Agreement
No. CE 29/2008(EP)
Engineering
Investigation and Environmental
Studies
for Integrated Waste Management Facilities
Phase
1 – Feasibility Study
EIA
Executive Summary
Table of Contents
1.2 Objective of the EIA Study
2............ PROJECT DESCRIPTION
3............ CONSIDERATION OF ALTERNATIVES
4............ KEY FINDINGS OF THE EIA STUDY
4.1 Assessment Scenarios of the EIA Study
4.3 Artificial Island near SKC
Alone
4.4 TTAL Site and Artificial Island near SKC (Co-existing Scenario)
Lists of Figures
Figure
ES1 |
|
Figure
ES2 |
Location
of the IWMF at the Artificial Island near Shek Kwu Chau |
Figure
ES3 |
|
Figure
ES4 |
Photomontage
of the IWMF at the Artificial Island near Shek Kwu Chau |
Figure
ES5 |
|
Figure
ES6 |
1.1.1.1 The Project is to construct and operate a modern Integrated Waste Management Facilities (IWMF) for managing municipal solid waste (MSW) under a design-build-operate (DBO) contract arrangement. The IWMF comprises: (a) an advanced thermal incineration plant with design capacity of 3,000 tonnes per day (tpd) and (b) a mechanical sorting and recycling plant with design capacity of 200 tpd. The non-recyclables sorted from the mechanical plant will be sent to the thermal incineration plant for further treatment. Under any conditions, the total MSW feeding to the thermal incineration plant and the mechanical plant will not exceed 3,000 tpd.
1.1.1.2
Over
the past years, the quantity of MSW generated in
1.1.1.3 Compared with other major cities in the world that have diverse means of disposing of waste, Hong Kong relies solely on three strategic landfills, including the South East New Territories (SENT) Landfill, the North East New Territories (NENT) Landfill and the West New Territories (WENT) Landfill for the disposal of its MSW. Consequently, the three strategic landfills are now projected to approach their capacities in 2014, 2016 and 2018 respectively; hence there is a pressing need for adoption of advanced waste treatment technologies to reduce the volume of unavoidable MSW so as to extend the life span of the strategic landfills and their future extensions.
1.1.1.4
To
address this imminent waste problem in a holistic manner, the Government has
reviewed the action agenda outlined in the “Policy Framework for the Management
of Municipal Solid Waste (2005-2014)” (the Policy Framework) published in 2005
against the latest development in January 2011. To ensure solid waste can
continue to be handled properly without causing environmental problems, the Government
will:
(a)
revise upward the MSW recovery target to 55% by 2015 by stepping up
publicity and promotional efforts on waste reduction and recycling;
(b)
expedite legislative proposals to introduce new Producer Responsibility
Scheme (PRS) and extend current PRS to encourage waste reduction;
(c)
engage the public in continued discussions on possible options to
introduce MSW charging as a direct economic disincentive to reduce waste at
source; and
(d)
seek funding approval from the Finance Committee of the Legislative
Council (LegCo) in early 2012 so that advanced waste treatment facilities (including an IWMF with a treatment
capacity of 3,000 tonnes of MSW daily, two organic waste treatment facilities
with total capacity of 500 tonnes of food/ organic waste daily), and extension to the existing landfills will be commissioned in time to
ensure continual and more sustainable management of solid waste.
1.1.1.5
s
of a world class city if there is no timely and adequate provision of appropriate
waste treatment and disposal facilities.
1.1.1.6 There are a number of benefits with the implementation of the first IWMF, including:
·
Substantial Bulk Reduction for Landfill Disposal - The amount of MSW to be disposed of at landfills will
substantially decrease as the volume of waste remained after the thermal treatment process
would only be about 10% of the original volume. Hence, the existing landfills and their extensions can serve for a longer
period of time.
·
Energy Recovery - The IWMF
could generate and export electricity for gainful uses by the community.
·
Greenhouse Gas Reduction - The production of greenhouse gases due to
landfilling of MSW will be reduced. The IWMF will
also generate and
export electricity for the community’s gainful uses thus
replacing fossil fuel use for power generation, leading to overall reduction of greenhouse gas emission in
1.2
Objective
of the EIA Study
1.2.1.1 Two potential sites have been identified for the development of the IWMF, they arei Tsang Tsui Ash Lagoons site in Tuen Mun (TTAL site) and an artificial island near Shek Kwu Chau (SKC). Based on the two potential sites, the following elements of the Project are classified as Designated Projects under the Environmental Impact Assessment (EIA) Ordinance:
TTAL Site
· An incinerator with an installed capacity of more than 50 tonnes per day (under Item G.3 of Part I, Schedule 2 of the EIAO)
· A waste disposal facility for refuse (under Item G.4 of Part I, Schedule 2 of the EIAO)
· A waste disposal facility for pulverized fuel ash or furnace bottom ash (under Item G.6 of Part I, Schedule 2 of the EIAO)
· Public utility electricity power plant (under Item D.1 of Part I , Schedule 2 of the EIAO)
· An activity for the reuse of treated sewage effluent from a treatment plant (under Item F.4 of Part 1, Schedule 2 of the EIAO)
· Decommissioning of a waste disposal facility for pulverized fuel ash, furnace bottom ash or gypsum (under Item 8 of Part II, Schedule 2 of the EIAO)
Artificial Island near SKC
· An incinerator with an installed capacity of more than 50 tonnes per day (under Item G.3 of Part I, Schedule 2 of the EIAO)
· A waste disposal facility for refuse (under Item G.4 of Part I, Schedule 2 of the EIAO)
· A waste disposal facility for pulverized fuel ash or furnace bottom ash (under Item G.6 of Part I, Schedule 2 of the EIAO)
· Public utility electricity power plant (under Item D.1 of Part I , Schedule 2 of the EIAO)
· Reclamation works (including associated dredging works) of more than 5 hectares in size (under Item C.1 of Part I, Schedule 2 of the EIAO)
·
A dredging operation exceeding
· An activity for the reuse of treated sewage effluent from a treatment plant (under Item F.4 of Part 1, Schedule 2 of the EIAO)
1.2.1.2 This EIA Report was prepared in accordance with the EIA Study Brief No. ESB-184/2008. The purpose of this EIA Study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the Project at the two potential sites. The information will contribute to decisions by the Director of Environmental Protection on:
· The overall acceptability of any adverse environmental consequences that is to arise as a result of the Project and the associated activities of the Project;
· The conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences; and
· The acceptability of residual impacts after the proposed mitigation measures are implemented.
2.1.1.1 The locations of the two potential sites, Tsang Tsui Ash Lagoons site (TTAL site) and an artificial island near Shek Kwu Chau (SKC) are shown in Figures ES1 and ES2 respectively. The first IWMF will be sited at the TTAL site or the artificial island near SKC.
2.1.1.2
The
TTAL
site is located at the existing ash
lagoons in Nim Wan, Tuen Mun, overlooking
2.1.1.3
The
artificial island near SKC will be formed by reclamation at the south-western
coast of Shek Kwu Chau, an island located to the southwest of Cheung Chau and
to the south of Chi Ma Wan Peninsula,
2.1.1.4
Shek
Kwu Chau is granted to the Society for the Aid and Rehabilitation of Drug
Addicts (SARDA) for use as a rehabilitation centre, which presently has a
population of about 300 rehabilitators and staff. There is no other existing or
planned residential, commercial or industrial development on the island.
2.2
Project Scope
2.2.1 Project Facilities
2.2.1.1 The infrastructure for this Project would comprise an advanced incineration plant, a mechanical sorting and recycling plant, and ancillary & supporting facilities. The facilities of the IWMF mainly include the following:
Incineration Plant
· MSW receiving, storage and feeding system
· Moving grate incineration furnaces
· Waste heat recovery and power generation system
· Boiler feedwater treatment system
· Flue gas treatment system
· Flue gas discharge system with stack
· Ash storage and handling system
· Reagent reception and storage system
· Odour control system
·
Process control and monitoring
system
Mechanical Treatment (MT) Plant
· MSW receiving, storage and feeding system
· Mechanical treatment system including shredding and sorting facilities
· Products and by-products storage and handling system
· Odour control system
· Process control and monitoring system
Ancillary & Supporting Facilities
· Weighbridge
· Site security
· Administration building / visitors and environmental education centre
· Vehicle washing facilities
· Maintenance workshop
· Fuel storage tanks
· Water treatment plant
· Wastewater treatment plant
· Electricity supply and export system
· Utilities
· Berthing area for marine vessels and storage of refuse containers (for the artificial island near SKC only)
2.2.1.2 Design-Build-Operate (DBO) contract arrangement would be adopted for the Project and the operation period would be 15 years. Under this contract arrangement, a DBO contractor would be engaged to conduct the detailed design, construction and operation of the IWMF. For the purpose of the EIA Study, a reference design for the IWMF was prepared. Photomontages showing the IWMF facilities at the TTAL site and the artificial island near SKC are presented in Figures ES3 and ES4 respectively.
2.2.1.3
In the reference design, the incineration plant consists of six incinerator units, each with a design capacity of 600 tpd. The
incineration plant is designed to meet the target emission limits as shown in Table ES1. Apart from nitrogen oxides (NOx) standard,
these target emission limits are based on the internationally most stringent European
Union (EU) standard for MSW incinerators and the Hong Kong Best Practicable
Means for Incinerators. For NOx, as it is the most critical parameter in
2.2.1.4 An on-site desalination plant will be provided for supplying water to the IWMF. The desalination plant would involve membrane separation of dissolved ions such as chloride ions from seawater, and would not involve any boiling or combustion processes.
2.2.1.5 An on-site wastewater treatment plant will be provided to treat the wastewater generated from floor/ vehicle washing and from staff/ visitors. The treated effluent will be reused in the incineration plant or mechanical treatment plant or for washdown and landscape irrigation within the IWMF. No effluent would be discharged to the nearby water body or any existing sewerage or drainage systems.
2.2.1.6 The heat produced during the incineration process will be recovered and used for electricity generation. The electricity generated will be used to support the normal operation of the facilities within the IWMF. Surplus energy will be exported to other users via the existing electricity grids maintained by power companies. For the TTAL site, underground cables will be laid to export surplus energy to the nearby Black Point Power Station. For the artificial island near SKC, installation of submarine cables will be required in order to export the surplus energy from the artificial island near SKC to an electricity substation at Cheung Sha.
