2.1
In the course of design
development of the Shatin to Central Link - Mong Kok East to Hung Hom section [SCL (MKK-HUH)], engineering feasibility and
site investigation works have been undertaken to determine all technical
parameters for the construction of the scheme. Alternative schemes were also
studied to enhance the overall rail network for the benefit of the travelling
public and the local community, taking into account of all interfacing projects
and constraints. This section of the report provides details of the project
options considered and the constraints and considerations assessed in adopting
the preferred scheme.
2.2
Various construction methodology options and
locations of works areas have been reviewed in order to determine the most cost
effective means of building the Project. Alternative rail alignment and
alternative locations for Hung Hom Station (HUH) as
well as ventilation shafts have been reviewed to identify the optimum option.
The review has taken into account engineering feasibility, site constraints,
construction programme and environmental
considerations as well as feedback from the public consultation, Value
Engineering workshops and technical review.
Purpose and Objective of the Project
2.3
The Shatin to Central Link (SCL) is
strategically important for connecting the existing railway lines into an
integrated rail network. The east-west connection will allow the creation of an
east-west rail corridor across the city connecting Wu Kai Sha
with Tuen Mun via
2.4
As part of the SCL, the objective of this Project is to realign the
existing EAL from Portal 1A to the HUH, enabling the extension from HUH to ADM
across
Brief Description of the Project
2.5
This Project refers to the 1.2 km railway section from tunnel
portal near Oi Man Estate (Portal 1A) to the revamped HUH. The alignment will be
both underground and at grade. Figure No. NEX2213/C/361/ENS/M50/502 illustrates an overview of the Project
alignment.
Project Scope
2.6
The Project comprises the following key elements:
·
Realignment and
modification of the railway section from MKK to HUH; and
·
Ventilation shaft
and other associated station-related works at Hung Hom
with new platforms.
2.7
Apart from the above key
elements, barging facilities, supporting works areas and access roads will be
required to support the construction of the Project. It should be noted that
the works at the HUH would be within the scope of this Project.
Benefit of the Project
2.8
The SCL is an
important strategic rail corridor. It consists of a new
section of railway allowing a through-running line between Mong
Kok and the Central District of Hong Kong
·
Providing a fast,
reliable and convenient mode of transport running through the northern
·
Redistribution of
railway passenger flows to relieve the existing railway lines in urban
·
Relieving
road-based public transport in the existing developed areas, and alleviation of
the traffic congestion and environmental nuisance on existing road networks,
including the demand on the Hung Hom Cross Harbour
Tunnel;
·
Stimulation of the
redevelopment of Hung Hom and Waterfront areas; and
·
Providing more
environmentally friendly public transport in terms of energy conservation and
gas emissions.
2.9
The Project improves
the accessibility to the harbour by providing a direct link between Hung Hom and
2.10
More importantly, the expansion in railway network can gradually conduce
a significant modal shift in passengers’ travel behaviours from road-based
transport to railway system, and thereby alleviating environmental
nuisance from existing road networks.
2.11
From the environmental perspective, the
railway will be powered electrically. Railways are widely recognized as a more
sustainable form of transport than road transport in terms of carrying capacity
and energy effectiveness and adverse environmental implications such as
roadside air pollution associated with electrically-powered rail are far less
in comparing to road-based transport.
Having anticipated that the Project will increase public transport
patronage and reduce the overall road traffic volumes through providing a more
convenient and easily accessible transport option, the Project will bring
improvements in air quality, noise pollution, on-road safety and the overall
quality of the ambient environment.
2.12
In addition, new types of
train services, i.e. 9-car SP1900 or equivalent, will be adopted. The SP1900
type of train is a modern electrically powered train that is considered to be
more environmentally friendly. With the shorter train length, length of platforms
and stations can be reduced accordingly. In general, this will reduce the
potential environmental impact (in terms of extent and/or duration) that would be
generated from the Project during both the construction and operational phases.
2.13
The construction and
operation of the SCL will also create numerous new employment opportunities
within
Considerations
for Alternative Project Design and Alignment Options
2.14
The following sections
present the consideration of the alternatives for the following key elements of
the Project:
·
Alignment;
·
Station/platforms;
·
Ventilation shafts;
·
Train system and
·
Locomotive sidings.
Alignment
Criteria for Options Development
2.15
In order to assess the suitability of alternative alignments, a range of
environmental, engineering, safety and general community disruption
considerations has been developed to help the decision making process. They
were based on considerations commonly adopted for large infrastructure projects
in Hong Kong and are presented in Table 2.1.
