4.1
Potential
air quality impact arising from the construction works would mainly be related
to construction dust from excavation, materials handling, spoil removal and
wind erosion. As construction dust is
the prime concern, monitoring should be carried out to evaluate the dust impact
during the construction phase. Total Suspended Particulates (
4.2
In
this section, the requirements, methodology, equipments, monitoring locations
and criteria for the monitoring and audit of air quality impact during the
construction phase of the Project are presented.
Monitoring Parameters and Equipment
4.3
Monitoring
and audit of the TSP levels should be carried out by the ET to ensure that any
deteriorating air quality could be readily detected and timely action taken to
rectify the situation.
4.4
One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The TSP levels should be measured by
following the standard method as set out in High Volume Method for Total
Suspended Particulates, Part 50 Chapter 1 Appendix B, Title 40 of the Code of
Federal Regulations of the USEPA (hereinafter referred to as “HVS method”).
4.5
All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of sampler, identification and weight of
the filter paper, and other special phenomena and work progress of the
concerned site, etc, should be recorded down in detail. A sample data sheet is shown in Appendix B3.
4.6
High
volume sampler (HVS) in compliance with the following specifications should be
used for carrying out the 1-hour and 24-hour monitoring:
(i)
0.6 - 1.7 m3 per minute (20 -
60 standard cubic feet per minute) adjustable flow range;
(ii)
equipped with a timing / control device
with ± 5 minutes accuracy for 24 hours operation;
(iii) installed with elapsed-time meter with ± 2 minutes accuracy
for 24 hours operation;
(iv) capable of providing a minimum exposed area of 406 cm2
(63 in2);
(v) flow control accuracy:
± 2.5% deviation over 24-hour sampling period;
(vi) equipped with a shelter to protect the filter and sampler;
(vii) incorporated with an electronic mass flow rate controller or
other equivalent devices;
(viii) equipped with a flow recorder for continuous monitoring;
(ix) provided with a peaked roof inlet;
(x) incorporated with a manometer;
(xi) able to hold and seal the filter paper to the sampler housing
at horizontal position;
(xii) easy to change the filter; and
(xiii) capable
of operating continuously for 24-hour period.
4.7
The
ET should be responsible for the provision of the monitoring equipment. He
should provide sufficient number of HVS or direct reading dust meter with
appropriate calibration kit for carrying out the baseline, regular impacts
monitoring and ad-hoc monitoring.
The HVSs should be equipped with an electronic mass flow controller and
be calibrated against a traceable standard at regular intervals, in accordance
with requirements stated in the manufacturers operating manual and as described
below. All the equipment,
calibration kit, filter papers, etc, should be clearly labelled.
4.8
Initial
calibration of HVSs with mass flow controller should be conducted upon
installation and thereafter at bi-monthly intervals. The transfer standard
should be traceable to the internationally recognized primary standard and be
calibrated annually. The
calibration data should be properly documented for future reference by the IEC.
All the data should be converted into standard temperature and pressure
condition.
4.9
The
flow-rate of the sampler before and after the sampling exercise with the filter
in position should be verified to be constant and be recorded on the data sheet
as shown in Appendix B3.
4.10
If
the ET Leader proposes alternative dust monitoring equipment / methodology
(e.g. direct reading methods) after this manual is issued, the ET should submit
sufficient information to the IEC to prove that the instrument is capable of
achieving a comparable result to the HVS. The instrument should also be
calibrated regularly, and the 1-hour sampling should be determined periodically
by the HVS to check the validity and accuracy of the results measured by direct
reading method.
4.11
Wind
data monitoring equipment should also be provided and set up for logging wind
speed and wind direction near the dust monitoring locations. The equipment
installation location should be proposed by the ET and agreed with the IEC. For
installation and operation of wind data monitoring equipment, the following
points should be observed:
(i)
The wind sensors should be installed 10m
above ground so that they are clear of obstructions or turbulence caused by
buildings.