Table ES1 - Air Emission Limits for the IWMF
Air Pollutants |
Emission Limits (mg/m3) (1) |
Monitoring Requirements |
|
|
Daily |
Half -
Hourly |
|
Particulates
(2) |
10 |
30 |
Continuous |
Organic
Compounds |
10 |
20 |
Continuous |
Hydrogen
Chloride (HCl) |
10 |
60 |
Continuous |
Hydrogen
Fluoride (HF) |
1 |
4 |
Continuous |
|
50 |
200 |
Continuous |
Carbon
Monoxide (CO) (3) |
50 |
100 |
Continuous |
Nitrogen Oxides (NOX) as Nitrogen
Dioxide (NO2)(7) |
100 |
200 |
Continuous |
Mercury |
0.05 (4) |
- |
Intermittent |
Total
Cadmium & Thallium |
0.05 (4) |
- |
Intermittent |
Total Heavy
Metals (5) |
0.5 (4) |
- |
Intermittent |
Dioxins
& Furans (6) |
1´10-7 |
- |
Intermittent |
Notes: (1) The emission limit is expressed at reference conditions of 0oC temperature, 101.325 kPa pressure, dry and 11% oxygen content conditions.
(2) The particulate emission limits are assumed to be for respirable suspended particulates (RSP).
(3) The CO emission limits do not apply to the start-up and shut-down periods.
(4) Average values over a sampling period of a minimum of 30 minutes and a maximum of 8 hours.
(5) Including Sb, As, Pb, Co, Cr, Cu, Mn, V and Ni.
(6) The unit is I-TEQ (The emission limit is equal to 0.1 ng I-TEQ m-3), according to the BPM 12/1(08), the averaging time for dioxin is 6 to 8 hours.
(7) The emission levels for NOx are half of that stipulated in European’s Emission Limits in EC’s Waste Incineration Directive.
2.2.2 Construction of the IWMF
TTAL Site
2.2.2.1 The Project would require decommissioning of the Middle Lagoon, formation of about 1.2 hectares of pond habitat for Litter Grebe and about 9.8 hectares of land and associated roads and drains, followed by foundation works, construction of superstructures and installation of plants and equipment for the various systems mentioned in Section 2.2.1.1.
2.2.2.2 Currently, the land is largely formed by PFA that was filled to this site in previous years. As there are no existing structures in the site area, the works related to the decommissioning of the lagoon would be minimal.
2.2.2.3 The finished ground level of the IWMF will be at a level higher than the average ground level of the existing Middle Lagoon. Therefore, the formation of land for the IWMF would involve mainly filling and levelling work. No disposal of PFA will be required during the construction phase.
2.2.2.4 The construction of the IWMF will include the following stages:
· Site drainage;
· Site formation;
· Foundation piling;
· Civil and building works;
· Mechanical & electrical plant installation;
· Roads, utilities, services and landscaping; and
· Ancillary instrumentation and control works.
Artificial Island near SKC
2.2.2.5 Reclamation will be needed to form about 11.8 hectares of land for the various systems mentioned in Section 2.2.1.1. Due to occasionally rough sea condition in the vicinity of the artificial island near SKC, breakwater will be provided to ensure safe loading and unloading operation at the berth area.
2.2.2.6
The
reclamation will be formed with filling materials supported on the in-situ
marine deposits with suitable geotechnical ground treatment (such as surcharge
loading, installation of vertical band drains, etc.) at a finished ground level
of about +5mPD high. Seawalls will be constructed to confine the reclamation
area and breakwaters will be provided to protect the water basin. To minimize
dredging and filling activities and the associated environmental impacts,
vertical cellular structure consisting of circular cells instead of sloping gravity
structure is proposed to be adopted for the construction of the seawalls and
breakwaters. The cellular breakwater protecting the reclamation area and the
water basin would be about +9mPD high for resisting waves with significant
heights.
2.2.2.7 The berth area, which will be extended from the seawall at the northwest side of the reclaimed area, will be formed by a piled deck structure with precast slab. Tubular piles are proposed to form the foundation of the berth. Non-percussive bore piling method would be adopted for the installation of tubular piles.
2.2.2.8 The construction of the IWMF will include the following stages:
· Construction of cofferdam surrounding the reclamation area;
· Site filling for reclamation;
· Surcharge loading for reclamation area;
· Construction of breakwater;
· Pilling for berth area;
· Site drainage;
· Foundation (spread footing);
· Civil and building works;
· Mechanical & electrical plant installation;
· Roads, utilities, services and landscaping; and
·
Ancillary instrumentation and
control works.
2.2.2.9 The submarine cables would be installed by burying method using water jets. A cable burying machine which include an injector would be lowered to the seabed. The injector fluidizes a trench using high pressure water jets and a cable is immediately laid within the trench. The sides of the trench then slip around the cable, burying it and leaving a small depression in the seabed.
2.2.3 Operation of the IWMF
2.2.3.1 The IWMF will be operated on a 24-hour basis daily, while the reception of MSW would be limited from 8 am to 8 pm.
2.2.3.2 For the artificial island near SKC, about 3,000 tpd MSW loaded in containers would be delivered by marine vessels from the existing refuse transfer stations, including Island East Transfer Station, Island West Transfer Station and West Kowloon Transfer Station. For the TTAL site, about 3,000 tpd MSW loaded in containers currently delivered to the berth of WENT Landfill by marine vessels or delivered directly to the WENT Landfill or its extension by land transport will be diverted from the WENT Landfill to the adjoining the TTAL site.
2.2.3.3 At the reception hall of the incineration plant, MSW from the containers will be discharged to a bunker. The MSW will then be fed into incineration furnaces for combustion. The heat energy released will be recovered to generate electricity through waste heat boilers and steam turbine generators. Flue gas generated from the incineration furnaces will be treated before discharging to the atmosphere. Bottom ash, fly ash and air pollution control (APC) residues produced from the incineration process will be collected for treatment and disposed of at the WENT Landfill or its extension if they have met the disposal requirements or will be reused if possible.
2.2.3.4
MSW delivered to the MT
plant will be discharged to a bunker. A grab bucket will cut the plastic bags commonly used for household
waste collection and convey the MSW to the hopper of the mechanical treatment facilities.
Large-size MSW will first be cut into smaller
pieces by a shredder. The well-prepared MSW will
then run through a series of mechanical treatment processes and separate into
different types of outputs, including recyclable materials (e.g. metals, papers
and plastics) to be collected by recyclers, sorted combustible MSW to be sent
to the incineration plant for treatment with other MSW, and non-combustible MSW
to be disposed of at the WENT Landfill.
2.3.1.1 The tentative construction programmes for the TTAL site and the artificial island near SKC are shown in Tables ES2 and ES3 respectively.
Table ES2 - Construction Programme of the IWMF at the TTAL Site
Description |
Date |
Award
of Contract |
March
2013 |
Site
Clearance & Backfilling |
March
2013 – August
2013 |
Foundation
(Pilling) |
June
2013 – February
2015 |
Civil and E&M Works |
November
2013 – May
2016 |
Testing and Commissioning |
June
2016 – August
2016 |
Table ES3 - Construction
Programme of the IWMF at the Artificial Island near SKC
Description |
Date |
Award
of Contract |
March
2013 |
Construction
of Cofferdam Surrounding Reclamation Area Phase 1 |
June 2013 – November 2013 |
Construction
of Breakwater Phase 1 |
June 2013 – November 2013 |
Construction
of Cofferdam Surrounding Reclamation Area Phase 2 |
June 2014 – July 2014 |
Site
Filling for Reclamation |
January 2014 – October 2014 |
Surcharge
Loading for Reclamation Area |
May 2014 – July
2015 |
Construction
of Breakwater Phase 2 |
June 2014 –
October 2014 |
Installation
of Anti-scouring Layer |
November 2014 |
Pilling
for Berth Area |
June 2014 –
November 2014 |
Construction of Submarine Cables |
June 2015 |
Foundation
(Spread Footing) |
May 2015 –
October 2015 |
Civil
and E&M Works |
August 2015 – February
2018 |
Testing
and Commissioning |
March 2018 – May
2018 |
3.1.1 Identification of Potential Sites
3.1.1.1 A site search exercise was completed in 2008 under the study Site Search for Integrated Waste Management Facilities in Hong Kong for Municipal Solid Waste for the identification of potential sites for the development of the IWMF. The Legislative Council, the Tuen Mun and Islands District Councils and the Advisory Council on the Environment were briefed on the findings of the site search in 2008.
3.1.1.2 The Government formed an Advisory Group (AG) on Waste Management Facilities and five AG sub-groups comprising 24 non-official members from the professional bodies, green groups, academic and business sectors. Based on the recommendations from the AG, the following 23 types of areas were excluded from the preliminary search for potential sites:
·
All areas for Residential and Commercial Use;
·
All 23 existing or potential Country Parks;
·
All existing or potential
·
All Special Areas (outside Country Parks);
·
All Sites of Special Scientific Interest (SSSI) (including buffer
areas);
·
All Restricted Areas (Wildlife);
·
The RAMSAR Site (including buffer area);
·
All Green Belt (GB) and Urban
·
All Conservation Areas (CA);
·
All Coastal Protection Areas (CPA);
·
All Water Gathering Grounds;
·
All Wetlands Areas;
·
All Fish Culture Zones;
·
All Proposed Fisheries Protection Areas;
·
All Gazetted Beaches;
·
All Declared Monuments, Graded Historical Buildings and Structures,
Deemed Monuments and Archaeological Sites;
·
All Cemeteries, Burial Grounds or Grave Zones;
·
All Fairways and Shipping Lanes and Port Areas;
·
All Airports and Restricted Areas around them (including the
·
All Tunnels and Roads, existing and proposed Railways;
·
All Other Major Infrastructure (including
·
All Major Tourism Development Areas; and
·
All Priority Sites for Enhanced Conservation promulgated under the New
Nature Conservation Policy.
3.1.1.3
Figure ES5 shows the locations of the
existing or potential
3.1.1.4
3.1.1.5 Apart from the above recommendations of the AG, the following factors were also taken into account in identifying the potential sites:
·
The IWMF should be located in areas compatible with neighboring
activities;
·
It should have marine access; and
·
It should be less exposed to waves or typhoons
in case outlying islands are chosen.
