Section Title Page
Figures
Figure 1.1 Project
Layout Plan
Figure 4.1.1 Assessment Area and
Outline Zoning Plan
Figure 4.1.2 Recommended
Development Plan (Sheet 1 of 2)
Figure 4.1.3 Recommended
Development Plan (Sheet 2 of 2)
Figure 4.2 Representative
Noise Sensitive Receivers (Sheet 1 of 11)
Figure 4.3 Representative
Noise Sensitive Receivers (Sheet 2 of 11)
Figure 4.4 Representative
Noise Sensitive Receivers (Sheet 3 of 11)
Figure 4.5 Representative
Noise Sensitive Receivers (Sheet 4 of 11)
Figure 4.6 Representative
Noise Sensitive Receivers (Sheet 5 of 11)
Figure 4.7 Representative
Noise Sensitive Receivers (Sheet 6 of 11)
Figure 4.8 Representative
Noise Sensitive Receivers (Sheet 7 of 11)
Figure 4.9 Representative
Noise Sensitive Receivers (Sheet 8 of 11)
Figure 4.10 Representative
Noise Sensitive Receivers (Sheet 9 of 11)
Figure 4.11 Representative
Noise Sensitive Receivers (Sheet 10 of 11)
Figure 4.12 Representative
Noise Sensitive Receivers (Sheet 11 of 11)
Figure 4.13 Photos
of Noise Sensitive Receivers
Figure 4.14 Photos
of Noise Sensitive Receivers
Figure 4.15 Photos
of Noise Sensitive Receivers
Figure 4.16 Photos
of Noise Sensitive Receivers
Figure 4.17 Photos
of Noise Sensitive Receivers
Figure 4.18 Schematic
Diagram of Movable Noise Barrier
Figure 4.19 Schematic Diagram of Full
Noise Enclosure for PME
Figure 4.20.1 Proposed Location of
Noise Barriers (Sheet 1 of 4)
Figure 4.20.2 Proposed Location of
Noise Barriers (Sheet 2 of 4)
Figure 4.20.3 Proposed Location of
Noise Barriers (Sheet 3 of 4)
Figure 4.20.4 Proposed Location of
Noise Barriers (Sheet 4 of 4)
Figure 4.20.5 Cross-section Plans of
Proposed Barriers
Figure 4.21.1 Fixed Plant of Boundary Control Point
Figure 4.21.2 Fixed Plant of North
Tunnel North Portal
Figure 4.21.3 Fixed Plant of North
Tunnel South Portal
Figure 4.21.4 Fixed Plant of
Figure 4.21.5 Fixed Plant of South
Tunnel North Portal
Figure 4.21.6 Fixed Plant of
Figure 4.21.7 Fixed Plant of South
Tunnel South Portal
Appendices
Appendix 4.1 Unmitigated Construction
Plant Inventory
Appendix 4.2 Unmitigated
Construction Airborne Noise Impacts
Appendix 4.3 Mitigated Construction
Plant Inventory
Appendix 4.4 Mitigated Construction
Airborne Noise Impacts
Appendix 4.5 Unmitigated
Construction Ground-borne Noise Impacts
Appendix 4.6 Traffic Data and Road
Traffic Network
Appendix 4.7 Comparison Scenario
Between With and Without Project
Appendix 4.8 Unmitigated Road
Traffic Noise Level
Appendix 4.9 Mitigated Road Traffic
Noise Level
Appendix 4.10 Sample Calculation of
Fixed Plant Noise
4. Noise Impact Assessment |
This section presents the assessment of the potential noise impacts associated with the
construction and operation phases of the proposed BCP and associated facilities, according to section
Potential noise impacts associated with the construction and
operational phases of the Project have been assessed. Noise generated from various construction
activities is the primary concern during the construction phase. Road traffic
noise from the proposed connecting roads, fixed plant noise from ventilation
shafts, as well as noise from fixed plant of the BCP are major noise impacts during
the operational phase. Representative Noise
Sensitive Receivers (NSRs) within
4.2
Environmental Legislation,
Standards and Guidelines
Control over the
generation of construction noise in
¡ TM on Environmental Impact Assessment Process (EIAO-TM)
¡ TM on Noise from Construction Work other than Percussive Piling (GW-TM)
¡ TM on Noise from Construction Work in Designated Areas (DA-TM)
4.2.1.1 General Construction Activities during Non-Restricted Hours
Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) are assessed against the noise standards tabulated in Table 4.1 below.
Table 4.1: Noise Standards for Daytime Construction Activities
Noise Sensitive Uses |
0700 to 1900 hours on any day not being a Sunday or
general holiday, Leq (30 min), dB(A) |
All domestic premises including
temporary housing accommodation |
75 |
Hotels and hostel |
|
Educational institutions
including kindergarten, nurseries and all others where unaided voice
communication is required |
70 65 during examination |
Source: EIAO-TM, Annex 5, Table 1B - Noise Standards for Daytime construction Activities
Note: The above noise standards apply to uses,
which rely on opened windows for ventilation
The
above standards shall be viewed as the maximum permissible noise levels
assessed at
The
above standards shall be met as far as possible. All practicable mitigation measures shall be
exhausted and the residual impacts are minimised
4.2.1.2 General Construction Activities during Restricted Hours
Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the Noise Control Ordinance (NCO).
For carrying out of any general construction activities involving the use of any Powered Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit (CNP) is required from the Authority under the NCO. The noise criteria and the assessment procedures for issuing a CNP are specified in Technical Memorandum on Noise from Construction Work Other Than Percussive Piling (GW-TM) under the NCO.
The use of Specified PME (SPME) and/or the carrying out of Prescribed Construction Work (PCW) within a Designated Area (DA) under the NCO during the restricted hours are also prohibited without a CNP. The relevant technical details in Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM) under NCO can be referred.
Designated areas, in which the control of
SPME and PCW shall apply, are established through the Noise Control
(Construction Work Designated Areas) Notice made under Section
As such, the application for CNP for any general construction activities involving the use of any PME shall refer to the GW-TM only. However, the Contractor has the responsibility to check the latest status and coverage of the Designated Areas at time of construction of the Project.
Regardless of any description or assessment made in this section, in assessing a filed application for a CNP the Authority will be guided by the relevant Technical Memoranda. The Authority will consider all the factors affecting their decision taking contemporary situations/ conditions into account. Nothing in this Report shall pre-empt the Authority in making their decisions, and there is no guarantee that a CNP will be issued. If a CNP is to be issued, the Authority may include any conditions they consider appropriate and such conditions are to be followed while the works covered by the CNP are being carried out. Failing to do so may lead to cancellation of the permit and prosecution action under the NCO.
According to the construction programme, the proposed construction works would be carried out during non-restricted hours. In case of any construction activities during restricted hours, it is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs. The Contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.
4.2.1.3 Ground-borne Noise
Noise arising from general construction works during normal working hours is governed by the EIAO-TM under the EIAO as shown in Table 4.1. The Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM) under the NCO stipulates that noise transmitted primarily through the structural elements of building, or buildings, shall be 10 dB(A) less than the relevant Acceptable Noise Level (ANLs).
Based on the same principle for the ground-borne noise criteria (i.e. ANL-10 dB(A) under the IND-TM), the ground-borne construction noise levels inside domestic premises and schools shall be limited to 65 dB(A) and 60 dB(A) respectively when compared to the EIAO-TM.
For construction works conducted on general holidays, Sundays and weekdays during evening (1900-2300 hrs) and night time (2300-0700 hrs) the following day, the ground-borne construction noise level shall be limited to 10 dB(A) below the respective ANLs for the Area Sensitivity Rating appropriate to those NSRs affected by the Project. A summary of these criteria is given in Table 4.2.
Table 4.2: Ground-borne Noise Criteria (Leq 30min, dB(A))
NSR type |
Ground-borne Noise Criteria (1), dB(A) |
||
Daytime (0700-1900) except general holidays and Sunday |
Daytime (0700-1900) during general holidays and Sundays and all days during Evening (1900-2300 hrs) |
Night-time (2300 – 0700 hrs) |
|
All domestic premises including temporary housing accommodation |
65 |
50/55/60(2,3) |
35/40/45(2,3) |
Hotels and hostel |
|||
Educational institutions including kindergarten, nurseries and all
others where unaided voice communication is required |
60 55 (for
during examination) |
N/A(4) |
N/A(4) |
Notes: (1) Noise descriptor for daytime noise
except general holidays and Sunday and other periods are Leq (30min) and Leq
(5min) respectively. Measurement shall
be carried out at an internal location representative of normal occupancy of
the building. For residential building, measurement shall be conducted in the
bedroom of the apartment. (2) Based on the Basic Noise Level for NSRs
with Area Sensitivity Ratings of A, B, and C detailed in the Technical
Memorandum on Noise From Construction Work Other Than Percussive Piling. (3) Construction Noise Permit is required
for works during this period. (4) No sensitive use in Education
institutions during evening and night-time period is assumed except specified. |
There
are no statutory procedures and criteria under the NCO and EIAO for assessing
the airborne noise impacts of blasting, hence the airborne noise impact
assessment generated by this activity is beyond the scope of the EIA. However, it
is expected that the impact due to blasting shall be minimal as the blasting
location is deep underground (about
4.2.2 Operation Phase
4.2.2.1 Road Traffic Noise
The Technical Memorandum (TM) published under Section 16(5) of the Environmental Impact Assessment Ordinance (EIAO) gazetted in 1997, is the fundamental legislation of noise criteria for evaluating noise impact of designated projects. The summary of noise criteria is given in Table 4.3.
Table 4.3: Relevant Noise Standards for Planning Purposes
Uses |
L10 (1hour),
dB(A) |
|
All domestic premises including
temporary housing accommodation |
70 |
|
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
65 |
|
Notes: (i) The above standards apply to uses which rely on opened windows for ventilation
(ii) The above standards should be viewed
as the maximum permissible noise levels assessed at
For the fixed plant noise assessment, the ANLs for the NSRs are determined based on the Area Sensitivity Rating (ASR).
