         Not to be exceeded more than once per year.

(3)         Arithmetic mean.

 

5.4          The EIAO-TM stipulates that the hourly TSP level should not exceed 500 mgm-3 (measured at 25oC and one atmosphere) for construction dust impact assessment. 

Air Pollution Control (Construction Dust) Regulation

5.5          Notifiable and regulatory works are under the control of Air Pollution Control (Construction Dust) Regulation.  Notifiable works are site formation, reclamation, demolition, foundation and superstructure construction for buildings and road construction.  Regulatory works are building renovation, road opening and resurfacing, slope stabilisation, and other activities including stockpiling, dusty material handling, excavation, concrete production, etc.  This Project is expected to include notifiable works (reclamation, demolition, foundation and superstructure construction) and regulatory works (temporary stockpile, dusty material handling, excavation and concrete production).  Contractors and site agents are required to inform EPD and adopt dust reduction measures to minimize dust emission, while carrying out construction works, to the acceptable level.

Description of the Environment

Environs

5.6          The SCL Protection Works is located entirely offshore within the Causeway Bay Typhoon Shelter.  The locality of the Project Area is a developed urban area and the sensitive receivers are located along the harbour-front area with major land uses including commercial, residential and open spaces.

Background Air Quality

5.7          The study area is located in the Causeway Bay area.  No air quality monitoring station operated by the Environmental Protection Department (EPD) is identified in the vicinity of the study area.  The nearest one would be the Central/Western monitoring station.  The average annual TSP level recorded at EPD’s Central/Western monitoring station for the recent five years (2005 – 2009) is 77.4μg/m3.

5.8          Central/Western monitoring station is located at Sai Ying Pun at the centre of the hinterland area.  The monitoring station is surrounded by mixture of commercial as well as densely populated residential areas and busy local traffic networks in all directions.  The TSP recorded at this station would largely be contributed by the vehicular emissions from the surrounding road network.   Contrastly, the study area of this Project is a harbour front location facing the Harbour to the north.  Lower TSP levels would be expected in the study area when wind is blowing in the prevailing north-easterly direction.  Given the different site characteristic of the study area and EPD’s Central/Western monitoring station, alternative historic TSP monitoring data are considered.  In order to estimate the background TSP level in the vicinity of the study area, recent environmental monitoring data recorded at harbour front locations by the environmental monitoring and audit (EM&A) programme for other designated project in close proximity to the study area are referred to.

5.9          Central Reclamation Phase III (CRIII) is a designated project under the EIA Ordinance and its project site is located near the northern harbour front of the Hong Kong Island similar to the site environs of this Project.  The construction of CRIII commenced in 2003.  In accordance with the EM&A Manual[1] approved for CRIII, two air quality monitoring stations were set up to measure the TSP level in the vicinity of the project site.  One monitoring station is located at the Chinese People’s Liberation Army Force Hong Kong Building (PLA) while the other one is located at City Hall.  Hong Kong as a whole is characterized with northeast prevailing wind throughout the year.  Influence from the traffic emission impact is relatively lower in most of the time at the harbour-front location of CRIII.  Both CRIII’s monitoring stations are located immediate to the construction site, the dust impact arising from CRIII is therefore the dominant source.  The site characteristic of this Project and CRIII are similar, the air quality monitoring data recorded by CRIII is therefore considered more appropriate to represent the background air quality concentration of this Project. 

5.10        The air quality monitoring at PLA commenced in April 2005 and data of up to 5 years are available to represent the background air quality in the surrounding area.  Whereas the air quality monitoring at City Hall only commenced in March 2006 with less than 5 years available data and thus is not selected for background air quality estimation.

5.11        All the TSP monitoring data were recorded in accordance with the requirements stipulated in the EM&A Manual of CRIII and were reviewed and submitted as per the requirements of the corresponding environmental permit issued under the EIA Ordinance.  All the TSP levels were measured in accordance with the standard high volume sampling method set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.  Initial calibration of dust monitoring equipment was conducted upon installation and thereafter at bi-monthly intervals.  The transfer standard is traceable to the internationally recognised primary standard and was calibrated annually.  The calibration and air quality monitoring was conducted by independent environmental team and led by an environmental team leader.  The calibration data were also reviewed and validated by independent environmental checker.  The collected dust samples were analysed by a laboratory which had been inspected and audited by the independent environmental checker as per the EM&A Manual of CRIII Project to undertake the dust analysis.