3.1.1.6
The islands in Sai Kung (e.g. Kau Sai Chau,
3.1.1.7 The above have resulted in forming an initial list of 21 sites, including 13 closed landfills as follows:
Outlying
·
Ex-Lamma Quarry,
·
·
Siu Ho Wan;
·
Ha Mei Wan,
Large Scale Artificial
·
Eastern Waters;
·
Lamma South West;
·
·
South Cheung Chau;
·
South East Offshore;
·
Tai Long Wan Offshore.
Other Regions
·
Ha Pak Nai;
·
NENT Landfill Extension B;
·
Nim Wan;
·
·
·
Tseung Kwan O Area 137;
·
Tuen Mun Area 38;
·
·
WENT Landfill Extension A;
·
WENT Landfill Extension B;
· Tsang Tsui Ash Lagoons.
3.1.1.8 The initial list of potential sites was then subject to further consideration with respect to their site characteristics, latest development status, prevailing wind directions and the dominant environmental conditions to form a site proposal.
3.1.1.9 All the 13 closed landfill sites were considered not suitable due to the lack of large flat platforms, unstable foundations and commitment to other uses.
3.1.1.10 Under the study of “Extension of Existing Landfills and Identification of Potential New Waste Disposal Sites”, some sites were identified and assessed for the feasibility to be developed as large scale artificial islands for landfill purpose. These large scale artificial islands could be the potential locations for the development of the IWMF. However, since these sites were not selected for the development of new landfills, the development of the IWMF at these sites were not considered.
3.1.1.11
For the remaining sites,
commitments have been made to reserve some of them for other developments (e.g.
Siu Ho Wan for Organic Waste Treatment Facilities and
3.1.1.12 As a result, eight potential sites (as shown in Figure ES6) were shortlisted as follows:
·
S1 - Tseung Kwan O Area 137
·
S2 - Ex-Lamma Quarry,
·
S3 - Ha Mei Wan,
·
S4 - Artificial
·
S5 - Tsang Tsui Ash Lagoons
·
S6 - Tuen Mun Area 38
·
S7 - Ha Pak Nai
·
S8 -
3.1.1.13
With due consideration of site
availability, land use, traffic, environmental, social and other relevant
aspects, it was concluded that the last two of the above sites, Ha Pak Nai (S7)
and Tuen Mun Port (S8), be dropped from further consideration. The
reasons for dropping the Ha Pak Nai site are that it is located at the ecologically
sensitive coastal area at
3.1.1.14 The remaining six sites were the shortlisted sites for further site selection assessment.
Environmental
·
Air Quality
·
Noise
·
Visual and Landscape
·
Terrestrial Ecology
·
Drainage, Water Quality, Marine Ecology & Fisheries
·
Hazard to Life
Engineering / Technical
·
Ease of Integration with Existing or Planned MSW Infrastructure
·
Site Access
·
Constraints to Site Layout
·
Utilities
·
Construction Duration
·
Construction Risk
· Operational Risk
Economics
·
Capital Cost
·
Operating Cost
·
Social
·
Land Use
·
Land Ownership
·
Traffic Impact
Consumer & User
·
Community Impacts
3.1.3 Evaluation of Shortlisted Sites
S1 - Tseung Kwan O Area 137
3.1.3.1 The proposed site is located at the southwest edge of Area 137 reclamation near Tit Cham Chau in Tseung Kwan O. It has been reserved for the use of “Potentially Hazardous Installations (PHIs)”.
3.1.3.2
This site is currently the only
available site in
3.1.3.3
In addition, as the site is
directly facing Siu Sai Wan, Chai Wan, and Heng Fa Chuen on the eastern side of
S2 - Ex-Lamma Quarry,
3.1.3.4
The proposed site is located at
the ex-Lamma Quarry at the northeast side of the island. It is directly facing
a popular tourist spot, Sok Kwu Wan where seafood restaurants and a mariculture
zone exist, and is in proximity to various indigenous villages such as Luk Chau
village. The overall planning intention for
3.1.3.5
The IWMF development would be
incompatible with the planning intention of the remaining portion of the
ex-Lamma Quarry site which is proposed for tourism and recreation purposes, and
the adjoining “Comprehensive Development Area” (CDA) site which is planned for
comprehensive low-rise residential development. The Planning and Development
Study on Hong Kong Island South and
3.1.3.6
As the site is directly facing
Wah Fu,
S3 - Ha Mei Wan, Lamma Island
3.1.3.7
The proposed site is an artificial
island to be reclaimed at the west end of
3.1.3.8
Like the Ex-Lamma Quarry site,
should the IWMF be built here, it would cause significant visual impact on the
substantial population residing in Wah Fu,
S4 - Artificial
3.1.3.9
The site is to be formed by
reclamation at the south-western side of the Shek Kwu Chau which is located to
the south of Chi Ma Wan Peninsula of Lantau
·
It is located far from any major population clusters. There is only a
very light population of about 300 persons living in a rehabilitation centre
managed by the Society for the Aid and Rehabilitation of Drugs Addicts (SARDA).
As such, any visual impact could be insignificant due to the small number of
sensitive receivers.
·
Regarding the air quality impact, the only major air sensitive receivers
are residents in Cheung Chau, however the impact should be minimal. Moreover,
the residents in Cheung Chau are not located at the prevailing downwind
direction. Since no other emission sources exist in the nearby areas, there are
no concerns on the cumulative air quality impact.
·
Due to its relatively central location with respect to the refuse
transfer stations throughout Hong Kong Island and the outlying islands, the
aggregate refuse vessel transfer trip length associated with an IWMF at the
artificial island near Shek Kwu Chau would be less than the existing operation
of refuse transfer to the WENT Landfill. This would offer more environmental
and cost-effective marine transportation over reasonable trip length without
undue impact on the marine traffic.
·
Since the proposed IWMF would be developed on
reclaimed land without encroachment onto the existing island, impacts on the
terrestrial habitat on the existing island would be minimal.
3.1.3.10 However, the construction of an IWMF on this site would involve reclamation which might affect the natural coastline, statutory gazetting procedures, and installation of power lines and the utilities, which might impact on the natural landscape and would result in longer construction time, higher cost and the development time table may be subject to greater uncertainty due to more complex technical requirements and statutory procedures. There are also some other concerns:
·
The nearby marine area is a fish spawning and nursery ground, where Chinese
White Dolphin and Finless Porpoise have been sighted.
· The compatibility of the IWMF with the adjacent rehabilitation centre will need to be carefully studied.
S5 - Tsang Tsui Ash Lagoons
3.1.3.11
The Tsang Tsui Ash Lagoons are
situated at the northwest
·
Being located right next to the WENT Landfill, the site has an operational
advantage of sharing the existing infrastructure (e.g. berthing facilities and
waste container storage area etc.) and efficient disposal of the ash residues
generated by the IWMF to the WENT Landfill. Because of the above synergy
effect, the IWMF could occupy a smaller site area, thus translating into both
land and cost saving.
·
It is also close to the existing power plant. Surplus energy generated
from the IWMF can easily be connected to the power grid.
·
Unlike the island options, both marine and land transport of waste and
ash are possible, and no reclamation is required.
·
As there are no major population clusters in the vicinity, the IWMF
should not have significant visual impact on the
immediate local community.
3.1.3.12 Regarding air quality impact, preliminary assessment has found that the cumulative air quality impact arising from the IWMF and the existing and proposed emission sources nearby, such as the Black Point and Castle Peak Power Stations, as well as the Sludge Treatment Facilities under construction, etc. on the nearby sensitive air receivers should meet the air quality requirements. Detailed assessment would need to be carried out to confirm the cumulative air quality impact should this site be selected for the IWMF development.
S6 - Tuen Mun Area 38
3.1.3.13
The site is located in an
industrial setting adjacent to the EcoPark and is not far from the WENT
Landfill. It is in close proximity to the air sensitive receivers at Tuen Mun
New Town, in particular the
3.1.3.14 Another major constraint of this site is its relatively small size. The site in question is currently reserved for another waste management facility and is only about 5.75 hectares, which is not enough to accommodate an IWMF of capacity of 3,000 tpd and of around 10 hectares. Even if developing the IWMF alone, additional land would need to be acquired from the nearby sites. However, other areas in Tuen Mun Area 38 have been planned for other land intensive facilities including EcoPark, construction and demolition materials handling facilities and permanent aviation fuel facility, etc. such that there is no surplus land available. In addition, transfer of waste to this site by marine vessels will be constrained. This is because there is limited space for the development of berthing facilities along the waterfront in Tuen Mun Area 38 as the waterfront area has already been reserved to meet the operational requirements of other planned uses.
Recommendations
3.1.3.15 The outcomes of the assessment indicated that the Tseung Kwan O Area 137 (S1), Ex-Lamma Quarry, Lamma Island (S2), Ha Mei Wan, Lamma Island (S3) and Tuen Mun Area 38 (S6) all had some major constraints and were not recommended for further engineering and EIA studies.
3.1.3.16 An artificial island near Shek Kwu Chau (S4) and Tsang Tsui Ash Lagoons (S5) are worth taking forward for detailed studies and further consideration as potential sites for the IWMF. From an air quality aspect, the artificial island near Shek Kwu Chau is comparatively more favourable. However, its potential impacts on the natural coastal landscape, marine ecology, water quality, and fishery would need further study and detailed assessment. In addition, the compatibility of the IWMF with the adjacent rehabilitation centre would need to be reviewed and carefully considered. Regarding the Tsang Tsui Ash Lagoons site, it has relative overall merits because of the ease of integration with the existing landfill and waste reception facilities, much less impact on local ecology, shorter construction time, and lower construction cost. However, the cumulative air quality impact on the air sensitive receivers would still need to be carefully and thoroughly studied and assessed to confirm its acceptability.
3.2.1 Identification of Potential Technologies
3.2.1.1
To identify suitable MSW
treatment technologies, the Government conducted an Expression of Interest
(EoI) exercise in
3.2.1.2 Based on the AG’s recommendations, a review of the latest development of the moving grate, fluidized-bed, rotary kiln incineration technologies, eco-co-combustion system, gasification, plasma gasification and pyrolysis technologies was conducted in 2009. It reconfirmed the recommendations of the EoI exercise, including:
·
Incineration technology (i.e., moving grate incineration technology)
could play a core role in the IWMF for MSW treatment;
·
The key issues of the eco-co-combustion including its technical
feasibility and long-term commercial viability have still not been
satisfactorily solved; and
· Application of the plasma gasification and pyrolysis technologies for untreated MSW treatment is still limited and are of small-scale. These technologies are not able to meet the criteria in the EoI exercise for forming the core technology of the IWMF for treating 3,000 tpd of mixed MSW.
