7            Construction Dust Impact Assessment

This chapter presents the findings of the assessment of construction dust implications arising from the Project during the construction phase. All above-ground works areas with potential dust emission activities have been examined and their impacts assessed. With the implementation of on-site watering, potential environmental impacts associated with construction dust would be controlled to acceptable levels.

For the criteria as regards air quality impact assessment, reference shall be made to the Hong Kong Planning Standards and Guidelines (HKPSG), the Air Pollution Control Ordinance (APCO) (Cap.311), and Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO).

The APCO (Cap.311) provides the power for controlling air pollutants from a variety of stationary and mobile sources and encompasses a number of Air Quality Objectives (AQOs). In addition to the APCO, the following overall policy objectives are laid down in Chapter 9 of the Hong Kong Planning Standards and Guidelines (HKPSG) as follows:

a)   Limit the contamination of the air in Hong Kong, through land use planning and through the enforcement of the APCO, to safeguard the health and well-being of the community; and

b)   Ensure that the AQO for 7 common air pollutants are met as soon as possible.

Currently, the AQOs stipulate limits on concentrations for 7 pollutants including sulphur dioxide (SO2), Total Suspended Particulates (TSP), Respirable Suspended Particulates (RSP), Nitrogen Dioxide (NO2), Carbon Monoxide (CO), photochemical oxidants, and Lead (Pb).  The AQOs are listed in the table below.

Table 7.1: Hong Kong Air Quality Objectives (HKAQO)

 

Limits on Concentration, ug/m3 [1]

(ppm in brackets)

Pollutant

1-hr [2]

8-hr [3]

24-hr [3]

3-Month [4]

Annual [4]

Sulphur Dioxide

800

(0.3)

 

350

(0.13)

 

80

(0.03)

Total Suspended Particulates

500 [7]

 

260

 

80

Respirable Suspended Particulates [5]

 

 

180

 

55

Carbon Monoxide

30,000

(26.2)

10,000

(8.7)

 

 

 

Nitrogen Dioxide

300

(0.16)

 

150

(0.08)

 

80

(0.04)

Photochemical Oxidants (as ozone) [6]

240

 

 

 

 

Lead

 

 

 

1.5

 

Notes:

[1]   Measured at 298K and 101.325 kPa.

[2]   Not to be exceeded more than three times per year.

[3]   Not to be exceeded more than once per year.

[4]   Arithmetic mean.

[5]   Respirable suspended particulates means suspended particulates in air with a nominal aerodynamic diameter of 10 micrometres or smaller.

[6]   Photochemical oxidants are determined by measurement of ozone only.

[7]   Not an AQO but is a criterion for evaluating air quality impacts as stated in Annex 4 of TM-EIAO.

The key air emission source from Project is the dust generated during construction phase at above-ground works areas. In this regard, air pollutant of concern would only include total suspended particulates (TSP) which has been assessed in this study.  The dust emissions generated during grouting, bored tunnelling and drill-and-blast activities would be insignificant.

Existing Air Sensitive Receivers (ASRs) in the vicinity of the project include various residential developments, educational institution etc (see Section 7.4). Key existing air pollution sources that may bear upon the air quality at Project at construction phase including work sites demarcated for construction and railway works, barging facilities and haul roads located nearby. Details of air pollution emission sources are discussed in Section 7.5.

Historical air quality monitoring data from the monitoring stations, namely the Tsuen Wan, Kwai Chung, Sham Shui Po, Kwun Tong, and Central/Western Monitoring stations operated by EPD, have been examined.  The latest air quality monitoring data from 2006 to 2010 at these monitoring stations are tabulated in the table below. In order to determine the meaningful background air quality, the latest 5-year annual average would be adopted.

Table 7.2:   TSP Monitoring Data in 2006-2010

Monitoring Station

Annual TSP Concentration (ug/m3)

2006

2007

2008

2009

2010

5-year

Average

Tsuen Wan

82

79

67

63

63

70.8

(89%)

Kwai Chung

81

85

79

70

71

77.2

(96%)

Sham Shui Po

79

79

81

77

76

78.4

(97%)

Kwun Tong

75

82

72

70

67

73.2

(92%)

Central/ Western

78

77

78

73

76

76.4

(96%)

 

 

 

 

 

Average:

75.2

(94%)

Note:

% of AQO is provided in the bracket.

Monitoring results exceeded AQO are shown as bolded characters.

 

The existing environment of the study area in Kowloon is mainly a densely populated and developed area with a mix of residential, commercial and institutional development. Given the developed nature of the study area and the similarity with the area surrounding EPD’s monitoring stations in urban area, including Tsuen Wan, Kwai Chung, Sham Shui Po, Kwun Tong, and Central/Western Monitoring Stations, it is considered reasonable to adopt all the monitoring data from these stations to represent background conditions in the Kowloon Area. As such the background TSP concentration of 75.2 ug/m3 is therefore adopted.

Construction of the project will involve the emission of fugitive dusts and hence TSP has to be assessed for construction phase air quality impact. During the operational phase, only electrified trains would be operated and hence there will not be air quality emission.

7.4.1       Air Sensitive Receivers

With reference to EIA Study Brief No. ESB-233/2011 for Project, the study area for air quality impact assessment should generally be defined by a distance of 500m from the boundary of Project Site.  Further, it should be extended to include major emission sources that may have a bearing on the environmental acceptability of the project.  The study will also review the air quality impacts on the areas and other sensitive receivers beyond 500m from the Project site boundary, which may be potentially affected by the Project.

In accordance with Annex 12 of the TM-EIAO, Air Sensitive Receivers (ASRs) include domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre. Any other premises or places with which, in terms of duration or number of people affected, has a similar sensitivity to the air pollutants as the aforelisted premises and places would also be considered as a sensitive receiver. Representative ASRs within a distance of 500m from the alignment, temporary work areas, and associated barging facilities have been identified.

These ASRs include both the existing and planned developments. Existing ASRs are identified by means of reviewing topographic maps, aerial photos, land status plans, supplemented by site inspections. They mainly include developed residential buildings with different storey high, educational institution of few storey high and hotels etc.

Planned/committed ASRs are identified by making reference to relevant Outline Zoning Plans (OZP), Outline Development Plans, Layout Plans and other published plans in the vicinity of the alignment, including:

·        Approved Tsim Sha Tsui (KPA 1) Outline Zoning Plan (No. S/K1/26);

·        Draft Yau Ma Tei (KPA 2) Outline Zoning Plan (No. S/K2/21);

·        Draft Ho Man Tin (KPA 6&7) Outline Zoning Plan (No. S/K7/21);

·        Approved Wang Tau Hom & Tung Tau (KPA 8) Outline Zoning Plan (No. S/K8/21)

·        Approved Hung Hom (KPA 9) Outline Zoning Plan (No. S/K9/24);

·        Approved Tsz Wan Shan, Diamond Hill & San Po Kong (KPA 11) Outline Zoning Plan (No. S/K11/25);

·        Draft Kai Tak (KPA22) Outline Zoning Plan (No. S/K22/3)

The relevant stakeholders were also approached to obtain latest information on planning application, layout and building height.  The major planned uses in the vicinity of the area include:

·       Kai Tak Further Development proposed in Agreement No. CE35/2006 (CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction (Approved EIA Report: EIA-157/2008)

The locations of the representative ASRs for air quality assessment during the construction of the project are illustrated in Figures 7.1.1 to 7.1.3, and are summarised in the table below. Detailed information of representative ASRs are presented in Appendix 7.1.