Table 2.1 Considerations
Used to Determine Preferred Alignment and Construction Method
Considerations |
Description |
Engineering Factors |
|
Implementation Programme |
Minimisation of
construction period. Shorter construction period is preferable in order to
minimise the disturbance to the community. |
Interface with Existing Facilities |
The alignment should be a
direct connection with minimal distance to reduce construction costs,
maintain operational efficiency and to minimise passenger travelling time between
stations and interfacing with existing facilities. Specific issues
investigated at HUH included: ·
having minimum impact on the operation of the existing station; and ·
ensuring an efficient interchange between the
east-west corridor and the north-south corridor. Other specific
interfacing issues that were taken into account during selection of alignment
options include the need for the associated Shatin to Central Link - Hung Hom to Admiralty
Section [SCL (HUH-ADM)) to have a depth of up to -20mPD when crossing under the Hung Hom Bypass piers and the fender piles, the need to
minimise impacts to the existing freight pier and to avoid impacting on the
Cross Harbour Tunnel and tension anchors. |
Construction/ Operational Safety,
Flexibility and Maintenance Requirements |
A number of safety,
flexibility and maintenance requirements in the design and construction of
railway lines can constrain certain alignment options. Constraints identified within this
Project included: ·
the desired horizontal curve radius for a rail track is 300 m minimum; ·
a maximum vertical gradient of 3% should be achieved, with minimum
gradients for long lengths of track to improve energy efficiency; and ·
additional tunnel ventilation and emergency access
points are required for a long tunnel. |
Constructability |
Constructability is
primarily related to concerns surrounding destabilising structures already
present or to be built. Specific
concerns identified in the SCL include:
·
allowing for practical construction under the Hong Kong Coliseum
(HKC); ·
avoidance/minimisation of constructing soft ground tunnel due to
safety and building settlement issues; and ·
avoidance/minimisation on construction risks
due to uncertain ground condition and long tunnel. |
Land acquisition |
Land
acquisition is considered in order
to minimise area of land that may need to be acquired so as to minimise
disruption to the local community. |
Environmental Factors |
|
Air
Quality |
Dust generated during the
construction of the Project and its impact on human health and the
environment is considered. |
Noise |
Both airborne and
ground-borne noise impact associated with the train pass-bys, together with impact
on nearby residential premises and schools during the construction phase of
the Project is considered. |
Other Environmental considerations |
Other environmental
factors that are considered include: ·
the avoidance or minimisation of landscape and visual impacts
associated with the above-ground structures; ·
avoiding the felling or disturbance of mature trees; ·
minimisation of C&D material / waste generation (e.g. contaminated
soil/sediment); and ·
minimisation of fuel usage. |
Other Factors |
|
Avoidance/Minimisation of
issues/constraints |
This includes the minimisation of Project
areas encroaching into developed area and minimising interface issues with
other projects currently being planned or constructed. |
Disruption to the community |
This minimisation of disruption to the
community takes into account residential households, business operations and
potential structural impacts along the alignment. |
2.16
During the preliminary and detailed design stages for the Project,
comprehensive studies have been carried out to investigate various alignment
options.
Alignment Options
2.17
There are many constraints which dictate the alignment selection of the
Project. These include the existing Cross Harbour Tunnel, existing buildings,
location of HUH and existing rail service. Given the relatively short length of
this section, the potential area available when considering alternative
alignments is largely confined by the existing buildings adjacent to the
existing East Rail alignment.
2.18
Besides, one of the key factors in determining the alignment options is the
location of the HUH. A review of the locations for HUH has concluded that the
HUH must be located to the east of the existing platforms and to the west of
the Metropolis. This is because the location of the HUH is constrained by the
existing platforms and plant rooms on one side and Metropolis and its structure
on the other side. Alternative station locations were proved to be unfeasible
due to constraints caused by existing infrastructure and the impacts on the
existing operating railway (detail in sections 2.48 – 2.57 of this Chapter).
Moreover, the alignment option selection will also be affected by the
construction methods which will be described in sections 2.73 – 2.83.
2.19
Possibilities were explored
extensively during the preliminary and detailed design of the Project. Three basic alignment options were
consolidated for further development. Details of these three options are
illustrated in Appendix 2.1 and summarised below.
Option A
2.20
Option A is required in conjunction with the bored tunnel construction
method across
Option B
2.21
Option B has been developed in the previous feasibility study. This option, running on the west side of the existing EAL, includes a 1.2km long realignment from the Portal 1A
to the HUH. The at-grade section of
this alignment will run very close to Wylie Court and go underground underneath
the Chatham Road Interchange and pass under the HUH.
Option C
2.22
Option C is similar to Option B except the alignment being closer to Oi Man Estate that it will be running on the east side of
the existing EAL. It assumes that freight will no longer operate at HUH in
order to utilise the corridor currently occupied by the freight sidings.
Evaluation of Option
Option A
2.23
Option A provides a
tunnel option from HUH to EXH. A number of “no-reclamation” options in terms of
tunnel options have been investigated. The tunnel options include Shallow/Deep
Tunnel Options.
(1) Shallow Tunnel Boring Machine (TBM) Option
2.24
The tunnel option would require the tunnel to be
deep enough to achieve sufficient ground cover to enable ground control and
steering and for safety requirements. The minimum ground cover required for
safe bored tunnelling is generally an absolute minimum of one and preferably
two TBM diameters above the tunnel. An internal diameter of 9m would be
required for the TBM which would equate to the external diameter of about
10.35m for each tunnel. Accordingly, to allow for sufficient ground cover, the
top of the tunnel would require an absolute minimum depth of 10.35m and
preferably more than 20m below the ground.
2.25
The requirement for the ground cover results in a
deeper HUH. Given that the maximum vertical gradient cannot be greater than 3%,
the Project cannot connect to the existing EAL south of Tunnel 1A (about 800 m
north of HUH). Instead, it must be extended almost 2km to the north. This
additional rail section would require the following items to be constructed,
which would significantly increase the environmental impacts, as well as the
difficulties and cost for the Project construction:
·
350m of cut-and-cover
tunnel in the HUH north fan track area;
·
980m of
twin bored tunnel to a reception shaft in
·
350m of cut-and-cover
and trough along
·
new bridge over
·
an increase in the overall length
of the Project alignment by 1.2km.