3.2.1.3 Although no proposal on rotary kiln incineration technology was received during the EoI exercise in 2002, a review of its latest development was also carried out in 2009 because of the reported application for MSW treatment. The review results indicate that most of the rotary kiln incineration systems installed are used for sludge, industrial or hazardous waste treatment; whereas their applications for MSW treatment are uncommon and limited to relatively small scale, and therefore is not well proven for the IWMF. Hence, rotary kiln incineration technologies, eco-co-combustion system, plasma gasification and pyrolysis technologies have not been included for further evaluation.
3.2.1.4 There may be development in the fluidized-bed incineration technology and gasification technology since the EoI exercise in 2002, which may prove them to be as effective as the moving grate incineration technology for mixed MSW treatment. Therefore, these two technologies were further comparatively evaluated with the moving grate incineration technology in order to select the most suitable core technology for the IWMF.
3.2.2 Evaluation Criteria
3.2.2.1 The three thermal treatment technologies, including moving grate incineration, fluidized-bed incineration and gasification technologies are evaluated based on the criteria shown in Table ES4 below.
Table ES4 - Criteria for Selection of Thermal Treatment Technology
Main Criteria |
Sub-criteria |
Assessment Measures |
Environmental Factor |
Air Emission |
The volume of flue gas produced from the furnaces required for
treatment and the amount of gas pollutants generated. |
Engineering Factors |
Flexibility |
Are there any
special requirements on the quality of feedstock? How capable is the process of adapting to short term and long term
variations in the characteristics of the input waste? |
Electricity Production Efficiency |
- |
|
Reliability |
What is the maximum demonstrated capacity of a fully commercial plant?
What is the scale
up risk? The numbers of suppliers which can provide the system for MSW
treatment. |
|
Land Requirement |
Footprint of the process, which refers to number of incineration/
gasification units required for treating 3,000 tpd of MSW. |
|
Operating Experience for Mixed MSW Treatment |
How long have the incineration/ gasification systems been adopted for
MSW treatment? |
|
Costs |
Capital Cost and Operating Costs |
- |
3.2.2.2 The selection criteria focus on the environmental, engineering and cost considerations. Other considerations, such as visual impacts, employment opportunities and public acceptance, for moving grate incineration, fluidized bed incineration and gasification are considered to be almost the same since all these treatment technologies are thermal treatment technologies. Public health is also not compared since the most advanced flue gas treatment system will be adopted for all the three technologies to meet the most stringent air quality standards in the world. Thus, all the three technologies should pose very low or insignificant risk to public health.
3.2.3 Evaluation of Thermal Treatment Technologies
3.2.3.1 Table ES5 summarizes the option evaluation for the three thermal treatment technologies based on a qualitative assessment of the criteria.
Table ES5 - Summary of Option Evaluation for Thermal Treatment Technologies(1)
Criteria |
Moving Grate
Incineration |
Fluidized-bed
Incineration |
Gasification |
|||
Environmental Factors |
||||||
Air Emission(2) |
Medium |
△ |
High |
X |
Low |
O |
Engineering Factors |
||||||
Flexibility(3) |
High |
O |
Low |
X |
Low |
X |
Electricity Production Efficiency |
Medium |
△ |
Medium |
△ |
Medium to High(7) |
△/O |
Reliability - Unit Capacity |
10-920 tpd |
O |
10-80 tpd |
X |
20-150 tpd |
△ |
Reliability - Plant Capacity |
20-4,300 tpd |
10-200 tpd |
30-405 tpd |
|||
Reliability -
Key Suppliers for Mixed MSW Treatment(4) |
Many, including B&W Volund,
CNIM, Fisia, Inova |
Limited,
including |
Limited, including Ebara(5),
|
|||
Land
Requirements and System Complexity(6) |
Low |
O |
Large |
X |
Large |
X |
Operating Experience for Mixed MSW Treatment |
Longest track
record |
O |
Limited
Experience |
△ |
Limited
Experience |
△ |
Cost Factors |
||||||
Capital Costs |
Low |
O |
High |
X |
High |
X |
Operation Costs |
Low |
O |
High |
X |
High |
X |
Overall |
Most Favorable |
Least Favorable |
Less Favorable |
Note: (1) O, △and X represent the most favourable, medium favourable and the least favourable to the IWMF, respectively. Please note that the ranking shown in each criterion represents comparative rather than absolute ranking.
(2) Air emission criterion refers to the volume of flue gas produced from the furnaces required for treatment and the amount of the air pollutant generated.
(3) Flexibility refers to the applicability of the technology for MSW treatment and the ability to tolerate a fluctuation of the MSW characteristics.
(4) B&W Volund, CNIM, Ebara, Fisia, Hitachi, IET, JFE, Kawasaki, Lentjes, Seghers, Lurgi, Mitsubishi, Nippon Steel, and Takuma refer to Babcock & Wilcox Volund, CHIM/Martin, Ebara Corporation, Fisia Babcock Environment GmbH, Hitachi Zosen, IET Energy, JFE Engineering Corporation, Kawasaki Heavy Industries, Ltd, Lentjes UK Limited, Képpel Seghers, Lurgi Envirotherm GMBH, Mitsubishi Heavy Industries Ltd., Nippon Steel Engineering, and Takuma Co. Ltd, respectively.
(5) The systems are incorporated with ash melting systems.
(6) Land requirement and complexities are compared based on the number of the incineration/ gasification units required for treating 3,000 tpd of mixed MSW.
(7) Electricity production efficiency of gasification is ranked as high if a more efficient approach for converting the chemical energy in syngas to electrical energy is used such as combustion of the syngas after cleaning in a more efficient internal combustion engine or combustion of the syngas after significant cleaning in a gas turbine with further energy recovery though raising steam and generating power in a steam tubine. If the sygnas is combusted in a close coupled combustion chamber, there is no real energy benefits since the electrical energy would be generated from a steam turbine generator similar to conventional incineration plants.
3.2.3.2 As shown in Table ES5, moving grate incineration is more favorable to be adopted as a core technology of the IWMF for treating 3,000 tpd of mixed MSW. The advantages of moving grate incineration over the gasification and fluidized-bed incineration technologies in terms of reliability, operating experience, flexibility, land requirements, and capital and operating costs are summarized as follows:
·
It is the only thermal technology which has been adopted for treating
over 3,000 tpd of mixed MSW, whereas fluidized bed incineration and
gasification technologies for mixed MSW treatment are of much smaller scale;
·
It has the least scale-up risks, whereas the other two will suffer
higher scale-up risk when being adopted in the IWMF for mixed MSW treatment;
·
It has the longest track record of operation (over 100 years of
operation experience), whereas the other two have little or limited track
record for mixed MSW treatment;
·
It shows the highest capability to tolerate the fluctuation of MSW characteristics
with robust/ forgiving nature when handling mixed MSW, whereas the other two
are less robust and usually require pretreatment of MSW;
·
It requires the least land area for the treatment units, whereas the
other two have larger land requirement because of the requirement of more
treatment units;
·
It possess over 10 suppliers and thereby ensure adequate tender
competition, whereas there are 5 – 6 suppliers of gasification/ fluidized bed
technologies and a key gasification supplier is retreating from the MSW market;
·
There is a concern for operation failure of the gasification technology
due to unpleasant experience in
·
It possesses the least operation complexity in comparison to fluidized
bed incineration and gasification technologies; and
· It requires the least capital and operating costs in comparison to fluidized bed incineration and gasification technologies.
3.2.3.3 Theoretically, gasification technology generates less volume of flue gas and less amount of gas pollutants than the incineration technologies. Since gasification requires just a fraction of the stoichiometric amount of oxygen, the volume of process gas flow is smaller. It is however important to note that the quantity of air emission is not the dominating factor. By applying necessary flue gas treatment systems, the quality of air emissions from the moving grate incineration system can be regulated to meet the most stringent international air emission standards.
3.2.3.4 While extensive information on the types and levels of pollutants generated from incineration is available, there is very little published data on emissions from full-scale gasification process. If available, much of the published data for gasification process is from small scale or pilot operations. Hence comparison of the types and levels of flue gas pollutants generated by different types of thermal treatment technologies based on currently available data is rather difficult, bearing in mind also that a meaningful comparison could only be made provided that the different technologies treated similar type of wastes and employed similar energy recovery system.
3.2.3.5 It was recommended in the EoI exercise that incineration could play a key role in the overall IWMF strategy since it had a favorable treatment cost and was the most cost-effective technology to divert MSW from landfills amongst the other strategy options. Land requirement of incineration is also low. The evaluation result arrives at the same conclusion as the EoI exercise, whereby moving grate incineration technology is the most suitable technology for the IWMF in terms of environmental, engineering and cost factors. It is therefore recommended to adopt moving grate incineration as the core technology for the IWMF for treating of 3,000 tpd of mixed MSW.
3.2.3.6 At the Meeting of Advisory Council on the Environment (ACE) held on 14 December 2009, the Council discussed the findings of the technology review and had no objection to employing moving grate incineration technology as the core thermal treatment technology for the development of the IWMF.
3.2.4 Evaluation of Sorting and Recycling Technologies
3.2.4.1 As highlighted in the EoI exercise, mechanical-biological treatment (MBT) was considered to be a potential sorting and recycling technology to be adopted in the IWMF than the other technologies. This was because MBT could potentially recover both materials and energy from the mixed MSW, whereas the others could only recover recyclables. Due to its ineffectiveness in waste volume reduction and requirement of relatively large footprint than thermal treatment technologies, MBT technology was recommended to be adopted at a small scale in the IWMF.
3.2.4.2
A review of the latest
development in MBT technology shows that there is no noticeable advancement in
the MBT technology
in terms of volume reduction and land requirement since the EoI exercise. The
land requirement for MSW treatment, despite being subject to the technology
approach selected, odour management adopted, output requirement, waste input
characteristics etc, typically ranges from 60 to
3.2.4.3
At the Meeting of the Waste
Management Subcommittee (WMSC) of
ACE on 26 January 2010, the WMSC discussed
the proposal of whether a
sorting and recycling plant should be incorporated in the IWMF project. The
WMSC considered the proposal in detail, taking into account previous advice and
recommendations by the Advisory Group on Waste Management Facilities in mid 2005 and by the ACE after the
delegation’s visit to
3.2.5.1 Based on the results of the evaluation of the shortlisted treatment options and the recommendations of ACE, it was concluded that moving grate incineration would be the most preferable option and would be adopted as the core treatment technology, supplemented with demonstration-scale mechanical treatment facilities, in the IWMF.