(ii)
The wind data should be captured by a
data logger. The data should be downloaded for analysis at least once a month.
(iii) The wind data monitoring equipment should be re-calibrated
at least once every six months.
(iv) Wind direction should be divided into 16 sectors of 22.5
degrees each.
4.12
In
exceptional situations, the ET may propose alternative methods to obtain
representative wind data upon approval from the ER and agreement from the IEC.
Laboratory Measurement /
Analysis
4.13
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments to handle the dust
samples collected, should be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
4.14
If
a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for
carrying out the laboratory analysis, the laboratory equipment should be
approved by the ER and the measurement procedures should be witnessed by the
IEC. Any measurement performed by the laboratory should be demonstrated to the
satisfaction of the ER and IEC. IEC should regularly audit to the measurement
performed by the laboratory to ensure the accuracy of measurement results. The
ET Leader should provide the ER with one copy of the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B
for his reference.
4.15
Filter
paper of size 8” x 10” should be labeled before sampling. It should be a clean
filter paper with no pinholes, and should be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.16
After
sampling, the filter paper loaded with dust should be kept in a clean and
tightly sealed plastic bag. The filter paper should then be returned to the
laboratory for reconditioning in the humidity-controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance should be regularly calibrated against a traceable standard.
4.17
All
the collected samples should be kept in a good condition for 6 months before
disposal.
Proposed Dust Monitoring Stations
4.18
The worst affected locations in the vicinity of the
construction activities of the Project identified for dust monitoring are
listed in Table 4.1 and shown in Figure Nos.
NEX2213/C/331/ENS/M62/530.
Table 4.1 Proposed Dust Monitoring Locations
Identification No. |
ASR ID in EIA Report |
Air Monitoring
Location |
AM1 |
CHA4 |
Royal |
4.19
The
status and locations of air quality sensitive receivers may change after this
manual is issued. If this happens, the ET Leader should propose updated
monitoring locations and seek approval from ER and agreement from the IEC and
EPD.
4.20
When
alternative monitoring locations are proposed, the monitoring locations should
be chosen based on the following criteria:
(i)
Monitoring at sensitive receivers close
to the major site activities which are likely to have air quality impacts;
(ii) Monitoring at the air sensitive receivers as defined in the
EIAO-TM; and
(iii) Assurance of minimal disturbance to the occupants during
monitoring.
4.21
When
positioning the HVSs, the following points should be noted:
(i)
A horizontal platform with appropriate
support to secure the samplers against gusty wind should be provided;
(ii) no two samplers should be placed less than 2m apart;
(iii) the distance between the sampler and an obstacle, such as
buildings, must be at least twice the height that the obstacle protrudes above
the sampler;
(iv) a minimum of 2m separation from walls, parapets and
penthouses is required for rooftops samplers;
(v) a minimum of 2m separation from any supporting structure,
measures horizontally is required;
(vi) no furnace or incinerator flue is nearby;
(vii) airflow around the sampler is unrestricted;
(viii) the sampler is more than
(ix) any wire fence and gate to protect the sampler, should not
cause any obstruction during monitoring;
(x) permission must be obtained to set up the samplers and to
obtain access to the monitoring stations; and
(xi) a
secured supply of electricity is needed to operate the samplers.
4.22
Baseline
monitoring should be carried out to determine the ambient 1-hour and 24‑hour
TSP levels at the monitoring locations prior to the commencement of the Project
works. Before commencing the baseline monitoring, the ET leader should inform
the IEC of the baseline monitoring programme such
that the IEC can conduct on-site audit to ensure accuracy of the baseline
monitoring results.
4.23
During
the baseline monitoring, there should not be any construction or dust
generating activities in the vicinity of the monitoring stations. TSP baseline
monitoring should be carried out for a continuous period of at least two weeks
with the 24-hour and three sets of 1-hour ambient measurements taken daily at
each monitoring location. General
meteorological conditions (wind speed, direction and precipitation) and notes
regarding any significant adjacent dust producing sources should also be
recorded throughout the baseline monitoring period. A summary of baseline monitoring is
presented in Table 4.2.