Fixed plant noise is controlled under the
NCO and shall comply with the ANLs laid down in the Table 2 of the IND-TM. For
a given
Table 4.4: Acceptable Noise Level for Fixed Plant Noise
Time Period |
Area Sensitivity Rating |
||
A |
B |
C |
|
Day (0700 to 1900 hours) |
60 |
65 |
70 |
Evening (1900 to 2300 hours) |
|||
Night (2300 to 0700 hours) |
50 |
55 |
60 |
4.2.2.3 Area Sensitivity Rating (ASR)
ASR is defined in the IND-TM. The
Table 4.5: Area Sensitivity Rating
Type of Area Containing NSR |
Degree to which NSR is affected by IF |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
(i) Rural area, including country parks or
village type developments |
A |
B |
B |
(ii) Low density residential area
consisting of low-rise or isolated high-rise developments |
A |
B |
C |
(iii) Urban area |
B |
C |
C |
(iv) Area other than those above |
B |
B |
C |
4.3 Assessment Area, Noise Sensitive Receivers and Background Noise Climate
4.3.1.1 Assessment Area
The Assessment Area is defined as within
4.3.1.2 Noise Sensitive Receivers (NSRs)
Noise Sensitive Receivers (NSRs) have been identified in accordance with Annex 13 of the EIAO-TM. The NSRs have included existing, planned/ committed noise sensitive developments and relevant uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department. The Outline Zoning Plans within the assessment area are shown in Figure 4.1.1.
There are numerous village houses situated along the proposed BCP and the connecting road which are identified as NSRs. For the purpose of noise assessment, the first layer of houses of each village located close to the site boundary have been selected as assessment points/ identified representative NSRs within the Study Area for prediction of noise impact levels.
According to the Outline Zoning Plans (S/NE-TKL/13 – Ping Che & Ta Kwu Ling, S/NE-WKS/10 – Wo Keng Shan, S/NE-MUP/11 – Man Uk Pin, S/NE-KLH/11 – Kau Lung Hang) located within the works area, there are Village Type Development zoning (“V” zone) near Nga Yiu Ha, Ping Yeung, Wo Keng Shan, Tai Tong Wu, Loi Tung and Kau Lung Hang. Construction of New Territories Exempted House is permitted in this zoning. Existing NSRs in those “V” zone located close to the site boundary have been identified and selected as representative NSRs. It is identified that the first layer of existing NSRs does not cover the worst affected location of the “V” zone at Wo Keng Shan. Hence an assessment point i.e. WKS8 has been selected to represent a planned NSR in the area.
It is noted that some of the existing NSRs along the proposed road alignment are located in the Agriculture and Green Belt zonings. Construction of new New Territories Exempted House outside the 'V' Zones would require planning permission from the Town Planning Board under Section 16 of the Town Planning Ordinance. At the time of preparation of this Report, no approved application for such planned development was identified along the site boundary of the Project.
According to the North East New Territories New Development Areas (NENT NDAs) Planning and Engineering Study – Investigation (2009), part of the Ping Che/ Ta Kwu Ling NDA is located within the Study Area. However, the study is still in progress and land uses within the NDA has not been finalised. As first layer of NSRs have been selected as assessment points, no additional assessment point has been selected for the NDA.
According to the planned programme (see Appendix
2.2), the Chuk Yuen Village Resite will be completed in early 2012 for
population intake by early 2013, and construction of this Project will commence
in around mid 2013. Therefore, the existing
Based on the Recommended Development Plan in the Final Report
(July 2010) of Planning Department’s Land Use Planning for the Closed Area –
Feasibility Study (see Figures 4.1.2 and 4.1.3), areas of Tsung Yuen Ha, Chuk Yuen and Kan
Tau Wai fall within the Study Area of this noise impact assessment are proposed
to be zoned as “V” zone. As the existing
NSR TYH in Tsung Yuen Ha and NSR CY
Descriptions of selected representative NSRs are tabulated in Table 4.6. The representative NSRs are shown in the Figures 4.2 to 4.12. Photos of existing noise sensitive receivers are shown in Figures 4.13 to 4.17.
4.3.1.3 Background Noise Climate
Noise surveys were carried out from November 2009 to April 2010 to investigate the background noise condition of the surrounding environment and the Project Area. Figures 4.2 to 4.12 show the baseline noise measurement locations.
Five noise measurements were carried out in the Project Area. The noise measurements were undertaken using Type 1 sound level meters, namely Rion NL-18 and Rion NL-31. During each measurement, the sound level meter was checked using an acoustic calibrator generating a sound pressure level of 94dB(A) at 1kHz immediately before and after the noise measurement. The measurements were accepted as valid only if the calibration levels before and after the noise measurement were agreed to within 1.0dB(A). Moreover, the sound level meters and acoustic calibrators are calibrated in accredited laboratories yearly to ensure reliable performance. The measurement results are shown in Table 4.7.
Table 4.7 Measured Noise Levels
Location ID |
Location Description |
Time Period |
Start Time |
Measured Noise Level in Leq(30min), dB(A) |
Corrected Facade Noise Level, dB(A) |
A |
Tsung
Yuen Ha |
Daytime (0700 – 1900) |
07:15 |
49 |
52 |
|
|
Evening Time (1900 – 2300) |
19:00 |
46 |
49 |
|
|
Night-time (2300 – 0700) |
06:15 |
42 |
45 |
B |
|
Daytime (0700 – 1900) |
15:30 |
53 |
56 |
|
|
Evening Time (1900 – 2300) |
19:20 |
49 |
52 |
|
|
Night-time (2300 – 0700) |
05:45 |
43 |
46 |
C |
Wo Keng
Shan |
Daytime (0700 – 1900) |
09:15 |
51 |
54 |
|
|
Evening Time (1900 – 2300) |
20:15 |
44 |
47 |
|
|
Night-time (2300 – 0700) |
23:15 |
42 |
45 |
D |
Loi
Tung |
Daytime (0700 – 1900) |
16:10 |
46 |
49 |
|
|
Evening Time (1900 – 2300) |
19:20 |
41 |
44 |
|
|
Night-time (2300 – 0700) |
05:25 |
40 |
43 |
E |
|
Daytime (0700 – 1900) |
10:40 |
43 |
46 |
|
|
Evening Time (1900 – 2300) |
20:15 |
33 |
36 |
|
|
Night-time
(2300 – 0700) |
23:30 |
33 |
36 |
4.4.1 Construction Airborne Noise
4.4.1.1 Identification of Emission Source
The major construction activity involved in the Project is
the site formation for the construction of a BCP building, construction of a
dual two-lane trunk road with connecting the BCP with
4.4.1.2 Assessment Methodology
Assessment approach to the noise impact is in line with the Guidance Note titled “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2004).
In addition, the assessment of construction noise impact is
based on standard acoustic principles, and the guidelines given in GW-TM issued
under the NCO where appropriate. Where
no sound power level (SWL) can be found in the relevant TM, reference has been
made to BS 5228 Part I or noise emission levels measured for PME used in
previous projects in
i. Assume a typical construction schedule/ programme;
ii. Assume a typical project-specific equipment inventory for each work stage together with the number;
iii. Obtain from GW-TM, the Sound Power Level (SWL) for each PME assumed in the equipment inventory;
iv. Select representative NSRs for the construction noise impact assessment;
v. Calculate the unmitigated Predicted Noise Level (PNL) and correct it for facade reflection to obtain the Corrected Noise Level (CNL) at any NSRs;
vi. If necessary, re-select typical project-specific silenced equipment and calculate the mitigated noise impact;
vii. Compare the mitigated CNL with the noise standards to determine acceptability and the need for further mitigation.
The calculation methodology is estimated with the following standard formula (1):
SPL = SWL – DC + FC (1)
where
Sound Pressure Levels, SPL in dB(A)
Sound Power Levels, SWL in dB(A)
Distance Attenuation, DC in dB(A) = 20∙log(D)+8 (where
D is the distance between NSRs and noise source in meters)
Façade Correction, FC in dB(A) = 3dB(A)
4.4.1.3 Evaluation of Impacts
The type and quantity of Powered Mechanical Equipment (PME) likely to be used for the construction of the BCP and associated road works are described below and their Sound Power Levels (SWLs) are shown in Appendix 4.1.
Table 4.8 to Table 4.13 and Appendix 4.2 indicates that the noise impact of unmitigated construction activities of proposed road works would cause exceedance of the relevant daytime construction noise criteria. Mitigation measures are therefore required for these NSRs in order to alleviate the noise impacts generated during the construction phase.