2.26
The impact to the environment and the community of
the Shallow TBM Tunnel Option is significant in the area surrounding
2.27
In addition, a main constraint associated with the
Shallow TBM Tunnel Option is the proximity of the alignment to the Hong Kong
Coliseum (HKC) foundations. The SCL
tunnels must be constructed through or below the limited space between the
existing HKC foundations, which significantly increases construction
difficulty, and ensuring construction tolerances becomes more critical. Therefore an alignment
under the HKC but above the rockhead is preferred in
order to avoid undermining the existing foundations and limit the volume
of rock to be excavated.
2.28
Moreover, the tunnel options would require working
in high pressure exceeding the statutory limit of 3.45 bar
as currently set in the Factories and Industrial Undertakings Ordinance (Cap
59). It is considered that the health and safety risks associated with these
options cannot be justified when there are options available which avoid this
problem.
2.29
The Shallow TBM Tunnel Option also has significant
constraints and difficulties for connecting the stations and achieving
operational requirements on both sides of the harbour. At the proposed Exhibition
Station (EXH), a cross platform interchange could not be provided since the SCL
platform at HUH would need to be at least 15m lower than the Cut & Cover
(C&C) Option. This would result
in the following implications:
·
Approximately 2km of
the existing EAL north of HUH would have to be lowered to tie into the deeper
platforms at the station;
·
Impacts on the HKC
may occur due to increased volumes of rock excavation adjacent to and under it;
·
Increased
construction risks and costs associated with construction adjacent to the
existing HUH foundations and under the HKC;
·
Increased interchange
times, as commuters would need to travel to a higher platform level to change
trains;
·
Extremely difficult,
risky and challenging construction immediately adjacent to long lengths of the
existing EAL. The modification of
the existing semi noise enclosure along Wylie Road while still keeping EAL
operating will be particularly difficult and would require non-operational hours
construction in an environmentally sensitive area;
·
Resumption and
temporary occupation of private land adjacent to the alignment;
·
Significant loss of
trees and amenity area at
·
Significant
disruption and impacts to the public including schools;
·
Disruption to traffic
at
·
Major utility
diversions including 400kV power cables;
·
Tunnel 1A is an old
design tunnel with a simple portal structure on pad footings. In terms of the
structure of the tunnel, it is very risky to apply bored tunnel construction
under Tunnel 1A since it is a critical element of the EAL network;
·
Undercutting of the
steep retained slopes opposite
·
It is considered that
the risks to health, life and the Project associated with the TBM Tunnel Option
cannot be justified. There are alternative ways of constructing the project
which avoid these risks.
·
Two ventilation facilities are required due to the
long tunnel length between HUH and MKK (1.8km approximately). Ventilation
buildings are proposed at
2.30
In summary, with the
shallow tunnel option there will be several major impacts on the community. The
section of the EAL to be lowered even deeper would extend to the north of
(2) Deep Tunnel Option
2.31
As mentioned in
section 2.27, an alignment under the HKC foundations but above the rockhead is preferred. However, the Deep Tunnel Option is
expected to have cost and programme implications and cause disruption to the
community and environment in the area surrounding the HKC.
2.32
For the connection to
the SCL (HUH – ADM), the tunnels would have to be lowered to approximately 80m
below ground to be in rock to avoid the need for pressurized face
interventions. The stations at both sides of the harbour would also have to be
deepened significantly. The HUH and EXH would be approximately 50m and 43m in
depth respectively and cross platform interchange would not be possible at
these stations. This would provide an unacceptable level of service for
passengers entering or leaving these stations and an inconvenient interchange due
to the level difference.
2.33
There would be a
knock on effect along the EAL. A significant length of EAL would have to be
lowered to suit this new level including MKK. Tunnelling at depths with
intervention pressures greater than 3.45 bars would also be required along the
Project. Health protection for workers under compressed air will be strictly
regulated by the Factories and Industrial Undertakings Ordinance, and strong
justification on the safety concerns shall be fully addressed.
2.34
The overall design
implication of the above would be significant and the poor vertical interchange
arrangement for the east-west corridor and the north-south corridor at HUH
would not meet the project objectives of providing a direct and convenient
interchange for passengers. Furthermore, most of the construction works would
be difficult and risky and the overall construction duration would be greatly
increased.
2.35
It is estimated that
immersed tube tunnel option (IMT)/cut-and-cover option across the Harbour would
cost approximately HK$3.3 Billion less than the bored tunnel TBM “No
Reclamation” option. The programme implications are that the SCL cross harbour
tunnels constructed using IMT/cut-and-cover option would be completed up to
around 2 years earlier than the TBM options.
2.36
Due to engineering
difficulties, additional risks, relatively long construction programme, costs
and impacts on the community, Shadow or Deep TBM option is deemed not to be a
viable option.
Option B
2.37
Option B bifurcates
to the west of the existing EAL Tracks.