3.3.1.1
A
review of the existing incineration plants in the world was conducted. Based on the existing installations in
the world, most of the incineration plants have a treatment capacity ranging
from less than 1,000 tpd to 4,000 tpd.
Selection of plant capacity is normally
dependent on local requirements and constraints. Localized small scale incineration
plants likely have less traffic impact when compared to centralized large scale
incinerations. The advantages of
large scale incineration plants are that they are more efficient in cost and
land utilization when compared with small scale incineration plants. With due regard to the scarcity of
suitable land in densely populated cities and considerations of economy of
scale, there is a tendency to maximize the potential of a site and to plan for
an incineration plant with higher treatment capacity. Some overseas examples with installed treatment
capacity larger than 3,000 tpd are listed below:
·
Tuas South Incineration Plant and Senoko
Incineration Plant in
·
Afval Energie Bedrijf (AEB) Incineration Plant in
3.3.1.2
In
3.4.1.1 With reference to the “A Guidance Note on the Best Practicable Means for Incinerators (Municipal Waste Incineration) BPM 12/1(08)”, EPD, the design of the chimney height shall be determined by mathematical or physical dispersion modelling techniques. Therefore, wind tunnel tests (physical dispersion modelling technique) were conducted to determine and verify that the stack height for the IWMF would not result in adverse terrain or building wake effects at the TTAL site and the artificial island near SKC. The wind tunnel tests consisted of plume visualization for 75m, 100m, 125m and 150m stack heights.
3.4.1.2 Visualization of stack plume behaviour under various wind directions and speeds has been conducted to provide a qualitative understanding of the effect of the immediate terrain and building structures on the dispersion of the plume emitted from the IWMF stack. The visualization also serves to check whether the plume from the IWMF stack will hit the critical Air Sensitive Receivers in close proximity to the TTAL site and the artificial island near SKC. The findings of the wind tunnel tests verified that both 125m and 150m stack heights for the IWMF would not result in adverse terrain and building wake effects at both the TTAL site and the artificial island near SKC.
3.4.1.3
Besides, a Good Engineering
Practice (GEP) stack height requirement has been established in the
3.4.1.4 With a view to further alleviate the potential air quality impacts at critical air sensitive receivers (ASRs) but at the same time to minimize potential visual impact associated with a tall stack, 150m is selected as the stack height for the IWMF at both the TTAL site and the artificial island near SKC. It has considered both the air quality benefit and visual impact due to a tall stack.
3.5.1.1 With a view to minimize the land use and the associated environmental impacts at the two sites, in particular at the artificial island near SKC, the layout for the IWMF is considered appropriate taking into consideration the functional need for operation of the IWMF, reasonable flexibility in design for future DBO contractor and allowance of suitable size of land for provision of visitors and community facilities. Based on the proposed layouts, the footprint requirement for treating per tonnage of MSW daily is approximately 32m2 at the TTAL site and 38m2 at the artificial island near SKC respectively. The area for compensated habitat for Little Grebe at the TTAL site and the area for breakwater at the artificial island near SKC were excluded in the unit footprint calculation. A larger footprint requirement at the artificial island near SKC is due to the additional land required for the berth area.
3.5.1.2
The unit footprint requirement
of the IWMF is comparable with other overseas incineration plants, including Afval
Energie Bedrijf (AEB) Incineration Plant with design capacity of 4,000 tpd in
the
3.5.1.3
At the artificial island near
SKC, the artificial island for construction of the IWMF was designed to be
apart from the existing
3.5.1.4 Furthermore, the breakwater at the artificial island near SKC was designed to provide protection to the marine vessels and to maintain the loading and unloading needs even during typhoon signal no. 3.
3.6.1.1 Alternative sequences of construction, including concurrent construction sequence and phased construction sequence, have been considered.
3.6.1.2
Concurrent construction
sequence involves various construction activities occurring at the same time. The environmental benefit of this
construction sequence would be the reduction of the
construction period and hence the duration of impact due to the
construction. However, the
magnitude of the overall environmental impact could be larger.
3.6.1.3
Phased construction sequence
involves construction activities being carried out one after another. This construction sequence would help in reducing the magnitude of the overall impacts,
but the construction period would be longer.
3.6.1.4 As the two approaches have their environmental benefits and dis-benefits, a balancing approach which involves a combination of concurrent and phased construction sequences at different stages of the construction has been adopted to alleviate the potential environmental impact and to meet the target commissioning date. For instance, at the artificial island near SKC, the construction of the breakwater and berth area would start off after completion of the cellular cofferdam installation surrounding the reclaimed area so as to minimize magnitude of the overall environmental impact.
3.7.1.1 To minimize the potential environmental impacts, alternative construction methods have been considered. For the piling works at the TTAL site, percussive piles and socketted H-piles were considered. Percussive piles would cause substantial noise and vibration impacts, whereas the noise and vibration impacts due to the construction of socketted H-piles would be significantly lower. Considering the environmental benefits and dis-benefits of the alternative piling methods, socketted H-piles is recommended for this Project to minimize the potential noise impact during the construction.
3.7.1.2 Sloping seawall was originally proposed to be used at the artificial island near SKC. The width of the sloping seawall at the seabed level would be about 100m. The construction of the seawall involves dredging of a trapezoid trench to a width of 140m, and depth of 10m along the proposed location of the seawall at the seabed, filling of the trench with sand up to 2.5m below the seabed level and formation of the seawall above the sand fill by rock fill. The site area and dredging volume for the construction of the seawall is substantial. To minimize dredging and filling activities and the associated environmental impacts, cellular cofferdam and circular cell breakwater instead of sloping seawall were proposed to be adopted for the construction of the seawalls and breakwaters, respectively.
4.1
Assessment
Scenarios of the EIA Study
4.1.1.1 Based on the two potential sites, the following three assessment scenarios have been examined in the EIA Study:
(a) developing a 3,000 tpd IWMF at the TTAL site alone;
(b) developing a 3,000 tpd IWMF at the artificial island near SKC alone; and
(c) developing a 3,000 tpd IWMF at each of the two potential sites (co-existing scenario).
4.2
TTAL Site Alone
4.2.1 Air Quality Impact
Construction
Phase
4.2.1.1 Air quality impacts from the construction works for the Project would mainly be related to construction dust from excavation, materials handling, filling activities and wind erosion. With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation, dust impact on air sensitive receivers would be minimal.
Operation
Phase
4.2.1.2 During the operation of the IWMF, the potential sources of air quality impact would be the air emissions from the incinerator stacks and the odour nuisance from the waste reception halls, the waste storage area, the mechanical treatment plant and the wastewater treatment plant.
4.2.1.3
Advanced air pollution control
system, including selective catalytic reduction (SCR) for Nitrogen oxides (NOx) removal and activated carbon
for dioxins removal and continuous emissions monitoring
system will be installed for the IWMF to ensure that the emissions from the
IWMF stacks will meet the target emission limits that are the same as or more
stringent than those stipulated in Hong Kong and the European Commission for
waste incineration. NOx is the most
critical parameter in
4.2.1.4
Cumulative air quality impact
assessment has been undertaken for the Project at the TTAL site taking
into account the emissions from both regional and local sources, including the
emissions within the Pearl River Delta Economic Zone and major local air
pollution sources in
4.2.1.5 Besides, odour nuisance may arise from the operation of the on-site wastewater treatment plant, the waste reception halls, the waste storage areas and the mechanical treatment plant of the IWMF. The wastewater treatment plant, the waste reception halls and the waste storage areas would be fully enclosed and the odorous air in this facility would be extracted and used as combustion air for incineration to remove the odorous compounds. For the mechanical plant, they would be equipped with deodorizing system of 95% odour removal efficiency. Besides, the wastewater treatment plant, waste reception halls, waste storage areas and mechanical treatment plant would also be operated under negative pressure to prevent odour leaking to the outdoor environment. The predicted cumulative odour concentrations would comply with the criteria required in the EIAO-TM. Adverse odour impact on nearby ASRs would not be expected.
4.2.2 Noise Impact
4.2.2.1
The
TTAL site is situated
in a remote location and no existing or planned noise sensitive receiver (NSR)
is identified within 300m from the boundary of the site. Adverse noise impacts from the TTAL site on NSRs during both construction
and operation phases are therefore not anticipated.
4.2.2.2
Having
said that, an assessment has been undertaken to examine the potential traffic
noise impact on the NSRs along
4.2.3 Water Quality Impact
Construction
Phase
4.2.3.1
The
potential sources of water quality impact arising during the construction phase
of the Project include construction site runoff and drainage, wastewater
generated from general construction activities and sewage from the
workforce. With the implementation
of the recommended mitigation measures and site practices outlined in ProPECC
PN 1/94 (Practice Note for Professional Persons on Construction Site
Drainage), no unacceptable residual impacts on water quality are expected.
Operation
Phase
4.2.3.2
During
the operation
phase, wastewater will be generated from the proposed incineration plant and
mechanical treatment plant. An
on-site wastewater treatment plant will be provided. All generated wastewater will be
discharged to the on-site wastewater treatment plant for treatment. The treated effluent from the wastewater
treatment plant will be reused in the incineration plant
and mechanical treatment plant or for washdown and landscape irrigation within
the IWMF site. A “net zero discharge” scheme will be
adopted during the operation of the IWMF.
4.2.3.3
An
on-site desalination plant will be provided for supplying water to the IWMF. Saline water would be discharged from
the desalination plant at a low discharge rate. The saline water has been quantitatively
assessed to be minor and adverse impacts on water quality due to the saline
water discharge would not be expected.
4.2.4 Waste Management Implications
Construction
Phase
4.2.4.1
The types of waste that would
be generated during the construction phase of the Project include construction
and demolition (C&D) materials from the construction activities, general
refuse from the workforce and chemical wastes from the maintenance of
construction plant and equipment.
Provided that the wastes are handled, transported and disposed of
properly and good site practices and waste reduction measures are implemented
accordingly, adverse environmental impact is not expected during the
construction phase of the Project.
