Annex A Implementation
Schedule for Environmental Protection Measures for the Regulation of
EIA Ref. |
Environmental
Protection Measures |
Location/Duration of Measures/Timing of
Completion of Measures |
Implementation Agent |
Implementation Stage |
Relevant Legislation & Guidelines |
|||
Des |
C |
Post- C |
O |
|||||
1. Air Quality Measures |
||||||||
S4.8 |
Dust control measures stipulated in the Air Pollution Control (Construction Dust)
Regulation will be implemented during the construction phase to control
the potential fugitive dust emissions. In particular: ·
Water spaying on haul roads and
dusty areas for every hour during construction, ·
Covering the stockpile areas of at
least 70% area with tarpaulin sheet or impervious sheet; ·
Covering of dusty materials/spoils
on trucks by impervious sheets; ·
Controlling the dropping height of
fill materials; ·
Covering or storing all debris and
materials in a sheltered debris collection area; ·
Storing dredged sediment in a
separate enclosed tank; and ·
Providing wheel washing facility at
each exit of the works site. |
Whole Site / During Construction |
Contractor(s) |
|
ü |
|
|
Air Pollution Control (Construction Dust) Regulation |
S4.8 |
Site practices such as regular
maintenance and checking of the diesel powered mechanical equipment will be
adopted to avoid any black smoke emissions and to minimize gaseous emissions. |
Whole Site / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S4.8 |
Dredged sediment placed on truck or
marine vessel for disposal should be properly covered during transportation
to minimize the potential odour.
In the event that dredging material are found to be o |
Whole Site / During
Construction and Maintenance Dredging |
Contractor(s) |
|
ü |
|
ü |
- |
S4.10 |
Construction Dust Monitoring at two
monitoring stations and site inspection and audit of dust generating
activities. Monitoring of 24-hour and 1-hour TSP levels will be conducted
once every six days throughout the construction period. |
Whole Site / During
Construction |
Environmental
Team (ET) & Independent Environmental Checker (IEC) |
|
ü |
|
|
Environmental Impact
Assessment Ordinance |
2. Noise |
||||||||
S5.8 |
The following
site practices should be followed during the construction of the Project: ·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction phase; ·
Silencers or
mufflers on construction equipment should be utilized and should be properly
maintained during the construction phase; ·
Mobile plant,
if any, should be sited as far from NSRs as possible; ·
Machines and
plant (such as trucks) that may be in intermittent use should be shut down
between work periods or should be throttled down to a minimum; |
Whole Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
|
·
Plant known to
emit noise strongly in one direction should, wher ·
Material
stockpiles and other structures should be effectively utilised, wher |
|
|
|
|
|
|
|
S5.8 |
Use quiet PME
as far as practicable to mitigate the construction noise impact. |
Whole Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S5.8 |
Use temporary nosie barriers to mitigate the noise impact arising from the
construction works, particularly for low-rise NSRs. Movable noise barriers of 3 m in height with
skid footing should be used and located within a few metres of stationary
plant and mobile plant such that the line of sight to the NSR is blocked by
the barriers. The length of the barrier should be at least five times
greater than its height. With reference to A Practical Guide for the Reduction of
Noise from Construction Works, the noise barrier material should have a
superficial surface density of at least 7 kg m-2 and have no
openings or gaps. |
Works Area III and IV/ During
Construction |
Contractor(s) |
|
ü |
|
|
A Practical Guide for the
Reduction of Noise from Construction Works |
S5.8 |
Scheduling of
construction activities with identified grouping of PMEs. |
Works Area III/ During Construction |
Contractor(s) |
|
ü |
|
|
- |
S5.10 |
Weekly noise monitoring at two monitoring
stations and monthly site inspection and audit of construction activities. |
Whole Site / During
Construction |
ET & IEC |
|
ü |
|
|
Environmental Impact
Assessment Ordinance |
3. Water Quality |
||||||||
S6.8 |
Maximum loss rate during the wet
excavation should be kept at or below the limits specified in the EIA Report.