This alignment passes through the existing Ho Man Tin traction feeder
station and descends below the Chatham Road Interchange before passing
underneath the operating EAL tracks and going into the HUH. The EAL crossing
was recognized as a particularly difficult piece of work to construct due to
the limited clearance, confined working space and stringent movement criteria
imposed on the existing tracks. This Option also has risk associated with
tunnel construction beneath the live EAL tracks in the north of HUH.
2.38
In addition, the
Option C
2.39
In order to avoid the risk
associated with tunnel construction beneath the live EAL tracks in the north of
HUH, Option C has been established taking into account the criteria namely
safety, constructability, convenient transportation system, cost, local and
urban constraint, environmental and statutory constraints as well as visually
coherent station planning. The alignment has been changed both vertically and
horizontally. This has positive effects on the station design in terms of
passenger connectivity and reduced vertical travel distances. The changes are
as follows:
Horizontal change
2.40
The rail freight business
would be ceased thereby freeing up land to the east of the operating East Rail
tracks. The alignment could therefore adopt an easterly route avoiding the
difficult and complex EAL crossing.
In addition, the western track of the project has been moved slightly
eastwards in order to maximize the distance of the station diaphragm wall from
existing piles that are shallow and not founded on rock, and therefore
potentially sensitive to ground movements induced by the construction. This
also has the benefit of reducing the station width and thus the excavation
volume.
2.41
The distance between the
Project tracks is increased at the location close to the NOV. Such change is a
consequence of the relocation of the ventilation building adjacent to the
floodgate and immediately above the Project tunnel. The wider track spacing
will allow sufficient space between them to house a ventilation duct that
carries the air from the fans towards the station.
2.42
Another change is to reduce
the spacing between the SCL (TAW-HUH) tracks through the station area and thus
to allow SCL (TAW-HUH) on the western perimeter to be completely accommodated
within the structural envelope of the project station box. This would simplify
construction by allowing one vertical perimeter wall to house both railways.
Vertical change
2.43
The change involves the
raise of the Project alignment by 3m, thus reducing excavation depth and
volume. The Project will bifurcate from south of portal 1A, descending in a
ramp structure at maximum grade. SCL (TAW-HUH) will adopt a rising gradient
into the HUH. Its alignment has been developed to maximize the clearance to the
existing Winslow Street underpass to avoid the known piled foundations and low
ground cover associated with the descending road tunnel ramp. Where the two
tunnels converge, a joint box structure will be constructed with SCL (MKK-HUH)
sitting below the SCL (TAW-HUH) which rises in a ramp on approach to the ground
level platforms in the HUH.
Other Modification
2.44
The
Preferred Alignment Option
2.45
The comparison of potential
environmental benefits and disbenefits is shown in Table 2.2.
Table 2.2 Potential Environmental Benefits/Disbenefits of Alignment Option
Criteria |
Alignment
Option |
||
Option
A |
Option
B |
Option
C |
|
Construction Dust |
A much longer tunnel and more works are
required; and therefore, more Air Sensitive Receivers are likely to be
affected. The construction period and therefore the
period of dust generation will be longer (both construction truck movement
and operation at above ground works area). The potential for dust impact is likely to
be the highest since more above ground works areas/works items would be
involved. HUH would be deeper and require more
excavation, generating more dust. |
A relatively shorter tunnel and fewer works
sites are required; and therefore fewer air sensitive receivers are likely to
be affected. The construction period and therefore the
period of dust generation will be shorter (both construction truck movement
and operation at above ground works area). The potential for dust impact is likely to
be smaller since fewer above ground works areas/works items are required. HUH would be shallower and require less
excavation, generating less dust. |
A relatively shorter tunnel and fewer works
sites are required; and therefore fewer air sensitive receivers are likely to
be affected. The construction period and therefore the
period of dust generation will be shorter than Option A (both construction truck movement and
operation at above ground works area). The potential for dust impact is likely to
be lower than Option A since fewer above ground works areas/slope
works items would be involved. HUH would be shallower and require less
excavation, generating less dust. |
Construction noise |
More noise sensitive receivers are likely
to be affected since the extent of construction works is larger. The construction period will be longer and
the potential affecting period will be longer (both construction truck
movement and operation at above ground works area). Since more construction works within rock
would be required, a higher and longer ground-borne construction noise impact
would be anticipated. |
Fewer noise sensitive receivers are likely
to be affected since the extent of construction works is smaller. The construction period will be shorter and
the potential affecting period will be shorter (both construction truck
movement and operation at above ground works area). Since minimal construction works in rock
layer need to be conducted underneath sensitive buildings (e.g. residential
premises and schools), a lesser and shorter ground-borne construction noise
impact would be anticipated. |
Fewer noise sensitive receivers are likely
to be affected since the extent of construction works is smaller. But slope
cutting is much closer to Ho Man Tin Estate. The construction period will be shorter
than Option A and the potential affecting period
will be shorter (both construction truck movement and operation at above
ground works area). Temporary traffic management
scheme utilizing diverted traffic lanes north of |
Waste Management |
An increase in C&D material would be
expected to be generated due to much longer tunnel construction. HUH would be deeper and require more
excavation, generating more spoil. |
Much less C&D material will be
