13.          Land Contamination

Introduction

13.1        Contaminated land refers to the land which has been polluted by hazardous substances as a result of industrial operations carried out on site over a number of years.  These contaminants, if present, may pose hazardous risks or cause adverse effects to the land users and the nearby environment. 

13.2        The implications of land contamination associated with the Project and its works areas have been assessed with reference to the EIA Study Brief.  This section summarises the site appraisal results from the Contamination Assessment Plans (CAPs), site investigation results as reported in the Contamination Assessment Reports (CARs), and any recommended remediation works outlined Remediation Action Plans (RAPs), together with overall findings and recommendations relevant to the EIA.

Environmental Legislation, Standards and Guidelines

13.3        The relevant environmental legislation guidelines and standards on land contamination aspect include the followings:

(i)             Section 3 (Potential Contaminated Land Issues) of Annex 19 “Guidelines for Assessment of Impact on Sites of Cultural Heritage and Other Impacts” of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

(ii)            Guidance Note for Contaminated Land Assessment and Remediation” (Guidance Note 1)

Guidance Note 1 sets out the requirements for proper assessment and management of potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling stations), gas works, power plants, shipyards/boatyards, chemical manufacturing/processing plants, steel mills/metal workshops, car repairing/dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be conducted and analysed and suggests practical remedial measures that can be adopted for the cleanup of contaminated sites.

(iii)           Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop” (Guidance Note 2)

Guidance Note 2 specifically sets out guidance for land contamination assessment and remediation for sites previously used for petrol filling stations, boatyards and vehicle repair/dismantling workshops.

(iv)           Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (Guidance Manual)

The Guidance Manual introduces the risk based approach in land contamination assessment and present instructions for comparison of soil and groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary.

Assessment Methodology

13.4        The first step was to assess and identify any potentially contaminated sites within the Project area.  The following tasks have been undertaken to identify and evaluate the potential land contamination impacts associated with the Project

l   Desktop study to review the current and historical land uses;

l   Acquisition of information related to potential land contamination from Environmental Compliance Division of Environmental Protection Department (EPD) and Fire Services Department (FSD); and

l   Site reconnaissance to identify the existing land uses and potential contamination.

13.5        In addition, the following sources of information have been collated and reviewed:

l   Selected aerial photographs from Lands Department;

l   Hong Kong Geological Survey Maps  (Series HGM20) – Sheet Nos. 6, 11, 12 and 15 (1:20,000);

l   Information on dangerous goods for potentially contaminated areas from Fire Services Department (FSD);

l   Records and photographs obtained during the site visit; and

l   Relevant approved EIA report (i.e. Environmental Assessment Report of West Island Line (EIA-153/2008)).

13.6        According to the findings of the site appraisal, a CAP was prepared and submitted to EPD.  Based on the desktop review and site inspection, sampling locations and depths for soil and groundwater at potentially contaminated sites have been proposed for the site investigation (SI) works.  The CAP also specified the sampling and testing requirements for the SI works. It has been endorsed by EPD and is given in Appendix 13.1.

13.7        During SI, sampling will be conducted at areas identified as having a high potential contamination (potential hotspots), with the objective to preliminarily assess the soil and groundwater quality through sampling and laboratory testing at worst-case locations of potential contaminated sites as far as possible.  After the completion of the SI works, the soil and groundwater analytical results were compared to the adopted RBRGs. The nature, level and extent of land contamination were evaluated and findings were documented in the CAR. Due to current land use and site constraints, the SI is proposed to be undertaken in two stages. The Stage 1 SI has been completed with the CAR provided in Appendix 13.2.

13.8        Sites inaccessible or with SI constraints in Stage 1 will be assessed in Stage 2. The Stage 2 SI will be conducted after the completion of this EIA study/upon decommissioning and prior to the commencement of construction works at the potentially contaminated sites. Supplementary CAR(s) and if contamination is found, RAP(s) will be prepared and submitted to EPD for endorsement.  A Remediation Report (RR) will be prepared and submitted to EPD to demonstrate that the decontamination work is adequate and is carried out in accordance with the endorsed CAR and RAP.  Information such as soil treatment/ disposal records (including trip tickets), confirmatory sampling results, and photographs will be included in the aforesaid RR.  No construction work will be carried out prior to the endorsement of the RR by EPD.