Operation
Phase
4.2.4.2 The end product from the incineration process of the IWMF would include bottom ash, fly ash and air pollution control residues, which would be disposed of at a landfill after checking for compliance with the proposed incineration residue pollution control limits. Pre-treatment of fly ash and air pollution control residues by cement solidification or chemical stabilization will be undertaken prior to disposal at landfill to ensure that pollutants would not leach to the environment. A small amount of non-combustible inert refuse (e.g. glass, sand etc.) sorted out in the mechanical treatment process would also be disposed of at the WENT Landfill.
4.2.4.3 Limited amount of chemicals or chemical wastes would be used or generated for the operation of the IWMF. With proper implementation of the recommended practices and response procedures on land contamination prevention, the potential for land contamination due to the IWMF operation is expected to be minimal.
4.2.5 Ecology
Construction
Phase
4.2.5.1 The major ecological impact of the Project would be the loss of about 11 hectares of ash lagoon habitat, of which about 82% is usually dry and support sparse vegetation which has a low biodiversity and ecological value. The loss of the remaining ash lagoon with low to moderate ecological value including 1.98 hectares breeding ground of Little Grebe would be mitigated by the provision of permanent pond habitat within the IWMF site (about 1.2 ha), as well as the interim habitat enhancement work for the southern unoccupied Middle Lagoon (about 4.5 ha). Disturbance impact to the breeding activities of Little Grebe would be minimized by scheduling the commencement of site formation work in the dry season. As a precautionary measure, the works area would be thoroughly inspected by experienced ecologist(s) to confirm no breeding activities of Little Grebe would be affected by the construction work before commencement of site clearance.
4.2.5.2 Other indirect impacts would include noise and human disturbance, release of PFA leachate and construction site runoff and wastewater. With proper implementation of good site practices including the use of quiet machinery to reduce noise emissions, proper drainage arrangement to minimize construction runoff etc., adverse ecological impact is not anticipated. The implementation of mitigation measures would be subject to regular audit as part of the EM&A programme.
Operation
Phase
4.2.5.3 No direct habitat loss would be resulted from the operation of the proposed Project. Disturbance impacts would include human activities and noise due to increased operational traffic. Mitigation measures such as landscape planting and boundary wall have been recommended to screen the visual interface and to limit public access to the adjoining lagoon habitat. The ecological function of the compensatory ponds as an alternative habitat for Little Grebe will be monitored.
4.2.5.4
With the implementation of the
recommended mitigation measures, no unacceptable ecological impact due to the
operation of the proposed Project would be expected.
4.2.6 Fisheries
4.2.6.1
No loss of fishing ground and
resources is expected during construction and operation phases of the proposed
Project. The construction of the IWMF would be mainly
land-based with only minor work anticipated at the seawall for the construction
of the saline water outfall. No
unprocessed or processed effluent would be discharged into the
4.2.7 Health Impact
4.2.7.1 The cancer risk arising from exposure to compounds of potential concern (COPCs) associated with the emissions of the IWMF has been evaluated in this EIA Study. The highest incremental (excess) cancer risk arising from the IWMF is predicted to be 9.82x10-7 which is within the screening level of 1x10-5 adopted by USEPA and it is considered that the Project would not present an unacceptable risk and no further analysis is necessary. The highest predicted total Hazard Index (HI) at all receptors are well below 0.25, which is an initial screening exposure benchmark derived from a conservative approach by the USEPA. Cumulative acute non-carcinogenic health impact of the IWMF imposed to the worst impacted human receptors were assessed and compared with local and overseas guideline levels. It was concluded that the levels of non-carcinogenic chemicals were found to be insignificant when compared to the adopted/ derived reference levels. For the classical COPCs of the HKAQO, while it is not possible to rule out adverse health effects from the IWMF with complete certainty, the impact on health from small additional air pollutants is likely to be very small and unlikely to be quantifiable.
4.2.7.2
As the vast majority of foods
in
4.2.7.3 The existing practices of transporting wastes in enclosed containers will be followed. With regards to the storage and handling of waste and ash, given that all the reception halls and ash storage pits will be fully enclosed with slightly negative air pressure and a closed grab will be use to grab waste and ash, leakage of any fugitive emissions to the outdoor environment is not expected. With the implementation of the recommended health risk control measures, the potential health impacts associated with the transportation, storage and handling of waste and ash are considered to be insignificant.
4.2.7.4 The potential health risk induced by radon emissions associated with PFA arising from the construction and operation was also evaluated. The estimation indicated that there would be no significant radiological hazard to workers working outdoors in the IWMF or in the restored/ operating ash lagoon area adjacent to the IWMF.
4.2.7.5 The IWMF will be designed and operated to the most up-to-date standards and practices. The operator must be well trained to avoid any accidental events as well as to implement industry best practice with reference to international standards and guidelines. To avoid or minimize potential health impacts associated with potential accidental events, an emergency response plan will be developed and properly implemented for the IWMF. It should be noted that the emergency response plan should be specific to the final design and operation of the IWMF. The recommended preventive measures include the use of best available techniques, continuous and regular stack emission monitoring, as well as conducting regular safety monitoring and audit. With the implementation of the recommended preventive measures and an effective emergency response plan for the IWMF, the health impacts associated with any potential accidental events could be minimized if not avoided.
4.2.8 Landscape and Visual Impact
Construction
Phase
4.2.8.1 During the construction phase, the impact to the landscape resources and landscape character areas would be “insubstantial”, except to the Ash Lagoon (LR1 & LCA1). The impact to the Ash Lagoon (LR1 & LCA1) before mitigation would be “substantial”.
4.2.8.2
The visual impact to most of
the visual sensitive receivers during the construction phase would be
“moderate”, and the visual impact to sea travellers of Deep Bay (VSR4) would be
“substantial”. After the implementation of the mitigation measures, the
residual impact to the sea travellers of
Operation
Phase
4.2.8.3 During the operation phase, the proposed works has negligible impact to most of the landscape resources and landscape character areas, except the Ash Lagoon (LR1 & LCA1) where the Project site locates. The impact to the Ash Lagoon would be “substantial”. Mitigation measures including proper landscape design blending the facilities into the surroundings, rooftop/ vertical greening design, landscape treatment, provision of compensatory habitat for Little Grebe, etc. are anticipated to mitigate the landscape impact and enhance the overall landscape quality of the environment. The long-term residual impact to the Ash Lagoon would be reduced to “moderate” in day 1 of operation and “slight” in year 10 of operation.
4.2.8.4 The visual impact to most of the visual sensitive receivers during the operation phase would be “moderate”, and the visual impact to the residents/ visitors of Ha Pak Lai (VSR5) and the sea travellers of Deep Bay (VSR4) would be “moderate/ substantial” and “substantial” respectively. After the implementation of the proposed mitigation measures, the residual impact to most of the visual sensitive receivers would be reduced to “slight”, and the residual impact to the residents/ visitors of Ha Pak Lai and the sea travellers of Deep Bay would be “slight/ moderate” in year 10 of operation.
4.2.8.5 The development of Sludge Treatment Facilities (STF), which is located adjacent to the TTAL site, has been confirmed and the STF will start commissioning before the IWMF. Surrounded by facilities of similar nature (e.g. STF, Black Point Power Station), the development of the IWMF at the TTAL site is considered compatible with the surrounding context. With the architectural and landscape design of the IWMF being coherent with the adjacent STF, the development of the two facilities could be integrated and blend well in the surrounding landscape. The two developments would form a harmonic view, and the cumulative landscape and visual impact of the two developments would be alleviated. Another concurrent project is the WENT Landfill Extension. The construction phase of the IWMF will occur concurrently during the early construction phase of the WENT Landfill Extension while the operation phase of the IWMF will occur during the construction, operation, restoration and aftercare phases of the WENT Landfill Extension. The construction and operation of the WENT Landfill Extension will cause significant cumulative impact to the area due to large-scale site formation. During the restoration & aftercare phases of the WENT Landfill Extension, the IWMF and STF would be in Year 8 and Year 11 of the operation phase respectively. The mature advanced planting at the WENT Landfill Extension can act as screening effect for the WENT Landfill Extension, and the compensatory planting at the WENT Landfill Extension will be provide preliminary vegetation cover for site area of the WENT Landfill Extension. The WENT Landfill Extension will become compatible with the surrounding IWMF and STF in which various landscape mitigation measures, such as landscape planting, green roof, vertical greening, have been implemented for a substantial period of time. After the whole period of restoration and aftercare phases of the WENT Landfill Extension, the impact due to the WENT Landfill Extension would be greatly mitigated by semi-mature compensatory woodland, shrubland and grassland. The IWMF, STF and resorted WENT Landfill Extension would blend well and be merged as a whole. No significant residual cumulative impact is anticipated.
4.2.8.6 Regarding the visual impacts during the waste transportation/ handling and cumulative visual impacts, the impact is expected to be insignificant. During the operation stage, MSW will be contained in containers and transported to the berth of the WENT Landfill from the Refuse Transfer Stations (RTSs) by marine transport. This is the current mode of transportation for MSW from the RTSs to the WENT Landfill. After arriving at the berth of the WENT Landfill, the containers will be hauled to the IWMF and the MSW will then be discharged from the containers to the bunker at the IWMF reception hall, which is enclosed in a covered building. The potential visual impact due to transportation/ handling is anticipated to be minimal.
4.2.8.7 In conclusion, the potential landscape and visual impacts can be effectively reduced by implementing the proposed mitigation measures during construction and operation phases. With reference to criteria defined in Annex 10 of the EIAO TM, the overall residual impact is considered as “acceptable with mitigation measures” after implementing the mitigation measures.
4.2.9 Cultural Heritage Impact
4.2.9.1 Based on the results of the desktop review and survey, the Tsang Tsui Archaeological Site has a high archaeological potential. However, the Tsang Tsui Archaeological Site is located approximately 150m from the Project boundary and adverse impacts associated with this Project are not expected.
4.2.9.2
The Hung Shing and
4.2.10 Landfill Gas Hazard
4.2.10.1 A qualitative assessment of the potential hazards associated with landfill gas migration from the WENT Landfill Extensions to the IWMF site has been conducted. A source-pathway-target analysis shows that the overall risk level for construction and operation phase of the IWMF are Medium and High respectively.
4.2.10.2 A number of measures have been recommended for the Project to safeguard the safety of all personnel and the general public (i.e. visitors) present at the Project site during construction and operation phase. These include site safety measures and routine monitoring of landfill gas at excavation areas during construction phase, and installation of gas barrier and monitoring wells and other building protection measures as necessary during the operation phase. With the implementation of these measures, no adverse impact of landfill gas hazard on this Project is anticipated.