generated due to a fairly short tunnel construction. HUH would be shallower and require less
excavation, generating less spoil. |
Much less C&D material will be
generated due to a fairly short tunnel construction. HUH would be shallower and require less
excavation, generating less spoil. Reduced excavation volume
due to raising of SCL (MKK-HUH) and SCL (TAW-HUH)
levels, reduced platform’s width by 800mm and reduced spacing to the SCL
(TAW-HUH) track in the eastern part of the alignment. |
Water Quality |
Longer tunnel route length (about 2km) so
more tunnel wastewater generated. |
Shorter tunnel route length (about 1km) so
less tunnel wastewater generated. |
Shorter tunnel route length (about 0.8km)
so less tunnel wastewater generated. |
Land Contamination |
Potential interface with contaminated land
at Chatham Road Interchange. |
Potential interface with contaminated land
at Chatham Road Interchange. |
Potential interface with contaminated land
at Chatham Road Interchange. |
Landscape and Visual |
It is likely that more trees are likely to
be required to be felled or transplanted. Significant visual impact from ventilation
buildings. |
Tree impact reduced. Significant visual impact from tunnel
ventilation building. |
Tree impact reduced. Tunnel ventilation building is not
required. |
Construction Duration |
Longer construction programme (two more
years than Option C) involves longer duration of disturbance, longer presence
of works areas with associated air quality, noise and landscape & visual
impacts and later commencement of operations. |
Shorter construction programme involves
shorter duration of disturbance, shorter presence of works areas with
associated air quality, noise and landscape & visual impacts and earlier
commencement of operations. |
Shorter
construction programme involves shorter duration of disturbance, shorter
presence of works areas with associated air quality, noise and landscape
& visual impacts and earlier commencement of operations. |
Disruption to the Community |
Due to longer time span and more works
areas, a greater disruption to the community would be expected. |
Due to shorter time span and fewer works
areas, a less disruption to the community would be expected. |
Due to shorter time span and fewer works
areas, a less disruption to the community would be expected. |
2.46
According to the comparison in Table 2.2, Option A has less of identified environmental
benefits for the selected criteria than Options B and C. There are major risk,
costs and impacts on community for the Option A such
that it is not considered as a viable option.
2.47
As compared to Option C,
Option B is also considered less favourable in the
construction and environmental perspective. Option C significantly reduces
complexity of construction for the Project tunnel box and shortens the length
of the vertical circulation elements. The Project platform’s width was also
reduced by 800mm. This alignment presents the following environmental benefits:
·
reduced excavation volume
due to raising of SCL (MKK-HUH) and SCL (TAW-HUH) levels, and reduced spacing
to the SCL (TAW-HUH) track in the eastern part of the alignment;
·
deletion of the tunnel
ventilation building so that the visual impact could be reduced;
·
shorter tunnel route length resulting in less tunnel waste water
generated; and
·
temporary traffic management scheme
utilizing diverted traffic lanes north of
2.48
Option C has been determined to have minimized environmental effects and
provides overall environmental benefits over the other two options and presents
the optimum scheme from an operational and environmental perspective. As such, Option C was selected as the preferred
alignment.
Station/Platforms
2.49
In addition to the different alignment options, alternative options for
HUH location have been considered in order to maximise station functionality
and minimise constraints on other sections of the Project.
2.50
The existing HUH, located in a heavily developed area, currently
provides an interchange between the West Rail Line, EAL, Intercity and the
existing Cross Harbour Tunnel bus routes. This critical function will be
required to be maintained throughout the construction stage of the
Project. On completion of the SCL,
the station will need to provide an additional cross platform between east-west
corridor and north-south corridor, whilst also continuing to provide
interchanges with intercity services and the cross harbour tunnel bus routes.
2.51
Key factors in the development of an enhanced scheme for Hung Hom are:
·
Provision of freight – freight operation will be ceased
·
Intercity – Provision is made in the design of HUH for Intercity
continuing operation
2.52
On the abovementioned basis, station options were developed within the
existing Freight Terminal. The differences between them mainly relate to the
configuration of entrances and concourse, and how they relate to the
surrounding facilities and connections. Subsequent to the review, options in
terms of podium level concourse have been adopted due to the least expensive to
build and the least impact to the existing station operation.
West of existing HUH
2.53
The heavily trafficked approach roads to the Cross Harbour Tunnel (CHT)
at the west of the existing HUH restrict the use of cut and cover construction
techniques that would likely create unacceptable impacts on traffic flow. To
move HUH to the west would also bring the Mong Kok East – Hung Hom alignment too
close to the existing CHT, which would likely produce unacceptable interfacing
impacts due to potential settlement / movements of that structure.
2.54
The area to the west of the CHT approach road is currently occupied by
the Hong Kong Polytechnic University, which may require large portions of the
existing facility to be demolished in order to allow the HUH to be moved
there. In order to access the
harbour, this alignment would also have to use a similar alignment occupied by
the EAL between Hung Hom and East Tsim
Sha Tsui Stations. Thus there is insufficient space
to allow station to be located west of HUH.
East of Existing HUH
2.55
The area to the east of the station is constrained due to the major
Metropolis development and its foundations, which would likely restrict
possible EAL alignment in this area. Due to horizontal alignment constraints it
is also infeasible to realign the SCL (TAW-HUH) from East Tsim
Sha Tsui Station to the east of the existing HUH.
However, with the termination of the freight service, this area for freight
operation can be used for future development.