Table 7.3: Representative air sensitive receivers

ASR ID

Location

Landuse [1]

No. of Storey

Approximate separation distance from project site boundary (m)

DIH-5

Residential Premises along Fung Tak Road and Lunk Fung Street

DIH-5-1

Rainbow Home

R

11

70

DIH-5-2

Residential premises

R

6

70

DIH-5-5

Our Lady’s Kindergarten

E

2

60

DIH-6

Wong Tai Sin Fire Station and Quarters

DIH 6-1

Wong Tai Sin Fire Station and Quarters Block A

R

34

100

DIH-7

Tropicana Gardens

DIH-7-1

Tropicana Gardens Block 2

R

25

190

DIH-7-2

Tropicana Garden Block 3

R

25

190

DIH-8

Redmption Lutheran Church

DIH-8-1

Redemption Lutheran Church

W

3

130

DIH-9

Shek On Building

DIH-9-1

Shek On Building

E + W

5

30

DIH-10

Hong Kong Sheung Hui Nursing Home

DIH-10-1

Hong Kong Sheung Keung Hui Nursing Home

H

9

30

DIH-11

Lung Poon Court

DIH-11-1

Lung Poon Court – Lung Wan House

R

34

<10

DIH-12

Galaxia

DIH-12-1

Galaxia Tower B

R

44

100

DIH-12-2

Galaxia Tower E

R

43

40

DIH-13

Canossa Primary School

DIH-13-1

Canossa Primary School

E

5

80

DIH-14

Rhythm Garden

DIH-14-1

Rhythm Garden Block 2

R

22

<10

DIH-14-2

Rhythm Garden Block 5

R

22

<10

DIH-14-3

Rhythm Garden Block 8

R

22

110

DIH-14-4

Canossa Primary School (San Po Kong)

E

6

90

DIH-14-5

Rhythm Garden Block 1

R

22

<10

DIH-14-6

Rhythm Garden Block 3

R

22

<10

DIH-15

Choi Hung Estate

DIH-15-1

Choi Hung Estate - Kam Wan House

R

20

100

DIH-15-2

Choi Hung Estate - Pik Hoi House

R

20

100

DIH-17

Chuk Yuen United Village

DIH-17-1

Chuk Yuen United Village

R

1-3

60

DIH-25

Choi Hung Road Playground

DIH-25-1

Football Field in Choi Hung Road Playground

GIC

-

80

DIH-26

Hammer Hill Road Leisure Pool

DIH-26-1

Hammer Hill Road Leisure Pool

GIC

-

270

KAT-1

Kowloon Cognito College

KAT-1-1

Kowloon Cognito College

E

5

210

HOM-3

Residential Premises along Shun Yung Street

HOM-3-1

Fook Sing Mansion

R

18

240

HOM-3-2

Marigold Mansion Block A

R

20

280

HOM-4

Residential Premises along Valley Road

HOM-4-1

Yee Fu Building

R

25

170

HOM-5

271 Chatham Road North

HOM-5-1

271 Chatham Road North

R

5

110

HUH-1

Residential Premises and Educational Institution along Chatham Road North and Hong Chong Road

HUH-1-1

Cartas Branchi College of Careers [2]

E

8

60

HUH-1-2

Lok Ka House

R

7

20

HUH-1-3

Wing Fung Building

R

8

<10

HUH-2

The Hong Kong Polytechnic University

HUH-2-1

Hong Kong Polytechnic University - Cheung On Tak Lecture Theatre

E

6

100

HUH-3

Residential Premises along Shun Yung Street

HUH-3-1

Royal Peninsula Block 2

R

42

140

HUH-4

The Metropolis Residence

HUH-4-1

The Metropolis Residence Tower 2

R

18

130

HUH-5

Harbour Plaza Metropolis

HUH-5-1

Harbour Plaza Metropolis

R

11

90

HUH-6

HK Fire Service Headquarters Building

HUH-6-1

HK Fire Services Headquarters Building

GIC

13

90

HUH-7

Hotel Nikko Hong Kong

HUH-7-1

Hotel Nikko Hong Kong

R

12

100

HUH-9

Hong Kong Coliseum

HUH-9-1

Hong Kong Coliseum

P

1

<10

HUH-10

Harbourfront Horizon

HUH-10-1

Harbourfront Horizon

R

22

240

HUH-11

China Travel Cargo Logistic Centre

HUH-11-1

China Travel Cargo Logistic Centre

I

-

30

Note:

[1]   R– residential; E – educational; I – Industrial; H – clinic/ home for the aged; W – worship; GIC – government, institution and community; P – performing arts centres

Table 7.4:   Planned ASRs

ASR ID

Location

Landuse [1]

No. of Storey

KAT-P1

Residential premises near Kai Tak Station

KAT-P1-1

Residential premises near Kai Tak Station

R

[3]

KAT-P1-2

Residential premises near Kai Tak Station

R

[3]

KAT-P1-3

Residential premises near Kai Tak Station

R

[3]

KAT-P1-4

Residential premises near Kai Tak Station

R

[3]

KAT-P1-5

Residential premises near Kai Tak Station

R

[3]

KAT-P1-6

Residential premises near Kai Tak Station

R

[3]

KAT-P1-7

Residential premises near Kai Tak Station

R

[3]

KAT-P2

Public Housing Development at ex-San Po Kong Flatted Factory

KAT-P2-1

Public Housing Development at ex-San Po Kong Flatted Factory

R

[2]

HOM-P2

Proposed Dormitory for HKPU

HOM-P2

Proposed Dormitory for HKPU

R

-

Notes:

[1]   R– residential; E – educational; H – clinic/ home for the aged; W – worship; GIC – government, institution and community; P – performing arts centres

[2]   To be determined by respective project proponents

[3]   Not available from approved EIA Report: EIA-157/2008

7.4.1       Air Pollution Sources

Construction of the Project would inevitably generate air pollutants with potential impacts on neighbouring sensitive receivers.  As discussed in Section 3, the key elements under this EIA include the HHS at Hung Hom Freight Yard, construction of KAT and DIH, and the modification works at HUH. It should be noted that the EIA studies for SCL (MKK-HUH), SCL (HUH-ADM) and SCL (TAW-HUH) are assessed based on the design option of Diamond Hill Stabling Sidings (DHS). The worksites for the construction of HHS option considered in this EIA would therefore be different from the abovementioned EIA studies.

These air pollutant emission sources include fugitive dust from various construction activities, including excavation, stockpiling, and cut-and cover section for Project and fugitive dust from stockpiles within ex- Kai Tak Airport etc. There would be no concrete batching plant operating under the SCL (HHS).

Apart from the above construction activities, loading and unloading of materials at barging facilities for other projects would also generate potential dust impact. Based on the latest construction programme, 2 barging facilities will be needed to support the material transfer for SCL (MKK-HUH) and SCL (TAW-HUH). The locations of these barging facilities are listed below:

·       Freight Pier at Hung Hom (shared use); and

·       Kai Tak Runway

The proposed stabling sidings will be electrically operated, air quality impact associated with train emission is therefore not anticipated. Exhausts for general ventilation and smoke extraction facilities will also be carefully positioned to avoid causing nuisance to the surrounding environment. In addition, only light maintenance such as occasional track washing will be carried out during the operation of HHS. No significant air quality impact is therefore anticipated during the operational phase.

Since freight train (with diesel locomotive) operations have been discontinued, and intercity service would remain the same in fairly low frequency, less emission would be envisaged from diesel locomotives as compared to the current situation. No additional gaseous emission associated with diesel combustion, and hence no adverse operational air quality impact is therefore anticipated.

7.4.2       Potential Concurrent Projects

The tentative commencement year for the construction of Project is 2012, and would take approximately 6 years for completion. All concurrent projects, which may have cumulative environmental impacts during its construction period, have been identified and summarised in the table below. Details of these concurrent projects are given in Section 7.5.3.

Table 7.5:   Key Concurrent Projects for Air Quality Assessment

Key Concurrent Projects

Tentative Construction Programme

Central Kowloon Route

2015 – 2020

Trunk Road T2

2012 – 2016

Kai Tak Development

2009 – 2021

Shatin to Central Link – Tai Wai to Hung Hom Section

2012 – 2018

Shatin to Central Link – Mong Kok East to Hung Hom Section (Phase I)

2012 – 2018

Shatin to Central Link – Hung Hom to Admiralty Section (Phase II)

2012 – 2020

Kwun Tong Line Extension

2011 – 2015

Polytechnic University Student Hostel at Ex-Valley Road Site

2009 – 2012

Tsz Wan Shan Pedestrian Link

2013 – 2015

There are 3 existing concrete batching plants (CBPs) within the ex-Kai Tak Airport area, including the Yue Xiu CBP, Glorious CBP, and Yau Lee CBP. Based on the latest information provided by relevant government departments, the Yue Xiu CBP, Glorious CBP and the associated sand depot would cease operation before SCL commences construction. The dust emissions from the Yau Lee CBP, on the other hand, have been included in the cumulative impact assessment. In addition, the landlot next to the proposed TKW (as shown in Appendix 7.5) could be used for concrete batching plant or sand depot under short-term tenancy. Although the newly identified sites are yet to be confirmed, their potential emissions have been included in this assessment.

7.5.1       Potential Source of Dust

A review has been conducted on the construction methodology (see Section 3 for details) for various works areas at DIH, KAT and HHS. Construction dust will be potentially generated from mainly the land-based construction works including the following activities:

·       Soil excavation;

·       Backfilling;

·       Temporary storage of spoil on site;

·       Construction of portals and cut-&-cover tunnel;

·       Temporary storage, handling and transportation of material at tunnel exit sites;

·       Construction of infrastructure and utilities; and

·       Loading and unloading of excavated materials / fill materials at barging facility

Since excavation and backfilling activities will involve large quantities of earthworks and silty material handling, it is anticipated that there may be elevated dust levels due to these activities if appropriate mitigation measures are not implemented.

