Content
Chapter Title Page
Figures
Figure 1.1 Project Layout (Main
Sections)
Figure 1.2 Project
Organisation Chart
Figure 2.1 Proposed
Location of Construction Air Quality
Monitoring Stations
Figure 3.1 Proposed
Location of Construction Noise Monitoring
Stations
Figure 3.2 Proposed Location
of Operational Noise Monitoring Stations
Figure 4.1 Locations of Proposed Water
Quality Monitoring Stations
Figure 8.1 Potential
Figure 8.2 Indicative
Boundary of the Potential Wetland Compensation Area
Figure 8.3 Conceptual
Plan and Typical Cross-section Views of the Proposed Wetland Compensation Area
Figure 10.1 Landscape
and Visual Mitigation Plan – Key Plan
Figure 10.2 Landscape and Visual
Mitigation Plan – Section A, Zone 1
Figure 10.3 Landscape and Visual
Mitigation Plan – Section A, Zones 1 & 2
Figure 10.4 Landscape and Visual
Mitigation Plan – Section A, Zone 2
Figure 10.5 Landscape and Visual
Mitigation Plan – Section A, Zone 3
Figure 10.6 Landscape and Visual
Mitigation Plan – Section B
Figure 10.7 Landscape and Visual
Mitigation Plan – Section C
Figure 11.1 Areas Requiring
Further Archaeological Survey within Section between Lin Ma Hang and Frontier
Closed Area Boundary
Figure 11.2 Areas Requiring
Archaeological Survey Cum-rescue Excavation and Further Archaeological Survey
within Section between Ping Yeung and Wo Keng Shan
Figure 11.3 Areas Requiring
Further Archaeological Survey within Section between Ping Yeung and Wo Keng
Shan
Figure 11.4 Areas Requiring
Further Archaeological Survey within
Figure 11.5 Area Requiring Further
Archaeological Survey within Lau Shui Heung Tunnel Section
Figure 11.6 Area Requiring Further
Archaeological Survey within Fanling Section
Figure 12.1 Flow Chart of Complaint
Investigation Procedures
Appendices
Appendix A Implementation
Schedule of Environmental
Mitigation Measures
Appendix B Sample Environmental Monitoring Data Recording
Sheets
Appendix C Sample Template for the Interim Notifications
Appendix
D Guidelines for
Photographic Records and Cartographic Records established by AMO
The purpose of this Environmental Monitoring and Audit
(EM&A) Manual (hereafter referred to as the Manual) is to guide the setup
of an EM&A programme to ensure compliance with the Environmental Impact
Assessment (EIA) study recommendations, to assess the effectiveness of the
recommended mitigation measures and to identify any further need for additional
mitigation measures or remedial action. This Manual outlines the monitoring and
audit programme proposed for the “Liantang / Heung Yuen Wai Boundary Control
Point and Associated Works (LT/HYW)” (The Project).
It
should be noted that this EM&A Manual would be further reviewed and updated
where necessary.
There are currently four existing boundary
control points (BCPs) that provide vehicular crossing at the
It is anticipated that the volume of cross-boundary traffic will continue to increase with the closer ties of Hong Kong-Shenzhen and the completion of the planned Eastern Corridor in Shenzhen. Therefore, it was identified necessary to establish a new BCP in the eastern part of Hong Kong-Shenzhen boundary to meet the future traffic demand and re-distribute cross-boundary traffic amongst the crossings in the east.
In December 2006, the Hong Kong Government and the Shenzhen Government jointly commissioned a study entitled “Preliminary Planning Study on Developing Liantang/Heung Yuen Wai Control Point” (hereafter referred to as “the Joint Study”) to examine the need, benefit and function of a new BCP at LT/HYW. The Joint Study confirmed the need for a new BCP at LT/HYW.
In January 2007, the Planning Department commissioned a consultancy study entitled “Planning Study on Liantang/Heung Yuen Wai Cross-boundary Control Point and its Associated Connecting Roads in Hong Kong – Feasibility Study” (hereafter referred to as “the Feasibility Study”) to examine the land, planning, traffic and engineering implications and its associated connecting road within Hong Kong territory for the LT/HYW BCP. With evaluation of a number of alternative options, the Feasibility Study (FS) put forward a preferred layout of the LT/HYW BCP and preferred alignment of the LT/HYW BCP connecting road.
On 18 September 2008, at the second meeting of the Hong Kong-Shenzhen Joint Task Force on Boundary District Development, the two Governments endorsed the major findings of the Joint Study and jointly announced to implement the LT/HYW BCP after the meeting on the following basis:
(a)
The LT/HYW BCP would adopt the separate-location
model but design of the BCP should maximize convenience to users including the
construction of an integrated passenger hall over the
(b)
The LT/HYW BCP on Hong Kong side would require
resumption and resite of
(c) The connecting road with the LT/HYW BCP on Hong Kong side would adopt the alignment leading to Tolo/Fanling Highway in the eastern direction; and
(d)
The design and construction of the LT/HYW BCP
should be packaged with the improvement works of Liantang section of the
Mott MacDonald Hong Kong Ltd. (MMHK) was commissioned by the Civil Engineering and Development Department (CEDD) on 24 April 2009 under Agreement No. CE 45/2008 (CE) to provide professional services to address issues related to the planning, design and construction of the Project and to work out details of the Project to an extent to enable CEDD to take forward the Project to the detailed design and construction stages.
The Project consists of two main components, construction of a BCP; and construction of a connecting road alignment.
The
proposed BCP is located at the boundary with Shenzhen near the existing
The connecting road alignment consists of six main sections:
1.
Lin Ma
Hang to Frontier Closed Area (FCA) Boundary
– this section comprises at-grade and viaducts and includes the
improvement works at
2. Ping Yeung to Wo Keng Shan – this section stretches from the Frontier Closed Area Boundary to the tunnel portal at Cheung Shan and comprises at-grade and viaducts including an interchange at Ping Yeung;
3. North Tunnel – this section comprises the tunnel segment at Cheung Shan and includes a ventilation building at the portals on either end of the tunnel;
4.
5. South Tunnel – this section comprises a tunnel segment that stretches from Loi Tung to Fanling and includes a ventilation building at the portals on either end of the tunnel as well as a ventilation building in the middle of the tunnel near Lau Shui Heung;
6.
Fanling
– this section comprises the at-grade, viaducts and interchange connection to
the existing
Figure 1.1 shows the Project layout and corresponding sections.
1.4
Tentative
Construction Programme
Construction of the Project
is expected
to commence in mid-2013 for completion in mid-2018. The tentative construction
programme is given in Appendix 2.1 of the EIA Report.
The proposed project organisation is shown in Figure 1.2. The responsibilities of respective parties are:
Civil
Engineering and Development Department (CEDD)
CEDD
will be the Project Proponent of the development of the Project and will assume overall responsibility
for the project.
Environmental
Protection Department (EPD)
EPD is the statutory enforcement body for environmental
protection matters in
Engineer or Engineer’s Representative (ER)
The
ER is responsible for overseeing the construction works and for ensuring that the works
are undertaken by the Contractor in accordance with the specification and
contract requirements. The duties and responsibilities of the ER with respect
to EM&A are:
§
Monitor the Contractors’ compliance with contract specifications, including
the implementation and operation of the environmental mitigation measures and
their effectiveness
§
Employ an Independent Environmental Checker (IEC) to audit the results
of the EM&A works carried out by the ET
§
Monitor Contractors’, ET’s and IEC’s compliance with the requirements in
the Environmental Permit (EP) and EM&A Manual
§
Facilitate ET’s implementation of the EM&A programme
§
Participate in joint site inspection by the ET and IEC
§
Oversee the implementation of the agreed Event / Action Plan in the
event of any exceedance
§
Adhere to the procedures for carrying out complaint investigation
§
Liaison with DSD, Engineer/Engineer’s Representative, ET, IEC and the
Contractor of the “Construction of the DSD’s Regulaiton of Shenzhen River Stage
4 (RSR 4)” Project discussing regarding the cumulative impact issues.
The Contractor
The
Contractor should report to the ER. The duties and responsibilities of the
Contractor are:
§
Comply with the relevant contract conditions and specifications on
environmental protection
§
Employ an Environmental Team (ET) to undertake monitoring, laboratory
analysis and reporting of EM&A
§
Facilitate ET’s monitoring and site inspection activities
§ Participate in the
site inspections by the ET and IEC, and undertake any corrective actions
§
Provide information / advice to the ET regarding works programme and
activities which may contribute to the generation of adverse environmental
impacts
§
Submit proposals on mitigation measures in case of exceedances of Action
and Limit levels in accordance with the Event / Action Plans
§
Implement measures to reduce impact where Action and Limit levels are
exceeded
§
Adhere to the procedures for carrying out complaint investigation
Environmental Team (ET)
The ET shall not be in any way an associated
body of the Contractor, and shall be employed by the Project Proponent/Contractor
to conduct the EM&A programme. The ET should be managed by the ET Leader. The
ET Leader shall be a person who has at least 7 years’ experience in EM&A
and has relevant professional qualifications. The appointment of ET Leader
should be subject to the approval of EPD. Suitably qualified staff should be
included in the ET, and resources for the implementation of the EM&A programme
should be allocated in time under the Contract, to enable fulfilment of the
Project’s EM&A requirements as specified in the EM&A Manual during
construction of the Project. The ET shall report to the Project Proponent and
the duties shall include:
§
Monitor and audit various environmental parameters
as required in this EM&A Manual
§
Analyse the environmental monitoring and audit data, review the success
of EM&A programme and the adequacy of mitigation measures implemented,
confirm the validity of the EIA predictions and identify any adverse
environmental impacts arising
§
Carry out regular site inspection to investigate and audit the
Contractors' site practice, equipment/plant and work methodologies with respect
to pollution control and environmental mitigation, and effect proactive action
to pre-empt problems
§
Monitor compliance with conditions in the EP, environmental protection,
pollution prevention and control regulations and contract specifications
§
Audit environmental conditions on site
§
Report on the environmental monitoring and audit results to EPD, the ER,
the IEC and Contractor or their delegated representatives
§
Recommend suitable mitigation measures to the Contractor in the case of
exceedance of Action and Limit levels in accordance with the Event and Action
Plans
§
Liaise with the IEC on all environmental performance matters and timely
submit all relevant EM&A proforma for approval by IEC
§
Advise the Contractor on environmental improvement, awareness,
enhancement measures etc.,on site
§
Adhere to the procedures for carrying out complaint investigation
§
Liaison with DSD, Engineer/Engineer’s Representative, ET, IEC and the
Contractor of the “Construction of the DSD’s Regulaiton of Shenzhen River Stage
4 (RSR 4)” Project discussing regarding the cumulative impact issues.
Independent Environmental Checker (IEC)
The Independent Environmental Checker (IEC)
should not be in any way an associated body of the Contractor or the ET for the
Project. The IEC should be employed by the Project Proponent/ Engineer prior to
the commencement of the construction of the Project. The IEC should have at
least 10 years’ experience in EM&A and have relevant professional
qualifications. The appointment of IEC should be subject to the approval of
EPD. The IEC should:
§
Provide proactive advice to the ER and the Project Proponent on EM&A
matters related to the project, independent from the management of construction
works, but empowered to audit the environmental performance of construction
§
Review and audit all aspects of the EM&A programme implemented by
the ET
§
Review and verify the monitoring data and all submissions in connection
with the EP and EM&A Manual submitted by the ET
§
Arrange and conduct regular, at least monthly site inspections of the
works during construction phase, and ad hoc inspections if significant
environmental problems are identified
§
Check compliance with the agreed Event / Action Plan in the event of any
exceedance
§
Check compliance with the procedures for carrying out complaint
investigation
§
Check the effectiveness of corrective measures
§
Feedback audit results to ET by signing off relevant EM&A proforma
§
Check that the mitigation measures are effectively implemented
§
Report the works conducted, the findings, recommendation and improvement
of the site inspections, after reviewing ET’s and Contractor’s works, and
advices to the ER and Project Proponent on a monthly basis
§
Liaison with DSD, Engineer/Engineer’s Representative, ET, IEC and the
Contractor of the “Construction of the DSD’s Regulaiton of Shenzhen River Stage
4 (RSR 4)” Project discussing regarding the cumulative impact issues.