Description of the Environment

13.9        The assessment areas of the land contamination impact assessment under the Project are shown in Figure nos. NEX2213/C/361/ENS/M57/001 through NEX2213/C/361/ENS/M57/016 of the endorsed CAP (Appendix 13.1). Since the endorsement of the CAP, the Project boundary and the supporting works areas have been slightly modified.  Based on desktop studies and site inspections, there is no newly identified potential contamination site requiring assessment within the modified project boundary/works area and the planned SI works is, therefore, still considered sufficient.  The latest Project boundary and the designed alignment are indicated in Figure no. NEX2213/C/331/ENS/M57/400 of the CAR (Appendix 13.2).

13.10      The assessment areas have been classified into three geographic categories for easy reference and details can be referred to in the endorsed CAP.  Brief descriptions are as follows:

(i)            Area 1: Works Area from the New Hung Hom Station to Causeway Bay Typhoon Shelter

13.11      Area 1 starts from north of the North Ventilation Building, Plant Rooms and Emergency Access (NOV) in Hung Hom Freight Yard (cut & cover construction method) stretching south through Victoria Harbour (generally immersed tube tunnel (IMT) construction).  The Project interfaces with the SCL (TAW – HUH) and SCL (MKK-HUH) at this section.

(ii)           Area 2: Works Area on Hong Kong Island

13.12      This area encompasses Hong Kong Island, including the alignment which starts at CBTS.  Various construction methods will be utilised in Area 2, including the tunnel boring machine (TBM), cut & cover, mechanical excavation and drill & blast through to Mid Levels.  Two new stations, the Exhibition Station (EXH) near the existing Hong Kong Convention and Exhibition Centre and the Admiralty Station (ADM), will be built.  The South Ventilation Shafts, Plant Rooms and Emergency Access (SOV) are proposed to be constructed at the Police Officers’ Club in Causeway Bay. 

(iii)          Area 3: Supporting Works Area

13.13     An offsite supporting works area at Shek O Quarry will be used as a casting basin for immersed tunnel (IMT), concrete batching plant, material conveyor, site offices, workshops, storage for materials, plants and equipment, barge loading and unloading and material delivery.  Rehabilitation works was being undertaken at the site by CEDD at the time of the site appraisal and was completed in 2010.

13.14     The offsite works areas for at Tseung Kwan O Industrial Estate (Site ID 3-01), Siu Lam (Site ID 3-02), Chung Hom Kok (Site ID 3-03), Mount Davis (Site ID 3-04), and Western District Public Cargo Working Area (Site ID 3-05) as proposed in the CAP are no longer required for this Project.   No further investigation was therefore conducted for these areas.

Identification of Potential Environmental Impacts

Identification of Impact Sources

13.15      The identification of potentially contaminated land within the Project areas has been completed through the site appraisal exercise.  The list of potentially contaminated sites identified within Stage 1 SI is summarised in Table 13.1 below.

Table 13.1         Potentially Contaminated Sites Identified and SI Conducted in Stage 1

Site ID (Description)

Current Land Use

Reference Figure in CAR (Appendix 13.2)

Area 1

1-01

(Kowloon Freight Building near Hung Hom waterfront)

Kowloon Freight Building

·             Emergency generator and associated fuel tank

NEX2213/C/331/ENS/M57/401

Area 2

2-10

(Police Officer’s Club near Causeway Bay Typhoon Shelter)

Police Officers’ Club

·        Underground grease trap

·        Emergency generator and associated fuel tank

NEX2213/C/331/ENS/M57/402

2-24

(Area north of Harcourt Garden near the existing Admiralty Station)

Open car park, vacant area, streets (historically used as a boat basin of the former War Department)

NEX2213/C/331/ENS/M57/404

13.16      For sites with constraints (e.g. accessibility, site operation) (refers to Appendix 13.3) in which the SI was not able to be carried out/completed during Stage 1, the SI will be undertaken in Stage 2.  The details of such sites were listed in Table 5.2 of the CAP in Appendix 13.1 and are also summarised in Table 13.2 below.

Table 13.2         Potentially Contaminated Sites Identified and SI Conducted in Stage 2

Site ID (Description)

Current Land Use and Site Constraints

Reference Figure in CAR (Appendix 13.2)

Area 2

2-15

(Southeast corner of Wanchai Swimming Pool)

Aboveground diesel tanks for Wan Chai Swimming Pool (only observation from the nearest overpass); it was in operation and inaccessible during Stage 1 SI

NEX2213/C/331/ENS/M57/403

Identification of Sensitive Receptors

13.17      Onsite construction workers have the potential to be exposed to potentially contaminated materials during the decommissioning stage. The principle exposure pathways for onsite workers include:

l   Direct ingestion of contaminated soil through eating, drinking or smoking onsite; and

l   Dermal contact with contaminated soil.