|
Excavation area / During Construction |
Contractor(s) |
|
ü |
|
|
|
S6.8 |
Cofferdam
Demolition During excavation, the following measures
shall apply at all times: ·
Dry excavation will be used, as
far as practicable, for cofferdam excavation. ·
Attention will be paid to the
lifting speed of the grab to minimise the loss of sediment. ·
Excavated sediment will be
disposed of in a gazetted marine disposal area in accordance with the Dumping
at Sea Ordinance (DASO) permit conditions. ·
The marine vessels for
transport of sediment to the marine dumping ground will be fitted with tight
bottom seals in order to prevent leakage of material during transport. The barges will be filled to a level
that adequate freeboard is maintained to ensure that the decks are not washed
by wave action. ·
The contractor(s) will confirm
that the works cause no visible foam, oil, grease, litter or other
objectionable matter to be present in the water within and adjacent to the
excavation site. ·
For concurrent excavation works
at adjacent work areas (ie Work Areas I and II, and Work Areas III and IV),
construction will be carried out along the same flow direction (ie from
upstream to downstream / downstream to upstream) to minimise the overall
impacts to SS concentrations from adjacent work areas. |
Cofferdam excavation area / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Construction
Site Runoff and Drainage Channels, earth bunds or sand bag
barriers will be provided on site to direct stormwater to silt removal
facilities. The design of silt
removal facilities will make reference to the guidelines in Appendix A1 of ProPECC PN 1/94. All
drainage facilities and erosion and sediment control structures will be
inspected on a regular basis and maintained to confirm proper and efficient
operation at all times and particularly during rainstorms. Deposited silt and grit will be
removed regularly. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
ProPECC PN 1/94 TM standard under the WPCO |
S6.8 |
Excavation within cofferdam will be
maintained in dry condition as far as possible. Water within the cofferdam will be
discharged to the river before excavation commence and at times when needed,
e.g. after heavy rain. Adequate
time (48 hours) will be allowed for suspended solid to settle (potentially
overnight) before foundation pit drainage are being discharged outside the
works area |
Within
cofferdam / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Non-active area
along the river bank will be covered by impermeable sheets or hydroseeding
completed sections immediately whenever possible to minimise erosion of soil
by runoff particularly during heavy rainstorms |
River bank /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Earthworks to form the final surfaces
will be followed up with surface protection and drainage works to prevent
erosion caused by rainstorms. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Appropriate surface drainage will be
designed and provided where necessary.
In particular,
surface runoff will be collected along the river bank and be diverted to
sedimentation tank/pond before being discharged into the river. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
The precautions to be taken at any time
of year when rainstorms are likely together with the actions to be taken when
a rainstorm is imminent or forecasted and actions to be taken during or after
rainstorms are summarised in Appendix
A2 of ProPECC PN 1/94. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
ProPECC PN 1/94 |
S6.8 |
Oil interceptors will be provided in the
drainage system where necessary and regularly emptied to prevent the release
of oil and grease into the storm water drainage system after accidental
spillages. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Temporary and permanent drainage pipes
and culverts provided to facilitate runoff discharge will be adequately
designed for the controlled release of storm flows. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
The temporary diverted drainage will be
reinstated to the original condition when the construction work has finished
or when the temporary diversion is no longer required. |
Land Site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
The dredged sediment will be temporary
stored in the stockpile areas for dewatering by natural ventilation. Runoff from these stockpile areas will
be collected for treatment by sedimentation with the addition of
coagulant. The treated water will
be reuse on site for water spraying. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
An adequate number of portable toilets
will be provided for the on-site construction workforce. Wastewater/sewage will be handled by
registered collector in |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Debris and refuse generated on-site will
be collected, handled and disposed of properly to avoid entering the nearby
WSRs. Stockpiles of cement and
other construction materials will be covered when not being used. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S6.8 |
Oil leakage or spillage will be contained
and clean up immediately. Waste
oil will be collected and stored for recycling or disposal, in accordance
with the Waste Disposal Ordinance. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal Ordinance |
S6.11 |
Water
quality monitoring will be undertaken during the foundation pit drainage and
cofferdam demolition activities at the following locations: During foundation
pit drainage and cofferdam demolition activities at
Work Area I and Work Area II ·
500
m upstream of Work Area I; and ·
1,000
m downstream of Work Area II. During foundation
pit drainage and cofferdam demolition activities at
Work Area III and Work Area IV ·
500
m upstream of Work Area III; and ·
1,000
m downstream of Work Area IV. |
500m upstream of Work Area and 1000m
downstream of work area/During foundation pit drainage and cofferdam demolition |
Contractor(s) |
|
ü |
|
|
- |
4. Terrestrial Ecology |
||||||||
S7.11 |
Avoid
potential impacts on the trees whenever possible
during the detailed design stage. The retained trees will be fenced off as
protection from the construction works.