7.5.2       Assessment Year

A review of the tentative construction programme has been conducted to identify the construction period which is deemed to have significant impact on nearby ASRs. Based on the construction programme as shown in Appendix 7.2, it is identified that all the dusty construction activities, such as cut-&-cover  and open cut excavation, would be taken place during Year 2014, particularly the worksites for KAT, where cumulative impacts from other projects in Kai Tak area are anticipated.

7.5.3       Emission Inventory

Dust Emission associated with the Project

Fugitive dust impact assessments were carried out based on conservative assumptions of general construction activities which include the following:

·       Heavy construction activities including site clearance, ground excavation, construction of the associated facilities, haul road etc;

·       Wind erosion of all active open sites, including stockpile and barging area;

·       Loading/unloading from trucks at barging facilities and stockpiles;

·       All construction activities at work sites and areas that would be undertaken concurrently during the major construction period throughout Year 2014 in order to assess the worst case situation

·       12 hours a day from 7:00am to 7:00pm, except Sundays and public holidays.

The prediction of dust emissions is based on typical values and emission factors from United States Environmental Protection Agency (USEPA) Compilation of Air Pollution Emission Factors (AP-42), 5th Edition. Calculation of dust emission factors is given in Appendix 7.3.  References of the calculations of dust emission factors for different dust generating activities are listed below.  Detailed descriptions are also discussed in the following sections.

Table 7.6a: References of Dust Emission Factors for Different Activities

i)              SCL – Stabling Sidings at Hung Hom Freight Yard – Heavy Construction Works, Wind Erosion and Stockpile

Dust emission from construction vehicle movement will generally be limited within the confined worksites area and the emission factor given in AP-42 S.13.2.3.3 has taken this factor into account, as indicated in the approved EIA Study “Kai Tak Development” (EIA-157/208).  Watering facilities will be provided at every designated vehicular exit point.  Haul roads within the work sites would be paved and water spraying would be provided to keep them in wet condition. Since all vehicles will be washed at exit points and vehicle loaded with the dusty materials will be covered entirely by clean impervious sheeting before leaving the construction site, dust nuisance from construction vehicle movement outside the worksites is unlikely to be significant.

For stockpiling, it is recommended that vehicles will move to the stockpiling areas where C&D materials will be unloaded immediately. The vehicles will then be washed again before leaving the stockpiles in order to minimise generation of dusty materials. Therefore, the major dust generating activities at stockpiling areas will be originated mainly from wind erosion and loading/unloading of materials; and these will be assumed in the fugitive dust modelling.

For the calculation of 1-hour and 24-hour TSP concentration, an active operating area of 30% has been assumed at any one time. Based on the justification for the percentage of active area provided in Appendix 7.4, the actual percentage active area associated with construction works would however be less than 30% during the construction period. However, in order to be conservative, a 100% active area screening test has been undertaken initially for the short term hourly and daily TSP assessment as detailed in the Section 7.5.4.

For the calculation of annual TSP construction, the active works area over the entire year would be less than for a typical hour and typical day.  On this basis, further information has been obtained from the Project Proponent, and it is confirmed that a 6% active operating area would be a practicable assumption. The active operating area for 1-hr, 24-hr and annual concentration has been agreed by the Engineer. Appendix 7.4 presents the justification for the percentage of active areas.

It should be noted that there would still be some minor construction works being conducted during grouting. However, as all grouting works would be carried out in a caution way and fugitive dust generation can be controlled at a minimum level, there would be insignificant fugitive dust impacts from this source.

Dust Emission associated with Concurrent Projects

i)              SCL – Tai Wai to Hung Hom Section

All the construction works, including site clearance, ground excavation, cut-&-cover tunnel section etc., presented in the EIA report for SCL (TAW-HUH) would be included in this assessment to account for the cumulative impacts. However, it should be noted that the construction works under the HHS options at KAT and DIH will be different from the original configuration adopted in the SCL (TAW-HUH) EIA. Hence dust emissions from the construction of Diamond Hill Stabling Siding (DHS), KAT and DIH based on the scheme assessed in the SCL (TAW-HUH) would be superseded and would not be included in the cumulative assessment as it is assumed in this EIA that the HHS options would be adopted and emissions from the construction of these elements are assessed based on the scheme proposed under the Project. Nevertheless, dust emission from the barging facilities adjacent to To Kwa Wan Typhoon Shelter (i.e. Kai Tak Runway) associated with SCL (TAW-HUH) would be included in the cumulative assessment in this EIA. Latest available information has been obtained from the EIA for SCL (TAW-HUH) and is adopted in the assessment.

ii)             SCL – Mong Kok East to Hung Hom Section and Hung Hom to Admiralty Section

The other sections of the SCL, namely Mong Kok East to Hung Hom Section (SCL (MKK-HUH)), and Hung Hom to Admiralty Section (SCL (HUH-ADM)) would also have cumulative impacts. SCL (MKK-HUH) will include the realignment work for the existing East Rail Line tracks from south of Mong Kok East to the new HUH, while SCL (HUH-ADM) will include the construction of the section across the harbour from Hung Hom to Admiralty. Similar to the case for DHS, KAT and DIH mentioned above, since it is assumed in this EIA that the HHS option would be adopted, dust emission from the construction of HUH based on the scheme assessed in the SCL (MKK-HUH) would not be included in the cumulative assessment. Emission from the construction of HUH would be assessed as per the scheme proposed under the Project.

According to the current construction programme, construction works and dusty activity at the Freight Pier barging facility associated with the SCL (MKK-HUH) and SCL (HUH-ADM) will be interfacing this Project at Hung Hom Area. Appendix 7.6 illustrates the possible arrangement in Freight Pier Barging Facility. As such, cumulative dust impact is therefore anticipated. Dust emission details have been obtained from the respective consultant and included in the assessment to account for the cumulative effect.

iii)            Kwun Tong Line Extension (KTE) & associated EPIW

The KTE project is approximate 3km extension of the existing Kwun Tong Line from Yau Ma Tei Station to a new station at Whampoa and with an interchange with the SCL at the proposed HOM. It is expected to be completed in 2015.

With reference to the approved EIA Study “Kwun Tong Line Extension” (AEIAR-154/2010), construction works under KTE Project will likely be interfacing the Project in Hung Hom and Ho Man Tin areas. Potential dusty activities are generally similar to those associated with this Project. In particular, one rock crushing facility would be located at the worksite in HOM Station and two others would be located at the Freight Pier barging point. Hence, dust emissions are anticipated during unloading activities and the discharge point of the dust extraction systems. As such, cumulative dust impact is therefore anticipated. Dust emission details have been extracted from the approved EIA Study and all the assessment scenarios have been included in the assessment to account for the cumulative effect.

iv)            Kai Tak Development

Redevelopment plan for the former Kai Tak Airport area is proposed to optimise the development potential of the ex-airport site. It covers a land area of about 328 hectares, including the ex-Kai Tak Airport and existing waterfront area at To Kwa Wan, Kowloon Bay etc. According to the current development plan, the infrastructure works are split into 7 sub-packages, such as Cruise Terminal Development, Trunk Road T2 etc. This development is anticipated to commence in 2009, with completion beyond 2020. A summary of infrastructures included in this assessment is given below:

·         Trunk Road T2;

·         Multi-purpose Stadium Complex;

·         Kai Tak Nullah;

·         Other infrastructures, including pumping stations, local roads and distributors.