Table 4.8: Unmitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)
Land Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
|
TYH |
Residential |
69-80 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.9 Unmitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A)
NSR ID |
Land Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
V1 |
Residential |
56-87 |
75 |
Yes |
Yes |
V2 |
Residential |
55-88 |
75 |
Yes |
Yes |
CY3 |
Residential |
55-76 |
75 |
Yes |
Yes |
KL1 |
Residential |
50-79 |
75 |
Yes |
Yes |
TKL1 |
Residential |
49-85 |
75 |
Yes |
Yes |
TKL2 |
Residential |
48-85 |
75 |
Yes |
Yes |
KTW1 |
Residential |
56-80 |
75 |
Yes |
Yes |
KTW2 |
Residential |
53-83 |
75 |
Yes |
Yes |
KTW3 |
Residential |
57-83 |
75 |
Yes |
Yes |
KTW4 |
Residential |
55-89 |
75 |
Yes |
Yes |
KTW5 |
Residential |
58-83 |
75 |
Yes |
Yes |
NYH1 |
Residential |
64-84 |
75 |
Yes |
Yes |
NYH2 |
Residential |
65-79 |
75 |
Yes |
Yes |
PY2 |
Residential |
67-91 |
75 |
Yes |
Yes |
PY3 |
Residential |
59-82 |
75 |
Yes |
Yes |
PY4 |
Residential |
59-89 |
75 |
Yes |
Yes |
PY5 |
Residential |
58-81 |
75 |
Yes |
Yes |
PY6 |
Residential |
57-82 |
75 |
Yes |
Yes |
PY7 |
Residential |
57-76 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.10 Unmitigated Construction Airborne Noise Impact at Wo Keng Shan, Leq (30mins) dB(A)
NSR ID |
Land Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
WKS1 |
Residential |
66-81 |
75 |
Yes |
Yes |
WKS2 |
Residential |
64-77 |
75 |
Yes |
Yes |
WKS3 |
Residential |
62-72 |
75 |
No |
No |
WKS4 |
Residential |
68-84 |
75 |
Yes |
Yes |
WKS5 |
Residential |
64-89 |
75 |
Yes |
Yes |
WKS6 |
Residential |
60-89 |
75 |
Yes |
Yes |
WKS7 |
Residential |
60-85 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.11 Unmitigated
Construction Airborne Noise Impact near
NSR ID |
Land Use |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
ST1 |
Residential |
69-82 |
75 |
Yes |
Yes |
ST2 |
Residential |
68-85 |
75 |
Yes |
Yes |
ST3 |
Residential |
61-79 |
75 |
Yes |
Yes |
ST5 |
Residential |
64-84 |
75 |
Yes |
Yes |
ST6 |
Residential |
59-80 |
75 |
Yes |
Yes |
LT1 |
Residential |
58-85 |
75 |
Yes |
Yes |
LT2 |
Residential |
55-79 |
75 |
Yes |
Yes |
LT3 |
Residential |
59-83 |
75 |
Yes |
Yes |
LT4 |
Residential |
76-78 |
75 |
Yes |
Yes |
TTW1 |
Residential |
60-74 |
75 |
No |
No |
TTW2 |
Residential |
63-85 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.12 Unmitigated Construction Airborne Noise Impact near Po Kat Tsai, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
PKT1 |
Residential |
63-72 |
75 |
No |
No |
PKT2 |
Residential |
78-86 |
75 |
Yes |
Yes |
PKT3 |
Residential |
77-84 |
75 |
Yes |
Yes |
Table 4.13 Unmitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Mitigation measure required |
TH1 |
Residential |
56-87 |
75 |
Yes |
Yes |
TH2 |
Residential |
57-81 |
75 |
Yes |
Yes |
TH4 |
Residential |
54-84 |
75 |
Yes |
Yes |
TH5 |
Residential |
55-79 |
75 |
Yes |
Yes |
TH6 |
Residential |
53-73 |
75 |
No |
No |
WKS1 |
Residential |
55-72 |
75 |
No |
No |
KT1 |
Residential |
59-82 |
75 |
Yes |
Yes |
KT2 |
Residential |
64-86 |
75 |
Yes |
Yes |
KT3 |
Residential |
62-91 |
75 |
Yes |
Yes |
NWP1 |
Residential |
62-91 |
75 |
Yes |
Yes |
KLHSW |
Residential |
61-82 |
75 |
Yes |
Yes |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
¡ good site practice to limit noise emissions at source;
¡ selection of quieter plant;
¡ use of movable noise barrier;
¡ use of noise enclosure/ acoustic shed; and
¡ use of noise insulating fabric.
While it is recognised that the Contractor may develop a different package of mitigation measures to meet the required noise standards, the following suite of practical and implementable measures demonstrate an approach that would be feasible to reduce noise to acceptable levels.
Good Site Practice
Good site practice and noise management can significantly reduce the impact of construction site activities on nearby NSRs. The following package of measures should be followed during each phase of construction:
¡ only well-maintained plant to be operated on-site and plant should be serviced regularly during the construction works;
¡ machines and plant that may be in intermittent use to be shut down between work periods or should be throttled down to a minimum;
¡ plant known to emit noise strongly in one direction, should, where possible, be orientated to direct noise away from the NSRs;
¡ mobile plant should be sited as far away from NSRs as possible; and
¡ material stockpiles and other structures to be effectively utilised, where practicable, to screen noise from on-site construction activities.
Selecting Quieter Plant
The Contractor may be able to obtain particular models of plant that are quieter than the standards given in the GW-TM. This is one of the most effective measures and is increasingly practicable because of the availability of quiet equipment.
Quiet plant is defined as QPME whose actual SWL is less than
the value specified in GW-TM for the same piece of equipment. Examples of SWLs for specific silenced PME
taken from a British Standard, namely Noise Control on Construction and Open
Sites, BS 5228: Part 1: 2009 and are presented in Table
4.14. It
should be noted that various types of silenced equipment can be found in
Table 4.14 Quieter PME Recommended for Adoption during Construction Phase
PME |
Power rating/size, weight |
Reference |
SWL, dB(A) |
Handheld breaker |
|
BS D2-10 |
110 |
Hydraulic breaker, Excavator mounted |
52kW |
BS D8-12 |
106 |
Concrete lorry mixer |
|
BS D6-35 |
100 |
Concrete pump |
100kW |
BS D6-36 |
106 |
Mobile crane |
62kW |
BS D7-114 |
101 |
Vibratory Poker, handheld |
0.75kW each poker |
BS D6-40 |
102 |
Bulldozer |
239kW |
BS D3-27 |
109 |
Excavator |
45kW |
BS D3-35 |
106 |
Dump truck |
50t |
BS D9-39 |
103 |
Vibratory roller |
9kW |
BS D3-115 |
102 |
Asphalt paver |
90kW |
BS D8-24 |
101 |
Road
Roller |
51kW |
BS D8-30 |
101 |
Lorry |
310kW |
BS D3-59 |
105 |
Whilst quieter PME are listed, the Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM.
Use of Movable Noise Barriers
Movable noise barriers can be very effective in screening noise from particular items of plant when constructing the Project. Noise barriers located along the active works area close to the noise generating component of a PME could produce at least 10 dB(A) screening for stationary plant and 5 dB(A) for mobile plant provided the direct line of sight between the PME and the NSRs is blocked. A schematic configuration of a single movable noise barrier for PME is shown in Figure 4.18.
Use of Noise Enclosure/ Acoustic Shed
The use of noise enclosure or acoustic shed is to cover stationary PME such as air compressor and concrete pump. With the adoption of the noise enclosure, the PME could be completely screened, and noise reduction of 15 dB(A) can be achieved according to the EIAO Guidance Note No.9/2004. A schematic configuration of full noise enclosure for PME is shown in Figure 4.19.
Use of Noise Insulating Fabric
Noise insulating fabric can also be adopted for certain PME (e.g. drill rig, pilling auger etc). The Fabric should be lapped such that there are no openings or gaps on the joints. According to the approved Tsim Sha Tsui Station Northern Subway EIA Report (AEIAR-127/2008), a noise reduction of 10 dB(A) can be achieved for the PME lapped with the noise insulating fabric.
The noise screening benefit for each item of plant considered in this assessment is listed in Table 4.15.
Table 4.15 Noise Mitigation Measures for Certain PME during Construction Phase
PME |
Mitigation Measures Proposed |
Noise Reduction, dB(A) |
Concrete pump |
Noise enclosure |
15 |
Air compressor |
Noise enclosure |
15 |
Grout pump |
Noise enclosure |
15 |
Handheld breaker |
Movable noise barrier |
10 |
Piling,
large diameter bored, grab and chisel |
Noise insulating fabric |
10 |
Piling,
large diameter bored, reverse circulation drill |
Noise insulating fabric |
10 |
Piling,
large diameter bored, oscillator |
Noise insulating fabric |
10 |
Piling, diaphragm wall, bentonite
filtering plant |
Noise insulating fabric |
10 |
Drill rig, rotary type |
Noise insulating fabric |
10 |
Air compressor |
Movable noise barrier |
10 |
Water pump |
Movable noise barrier |
10 |
Generator |
Movable noise barrier |
10 |
Poker, Vibratory, hand-held |
Movable noise barrier |
10 |
Excavator |
Movable noise barrier |
5 |
Mobile
crane |
Movable noise barrier |
5 |
Prestress Jack |
Movable noise barrier |
5 |
Lorry with crane/grab |
Movable noise barrier |
5 |
Lorry |
Movable noise barrier |
5 |
Compactor, vibratory |
Movable noise barrier |
5 |
Bulldozer |
Movable noise barrier |
5 |
Asphalt paver |
Movable noise barrier |
5 |
Road Roller |
Movable noise barrier |
5 |
Dump Truck |
Movable noise barrier |
5 |
Concrete pump, lorry mounted |
Movable noise barrier |
5 |
These noise barriers should be free of gaps and made of
materials having a surface mass density in excess of
The effect of the use of quiet plant and using movable barriers has been investigated for the practicable construction activities and the results are presented in Table 4.16 to Table 4.21 and the detailed calculation was shown in Appendix 4.4.