4.2.11 Environmental Monitoring and Audit
4.2.11.1
Environmental
monitoring and audit (EM&A) requirements for the IWMF at the TTAL site have
been specified in an EM&A Manual.
The EM&A Manual contains details of proposed baseline and compliance
monitoring programmes, implementation schedule of the environmental protection/
mitigation measures, EM&A reporting procedures and complaint handling procedures.
4.3
Artificial Island near SKC Alone
4.3.1 Air Quality Impact
Construction
Phase
4.3.1.1
Air quality impacts from the
construction works for the Project would mainly be related to construction dust
from excavation, materials handling, filling activities and wind erosion. With the implementation of mitigation
measures specified in the Air Pollution Control (Construction Dust) Regulation,
dust impact on air sensitive receivers would be minimal.
Operation
Phase
4.3.1.2 During the operation phase, the potential sources of air quality impacts would be the air emissions from the incinerator stacks and the odour nuisance from the waste reception halls, the waste storage area, the mechanical treatment plant and the wastewater treatment plant.
4.3.1.3 Advanced air pollution control system, including SCR for NOx removal and activated carbon for dioxins removal and continuous emissions monitoring system will be installed for the IWMF to ensure that the emissions from the IWMF stacks will meet the target emission limits that is the same as or more stringent than those stipulated in Hong Kong and the European Commission for waste incineration.
4.3.1.4
Cumulative air quality impact
assessment has been undertaken for the Project at the artificial island near
SKC. The cumulative air quality
impact assessment has taken into account the emissions from both regional and
local sources, including the emissions within the Pearl River Delta Economic
Zone and major local air pollution sources in
4.3.1.5 Besides, odour nuisance may arise from the operation of the on-site wastewater treatment plant, the waste reception halls, the waste storage areas and the mechanical treatment plant of the IWMF. The wastewater treatment plant, the waste reception halls and the waste storage areas would be fully enclosed and the odorous air in this facility would be extracted and used as combustion air for incineration to remove the odorous compounds. For the mechanical plant, they would be equipped with deodorizing system of 95% odour removal efficiency. Besides, the wastewater treatment plant, waste reception halls, waste storage areas and the mechanical treatment plant would also be operated under negative pressure to prevent odour leaking to the outdoor environment. The predicted cumulative odour concentrations would comply with the criteria required in the EIAO-TM. Adverse odour impact on nearby ASRs would not be expected.
4.3.2 Noise Impact
Construction
Phase
4.3.2.1 The assessment results have demonstrated that daytime noise criteria would not be exceeded by the predicted construction noise levels under the unmitigated scenario. Having said that, good practices for the control of noise emissions from construction sites are recommended to further eliminate the potential of noise impact. These include good site practices to limit noise emissions at source and the use of quiet plant and working methods, whenever practicable.
4.3.2.2 Besides, a construction noise EM&A programme is recommended to check the compliance of the noise criteria during normal daytime working hours.
Operation
Phase
4.3.2.3
Operation
noise impacts from fixed plant noise can be effectively mitigated by including
noise control treatment at the source during the design stage and implementing
the same during operation. Adverse residual operation noise impacts are not
anticipated. The need for noise
measurement during commissioning of fixed noise sources should be included in
the contract documents of the IWMF.
4.3.3 Water Quality Impact
Construction
Phase
4.3.3.1
The
potential sources of water quality impact arising during the construction phase
of the Project include construction site runoff and drainage, wastewater
generated from general construction activities and sewage from the
workforce. With the implementation
of the recommended mitigation measures and site practices outlined in ProPECC
PN 1/94 (Practice Note for Professional Persons on Construction Site
Drainage), no unacceptable residual impacts on water quality are expected.
4.3.3.2
To minimize dredging and
filling activities and the associated environmental impacts, cellular cofferdam
and breakwater instead of sloping seawall are proposed to be adopted. Large-scale sediment dredging is therefore
not anticipated for the proposed reclamation and breakwater
construction works at the
artificial island near SKC. Only small-scale dredging may be
required along the proposed cofferdam to remove the top 1m of clayey marine
deposit for installation of an anti-scouring protection layer. The water quality impact during the
dredging for anti-scouring protection layer has been quantitatively assessed
using the near field sediment dispersion model. The model results indicated that the
water quality impact generated from the dredging works would be localized and
minor under the mitigated scenario and would unlikely contribute to any
significant water quality impact.
Mitigation measures including the employment of silt curtain system,
control of dredging and filling rates etc. are proposed to ensure that no
unacceptable water quality impact would be resulted from the dredging works.
4.3.3.3
Besides, during installation of
submarine cables, the seabed sediment will be released at the bottom of the
water column which will result in high localized suspended sediment
concentrations. An analysis has
been undertaken to determine the potential transport of fine sediments
suspended into the water column during the cable laying process. The analysis results indicated that the
sediment disturbed during laying of the submarine cable will settle onto the
seabed within approximately 80m of the cable alignment. Since all the identified water sensitive
receivers are located beyond this impact zone and the whole submarine cable
installation works will be completed within a short duration, the potential
water quality impacts are considered short term and acceptable.
Operation
Phase
4.3.3.4
During
the operation phase, wastewater will be generated from the proposed
incineration plant and mechanical treatment plant. An on-site wastewater treatment plant
will be provided. All generated
wastewater will be discharged to the on-site wastewater treatment plant for
treatment. The treated effluent from the wastewater
treatment plant will be reused in the incineration
plant and mechanical treatment plant or for washdown and landscape irrigation
in the IWMF site. There would be no wastewater effluent
discharged to the coastal waters of Southern Water Control Zone (WCZ).
4.3.3.5
An
on-site desalination plant will be provided for supplying water to the
IWMF. Saline water would be
discharged from the desalination plant at a low discharge rate. The saline water has been quantitatively
assessed to be minor and adverse impacts on water quality due to the saline water
discharge would not be expected.
4.3.4 Waste Management Implications
Construction
Phase
4.3.4.1
The types of waste that would
be generated during the construction phase of the Project include dredged
marine sediment, construction and demolition (C&D) materials from foundation
works and piling works, general refuse from the workforce and chemical wastes
from the maintenance of construction plant and equipment. Provided that the wastes are handled,
transported and disposed of properly and good site practices and waste reduction
measures are implemented accordingly, adverse environmental impact is not
expected during the construction phase of the Project.
Operation
Phase
4.3.4.2
The end product from the
incineration process of the IWMF would be bottom ash, fly ash and air pollution
control residues which would be disposed of at landfill after checking for
compliance with the proposed incineration residue pollution control
limits. Pre-treatment of fly ash
and air pollution control residues by cement solidification or chemical stabilization
will be undertaken prior to disposal at landfill to ensure that pollutants
would not leach to the environment.
A small amount of non-combustible inert refuse (e.g. glass,
sand etc.) sorted out in the mechanical
treatment process would also be disposed of at landfill.
4.3.4.3 Limited amount of chemicals or chemical wastes would be used or generated from the IWMF operation. Good practices and response procedures for contamination prevention have been recommended. With proper implementation of the recommended practices and procedures, the potential for land contamination due to the IWMF operation is expected to be minimal.
4.3.5 Ecology
4.3.5.1
The waters to the south of
Lantau and
4.3.5.2 The key potential direct impact identified under the Project include permanent loss of 31 ha of important habitat for Finless Porpoise, covering the reclamation and the embayment area within breakwater. Mitigation measures proposed to mitigate the loss include firm commitment from the Project Proponent to seek to designate a marine park of approximately 700 ha in the waters between Soko Islands and Shek Kwu Chau, in accordance with the statutory process stipulated in the Marine Parks Ordinance by 2018, in order to tie in with the operation of the IWMF at the artificial island near SKC. Deployment of artificial reef and release of fish fry have also been proposed as additional enhancement measures for the loss of important habitat for Finless Porpoise and fisheries resources. For the indirect impacts on Finless Porpoise, such as acoustic disturbance, collision with vessels, and alteration of behavioural pattern during construction and operation phases, mitigation measures proposed include avoidance of noisy works during peak Finless Porpoise season, monitoring of exclusion zone, marine mammal watching plan, adoption of regular traffic route, and limitation of vessel speed to ten knots at areas with high Finless Porpoise sighting density. With the implementation of the proposed mitigation measures, adverse impacts on Finless Porpoise would be mitigated to acceptable level.
4.3.5.3
A total of 198 coral colonies
of small sizes and low coverage (<1%), comprising one hard coral and 7
octocoral species, within the proposed reclamation area may be directly affected. As all the corals to be affected were
recorded to be translocatable, coral translocation has been recommended to
avoid any direct loss. Other corals,
including the one uncommon species that are located along the
4.3.5.4
The
4.3.5.5 Besides the above marine works, the construction of the Project also involves laying of submarine cables between SKC and Cheung Sha as well as the construction of a landing portal at Cheung Sha. The benthos communities of the temporarily affected areas are expected to recolonise the seabed areas after the short period of submarine cable laying operation (about 20 working days). In view of the low to moderate ecological value of the subtidal habitats and temporary nature of the impact, the potential impact on subtidal habitat and the associated benthos communities due to submarine cable laying works is considered to be low. Moreover, considering the localized nature of sediment plume and short term duration of the works, as well as the natural adaption of fish, no significant impacts are expected on the potential fish spawning and nursery ground due to the submarine cable laying works. For the construction of Cheung Sha landing portal, considering the small scale of landing portal works, existing turbid condition, and absence of ecological sensitive receiver along the shoreline, with the adoption of good site practice and water quality control measures, potential impact on ecological resources during construction of Cheung Sha portal is considered to be acceptable.
4.3.5.6
Monitoring programmes for Finless
Porpoise, coral colonies, and
4.3.6 Fisheries
4.3.6.1 Permanent loss of 31 hectares of fishing ground, and 15.9 hectares of fisheries spawning and nursery ground, is expected. Indirect impact on fisheries due to elevation in suspended solids level during construction phase would be temporary and localized. Mitigation measures such as adoption of silt curtain, reduced dredging rate, and phasing of marine works have been recommended, in order to minimize adverse impact on water quality, hence protecting fisheries resources. During operation phase, although the rate of water intake for water supply at the desalination plant of the IWMF is slow, the potential impact from impingement and entrainment of fisheries resources would be further minimized by provision of screen at the seawater intake.