5.12        Review of the detailed TSP monitoring results recorded at PLA was undertaken and it is observed that some unusually low TSP concentrations were measured on some days.  TSP comprises of suspended particulates of different size including respirable suspended particulates (RSP).  The background RSP level in Hong Kong is largely influenced by regional contribution, thus the spatial variation of RSP level over the Hong Kong territory is relatively small in general.  The TSP level recorded at PLA is considered as unusually low if the TSP value is lower than the RSP level recorded at EPD’s rural monitoring station at Tap Mun during the same monitoring day. For the purpose of quality control, those unusually low TSP levels are discarded in the calculation of annual average TSP level for this study.

5.13        The TSP data recorded at PLA are considered as of acceptable quality and with sufficient valid data after discarding the unusually low TSP monitoring data.  The estimated background TSP concentration using the PLA monitoring results is 76.2μg/m3.  The past TSP monitoring data recorded at PLA is attached in Appendix 5.1.

Air Sensitive Receivers

5.14        In accordance with Annex 12 of the EIAO-TM, any domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre are considered as air sensitive receivers (ASRs).  As stated in the EIA Study Brief, the boundary of the assessment area for air quality assessment should be 500m from the boundaries of all associated works areas under the Project.  A total of 6 representative ASRs were identified for this assessment in accordance with the criteria set out in the EIAO-TM which are considered to be most likely to be affected by the construction of the Project.  The representative ASRs are listed in Table 5.2 and their locations are illustrated in Figure No. NEX2213/C/331/ENS/M60/501.

5.15        The proposed SCL protection works would be constructed by cut-and-cover methods on the temporary reclamation land.  All associated construction works would be at ground level.  The air quality impact at the lowest level of each representative ASR with sensitive use, which is the worst affected level, was assessed in this assessment.  Higher assessment height of 5m above ground level (AGL) was also selected for elevated ASRs to show the vertical variation of the pollutant concentrations.

Table 5.2           Representative Air Sensitive Receivers

ASRs

Description

Land Use

Distance from the nearest dust emission sources (m)

No. of storey

Assessment Height

(m AGL)

CHA1*

World Trade Centre

Commercial

80

34

5

CHA2*

Sino Plaza

Commercial

120

33

5

CHA3

Highland Mansion

Residential

150

15

1.5 & 5

CHA4

Royal Hong Kong Yacht Club

Recreation

140

3

1.5 & 5

CHA5

Police Officers Club (POC)

Recreation

20

3

1.5 & 5

CHA6

Riveria Mansion

Residential

130

14

1.5 & 5

Note:

*  Only non-sensitive use was observed at the ground level, assessment height was taken as the second level of 5m AGL.

 

Potential Sources of Impact

5.16        The SCL Protection Works involves the construction of a section of the railway tunnel box by cut-and-cover method at the crossing above the proposed Central Wanchai Bypass (CWB) tunnels.  Temporary reclamation would be required to construct the Protection Works. The construction works included dredging, temporary sea wall construction, filling, installation of diaphragm wall, excavation, placing a reinforced concrete tunnel box and removal of temporary reclamation.  Construction of temporary seawall and fill works are the major construction works during reclamation.  Excavation, materials handling, wind erosion, truck haulage on unpaved roads are other major sources of dust impact.

5.17        Apart from the potential dust impact associated with the temporary reclamation, dredging at the southeast corner of the CBTS is required to provide space for temporary relocation of anchorage area for the vessels due to the additional temporary reclamation for the Protection Works.  Since the dredging activities are not dusty activities and the moisture content of dredging materials is very high, negligible fugitive dust emissions is expected.  Yet in view of the small scale, short duration and low dredging rate of the proposed dredging works, adverse odour impact during the dredging operation is not anticipated.  The potential odour impact arising from the dredging process is further discussed in Section 6 of this EIA Report.

5.18        Alternative construction methods/phasing programme were described in Chapter 2 of this report.

Cumulative Dust Impact from Other Concurrent Project

5.19        Based on the current programme, the Project would likely interface with Wan Chai Development Phase II & Central-Wan Chai Bypass (WDII & CWB) in 2012 – 2013.

WDII & CWB

5.20        The major construction works for WDII & CWB Project would be the construction of trunk road and reclamation works.  The proposed trunk road runs from Central Interchange in Central Reclamation Phase I through the Central Reclamation Phase III and WDII & CWB project areas, and the Island Eastern Corridor Link (IECL) which provides connection from the eastern portal of the CWB to the IEC.