13.18      Through the correct implementation of occupational health and safety guidelines and usage of correct personal protective equipment these potential pathways can be successfully managed.

13.19      Other potential sensitive receptors include water bodies and other humans, working or travelling near the sites and during the intrusive investigation and remediation work stages.  During these stages there is a potential to generate dust emissions and water discharges that have the potential to affect the surrounding sensitive receivers (e.g. human receivers and water bodies).  However, adoption of appropriate work practices and mitigation measures during investigation and remediation works will ensure that these risks can be successfully managed. 

Prediction and Evaluation of Environmental Impacts

Stage 1 Site Investigation Results

13.20      Potentially contaminated sites have been identified in the CAP (Appendix 13.1) and a site investigation involving sampling and testing of soil and groundwater at identified hotspots has been conducted.  A summary of the number of borehole/trial pits sampled, the number of samples tested, their compliance to the adopted RBRGs, and the planned post-restoration land use is provided in Table 13.3 below:

Table 13.3         Summary of SI Findings in Stage 1

  Site ID

No. of Borehole/ Trial Pits Sampled

No. of Samples Tested#

Compliance to Industrial RBRGs

Planned Post-Restoration Land Uses

Area 1

1-01

1

3*

All samples tested in compliance

Construction of cofferdam, tunnel and the North Ventilation Building

Area 2

2-10

2

6*

All samples tested in compliance

SOV and railway tunnel

2-24

1

11*

All samples tested in compliance

Ventilation shaft and railway tunnel

Total

4

20

-

-

#: Number of tested soil and groundwater (if encountered) samples.

*: Number of duplicated sample is not included in this table.

 

13.21      A total of 19 soil and 1 groundwater samples were collected at four borehole/trial pits under Stage 1 as scheduled in the CAP.  According to the analytical results, no exceedances of the RBRG (industrial) or Soil Saturation Limit/ Solubility Limit were found among the soil and groundwater samples collected during Stage 1 SI. 

Stage 2 Site Investigation

13.22      The Stage 2 SI will be conducted after the completion of this EIA study/land resumption/site decommissioning and prior to the commencement of the construction work.  A revised CAP with sampling and testing schedule updated based on site conditions should then be submitted to EPD for endorsement.  After completion of sampling and testing, a supplementary CAR and if contamination is found, RAP will be submitted for EPD endorsement. The revised CAP and supplementary CAR and RAP should be submitted in separate packages for different works area depending on the schedule of land resumption and the commencement of construction works for each works area.  Based on the site appraisal conducted previously in the endorsed CAP, the potential contamination (if any found) at the representative sites is expected to be surmountable, with implementation of the mitigation measures proposed in Section 13.37 of this report.

Remediation Actions and Precautionary Measures to Be Undertaken during Construction

Sites under Stage 1 SI

Review of Remediation Options, Methods and Targets

13.23      Based on the Stage 1 SI results of the soil and groundwater samples, no exceedance of the adopted RBRG guidelines has been found at the identified potentially contaminated sites, therefore no remediation actions are needed for these sites. 

Summary of Proposed Precautionary Measures to Be Undertaken during Construction

13.24      Although no exceedance was found in Stage 1 SI, to be conservative, precautionary measures such as visual inspection are recommended to be undertaken during construction activities that disturb soil. The inspection process shall involve a visual observation of excavated soils for discolouration and the presence of oils, together with identifying the presence of odours, which may also indicate soil and/or groundwater contamination.  

13.25      If soil materials suspected to be contaminated are encountered during excavation, sampling and testing shall be undertaken to verify the presence of contamination.  The soil extracted during demolition, excavation and cut & cover construction shall be temporary stockpiled.  Should the concentrations of contaminants of concern (COCs) exceed relevant RBRGs as indicated by laboratory analyses, remediation works shall be undertaken with reference to the CAR and RAP.

13.26      The following is a summary of proposed precautionary measures to be carried out at the sites Stage 1 SI:

Site IDs 1-01: Emergency Generator and the Associated Fuel Tank

13.27      Due to site constraints, only a trial pit was only conducted outside the emergency generator and its associated fuel tank rooms during Stage 1 SI.  Visual inspection for the presence of contamination shall therefore be carried out during construction of the cut & cover tunnel onsite. Attention should be paid to potential contamination due to the historic and current operation.