Table 4.16: Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
TYH |
Residential |
64-70 |
75 |
No |
No |
Table 4.17 Mitigated Construction Airborne Noise Impact from Lin Ma Hang to Wo Keng Shan, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
V1 |
Residential |
51-72 |
75 |
No |
No |
V2 |
Residential |
51-74 |
75 |
No |
No |
CY3 |
Residential |
50-67 |
75 |
No |
No |
KL1 |
Residential |
45-65 |
75 |
No |
No |
TKL1 |
Residential |
44-71 |
75 |
No |
No |
TKL2 |
Residential |
44-71 |
75 |
No |
No |
KTW1 |
Residential |
43-67 |
75 |
No |
No |
KTW2 |
Residential |
40-69 |
75 |
No |
No |
KTW3 |
Residential |
44-69 |
75 |
No |
No |
KTW4 |
Residential |
42-72 |
75 |
No |
No |
KTW5 |
Residential |
45-69 |
75 |
No |
No |
NYH1 |
Residential |
53-70 |
75 |
No |
No |
NYH2 |
Residential |
56-66 |
75 |
No |
No |
PY2 |
Residential |
56-75 |
75 |
No |
No |
PY3 |
Residential |
47-68 |
75 |
No |
No |
PY4 |
Residential |
48-72 |
75 |
No |
No |
PY5 |
Residential |
47-68 |
75 |
No |
No |
PY6 |
Residential |
46-69 |
75 |
No |
No |
PY7 |
Residential |
45-63 |
75 |
No |
No |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.18 Mitigated Construction Airborne Noise Impact at Wo Keng Shan, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
WKS1 |
Residential |
62-70 |
75 |
No |
No |
WKS2 |
Residential |
60-69 |
75 |
No |
No |
WKS3 |
Residential |
57-64 |
75 |
No |
No |
WKS4 |
Residential |
55-71 |
75 |
No |
No |
WKS5 |
Residential |
60-72 |
75 |
No |
No |
WKS6 |
Residential |
57-75 |
75 |
No |
No |
WKS7 |
Residential |
57-72 |
75 |
No |
No |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.19 Mitigated
Construction Airborne Noise Impact near
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
ST1 |
Residential |
59-69 |
75 |
No |
No |
ST2 |
Residential |
58-72 |
75 |
No |
No |
ST3 |
Residential |
51-67 |
75 |
No |
No |
ST5 |
Residential |
52-72 |
75 |
No |
No |
ST6 |
Residential |
49-67 |
75 |
No |
No |
LT1 |
Residential |
48-71 |
75 |
No |
No |
LT2 |
Residential |
45-69 |
75 |
No |
No |
LT3 |
Residential |
50-71 |
75 |
No |
No |
LT4 |
Residential |
64-70 |
75 |
No |
No |
TTW1 |
Residential |
50-61 |
75 |
No |
No |
TTW2 |
Residential |
53-74 |
75 |
No |
No |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
Table 4.20 Mitigated Construction
Airborne Noise Impact near
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
PKT1 |
Residential |
54-59 |
75 |
No |
No |
PKT2 |
Residential |
68-73 |
75 |
No |
No |
PKT3 |
Residential |
67-71 |
75 |
No |
No |
Table 4.21 Mitigated Construction Airborne Noise Impact near Fanling, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Exceedance of noise criteria dB(A) |
Residual Impact |
TH1 |
Residential |
43-73 |
75 |
No |
No |
TH2 |
Residential |
44-67 |
75 |
No |
No |
TH4 |
Residential |
42-70 |
75 |
No |
No |
TH5 |
Residential |
42-65 |
75 |
No |
No |
TH6 |
Residential |
41-60 |
75 |
No |
No |
WKS1 |
Residential |
42-58 |
75 |
No |
No |
KT1 |
Residential |
46-67 |
75 |
No |
No |
KT2 |
Residential |
52-71 |
75 |
No |
No |
KT3 |
Residential |
50-75 |
75 |
No |
No |
NWP1 |
Residential |
50-75 |
75 |
No |
No |
KLHSW |
Residential |
49-68 |
75 |
No |
No |
Note: Bold figures denotes the predicted noise level is higher than the relevant daytime construction noise criteria
With the incorporation of quiet plant and the use of movable noise barriers (to reduce noise level at source), the results indicated that the mitigated noise impact associated with the construction of the Project would comply with the daytime construction noise criterion at all the NSRs. Residual construction noise impact is not anticipated.
The mitigation measures recommended above can be altered, the Contractor may be allowed to use acoustic blankets on PMEs or re-schedule noisy works, while it is the responsibility of the Contractor to comply with the construction noise criteria which should be stated in the contractual agreement. It is further recommended that the Contractor should follow the “Recommended Pollution Control Clauses for Construction Contracts” to minimise the construction noise impact.
4.4.1.5 Cumulative Construction Airborne Noise Impact
According to the tentative construction
programme, it is likely that there will be an overlap of this Project with some
other potentially concurrent projects. These
projects are described in Section 2.10.
For
projects “Regulation of Shenzhen River Stage IV” and “Construction of a
Secondary Boundary Fence and new sections of Primary Boundary Fence and
Table 4.22: Cumulative Mitigated Construction Airborne Noise Impact near BCP, Leq (30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Max. Overall Noise Level, dB(A) |
Noise Criteria, dB(A) |
Exceedance of noise criteria, dB(A) |
Residual
Impact |
|
This Project |
*Concurrent Projects |
||||||
TYH |
Residential |
64-70 |
54 - 71 |
74 |
75 |
No |
No |
Note: (*) reference to the predicted results of the closest NSR in the EIA Report of the Regulation of Shenzhen River Stage IV with appropriate distance correction
Table 4.23 Cumulative
Mitigated Construction Airborne Noise Impact at Lin Ma Hang to Frontier Closed
Area Boundary, Leq
(30mins) dB(A)
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Max. Overall Noise Level, dB(A) |
Noise Criteria, dB(A) |
Exceedance of noise criteria, dB(A) |
Residual Impact? |
|
This Project |
*Concurrent Projects |
||||||
KL1 |
Residential |
45-65 |
53 - 63 |
67 |
75 |
No |
No |
TKL1 |
Residential |
44-71 |
57 - 67 |
72 |
75 |
No |
No |
TKL2 |
Residential |
44-71 |
53 - 63 |
72 |
75 |
No |
No |
Note: (*) reference to the predicted results of the closest NSR in the EIA Report of the Regulation of Shenzhen River Stage IV with appropriate distance correction
For the project “Resite of Chuk Yuen Village”,
as the construction of the BCP Project will be commenced after the resite of
the
For project “North East New
Territories (NENT) Landfill Extension”, the project boundary and works areas
are out of the
According
to the project proponent, the implementation programme of Stage 2 of the
As mentioned in Section 2.10.9, the project “Provision of Cremators at Wo Hop Shek Crematorium” is located outside 500m from the site boundary of the BCP Project, the project will not be considered as a concurrent project.
For
project “Cycle Tracks Connecting North West New Territories with North East New
Territories – Sheung Shui to Ma On Shan section”, the section of the Cycle
Track which intersects the LT/HYW BCP Project’ study area (Fanling section) is
due to be completed by mid 2012. No cumulative impacts are anticipated and hence the
project will not be considered as a concurrent project.
For
the project “Drainage Improvements in
4.4.1.6 Evaluation of Residual Impact
With the implementation of the above-mentioned mitigation measures, the construction noise levels at all the representative NSRs are predicted to comply with the noise standards stipulated in the EIAO-TM. No residual construction noise impact is anticipated. Nevertheless, the Contractor is recommended to implement the good site practice as mentioned in Section 4.4.1.4 and carry out the environmental monitoring and audit (EM&A) to be discussed in Section 4.6.
4.4.2 Construction Ground-borne Noise
4.4.2.1 Identification of Emission Source
Potential ground-borne noise impact during the construction phase could be caused by drill and blast activities and mechanical excavation for tunnelling works, and the use of PMEs such as the hydraulic breakers, hand-held breakers and drill rigs for other construction activities.
4.4.2.2 Assessment Methodology
Drill & Blast and Mechanical Excavation methods would be used to excavate rock along the alignment. The interaction between the operation of equipment and the rock will induce ground-borne noise. The prediction methodology for assessing the ground-borne noise impact from construction equipment is detailed as follows:
The method used to predict construction ground-borne noise from the use of PME construction equipment is shown below.
LA = Lv,rms
+ C dist + C damping
+ BCF + BVR + CTN + C cum |
|
LA |
A-weighted
Ground-borne noise level at NSR, ref: 20 µ-Pascal |
C dist |
Distance attenuation |
C damping |
Soil damping loss
across the geological media |
Lv,rms |
Vibration velocity
(in RMS) of a PME at a reference distance |
BCF |
Vibration coupling
loss factor between the soil and the foundation, relative level |
BVR |
Building vibration
reduction or amplification within a structure from the foundation to the
occupied areas, relative level |
CTN |
Conversion from floor
and wall vibration to noise, 10 |
C cum |
Cumulative noise
impact from concurrent projects |
The vibratory velocities for typical
construction equipment with reference to the approved Kowloon Southern Link EIA
(Register No.: AEIAR-083/2005) are listed in Table 4.24 to Table
4.25.
Table 4.24: Reference Vibration Level based on Measurements
Construction Equipments |
Construction Site |
Vibration
(RMS) at Reference Distance of |
Drilling Rig |
|
|
Hydraulic Breaker |
TST site |
|
Handheld Breaker |
New World Centre site |
|
Source: Appendix 7-1 of |
Table 4.25: Source Vibration Velocity of Octave Band Frequency for Hydraulic Breaker
Octave Band Frequency
(Hz) |
16 |
31.5 |
63 |
125 |
250 |
500 |
Source Vibration
Velocity, mm/s |
0.0589 |
0.0682 |
0.0620 |
0.0503 |
0.0623 |
0.1209 |
Source: Appendix
7-1 of |
Soil Damping Loss
Vibration wave propagation in ground will decay with distance due to damping loss within the soil. The reduction in vibration amplitude can be estimated based on the Transportation Noise Reference Book[1].
|
The rate of decay will depend on vibration frequency, the soil loss factor (η), the wave speed c of the soil and the distance R between sources to the NSR. The wave propagation properties of typical soil are shown in the Table 4.26.
Table 4.26: Wave Propagation Properties of Soil
Ground Type |
Longitudinal Wave Speed c, ms-1 |
Loss Factor, η |
Density, g/cm3 |
Soil |
1500 |
0.5 |
1.7 |
Rock |
3500 |
0.01 |
2.65 |
For this noise impact assessment, no damping attenuation (i.e. 0 dB(A)) will be applied to propagation in rock.
Interaction between the building foundation and the soil will cause some reduction in the vibration level. The correction factors shown in Table 4.27 are based on Saurenman (1982). For conservative assessment, the lower limit adjustment factors (highlighted in Bold) have been used in the study.