5.21        Any above ground construction activity arising from WDII & CWB that is located within 500m from the Project boundary were considered in this assessment. 

 

Assessment Methodology

5.22        Referring to the above sections, potential adverse dust impact would be expected from construction of temporary seawall, fill works and cut-and-cover tunnel.  The potential dust emission sources considered in the assessment are shown in Appendix 5.2.

Emission Inventory

5.23        The principal source of air pollution during the construction phase will be dust from the dusty activities as mentioned above.  The impact of fugitive dust sources on air quality depends upon the quantity as well as the drift potential of the dust particles emitted into the atmosphere.  Large dust particles (i.e. over 100 mm in diameter) will settle near the source and particles that are between 30 and 100 mm in diameter are likely to undergo impeded settling.  The main dust impacts are likely to arise from particles less than 30 mm in diameter, which have a greater potential to disperse over greater distance.

5.24        According to the USEPA AP-42, construction dust particles may be grouped into nine particle size classes.  Their size ranges are 0.5 mm, 1.5 mm, 2.25 mm, 2.75 mm, 3.5 mm, 4.5 mm,  5.5 mm, 8 mm, 20 mm, and the percentage of particles in each class was estimated to be 4%, 7%, 4%, 3%, 7%, 5%, 4%, 17% and 49%, respectively.

5.25        Predicted dust emissions are based on emission factors from AP-42.  The major dusty construction activities for the Project to be considered in the modelling assessment include:

 

(A) Temporary Reclamation areas (modeled as heavy construction)

-                 Construction of seawall

-                 Back filling the spoils

-                 Installation of diaphragm wall

-                 Truck haulage on unpaved roads

 

(B) Tunnel Cut & Cover areas

-                 Excavation and material handlings within the construction site and truck haulage on unpaved roads modelled as heavy construction activities

-                 Wind erosion of open active site

5.26        In terms of the construction programme, it should be noted that the sequencing of works for each works activity over each works site or area will be determined by the Contractor and is not known at this stage.  However, due to the constrained size of the works sites and the tight construction programme, it will be necessary for active construction activities to be undertaken at multiple work faces spread across each site.  Therefore, it is not feasible to identify the exact location of individual dust emission source.  As such, for the purpose of predicting annual TSP concentrations, it is assumed that dust emissions would be distributed across the whole area of each site and the dust emission rates are estimated based on the annual average percentage active works area of each works site.

5.27        Whereas for predicting shorter-term TSP levels including hourly and daily average TSP levels, a more conservative approach is adopted.  It is assumed that the whole construction site would be 100% actively operated, notwithstanding that such a scenario would unlikely to occur.

5.28        The emission rates of identified pollutant sources are summarised in Tables 5.3.  Detailed calculations of the emission factors are given in Appendix 5.2.

Table 5.3           Emission Factors for Dusty Construction Activities (For Hourly and Daily TSP Concentrations Prediction)

 

Emission Source

Activity

Emission Rate

Remarks

Temporary Reclamation/Tunnel Construction at Causeway Bay Typhoon Shelter

Heavy Construction Activities

E=2.69 Mg/hectare

/month of activity

 

*   100% area actively operating

*   AP42, Section 13.2.3

 

Wind Erosion

 

E=0.85Mg/hectare

/year

 

*   100% active site

*   AP42, Section 11.9.4

5.29        Based on the preliminary engineering design, the annual averaged active area is estimated to be 6% and would be assumed for predicting the annual concentrations.  The justification for the percentage of annual average active area is presented in Appendix 5.3.

5.30        With reference to the proposed construction method of both SCL Protection Works and CWB, temporary seawall construction will be first conducted to enclose each phase of the temporary reclamation.  Installation of diaphragm wall on temporary reclamation land as well as any bulk filling will proceed behind the completed seawall.  After the temporary reclaimed land was formed, tunnel box construction by cut-and-cover method down to below water level will be conducted.  Then all construction works would be carried out below water level and adverse dust impact would not be anticipated.  Finally, the temporary reclamation will be removed after completion of all tunnel construction works.  According to the assumption made under WDII & CWB EIA, the maximum percentage of active construction works area is 50%, the remaining 50% of the works area is just exposed to air without any construction works.  Therefore, as the worst-case assumption, the annual exposed area is assumed to be 50% for predicting the annual concentrations. 