Site ID 2-10: Underground Grease Trap, Emergency Generator and the Associated Fuel Tank

13.28      A trial pit was constructed with a depth of 3 m bgs at the grease trap which is 1-2 m in depth.   No exceedances of the adopted RBRGs were recorded during the Stage 1 SI.  However, to be conservative, visual inspection shall be carried out at the underground grease trap when constructing the SOV at the present Police Officers’ Club, for any sign of potential contamination due to the storage of grease.

13.29      Due to site constraints, a trial pit was only conducted outside the emergency generator and its associated fuel tank rooms during the Stage SI.  Visual inspection for the presence of contamination shall therefore be carried out during construction of the proposed the ventilation building onsite; attention should be paid to potential contamination due to the historic and current operation.

Site ID 2-24: Past Marine Boat Basin of the former War Department

13.30      Since the exact area, extent and facilities of the previous War Department could not be confirmed, the Stage 1 SI was conducted as a preliminary screening to confirm the presence of land contamination in this area. Though all parameters tested did not exceed the adopted RBRGs, to be conservative, a visual inspection shall be carried out during the construction of ventilation shaft at which the boat basin was identified, for any sign of potential contamination due to its past operations. 

Sites with No SI Proposed

13.31      For some sites with currently no SI proposed (i.e. sites ID 2-02, 2-18, 2-22, 2-23, 2-27, 2-28), to be conservative, visual inspection shall be conducted during demolition and excavation to detect any abnormal colour, smell or other characteristics of the soil due to the nearby land use and/ or construction method.  If abnormal colour, smell or other characteristics of contamination are identified for any of these sites, sampling and testing shall be undertaken to verify the presence of contamination.  The soil extracted during demolition, excavation and cut & cover construction shall be temporary stockpiled.  Should the concentrations of contaminants of concern (COCs) exceed relevant RBRGs as indicated by laboratory analyses, remediation works shall be undertaken with reference to the CAR and RAP.

13.32      In view of there are no historical potential contamination sources, and no or limited amounts of chemicals are currently used at these sites, with the ground generally in good condition, the potential contamination, if any found at these sites, is expected to be limited extent and surmountable with the implementation of the mitigation measures as proposed in Section 13.30 of this Report.

Sites under Stage 2 SI

Review of Remediation Options, Method and Targets

13.33      If potential soil and groundwater contamination is identified during the Stage 2 SI, a review of remediation options (such as biopiling, ex-situ chemical oxidation (ESCO), soil venting, landfarming, natural attenuation and excavation and landfill disposals) shall be conducted in the RAP (if required). Based on the site appraisal conducted previously in the endorsed CAP, the potential contamination (if any found) at the respective sites under Stage 2 SI is expected to be surmountable, with implementation of the mitigation measures proposed in Section 13.39 of this Report.

13.34      Remediation works will include the excavation of identified contaminated area, followed by a closure assessment to verify clearance of contaminated soil.  The excavated contaminated soil will then be formed into piles for either biopiling or chemical oxidation.  During this, monitoring of treatment performance will be carried out in the form of regular sampling and testing.  Once the monitoring data indicates the treatment target is achieved, a closure assessment consisting of sampling and testing will be carried out at a defined sampling frequency for the treated soil. 

13.35      The acceptance criterion is defined as contaminant concentrations complying with the remediation targets making reference to “industrial” land use category of the RBRGs.  In the event that the samples are still exceeding the remediation target, treatment will continue until the soil target values are achieved.  Following validation of successful soil treatment, the decontaminated soil will be used as fill materials for re-use on site with reference to the land use scenario in the RBRGs.   A remediation report demonstrating completion of remediation works will be prepared and submitted to EPD for endorsement.

Summary of Proposed Precautionary Measures to Be Undertaken during Construction

13.36      The Stage 2 SI is proposed for the site considered to have the potential for land contamination but was impeded from site appraisal and/or SI due to a constraint.  Since limited information is currently available to determine whether remediation actions are required, in order to be conservative, precautionary measures are suggested to be undertaken both during the SI and construction.

13.37      Visual inspection shall be undertaken during demolition or excavation works at the Stage 2 SI works areas as listed below.  If discolouration and the presence of oils and odours are detected, sampling and testing shall also be undertaken to verify the presence of contamination.  Should concentrations of COCs exceed the adopted RBRGs, remediation works shall be undertaken with reference to the CAR and RAP.  A Remediation Report (RR) will then be prepared and submitted to EPD to demonstrate that the decontamination work is adequate and is carried out in accordance with the endorsed CAR and RAP.  Information such as soil treatment/ disposal records (including trip tickets), confirmatory sampling results, and photographs will be included in the aforesaid RR.  No construction work shall be carried out prior to the endorsement of the RR by EPD.