2.1 Construction Air Quality Monitoring
Dust monitoring is considered necessary during the construction phase and regular site inspections are required to ensure that the dust control measures are properly implemented.
2.1.1 Monitoring Requirements
Monitoring and audit of the Total Suspended Particulate
(TSP) levels should be carried out by the ET to ensure that any
deteriorating air quality could be readily detected and timely actions
taken to rectify the situation.
1-hour or 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality. The TSP levels should be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. Upon approval of the ER, 1-hour TSP levels can be measured by direct reading methods which are capable of producing comparable results as that by the high volume sampling method, to indicate short event impacts.
All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, other special phenomena and work progress of the concerned project area etc. should be recorded. A sample data record sheet is shown in Appendix B. The ET may develop project specific data record sheet to suit this EM&A programme.
2.1.2 Monitoring Equipment
High Volume Sampler (HVS) in compliance with the following specifications should be used for carrying out the 1-hour or 24-hour TSP monitoring:
§
0.6 -
1.7 m3/min (20 - 60 standard cubic feet per minute) adjustable flow
range;
§
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
§
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
§
capable
of providing a minimum exposed area of 406 cm2 (63 in2);
§
flow
control accuracy: +/- 2.5% deviation over 24-hr sampling period;
§
equipped
with a shelter to protect the filter and sampler;
§
incorporated
with an electronic mass flow rate controller or other equivalent devices;
§
equipped
with a flow recorder for continuous monitoring;
§
provided
with a peaked roof inlet;
§
incorporated
with a manometer;
§
able to
hold and seal the filter paper to the sampler housing at horizontal position;
§
easy to
change the filter, and
§
capable
of operating continuously for 24-hour period.
The ET is responsible
for provision of the monitoring equipment. They shall ensure that sufficient number
of HVSs with an appropriate calibration kit are available for carrying out the
baseline monitoring, regular impact monitoring and ad hoc monitoring. The HVSs
shall be equipped with an electronic mass flow controller and be calibrated
against a traceable standard at regular intervals. All the equipment, calibration kit, filter
papers, etc., shall be clearly labelled.
Initial calibration
of dust monitoring equipment shall be conducted upon installation and
thereafter at bi-monthly intervals. The transfer standard shall be traceable to
the internationally recognised primary standard and be calibrated annually. The
concern parties such as IEC shall properly document the calibration data for
future reference. All the data should be converted into standard temperature
and pressure condition.
The flow-rate of the
sampler before and after the sampling exercise with the filter in position
shall be verified to be constant and be recorded in the data sheet as mentioned
in Appendix B.
If the ET proposes
to use a direct reading dust meter to measure 1-hour TSP levels, he shall
submit sufficient information to the IEC to prove that the instrument is
capable of achieving a comparable result to the HVS. The instrument should also
be calibrated regularly, and the 1-hour sampling shall be determined
periodically by the HVS to check the validity and accuracy of the results
measured by direct reading method. A sample data sheet is shown in Appendix B.
Wind data monitoring
equipment shall also be provided and set up for logging wind speed and wind direction
near the dust monitoring locations. The equipment installation location shall
be proposed by the ET and agreed with the IEC. For installation and operation
of wind data monitoring equipment, the following points shall be observed:
§
The wind sensors
should be installed 10 m above ground so that they are clear of obstructions or
turbulence caused by buildings.
§
The wind data should
be captured by a data logger. The data shall be downloaded for analysis at
least once a month.
§
The wind data
monitoring equipment should be re-calibrated at least once every six months.
§
Wind direction
should be divided into 16 sectors of 22.5 degrees each.
In exceptional situations, the ET may propose
alternative methods to obtain representative wind data upon approval from the
ER and agreement from the IEC.
2.1.3 Laboratory Measurement / Analysis
A
clean laboratory with constant temperature and humidity control, and equipped
with necessary measuring and conditioning instruments to handle the dust
samples collected, shall be available for sample analysis, and equipment
calibration and maintenance. The laboratory should be HOKLAS accredited.
If
a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for
carrying out the laboratory analysis, the laboratory equipment shall be
approved by the ER and the measurement procedures shall be witnessed by the
IEC. Any measurement performed by the laboratory shall be demonstrated to the
satisfaction of the ER and IEC. IEC shall regularly audit to the measurement
performed by the laboratory to ensure the accuracy of measurement results. The
ET Leader shall provide the ER with one copy of the Title 40 of the Code of
Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.
Filter
paper of size 8" x 10" shall be labelled before sampling. It shall be
a clean filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
After
sampling, the filter paper loaded with dust shall be kept in a clean and tightly
sealed plastic bag. The filter paper
shall then be returned to the laboratory for reconditioning in the
humidity-controlled chamber followed by accurate weighing by an electronic
balance with readout down to 0.1 mg. The balance shall be regularly calibrated
against a traceable standard.
2.1.4 Monitoring Locations
Nine air quality monitoring locations are proposed and summarised in Table 2.1 and shown in Figure 2.1. As approval is needed from the premises landlord for dust monitoring equipment installation, it is not certain that a suitable location would be approved. The status and locations of dust sensitive receivers may change after issuing this manual. If such cases exist, the ET should propose updated monitoring locations and seek agreement from EPD.
Table 2.1: Construction Air Quality Monitoring Stations
ID |
ID adopted in EIA |
Description |
Works Area |
AM1 |
TYH |
Tsung Yuen Ha Village House No. 63 |
BCP |
AM2 |
V1 |
Village House near |
Lin Ma Hang to
Frontier Closed Area |
AM3 |
TKL2 |
Ta Kwu Ling Village House |
Lin Ma Hang to
Frontier Closed Area |
AM4 |
KTW4 |
Kan Tau Wai Village House |
Lin Ma Hang to
Frontier Closed Area |
AM5 |
PY1 |
|
Ping Yeung to
Wo Keng Shan |
AM6 |
WKS7 |
Wo |
Ping Yeung to
Wo Keng Shan |
AM7 |
TTW3 |
Tai Tong Wu
Village House |
|
AM8 |
PKT2 |
Po |
|
AM9 |
NWP1 |
|
Fanling |
When alternative monitoring locations are
proposed, the proposed site should, as far as practicable:
§
be at the site
boundary or such locations close to the major dust emission source;
§
be close to the
sensitive receptors; and
§
take into account
the prevailing meteorological conditions.
The ET shall agree with the ER in
consultation with the IEC on the position of the HVS for the installation of
the monitoring equipment. When positioning the samplers, the following points
shall be noted:
§
a horizontal
platform with appropriate support to secure the samplers against gusty wind
should be provided;
§
no two samplers
should be placed less than 2 meters apart;
§
the distance between
the sampler and an obstacle, such as buildings, must be at least twice the
height that the obstacle protrudes above the sampler;
§
a minimum of 2
meters of separation from walls, parapets and penthouses is required for
rooftop samplers;
§
a minimum of 2
meters separation from any supporting structure, measured horizontally is
required;
§
no furnace or
incinerator flue is nearby;
§
airflow around the
sampler is unrestricted;
§
the sampler is more
than 20 meters from the dripline;
§
any wire fence and
gate, to protect the sampler, should not cause any obstruction during
monitoring;
§
permission must be
obtained to set up the samplers and to obtain access to the monitoring
stations; and
§
a secured supply of
electricity is needed to operate the samplers.
Baseline
monitoring shall be carried out at all of the designated monitoring locations
for at least 14 consecutive days prior to the commencement of the construction
works to obtain daily 24-hour TSP samples. The selected baseline monitoring
stations should reflect baseline conditions at the impact stations. One-hour
sampling should also be done at least 3 times per day while the highest dust
impact is expected.
During
the baseline monitoring, there should not be any construction or dust
generation activities in the vicinity of the monitoring stations. Before
commencing baseline monitoring, the ET shall inform the IEC of the baseline
monitoring programme such that the IEC can conduct on-site audit to ensure
accuracy of the baseline monitoring results.
In
case the baseline monitoring cannot be carried out at the designated monitoring
locations during the baseline monitoring period, the ET Leader shall carry out
the monitoring at alternative locations that can effectively represent the
baseline conditions at the impact monitoring locations. The alternative
baseline monitoring locations shall be approved by the ER and agreed with the
IEC.
In
exceptional cases, when insufficient baseline monitoring data or questionable
results are obtained, the ET shall liaise with the IEC and EPD to agree on an
appropriate set of data to be used as a baseline reference and submit to ER for
approval.
Ambient
conditions may vary seasonally and shall be reviewed once every three months.
When the ambient conditions have changed and a repeat of the baseline
monitoring is required to be carried out for obtaining the updated baseline
levels, the monitoring should be at times when the Contractor's activities are
not generating dust, at least in the proximity of the monitoring stations.
Should change in ambient conditions be determined, the baseline levels and, in
turn, the air quality criteria, should be revised. The revised baseline levels
and air quality criteria should be agreed with the IEC and EPD.
2.1.6 Impact Monitoring
The ET shall carry out
impact monitoring during the course of the Works. For regular impact monitoring,
the sampling frequency of at least once in every six-days, shall be strictly
observed at all the monitoring stations for 24-hour TSP monitoring. For 1-hour
TSP monitoring, the sampling frequency of at least three times in every
six-days should be undertaken when the highest dust impact occurs. Before
commencing baseline monitoring, the ET shall inform the IEC of the impact monitoring
programme such that the IEC can conduct on-site audit to ensure accuracy of the
impact monitoring results.
The
specific time to start and stop the 24-hour TSP monitoring shall be clearly
defined for each location and be strictly followed by the operator.
In
case of non-compliance with the air quality criteria, more frequent monitoring,
as specified in the Action Plan in the following section, shall be conducted
within 24 hours after the result is obtained.
This additional monitoring shall be continued until the excessive dust
emission or the deterioration in air quality is rectified.
2.1.7 Event and Action Plan
The
baseline monitoring results form the basis for determining the air quality
criteria for the impact monitoring. The
ET should compare the impact monitoring results with air quality criteria set
up for 24-hour TSP and 1-hour TSP level.
Table 2.2 shows the air quality
criteria, namely Action and Limit (AL) Levels to be used. Should non-compliance of the air quality
criteria occurs, actions in accordance with the Event and Action Plan in Table 2.3 should be carried out.
Table 2.2: Typical
Action and Limit Levels for Air Quality
Parameters |
Action Level |
Limit Level |
24-hr TSP Level in µg/m³ |
For baseline level
£ 200 µg/m³, Action
level = (130% of baseline level + Limit level)/2 For baseline level
> 200 µg/m³, Action level = Limit Level |
260 |
1-hour TSP Level
in µg/m³ |
For baseline level
£ 384 µg/m³, Action
level = (130% of baseline level + Limit level)/2 For baseline level
> 384 µg/m³, Action level = Limit Level |
500 |
Table 2.3: Event
and Action Plan for Air Quality
Event |
Action |
|||||||||
ET |
IEC |
ER |
Contractor |
|||||||
Action Level |
||||||||||
1. Exceedance for one sample |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
||||||
2.