Based on the construction programme presented in LegCo Papers on Kai Tak Development (LC Paper No. CB(1)570/08-09(03)), cumulative construction dust impact is expected during the interaction with major dusty construction works associated with the Project, which is expected to be undertaken in Year 2014. For the purpose of cumulative impact assessment, construction works which are located within 500m from the site boundary of this Project and are found to be overlapping with the major construction of Project during Year 2014 will be included. In addition, dust emission strengths presented in the approved EIA Study “Kai Tak Development” (KTD) (AEIAR-130/2009) are adopted where appropriate.

v)             Central Kowloon Route

Central Kowloon Route (CKR) is a strategic road linking from Yau Ma Tai area to Kowloon Bay in order to relieve the vehicular traffic loading on the existing urban distributor roads. Based on the latest construction programme, the construction would likely be commenced in early 2015. For the purpose of conservative assessment, the associated construction works are considered to be overlapping with the construction of the Project and the cumulative construction dust impact is therefore taken into account. Latest available information presented in the KTD EIA is adopted where appropriate in the assessment.

vi)            Trunk Road T2

Trunk Road T2 is a dual two-lane trunk road of approximately 3.6 km long connecting the CKR and Tseung Kwan O-Lam Tin Tunnel, and will form a new strategic highway network in order to relieve the existing heavily trafficked road network in the central and eastern Kowloon as well as Tseung Kwan O. However, the alignment of Trunk Road T2 is located at more than 500m from ASRs of the Project. No significant cumulative air quality impact is therefore anticipated.

vii)           Polytechnic University Student Hostel at Ex-Valley Road

A student hostel to accommodate students from the Polytechnic University is proposed at the site bounded by Yan Fung Street to the North, Fat Kwong Street to the East, and Chatham Road North to the South. However, the construction will be completed by Year 2012. Hence, the associated cumulative air quality impact is not anticipated.

viii)          Tsz Wan Shan Pedestrian Link

Covered walkway as well as lifts/escalators are proposed to connect the Tsz Wan Shan residential to the DIH Station. Based on the current construction programme, the associated construction works would likely interface with the major construction of the Project during Year 2014. Hence, cumulative dust impact is anticipated.

ix)            Concrete Batching Plants in ex-Kai Tak Airport area

As discussed in Section 7.5, there are currently 3 existing concrete batching plants (CBPs) within the ex-Kai Tak Airport area, including the Yue Xiu CBP, Glorious CBP, and Yau Lee CBP. Based on the latest information, the Yue Xiu CBP, Glorious CBP and the associated sand depot would cease operation before SCL commences construction.  Hence, there would not be cumulative dust impacts from these 2 CBPs at their existing locations. The dust emissions from the Yau Lee CBP, on ther other hand, have been included in the cumulative impact assessment.

It was noted at the time of reporting that the site next to TKW (as shown in Appendix 7.5) could be allocated for the use of a new concrete batching plant and sand depot under short-term tenancy. However, information on the capacity of these facilities was not available for the assessment.  In order to reasonably consider cumulative impacts from the emissions of these potential albeit not yet committed sources, an estimation of the capacity of these facilities was made with reference to general practices of the industry.  It was assumed that the production capacity of the concrete batching plant would be 280 m3 per hour and the total silo capacity would be 1050 tonnes. Dust emissions associated with the plant, including emission from the dust collectors of silos and mixers, and unloading of raw material to ground hopper within the plant and Kai Tak Barging Facility, have therefore been assessed.

However, it should be noted that, the concrete batching plant is controlled under the Specified Process and hence sufficient mitigation measures would be implemented to control the emission of dust. In general, the requirement and mitigation measures stipulated in the Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) should be followed and implemented. In particular, in order to minimise the overall dust impact on nearby ASRs, the emission concentrations of the dust collector for the cement/PFA silos and mixer could be designed to not more than 30 mg/m3 and 40 mg/m3 respectively. For unloading of aggregate from trucks at the concrete batching plant, 3-sided enclosure with top cover and water sprays could be provided to the ground hopper. The enclosure could be designed in such a way that would minimise the gap between the enclosure structure and the truck itself, which in turn would prevent dust from escaping the enclosure. With provision of watering spraying system, dust generated from unloading activities would be further suppressed within the enclosure, and hence would achieve an overall dust removal efficiency of 95%. The above assumptions have therefore been adopted for the purposed of potential cumulative impact assessment in this EIA. However, it is understood that the design of the potential new CBP is still subject to change. Once the use of the site is committed, the Contractor is required to demonstrate that the future design of the concrete batching plant would not cause unacceptable impacts. References of the calculations of dust emission factors for different dust generating activities are listed below.

Table 7.6b: References of Dust Emission Factors for Concrete Batching Plant

7.5.4       Assessment Methodology

Dust impact assessment was undertaken using the Fugitive Dust Model (FDM) as approved by USEPA and EPD.  It is a well-known Gaussian Plume model designed for computing air dispersion model for fugitive dust sources.  Modelling parameters including dust emission factors, particles size distributions, surface roughness, etc are referred to in EPD’s “Guideline on choice of models and model parameters” and USEPA’s AP-42.  The density of dust will be assumed to be 2.5g/m3.  The 5-year mean of the annual averaged TSP concentration will be taken as the background concentration.  As mentioned in Section 7.3, the TSP background concentration of 75.2ug/m3 is adopted for the fugitive dust modelling. A surface roughness of 100 cm is assumed in the model to represent the terrain.

During daytime working hours (7am to 7pm), it is assumed that dust emissions would be generated from all dust generating activities and site erosion. During night-time non-working hours (7pm to 7am of the next day), Sunday and statutory holidays, dust emission source would only be site erosion as construction activities during these hours are ceased.

The worst-case 1-hour, worst-case 24-hour average and annual TSP concentrations were calculated mainly based on real meteorological data (for Year 2008) on wind direction, wind speed, temperature and stability collected from the nearest weather station, the Hong Kong Observatory meteorological station for the construction site in the Kowloon Area. The anemometer height at Hong Kong Observatory is 42m above ground. A summary showing the validity of meteorological data from Year 2004 – 2008 respective to different weather stations is shown in Table 7.7.

Table 7.7:   Summary of data validity of meteorological data from Year 2004 – 2008

Stations

Data Validity

2004

2005

2006

2007

2008

Kai Tak

91%

96%

96%

89%

81%

King's Park

89%

92%

87%

90%

92%

HKO

97%

96%

95%

95%

95%

CPH

92%

94%

94%

93%

N/A

Fugitive dust assessment was conducted at 1.5m, 5m, 10m, 15m and 20m above local ground level. A summary of modelling parameters adopted in the assessment are given in the table below:

Table 7.8:   Modelling Parameters

Parameters

Input

Remark

Particle size distribution

1.25um = 7%

3.75um = 20%

7.5um = 20%

12.5um = 18%

22.5um = 35%

Reference from S13.2.4.3 of USEPA AP-42

Background Concentration

5-year averaged value recorded at Tsuen Wan, Kwai Chung, Sham Shui Po, Kwun Tong and Central/Western Monitoring Stations

Tsuen Wan, Kwai Chung, Sham Shui Po, Kwun Tong, Central/Western Monitoring Stations for Kowloon Area (75.2 μg/m3­­­­)

Modeling mode

Flatted terrain

-

Meteorological data

Data recorded in 2008 at Hong Kong Observatory (HKO) Meteorological Station

HKO for Kowloon Area (i.e. DIH to HUH)

 

Anemometer Height

42m for HKO

-

Surface Roughness

100cm

-

Emission period

General construction activities during daytime working hours (7 am to 7 pm)

Wind erosion during both day-time (7am to 7pm) and night-time (7pm to 7am of the next day)

-

ASR calculating levels

1.5, 5, 10, 15, and 20m

-

In terms of the construction programme, it should be noted that the sequencing of works for each works activity over each works site or area will be determined by the Contractor and is not known at this stage.  However, due to the constrained size of the works sites and areas and the tight construction programme constraints, it will be necessary for active construction activities to be undertaken at moving multiple work phases spread across each site.  Therefore, it is not feasible to identify the exact locations of individual dust emission sources.  As such, for the long term annual predictions, the dust modelling assessment has assumed that the dust emissions would be distributed across the whole area of each site to reasonably represent this mode of working and the dust emission rates have been proportioned to produce the effect of 6% active works site. Appendices 7.2 and 7.4 present the tentative construction programme and justification for the percentage of active areas respectively.

For the short term 1-hour and 24-hour periods, it is assumed that a total works area of 30% on each site would only be active at any one time and again active construction activities to be undertaken at moving multiple work faces spread across each site. Based upon this, works activities and plant would neither cover the whole site area nor be concentrated in certain areas of the site close to ASRs at any time during the construction period.  However, notwithstanding that such a scenario would not be expected to occur, in order to be conservative, an initial screening test has been undertaken, namely “Tier 1 Screening Test”.  The Tier 1 screening test is conservative and has simulated an absolute worst case situation, whereby all the worksites would be active (i.e. 100%).

The purpose of this absolute worst case Tier 1 screening assessment is to highlight those areas where construction dust may accumulate and potentially become an issue. The hot spot areas identified in the Tier 1 assessment have been subsequently assessed by a more focused Tier 2 test, where it is assumed that the projected actual 30% active works areas for the construction site is positioned closest to the potentially worst affected ASRs, while emission from all the other sites remain at 100% as per Tier 1. Thus, the Tier 2 assessment is also very conservative as it assumes that all works activities with the associated plant would be undertaken in the closest proximity to the potentially affected ASRs at the same time, which as noted above would not occur.