4.3.6.2 With the proper implementation of the recommended mitigation measures, potential impact on fisheries due to the Project is considered to be acceptable.
4.3.7 Health Impact
4.3.7.1 The cancer risk arising from exposure to compounds of potential concern (COPCs) associated with the emissions of the IWMF has been evaluated in this EIA. The highest incremental (excess) cancer risk arising from the IWMF is predicted to be 2.76x10-6 which is within the screening level of 1x10-5 adopted by USEPA and it is considered that the Project would not present an unacceptable risk and no further analysis is necessary. The highest predicted total Hazard Index (HI) at all receptors are well below 0.25, which is an initial exposure screening benchmark derived from a conservative approach by the USEPA. Cumulative acute non-carcinogenic health impact of the IWMF imposed to the worst impacted human receptors were assessed and compared with local and overseas guideline levels. It was concluded that the levels of non-carcinogenic chemicals were found to be insignificant when compared to the adopted/derived reference levels. For the classical COPCs of the HKAQO, while it is not possible to rule out adverse health effects from the IWMF with complete certainty, the impact on health from small additional air pollutants is likely to be very small and unlikely to be quantifiable.
4.3.7.2
As the vast majority of foods
in
4.3.7.3 The existing practices of transporting wastes in enclosed containers will be followed. With regards to the storage and handling of waste and ash, given that all the reception halls and ash storage pits will be fully enclosed with slightly negative air pressure and that closed grab will be use to grab waste and ash, leakage of any fugitive emissions to the outdoor environment is not expected. With the implementation of the recommended health risk control measures, the potential health impacts associated with the transportation, storage and handling of waste and ash are considered to be insignificant.
4.3.7.4
The IWMF will be designed and
operated to the most up-to-date standards and practice. The operator must also be well trained to
avoid any accidental events as well as to implement industry best practice with
reference to international standards and guidelines. To avoid or minimize the potential
health impacts associated with potential accidental events, an emergency
response plan will be developed and properly implemented for the IWMF. It should be noted that the emergency
response plan should be specific to the final design and operation of the
IWMF. The recommended preventive measures
include the use of best available techniques continuous and regular stack
emission monitoring, as well as conducting regular safety monitoring and
audit. With the implementation of
the recommended preventive measures and an effective emergency response plan
for the IWMF, the health impacts associated with any potential accidental
events could be minimized if not avoided.
4.3.8 Landscape and Visual Impact
Construction
Phase
4.3.8.1 During the construction phase, the impact to the landscape resources and landscape character areas would be “insubstantial”, except the Island Landscape (LCA1) which is rated as “moderate” and Seawater (LR3 & LCA2) which are rated as “substantial”.
4.3.8.2 During the construction phase, the visual impact to most of the visual sensitive receivers would be “moderate/ substantial”, and the visual impact to the sea travellers (VSR4) would be “substantial”. After the implementation of mitigation measures, the residual impact to the VSR4 would become “moderate/ substantial” during construction while most of the other VSRs become “slight/ moderate” or “moderate”.
Operation
Phase
4.3.8.3 During the operation phase, the impact to the landscape resources and landscape character areas would be “insubstantial”, except the Island Landscape (LCA1) which is rated as “moderate” and Seawater (LR3 & LCA2) which are rated as “substantial”.
4.3.8.4
To avoid direct impact to the
valuable landscape resources of SKC, such as the natural shoreline (LR2), the
reclamation area is designed not be connected to SKC. The coast of
4.3.8.5 For LR3, since the seawater will be permanently replaced by the reclamation area, this portion of landscape resource is lost and cannot be recovered or mitigated. However, the quantity of loss of the seawater as landscape resource is relatively small in comparison to the large extent of the adjacent seawater landscape. Together with other measures such as efficient site layout and use of cellular cofferdam for the construction of breakwater and the artificial island, the area occupied by the proposed works is reduced to practically minimum so that the impact to LR3 would be as small as possible.
4.3.8.6 For LCA2, apart from minimizing the landscape impact as mentioned above, extensive landscape areas and greening will be provided as a mitigation measure to improve the naturalness of the Project site. The provision of new landscape elements will transform the existing landscape character.
4.3.8.7 During the operation phase, the visual impact to most of the visual sensitive receivers would be “moderate/ substantial” or “moderate”, and the visual impact to the sea travellers (VSR4 & VSR12) would be “substantial” and “moderate/ substantial” respectively. As the view of these VSRs are of transient nature, the proposed works would unlikely create a prolonged visual impact to these VSRs.
4.3.8.8 Regarding the visual impacts induced by the reclamation and construction of facilities, mitigation measures are proposed including aesthetic design with a view to enhance the aesthetic quality and to blend in the proposed works into the natural surroundings, at the same time reducing the visual mass of the structure. This is achieved by rooftop and vertical greening along the building façade, use of natural materials with recessive colour, provision of sky gardens between the stacks, provision of observation deck to diminish the feeling of chimney, etc.
4.3.8.9 To maximize visual compatibility between the existing natural shoreline of SKC and the IWMF site, mitigation measure to adopt natural rocks with similar colour as the SKC rocky shore for the construction of breakwater and artificial shoreline will improve the visual quality.
4.3.8.10 After the implementation of the proposed mitigation measures, the residual impact to some of the visual sensitive receivers would be reduced to ‘slight/moderate’, and the residual impact to the sea travellers (VSR4 & VSR12) would become ‘moderate/substantial’ and ‘moderate’ respectively in day 1 of operation and ‘moderate’ and ‘slight/moderate’ respectively in year 10 of operation. The residual impact to some middle/ long distance VSRs such as Cheung Sha (VSR5), Pui O Beach (VSR8) and Tong Fuk Beach (VSR11) would remain “moderate” in year 10 of operation due to the fact that some of the mitigation measures such as rooftop and vertical greening would not easily be appreciated from a distance.
4.3.8.11 In conclusion, the potential landscape and visual impacts can be reduced by implementing the proposed mitigation measures during construction and operation phases. With reference to criteria defined in Annex 10 of the EIAO TM, the overall residual impacts are considered as “marginally acceptable with mitigation measures” after implementing the mitigation measures, that is to say “there would be some adverse effects, but these can be eliminated, reduced or offset by specific measures”.
4.3.9 Cultural Heritage Impact
4.3.9.1 Based on the results of the desktop review and survey, no archaeological site was identified within the study area. No adverse archaeological impact is expected.
4.3.9.2 Geophysical surveys were conducted to examine the marine archaeological potential in the proposed reclamation area, breakwater and cable corridor for the IWMF. A total of 12 unidentified objects were spotted within the geophysical survey area. To minimize the potential impact, the proposed alignments of the submarine cables were revised to avoid direct impact to five unidentified objects. The remaining seven unidentified objects would be directly affected by the proposed works. A diver inspection was carried out, trying to locate these seven unidentified objects and establish their archaeological potential. A detailed search was conducted, but nothing was located. The results of the geophysical survey and diver inspection indicate there are no archaeological resources within the proposed reclamation area, and therefore no adverse marine archaeological impact is anticipated due to the proposed reclamation.
4.3.9.3 One grade 3 historic building (Courtyard Complex on the SKC Treatment and Rehabilitation Centre of the Society for Aid and Rehabilitation of Drug Abusers) and four other built heritage structures with no grading are identified within the study area. However, due to large separation between the built heritages and the IWMF, no adverse impacts during the construction and operation phases are anticipated.
4.4
TTAL Site and
4.4.1 General
4.4.1.1 It is expected that the co-existing scenario with a 3,000 tpd IWMF at each of the sites would likely give rise to potential cumulative air quality and health impacts associated with aerial emissions from the two IWMFs during the operation phase. Other potential impacts arising from construction and operation of the two IWMFs would be localized at the respective sites and significant changes in the level of impacts specifically associated with the co-existence of the two IWMFs are not anticipated.
4.4.1.2 This EIA Report has provided an assessment of the potential air quality and health impacts associated with the operation of the two IWMFs at both the TTAL site and the artificial island near SKC, with the consideration of the potential cumulative impact from other concurrent projects in the vicinity of the TTAL site and the artificial island near SKC. Specific mitigation measures required for the Project, as well as an environmental monitoring and auditing programme, have been developed. A summary of the operation phase air quality and health impacts associated with this co-exist scenario is presented below.
4.4.2 Air Quality Impact
4.4.2.1
Advanced air pollution control system,
including SCR for NOx removal and activated carbon for dioxins removal and continuous
emissions monitoring system will be installed for the IWMF to ensure that the
emissions from the IWMF stacks will meet the proposed target emission limits
that is more stringent than those stipulated in
4.4.2.2
Cumulative air quality impact
assessment has been undertaken for the Project for the co-exist scenario. The cumulative air quality impact
assessment has taken into account the emissions from both regional and local
sources, including the emissions within the Pearl River Delta Economic Zone and
major local air pollution sources in
4.4.3 Health Impact
4.4.3.1 The cancer risk arising from exposure to compounds of potential concern (COPCs) associated with the emissions of IWMFs under the co-exist scenario is evaluated in this EIA Study. The highest incremental (excess) cancer risk arising from the IWMF is predicted to be 3.49x10-6 which is within the screening level of 1x10-5 adopted by USEPA and it is considered that the Project would not present an unacceptable risk and no further analysis is necessary. The highest predicted total Hazard Index (HI) at all receptors are well below 0.25, which is an initial exposure benchmark derived from a conservative approach by the USEPA. Cumulative acute non-carcinogenic health impact of the IWMF imposed to the worst impacted human receptors were assessed and compared with local and overseas guideline levels. It was concluded that the levels of non-carcinogenic chemicals were found to be insignificant when compared to the adopted/derived reference levels. For the classical COPCs of the HKAQO, while it is not possible to rule out adverse health effects from the IWMF with complete certainty, the impact on health from small additional air pollutants is likely to be very small and unlikely to be quantifiable.
5.1.1.1
The
EIA has determined the likely nature and extent of environmental impacts
predicted to arise from the Project.
Where necessary and practicable, the EIA has specified mitigation and
control measures to reduce the environmental impacts to acceptable levels.
5.1.1.2
With
the recommended mitigation measures applied and the adoption of advanced
technology, the Project would be environmentally acceptable and no unacceptable
residual impacts are anticipated.
The schedule of implementation of the recommended mitigation measures
has been provided in the EIA Report. Monitoring
requirements have also been specified in a separate EM&A Manual to ensure
proper implementation of the recommended mitigation measures.