If the trees
cannot be avoided due to the engineering
constraint, the affected individual(s) will be transplanted to compensatory
woodland planting site near Pak Fu Shan or a similar habitat in the vicinity of the Project Site if
considered suitable (subject to the detailed assessment of the feasibility of
transplantation). |
Whole Site / During
Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S7.11 |
A detailed vegetation survey
on the trees within the impacted area would be conducted by a suitably
qualified botanist/ ecologist to identify and record the affected individuals
prior to the commencement of site clearance works. Feasibility and suitability of
transplanting the affected plant species of conservation interest would be
carefully studied and suitable receptor sites would be identified during Tree
Felling Application. |
Whole Site / During Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S7.11 |
Avoid any
damage and disturbance, particularly those caused by filling and illegal
dumping, to the surrounding habitats through proper management of waste
disposal. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Arrange river
excavation works to be conducted in dry season (November to March) in order
to minimise the potential water quality impacts on downstream areas of high
ecological value. Impacts due to
the excavation works on the habitat and associated wildlife during dry season
can be minimised through phase implementation of works and adoption of good
site practices. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Regularly check
the Site boundaries to ensure that they are not breached and that no damage
occurs to surrounding areas |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Regularly check
the performance and/ or effectiveness of the cofferdam and “diversion dyke”
in order to minimise surface runoff and the chance of soil erosion; |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Prohibit and
prevent open burning within the site boundary during construction and provide
temporary fire fighting equipment in the work areas |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Reinstate
temporary work sites/disturbed areas (including approximately 1.6 ha of the |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Provided approximately 0.5 ha of compensatory woodland planting (in
addition to the reinstatement of the 0.4 ha secondary woodland) within the
Project Site near Pak Fu Shan. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Provide
additional stream/river habitat with natural bottom (~2.1 ha) after the
advanced works and river modification works. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S7.11 |
Adopt proper
ecological design for the landscape works along the river banks, including
the floodplain (the 1.9ha marshy low-lying grassland will be reinstated in
the floodplains at |
Along river bank and water retardation
pond / During Design Stage |
Designer(s) |
ü |
|
|
|
- |
S7.14 |
The
implementation of landscape works (including compensatory planting) adopting
ecological design at |
Whole site / During Post-Construction
Stage |
Designer(s) |
|
|
ü |
|
- |
S7.14 |
One-year bird
monitoring programme shall be conducted to monitor the effectiveness of the
reprovisioned/reinstated habitats |
Operation |
Project
Proponent/ Contractor(s) |
|
|
|
ü |
- |
5 Waste Management |
||||||||
S9.6 |
General The Contractor shall apply for and obtain
the appropriate licenses for the disposal of public fill, chemical waste and
effluent discharges. |
Contract
mobilisation / During construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes WBTC No 5/99, Trip-ticket System for Disposal of Construction and
Demolition Material Water Pollution Control Ordinance |
S9.6 |
Nomination of
approved personnel to be responsible for standard site practices,
arrangements for collection and effective disposal to an appropriate facility
of all wastes generated at the Project Site |
Contract mobilisation
/ During construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Training shall
be provided to site personnel in proper waste management and chemical
handling procedures, the concepts of site cleanliness and
appropriate waste management procedures, including waste reduction, reuse and
recycling. |
Contract mobilisation / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Provision of
sufficient waste disposal points and regular collection for disposal. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
WBTC Nos. 6/2002
and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness. Works
Bureau, |
S9.6 |
Appropriate
measures to reduce windblown litter and dust transportation of waste by
either covering trucks or by transporting wastes in enclosed containers. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Separation of
chemical wastes for special handling and appropriate treatment at the
licensed hazardous waste treatment facility in Shenzhen (during the river
modification and associated works) or the Chemical Waste Treatment Centre at
Tsing Yi (during the advanced works). |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation |
S9.6 |
Regular
cleaning and maintenance programme for drainage systems, sumps and oil
interceptors. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
A recording
system for the amount of wastes generated/recycled and disposal sites. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Waste Reduction Measures ·
Segregation
and storage of different types of waste in different containers, skips or
stockpiles to enhance reuse or recycling of material and their proper
disposal. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
WBTC Nos. 6/2002
and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness. |
S9.6 |
·
Encourage
collection of aluminium cans and waste paper by individual collectors during