4.24
The
baseline monitoring will provide data for the determination of the appropriate
Action levels with the Limit levels set against statutory or otherwise agreed
limits. In case the baseline monitoring cannot be carried out at the designated
monitoring locations during the baseline monitoring period, the ET leader should
carry out the monitoring at alternative locations that can effectively
represent the baseline conditions at the impact monitoring locations.
4.25
In
exceptional cases, when insufficient baseline monitoring data or questionable results
are obtained, the ET should liaise with IEC and EPD to agree on an appropriate
set of data to be used as a baseline reference and submit
to ER for approval.
4.26
Ambient
conditions may vary seasonally and should be reviewed once every three months. When the ambient conditions have changed
and a repeat of the baseline monitoring is required to be carried out for
obtaining the updated baseline levels, the monitoring should be at times when
the Contractor's activities are not generating dust, at least in the proximity
of the monitoring stations. Should
change in ambient conditions be determined, the baseline levels and, in turn,
the air quality criteria, should be revised. The revised baseline levels and air
quality criteria should be agreed with the IEC and EPD.
4.27
Before
commencing baseline monitoring, the ET should inform the IEC of the impact
monitoring programme such that the IEC can conduct
on-site audit to ensure accuracy of the impact monitoring results.
4.28
For
regular 24-hour TSP impact monitoring, a sampling frequency of at least once in
every six days should be strictly observed at the monitoring stations when there are Project related construction activities
being undertaken within a radius of 300m from these monitoring stations. For 1-hour TSP
monitoring, the sampling frequency of at least three times in every six-days
should be undertaken when the highest dust impact occurs.
4.29
In
case of non-compliance with the air quality criteria, more frequent monitoring,
as specified in the Action Plan in the following section, should be conducted
within 24 hours after the result is obtained. This additional monitoring should
be continued until the excessive dust emission or the deterioration in the air
quality is rectified.
4.30
A
summary of the impact monitoring programme is
presented in Table 4.2.
Table 4.2 Summary of Dust Monitoring Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline Monitoring |
Consecutive days of at least 2 weeks before
commencement of construction works |
1 hour TSP |
·
3 times per day |
Continuous 24-hour TSP |
·
Daily |
||
Impact Monitoring |
Throughout the construction phase* |
1 hour TSP |
·
3 times in every 6
days |
Continuous 24-hour TSP |
·
Once every 6 days |
Noted: *
Impact
monitoring should be conducted at the monitoring stations for 24-hour TSP
monitoring when there are
Project related construction activities being undertaken within a radius of
300m from these monitoring stations.
4.31
Action
and Limit (A/L) levels that provide an appropriate framework for the
interpretation of monitoring results have to be agreed between ET, IEC, EPD and
the ER before commencement of the air monitoring. The air quality monitoring data should
be checked against the agreed A/L levels.
Recommended A/L levels are listed in Table 4.3.
Table 4.3 Proposed Action and Limit Levels for Impact Monitoring
Parameter |
Action Level (1) |
Limit Level |
24-hour TSP |
·
BL £ 200μg m-3, ·
BL > 200μg m-3, |
260 μg m-3 |
1-hour TSP |
·
BL £ 384μg m-3, ·
BL
> 384μg m-3, |
500 μg m-3 |
(1) BL =
Baseline level,
4.32
In
the cases where exceedance of these A/L levels occurs,
actions in accordance with the Event and Action Plan in Table 4.4 should be carried out.
Table 4.4 Event and Action Plan for Construction Dust Monitoring
ACTION |
||||
ET |
IEC |
ER |
CONTRACTOR |
|
ACTION LEVEL |
||||
1. Exceedance
for one sample |
1. Identify source, investigate the causes of complaint
and propose remedial measures; 2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4.