5.31        There will be no construction activity carried out at the southwest retained temporary reclamation after the land was formed.  The land will be covered or paved once the filling is completed.  In accordance with the tentative construction programme, the filling activities of the whole temporary reclamation authorized under SCL Protection Works would take 2 months.  As a conservative assumption, the duration for filling the retained temporary reclamation is also assumed to be 2 months in the model.  The dust emission rates for the filling activities are estimated based on a conservative estimate of daily maximum percentage active works area of 20% for predicting the annual TSP concentration.

5.32        The averaged emission rate of general construction activities for predicting the annual concentrations are summarised in Table 5.4.

 

Table 5.4      Averaged Emission Factors for Dusty Construction Activities (For Annual TSP Concentrations Prediction)

Emission Source

Activity

Emission Rate

Remarks

Temporary Reclamation/Tunnel Construction at Causeway Bay Typhoon Shelter

Heavy Construction Activities

E=2.69 Mg/hectare

/month of activity

*    6% area actively operating

*    AP42, Section 13.2.3

 

Wind Erosion

 

E=0.85Mg/hectare

/year

*    50% active site

*    AP42, Section 11.9.4

Retained Temporary Reclamation – Filling (only for 2 months duration)

Heavy Construction Activities

E=2.69 Mg/hectare

/month of activity

*    20% area actively operating

*    AP42, Section 13.2.3

 

Wind Erosion

 

E=0.85Mg/hectare

/year

*    20% active site

*    AP42, Section 11.9.4

 

5.33        The SCL Protection Works would be carried out under the CWB project.  The same working hours of 10 hours per day was assumed for dusty construction during 08:00 to 18:00 in this assessment.  Wind erosion of open work sites was assumed to take place over the whole day.

5.34        According to the updated information presented in the Environmental Permit of WDII & CWB Project, the construction period of the whole WDII & CWB Project is from 2010 to 2017.  It is expected that the construction of SCL Protection Works would only occur concurrently with the construction of WDII & CWB project from 2012 to mid 2013.  The short-term dust impact arising from the construction of WDII & CWB in early 2012 (namely scenario 1 in this assessment) and mid 2012 to early 2013 (namely scenario 2 in this assessment) were predicted and presented in the approved WDII & CWB EIA Report.  Therefore, for the purpose of predicting the cumulative short-term (hourly and daily average) dust impacts, the contribution of dust impacts from WDII & CWB at the ASRs were taken as the predicted worst-case dust impacts at the respective ASR presented in the approved WDII & CWB EIA Report.

5.35        However, annual average TSP concentrations were not predicted in WDII & CWB EIA.  The annual TSP impact is therefore assessed by adding the WDII & CWB dust emission sources to dust model of this Project.  Based on the available construction programme and plant inventory of WDII & CWB, an annual average active area of 6% and watering on CWB work areas of TCBR1W and TPCWAE once per working hour were assumed for predicting the annual concentrations.  The justification for the percentage of annual average active area is presented in Appendix 5.3.  Detailed calculations of the emission factors for WDII & CWB are presented in Appendix 5.4.  According to the WDII & CWB EIA, dust suppression measures shall be implemented, thus emission factors of mitigated scenario are considered.  The major dusty construction activities located within the assessment boundary of SCL Protection Works during the period interfacing with the Project were extracted from WDII & CWB EIA Report Table 3.6 and its EP, EP-356/2009 as follows:

Table 5.5          Different Major Dust Generating Activities in the Worst Scenarios during Construction Phase of WDII & CWB

Activities

Scenario 1

Scenario 2

1

TCBR1E – CWB Tunnel

TCBR1W – CWB Tunnel

2

TCBR1W – CWB Tunnel

TCBR2 – CWB Tunnel

3

TCBR2 – CWB Tunnel

TCBR3 – CWB Tunnel

4

TPCWAE – CWB Tunnel

TPCWAE – CWB Tunnel

5

WCR1 – Drainage

 

6

WCR1 – Cooling Water

 

 

Dispersion Modeling and Concentration Calculation

5.36        Fugitive Dust Model (FDM) (1993 version) was adopted to assess potential dust impact from the construction works.  The worst case meteorological condition is used to predict the maximum hourly and daily average TSP concentrations at representative discrete ASRs in the vicinity of the construction sites which are the same as those selected in the WDII & CWB EIA.  Assessment heights are taken as 1.5m or the lowest air sensitive level, and 5m above ground level.