North of Existing HUH
2.56
The area to the north of the station is constrained due to the daily
rail operation at the railway fan area and the associated underground
utilities. There would be major operational constraint to re-route or divert
rail tracks at the fan area to other places in order to make room for the
construction of new platforms.
South of Existing HUH
2.57
The HKC constrains how far the station could be located to the south as
it occupies all of the podium level where the station concourse would be
located. Together with this, there is insufficient space to allow station
platforms to be located under the central core of the HKC.
Summary
2.58
In order to provide a convenient interchange between the SCL east-west
corridor and north-south corridor, minimal distance to reduce construction
costs, maintenance of operational efficiency and to minimise passenger
travelling time between HUH and Exhibition Station (EXH), it is proposed that
the new HUH platforms will be constructed in-situ at the eastern side of the
existing EAL platforms. In other words, instead of constructing a new station
elsewhere, new platforms will be constructed within the existing HUH. Platforms
for the SCL (MKK-HUH) are proposed to be built underneath the existing
HUH/podium and interchange with SCL (TAW-HUH) will be through the existing
podium level concourse. The
existing Platforms will be connected with future SCL (MKK-HUH) and SCL (TAW-HUH)
platforms via escalators for effective cross-platform interchange. Appendix
2.2 shows the cross-section of the new HUH platforms. Based on the
constraints caused by existing infrastructure and the impacts on the existing
operating railway, alternative station locations were considered and proved to
be unfeasible.
Ventilation Shaft
2.59
Ventilation shafts will serve several purposes. In normal operation,
they will be the air exchange route for the railway system. In emergency mode,
they will be essential components of the tunnel smoke control system. One major environmental consideration of the
Project is to design and locate the ventilation shafts such that environmental
impacts including fixed plant noise (fan noise), air quality and visual impacts
associated with their operations could be minimized.
2.60
The ventilation shafts would be designed to comply with the specified
noise limits with no adverse noise impacts.
2.61
Tunnel ventilation exhausts and smoke extraction facilities will also be
carefully positioned to avoid adverse air quality impacts.
2.62
Careful consideration has been given to the locations and design of
required ventilation shafts to minimize the visual impact. The number of
ventilation shafts has been significantly reduced from the original 22 in the
preliminary design stage to 13 in the detailed design stage. The ventilation
shafts for the reconfigured station have been grouped along the northern and
southern podium edges. The vent disposition has been coordinated with the
requirement of 5m separation from the podium level, from the other smoke
ventilation shafts and 3m above the grade where required. They form a series of
geometrically shaped boxes whose facades are articulated with trapezoidal vent
louvers. These structures appear as a natural extension of the podium.
2.63
The north and south side ventilation shafts are physically minimised
with the top level generally at the podium level. They have been provided with
the physical statutory separation requirements and the vent openings of up to
80% efficiencies. The top of these vent structures will be covered with planter
boxes and green roof. Details will be discussed in Chapter 4 (Landscape and
Visual Impact Assessment).
2.64
All the ventilation shafts of the HUH would be situated within the
station footprints where disturbance to nearby sensitive receivers can be
reduced to the greatest extent with the implementation of suitable mitigation
measures.
Train System
2.65
Two types of train services will be provided at different stages of the
project:
·
As per the current situation, a mixed fleet of MLR train and SP1900 will
be used before SCL (HUH – ADM) is commissioned; and
·
9-car SP1900 or equivalent will be adopted when the entire SCL (HUH–ADM)
is commissioned. The train will be less noisy as compared to the existing
fleets.
2.66
The SP1900 type of train is a modern electrically powered train that is
considered to be more environmentally friendly. With the shorter train length,
length of platform and stations can be reduced accordingly. In general, this
will reduce the potential environmental impact (in terms of extent and/or
duration) that would be generated from the project during both the construction
and operational phases.
Locomotive Sidings
2.67
Due to the long haulage to existing depots at Lo Wu or Ho Tung Lau,
backup engineering locomotive will be required for maintenance of
infrastructures and buildings, as well as handling of emergency situation such
as emergency inspection.
2.68
In order to provide supporting service to the main line, locomotive
sidings are required to meet the operational requirements. These requirements are listed below:
·
Locomotive travelled along
the existing rail siding is not operated regularly as the main line service;
and
·
Major maintenance works
will only be conducted in depot.
Layout of Stabling Siding
2.69
In order to achieve the operational requirements, the area will
comprise:
·
Maximum of three sidings;
and
·
Associated stores.
Preferable Location
2.70
Due to the long haulage distance, it is not recommended to stable all
maintenance locomotives at the existing depots despite that
emergency maintenance activities will still be carried out at the depot.
2.71
The sidings could be developed within the existing Homantin
sidings and Mong Kok
Freight Terminal without major modifications to the existing EAL tracks. In particular for Mong
Kok Freight Terminal, three existing freight tracks
decked under podium structure can be deployed for the use of siding. This site
has historically been used for loading and unloading activities and
locomotives/freight movements, and is already screened from the surrounding
community, with minimal visual or noise or social impact on sensitive receptors
expected.
2.72
The existing Homantin siding will be slightly
modified. Three existing tracks will be reduced to one track with spur track
approaching the Hong Kong Polytechnic University Phase 8 (HKPU Phase 8) area
and the number of crossing will be reduced. The alignment of the reprovisioned track will also be slightly further away from
the nearby residential blocks (
2.73
As such, the proposed locations detailed above are deemed the best
practical way to accommodate all operation requirements of the Project with
minimal impact to the surrounding community.