Table 4.27: Adjustment Factor for Building Coupling Loss (BCF)
Building Type |
Limit |
Building Coupling Loss (dB) |
|||||
|
|
16 |
31.5 |
63 |
125 |
250 |
500 |
Large |
Lower |
-6 |
-7 |
-11 |
-13 |
-14 |
-12 |
Upper |
-8 |
-10 |
-13 |
-15 |
-16 |
-14 |
|
Large |
Lower |
-12 |
-14 |
-14 |
-13 |
-11 |
-10 |
Upper |
-14 |
-16 |
-16 |
-15 |
-13 |
-12 |
|
1 to 2 Storey Residential |
Lower |
-4 |
-5 |
-5 |
-4 |
-3 |
-1 |
Upper |
-6 |
-7 |
-7 |
-6 |
-5 |
-3 |
|
Building Foundation on Rock Layer |
|
0 |
0 |
0 |
0 |
0 |
0 |
Building Vibration Response (BVR)
Building Vibration Response (BVR) consists of two factors, namely Building Structure Attenuation (BSA) and Building Structure Resonance (BSR). Vibration generally reduces in level as it propagates through a building. On the other hand, amplification occurs due to building element resonance. The following correction factors (Table 4.28) based on Saurenman (1982)[2] are proposed for the Project.
Table 4.28: Adjustment Factor for Building Structure Attenuation (BSA)
Floor level above Grade |
Floor Attenuation Factor (dB) |
|||||
16 |
31.5 |
63 |
125 |
250 |
500 |
|
1 |
2 |
2 |
3 |
3 |
3 |
4 |
2 |
2 |
2 |
2 |
3 |
3 |
4 |
3 |
2 |
2 |
2 |
2 |
3 |
3 |
4 to 5 |
1 |
1 |
2 |
2 |
3 |
3 |
6 to 7 |
1 |
1 |
1 |
2 |
3 |
3 |
8 to 9 |
1 |
1 |
1 |
1 |
2 |
3 |
10 and above |
1 |
1 |
1 |
1 |
2 |
3 |
Since ground-borne vibration level will be the highest on the lower level of a building, a conservative building structure attenuation factor of 2dB per octave band (Table 4.29) is proposed for the Project.
Table 4.29: Building Structure Attenuation (BSA)
Octave Band Centre Frequency (Hz) |
16 |
31.5 |
63 |
125 |
250 |
500 |
Floor
Attenuation Factor (dB) |
2 |
2 |
2 |
2 |
2 |
2 |
Ground vibration level will increase within the building due to building element resonance. The amount of amplification will depend on building construction method. For typical concrete based building construction, a 6 dB increase per octave band (Table 4.30) has been adopted for the Project in accordance with the FTA Handbook[3] recommendation.
Table 4.30: Building Structure Resonance (BSR)
Octave Band Centre Frequency (Hz) |
16 |
31.5 |
63 |
125 |
250 |
500 |
Floor and Wall
Resonance (dB) |
6 |
6 |
6 |
6 |
6 |
6 |
Conversion from Vibration to Noise (CTN)
The level of radiated noise inside a room will depend on the average vibration of the room surfaces, the radiation efficiency of the surfaces and the amount of absorption inside the room.
Based on the conservation of power principle, the reverberant sound field inside the room can be approximated by the following equation:
Reverberant Sound Pressure Level LA (dBA) = Lv (VdB ref 1 m in/s) + CTN Equation 4.4‑1 CTN = Krad + A-weighting Correction Equation 4.4‑2 where |
|
Krad |
Adjustment to account for conversion from vibration to
sound pressure level including accounting for the amount of acoustical
absorption inside the room |
For typical residential bedroom with nominal acoustical absorption treatment, the following factors (Table 4.31) are proposed for the Project:
Table 4.31: Room Correction Factors
Octave Band Centre Frequency (Hz) |
16 |
31.5 |
63 |
125 |
250 |
500 |
Krad (dB) |
0 |
0 |
0 |
0 |
0 |
0 |
A weighting |
-56.7 |
-39.4 |
-26.2 |
-16.1 |
-8.6 |
-3.2 |
CTN (for vibration) |
-56.7 |
-39.4 |
-26.2 |
-16.1 |
-8.6 |
-3.2 |
For Lv vibration level
reference to 1 m
in/s |
Multiple Vibration Sources C multi
The ground-borne noise levels from the construction plant will be summed logarithmically in accordance with standard acoustic principles to obtain the total ground-borne noise level.
Cumulative Ground-borne Noise Impact C cum
Potential concurrent projects leading to cumulative impacts would be considered in the ground-borne noise prediction.
4.4.2.3 Evaluation of Construction Ground-borne Noise Impacts
Detailed assessments have been conducted for three construction equipment (hydraulic breaker, hand-held breaker and drilling rig), for tunnelling works including drill & blast and mechanical excavation along the tunnel, the results are summarised in Table 4.32. The detailed assessment results were shown in Appendix 4.5.
Table 4.32 Unmitigated Construction Ground-borne Noise
NSR ID |
Usage |
Predicted Noise Level dB(A) |
Noise Criteria dB(A) |
Mitigation measure required |
LPT |
Residential |
34 |
65 |
No |
STS |
Residential |
34 |
65 |
No |
Based on the assessment result as shown in Table 4.32, the predicted ground-borne noise levels from the tunnelling work will not exceed the daytime ground-borne noise criteria and hence no mitigation measures are required.
4.5.1 Road Traffic Noise
4.5.1.1 Identification of Emission Source
During the operational phase, operation of the LT/HYW BCP
connecting road may pose traffic noise impact on the nearby NSRs. The road carriageways involved within the
assessment area, including the proposed BCP connecting road, the modified Lin
Ma Hang Road, existing roads and roads of other committed projects have been
selected for assessment. Appendix 4.6
shows the roads selected for the Road Traffic Noise Impact Assessment (RTNIA). The classification of “
4.5.1.2 Assessment Methodology
Road traffic noise levels at the representative assessment points will be calculated based on the peak hour traffic flow within a 15 years period upon commencement of operation of the Project i.e., the assessment year. Traffic noise will be predicted using the model “roadNoise”, which has been used before in other similar EIA studies. The model has fully incorporated the procedures and methodology documented in “Calculation of Road Traffic Noise (CRTN)” (1988) published by the U.K. Department of Transport.
In accordance with the requirements specified in Section
■
Scenario
(1) includes a comparison of the “with and without Project” situations at the
design year to identify the significance of road traffic noise at the
representative NSRs. Predicted traffic
noise impact would be considered to be significant if the traffic noise levels
in the presence of the Project is greater than that without the Project at the
design year (i.e. 2018) by 1.0 dB(A) or more;
■
Scenario
(2) involves an assessment of the unmitigated road traffic noise levels at the
representative NSRs at the assessment year.
If exceedances of the relevant road traffic noise criteria are
predicted, direct noise mitigation measures listed under Section
■
Scenario
(3) involves an assessment of the effectiveness and adequacy of the recommended
direct noise mitigation measures. It is envisaged that the direct noise
mitigation measures proposed may involve erection of noise barriers and/or
enclosure on the BCP connecting road.
Aesthetic design and greening measures will be considered for the noise
barriers to ensure that visual intrusion is minimised to acceptable
levels. Sections of barriers proposed to
protect existing NSRs will be differentiated clearly from those proposed for
the protection of planned NSRs;
■
Under
Scenario (4), upon exhaust of all practicable direct noise mitigation measures,
in case noise exceedances are still predicted at existing NSRs (e.g. dwellings
and classrooms), the eligibility of the affected NSRs for provision of indirect
technical remedies in form of noise insulation and air-conditioning will be
evaluated based on the three specific criteria set out in Section
If the NSRs are affected by noise from other existing roads, direct mitigation measures are required to reduce the noise from the proposed roads to a level that it
■
is
not higher than the standard; and
■
has
no significant contribution to the overall noise from other existing roads
If the noise criteria will still be exceeded at the existing NSRs after the implementation of direct mitigation measures, provision of acoustic insulation in form of windows and provision of air-conditioning for ventilation should be considered under the ExCo directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the use of New Roads”. Eligibility for indirect technical remedies should be tested against the following three criteria:
■
The
predicted overall noise level, L10(1 hour), from the “New Road”,
together with other traffic noise in the vicinity must be above 70 dB(A) for
domestic premises, 65 dB(A) for educational institutions and 55 dB(A) for home
for the aged.
■
The
predicted overall noise level is at least 1.0 dB(A) more than the prevailing
traffic noise level.