·                     Wind speed:                             1 m/s

·                     Wind direction:                          360 wind directions

·                     Wind direction resolution:          1°

·                     Stability class:                          D (daytime, 8:00-18:00) & F (night time, 18:00-8:00)

·                     Surface roughness:                   1m

·                     Mixing height:                           500 m

5.37        Daily TSP concentrations were calculated as follows:

Daily TSP concentration = (number of working hour)/24 ´ (1-hour average maximum TSP concentration during working hours) + (number of non-working hour)/24 ´ (1-hour average maximum TSP concentration during non-working hours) + Background

5.38        For prediction of the annual TSP concentrations due to the Project, hourly meteorological data including wind speed, wind direction, air temperature and Pasquill stability class from the Hong Kong Observatory for year 2008 were employed for the model run.

5.39        No construction activities would be operated on Sundays and the public holidays.  Dust emissions from active construction activities were assumed for the hours from 0800 to 1800 in the year excluding Sundays and public holidays.  Whereas for the hours from 1800 to 0800 in the year and the hours during Sundays and the public holidays, only dust emissions due to wind erosion were assumed.

5.40        As described in Sections 5.7 - 5.11 above, a background TSP level of 76.2 mg/m3 was adopted to represent the future TSP background concentration.

Prediction and Evaluation of Dust Impacts

Unmitigated Scenario

5.41        The predicted unmitigated cumulative maximum hourly, daily average and annual TSP concentrations at the representative ASRs during construction in scenario 1 and scenario 2 are summarized in Tables 5.6.

 

Table 5.6           Predicted Cumulative Maximum Hourly, 24-hour and Annual Average TSP Concentrations at Representative Air Sensitive Receivers (Unmitigated)

ASRs

Assessment Height

(mAG)

Cumulative Maximum TSP Concentrations in mg/m3

Hourly Average

24-hour Average

Annual Average

Sc.1

Sc.2

Sc.1

Sc.2

Sc.1

Sc.2

CHA1

1.5

734

734

362

362

78.0

78.0

 

5

640

658

319

326

77.6

77.7

CHA2

1.5

537

537

279

279

77.9

77.9

 

5

516

529

269

274

77.6

77.7

CHA3

1.5

387

387

215

215

77.1

77.2

 

5

370

382

206

211

77.0

77.1

CHA4

1.5

566

566

295

295

79.8

79.8

 

5

481

510

252

264

79.3

79.3

CHA5

1.5

1969

1969

894

894

84.5

84.4

 

5

1320

1350

608

620

79.7

79.7

CHA6

1.5

507

507

264

264

77.4

77.5

 

5

468

484

246

253

77.2

77.4

Notes:    (1) A background TSP level of 76.2 mg/m3 has been included in the above results.

                (2) The hourly, 24-hour and annual average TSP EIAO-TM / AQO criteria are 500 mg/m3, 260mg/m3

                     and 80mg/m3 respectively.

                (3) Boldfaced value presents the predicted TSP concentration exceeding the respective criteria.

 

Abbreviations:      Sc.1        Scenario 1

Sc.2        Scenario 2

 

5.42        Based on the results indicated in Tables 5.6, the predicted cumulative maximum hourly and daily average TSP at most representative ASRs would exceed the criteria in EIAO-TM and AQO.  Hence, proper dust mitigation measure should be implemented.

Recommended Air Quality Mitigation Measures

5.43        In order to minimise the construction dust impact, the following dust mitigation measures should be implemented:

Ÿ     Watering once every working hour on the temporary reclamation area of SCL Protection Works to reduce dust emission by 91.7%[2]; and

Ÿ     Covering/paving the southwest retained area of temporary reclamation once filling is completed

5.44        In additional to the dust mitigation measures described above, dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices should be carried out to further minimize construction dust impact.

Ÿ     Use of regular watering, with complete coverage, to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

Ÿ     Use of frequent watering for particularly dusty construction areas and areas close to ASRs.

Ÿ     Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

Ÿ     Open stockpiles shall be avoided or covered.  Where possible, prevent placing dusty material storage piles near ASRs.

Ÿ     Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

Ÿ     Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.

Ÿ     Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading points, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.

Ÿ     Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit.

Ÿ     Imposition of speed controls for vehicles on site haul roads.

Ÿ     Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.

Ÿ     Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides.

Ÿ     Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

Mitigated Scenario

5.45        The predicted mitigated cumulative maximum hourly, daily average and annual TSP concentrations at the representative ASRs during construction in scenario 1 and scenario 2 are summarized in Tables 5.7.