Considerations
for Construction Method
Tunnelling
2.74
The preferred alignment
results in the major length of the railway being within tunnel with remaining
sections at grade. Construction of the Project will potentially lead to certain
levels of environmental impacts. Thus alternative tunnel construction methods
have been considered to pre-empt the potential construction impact to the
nearby sensitive receivers.
2.75
There are several tunnel
construction methodologies that have been undertaken in
·
cut-and-cover construction;
·
drill and blast
construction; and
·
bored tunneling construction.
Cut-and-Cover
(C&C) Construction Method
2.76
Cut-and-cover construction
is a proven and common method of excavation and construction for tunnels,
stations and shafts. This construction method can accommodate different shapes
of works areas. It typically requires several overlapping stages of work to be
conducted in sequence, including removal of obstruction and diversion of
existing utilities, installation of pipe pile or sheet pile wall/diaphragm
wall, grouting, installation of decking, soil excavation, construction,
backfilling and reinstatement.
2.77
In urban areas, the trench
can be covered with a temporary deck following excavation to maintain traffic
management, if required.
Drill and Blast
2.78
For this project, drill and
blast construction has been ruled out predominantly due to the majority of the
tunneling works requiring soft ground excavation.
Bored Tunneling
Construction Method
2.79
Tunnel boring machines
(TBM) can be utilized for the soft and mixed ground tunnels with adequate
ground cover. The construction methodology eliminates the need for surface
access except at launching and retrieval shafts thus minimising
surface disruption. Availability of suitable sites for these shafts is a major
consideration. The machine can be utilized for short lengths of rock sections
of the tunnels but is not as efficient or flexible as traditional drill and
blast techniques.
2.80
The selection of the
appropriate tunneling machine will depend on many issues, including the ground
conditions and available ground cover above the tunnel, contractor’s
experience, and tunnel size and tunnel alignment. Given the ground conditions
anticipated, a shielded TBM erecting an un-drained (i.e. sealed) segmental lining
would be required to ensure the stability of the tunnel face and safety of the
workers, minimize the impact to the groundwater regime and limit surface
settlement. Dealing with buried obstructions would also be more difficult than
with the C&C method.
2.81
In order to adopt the TBM
Tunnel Option, sufficient ground cover is required over the TBM to enable
ground control and steering and for safety requirements. The minimum ground
cover required for safe bored tunneling is generally an absolute minimum of one
TBM diameter and preferably two diameters above the tunnel. This criterion
cannot be met for the proposed tunnels. In addition, the alignment conflicts
with many existing foundations (e.g. the foundations of the east abutments of Overbridge OB2 and OB2A) which could not be handled with a
TBM method within acceptable level of risk. Finally since the project tunnels
connect the existing EAL at Portal 1A, there is no suitable site for launching
or retrieval of the TBM south of Portal 1A.
Environmental Considerations of Construction Methods
2.82
Potential environmental
issues associated with the two possible tunneling methods have been reviewed
and a summary of the benefits and disbenefits of
construction methods is presented in Table 2.3.
Table 2.3 Environmental
Benefits and Disbenefits of Tunnel Construction
Methods
Tunnel Construction Method |
Cut-and-cover construction (C & C) method |
Bored tunnelling Construction method |
Benefits
|
l Accommodation
of different sizes of works areas. l Can
undertake both shallow and relatively deep tunnelling. l C&D
material can be sorted and reused easily. l Since
the extent of the tunnel can be limited, less sensitive receivers will be
affected over a short works extent within the existing EAL boundary (further
setback to sensitive receivers). |
l Noise
impact could be minimized by provision of temporary decks over the portal. l Less
impact on groundwater level with the installation of water tight concrete
tunnel lining in pre-cast segments. |
Disbenefits |
l
More construction plants will be involved
such that this is likely to generate relatively more airborne noise and dust
impacts. |
l Only
applicable for a fairly long tunnel section. l Require
recycling of bentonite/slurry l Spoil
usually well mixed with slurry and not easily to separate out for reuse. l Requires
additional land for the handling of slurry that requires processing before
disposal. l Tunnelling
in congested area next to existing EAL is likely to be a critical concern. l Extremely
difficult, risky and challenging construction immediately adjacent to long
lengths of the existing EAL and roads from the Chatham Road Interchange area. |
Selection of Preferred Construction Methods
2.83
Based on the considerations
presented above, an evaluation of the two main construction options was
conducted. It is concluded that the
C&C Option is the most appropriate option that can achieve the Project
requirements and benefits to the public and be constructed safely with proven
technology, lower costs, less environmental impacts and less risk to programme. As such, the C&C Option
using Option C is selected as the preferred construction method.
2.84
Based on the engineering
information, the works areas requiring for the C&C method will be minimal
and mostly confined to the existing EAL boundary. As such, minimal land
resumption and temporary traffic diversion will be necessary. Since the tunnel
length can be kept fairly short (about 0.8km), the C&C method is more cost-effective.
Owing to the large setback distances with the nearby sensitive receivers,
environmental impacts such as construction noise/dust and fixed source noise
impact would be minimized.