■
The
contribution to the increase in the predicted overall noise level from the “
The road scheme within the Study Area and the surrounding
road network have been set up
to define the road width, surface type, traffic condition and if applicable,
the height and locations of any roadside barriers. Parapet walls with height of 0.8m above road
surface along both sides of the viaduct sections of the proposed link road have
been applied. In accordance with
RD/GN/032, the extent of low-noise surfacing will cover the link roads and slip
roads, but not the local road sections i.e. the roundabouts at
4.5.1.3 Evaluation of impacts
The comparison
between with and without the Project at Year 2018 (AM) due to
operation of the
Table 4.33 Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Existing Receivers)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Difference, dB(A) (2) – (1) |
|
Without Project (1) |
With Project (2) |
|||
TYH |
70 |
52 |
62 |
10.5 - 10.6 |
V1 |
70 |
64 |
69 |
5.5 – 5.8 |
V2 |
70 |
58 |
64 - 65 |
6.7 – 7.4 |
KL1 |
70 |
60 |
63 - 64 |
3.6 – 3.7 |
TKL1 |
70 |
62 |
66 |
3.3 – 3.4 |
TKL2 |
70 |
65 |
69 |
3.9 – 4.0 |
KTW1 |
70 |
52 |
63 - 64 |
10.6 – 11.5 |
KTW2 |
70 |
32 |
59 |
27.2 |
KTW3 |
70 |
46 |
65 - 66 |
18.4 – 20.0 |
KTW4 |
70 |
40 |
58 |
18.0 |
KTW5 |
70 |
46 |
64 - 66 |
18.5 – 19.9 |
NYH1 |
70 |
42 |
65 - 66 |
22.4 – 23.5 |
NYH2 |
70 |
34 |
64 - 65 |
30.3 – 30.8 |
PY1 |
70 |
0 |
69 - 70 |
69.2 – 69.5 |
PY2 |
70 |
37 |
69 |
31.5 – 32.2 |
PY3 |
70 |
37 |
65 - 66 |
28.4 – 28.9 |
PY4 |
70 |
38 |
67 |
29.1 |
PY5 |
70 |
0 |
65 |
65.0 |
PY6 |
70 |
34 |
66 |
31.9 |
PY7 |
70 |
21 - 24 |
64 - 65 |
40.6 – 42.9 |
WKS1 |
70 |
52 |
71 |
18.7 |
WKS2 |
70 |
54 |
66 |
11.7 – 12.1 |
WKS3 |
70 |
52 |
64 |
11.5 – 11.7 |
WKS4 |
70 |
66 |
71 |
4.8 |
WKS5 |
70 |
66 |
68 |
2.1 |
WKS6 |
70 |
62 |
68 |
5.3 |
WKS7 |
70 |
67 |
70 |
2.7 |
Notes: Bold figure denotes the noise
exceedance which is over the relevant EIAO-TM noise criteria.
Table 4.34 Comparison between With and Without Project in Year 2018 from Lin Ma Hang to North Tunnel (Planned Receivers)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Difference, dB(A) (2) – (1) |
|
Without Project (1) |
With Project (2) |
|||
CY3 |
70 |
(*) |
61 - 62 |
(*) |
KTW6 |
70 |
64 |
66 - 67 |
2.1 – 2.2 |
WKS8 |
70 |
50 |
68 |
17.9 – 18.4 |
Notes: (*)CY3 exists in the "with project" scenario only.
Table 4.35 Comparison
between With and Without Project in Year 2018 near Sha Tau
Kok Road Section (Existing Receivers)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Difference, dB(A) (2) – (1) |
|
Without Project (1) |
With Project (2) |
|||
ST1 |
70 |
47-53 |
63-64 |
12.8 – 15.7 |
ST2 |
70 |
57 |
67-68 |
9.7 – 11.2 |
ST3 |
70 |
60 |
68 |
8.1 – 8.2 |
ST5 |
70 |
64 |
72 |
8.6 – 8.7 |
ST6 |
70 |
62 |
71 |
8.1 – 8.3 |
TTW1 |
70 |
67 |
67 |
-0.5 |
TTW2 |
70 |
64 |
68 |
3.6 |
LT1 |
70 |
60 |
74 |
14.3 |
LT2 |
70 |
62 |
70 |
8.3 |
LT3 |
70 |
68 |
73 |
5.1 – 5.2 |
LT4 |
70 |
51 |
70 |
18.9 – 19.0 |
Notes: Bold figure denotes the noise
exceedance which is over the relevant EIAO-TM noise criteria.
Table 4.36 Comparison
between With and Without Project in Year 2018 near
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Difference, dB(A) (2) – (1) |
|
Without Project (1) |
With Project (2) |
|||
TH1 |
70 |
70 |
75 |
4.8 |
TH2 |
70 |
70 |
72 |
2.1 – 2.2 |
TH4 |
70 |
70 |
70.5 |
0.5 - 0.6 |
TH5 |
70 |
73 |
73 |
-0.1 |
TH6 |
70 |
73 |
73 |
-0.2 |
WHS1 |
70 |
77 |
77 |
0.0 |
KT1 |
70 |
70 |
71 |
1.3 |
KT2 |
70 |
64-65 |
67 |
2.5 - 2.7 |
KT3 |
70 |
64 |
68 |
3.8 |
NWP1 |
70 |
71 |
73
- 75 |
2.6 - 4.1 |
NWP2 |
70 |
70 |
70 - 71 |
0.5 – 0.6 |
KLHSW |
70 |
65-66 |
65 - 66 |
0.0 |
Notes: Bold figure denotes the noise
exceedance which is over the relevant EIAO-TM noise criteria.
It can be seen from the above tables that the predicted differences between with and without the Project are equal to or greater than 1.0dB(A) at a lot of the representative NSRs (as highlighted in grey) which are considered as significant impact from the proposed connecting roads.
Scenario (2)
The roads proposed under the Project are scheduled to open in
2018. According to the projection of the
traffic impact assessment, the year with maximum traffic flow within a 15-year period upon commencement of
operation of the Project is determined to be 2033. Therefore, the traffic data for year 2033 has been
adopted for the assessment. The
potential unmitigated road traffic noise impacts on the NSRs for the Project at Year 2033 (AM) due to
operation of the
Table 4.37 Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Existing Uses)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Significant Contribution from New Roads* |
No. of Floors exceeded the Noise Criteria |
Assumed No. of Dwellings per floor |
No. of Dwellings Affected |
TYH |
70 |
62 |
Yes |
N/A |
N/A |
N/A |
V1 |
70 |
70 |
Yes |
N/A |
N/A |
N/A |
V2 |
70 |
65 |
Yes |
N/A |
N/A |
N/A |
CY3 |
70 |
61 – 62 |
Yes |
N/A |
N/A |
N/A |
KL1 |
70 |
64 |
Yes |
N/A |
N/A |
N/A |
TKL1 |
70 |
66 |
No |
N/A |
N/A |
N/A |
TKL2 |
70 |
69 |
No |
N/A |
N/A |
N/A |
KTW1 |
70 |
64 - 65 |
Yes |
N/A |
N/A |
N/A |
KTW2 |
70 |
60 |
Yes |
N/A |
N/A |
N/A |
KTW3 |
70 |
67 – 68 |
Yes |
N/A |
N/A |
N/A |
KTW4 |
70 |
59 |
Yes |
N/A |
N/A |
N/A |
KTW5 |
70 |
66 – 67 |
Yes |
N/A |
N/A |
N/A |
NYH1 |
70 |
66 – 67 |
Yes |
N/A |
N/A |
N/A |
NYH2 |
70 |
66 |
Yes |
N/A |
N/A |
N/A |
PY1 |
70 |
73
– 74 |
Yes |
2 |
1 |
2 |
PY2 |
70 |
73
|
Yes |
2 |
1 |
2 |
PY3 |
70 |
68 - 69 |
Yes |
N/A |
N/A |
N/A |
PY4 |
70 |
71 |
Yes |
1 |
1 |
1 |
PY5 |
70 |
67 |
Yes |
N/A |
N/A |
N/A |
PY6 |
70 |
68 |
Yes |
N/A |
N/A |
N/A |
PY7 |
70 |
66 - 67 |
Yes |
N/A |
N/A |
N/A |
WKS1 |
70 |
72 |
Yes |
1 |
1 |
1 |
WKS2 |
70 |
67 - 68 |
Yes |
N/A |
N/A |
N/A |
WKS3 |
70 |
65 - 66 |
Yes |
N/A |
N/A |
N/A |
WKS4 |
70 |
71 |
Yes |
1 |
1 |
1 |
WKS5 |
70 |
69 |
Yes |
N/A |
N/A |
N/A |
WKS6 |
70 |
69 |
Yes |
N/A |
N/A |
N/A |
WKS7 |
70 |
71 |
Yes |
1 |
1 |
1 |
Notes: (*) Significant Contribution from New Roads denotes the noise level from new roads to the overall noise level is equal to or higher than 1.0dB(A)
Table 4.38 Unmitigated Road Traffic Noise Impact in Year 2033 near Lin Ma Hang to Wo Keng Shan (Planned Uses)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Significant Contribution from New Roads* |
No. of Floors exceeded the Noise Criteria |
KTW6 |
70 |
67 - 68 |
No |
N/A |
WKS8 |
70 |
69 - 70 |
Yes |
N/A |
Notes: (*) Significant Contribution from New
Roads denotes the noise level from new roads to the overall noise level is
equal to or higher than 1.0dB(A)
Table 4.39 Unmitigated Road Traffic Noise Impact in Year 2033 near Sha Tau Kok Road Section (Existing Uses)
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Significant Contribution from New Roads* |
No. of Floors exceeded the Noise Criteria |
Assumed No. of Dwellings per floor |
No. of Dwellings Affected |
ST1 |
70 |
65 – 68 |
Yes |
N/A |
N/A |
N/A |
ST2 |
70 |
69 – 70 |
Yes |
N/A |
N/A |
N/A |
ST3 |
70 |
70 |
Yes |
N/A |
N/A |
N/A |
ST5 |
70 |
74 |
Yes |
2 |
1 |
2 |
ST6 |
70 |
72 |
Yes |
2 |
1 |
2 |
TTW1 |
70 |
68 |
Yes |
N/A |
N/A |
N/A |
TTW2 |
70 |
70 |
Yes |
N/A |
N/A |
N/A |
LT1 |
70 |
75
- 76 |
Yes |
2 |
1 |
2 |
LT2 |
70 |
72 |
Yes |
3 |
1 |
3 |
LT3 |
70 |
75 |
Yes |
2 |
1 |
2 |
LT4 |
70 |
72 |
Yes |
3 |
1 |
3 |
Notes: Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria and the contribution from new roads to the overall noise level is equal to or higher than 1.0dB(A).