For the concurrent projects, including SCL (TAW-HUH), SCL (MKK-HUH), SCL (HUH-ADM), KTE, the Polytechnic University Student Hostel, and the Tsz Wan Shan Pedestrian Link, similar assumptions have been made for the calculations of the emission factors for short and long-term assessments. For the committed Kai Tai Development (KTD), as mentioned above, the dust emission strength presented in the approved KTD EIA are adopted where appropriate.

7.5.5         Assessment Results - “Unmitigated” Scenario

Cumulative construction dust impacts arisen due to the construction of the Projects and concurrent projects listed in Section 7.5.3 have been assessed. Cumulative unmitigated 1-hour, 24-hour, and annual TSP levels predicted at identified ASRs are given in Tables 7.9a-b respectively. Results show that exceedances of the relevant Air Quality Objectives (AQOs) would be predicted without mitigation. Mitigation measures are considered necessary to reduce predicted dust impacts. Figures 7.2.0A – 7.2.0F illustrate the cumulative unmitigated 1-hour, 24-hour, and annual TSP concentrations in Diamond Hill-Kai Tak Area and Hung Hom-Ho Man Tin Area.

Table 7.9a:     Predicted Unmitigated Cumulative 1-hour and 24-hour TSP Concentrations at various heights above Ground (including background concentration of 75.2μg/m3)

ASR ID

Location

1-hour TSP Concentrations at various heightg/m3)

24-hour TSP Concentrations at various heightg/m3)

1.5m

5m

10m

15m

20m

1.5m

5m

10m

15m

20m

DIH-5-1

Rainbow Home

824

843

723

578

448

192

200

186

169

151

DIH-5-2

Residential premises

800

813

687

538

463

208

216

198

177

155

DIH-5-5

Our Lady’s Kindergarten

677

701

616

512

423

178

185

173

160

145

DIH 6-1

Wong Tai Sin Fire Station and Quarters Block A

951

962

804

618

458

218

223

199

173

153

DIH-7-1

Tropicana Gardens Block 2

1241

1216

941

646

487

322

321

267

208

160

DIH-7-2

Tropicana Garden Block 3

1139

1128

896

639

480

290

291

248

199

158

DIH-8-1

Redemption Lutheran Church

1339

1287

955

619

490

401

397

322

244

181

DIH-9-1

Shek On Building

1923

1753

1144

631

514

715

655

438

261

199

DIH-10-1

Hong Kong Sheung Keung Hui Nursing Home

1856

1678

1081

615

516

687

634

431

260

201

DIH-11-1

Lung Poon Court – Lung Wan House

3021

2343

1226

823

589

1102

638

331

262

222

DIH-12-1

Galaxia Tower B

1734

1651

1216

877

665

442

417

341

284

236

DIH-12-2

Galaxia Tower E

2168

1998

1368

922

679

469

464

388

308

243

DIH-13-1

Canossa Primary School

1560

1438

1000

619

505

583

555

407

267

197

DIH-14-1

Rhythm Garden Block 2

1726

1755

1446

1171

917

378

339

313

285

255

DIH-14-2

Rhythm Garden Block 5

3079

2965

2217

1517

988

402

401

347

289

237

DIH-14-3

Rhythm Garden Block 8

2149

2123

1648

1204

882

440

450

405

351

296

DIH-14-4

Canossa Primary School (San Po Kong)

1708

1488

1214

1005

790

546

487

325

263

242

DIH-14-5

Rhythm Garden Block 1

1997

1685

1402

1111

829

470

388

298

275

250

DIH-14-6

Rhythm Garden Block 3

1894

1958

1666

1326

1001

339

350

324

291

255

DIH-15-1

Choi Hung Estate - Kam Wan House

1870

1915

1599

1288

994

220

227

206

191

178

DIH-15-2

Choi Hung Estate - Pik Hoi House

2411

2472

2064

1602

1178

278

284

249

219

198

DIH-17-1

Chuk Yuen United Village

830

846

725

577

446

259

266

238

205

172

DIH-25-1

Football Field in Choi Hung Road Playground

1521

1375

882

638

526

390

367

271

211

181

DIH-26-1

Hammer Hill Road Leisure Pool

1615

1713

1525

1292

1046

211

220

203

183

164

KAT-1-1

Kowloon Cognito College

1336

1276

942

691

527

546

533

415

297

206

HOM-3-1

Fook Sing Mansion

511

551

512

469

426

162

170

163

155

147

HOM-3-2

Marigold Mansion Block A

476

518

489

454

416

154

162

157

151

143

HOM-4-1

Yee Fu Building

416

454

432

405

374

148

155

152

150

147

HOM-5-1

271 Chatham Road North

432

473

450

422

390

148

157

156

157

169

HUH-1-1

Cartas Branchi College of Careers [2]

429

470

448

421

390

164

158

158

158

157

HUH-1-2

Lok Ka House

462

458

432

429

405

191

161

158

166

166

HUH-1-3

Wing Fung Building

505

491

465

457

427

202

182

171

170

163

HUH-2-1

Hong Kong Polytechnic University - Cheung On Tak Lecture Theatre

1015

782

448

408

376

375

300

170

147

138

HUH-3-1

Royal Peninsula Block 2

1577

856

454

430

402

338

248

145

141

135

HUH-4-1

The Metropolis Residence Tower 2

926

774

430

384

361

304

271

190

148

132

HUH-5-1

Harbour Plaza Metropolis

1756

1230

549

367

321

287

257

184

137

127

HUH-6-1

HK Fire Services Headquarters Building

933

722

537

477

419

361

307

199

148

137

HUH-7-1

Hotel Nikko Hong Kong

1776

1354

601

461

412

367

300

175

144

135

HUH-9-1

Hong Kong Coliseum

Note [3]

Note [3]

394

374

352

Note [3]

Note [3]

170

134

127

HUH-10-1

Harbourfront Horizon

Note [3]

976

500

330

294

Note [3]

337

225

152

128

HUH-11-1

China Travel Cargo Logistic Centre

2179

936

467

440

410

650

277

176

145

138

KAT-P1-1

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-2

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-3

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-4

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-5

Residential premises near Kai Tak Station [4]

Note [3]

4872

2625

1505

1082

Note [3]

1010

601

400

286

KAT-P1-6

Residential premises near Kai Tak Station [4]

Note [3]

2106

1333

872

700

Note [3]

804

568

398

279

KAT-P1-7

Residential premises near Kai Tak Station

See Note [2]

KAT-P2-1

Public Housing Development at ex-San Po Kong Flatted Factory

1889

1843

1403

990

703

536

498

349

311

271

HOM-P2

Proposed Dormitory for HKPU

468

510

484

451

415

151

159

155

149

142

Notes:

Values which exceeded AQO are shown as bolded characters

 [1]  The population intake of this project would be after Year 2016 (Referenced from approved Kai Tak Development EIA Report), and hence there are no cumulative construction dust impact from the projects

[2]   The premises is located within the works site boundary, hence the population intake would be after the construction of the Project i.e. no impact from the Project

[3]   No air sensitive use is observed at such levels –

Hong Kong Coliseum (HUH-9-1):

Air sensitive use is on the podium of the HUH station, which is at least 10mAG. First assessment height is therefore considered at 10mAG.

Harbourfront Horizon (HUH-10-1):

The first floor of residential units is situated on the podium, which is at least 5m above ground. First assessment height is therefore considered at 5mAG.

Residential premises near Kai Tak Station (KAT-P1-5 / KAT-P1-6):

These residential premises are currently occupied for the construction of public rental housing, which would have a 5m height lift lobby on the ground floor. First assessment height is therefore considered at 5mAG

[4]   The assessment results are for indication only as there are no air sensitive uses when the Yau Lee CBP is in operation.