construction with separate labelled bins provided to segregate these wastes
from other general refuse by the workforce |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
|
S9.6 |
·
Any
unused chemicals and those with remaining functional capacity will be
recycled as far as possible |
Land Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
·
Use
of reusable non-timber formwork to reduce the amount of C&D materials |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
Works Branch
Technical Circular (WBTC) No. 32/92, The Use of Tropical Hard Wood on
Construction Site |
S9.6 |
·
Prior
to disposal of construction waste, wood, steel and other metals will be
separated to the extent practical, for re-use and/or recycling to reduce the
quantity of waste to be disposed of to landfill |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
·
Proper
storage and site practices shall be adopted to reduce the potential for
damage or contamination of construction materials. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
·
Plan
and stock construction materials carefully to reduce amount of waste
generated and avoid unnecessary generation of waste |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Dredged
Sediments The dredged sediment shall be stored in enclosed container and will be
delivered to Shekou Pier by enclosed trucks |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
The disposal of
dredged river sediment will follow the requirements stipulated in the ETWB TC(W) No. 34/2002. Detailed sampling and
chemical testing will be carried out prior to the commencement of the
dredging activities to confirm the sediment disposal method. |
Contract
mobilisation / During construction and maintenance dredging |
Contractor(s) |
ü |
ü |
|
ü |
Dumping at Sea
Ordinance ETWB TC(W) No. 34/2002 |
S9.6 |
Excavated Materials The contractor
of the advanced work should open a billing account with EPD for the payment
of disposal charges. A
trip-ticket system will be established in accordance with ETWB TC(W) No. 31/2004 to monitor the
reuse of surplus excavated materials off-site and disposal of construction
waste and general refuse at landfills, and to control fly-tipping |
Contract
mobilisation / During construction |
Contractor(s) |
ü |
ü |
|
|
Waste Disposal
(Charges for Disposal of Construction Waste) Regulation ETWB TC(W) No.
31/2004 |
S9.6 |
Ways to minimise generation of
C&D materials include: (i)
The Contractor is required to submit the
Waste Management Plan (WMP) for approval by the Engineer with appropriate
mitigation measures to deal with and allow space for waste segregation.
Different C&D materials should be sorted into different categories
for re-use/recycle. Day-to-day site operations of the Contractor should
be closely monitored to ensure compliance with the approved WMP. (ii)
The designer shall ensure that the design
of levels and dimensions are reasonably accurate to avoid unnecessary demolition,
excavation and fill. (iii)
The Contractor shall be encouraged to use
long lasting materials such as steel and poly-fibre for formwork on site. (iv)
The RSS shall control the disposal of
public fill and C&D waste to the designated public filling facilities and
landfills respectively through the implementation of a trip-ticket system
according to ETWB TC(W) No. 31/2004. |
Whole site /
During construction |
Contractor(s) |
|
ü |
|
|
- |
|
Ways to maximize
the use of inert C&D material include: (i)
The Contractor shall review the
WMP quarterly to improve the site practice and maximise the use of inert
C&D material. (ii)
Different sections of works shall
be programmed to ensure the C&D materials generated could be re-used by
the other sections of works or works contracts. (iii)
Temporary storage areas should be
identified to resolve programming mismatch between excavation and filling
works. (iv)
The excavated soft inert C&D
materials should be reused for backfilling the boundary patrol road, channel
embankment, etc. whenever practicable. (v)
Good quality top soil should be
reused for landscaping. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
|
Ways to maximise
the re-use/recycle of C&D material and/or rock on site include: (i)
Recyclable materials such as wood
and metal should be salvaged for reuse and inert materials utilized as public
fill. (ii)
Segregation and storage of
different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of material and their proper disposal. Prior
to disposal of C&D waste, it is recommended that wood, steel and other
metals be separated for re-use and/or recycling and inert waste utilized as
fill material to minimize the quantity of waste to be disposed of at
landfills. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Ways to maximise
the use of recycled C&D materials include: (i)
Relevant clauses
would be incorporated in the Particular Specifications to facilitate the use
of recycled aggregates as far as practicable, such as, temporary works,
general fills and road sub-base. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
To reduce the potential dust impacts of the
excavation works, the C&D materials will be wetted as quickly as possible
to the extent practice after filling. |
Whole Site / During
Construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Chemical Waste Containers used for storage of chemical
waste shall be: ·
Maintained in good condition and
clearly labelled in both English and Chinese; ·
Suitable
for the substance they are holding, resistant to corrosion, and securely
closed; and ·
Capacity
of less than 450 L unless the specifications have been approved by the EPD. |
All facilities
/ During construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes |
S9.6 |
Storage areas for chemical waste shall: ·
Be
clearly labelled and used solely for the storage of chemical waste; ·
Be enclosed on at least 3 sides; ·