(*) Significant Contribution from New Roads denotes the noise
level from new roads to the overall noise level is equal to or higher than
1.0dB(A)
Table 4.40 Unmitigated
Road Traffic Noise Impact in Year 2033 near
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
Significant Contribution from New Roads* |
No. of Floors exceeded the Noise Criteria |
Assumed No. of Dwellings per floor |
No. of Dwellings Affected |
TH1 |
70 |
76 |
Yes |
1 |
1 |
1 |
TH2 |
70 |
73 |
Yes |
2 |
1 |
2 |
TH4 |
70 |
71 |
Yes |
2 |
1 |
2 |
TH5 |
70 |
73 |
No |
N/A |
N/A |
N/A |
TH6 |
70 |
74 |
No |
N/A |
N/A |
N/A |
WHS1 |
70 |
78 |
No |
N/A |
N/A |
N/A |
KT1 |
70 |
72 |
Yes |
1 |
1 |
1 |
KT2 |
70 |
68 |
Yes |
N/A |
N/A |
N/A |
KT3 |
70 |
69 |
Yes |
N/A |
N/A |
N/A |
NWP1 |
70 |
74
- 76 |
Yes |
2 |
1 |
2 |
NWP2 |
70 |
71 - 72 |
No |
N/A |
N/A |
N/A |
KLHSW |
70 |
66 - 67 |
Yes |
N/A |
N/A |
N/A |
Notes: Bold figure denotes the noise exceedance which is over the relevant EIAO-TM noise criteria and the contribution from new roads to the overall noise level is equal to or higher than 1.0dB(A).
(*) Significant Contribution from New Roads denotes the noise
level from new roads to the overall noise level is equal to or higher than
1.0dB(A).
Table 4.41 summarises the exceedance of road traffic noise criteria with significant contribution from “new roads” for existing uses, including the number of affected dwellings. No exceedance of road traffic noise criteria for planned uses is predicted.
Table 4.41 Summary of Exceedance of Road Traffic Noise Criteria
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Predicted Noise Level L10 (1hr) dB(A) |
No. of Floors exceeded the Noise Criteria |
Assumed No. of Dwellings per floor |
No. of Houses Represented |
No. of Dwellings Affected |
Lin
Ma Hang to Wo Keng Shan |
||||||
PY1 |
70 |
73
– 74 |
2 |
1 |
1 |
2 |
PY2 |
70 |
73
|
2 |
1 |
2 |
4 |
PY4 |
70 |
71 |
1 |
1 |
2 |
2 |
WKS1 |
70 |
72 |
1 |
1 |
2 |
2 |
WKS4 |
70 |
71 |
1 |
1 |
2 |
2 |
WKS7 |
70 |
71 |
1 |
1 |
2 |
2 |
Loi
Tung |
|
|
|
|
|
|
ST5 |
70 |
74 |
2 |
1 |
1 |
2 |
ST6 |
70 |
72 |
2 |
1 |
2 |
4 |
LT1 |
70 |
75
- 76 |
2 |
1 |
3 |
6 |
LT2 |
70 |
72 |
3 |
1 |
2 |
6 |
LT3 |
70 |
75 |
2 |
1 |
3 |
6 |
LT4 |
70 |
72 |
3 |
1 |
1 |
3 |
Fanling |
||||||
TH1 |
70 |
76 |
1 |
1 |
3 |
3 |
TH2 |
70 |
73 |
2 |
1 |
2 |
4 |
TH4 |
70 |
71 |
2 |
1 |
3 |
6 |
KT1 |
70 |
72 |
1 |
1 |
1 |
1 |
NWP1 |
70 |
74
- 76 |
2 |
1 |
9 |
18 |
Total
no. of Dwellings Affected |
73 |
4.5.1.4 Evaluation of Mitigation Measures
Exceedance of noise criteria were found in various sensitive receivers for both existing and planned uses, direct mitigation measures should be proposed. According to the Section 6.1, Annex 13 of EIAO-TM, direct mitigation measures as listed below should be considered and evaluated:
■
Open-textured
road surfacing; and
■
Noise
barrier/ enclosure
The mitigation measures above are at-source mitigation measures and were further elaborated in the following paragraphs.
Noise mitigation measures starting from direct ones were evaluated. When all practicable at-source mitigation measures have been exhausted, at-receiver mitigation measures would be considered in terms of modification of layout plan and setback requirement for the planned NSRs, and consideration of provision of noise insulation for the existing NSRs where justified and eligible.
Use of low noise road surfacing (LNRS)
The use of noise absorptive paving materials on project roads can theoretically reduce the traffic noise impact. As per the values specified in CRTN, the use of pervious macadam on road surface can reduce the basic noise level by 3.5 dB(A), as compared to that of 1.0dB(A) for common impervious paving.
In accordance with RD/GN/032, the extent of low-noise
surfacing has been considered in the unmitigated scenario and will cover the
link roads and slip roads, but not the local road sections i.e. the roundabouts
at
Noise barrier/enclosure
In view of practicability, the erection of noise barrier/ semi-enclosure along the new road sections are considered as effective mitigation measures in tackling the road traffic noise impact to sensitive receivers.
4.5.1.5 Mitigated Noise Impact
Existing Uses
As discussed above, direct mitigation measures in form of noise barrier/ enclosure should be considered in order to comply with the noise criteria. The locations of noise barriers proposed for the existing noise sensitive uses are tabulated in Table 4.42 below and shown in Figures 4.20.1 to 4.20.4. Typical cross-sections of the proposed noise barriers are shown in Figure 4.20.5.
Table 4.42 Proposed Location of Noise Barrier for Existing Uses
Location |
Chainage |
Type of Noise Mitigation Measures |
*Height |
Length, m |
Figure |
Ping Yeung |
9040 – 9085 ( |
Vertical Barrier |
0.8m |
85 |
|
Nga Yiu Ha |
166 (Access Road to Ping Yeung ) – 450
(Slip Road – North Bound) |
Vertical Barrier |
2.5m |
152 |
|
Wo Keng Shan |
8585 – 8500 ( |
Vertical Barrier |
2m |
85 |
|
|
8500 –
8355 ( |
Vertical
Barrier |
2m above parapet |
145 |
|
|
8180 – 8290 ( |
Vertical Barrier |
1m above parapet |
110 |
|
Loi Tung |
6488 – 6855 ( |
Vertical Barrier |
1.5m |
367 |
|
|
6800 – 6855 ( |
Vertical Barrier |
0.8m |
55 |
|
|
360 ( |
Vertical Barrier |
2m |
108 |
|
|
195 ( |
Vertical Barrier |
1.5m |
182 |
|
|
40 ( |
Vertical Barrier |
5m |
120 |
|
Tong Hang |
1640 – 1713 ( |
Vertical Barrier |
3m |
73 |
|
|
1589 – 1621 ( |
Vertical Barrier |
3m |
32 |
|
|
0 – 100 ( |
Vertical Barrier |
4m above parapet |
100 |
|
|
285 – 330 (Access to |
Vertical Barrier |
5m |
45 |
|
Wo Hop Shek |
185 – 430 (Fanling Highway South Bound connecting
Link Road 2) |
Vertical Barrier |
3m |
245 |
|
|
543 – 662 ( |
Vertical Barrier |
2.5m above parapet |
119 |
|
|
662 - 700
( |
Vertical
Barrier |
1m |
38 |
|
|
815 – 856 ( |
Vertical Barrier |
1m above parapet |
41 |
|
|
276 – 336 ( |
Vertical Barrier |
3m above parapet |
60 |
|
|
274 – 175 ( |
Vertical Barrier |
3m above parapet |
99 |
Notes: (*) The parapet wall is 0.8m high above
road surface
With the erection of noise barriers, the predicted noise levels are shown in Table 4.43. The detailed breakdowns for road traffic noise are shown in Appendix 4.9.
Table 4.43: Mitigated Road Traffic Noise Levels of Existing Uses
NSR ID |
Noise Criteria L10(1
hr) dB(A) |
Mitigated Noise Level L10 (1hr) dB(A) |
Lin Ma Hang to Wo Keng Shan |
|
|
PY1 |
70 |
68 – 69 |
PY2 |
70 |
67 – 70 |
PY4 |
70 |
68 |
WKS1 |
70 |
68 |
WKS4 |
70 |
70 |
WKS7 |
70 |
70 |
Loi Tung |
|
|
ST5 |
70 |
68 – 70 |
ST6 |
70 |
67 – 68 |
LT1 |
70 |
68 – 69 |
LT2 |
70 |
70 |
LT3 |
70 |
69 – 70 |
LT4 |
70 |
68 – 70 |
Fanling |
|
|
TH1 |
70 |
65 |
TH2 |
70 |
69 - 70 |
TH4 |
70 |
70 |
KT1 |
70 |
68 |
NWP1 |
70 |
68 - 70 |
Notes: (*) Significant Contribution from New
Roads denotes the noise level from new roads to the overall noise level is
equal to or higher than 1.0dB(A).
Based on the tables above, although some of the NSRs i.e. WHS1, TH5, TH6 and NWP2 would exceed the relevant noise criteria, the noise contribution from new roads is smaller than 1.0 dB(A). Therefore, no further mitigation measure is considered.
Planned Uses
It is noted that the construction of New Territories Exempted House is permitted in V zone within the assessment area. However, as no exceedance of road traffic noise criteria is predicted for such planned uses, no further mitigation measures is required.
4.5.2 Fixed Plant Noise
4.5.2.1 Identification of Emission Source
Potential noise impacts from operation of planned fixed plant including any noisy facilities inside the BCP and ventilation shafts of the tunnel sections of the connecting road on the nearby NSRs have been assessed quantitatively. In accordance with Annex 5 of the EIAO-TM, the noise criteria for fixed plant noise assessment shall be either
■
5
dB(A) below the appropriate Acceptable Noise Levels (ANL) shown in Table 2 of
the Technical Memorandum for the Assessment of Noise from Places Other than
Domestic Premises, Public Places or Construction Sites, or
■
the
prevailing background noise levels (for quiet areas with level 5 dB(A) below
the ANL).
For the potential noise impact from the operation of the BCP other than the inside fixed plant sources, discussion is given in Section 4.5.2.5.