Exceedance for two or more consecutive samples |
1. Identify source; 2. Inform IEC and ER; 3. Advise the ER on the effectiveness of the proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on remedial actions required; 7. If exceedance continues, arrange meeting with IEC and ER; 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial measures; 4. Advise the ET on the effectiveness of the proposed remedial measures; 5. Monitor the implementation of remedial
measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Submit proposals for remedial to ER within 3 working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
||||||
Limit Level |
||||||||||
1. Exceedance for one sample |
1. Identify source, investigate the causes of exceedance and propose remedial measures; 2. Inform ER, Contractor and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial measures; 4. Advise the ER on the effectiveness of the proposed remedial measures; 5. Monitor theimplementation of remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within 3 working days of notification; 3. Implement the agreed proposals; 4.
Amend proposal if appropriate. |
||||||
2. Exceedance for two or more
consecutive samples |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER to discuss the remedial actions to be taken; 7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss amongst ER, ET, and Contractor on the potential remedial actions; 4. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly; 5. Monitor the implementation of remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the Contractor on the remedial measures to be implemented; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion
of work until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under control; 5. Stop the relevant portion of works as determined by the ER until the exceedance is
abated. |
||||||
2.1.8 Mitigation Measures
Appropriate dust suppression measures should be adopted as required under the Air Pollution Control (Construction Dust) Regulation. A control programme can be instigated to monitor the construction process in order to enforce dust controls and modify methods of works where feasible to reduce the dust emission down to acceptable levels. The implementation schedule of the recommended air quality mitigation measures is presented in Appendix A.
2.2 Operational Air Quality Monitoring
With the full implementation of the recommended mitigation measures during operation phase, no adverse air quality impact is anticipated. Operational phase air quality monitoring is considered not necessary.
3. Noise Impact |
3.1 Construction Airborne Noise Monitoring
The
construction noise level shall be measured in terms of the A-weighted
equivalent continuous sound pressure level (Leq). Leq (30 minutes) shall be
used as the monitoring parameter for the time period between 0700 and 1900
hours on normal weekdays. For all other time periods, Leq (5 minutes) shall be
employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary
information for data auditing, statistical results such as L10 and L90 shall
also be obtained for reference. A sample data record sheet is shown in Appendix B.
The ET Leader may modify the data record sheet for this EM&A programme, of
which the format should be agreed by the ER and the IEC.
3.1.2 Monitoring Equipment
As
referred to in the Technical Memorandum (TM) issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
The
ET is responsible for the provision of the monitoring equipment. He shall
ensure that sufficient noise measuring equipment and associated instrumentation
are available for carrying out the baseline monitoring, regular impact
monitoring and ad hoc monitoring. All the equipment and associated
instrumentation shall be clearly labelled.
3.1.3 Monitoring Locations
The noise monitoring locations (refer to Figures 3.1) are summarised in Table 3.1. The
status and locations of noise sensitive receivers may change after issuing this
manual. If such cases exist, the ET
should propose updated monitoring locations and seek agreement from EPD.
Table 3.1: Construction Noise Monitoring
Stations
ID |
ID adopted in EIA |
Description |
Works Area |
NM1 |
TYH |
Tsung Yuen Ha
Village House No. 63 |
BCP |
NM2 |
V2 |
Village House
near |
Lin Ma Hang to Frontier Closed Area |
NM3 |
PY2 |
Ping Yeung Village House (facade facing
northeast) |
Ping Yeung to Wo Keng Shan |
NM4 |
WKS6 |
Wo |
Ping Yeung to Wo Keng Shan |
NM5 |
LT1 |
Village
House, Loi Tung |
|
NM6 |
TTW2 |
Tai Tong Wu Village House 2 |
Sha Tau Kok Rpad |
NM7 |
PKT2 |
Po |
|
NM8 |
TH1 |
Village
House, Tong Hang |
Fanling |
NM9 |
KT3 |
Village House, Kiu Tau Village |
Fanling |
NM10 |
NWP1 |
|
Fanling |
The
status and locations of noise sensitive receivers may change after issuing this
manual. If such case exists, the ET Leader shall propose updated monitoring
locations and seek approval from EPD and agreement from the ER and the IEC
before baseline monitoring commences.
When
alternative monitoring locations are proposed, the monitoring locations shall
be chosen based on the following criteria:
§ Monitoring at sensitive receivers close to
the major site activities which are likely to have noise impacts;
§ Monitoring at the noise sensitive receivers
as defined in the Technical Memorandum; and
§ Assurance of minimal disturbance to the
occupants during monitoring.
The
monitoring station shall normally be at a point 1 m from the exterior of the
sensitive receiver building facade and be at a position 1.2 m above the ground.
If there is problem with access to the normal monitoring position, an
alternative position may be chosen, and a correction to the measurements shall
be made. For reference, a correction of +3 dB(A) shall be made to the free
field measurements. The ET shall agree with the IEC on the monitoring position
and the corrections adopted. Once the positions for the monitoring stations are
chosen, the baseline monitoring and the impact monitoring shall be carried out
at the same positions.
3.1.4 Baseline Monitoring
The
ET shall carry out baseline noise monitoring prior to the commencement of the
construction works. The baseline monitoring shall be carried out daily for a
period of at least two weeks. Before commencing the baseline monitoring, the ET
shall develop and submit to the IEC the baseline monitoring programme such that
the IEC can conduct on-site audit to check accuracy of the baseline monitoring
results.
There
shall not be any construction activities in the vicinity of the stations during
the baseline monitoring.
In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with the ER, EPD and IEC to agree on an appropriate set of data to be used as a baseline reference and submit to the ER and IEC for agreement and EPD for approval.
3.1.5 Impact Monitoring
Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
§ one set of measurements between 0700 and
1900 hours on normal weekdays;
If
construction works are extended to include works during the hours of 1900 –
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods.
Applicable permits under NCO shall also be obtained by the Contractor.
If
a school exists near the construction activity, noise monitoring shall be
carried out at the monitoring stations for the schools during the school
examination periods. The ET Leader shall liaise with the school’s personnel and
the Examination Authority to ascertain the exact dates and times of all
examination periods during the course of the contract.
In
case of non-compliance with the construction noise criteria, more frequent
monitoring, as specified in the Action Plan in Table 3.3,
shall be carried out. This additional monitoring shall be continued until the
recorded noise levels are rectified or demonstrated to be unrelated to the
construction activities.
3.1.6 Event and Action Plan
The Action and Limit (AL) Levels for construction noise are defined in Table 3.2. Should non-compliance of the criteria occurs, action in accordance with the Event and Action Plan in Table 3.3, should be carried out.
Table 3.2 : Typical Action and Limit Levels for Construction Noise
Time Period |
Action |
Limit |
0700-1900 hrs on
normal weekdays |
When one valid documented complaint is received. |
75* dB(A) |
Note: *70 dB(A)
for schools and 65 dB(A) during school examination periods.
If works are to
be carried out during restricted hours, the conditions stipulated in the
Construction Noise Permit (CNP) issued by the Noise Control Authority have to
be followed.
Table 3.3: Event and Action Plan for Construction Noise
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1. Notify ER, IEC and Contractor; 2. Carry
out investigation; 3. Report the results of investigation to the
IEC, ER and Contractor; 4. Discuss with the IEC and Contractor on
remedial measures required; 5. Increase monitoring frequency to check
mitigation effectiveness. |
1. Review the investigation results submitted by
the ET; 2. Review the proposed remedial measures by the Contractor and advise
the ER accordingly; 3. Advise the ER on the effectiveness of the
proposed remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the
Contractor on the remedial measures to be implemented; 4. Supervise the implementation of remedial
measures. |
1. Submit noise mitigation proposals to IEC and
ER; 2. Implement noise mitigation proposals. |
Limit Level |
1. Inform IEC, ER, Contractor and EPD; 2. Repeat measurements to confirm findings; 3. Increase monitoring frequency; 4. Identify source and investigate the cause of
exceedance; 5. Carry out analysis of Contractor’s working
procedures; 6. Discuss with the IEC, Contractor and ER on
remedial measures required; 7. Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional
monitoring. |
1. Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2. Review Contractor’s remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the Contractor on the remedial measures to be implemented; 4. Supervise the implementation of remedial measures; 5. If exceedance continues, consider stopping the
Contractor to continue working on that portion of work which causes the
exceedance until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to IEC and ER within 3 working days of notification; 3. Implement the agreed proposals; 4. Submit further proposal if problem still not
under control; 5. Stop the relevant portion of works as
instructed by the ER until the exceedance is abated. |
3.1.7 Mitigation Measures
The EIA Report has recommended construction noise control and mitigation measures. The Contractor should be responsible for the design and implementation of these measures under the supervision of the ER and monitored by the ET. The implementation schedule of the recommended noise mitigation measures is presented in Appendix A.
3.2 Operational Traffic Noise Monitoring
3.2.1 Monitoring Requirements
The
ET Leader shall prepare and deposit to EPD, at least 6 months before the
operation of the works under the Project, a monitoring plan for the purpose of
assessing the accuracy of traffic noise predictions by comparing the project
noise impact predictions with the actual impacts. The monitoring plan shall
contain monitoring locations, monitoring schedules, methodology of noise
monitoring including noise measurement procedures, traffic counts and speed
checks, and methodology of comparison with the predicted levels. The ET Leader
shall implement the monitoring plan in accordance with the deposited monitoring
plan unless with prior justification. Monitoring details and results including
the comparison between the measured noise levels and the predicted levels shall
be recorded in a report to be deposited with EPD within one month of the
completion of the monitoring. The report
shall be certified by the ET Leader and verified by IEC and agreed with CEDD
before deposit with EPD.
3.2.2 Monitoring Parameters
The
traffic noise levels shall be measured twice at 6-month intervals within the
first year upon completion
of the Project. Measurements shall be made in terms of the A-weighted L10 over
peak periods, other metrics like Leq, L90
and Lmax may be used for comparison.
3.2.3 Monitoring Equipment
Monitoring equipment to be used shall be the same as that specified in Section 3.1.2. That is, sound level meters in compliance with the International Electro-technical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications shall be used for carrying out the traffic noise monitoring. Calibration procedures and other measurement conditions shall also be in the same as stated in Section 3.1.2.
Noise
measurements should not be made in the presence of fog, rain, wind with a
steady speed exceeding 5m/s or wind with gusts exceeding 10m/s. The wind speed
shall be checked with a portable wind speed meter capable of measuring the wind
speed in m/s.
The
ET Leader is responsible for the provision of the monitoring equipment. He
shall ensure that sufficient noise monitoring equipment and associated
instrumentation are available for carrying out the baseline monitoring, regular
impact monitoring and ad hoc monitoring. All the equipment and associated
instrumentation shall be clearly labelled.
3.2.4 Monitoring Locations
Three
designated monitoring stations, OM1 to OM3 are selected for operational noise
monitoring. Figure 3.2
describes the operational noise monitoring locations, which are also depicted
in Table
3.4.
The status and locations of noise sensitive receivers may change after this
Manual is issued. If such cases exist, the ET Leader shall propose updated
monitoring locations and seek approval from ER & IEC and agreement from EPD
of the proposal.
Table 3.4: Operational Noise Monitoring Stations
ID |
ID adopted in EIA |
Description |
Works Area |
OM1 |
WKS4 |
Wo |
Ping Yeung to Wo Keng Shan |
OM2 |
LT4 |
Village
House, Loi Tung |
Sha Tau Kok |
OM3 |
TH2 |
Village
House, Tong Hang |
Fanling |
The
monitoring locations shall be selected according to the following criteria:-
§
they should be at
NSRs in the vicinity of recommended direct technical remedies; preferably, there
should be one representative monitoring locations near each types of noise
screening element (i.e. vertical barrier, cantilever barrier and enclosure);
§
selected monitoring
locations should enable monitoring to be done twice within one year after implementation
of the mitigation measures during operation of the proposed road
When
alternative monitoring locations are proposed, the monitoring locations shall
be chosen based on the following criteria:-
§
alternative location
shall be similarly exposed to potential noise impacts;
§
it shall be close to
the noise sensitive receivers; and
§
shall be located so
as to cause minimal disturbance to the occupants.