13.38      The following is the precautionary measures to be undertaken at the works area under the Stage 2 SI:

Site ID 2-15: Aboveground Diesel Storage Tanks

13.39      A SI including soil and groundwater samplings was proposed for Site ID 2-15 under Stage 2.  Due to site constraints, proper site appraisal and SI could not be conducted onsite for the aboveground diesel tanks, located near the proposed EXH.  Visual inspection shall be carried out during construction where intrusive works and soil excavation is encountered, for attention on any potential contamination due to its current operation. 

Potential Remediation Works

13.40      If land contamination is identified during the Stage 2 SI, a RAP detailing the proposed remediation works will prepared in order to remediate the land.  In order to minimise environmental impacts arising from the handling of potentially contaminated materials, the following environmental precautionary measures are recommended to be utilised during the course of the site remediation:

·      Excavation profiles must be properly designed and executed with attention to the relevant requirements for environment, health and safety;

·      Excavation shall be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils;

·      Supply of suitable clean backfill material is needed after excavation;

·      If remediation is required with chemical oxidation proposed as a contaminant mass reduction technology, chemicals shall be securely and separately stored away from sources of ignition or oxidisable items.  Handling shall be undertaken by personnel with appropriate training and personnel protective equipments (PPE).

·      Vehicles containing any excavated materials shall be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates shall be sealed to prevent any discharge during transport or during wet conditions;

·      Speed control for the trucks carrying contaminated materials shall be enforced;

·      Vehicle wheel and body washing facilities at the site’s exist points shall be established and used; and

·      Pollution control measures for air emissions e.g. from biopile blower, noise emissions e.g. from blower, and water discharges e.g. runoff control shall be implemented and complied with relevant regulations and guidelines.

Summary of Proposed Occupational Health and Safety Controls

13.41      In the event that remediation is required the Occupation Safety and Health Ordinance (OSHO) (Chapter 509) and its subsidiary Regulations shall be followed by all site personnel working on the site at all times to minimise the potential adverse effects on the health and safety of construction workers during the course of site remediation. In addition, basic health and safety measures shall be implemented, but not limited to the followings:

·      Set up a list of safety measures for site workers;

·      Provide written information and training on safety for site workers;

·      Keep a log-book and plan showing the contaminated zones and clean zones;

·      Maintain a hygienic working environment;

·      Avoid dust generation;

·      Provide face and respiratory protection gear to site workers if necessary;

·      Provide personal protective clothing (e.g. chemical resistant jackboot, liquid tight gloves) to site workers if necessary; and

·      Provide first aid training and materials to site workers.

13.42      The corresponding responsible party for the above precautionary measures and supplementary site investigation are provided in the implementation schedule of this EIA.

Evaluation of Residual Environmental Impacts

13.43      No contaminants were detected in the soil and groundwater samples collected in the Stage 1 SI. In terms of the potential soil and groundwater contamination detected in Stage 2 SI, options of remediation methods will be reviewed and implemented so that contaminants will be removed to achieve the remediation targets. After completion of soil remediation for identified contaminated areas, no adverse residual impact in respect of land contamination on the future users is anticipated. Apart from these, precautionary measures as mentioned in Sections 13.23 through 13.30 and Sections 13.35 through 13.38 should still be implemented during the construction phase for conservancy. 

Conclusion

13.44      This assessment has examined the potential contaminating land uses within the relevant Assessment Area. It also covers potential impacts of the contamination on future use.  The assessment involved site appraisal, site investigation, and assessment of contamination extent.  Stage 1 SI has been carried out for Site IDs 1-01 (Kowloon Freight Building at Hung Hom), 2-10 (Police Officers’ Club at Causeway Bay), and 2-24 (past marine boat basin of the War Department at Admiralty).  Based on the findings from the Stage 1 SI, no adverse impacts have been identified within the assessment areas.  As a precaution, mitigation measures are proposed for the excavation of soil, treatment of soil and general environmental, health and safety on site during the construction stage.

13.45      Due to current land use and site constraints, SI was not conducted for Site ID 2-15 (aboveground diesel storage tanks at Wan Chai Swimming Pool) under Stage 1.  The investigation will be conducted under Stage 2 after decommissioning of existing buildings and access has been granted.  Based on the site appraisal conducted previously in the endorsed CAP, the potential contamination (if any found) at Site ID 2-15 under Stage 2 SI is expected to be surmountable, with the mitigation measures proposed in Section 13.40 of this Report.