Have
adequate ventilation; ·
Be
arranged so that incompatible materials are appropriately separated ·
Have an impermeable floor and
bunding, of capacity to accommodate 110% of the volume of the largest
container or 20% by volume of the chemical waste stored in that area,
whichever is the greatest; and ·
Be
covered to prevent rainfall from entering |
All facilities
/ During construction |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes |
S9.6 |
Any unused
chemicals and those with remaining functional capacity shall be recycled to
the extent practical. |
Land site /
During construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
A licensed contractor shall be employed
to collect chemical waste for delivery to a licensed treatment facility. |
Chemical Waste
Treatment |
Contractor(s) |
|
ü |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation Code of Practice on the Packaging, Labelling and Storage of Chemical
Wastes |
S9.6 |
General
Refuse General refuse shall be timely cleared
and shall be disposed of to the nearest licensed facility by reputable waste
collector on regular basis to reduce odour, pest and litter impacts. |
All areas /
During construction |
Contractor(s) |
|
ü |
|
|
WBTC Nos. 6/2002
and 6/2002A, Enhanced Specification for Site Cleanliness and Tidiness. |
S9.6 |
No waste shall be burnt on site. Wastes shall be collected by licensed
waste haulier and be disposed of at licence sites. |
Land site/
During construction |
Contractor(s) |
|
ü |
|
|
Air Pollution Control Ordinance |
S9.6 |
Recycling bins
will be provided at strategic locations to facilitate recovery of aluminium
can and waste paper from the site.
|
All areas /
During construction |
Contractor(s) |
|
ü |
|
|
- |
S9.6 |
Training will be provided to workers on
the concepts of site cleanliness and appropriate waste management procedures,
including waste reduction, reuse and recycling at the beginning of the
construction works. |
All areas /
During construction |
Contractor(s) |
|
ü |
|
|
- |
S9.8 |
EM&A of waste handling, storage,
transportation, disposal procedures and documentation through the site inspection
and audit programme shall be undertaken. |
All facilities /
During construction |
ET and IEC |
|
ü |
|
|
- |
S9.8 |
Waste
Management Plan (WMP) will be prepared and implemented in accordance with ETWB TC(W) No. 19/2005. |
All facilities /
During construction |
Contractor(s) |
|
ü |
|
|
ETWB TC(W) No. 19/2005 |
6 Cultural Heritage |
||||||||
S11.8.1 |
Pursuant to the
Antiquities and Monuments Ordinance, the project proponent should inform the
AMO immediately in case of discovery of antiquities or supposed antiquities
in the course of soil excavation works in construction stage. |
Whole site /
During construction |
Project
Proponent |
|
ü |
|
|
Antiquities and Monuments
Ordinance |
S11.8.1 |
In case the works boundary of the Project
changes during the detailed design stage to cover additional area not being
assessed, the need for further archaeological survey and subsequent impact
assessment should be reviewed and AMO should be consulted. |
Additional works boundary not covered in
EIA / During design stage |
Design Team and the Project Proponent
(i.e. DSD) |
ü |
|
|
|
EIAO TM, Guidelines for CHIA, Antiquities
and Monuments Ordinance |
7. Landscape & Visual |
||||||||
S12.6.10 |
MM1: Tree Protection and
Preservation - Trees/ woodland within the Project Site will be protected and
preserved as far as possible in accordance with ETWB TCW No. 29/2004 and
3/2006.. |
Land site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM2: Tree Transplantation – Should removal of
trees be unavoidable due to construction impacts, trees will be transplanted
or felled according to the Detailed Tree Survey and Tree Felling
Application. Established trees of
value are to be re-located where practically feasible. |
Land site /
During Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S12.6.10 |
MM3: Minimize Disturbance – temporary structures
and construction works should be planned with care to minimize disturbance to
existing built structures as well as vegetation including riparian vegetation
along the river. |
Land site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM4: Compensatory Tree Planting - Where loss
of existing trees is unavoidable, compensatory planting of trees should be
provided in accordance with ETWB TCW No. 03/2006 to compensate for those
trees felled. Space is to be
allowed within the Project Site (mainly planting in riverbank landscape areas
of ~4.1 ha) for such planting. Plants will have 12 months to establish. Approximately 0.5 ha of compensatory
woodland planting (in addition to the reinstatement of the woodland (LR4) if
unavoidably affected) will be provided within the Project Site near Pak Fu
Shan. The proposed compensatory
woodland planting site will locate adjoining to the reinstated and existing
(undisturbed by the Project) woodland on hillside. The selection of planting species
shall be made with reference to the species identified in the Tree Survey and
be native to Hong Kong or the South China region. The compensatory woodland planting
should also adopt ecological design, ie provision of rare butterfly species
larval food plant (Trema sp.), and
further details refer to Section 7.11.3
of the EIA Report. The
arrangement of the on-site compensatory planting, ie tree/ shrub mix and Trema sp., will be subject to detailed
landscape design and planting plan, and recommended to be implemented prior
to the construction activities as far as practical. |
Compensatory
planting area / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM5: Screening – Stockpiles of materials
should be covered or hoarding erected where possible to reduce undesirable
views of the construction site (such as stockpile areas), having
consideration of safety and security.