3.2.5 Compliance Monitoring
The
operational noise monitoring shall be carried out at a distance of 1 m from the
openable window and 1.2 m above the floor level of the noise sensitive
receivers identified. The ET Leader shall agree with the IEC on any necessary
corrections adopted.
Noise
monitoring shall be carried out at all the designated traffic noise monitoring
stations. The following is an initial guide on the traffic noise monitoring
requirements during the operational phase:-
(a) one
set of measurements at the morning traffic peak hour on normal weekdays;
(b) one
set of measurements at the evening traffic peak hour on normal weekdays;
(c) a
concurrent census of traffic flow and percentage heavy vehicle shall be
obtained for far-side and near-side of the road and the existing road network
in the vicinity of each measuring point;
(d) average
vehicle speed estimated for far-side and near-side of the road and the existing
road network in the vicinity of each measuring point; and
(e) the
two sets of monitoring data should be obtained within the first year of
operation.
Measured
noise levels should be compared with predicted noise levels by applying
appropriate conversion corrections to allow for the traffic conditions at the
time of measurement. Operational noise field data sheet should be designed
during submitting the monitoring plan.
The
measured/monitor noise levels shall be compared with the predicted results and
the predicted traffic flow conditions (calculated noise levels based on
concurrent traffic census obtained). In case discrepancies are observed,
explanation should be given to justify the discrepancies. Operational EM&A reports shall be
certified by the ET Leader and verified by the IEC before sending to EPD.
4.1
Construction Water Quality Monitoring
4.1.1
Water
Quality Parameter
Monitoring for Dissolved Oxygen (DO), Dissolved Oxygen Saturation (DO%), temperature, pH, turbidity, water depth and suspended solid (SS) should be undertaken at designated monitoring locations. All parameters should be measured in-situ whereas SS should be determined by the laboratory. DO should be presented in mg/L and in % saturation.
Other relevant data should also be recorded, including monitoring location / position, time, weather conditions and any special phenomena or work underway at the construction site.
4.1.2
Sampling
Procedure and Monitoring Equipment
Water
samples for all monitoring parameters should be collected, stored, preserved
and analyzed according to Standard Methods, APHA 21st ed. and/or methods agreed
by EPD. In-situ
measurements at monitoring locations including DO, temperature, pH, turbidity and
water depth shall be collected by equipment with the characteristics and
functions listed in the following sections. A
sample data record sheet is shown in Appendix B for reference.
The following equipment and facilities should be provided by the ET and used for the monitoring of water quality impacts:
4.1.2.1 Dissolved Oxygen and Temperature Measuring Equipment
DO and water temperature should be measured in-situ by a DO/ temperature meter. The instrument should be portable and weatherproof using a DC power source. It should have a membrane electrode with automatic temperature compensation complete with a cable. The equipment should be capable of measuring:
§
a DO level in the
range of 0-20 mg/l and 0-200% saturation; and
§
a temperature of
between 0 and 45 degree Celsius.
4.1.2.2 pH Measuring Instrument
A portable pH meter capable of measuring a
range between 0.0 and 14.0 should be provided to measure pH under the specified
conditions accordingly to the Standard Methods, APHA.
4.1.2.3 Turbidity Measurement Instrument
The instrument should be portable and weatherproof using a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0-1000 NTU.
4.1.2.4 Water Depth Detector
A portable, battery-operated echo sounder should be used for the measurement of water depth at each designated monitoring station. The unit would be either handheld or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
4.1.2.5 Calibration of In-Situ Instruments
All in-situ monitoring instruments should be calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use, and subsequently re-calibrated at 3 monthly intervals throughout all stages of the water quality monitoring programme. Responses of sensors and electrodes should be checked with certified standard solutions before each use.
Wet bulb calibration for a DO probe should be carried out before measurement at each monitoring station. A zero check in distilled water should be performed with the turbidity probe at least once per monitoring day. The probe should then be calibrated with a solution of known NTU. In addition, the turbidity probe should be calibrated at least twice per month to establish the relationship between turbidity readings (in NTU) and levels of suspended solids (in mg/L).
For
the on-site calibration of field equipment, the BS 127: 1993, Guide to Field
and On-Site Test Methods for the Analysis of Waters should be observed.
Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment should also be made available so that monitoring could proceed uninterrupted even when some equipment is under maintenance, calibration etc.
4.1.2.6 Sample Containers and Storage for Suspended Solids Measurement
A water sampler comprises a transparent PVC cylinder, with a capacity of not less than 2 litres, and could be effectively sealed with latex cups at both ends should be used. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (Kahlsico Water Sampler or an approved similar instrument).
Water samples for SS analysis should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4oC without being frozen), delivered to the laboratory, and analysed as soon as possible after collection.
4.1.3
Laboratory Measurement/Analysis
Analysis of suspended solids should be carried out in a HOKLAS or other accredited laboratory. Water samples of about 1L should be collected at the monitoring stations for carrying out the laboratory suspended solids determination. The SS determination work should start within 24 hours after collection of the water samples. The SS analyses should follow the standard method APHA 2540D with a detection limit of 1mg/L as described in APHA Standard Methods for the Examination of Water and Wastewater, 21st Edition, unless otherwise specified.
Additional duplicate samples may be required by EPD for inter laboratory calibration. Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required. If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD. In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes. The laboratory should prepare to demonstrate the programmes to EPD or his representatives when requested.
4.1.4
Monitoring Locations
The proposed water quality monitoring stations are shown in Table 4.1 and Figure 4.1. The monitoring stations proposed in this section are indicative subject to further review before construction phase. The final locations and number of the monitoring points should be agreed with EPD at least 2 weeks before undertaking any works. The status and locations of water sensitive receivers may change after issuing this Manual. If such case exists, the ET Leader should propose updated monitoring locations and seek approval from the IEC and EPD.
It is proposed to monitor the water quality at four locations closest to the construction works. At each of the water quality monitoring location, one or more control stations are also proposed to be monitor within the same water courses as the impact monitoring stations but is outside the area of influence of the construction works as far as practicable.
Table 4.1: Construction Water Quality Monitoring Stations
ID |
Description |
Co-ordinates |
|
Easting (m) |
Northing (m) |
||
WM1 |
Downstream of Kong Yiu
Channel |
833668.635 |
845371.097 |
WM1 - Control |
Upstream of Kong Yiu
Channel |
834185.480 |
845916.662 |
WM2A |
Downstream of River |
834132.193 |
844432.910 |
WM2A - Control |
Upstream of River |
835205.329 |
844200.151 |
WM2B |
Downstream of River |
835434.744 |
843394.606 |
WM2B - Control |
Upstream of River |
835845.878 |
843343.625 |
WM3 |
Downstream of River |
836323.622 |
842404.977 |
WM3 - Control |
Upstream of River |
836763.419 |
842425.507 |
WM4 |
Downstream of Ma Wat
Channel |
833840.783 |
838344.842 |
WM4 – Control A |
Kau Lung Hang Stream |
834038.937 |
837668.995 |
WM4 – Control B |
Upstream of Ma Wat Channel |
833769.123 |
837406.936 |
When alternative monitoring locations are proposed, they should be chosen based on the following criteria:
§
at locations close
to and preferably at the boundary of the mixing zone of the major site
activities as indicated in the EIA report, which are likely to have water
quality impacts;
§
close to the
sensitive receptors which are directly or likely to be affected;
§
for monitoring
locations located in the vicinity of the sensitive receptors, care should be
taken to cause minimal disturbance during monitoring;
§
two or more control
stations which should be at locations representative of the project site in its
undisturbed condition. Control stations should be located, as far as is
practicable, both upstream and down stream of the works area.
Control stations are necessary to compare the water quality from potentially impacted sites with the ambient water quality. Control stations shall be located within the same body of water as the impact monitoring stations but shall be outside the area of influence of the works and, as far as practicable, not affected by any other works. The ET should agree with EPD on all the monitoring stations.
Duplicate in-situ measurements and samples collected from each independent monitoring event are required for all parameters to ensure a robust statistically interpretable dataset.
Baseline conditions for the water quality of the sensitive nature of the rivers/streams shall be established and agreed with EPD prior to the commencement of works. The purposes of the baseline monitoring are to establish ambient conditions prior to the commencement of the construction works and to demonstrate the suitability of the proposed impact, control and reference monitoring points.
The baseline conditions shall normally be established by measuring the water quality parameters specified in Section 4.1.1. The measurements shall be taken at all designated monitoring stations including control points, 3 days per week, for at least 4 weeks prior to the commencement of construction works.
There shall not be any construction activities over water in the vicinity of the points during the baseline monitoring.
In exceptional case when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall seek approval from the IEC and EPD on an appropriate set of data to be used as baseline reference.
Baseline monitoring schedule shall be faxed to EPD 1 week prior to the commencement of baseline monitoring. The interval between 2 sets of monitoring shall not be less than 36 hours.
During construction period, impact monitoring should be undertaken at all monitoring stations three working days per week, with sampling /measurement. The interval between two sets of monitoring should not be less than 36 hours except where the Action and/or Limit levels is/are exceeded, in which case the monitoring frequency should be increased.
Two consecutive measurements of DO concentration (mg/L), DO saturation (%) and turbidity (NTU) should be taken in-situ according to the stated sampling method. Where the difference in value between the first and second measurement of DO or turbidity parameters is more than 25% of the value of the first reading, the reading should be discarded and further readings would be taken. Water samples for SS (mg/L) measurements should be collected at the same depths. Duplicate water samples should be taken and analyzed.
In addition to the above in-situ measurements, water temperature and pH should be determined at all monitoring stations at the same depths, as specified above. Note that in addition to the water depth, monitoring location/position, time, weather conditions and any special phenomena should be recorded.
The Action and Limit (AL) Levels for water quality are defined in Table 4.2. The actions in accordance with the Event and Action Plan in Table 4.3 should be carried out if the water quality assessment criteria are exceeded at any designated monitoring points.
Table 4.2: Typical Action and Limit Levels for Water Quality
Parameters |
Action Level |
Limit Level |
DO in mg/l |
5 percentile of
baseline data |
4 mg/L or 1
percentile of baseline data |
SS in mg/l |
95 percentile of
baseline data or 120% of upstream control station of the same day |
99 percentile of
baseline data or 130% of upstream control station of the same day |
Turbidity in NTU |
95 percentile of
baseline data or 120% of upstream control station of the same day |
99 percentile of
baseline data or 130% of upstream control station of the same day |
Notes: 1. For DO measurement,
non-compliance occurs when monitoring result is lower than the limits.
2. For
SS and turbidity, non-compliance of water quality results when monitoring
results is higher than the limits.
3. All
the figures given in the table are used for reference only and the EPD may
amend the figures whenever necessary.
Table 4.3: Event and Action Plan for Water Quality
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action level being exceeded by one sampling day |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
reasons for non-compliance and sources of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; 6. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3.
Assess the effectiveness of the implemented mitigation measures |
1. Discuss
with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; 3. Assess
the effectiveness of the implemented mitigation measures |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER; 6. Implement
the agreed mitigation measures. |
Action Level being exceeded by more
than two consecutive sampling days |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
reasons for non-compliance and sources of impact; 3. Inform
IEC and Contractor; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC and Contractor; 6. Ensure
mitigation measures are implemented; 7. Prepare
to increase the monitoring frequency to daily; 8. Repeat
measurement on next day of exceedance. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3. Assess
the effectiveness of the implemented mitigation measures |
1.
Discuss with IEC on the proposed mitigation measures; 2. Make
agreement on the mitigation measures to be implemented; 3. Assess
the effectiveness of the implemented mitigation measures |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2.
Rectify unacceptable practice; 3. Check
all plant and equipment; 4.