Table 5.7           Predicted Cumulative Maximum Hourly, 24-hour and Annual Average TSP Concentrations at Representative Air Sensitive Receivers (Mitigated)

ASRs

Assessment Height

(mAG)

Cumulative Maximum TSP Concentrations in mg/m3

Hourly Average

24-hour Average

Annual Average

Sc.1

Sc.2

Sc.1

Sc.2

Sc.1

Sc.2

CHA1

1.5

234

234

154

154

77.1

77.2

 

5

206

224

138

145

76.9

77.0

CHA2

1.5

180

180

131

131

77.0

77.0

 

5

169

182

124

129

76.9

76.9

CHA3

1.5

176

176

127

127

76.7

76.8

 

5

163

175

119

124

76.7

76.8

CHA4

1.5

327

327

195

195

78.9

78.9

 

5

250

279

156

168

78.5

78.4

CHA5

1.5

417

417

247

247

78.6

78.6

 

5

322

352

192

204

77.7

77.7

CHA6

1.5

206

206

139

139

76.9

77.1

 

5

185

201

128

135

76.8

77.0

Note:      (1) A background TSP level of 76.2 mg/m3 has been included in the above results.

                (2) The hourly, 24-hour and annual average TSP EIAO-TM / AQO criteria are 500 mg/m3, 260mg/m3

                     and 80mg/m3 respectively.

                (3) Boldfaced value presents the predicted TSP concentration exceed the respective criteria.

 

Abbreviations:      Sc.1        Scenario 1

Sc.2        Scenario 2

 

5.46        Based on the results indicated in Table 5.7, the cumulative maximum hourly, daily and annual average TSP levels at all ASRs would comply with the criteria in EIAO-TM and AQO with implementation of proposed dust mitigation measures.  The worst-hit level would be at 1.5m AGL.  The contour plots of cumulative maximum hourly, daily and annual average TSP concentrations at 1.5m above ground level for scenario 1 and 2 are presented in Figure Nos. NEX2213/C/331/ENS/M60/502 – NEX2213/C/331/ENS/M60/507.  Marginal exceedance of 24-hour and annual average TSP concentrations are predicted at part of the building of POC in the contour plots, however, the building of the POC is provided with central air conditioning and there is no fresh air intake at these areas, i.e. no air sensitive areas are located within the exceedance areas.  Potential impacts at dwelling vessels within the CBTS have also been examined for the purposes of being comprehensive as they do not have exact addresses and are movable within the anchorage area.   As known, the area for dwelling vessels anchored within the CBTS would be at about 40m setback from the temporary reclamation area.  No exceedance of 1-hour and 24-hour average TSP concentrations is predicted at the anchorage area for the dwelling vessels for the dwelling vessels due to the works under this Project.  Marginal exceedances of annual average TSP concentration are predicted at a relatively small part outside the works area as shown in the contour plots, i.e. near the proposed temporary jetty and along the southern works boundary. In view of the small area and narrow navigation channel at these locations, the dwellings will unlikely be anchored within these exceedance zones. Also, in view of the fact that the dwelling vessels do not have exact addresses and are movable within the anchorage area, the predicted annual average impacts are not relevant.

Evaluation of Residual Impacts

5.47        With the implementation of the recommended mitigation measures as well as the dust suppression measures and good site practices stipulated in the Air Pollution Control (Construction Dust) Regulation, the predicted dust impact at ASRs would comply with the hourly, daily and annual average TSP criteria in the EIAO-TM and AQO. 

Environmental Monitoring and Audit Requirements

5.48        Environmental monitoring and audit for dust emission should be conducted during the construction phase of the Project so as to check compliance with legislative requirements.  Details of the monitoring and audit programme are contained in a stand-alone EM&A Manual.

Conclusion

5.49        Potential air quality impacts from the construction works for the Project would mainly be related to construction dust from temporary reclamation, excavation, materials handling, spoil removal and wind erosion.  With the implementation of the recommended mitigation measures as well as the dust suppression measures and good site practices stipulated in the Air Pollution Control (Construction Dust) Regulation, no adverse dust impact on the ASRs in the vicinity of the construction sites would be anticipated. 


 



[1]  Territory Development Department (July 2001). Central Reclamation, Phase III Studies, Site Investigation, Design and Construction, Environmental Monitoring and Audit Manual  

 

[2] USEPA, AP-42, “Control of Open Fugitive Dust Sources”