Hung Hom Station
2.85
The construction
methodology employed for the new platform at the existing HUH will also
determine the impact on the surrounding environment. Two construction methods
were considered appropriate for further investigation for the areas next to
HKC:
·
Temporary Open Deck Scheme; or
·
Underpinning Scheme.
Temporary Open Deck Scheme
2.86
The defining construction
methodology of the Temporary Open Deck Scheme is to “remove” the constraints
imposed by the existing podium deck arrangements. The affected part of the
existing podium deck would need to be demolished prior to the construction of
the SCL (MKK-HUH) tunnel.
2.87
In order to minimize any
potential implication to existing infrastructure (e.g. HKC), a staged
construction scheme must be developed to minimize the duration and extent of
podium deck to be removed at any one time.
The main tunnel works would be deferred until after each stage of podium
deck reconstruction is completed, with only the temporary cofferdam walls being
installed at each stage of the deck removal. Temporary reprovisioning
of the affected HKC facilities would also be required.
2.88
Since part of the deck must
be demolished and major construction activities would be exposed, construction
noise and dust should be managed properly. HKC operator, LCSD raised objections
to this scheme. Thus alternative scheme such as underpinning is considered.
Underpinning Scheme
2.89
The defining construction
methodology of the Underpinning Scheme is to construct new foundations and
columns to underpin the existing podium deck structure. Once the loading is
successfully transferred to the new supporting structure, those columns and
foundations which are obstructing the SCL (MKK-HUH) tunnel are able to be
demolished.
2.90
The underpinning works are
more complex. The mid-level walkway and plant room locations must be maintained
throughout construction and the headroom under these structures must be limited
to 5m. The CLP substation and chiller plant room which serve the existing HUH
will also be required to be maintained during all construction stages. In
addition, no cofferdam wall could be undertaken within this area as maintenance
access will be required. However in order to avoid impact with existing
foundation locations, the alignment of the cofferdam wall and temporary
retaining wall will require precision engineering.
2.91
After the underpinning
works, the connection between the column base and the pile cap can be cut. An
excavation with layers of strut and waling can then commence in stages and a
bottom up method could be used. Underpinning schemes have been modified to
minimize the engineering difficulties as this is the scheme favoured
by stakeholders such as HKC due to minimal interference with their activities.
Summary
2.92
The benefits and disbenefits of the two HUH construction methods are compared
in Table 2.4.
In summary the Underpinning Scheme would have less environmental impact through
reductions in construction noise, dust and waste.
Table 2.4 Benefits
and Disbenefits of the Proposed HUH Construction
Methods
Station Works Construction Method |
Benefits |
Disbenefits |
Underpinning Scheme |
·
This
method in general is favoured by stakeholders, such
as HKC due to minimal interference with their activities; · Less environmental impacts, through
reduction in construction noise, dust and waste; · Less
impacts on community through reduction in construction noise and dust; · Existing
evacuation route and emergency vehicular access for the HKC would not be
affected; and · This
method can be modified to minimize the engineering difficulties. |
· More
difficult construction method and very complex in design; · Continuous
inspection and maintenance of permanent left in place bearing in future are
required; and · Longer
programme is expected for underpinning due to the complexity of works. |
Temporary Open Deck
Scheme |
· Easier
construction method and simple form of design; · No need
for long term continuous inspection and maintenance of permanent bearings;
and · Shorter
construction programme. |
· A staged
construction scheme has to be developed to minimise as much as possible the
duration and extent of podium deck to be removed at any one time; · Temporary
reprovisioning of the affected HKC facilities would
also be required which will have concern from HKC due to the potential
interference on activities; and · Since
part of the deck needs to be demolished and some of the construction
activities will be exposed. Relatively higher construction noise and dust
will be anticipated. Additional mitigation measures would be required to
minimize the impact. |
2.93
In view of the HKC’s
constraint and the latest designs to simplify the underpinning works of
existing columns supporting the podium being developed in the detailed design
of the Project underpinning construction methods for the
HUH has been selected as the preferred construction method for the station
works.
2.94
Given the scale of the
Project, works areas/sites would be required for supporting the construction
and have been identified for site office, storage of materials, utility,
barging facilities and traffic diversion. For construction of a new railway
system within a built-up urban environment, identification of available works
areas/sites represents a significant challenge. Details of the works
areas/sites are discussed in Chapter 3.
2.95
The location of works
areas/sites have been selected with consideration to their accessibility and
suitability for construction works and future permanent facilities. The
above-ground works areas/sites have been minimised to
reduce the land taken as far as possible and avoid the potential environmental
sensitive areas. In this regards, the works area/site are mostly planned within
the EAL boundary. Other minor works areas/sites for storage can utilise works sites from other concurrent projects. In
other words, new works area/site has been minimised
as much as possible such that potential impact to additional sensitive
receivers can be avoided.
2.96
To support the construction
of the Project, additional temporary works areas/sites would be required for
the provision of site office, storage of materials, utility, traffic diversion
and barging points for efficient removal of spoil. With a view to minimizing
road-based traffic and stress on existing road networks, barging points have to
be set up at waterfront sites to remove the excavated materials generated from tunnelling and earth works by sea. This will significantly
reduce the impact on road traffic in particular the burden on routes in Hung Hom and Tsim Sha
Tsui and hence the impact on nearby environment.