Consider changes of working methods; 5. Discuss
with ET and IEC and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures. |
Limit Level being exceeded by one
sampling day |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
reasons for non-compliance and sources of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; 7. Increase
the monitoring frequency to daily until no exceedance of Limit Level. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3. Assess
the effectiveness of the implemented mitigation measures |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4.
Assess the effectiveness of the implemented mitigation measures |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET, IEC and ER and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures. |
Limit level being exceeded by
more than one consecutive sampling days |
1. Repeat
in-situ measurement to confirm findings; 2. Identify
reasons for non-compliance and sources of impact; 3. Inform
IEC, Contractor and EPD; 4. Check
monitoring data, all plant, equipment and Contractor’s working methods; 5. Discuss
mitigation measures with IEC, ER and Contractor; 6. Ensure
mitigation measures are implemented; 7. Increase
the monitoring frequency to daily until no exceedance of Limit Level for two
consecutive days. |
1. Discuss
with ET and Contractor on the mitigation measures; 2. Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3. Assess
the effectiveness of the implemented mitigation measures. |
1. Discuss
with IEC, ET and Contractor on the proposed mitigation measures; 2. Request
Contractor to critically review the working methods; 3. Make
agreement on the mitigation measures to be implemented; 4. Assess
the effectiveness of the implemented mitigation measures; 5.
Consider and instruct, if necessary, the Contractor to slow down or to stop
all or part of the construction activities until no exceedance of Limit
Level. |
1. Inform
the ER and confirm notification of the non-compliance in writing; 2. Rectify
unacceptable practice; 3. Check
all plant and equipment; 4. Consider
changes of working methods; 5. Discuss
with ET, IEC and ER and propose mitigation measures to IEC and ER within 3
working days; 6. Implement
the agreed mitigation measures; 7. As
directed by the ER, to slow down or to stop all or part of the construction
activities. |
4.1.8 Mitigation Measures
The implementation schedule of the recommended water quality mitigation measures is presented in Appendix A.
4.2 Operational Water Quality Monitoring
With the full implementation of the recommended mitigation measures during operation phase, no adverse water quality impact is anticipated. Operation phase water quality monitoring is not considered necessary.
5. Sewerage and Sewage Treatment Implications |
5.2
Sewerage and Sewage
Treatment Implications during Construction Phase
The sewage generated during the construction
stage from the on-site workers will be collected in chemical toilets and
disposed of off-site. Therefore, no
sewerage impacts are expected from the site during the construction phase. As such, environmental monitoring and audit
of the sewerage system is considered not required.
5.2.1
Mitigation Measures
The implementation schedule of the relevant mitigation measures is presented in Appendix A.
Waste management would be the contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements. The recommended mitigation measures should form the basis of the site Waste Management Plan to be developed by the Contractor in the construction phase.
6.2
Construction Phase Waste
Management Implications
During construction phase, regular site inspection
as part of the EM&A procedures should be carried
out to determine if wastes are being managed in accordance with approved
procedures and the site Waste Management Plan. It should look at different
aspects of waste management including waste generation, storage, recycling,
treatment, transport and disposal.
6.2.1
Mitigation Measures
The implementation schedule of the recommended waste management mitigation measures is presented in Appendix A.
Desktop study and site appraisal
have been conducted during EIA study and potential land contamination hotspots
was not identified in the Study Area.
7.2
In view of the desktop review results and the site reconnaissance findings, bulk excavation of soil for land remediation is not expected. As such, any environmental monitoring in relation to land remediation is not required.
On
the other hand during construction phase, land contamination monitoring could
be carried out in the form of regular site inspection. All related procedures
and facilities in handling or storage of chemicals and chemical wastes should be
audited regularly to make sure they are in order and intact and, reported in
the EM&A reports as such.
The implementation schedule of the recommended land contamination mitigation measures is presented in Appendix A.
The
ecological impact assessment in the EIA Report has evaluated the ecological
consequences of the proposed Project and concluded that the overall impacts would
be of minor significance with the implementation of mitigation measures.
The
major mitigation measures proposed for the identified ecological impact include
woodland compensation, wetland compensation and transplanting of floral species
of conservation interest. The proposed ecological mitigation measures to
avoid, minimize and compensate the identified impacts arising from the proposed
project should be checked as part of the environmental monitoring and audit
programme during the construction phase.
8.2 Ecological Mitigation Measures
Mitigation measures were designed in accordance with Annex
16 of the EIAO-TM which states the general policy and guidance in planning of
ecological measures. The implementation schedule of the
recommended mitigation measures is presented in Appendix A.
The major ecological mitigation measures proposed include provision of woodland
compensation area (approx 18.6 ha is proposed), provision of wetland
compensation area (more than 1.4 ha is proposed) and transplanting flora
species of conservation interest. Mitigation measures for noise, water quality
and landscape impact proposed in EIA report Sections 4, 5 and 11 respectively are also applicable to
minimize the disturbance on ecology integrity.
8.3
Environmental Monitoring and Audit
8.3.1
Environmental
Audit
The implementation of mitigation measures stated in Section 8.2 of
this Manual shall be routinely audited, during the implementation of the
Project. Requirements of the environmental audit are given in Section 12 of this Manual.
Implementation of the recommended ecological mitigation measures, detailed
in Section 15 of the EIA report and Appendix A of this Manual, shall be examined
during the routine environmental audit.
8.3.2
Environmental
Monitoring
8.3.2.1
Monitoring
on Transplanting of Flora Species of Conservation Interest
According to the EIA, two species of conservation interest Euonymus kwangtungensis and Aquilaria sinensis are required to be transplanted to undisturbed areas. As the condition (health and abundance) of plants recorded in the EIA stage may be varied in the detailed design stage, conducting a vegetation survey to confirm the condition of the affected plants (not covered by ETWB TCW 3/2006) prior to the commencement of the construction works is recommended. Suitable reception sites shall also be identified in the vegetation survey report for review by EPD and AFCD. The scope of the vegetation survey shall include the following:
§ The checking and updating the number, health condition and location of the floral species of conservation interest identified (Euonymus kwangtungensis, and seedlings and individual trees of Aquilaria sinensis suitable for transplanting) in the EIA;
§ Preparation of an updated location plan showing the individuals identified during the vegetation survey;
§ Identification of suitable reception site(s) in retained woodland habitat within the project limit for the shrub species Euonymus kwangtungensis;
§ Identification of suitable reception site(s) within the proposed compensatory woodland; or temporary transit nursery for seedlings/individuals trees of the tree species Aquilaria sinensis;
§ Recommendation of an implementation programme of transplanting.
The
transplanting shall be monitored by a suitably qualified ecologist / botanist
appointed as a member of the Environmental Team. The transplanted individuals
shall be monitored at least twice a month during the first year and once a
month for the remaining of the planting period of the compensation woodland.
The parameters to be monitored shall include the health condition and survival
rate of the transplanted species. Any
observations and recommendations should be reported in periodic EM&A
reports.
8.3.2.2
Monitoring
on Woodland Compensation
In order to mitigate the ecological impact
of loss of 6.2ha of woodland habitats, a Woodland Compensation Area (WLCA) of
about 18.6 ha is proposed on existing hillside grassland and shrubland.
Location of the WLCA is illustrated in Figures 8.1. A Woodland Compensation Plan is
presented in Appendix
9.4 of the EIA Report with an aim to form the basis to guide the
implementation of the proposed woodland mitigation.
According to the proposed Woodland
Compensation Plan, the planting works will be carried out in two phases, viz.
Initial Planting Phase and Enhancement Planting Phase, which would take about 5
years and 3 years of time respectively.
The second phase Enhancement Planting Phase could commence after the
implementation of the first Initial Planting Phase for 3 years or any earlier
time as agreed with AFCD.
Apart from the standard inspection and
establishment works for landscape softworks,
a 6-year ecological monitoring programme covering both initial and
enhancement planting phases is proposed. The necessity for further monitoring
would be reviewed after the 6-year ecological monitoring programme. The
monitoring of planting includes parameters of: general health condition and
survival rate; with establishment works would include basic replacement of dead
plants, weeding and watering. Due to the large size of the WLCA, monitoring is
proposed to be carried out in inspection walk and quadrat sampling. Monitoring
in inspection walks aims to observe the overview/ progress of the planting
within the whole WLCA; while monitoring in quadrats aims to collect
quantitative information.
Monitoring Requirements
The monitoring shall be conducted by the Environmental
Team (ET) and supervised by a qualified botanist/ecologist (Project
Botanist/Ecologist) of the ET.
The routes of the general inspection walk
should be selected to cover all representative areas of the WLCA as far as possible.
The general health condition (good/fair/poor/dead) and survival (%) of individual
species of planted trees and shrubs
will be recorded by direct observation.
Nine fixed 20m x 20m quadrats are proposed
for quantitative monitoring. These quadrats shall be evenly distributed
throughout the WLCA. Parameters to be measured within quadrats include health
condition (good/fair/poor/dead), and survival rate (%) of individual
species. Proposed locations for the
fixed quadrats are shown in Figure 8.1.
The frequency of the monitoring is proposed
to be bi-monthly during the first year of the initial planting phase and shall
be reduced to quarterly from the second year. Change of monitoring frequency
shall be advised by the Project Ecologist/Botanist and approved by
Environmental Protection Department and Agriculture, Fisheries and Conservation
Department.
The Trigger and
Action Levels for Monitoring and Action Plan of the WLCA are presented in Table 8.1.
Table 8.1: Trigger
and Action Levels for Monitoring and Action Plan of the WLCA
Parameters |
Trigger and Action Level |
Action Plan |
General Health Condition |
Trigger Level: % of individual plant species in poor health condition >20% |
- the ET should inform Contractor and IEC immediately; - identify the cause(s) of the exceedance; - advise Contractor the necessity of replanting. |
Action Level: % of individual plant species in poor health condition >30% |
- the ET should inform Contractor and IEC immediately; - identify the cause(s) of the exceedance; - advise remedial action and work out solution including change of species in re-planting, re-soiling of the target areas; and seek acceptance from AFCD; - Once the remedial action has been accepted by AFCD, the Contractor should implement the remedial action. |
|
Survival of Plants |
Trigger Level: Survival rate of individual plant species < 80% |
- the ET should inform Contractor and IEC immediately; - identify the cause(s) of the exceedance; - advise Contractor the necessity of replanting. |
Action Level: Survival rate of individual plant species < 70% |
- the ET should inform Contractor and IEC immediately; - identify the cause(s) of the exceedance; - advise remedial action and work out solution including change of species in re-planting, re-soiling of the target areas; and seek acceptance from AFCD; - Once the remedial action has been accepted by AFCD, the Contractor should implement the remedial action. |
8.3.2.3
Monitoring
on Wetland Compensation
In order to mitigate the ecological impact
of loss of 1.4 ha freshwater wetland, more than 1.4 ha Wetland Compensation Area
(WCA) will be created near Nga Yiu Ha. Location of the WCA is illustrated in Figure 8.2 while
a conceptual plan is presented in Figure 8.3.
Details of the Wetland Compensation and the
monitoring plan would be formulated and provided under a Habitat Creation and
Management Plan during the detailed design stage. According to the proposed
plan, the programme will comprise implementation, establishment and maintenance
stages. Ecological monitoring at implementation and establishment periods will
be conducted to cover the ecological attributes. Implementation of the wetland
will commence within the construction phase after completion of the
construction works at Ping Yeung Section. Monitoring on the WCA will be conducted
in implementation and establishment stages. The monitoring shall be conducted
by the Environmental Team (ET) and supervised by a qualified ecologist (Project
Ecologist) who will be formed as a member of the ET. After establishment stage,
AFCD will be responsible of the maintenance and the monitoring works, which is
not covered in this manual.