It is proposed that screening be compatible with the surrounding
environment and where possible, non-reflective, recessive colours be
used. Hoarding should be taken
down at the end of the construction period. |
Land site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM6: Light Control – Control of night time
lighting glare shall be implemented to minimize glare impact to adjacent VSRs. |
Whole site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM7: Reinstatement – Terrestrial areas
temporarily disturbed by the Project during construction, should be
re-vegetated with shrubs, ground cover or grass in order to restore the green
ambiance or LR as existed before the commencement of the Project to blend
with the new environment, eg the earth embankment underneath the boundary
patrol road near Pak Fu Shan should be planted to ensure the embankment structure
blends in with the new environment.
|
Whole site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM8: Buffer Planting – Tree and Shrub planting
shall be provided for screening the natural watercourse, woodland and shrubby
grassland on lowland, proposed boundary control road and fencing, where
needed and taking into account security and boundary control limitations. |
Appropriate
location / During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM9: River Area Enhancement Landscaping – The
river bed should be non-concreted as far as practical. The River bank and margins of
approximately 4.1 ha should be enhanced with vegetation to compensate for the
loss of existing vegetation and to enhance the visual and landscape value of
the river where slope gradient allows.
The typical design of riverbank landscaping areas for the Project is
presented in Section 7.11.3 and Figure 7.11 of the EIA Report. The overall objectives for the
landscaping works will be mainly concerned with ecological enhancement but also
include landscape enhancement. For
the sloping banks of the river, in order to guarantee safety of flood
prevention, ecologically and environmentally friendly materials will be used
as far as possible. The
preliminary proposed landscape treatment along the sloping river banks can be
classified into three types: natural vegetation, semi-natural and
artificial. Further details of
the river area enhancement plans can be found in Section 3 of the EIA Report, including protection of river bed
with armour rock only where necessary and provision of grassed, cellular,
reinforced concrete eco-friendly slope protection. Eco-bags are made of UV-resistant
Polyethylene gas filled with fiber soil.
Final details of the landscaping will be prepared during the detailed
design stage of the Project.. |
Whole site /
During Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S12.6.10 |
MM10: Flood Retardation Pond - The flood
retardation pond lies within the Shenzhen side of this Project. It should be planted with suitable
flora (both aquatic and, riparian) to enhance its landscape value. Subject to the details design and
planting plan, provision of wetland planting at the base of flood retardation
pond will be provided as far as practical and technical feasible. Final details of the landscaping will
be prepared during the detailed design stage of the Project. |
Flood
Retardation Pond / During Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S12.6.10 |
MM11: Floodplain Areas - The areas bound by
sharp turns in the natural meander of the river should be made into
floodplain areas to retain some of the riparian landscape at the river
margins. The overall objectives
for the landscaping works will be mainly concerned with ecological
enhancement but also include landscape enhancement (also refer to Section 7.11.3 of the EIA Report). Further details will be developed
during Detailed Design Stage. |
Floodplain
areas / During Construction |
Contractor(s) |
ü |
ü |
|
|
- |
S12.6.10 |
MM12: Colours of Structures - Colours for the
structures eg fences should be chosen to complement the surrounding
area. Lighter colours such as
shades of light grey, off-white and light brown may be utilised where
technically feasible to reduce the visibility of the structures. |
Whole site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.6.10 |
MM13: Topsoil Reuse - Excavated topsoil should
be conserved for re-use by the Project or other projects. |
Whole site /
During Construction |
Contractor(s) |
|
ü |
|
|
- |
S12.9 |
The completed
landscape works adopting ecological design on the |
Whole site /
During 1 year Establishment period |
Landscape
Contractor |
|
|
ü |
|
- |