Table 7.9b:     Predicted Unmitigated Cumulative Annual TSP Concentrations at various heights above Ground (including background concentration of 75.2μg/m3)

ASR ID

Location

Annual TSP Concentrations at various heightg/m3)

1.5m

5m

10m

15m

20m

DIH-5-1

Rainbow Home

75.8

75.7

75.6

75.6

75.5

DIH-5-2

Residential premises

75.7

75.7

75.6

75.5

75.5

DIH-5-5

Our Lady’s Kindergarten

75.6

75.6

75.6

75.5

75.5

DIH 6-1

Wong Tai Sin Fire Station and Quarters Block A

75.8

75.8

75.8

75.7

75.6

DIH-7-1

Tropicana Gardens Block 2

76.2

76.3

76.1

76.0

75.8

DIH-7-2

Tropicana Garden Block 3

76.1

76.1

76.0

75.9

75.8

DIH-8-1

Redemption Lutheran Church

77.8

77.9

77.5

77.0

76.6

DIH-9-1

Shek On Building

80.7

80.5

79.3

78.1

77.2

DIH-10-1

Hong Kong Sheung Keung Hui Nursing Home

80.7

80.5

79.4

78.2

77.3

DIH-11-1

Lung Poon Court – Lung Wan House

81.9

77.7

76.2

75.8

75.6

DIH-12-1

Galaxia Tower B

76.8

76.7

76.3

76.0

75.8

DIH-12-2

Galaxia Tower E

76.2

76.1

75.9

75.7

75.6

DIH-13-1

Canossa Primary School

79.5

79.5

78.7

77.8

77.1

DIH-14-1

Rhythm Garden Block 2

76.6

76.5

76.2

75.9

75.7

DIH-14-2

Rhythm Garden Block 5

76.6

76.5

76.3

76.1

75.9

DIH-14-3

Rhythm Garden Block 8

77.0

76.9

76.5

76.2

76.0

DIH-14-4

Canossa Primary School (San Po Kong)

78.1

77.8

76.8

76.2

75.9

DIH-14-5

Rhythm Garden Block 1

77.0

76.7

76.2

75.9

75.7

DIH-14-6

Rhythm Garden Block 3

76.5

76.5

76.2

75.9

75.7

DIH-15-1

Choi Hung Estate - Kam Wan House

75.8

75.8

75.8

75.7

75.6

DIH-15-2

Choi Hung Estate - Pik Hoi House

75.9

75.9

75.9

75.8

75.7

DIH-17-1

Chuk Yuen United Village

76.1

76.1

76.0

75.9

75.8

DIH-25-1

Football Field in Choi Hung Road Playground

78.8

78.7

78.0

77.3

76.7

DIH-26-1

Hammer Hill Road Leisure Pool

75.8

75.9

75.8

75.7

75.6

KAT-1-1

Kowloon Cognito College

79.4

79.4

78.8

78.1

77.4

HOM-3-1

Fook Sing Mansion

76.3

76.3

76.3

76.2

76.1

HOM-3-2

Marigold Mansion Block A

76.2

76.3

76.3

76.4

76.3

HOM-4-1

Yee Fu Building

76.2

76.3

76.4

76.5

76.5

HOM-5-1

271 Chatham Road North

76.5

76.6

76.7

77.0

76.9

HUH-1-1

Cartas Branchi College of Careers [2]

76.7

76.7

76.6

76.6

76.5

HUH-1-2

Lok Ka House

77.0

76.6

76.4

76.4

76.3

HUH-1-3

Wing Fung Building

77.3

76.7

76.3

76.2

76.1

HUH-2-1

Hong Kong Polytechnic University - Cheung On Tak Lecture Theatre

78.8

78.3

77.2

76.6

76.2

HUH-3-1

Royal Peninsula Block 2

77.3

77.1

76.5

76.2

76.0

HUH-4-1

The Metropolis Residence Tower 2

76.5

76.4

76.2

75.9

75.8

HUH-5-1

Harbour Plaza Metropolis

77.4

77.2

76.7

76.3

76.1

HUH-6-1

HK Fire Services Headquarters Building

80.4

80.2

79.1

78.1

77.3

HUH-7-1

Hotel Nikko Hong Kong

79.8

79.4

78.3

77.5

76.8

HUH-9-1

Hong Kong Coliseum

Note [3]

Note [3]

76.4

76.1

75.9

HUH-10-1

Harbourfront Horizon

Note [3]

79.2

77.7

76.8

76.3

HUH-11-1

China Travel Cargo Logistic Centre

80.6

77.5

76.4

76.0

75.9

KAT-P1-1

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-2

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-3

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-4

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-5

Residential premises near Kai Tak Station [4]

Note [3]

83.3

78.7

77.3

76.7

KAT-P1-6

Residential premises near Kai Tak Station [4]

Note [3]

83.3

82.0

80.9

79.8

KAT-P1-7

Residential premises near Kai Tak Station

See Note [2]

KAT-P2-1

Public Housing Development at ex-San Po Kong Flatted Factory

78.3

78.2

77.5

76.8

76.4

HOM-P2

Proposed Dormitory for HKPU

76.2

76.3

76.3

76.4

76.2

Notes:

Values which exceeded AQO are shown as bolded characters

 [1]  The population intake of this project would be after Year 2016 (Referenced from approved Kai Tak Development EIA Report), and hence there are no cumulative construction dust impact from the projects

[2]   The premises is located within the works site boundary, hence the population intake would be after the construction of the Project i.e. no impact from the Project

[3]   No air sensitive use is observed at such levels –

Hong Kong Coliseum (HUH-9-1):

Air sensitive use is on the podium of the HUH station, which is at least 10mAG. First assessment height is therefore considered at 10mAG.

Harbourfront Horizon (HUH-10-1):

The first floor of residential units is situated on the podium, which is at least 5m above ground. First assessment height is therefore considered at 5mAG.

Residential premises near Kai Tak Station (KAT-P1-5 / KAT-P1-6):

These residential premises are currently occupied for the construction of public rental housing, which would have a 5m height lift lobby on the ground floor. First assessment height is therefore considered at 5mAG

[4]   The assessment results are for indication only as there are no air sensitive uses when the Yau Lee CBP is in operation.

7.5.6         Recommended Mitigation Measures for Fugitive Dust

In order to reduce the dust emission from the Project and achieve compliances of TSP criteria at ASRs, the following specific mitigation measures are recommended:

i)        Mitigation measures in form of regular watering under a good site practice should be adopted. In accordance with the “Control of Open Fugitive Dust Sources” (USEPA AP-42) as given in Appendix 7.4, watering once per hour on exposed worksites and haul road is proposed to achieve dust removal efficiency of 91.7%. These dust suppression efficiencies are derived based on the average haul road traffic, average evaporation rate and an assumed application intensity of 1.8 L/m2 for the respective watering frequencies (see Appendix 7.4).  Any potential dust impact and watering mitigation would be subject to the actual site conditions.  For example, a construction activity that produces inherently wet conditions or in cases under rainy weather, the above water application intensity may not be unreservedly applied.  While the above watering frequencies are to be followed, the extent of watering may vary depending on actual site conditions but should be sufficient to maintain an equivalent intensity of no less than 1.8 L/m2 to achieve the respective dust removal efficiencies.  The dust levels would be monitored and managed under an EM&A programme as specified in the EM&A Manual.

In addition to the abovementioned, the Contractor is also obliged to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation. It stipulates the construction dust control requirements for both Notifiable (e.g. site formation) and Regulatory (e.g. road opening) Works to be carried out by the Contractor. 

In accordance with the Air Pollution Control (Construction Dust) Regulation, the following dust suppression measures should also be incorporated by the Contractor to control the dust nuisance throughout the construction phase:

·       Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting or sprayed with water to maintain the entire surface wet and then removed or backfilled or reinstated where practicable within 24 hours of the excavation or unloading;

·       Any dusty materials remaining after a stockpile is removed should be wetted with water and cleared from the surface of roads;

·       A stockpile of dusty material should not be extend beyond the pedestrian barriers, fencing or traffic cones;

·       The load of dusty materials on a vehicle leaving a construction site should be covered entirely by impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

·       Where practicable, vehicle washing facilities with high pressure water jet should be provided at every discernible or designated vehicle exit point.  The area where vehicle washing takes place and the road section between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

·       When there are open excavation and reinstatement works, hoarding of not less than 2.4m high should be provided as far as practicable along the site boundary with provision for public crossing. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period;

·       The portion of any road leading only to construction site that is within 30m of a vehicle entrance or exit should be kept clear of dusty materials;

·       Surfaces where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation takes place should be sprayed with water or a dust suppression chemical continuously;

·       Any area that involves demolition activities should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after the activities so as to maintain the entire surface wet;

·       Where a scaffolding is erected around the perimeter of a building under construction, effective dust screens, sheeting or netting should be provided to enclose the scaffolding from the ground floor level of the building, or a canopy should be provided from the first floor level up to the highest level of the scaffolding;

·       Any skip hoist for material transport should be totally enclosed by impervious sheeting;

·       Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides;

·       Cement or dry PFA delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line and no overfilling is allowed;

·       Loading, unloading, transfer, handling or storage of bulk cement or dry PFA should be carried out in a totally enclosed system or facility, and any vent or exhaust should be fitted with an effective fabric filter or equivalent air pollution control system; and

·       Exposed earth should be properly treated by compaction, turfing, hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen, shortcrete or other suitable surface stabiliser within six months after the last construction activity on the construction site or part of the construction site where the exposed earth lies.