Pond fish culture resources
and activities were not identified within
the Study Area. With the effluent control measures are
properly in place, the Project is unlikely to have indirect impacts on
the pond fish culture resources and activities in the NWNT area. Therefore, no EM&A
programme for fisheries impact is considered necessary.
The
EIA has recommended that EM&A for landscape and visual resources be
undertaken during both the construction and operation phases of the Project.
The implementation and maintenance of landscape, visual and glare mitigation
measures (see
Appendix A) should be checked to ensure that they are
properly implemented and that the potential conflicts between the proposed
measures and any other project works and operational requirements are resolved
at the earliest practical date and without compromising the intention of the
mitigation measures.
10.2
Construction Phase and Initial Operation Phase
A specialist landscape sub-contractor should
be employed by the Contractor for the construction of the landscape works and
subsequent maintenance operations during a 12-month establishment period. A qualified
landscape architect of the ET should monitor the works of the specialist
Landscape sub-contractor, including both hard and soft landscape works.
A tree survey update should be prepared by
the Contractor for submission to DLO prior to commencement of construction, and
for the purpose of protecting the retained/ preserved trees by the Project, if
any. Removal of existing trees should be minimised.
All measures undertaken by both the
Contractor and the specialist landscape sub-contractor during the construction phase
and establishment period (i.e. the first 12 months of operation phase) will be
audited by a qualified landscape architect of the ET, to ensure compliance with
the aims of the proposed measures. Site inspection should be undertaken at
least once per month throughout the construction phase and establishment
period.
The broad scope of the site inspection to be
undertaken by the qualified landscape architect is detailed below. For a detailed
checklist refer to Table
10.1.
§
To check the extent
of the agreed works areas regularly during the construction phase. Any trespass
by the Contractor outside the limits of the work areas, including any damage to
existing trees should be reported in the audit report;
§
To review the
progress of the engineering works regularly to identify the earliest practical
opportunities for the landscape works to be undertaken;
§
To check if the
existing trees and vegetation within the project site boundary which are not
affected by the construction works are retained and protected;
§
To review and
confirm that the methods of protection of the existing vegetation proposed by
the Contractor are acceptable and properly implemented;
§
To check if the
preparation, lifting transport and re-planting operations for any transplanted
trees are undertaken in accordance with the relevant guidelines;
§
To check if the Landscape
works are carried out in accordance with the contract specifications;
§
To check if the
planting of new trees, shrubs, groundcover, climbers, ferns, grasses and other
plants, together with the replanting of any transplanted trees are carried out
properly and within the right season; and
§
To check if
necessary horticultural operations and replacement planting are undertaken
throughout the establishment period to ensure the healthy establishment and
growth of both transplanted trees and all newly established plants.
Table 10.1: Detailed
Checklist for Implementation of Landscape Mitigation Measures during the Construction
Phase / Establishment Period
Measures |
|
CM1 |
Tree Protection and Preservation - Trees/ woodland
within the works area will be protected and preserved during the detailed
design stage and construction phase |
CM2 |
Tree Transplantation – Should removal of trees be
unavoidable due to construction impacts, trees will be transplanted where
technically feasible.(3) |
CM3 |
Decorative Screen Hoarding - Decorative screen
hoarding will be erected along areas of the construction works site boundary
where the works site borders publically accessible routes and/or is close to
visually sensitive receivers (VSRs) to screen undesirable views of the works
site. It is proposed that the screening be compatible with the surrounding
environment and where possible, non-reflective, recessive colours be used. |
CM4 |
Light Control – Construction and night time lighting
glare will be controlled to minimize glare impact to adjacent VSRs during the
construction stage. |
CM5 |
Topsoil reuse - Excavated topsoil should be conserved
for re-use by the Project or other projects. |
CM6 |
Watercourse Impact Mitigation - Where watercourses
are anticipated to be unavoidably affected, for natural/ semi-natural
watercourses, these will be modified to achieve a natural appearance similar
to existing. A proposed Wetland Compensatory Area is also included within the
Project Site and this will accommodate the natural watercourse currently
existing in the proposed area. For channelized watercourses these will be modified
to match the existing and some additional enhancement planting should be
implemented to upgrade these channels. Bridges will be used to minimise the necessity of
watercourse modification, and box culverts will also be used to protect
watercourses where necessary. |
OM1 |
Detailed Design Considerations – Detailed design of
development components should reduce landscape footprint and visibility of
structures. The area allowed for any development components should be reduced
to a practical minimum. |
OM2 |
Aesthetically Pleasing Design – The form, textures,
finishes and colours of the proposed development components should be
compatible with the existing surroundings. Light earthy tone colours such as
shades of green, shades of grey, shades of brown and off-white may be
utilised where technically feasible to reduce the visibility of the
development components, including all roadwork, buildings and noise barriers
etc. To further improve visual amenity, natural building materials such as
stone and timber, should be preferably adopted for architectural features,
where technically feasible. |
OM3 |
Compensatory Planting - All compensatory planting of
trees is to be carried out in accordance with ETWB TCW No. 03/2006. Section
9 (Ecology) of the EIA Report contains further details of the compensatory
planting specifically for woodland. A total woodland compensation area of
18.6 ha is proposed. In view of the maturity of the secondary woodland
impacted, a higher compensation ratio is proposed and details can be found in
the proposed Woodland Compensation Plan in Appendix
9.4. For key LRs containing substantial numbers of affected trees, Table 11.15a of
the EIA Report gives an approximation of the number of trees to be planted to
compensate for the trees felled in each of these key LRs. Some compensatory shrub and ground cover planting
will also be provided. Space is to be allowed on both sides of the associated
road works, on the peripheries of both BCP and the Middle Ventilation
building for such planting. This area of compensatory shrub and ground cover
planting is approximately 21 ha in size over the whole project area. In addition, a Wetland Compensation Area (WCA) is
proposed to compensate for some wet areas of farmland and shrubby grassland
on lowland Section 9 (Ecology) contains further details of the WCA with Figure 9.28 of the EIA Report
showing a conceptual plan of the area. Details of the Wetland Compensation
Plan (WCP) would be formulated and provided under a Habitat Creation and
Management Plan during the detailed design stage. |
OM4 |
Buffer Tree Planting – Tree planting shall be
provided to screen the proposed structures and associated facilities. In
addition, the compensatory shrub and ground cover planting detailed in OM3
will provide screening and improve compatibility with the surrounding
environment.. |
OM5 |
Aesthetic Improvement Planting-Viaduct Structure –
Planters will be provided for trailer planting to soften the hard, straight edges
of the viaduct. Where space allows for planters, climbers are proposed to
cover vertical, hard surfaces of the piers. |
OM6 |
Aesthetic Improvement Planting-Under Viaduct – Shade
tolerant plants will be planted, where light is sufficient, to improve aesthetic
value of areas under viaducts. |
OM7 |
Landscaped Slope – Where existing hillside slopes are
anticipated to be modified (eg cut slope at the portals of the tunnel
sections and embankments along the alignment) the final slope surface will be
landscaped by hydroseeding, tree or shrub planting where slope gradient
allows. |
OM8 |
Green Roof – Green roofing should be established on
proposed buildings to reduce exposure to untreated concrete surfaces and
mitigate visual impact to VSRs at high levels. |
OM9 |
Vertical Greening – Vertical planting should be
established to soften the hard, vertical surfaces of the proposed development
components. These components will
include walls of administration and ventilation buildings, retaining walls
and road abutments. |
OM10 |
Roadside Amenity Planting – Roadside amenity planting
should be provided, to enhance the landscape and visual quality of the
existing and proposed transport routes and car parks. |
OM11 |
Reinstatement – Certain areas unavoidably disturbed
by the Project will be reprovisioned. The Chuk Yuen Village within the BCP
area will be re-sited to a designed location before commencement of the
Project. Further details on the ‘Re-site of Chuk Yuen Village’ are discussed
in Section 11.8 of the EIA Report. Existing farmland, rural built/open storage areas and
industrial/factory areas will not be reinstated but such areas affected
should be conditioned to suit future land use. For reinstatement involving
planting measures, refer to other mitigation measures e.g. for woodland/shrubby
grassland/vegetated slopes, see CM1, CM2, OM3, OM7. For watercourse, see CM6. |
OM12 |
Light Control – Street and night time lighting glare
will be controlled to minimize glare impact to adjacent VSRs during the
operation stage. |
OM13 |
Reprovisioned LCSD Garden - The Open Space of Wo Keng
Shan public garden falls within the Project Site and will be reprovisioned to
reprovide the amenities of the garden on a one to one basis e.g. existing
trees, benches etc will be re-provided in the new garden. The proposed location of the reprovisioned garden is
near the existing location and shown on Figure 10.5 of this Report
and this is subject to confirmation by CEDD and LCSD. |
The landscape mitigation
measures are shown in Figures
10.1-10.7. In the event of non-compliance
the responsibilities of the relevant parties are detailed in the Event/ Action
Plan provided on Table 10.2.
Table 10.2: Event and Action Plan for Landscape and Visual Monitoring during Construction and Operational Phases
Action level |
Environmental Team (ET) |
Independent Environmental Checker (IEC) |
Contractor |
Non-conformity on one occasion |
1. Identify source 2. Inform the IEC and the Contractor 3. Discuss remedial actions with the IEC and the
Contractor 4. Monitor remedial actions until rectification has been
completed |
1.
Check report 2.
Check the
Contractor’s working method 3.
Discuss with the
ET and the Contractor on practical remedial measures 4.
Advise ER on
effectiveness of proposed remedial measures 5.
Check
implementation of remedial measures. |
6.
Amend working
methods 7.
Rectify damage
and undertake any necessary replacement |
Repeated Non-conformity |
8.
Identify source 9.
Inform the IEC
and the Contractor 10. Increase monitoring frequency 11. Discuss remedial actions with the IEC and the
Contractor 12. Monitor remedial actions until rectification has been
completed 13. If non-compliance stops, cease additional monitoring |
14. Check monitoring report 15. Check the Contractor’s working method 16. Discuss with the ET and the Contractor on practical
remedial measures 17. Advise the ER on effectiveness of proposed remedial
measures 18. Monitor the implementation of remedial measures |
19. Amend working methods 20. Rectify damage and undertake any necessary
replacement |
The cultural heritage impact assessment in the EIA Report has evaluated the potential cultural heritage impacts of the Project and recommended appropriate mitigation measures to avoid and minimize the identified impacts arising from the construction of the Project. As part of the EM&A requirements, the following EM&A programme should be implemented prior to and during construction stage of the Project.
As there will be no impact during the operation of the Project, no EM&A programme will be required during the operation phase.
11.2.1 Built Heritage
11.2.1.1 Photographic and Cartographic Records
Mitigation
measures in the form of detailed photographic and cartographic recordings are
recommended to be conducted on the sixteen sites of the directly impacted
graves, built structures and historical/cultural landscape features in order to
preserve them in record prior to their removal/relocation. These directly
impacted built heritage features include thirteen graves (GR01, GR02, GR05, GR06, GR08, GR10, GR13,
GR15, GR16, GR17, GR18, GR19, GR20), two built structures (BS64 and BS65) and one
historical/cultural landscape feature (LF08).