Increase monitoring
frequency to daily. (The above actions should be taken within 2 working
days after the exceedance is identified.) |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Notify Contractor. (The above actions should be taken within 2 working
days after the exceedance is identified.) |
1. Rectify any unacceptable
practice; 2. Amend working methods if
appropriate. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
2. Exceedance
for two or more consecutive samples |
1. Identify source; 2. Inform IEC and ER; 3. Advise the ER on the effectiveness of the proposed
remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on remedial actions
required; 7. If exceedance continues,
arrange meeting with IEC and ER; 8. If exceedance stops, cease
additional monitoring. (The above actions should be taken within 2 working
days after the exceedance is identified.) |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial
measures; 4. Advise the ET on the effectiveness of the proposed
remedial measures; 5. Supervise Implementation of remedial measures. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Confirm
receipt of notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Submit proposals for remedial to
ER within three working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
LIMIT LEVEL |
||||
1. Exceedance
for one sample |
1. Identify source, investigate the
causes of exceedance and propose remedial measures; 2. Inform IEC, ER, Contractor and
EPD; 3. Repeat measurement to confirm
finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of
Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results. (The above actions should be taken within 2 working
days after the exceedance is identified.) |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial
measures; 4. Advise the ER on the effectiveness of the proposed
remedial measures; 5. Supervise implementation of remedial measures. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within
three working days of notification; 3. Implement the agreed proposals; 4.
Amend proposal if
appropriate. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
2. Exceedance
for two or more consecutive samples |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER to discuss the
remedial actions to be taken; 7. Assess effectiveness of Contractor’s remedial actions
and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease
additional monitoring. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Discuss amongst ER, ET, and Contractor on the potential
remedial actions; 2. Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial measures. (The above actions should be taken within 2 working
days after the exceedance is identified.) |
1. Confirm receipt of notification of failue in writing; 2. Notify Contractor; 3. In consultation with the IEC, agree with the
Contractor on the remedial measures to be implemented; 4. Ensure remedial measures properly implemented; 5. If exceedance continues,
consider what portion of the work is responsible and instruct the Contractor
to stop that portion of work until the exceedance
is abated. (The above actions
should be taken within 2 working days after the exceedance
is identified.) |
1. Take immediate action to avoid
further exceedance; 2. Submit proposals for remedial
actions to IEC within three working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem
still not under control; 5. Stop the relevant portion of
works as determined by the ER until the exceedance
is abated. (The above actions should be taken within 2 working days after the exceedance is identified.) |
Mitigation Measures
4.33
Dust
mitigation measures stipulated in the Air Pollution Control (Construction Dust)
Regulation should be implemented to control dust emissions from all
construction work sites.
Use of regular watering, with complete
coverage, to reduce dust emissions from exposed site surfaces and unpaved
roads, particularly during dry weather.
Use of frequent watering for
particularly dusty construction areas and areas close to ASRs.
Side enclosure and covering of any
aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering shall be applied to aggregate fines.
Open stockpiles shall be avoided or
covered. Where possible, prevent
placing dusty material storage piles near ASRs.
Tarpaulin covering of all dusty
vehicle loads transported to, from and between site locations.
Establishment and use of vehicle wheel
and body washing facilities at the exit points of the site.
Provision of wind shield and dust
extraction units or similar dust mitigation measures at the loading points, and
use of water sprinklers at the loading area where dust generation is likely
during the loading process of loose material, particularly in dry seasons/
periods.
Provision of not less than
Imposition of speed controls for
vehicles on site haul roads.
Where possible, routing of vehicles
and positioning of construction plant should be at the maximum possible
distance from ASRs.
Every stock of more than 20 bags of
cement or dry pulverised fuel ash (PFA) should be
covered entirely by impervious sheeting or placed in an area sheltered on the
top and the 3 sides.
Instigation of an environmental
monitoring and auditing program to monitor the construction process in order to
enforce controls and modify method of work if dusty conditions arise.
4.34
Other
site-specific mitigation measures are presented in Appendix A.