These requirements should be incorporated into the Contract Specification for the civil work.  In addition, an audit and monitoring programme during the construction phase should be implemented by the Contractor to ensure that the construction dust impacts are controlled to within the HKAQO. Detailed requirements for the audit and monitoring programme are given separately in the EM&A manual.

7.5.7         Assessment Results - “Mitigated” Scenario

Short-term Assessment (Tier 1)

The maximum 1-hour and 24-hour TSP concentrations based on Tier 1 screening test have been assessed. Table 7.10 below summaries the cumulative 1-hour and 24-hour TSP impact (Tier 1) at identified ASRs. The results indicate that, for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria are not anticipated even assuming the absolute worst case situation, whereby all the worksites would be active (i.e. 100%). However, for the ASRs at the residential premises near Kai Tak Station (KAT-P1-5), exceedance of 1-hour TSP criterion is predicted. As the Tier 1 assessment is for screening purposes only and would not represent the actual on-site situation, a more focused Tier 2 assessment has been undertaken.

In addition, contour of Tier 1 1-hour and 24-hour TSP concentrations are shown in the Figures 7.2.1 – 7.2.4. Contours indicate that there are no exceedances at other locations.

Table 7.10:     Tier 1 Assessment - Predicted Mitigated Cumulative 1hr & 24-hr TSP Concentrations at various heights above Ground (including background concentration of 75.2μg/m3)

ASR ID

Location

1-hour TSP Concentrations at various heightg/m3)

24-hour TSP Concentrations at various heightg/m3)

1.5m

5m

10m

15m

20m

1.5m

5m

10m

15m

20m

DIH-5-1

Rainbow Home

180

182

175

166

156

107

98

94

92

90

DIH-5-2

Residential premises

175

184

177

167

157

96

98

95

93

90

DIH-5-5

Our Lady’s Kindergarten

187

178

172

164

154

98

95

93

91

89

DIH 6-1

Wong Tai Sin Fire Station and Quarters Block A

176

185

177

168

157

96

97

95

93

90

DIH-7-1

Tropicana Gardens Block 2

183

192

183

172

160

100

101

98

94

91

DIH-7-2

Tropicana Garden Block 3

181

190

182

171

159

98

100

97

94

91

DIH-8-1

Redemption Lutheran Church

186

195

186

174

161

108

107

103

98

93

DIH-9-1

Shek On Building

229

214

193

179

166

129

124

111

102

95

DIH-10-1

Hong Kong Sheung Keung Hui Nursing Home

223

208

195

180

166

127

122

111

103

96

DIH-11-1

Lung Poon Court – Lung Wan House

388

337

239

194

174

174

132

113

102

97

DIH-12-1

Galaxia Tower B

284

284

242

207

181

121

122

116

109

104

DIH-12-2

Galaxia Tower E

320

312

254

210

182

127

128

119

111

104

DIH-13-1

Canossa Primary School

198

201

191

178

164

118

116

109

102

96

DIH-14-1

Rhythm Garden Block 2

330

336

289

245

210

121

123

119

114

108

DIH-14-2

Rhythm Garden Block 5

484

439

337

266

213

133

132

120

112

105

DIH-14-3

Rhythm Garden Block 8

386

378

305

244

203

141

141

131

121

113

DIH-14-4

Canossa Primary School (San Po Kong)

268

277

254

225

195

121

117

115

111

107

DIH-14-5

Rhythm Garden Block 1

308

318

282

241

203

117

120

116

112

108

DIH-14-6

Rhythm Garden Block 3

353

360

312

261

217

123

125

120

114

108

DIH-15-1

Choi Hung Estate - Kam Wan House

329

339

299

255

214

104

106

104

101

98

DIH-15-2

Choi Hung Estate - Pik Hoi House

364

373

324

271

224

112

113

109

105

100

DIH-17-1

Chuk Yuen United Village

174

183

176

167

157

96

96

95

92

90

DIH-25-1

Football Field in Choi Hung Road Playground

206

214

201

185

169

107

109

104

99

94

DIH-26-1

Hammer Hill Road Leisure Pool

286

301

277

248

217

98

99

98

96

94

KAT-1-1

Kowloon Cognito College

313

305

248

198

169

150

148

129

113

101

HOM-3-1

Fook Sing Mansion

222

219

220

223

203

110

112

108

104

101

HOM-3-2

Marigold Mansion Block A

207

209

213

240

243

105

108

114

125

126

HOM-4-1

Yee Fu Building

199

197

211

260

308

106

108

112

129

146

HOM-5-1

271 Chatham Road North

237

211

216

288

352

119

120

123

147

168

HUH-1-1

Cartas Branchi College of Careers [2]

341

240

200

281

302

164

144

125

148

157

HUH-1-2

Lok Ka House

407

240

225

308

319

190

139

124

145

150

HUH-1-3

Wing Fung Building

441

280

255

286

273

202

149

140

145

139

HUH-2-1

Hong Kong Polytechnic University - Cheung On Tak Lecture Theatre

323

296

241

202

177

169

153

134

120

111

HUH-3-1

Royal Peninsula Block 2

219

189

165

155

148

128

119

108

104

101

HUH-4-1

The Metropolis Residence Tower 2

283

264

204

156

146

135

131

117

106

99

HUH-5-1

Harbour Plaza Metropolis

342

324

256

165

142

117

118

111

104

98

HUH-6-1

HK Fire Services Headquarters Building

225

203

185

171

157

135

126

110

105

101

HUH-7-1

Hotel Nikko Hong Kong

285

240

174

161

151

119

112

107

102

99

HUH-9-1

Hong Kong Coliseum

Note [3]

Note [3]

208

171

146

Note [3]

Note [3]

107

101

97

HUH-10-1

Harbourfront Horizon

Note [3]

241

182

146

137

Note [3]

124

105

101

96

HUH-11-1

China Travel Cargo Logistic Centre

413

265

183

169

155

193

140

116

109

103

KAT-P1-1

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-2

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-3

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-4

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-5

Residential premises near Kai Tak Station [4]

Note [3]

542

349

248

193

Note [3]

175

139

120

108

KAT-P1-6

Residential premises near Kai Tak Station [4]

Note [3]

300

242

207

191

Note [3]

154

133

115

103

KAT-P1-7

Residential premises near Kai Tak Station

See Note [2]

KAT-P2-1

Public Housing Development at ex-San Po Kong Flatted Factory

336

332

274

224

186

146

139

126

118

111

HOM-P2

Proposed Dormitory for HKPU

198

206

222

236

235

108

110

116

122

115

Notes:

Values which exceeded AQO are shown as bolded characters

 [1]  The population intake of this project would be after Year 2016 (Referenced from approved Kai Tak Development EIA Report), and hence there are no cumulative construction dust impact from the projects

[2]   The premises is located within the works site boundary, hence the population intake would be after the construction of the Project i.e. no impact from the Project

[3]   No air sensitive use is observed at such levels –

Hong Kong Coliseum (HUH-9-1):

Air sensitive use is on the podium of the HUH station, which is at least 10mAG. First assessment height is therefore considered at 10mAG.

Harbourfront Horizon (HUH-10-1):

The first floor of residential units is situated on the podium, which is at least 5m above ground. First assessment height is therefore considered at 5mAG.

Residential premises near Kai Tak Station (KAT-P1-5 / KAT-P1-6):

These residential premises are currently occupied for the construction of public rental housing, which would have a 5m height lift lobby on the ground floor. First assessment height is therefore considered at 5mAG

[4]   The assessment results are for indication only as there are no air sensitive uses when the Yau Lee CBP is in operation.

Short-term Assessment (Tier 2)

A more focused Tier 2 assessment has been conducted such that the projected 30% active works areas for the adjacent construction site is positioned closest to the potentially worst affected ASRs, while emission from all the other sites remain at 100% as per Tier 1. As mentioned in Section 7.5.4, the Tier 2 assessment is also very conservative and would over predict the dust emissions that would unlikely occur.

The maximum 1-hour and 24-hour TSP concentrations at the ASRs highlighted in Tier 1 have been assessed. Table 7.11 summaries the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the Residential Premises near Kai Tak Station (KAT-P1-5). Results show that, the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been plotted for 1-hour (Tier 2), and 24-hour (Tier 2) TSP concentrations at 1.5m and 5m above ground near the KAT Station to illustrate the short-term dust impact on the hot spot area at the worst affected level(s) of ASR, as presented in Figures 7.2.5 – 7.2.8 respectively. It is indicated in these figures that there are no active air sensitive uses located within the area of exceedance, and hence adverse short-term dust impact is not anticipated in the identified hot spot areas.