Their details are listed in Table 11.1:
Table 11.1: Impacted Built Heritage that Require Detailed Photographic and Cartographic Recordings
Site Code |
Site Name |
Relevant
Project Sections |
Reference
Figures |
Graves |
|||
GR01 |
Group of Law Clan Graves (4 Nos.) |
BCP Section |
Figure 12.2.1 of EIA Report |
GR02 |
Group of Tang Clan Graves (5 Nos.) |
BCP Section |
Figure 12.2.1 of EIA Report |
GR05 |
Fu Grave |
Section between Ling Ma Hang and Frontier Closed Area Boundary |
Figure 12.2.3 of EIA Report |
GR06 |
Yu Grave |
Section between Ling Ma Hang and Frontier Closed Area Boundary |
Figure 12.2.3 of EIA Report |
GR08 |
Chan Grave |
Section
between Ping Yeung and Wo Keng Shan |
Figure 12.2.7a
of EIA Report |
GR10 |
Tsui Grave |
Section
between Ping Yeung and Wo Keng Shan |
Figure 12.2.9c
of EIA Report |
GR13 |
Yim Grave |
Fanling section |
Figure 12.2.18 of EIA Report |
GR15 |
Chan Grave |
Fanling section |
Figure 12.2.21
of EIA Report |
GR16 |
Ho Grave |
Fanling section |
Figure 12.2.21 of EIA Report |
GR17 |
Cheung Grave |
Fanling section |
Figure 12.2.21
of EIA Report |
GR18 |
Yip Grave |
Section between Ping Yeung and Wo Keng Shan |
Figure 12.2.7b of EIA Report |
GR19 |
Law Grave |
BCP section |
Figure 12.2.1
of EIA Report |
GR20 |
Lam Grave |
Cheung Shan Tunnel Section |
Figure 12.2.10c of EIA Report |
Built
Structures |
|||
BS64 |
Village
Houses, Ha Wo Keng Shan Village |
Section between Ping Yeung and Wo Keng Shan |
Figure 12.2.9b of EIA Report |
BS65 |
Village
Houses, Ha Wo Keng Shan Village |
Section between Ping Yeung and Wo Keng Shan |
Figure 12.2.9b of EIA Report |
Historical/Cultural
Landscape Feature |
|||
LF08 |
Well |
BCP Section |
Figure 12.2.1
of EIA Report |
Prior to the
commencement of the photographic and cartographic recording, detailed work plan
should be submitted to the Antiquities and Monuments Office (AMO) for agreement. The plan should be prepared in accordance
with the requirements of the Guidelines for Photographic Records and
Cartographic Records established by AMO (see Appendix D). Liaison with and obtaining agreement from the descendents of the directly
impacted graves will need to be carried out by the Lands Department.
11.2.1.2 Vibration Monitoring
Since no potential construction vibration
impacts have been identified for the proposed scheme assessed in the EIA Study,
no vibration monitoring is considered necessary. However, if there is any amendment to the
design during detailed design stage, the potential impacts will need to be
reviewed. In case the design change will
cause potential vibration impacts on the identified built heritage features, it
is recommended that prior to commencement of the construction works, a baseline
condition survey and baseline vibration monitoring should be conducted by a qualified building surveyor and a qualified structural
engineer to define the vibration limit and to evaluate if construction
vibration monitoring and structural strengthening measures are required during construction phase to ensure
that the construction of the Project will not cause adverse impact to the
heritage features.
11.2.1.3 Temporary Grave Access Diversion
Access of the grave GR03 will temporarily be affected
by the proposed works during construction phase. Temporary access division will
be provided during the construction phase so that access to the grave will not
be blocked as a result of the construction works. After completion of
construction works, the affected access route is required to be re-provided.
11.2.2 Archaeology
Two mitigation measures are recommended to
mitigate the potential direct impacts on the potential or unknown
archaeological resources, namely Archaeological Survey-cum-Rescue Excavation
and Archaeological Survey on the resumed private land areas. These archaeological works should be
conducted by a professional archaeologist who should obtain a Licence to
Excavate and Search for Antiquities from the Authority under the AM Ordinance. An Archaeological Action Plan (AAP) following
the Guideline for Cultural Heritage Impact Assessment should be submitted to
Antiquities and Monuments Office (AMO). The project proponent should appoint
qualified and experienced archaeologist(s) with sufficient funding, time and
personnel arrangements to implement the AAP. Details of the proposal plan with
specification for further archaeological survey and survey-cum-rescue
excavation should be agreed with AMO. The AAP should include , but not limited
to, the following information:
§
a detailed plan for
further archaeological survey at inaccessible areas in Section between Lin Ma
Hang and Frontier Closed Area Boundary, Section between Ping Yeung and Wo Keng
Shan, Sha Tau Kok Road Section (Between North and South Tunnel), Lau Shui Heung
Tunnel Section (South Tunnel) and Fanling Section;
§
a detailed plan for
survey-cum-rescue excavation at the Section between Ping Yeung and Wo Keng
Shan; and
§
a contingency plan
to address possible arrangement if significant archaeological findings are
unearthed during the further archaeological survey and survey-cum-rescue
excavation.
Details of these
mitigation measures are described in Sections
11.2.2.1 and 11.2.2.2 below:
11.2.2.1 Survey-Cum-Rescue Excavation
A
survey-cum-rescue excavation with an indicative boundary as shown in Figure 11.2 in the Section between Ping Yeung
and Wo Keng Shan should be conducted after land resumption and before the
commencement of the construction works to further investigate the
archaeological remains and to preserve the
archaeological remains, if any, confirmed by the survey.
11.2.2.2 Archaeological Survey in Resumed Private Land Area
Due to site
access constraint, some areas have not yet been surveyed during the EIA Study of the
Project. A further archaeological survey should
be conducted after land resumption to complete the outstanding survey proposed
for the EIA Study to obtain field data to verify the EIA findings. Table 11.2 summarises the areas that need further archaeological
survey after land resumption.
Table 11.2: Areas Requiring Further Archaeological Survey
Relevant Project Sections |
Scope of Work |
Reference Figures |
|
Section between Lin Ma Hang and Frontier Closed Area Boundary |
§ 7 test pits; § 4 auger holes; and § Additional test pits and auger holes in area of low archaeological potential illustrated in Figure 12.6.1 of the EIA Report. Quantity and location of test pits and auger holes required to be agreed with AMO. |
§ Figure 12.6.1 of the EIA Report |
|
Section between Ping Yeung and Wo Keng Shan |
§ 4 test pits; § 6 auger holes; and § Survey-cum-rescue excavation, detailed scope to be agreed with AMO. |
||
Sha Tau Kok Road Section (Between North and South Tunnel) |
§ 9 test pits; and § 12 auger holes. |
§ Figure 12.6.4 of the EIA Report |
|
Lau Shui Heung Tunnel Section (South Tunnel) |
§ 2 test pits. |
§ Figure 12.6.5 of the EIA Report |
|
Fanling Section |
§ 2 test pits; and § 3 auger holes. |
§ Figure 12.6.6 of the EIA Report |
11.3.1 Built Heritage
Since all directly impacted built heritage features are to be relocated or removed prior to commencement of construction works, no impact is anticipated, and no EM&A programme is required during the operation phase of the Project.
11.3.2 Archaeological Resources
No EM&A programme is required.
Site inspections provide a direct means to trigger and enforce the specified environmental protection and pollution control measures. They should be undertaken routinely by the ET to inspect the construction activities in order to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented. With well defined pollution control and mitigation specifications and a well established site inspection, deficiency and action reporting system, the site inspection is one of the most effective tools to enforce the environmental protection requirements on the construction site.
The ET Leader
shall be responsible for formulating the environmental site inspection, the
deficiency and action reporting system, and for carrying out the site
inspection works. He shall submit a proposal for site inspection and deficiency
and action reporting procedures to the IEC for agreement, and to the ER for
approval. The Contractor’s proposal for rectification would be made known to
the ER and IEC.
Regular site
inspections led by the ET leader shall be carried out at least once per week.
The areas of inspection shall not be limited to the environmental situation,
pollution control and mitigation measures within the site; it should also
review the environmental situation outside the Project sites which is likely to
be affected, directly or indirectly, by the site activities. The ET shall make
reference to the following information in conducting the inspection:
§
the EIA and EM&A recommendations on environmental protection and
pollution control mitigation measures
§
the Environmental Permit conditions
§
ongoing results of the EM&A program
§
works progress and programme
§
individual works methodology proposals (which shall include proposal on
associated pollution control measures)
§
contract specifications on environmental protection
§
relevant environmental protection and pollution control laws
§
previous site
inspection results undertaken by the ET and others
The Contractor shall keep the ET Leader
updated with all relevant information on the construction contract necessary
for him to carry out the site inspections. Inspection results and associated
recommendations for improvements to the environmental protection and pollution
control works shall be submitted to the IEC and the Contractor within 24 hours
for reference and for taking immediate action. The Contractor shall follow the
procedures and time-frame stipulated in the environmental site inspection, and
the deficiency and action reporting system formulated by the ET Leader, to
report on any remedial measures subsequent to the site inspections.
The ET shall also carry out ad hoc site
inspections if significant environmental problems are identified. Inspections
may also be required subsequent to receipt of an environmental complaint, or as
part of the investigation work.
12.2 Compliance with Legal and Contractual Requirements
There are contractual environmental
protection and pollution control requirements as well as environmental
protection and pollution control laws in Hong Kong with which construction
activities must comply.
In order that
the works are in compliance with the contractual requirements, relevant
sections (e.g. sections related to environmental measures) of works method
statements submitted by the Contractor to the ER for approval shall be sent to
the ET Leader for vetting to see whether sufficient environmental protection
and pollution control measures have been included.
The ET Leader
shall also keep himself informed of the progress and programme of the works to
check that relevant environmental laws have not been violated, and that any
foreseeable potential for violation can be prevented.
The
Contractor shall regularly copy relevant documents to the ET Leader so that
works checking can be carried out. The document shall at least include the
updated Works Progress Reports, updated Works Programme, any application
letters for different licence / permits under the environmental protection
laws, and copies of all valid licences / permits. The site diary shall also be
made available for the ET Leader's inspection upon his request.
After
reviewing the documentation, the ET Leader shall advise the Contractor of any
noncompliance with contractual and legislative requirements on environmental
protection and pollution control for them to take follow-up actions, including
any potential violation of requirements.
Upon receipt
of the advice, the Contractor shall undertake immediate action to correct the
situation. The ER shall follow up to
ensure that appropriate action has been taken in order to satisfy contractual
and legal requirements.
Handling of environmental complaints should
follow the environmental complaint flow diagram and reporting channel as
presented in Figure 12.1.
During the complaint investigation work, the
Contractor and ER shall cooperate with the ET in providing all necessary
information and assistance for completion of the investigation. If mitigation
measures are identified in the investigation, the Contractor shall promptly
carry out the mitigation works. The ER
shall ensure that the measures have been carried out by the Contractor.
The reporting requirements of EM&A are
based upon a paper-documented approach. However, the same information can be
provided in an electronic medium upon agreeing the format with the IEC, the ER
and EPD (for construction phase), and with the Environmental Consultant, CEDD
and EPD (for operation phase). This would enable a transition from a paper / historic
and reactive approach to an electronic / real time proactive approach.
For construction phase of EM&A, types of
reports that the ET Leader shall prepare and submit include baseline monitoring
report, monthly EM&A report, quarterly EM&A summary report and final
EM&A review report. In accordance with Annex 21 of the EIAO-TM, a copy of
the monthly, quarterly summary and final review EM&A reports shall be
submitted to the Director of Environmental Protection. The exact details of the
frequency, distribution and time frame for submission shall be agreed with the
IEC, the ER and EPD prior to commencement of works
13.2 Baseline Monitoring Report
The ET Leader shall prepare and submit a
Baseline Environmental Monitoring Report within 10 working days of completion of
the baseline monitoring. Copies of the Baseline Environmental Monitoring Report
shall be submitted to the Contractor, the IEC, the ER, CEDD and EPD. The ET
Leader shall liaise with the relevant parties on the exact number of copies
they require. The report format and baseline monitoring data format shall be
agreed with the IEC, the ER and EPD prior to submission.