Given that the Project will be developed in a quiet rural
environment except the area near
Table 4.44 Noise Criteria of Fixed Plant Noise
Location Description |
Representative NSR ID. |
ASR |
Time Period |
ANL – 5, dB(A) |
Corrected Facade Noise Level, dB(A)* |
Fixed Plant Noise Criteria, dB(A) |
Tsung Yuen Ha |
TYH, V1,
V2, CY3 |
A |
Daytime |
55 |
52 |
52 |
|
|
|
Evening
Time |
55 |
49 |
49 |
|
|
|
Night-time |
45 |
45 |
45 |
|
WKS6,
WKS7 |
A |
Daytime |
55 |
56 |
55 |
|
|
|
Evening
Time |
55 |
52 |
52 |
|
|
|
Night-time |
45 |
46 |
45 |
Wo Keng Shan |
ST1,
ST2, ST3 and TTW2 |
A |
Daytime |
55 |
54 |
54 |
|
|
Evening
Time |
55 |
47 |
47 |
|
|
|
|
Night-time |
45 |
45 |
45 |
Loi Tung |
LT4 |
A |
Daytime |
55 |
49 |
49 |
|
|
|
Evening
Time |
55 |
44 |
44 |
|
|
|
Night-time |
45 |
43 |
43 |
|
PKT1,
PKT2 and PKT3 |
A |
Daytime |
55 |
46 |
46 |
|
|
Evening
Time |
55 |
36 |
36 |
|
|
|
|
Night-time |
45 |
36 |
36 |
|
TH1,
TH4 |
C |
Daytime |
65 |
N/A |
65 |
|
|
|
Evening
Time |
65 |
N/A |
65 |
|
|
|
Night-time |
55 |
N/A |
55 |
Notes: (*) A facade correction of 3dB(A) has been included in the measurement results.
4.5.2.2 Assessment Methodology
In the absence of any detailed information and noise specification for the proposed fixed plant, the maximum permissible noise emission levels at the shaft/ exhaust openings have been determined for future detailed design of the fixed plant.
For the assessment of noise from the fixed plant, the maximum permissible sound power levels (Max SWLs) of the identified fixed noise sources were determined by adopting standard acoustics principles. The following formula was used for calculating the Max SWLs of the fixed plant:
SPL = Max SWL – DC + FC
where
SPL: Sound Pressure Level in dB(A)
Max
SWL: Maximum Permissible Sound Power
Level in dB(A)
DC: Distance Attenuation in dB(A) = 20
log D + 8 [where D is the distance in m]
FC: Façade Correction in dB(A) = +3
dB(A)
If the noise sources do not fall within the view angle of the representative NSR under assessment or are completely blocked by the residential blocks/ buildings, it is assumed that these noise sources are insignificant to that NSR and would be excluded from calculation. While the sources fall within the view angle of the NSR but with no direct line of sight to the opening, a 10 dB(A) attenuation would be applied.
If exceedance to the noise criteria is found for one NSR, the initial SWL of the dominant sources to that NSR would be gradually lowered until the corrected SPL at that NSR meets the acceptable level. The process would be repeated for other representative NSRs with exceedance of the noise criteria until all corrected SPLs at the representative NSRs meet the noise criteria. The maximum allowable SWLs of the proposed fixed plants have been predicted by this approach.
4.5.2.3 Evaluation of Impacts
Noise from fixed plant for the Project would mainly be associated with BCP buildings, tunnel ventilation shaft, administration building and mid-ventilation building. According to the preliminary design information, major fixed plant noise is attributed to the following sources as summarised in Table 4.45 below and shown in Figures 4.21.1 to 4.21.7: -
¡ BCP Buildings;
¡ Ventilation Shafts in Tunnel Portals;
¡
¡
Table 4.45: Summary of Fixed Plant Noise Sources
Fixed Plant Location |
Fixed Noise Source |
Number of Fixed Plant |
Opening ID |
Figure |
BCP |
Sewage
Treatment Plant (G/F) |
7 |
STP-A
to G |
|
|
Fixed
X-Ray Inspection Station and Offices (G/F) |
4 |
FXO-A
to D |
|
|
Fixed
X-Ray Inspection Station (G/F) |
4 |
FXI-A
to D |
|
|
|
4 |
PTB-A
to D |
|
|
|
4 |
PTB-A
to D |
|
|
Fire
Station (G/F) |
4 |
FS-A
to D |
|
|
Police
Station (G/F) |
4 |
HKP-A
to D |
|
North
Tunnel North Portal |
|
2 |
VB1-A-B |
|
|
|
2 |
VB2-A-B |
|
|
3 |
|
||
South
Tunnel North Portal |
|
2 |
VB3-A-B |
|
South
Tunnel South Portal |
|
2 |
VB4-A-B |
|
|
|
1 |
MVB-A |
Based on the methodology
mentioned above, the maximum allowable SWLs of the proposed fixed plants during daytime and night-time are predicted as summarized in Table
4.46 below. Calculations
of fixed plant noise assessment are shown in Appendix 4.10.
Table 4.46: Maximum SWLs of the Fixed Plant
Fixed Plant Location |
Fixed Noise Source |
Opening ID |
*Maximum SWL, dB(A) |
||
Daytime |
Evening Time |
Night-time |
|||
BCP |
Sewage Treatment Plant (G/F) |
STP-A to G |
94 |
91 |
87 |
|
Fixed X-Ray Inspection Station and Offices
(G/F) |
FXO-A to D |
94 |
91 |
87 |
|
Fixed X-Ray Inspection Station (G/F) |
FXI-A to D |
88 |
85 |
81 |
|
|
PTB-A to D |
90 |
87 |
83 |
|
|
PTB-A to D |
90 |
87 |
83 |
|
Fire Station (G/F) |
FS-A to D |
88 |
85 |
81 |
|
Police Station (G/F) |
HKP-A to D |
88 |
85 |
81 |
North Tunnel North Portal |
|
VB1-A |
102 |
99 |
92 |
VB1-B |
107 |
104 |
97 |
||
|
|
VB2-A |
107 |
100 |
98 |
VB2-B |
107 |
100 |
98 |
||
|
AB-A |
95 |
88 |
86 |
|
AB-B |
95 |
88 |
86 |
||
AB-C |
94 |
87 |
85 |
||
South Tunnel North Portal |
|
VB3-A |
107 |
102 |
101 |
VB3-B |
107 |
102 |
101 |
||
South Tunnel South Portal |
|
VB4-A |
115 |
115 |
105 |
VB4-B |
110 |
110 |
100 |
||
|
|
MVB-A |
98 |
88 |
88 |
Notes: (*) Maximum SWL at each opening
4.5.2.4 Mitigation of Adverse Environmental Impact
With the fixed plant properly designed to meet the maximum SWL listed in Table 4.46, there would not be any residual impacts predicted. However, it is still recommended that the following noise reduction measures shall be considered as far as practicable during construction:
¡ Choose quieter plant such as those which have been effectively silenced.
¡ Include noise levels specification when ordering new plant (including chillier and E/M equipment).
¡ Locate fixed plant/louver away from any NSRs as far as practicable.
¡ Locate fixed plant in walled plant rooms or in specially designed enclosures.
¡ Locate noisy machines in a basement or a completely separate building.
¡ Install direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosure where necessary.
¡ Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain a controlled level of noise.
4.5.2.5 Potential Noise Impact from the Operation of the BCP
Other than the fixed plant sources inside
BCP, potential noise impact may be generated from the daily operation of the
BCP. The main activities that would be involved in the daily
operation include vehicles moving in and out of the BCP with relatively low
speed and vehicles lining up inside the BCP for inspection i.e. vehicles in idling. Public address system would be installed
inside the BCP but the usage of the system shall be limited as the BCP would be
operated mainly by sign gantry. The
closest noise sensitive receiver to the BCP i.e. the Tsung Yuen Ha Village is
located at a distance of about
4.6 Environmental Monitoring and Audit
4.6.1 Construction Phase
With the recommended
mitigation measures, no residual noise impacts are predicted at all representative NSRs during the
construction phase,, However, environmental monitoring and
audit (EM&A) is recommended
to ensure the mitigation measures and good site practice have been implemented
properly, and to minimize the potential noise impact during the construction
phase.
Details are given in the EM&A Manual.
4.6.2 Operational Phase
Prior to the
operation phase of the Project, a commissioning test should be conducted for
all major fixed noise sources to ensure compliance of the operational airborne
noise levels with the EIAO-TM noise criteria.
Road traffic noise
levels should be monitored at representative NSRs, which are in the vicinity of
the recommended direct noise mitigation measures, during the first year after
road opening.
Details of the EM&A
programme are provided in the stand-alone EM&A Manual
The noise impact associated with unmitigated construction
activities for the proposed BCP and the connecting road would
cause exceedance of the daytime construction noise criterion at the nearby NSRs
during the normal working hours.
Therefore, good site practices
and mitigation measures including the use of quiet plants, erection of movable noise barriers and noise insulating fabric have been proposed to alleviate the
noise impact. With the good site practices and mitigation
measures in place, no residual impacts are predicted at all the NSRs.
The assessment has predicted that the traffic noise impact arising from the proposed connecting roads of the Project and the contribution from existing road network in Year 2033 will exceed the noise criteria at the existing NSRs with around 76 dwellings affected by the Project roads. With the implementation of mitigation measures recommended, the noise criteria will be met at all representative NSRs with traffic noise impact dominated by the Project roads.
With the specification of maximum allowable sound power levels for the proposed fixed plants at ventilation shafts, mid-ventilation building, BCP buildings and Administration Buildings, full compliance of Noise Control Ordinance will be achieved.
[1] Nelson, P.M., Transportation Noise Reference Book. 1987.
[2] Saurenman, H., Nelson, J., Wilson, G. 1982, Handbook of Urban Rail Noise and Vibration Control, US Department of Transportation Urban Mass Transportation Administration (Table 8-7).
[3] Transit noise and vibration impact assessment, US Federal Transit Administration (FTA), 2006