Table 7.11:     Tier 2 Assessment - Predicted Mitigated Cumulative 1-hour & 24-hour TSP Concentrations at various heights above Ground (including background concentration of 75.2μg/m3)

ASR ID

Location

1-hour TSP Concentrations at Various Heightg/m3)

24-hour TSP Concentrations at Various Heightg/m3)

1.5m

5m

10m

15m

20m

1.5m

5m

10m

15m

20m

KAT-P1-5

Residential premises near Kai Tak Station

Note [1]

360

212

169

147

Note [1]

151

119

104

97

Notes:

 [1]  No air sensitive use is observed at such levels –

Residential premises near Kai Tak Station (KAT-P1-5):

These residential premises are currently occupied for the construction of public rental housing, which would have a 5m height lift lobby on the ground floor. First assessment height is therefore considered at 5mAG. The assessment results are for indication only as there are air sensitive uses when the Yau Lee CBP is in operation.

Long-term Assessment

The maximum predicted annual TSP concentrations at identified ASRs in the study area are given in Table 7.12. In summary, the predicted annual TSP concentrations would comply with the criterion of 80µg/m3, hence, there is no adverse long-term impact anticipated. Contours of annual TSP concentrations at 1.5m above ground have also been plotted in Figures 7.2.9-10. Results indicate full compliances of the relevant criteria predicted at all area adjacent to the work sites.

Table 7.12:     Long-term Assessment - Predicted Mitigated Cumulative Annual TSP Concentrations at various heights above Ground (including background concentration of 75.2μg/m3)

ASR ID

Location

Annual TSP Concentrations at various heightg/m3)

1.5m

5m

10m

15m

20m

DIH-5-1

Rainbow Home

75.5

75.5

75.4

75.3

75.3

DIH-5-2

Residential premises

75.4

75.4

75.4

75.3

75.3

DIH-5-5

Our Lady’s Kindergarten

75.4

75.4

75.3

75.3

75.3

DIH 6-1

Wong Tai Sin Fire Station and Quarters Block A

75.4

75.4

75.3

75.3

75.3

DIH-7-1

Tropicana Gardens Block 2

75.4

75.4

75.4

75.3

75.3

DIH-7-2

Tropicana Garden Block 3

75.4

75.4

75.4

75.3

75.3

DIH-8-1

Redemption Lutheran Church

75.6

75.6

75.5

75.4

75.4

DIH-9-1

Shek On Building

75.9

75.8

75.7

75.6

75.5

DIH-10-1

Hong Kong Sheung Keung Hui Nursing Home

75.9

75.9

75.7

75.6

75.5

DIH-11-1

Lung Poon Court – Lung Wan House

76.0

75.5

75.4

75.3

75.3

DIH-12-1

Galaxia Tower B

75.4

75.4

75.4

75.3

75.3

DIH-12-2

Galaxia Tower E

75.4

75.4

75.3

75.3

75.3

DIH-13-1

Canossa Primary School

75.7

75.7

75.6

75.5

75.5

DIH-14-1

Rhythm Garden Block 2

75.5

75.5

75.4

75.4

75.4

DIH-14-2

Rhythm Garden Block 5

75.6

75.6

75.5

75.5

75.4

DIH-14-3

Rhythm Garden Block 8

75.8

75.7

75.6

75.5

75.4

DIH-14-4

Canossa Primary School (San Po Kong)

75.6

75.6

75.5

75.4

75.4

DIH-14-5

Rhythm Garden Block 1

75.5

75.5

75.4

75.4

75.3

DIH-14-6

Rhythm Garden Block 3

75.5

75.5

75.4

75.4

75.4

DIH-15-1

Choi Hung Estate - Kam Wan House

75.4

75.4

75.4

75.4

75.3

DIH-15-2

Choi Hung Estate - Pik Hoi House

75.4

75.4

75.4

75.4

75.4

DIH-17-1

Chuk Yuen United Village

75.4

75.4

75.4

75.3

75.3

DIH-25-1

Football Field in Choi Hung Road Playground

75.7

75.7

75.6

75.5

75.4

DIH-26-1

Hammer Hill Road Leisure Pool

75.4

75.4

75.4

75.3

75.3

KAT-1-1

Kowloon Cognito College

76.4

76.4

76.2

76.0

75.8

HOM-3-1

Fook Sing Mansion

76.0

76.1

76.1

76.0

75.9

HOM-3-2

Marigold Mansion Block A

76.0

76.1

76.1

76.2

76.1

HOM-4-1

Yee Fu Building

76.0

76.1

76.1

76.3

76.3

HOM-5-1

271 Chatham Road North

76.2

76.3

76.5

76.8

76.7

HUH-1-1

Cartas Branchi College of Careers [2]

76.5

76.5

76.4

76.4

76.4

HUH-1-2

Lok Ka House

76.8

76.4

76.2

76.2

76.1

HUH-1-3

Wing Fung Building

77.1

76.4

76.1

76.0

75.9

HUH-2-1

Hong Kong Polytechnic University - Cheung On Tak Lecture Theatre

77.1

76.7

76.2

75.9

75.7

HUH-3-1

Royal Peninsula Block 2

76.1

76.1

75.9

75.8

75.7

HUH-4-1

The Metropolis Residence Tower 2

75.8

75.9

75.8

75.7

75.6

HUH-5-1

Harbour Plaza Metropolis

76.8

76.6

76.3

76.0

75.8

HUH-6-1

HK Fire Services Headquarters Building

78.3

78.2

77.7

77.1

76.6

HUH-7-1

Hotel Nikko Hong Kong

77.6

77.5

77.1

76.6

76.3

HUH-9-1

Hong Kong Coliseum

Note [3]

Note [3]

76.0

75.8

75.7

HUH-10-1

Harbourfront Horizon

Note [3]

78.1

76.9

76.3

75.9

HUH-11-1

China Travel Cargo Logistic Centre

76.9

76.3

75.9

75.8

75.7

KAT-P1-1

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-2

Residential premises near Kai Tak Station

See Note [1]

KAT-P1-3

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-4

Residential premises near Kai Tak Station

See Note [2]

KAT-P1-5

Residential premises near Kai Tak Station [4]

Note [3]

76.6

76.0

75.8

75.6

KAT-P1-6

Residential premises near Kai Tak Station [4]

Note [3]

78.2

78.3

78.4

78.1

KAT-P1-7

Residential premises near Kai Tak Station

See Note [2]

KAT-P2-1

Public Housing Development at ex-San Po Kong Flatted Factory

76.2

76.1

75.8

75.7

75.5

HOM-P2

Proposed Dormitory for HKPU

76.0

76.0

76.1

76.1

76.0

Notes:

Values which exceeded AQO are shown as bolded characters

 [1]  The population intake of this project would be after Year 2016 (Referenced from approved Kai Tak Development EIA Report), and hence there are no cumulative construction dust impact from the projects

[2]   The premises is located within the works site boundary, hence the population intake would be after the construction of the Project i.e. no impact from the Project

[3]   No air sensitive use is observed at such levels –

Hong Kong Coliseum (HUH-9-1):

Air sensitive use is on the podium of the HUH station, which is at least 10mAG. First assessment height is therefore considered at 10mAG.

Harbourfront Horizon (HUH-10-1):

The first floor of residential units is situated on the podium, which is at least 5m above ground. First assessment height is therefore considered at 5mAG.

Residential premises near Kai Tak Station (KAT-P1-5 / KAT-P1-6):

These residential premises are currently occupied for the construction of public rental housing, which would have a 5m height lift lobby on the ground floor. First assessment height is therefore considered at 5mAG

[4]   The assessment results are for indication only as there are no air sensitive uses when the Yau Lee CBP is in operation.

7.5.8         Residual Impacts for Fugitive Dust

With the implementation of the mitigation measures as stipulated in the Air Pollution Control (Construction Dust) Regulation, dust control measures and good site practices, the predicted 1-hour, 24-hour and annual TSP concentrations on area in the vicinity of the construction sites would comply with the relevant criteria. Hence, no adverse residual dust impact is anticipated.

An air quality impact assessment has been conducted for construction of Project. The fugitive dust assessment for the construction has concluded that watering in all works areas once per hour during working hours (7:00am – 7:00pm) would be required to control the fugitive dust impact. In addition, the Contractor is also recommended to adopt good site practices and is required to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation.

Potential dust impact would be generated from the soil excavation activities, backfilling, site erosion, storage of spoil on site, and transportation of soil during the construction phase. Quantitative fugitive dust assessments have been conducted.

The results show that, in general, the predicted 1-hour and 24-hour and annual TSP concentrations at identified ASRs would comply with the respective criteria. Hence, it is concluded that there will not be any adverse residual air quality impacts.