The baseline monitoring report shall include
at least the following:
(i) up
to half a page executive summary
(ii) brief
project background information
(iii) drawings
showing locations of the baseline monitoring stations
(iv) monitoring
results (in both hard and diskette copies) together with the following
information:
§
monitoring
methodology
§
name of
laboratory and types of equipment used and calibration details
§
parameters
monitored
§
monitoring
locations (and depth)
§
monitoring
date, time, frequency and duration
§
quality
assurance (QA) / quality control (QC) results and detection limits
(v) details
of influencing factors, including:
§
major
activities, if any, being carried out on the site during the period/monitoring
§
weather
conditions during the period/monitoring
§
other
factors which might affect results
(vi) determination
of the Action and Limit Levels for each monitoring parameter and statistical analysis
of the baseline data, the analysis shall conclude if there is any significant
difference between control and impact stations for the parameters monitored
(vii) revisions
for inclusion in the EM&A Manual
(viii) comments,
recommendations and conclusions.
The results and findings of all EM&A
work carried out during the month shall be recorded in the monthly EM&A
reports prepared by the ET Leader. The EM&A report shall be prepared and submitted
within 10 working days from the end of each reporting month. Each monthly
EM&A report shall be submitted to the following parties: the Contractor,
the IEC, the ER, CEDD and the EPD. Before submission of the first EM&A
report, the ET Leader shall liaise with the parties on the required number of
copies and format of the monthly reports in both hard copy and electronic medium.
The ET leader shall review the number and
location of monitoring stations and parameters every six months, or on as
needed basis, in order to cater for any changes in the surrounding environment and
the nature of works in progress.
13.3.1
First Monthly EM&A Report
The first monthly
EM&A report shall include at least but not be limited to the following:
(i)
executive summary (1-2 pages):
§
breaches of Action
and Limit levels
§
complaint log
§
notifications of any
summons and status of prosecutions
§
changes made that
affect the EM&A
§
future key issues
(ii)
basic project information:
§
project organisation
including key personnel contact names and telephone numbers
§
scope of works of
the Project
§
construction
programme
§
works undertaken
during the month with illustrations (such as location of works etc)
§
drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations (with co-ordinates of the monitoring locations)
(iii)
a brief summary of EM&A
requirements including:
§
all monitoring
parameters
§
environmental
quality performance limits (Action and Limit levels)
§
Event-Action Plans
§
environmental
mitigation measures, as recommended in the project EIA study final report
§
environmental
requirements in contract documents
(iv)
environmental status:
§
advice on status of
compliance with environmental permit including the status of submissions under
the environmental permit
(v)
implementation status:
§
implementation
status of environmental protection and pollution control / mitigation measures,
as recommended in the EIA Report
(vi)
monitoring results (in both hard
and diskette copies) together with the following information:
§
monitoring methodology
§
name of laboratory
and types of equipment used and calibration details
§
parameters monitored
§
monitoring locations
§
monitoring date,
time, frequency, and duration
§
weather conditions during the period/monitoring
§
graphical plots of the monitored parameters in the
month annotated against
-
the major activities
being carried out on site during the period
-
weather conditions
that may affect the monitoring results
-
any other factors
which might affect the monitoring results
-
QA/QC results and
detection limits
(vii)
Analysis of monitoring results,
non-compliance, complaints, and notifications of summons and status of
prosecutions:
§
analysis and
interpretation of monitoring results in the month
§
any non-compliance
(exceedances) of the environmental quality performance limits (Action
§
and Limit levels)
§
changes made that
affect the EM&A during the month
§
complaints received
(written or verbal) for each media, including locations and nature of complaints,
investigation, liaison and consultation undertaken, actions and follow-up procedures
taken, results and summary
§
notification of
summons and status of prosecutions for breaches of current environmental protection
/ pollution control legislation, including locations and nature of the
breaches, investigation, follow-up actions taken, results and summary
§
reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures
§
actions taken in the
event of non-compliance and deficiency, and follow-up actions related to
earlier non-compliance
(viii)
others
§
an account of the
future key issues as reviewed from the works programme and work method
statements
§
comment on the solid
and liquid waste management status during the month including waste generation
and disposal records
§
outstanding issues
and deficiencies
§
comments on
effectiveness of the environmental management systems, practices, procedures
and mitigation measures), recommendations (for example, any improvement in the
EM&A programme) and conclusions
(ix)
appendix
§
monitoring schedule
for the present and next reporting period
§
cumulative
statistics on complaints, notifications of summons and successful prosecutions
§
outstanding issues
and deficiencies
13.3.2 Subsequent Monthly EM&A Reports
Subsequent
monthly EM&A reports shall include the following:
(i)
executive summary (1-2 pages):
§
breaches of Action and Limit levels
§
complaint log
§
notifications of any summons and status of prosecutions
§
changes made that affect the EM&A
§
future key issues
(ii) environmental status:
§
advice on status of compliance with environmental permit including the
status of submissions under the environmental permit
(iii) implementation
status:
§
implementation status of environmental protection and pollution control
/ mitigation measures, as recommended in the EIA Report
(iv)
monitoring results (in both hard
and diskette copies) together with the following information:
§
monitoring methodology
§
name of laboratory and types of equipment used and calibration details
§
parameters monitored
§
monitoring locations
§
monitoring date, time, frequency, and duration
§
weather conditions during the period/monitoring
§
graphical plots of the monitored parameters in the month annotated
against:
-
the major activities being carried out on site during the period
-
weather conditions that may affect the monitoring results
-
any other factors which might affect the monitoring results
-
QA/QC results and detection limits
(v)
Analysis of monitoring results,
non-compliance, complaints, and notifications of summons and status of prosecutions:
§
analysis and interpretation of monitoring results in the month
§
any non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit levels)
§
changes made that affect the EM&A during the month
§
complaints received (written or verbal) for each media, including
locations and nature of complaints, investigation, liaison and consultation
undertaken, actions and follow-up procedures taken, results and summary
§
notification of summons and status of prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary
§
reasons for and the implications of non-compliance, complaints, summons
and prosecutions including review of pollution sources and working procedures
§
actions taken in the event of non-compliance and deficiency, and
follow-up actions related to earlier non-compliance
(vi)
others
§
an account of the future key issues as reviewed from the works programme
and work method statements
§
comment on the solid and liquid waste management status during the month
including waste generation and disposal records
§
outstanding issues and deficiencies
§
comments on effectiveness of the environmental management systems,
practices, procedures and mitigation measures), recommendations (for example,
any improvement in the EM&A programme) and conclusions
(vii)
appendix
§
monitoring schedule for the present and next reporting period
§
cumulative statistics on complaints, notifications of summons and
successful prosecutions
§
outstanding issues and deficiencies
Some information concerning the EM&A
works, such as the EM&A requirements would remain unchanged throughout the
EM&A programme. In the subsequent Monthly EM&A Reports, the First Monthly
EM&A Report can be referred instead of repeating the description of the
unchanged information.
A quarterly EM&A report shall be
produced and shall contain at least the following information. In addition, the
first quarterly summary report should also confirm if the monitoring work is
proving effective and that it is generating data with the necessary statistical
power to categorically identify or confirm the absence of impact attributable
to the works.
(i)
up to half a page executive
summary
(ii)
basic project information including
a synopsis of the project organisation and programme, and a synopsis of works
undertaken during the quarter
(iii)
a brief summary of EM&A
requirements including:
§
monitoring parameters
§
environmental quality performance limits (Action and Limit levels)
§
environmental mitigation measures, as recommended in the project EIA
Final Report
(iv)
drawings showing the project area,
environmental sensitive receivers and the locations of the monitoring and
control stations
(v)
implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the EIA Report
(vi)
graphical plots of the monitored
parameters over the past four months (the last month of the previous quarter
and the present quarter) for representative monitoring stations annotated against:
§
the major activities being carried out on site during the period
§
weather conditions during the period
§
any other factors which might affect the monitoring results
(vii)
advice on the solid and liquid waste
management status during the quarter including waste generation and disposal
records
(viii)
a summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels)
(ix)
a brief review of the reasons for
and the implications of any non-compliance, including a review of pollution
sources and working procedures
(x)
a summary description of actions
taken in the event of non-compliance and any follow-up procedures related to
any earlier non-compliance
(xi)
a summary of all complaints received
(written or verbal) for each media, liaison and consultation undertaken,
actions and follow-up procedures taken
(xii)
comments on the effectiveness and
efficiency of the mitigation measures); recommendations on any improvement in
the EM&A programme and conclusions for the quarter
(xiii)
proponents' contacts and any hotline
telephone number for the public to make enquiries.
The EM&A program coould be terminated
upon completion of those construction activities that have the potential to
cause significant environmental impacts, and/or the completion of operational
traffic noise monitoring, monitoring of woodland compensation and wetland
compensation, whichever is the later.
The proposed termination by the Contractor
should only be implemented after the proposal has been endorsed by the IEC, the
ER and the Project proponent followed by final approval from the Director of
Environmental Protection.
The final EM&A
report should include, inter alia, the following information:
(i)
an executive summary
(ii)
basic project information including
a synopsis of the project organisation and programme, contacts of key
management, and a synopsis of work undertaken during the entire construction
period
(iii)
a brief summary of EM&A
requirements including:
§
monitoring parameters
§
environmental quality performance limits (Action and Limit levels)
§
environmental mitigation measures, as recommended in the project EIA
study final report
(iv)
drawings showing the project area,
any environmental sensitive receivers and the locations of the monitoring and
control stations
(v)
advice on the implementation
status of environmental and pollution control/mitigation measures, as recommended
in the project EIA study final report, summarised in the updated implementation
status proformas
(vi)
graphical plots of the monitored
parameters over the construction period for representative monitoring stations,
including the post-project monitoring annotated against:
§
the major activities being carried out on site during the period
§
weather conditions during the period
§
any other factors which might affect the monitoring results
§
the baseline condition
(vii)
compare the EM&A data with the
EIA
(viii)
Effectiveness of the solid and liquid
waste management
(ix)
a summary of non-compliance
(exceedances) of the environmental quality performance limits (Action and Limit
levels)
(x)
a brief account of the reasons the
non-compliance including a review of pollution sources and working procedures
(xi)
a summary of the actions taken
against the non-compliance
(xii)
a summary of all complaints received
(written or verbal) for each media, liaison and consultation undertaken,
actions and follow-up procedures taken
(xiii)
a review of the monitoring
methodology adopted and with the benefit of hindsight, comment its
effectiveness (including cost effectiveness)
(xiv)
a summary of notifications of summons
and successful prosecutions for breaches of the current environmental
protection/pollution control legislations, locations and nature of the breaches,
investigation, follow-up actions taken and results
(xv)
a review of the practicality and
effectiveness of the EM&A programme (e.g. effectiveness and efficiency of
the mitigation measures), and recommendation on any improvement in the EM&A
programme
(xvi)
a conclusion to state the return of
ambient and/or the predicted scenario as per EIA findings
No site-based documents (such as monitoring
field records, laboratory analysis records, site inspection forms, etc.) are
required to be included in the EM&A reporting documents. However, any such
document shall be well kept by the ET Leader / Monitoring Team and be ready for
inspection upon request. All relevant information shall be clearly and
systematically recorded in the document.
Monitoring data shall also be recorded in magnetic media form, and the
software copy must be available upon request. Data format shall be agreed with
the IEC, the ER, CEDD and EPD. All documents and data shall be kept for at
least one year following completion of the construction contract and one year
after the completion of operation phase monitoring for construction phase
EM&A and operational phase EM&A respectively.
13.7 Interim Notifications of Environmental Quality Limit Exceedances
For construction phase EM&A, with
reference to the Event and Action Plan, when the environmental quality
performance limits are exceeded, the ET Leader shall immediately notify the
IEC, the ER and EPD, as appropriate and shall keep them informed of the results
of the investigation, proposed remedial measures, actions taken, updated
situation on site, need for further follow-up proposals, etc. A sample template for the interim
notifications is shown in Appendix C.
The ET Leader may modify the interim notification form for this EM&A
programme, the format of which should be approved by the ER and agreed by the
IEC.