17.          Implementation Schedule and Recommended Mitigation Measures

Table 17.1         Implementation schedule of Recommended Mitigation Measures

EIA Ref.

Recommended Mitigation Measures

Objectives of the Recommended Measures & Main Concern to Address

Who to implement the measures?

Location of the measure

When to implement the measures?

What requirements or standards for the measure to achieve

Applicable to Relevant Designated Elements (see Remark)

Cultural Heritage Impact

 

S4.93 & Table 4.2

Erection of decorative and sensibly designed hoarding along the boundary of the works area

To mitigate the temporary visual impact due to surface works.

Contractor

Works Areas in Causeway Bay and Wan Chai, and Works Shaft in Admiralty

Construction Phase

EIAO

DP1, DP2

S4.98 & Table 4.4

Sympathetic design shall be incorporated in aboveground structures such that they could blend into existing setting and environmental character of the site.

To mitigate the visual impact associated from aboveground structures

MTR

South Ventilation Shafts, Plant Rooms and Emergency Access (SOV), Ventilation Shafts and Hong Kong Park Ventilation Building (HKB)

Operation Phase

EIAO

DP1, DP2

Ecological Impact  

 

S5.132

The proposed footprint of the IMT casting basin and associated infrastructure is adjusted.

To avoid the loss of coral

MTR

Shek O casting basin

Design stage

EIAO - TM

N/A

S5.133

The following mitigation measures in controlling water quality change shall be implemented:

-       Installation of silt curtains around the dredgers, where appropriate, during dredging activities;

-       Use of closed grab dredger during dredging; and

-       Reduction of dredging rate

To minimize changes in water quality impact on marine flora and fauna

Contractor

All reclamation and dredging works areas

Construction Phase

EIAO - TM

DP3, DP4

S5.134

Accidental chemical spillage and construction site run-off to the receiving water bodies, mitigation measures such as removing the pollutants before discharge into storm drain and paving the section of construction road between the wheel washing bay and the public road as suggested in Sections 11.216 and 11.219 to 11.256 of the EIA Report shall be adopted

To minimize the contamination of wastewater discharge

Contractor

All land based works areas

Construction Phase

EIAO - TM

DP1, DP2,

Fisheries Impact  

 

S6.57

The size of the dredging and underwater blasting areas shall be minimized as much as possible

To minimize loss of fishing ground and fisheries resources

Contractor/ MTR

All dredging and underwater blasting works areas

Construction Phase

EIAO - TM

DP3, DP4

S6.57

Mitigation measures recommended in Sections 11.200 to 11.207, 11.209 to 11.211 and 11.213 to 11.256 of the EIA Report to control water quality, i.e. use of effective site drainage in land-based construction site and installation of silt curtain surrounding the dredging point, use of closed grab dredger and reduction of dredging rate shall be implemented.

 

 

To minimize change in water quality impact on fisheries resources and operation

Contractor

Works areas

Construction Phase

EIAO - TM

DP3, DP4

S6.58

Silt curtain shall be deployed at near-shore to fence off fish from entering the lethal zone during underwater blasting. 

 

 

To isolate the impact on fisheries resources outside the lethal zone

Contractor

Underwater blasting works areas

Construction Phase

EIAO - TM

DP3, DP4

S6.59

After completion of armour rock filling, the final surfaces of the protective armour rock layer shall be checked by ultrasonic sounding survey.  Measures such as removing the rock or breaking the rock into pieces shall be implemented in case of non-compliance.

To minimize the IMT protrusion above the seabed

Contractor

Along IMT laying works areas

Construction Phase

EIAO - TM

DP3, DP4

Landscape and Visual Impact    

 

Construction Phase

 

 

 

 

 

 

Table 7.9

CM1 - Trees unavoidably affected by the works shall be transplanted as far as possible in accordance with ETWB TC(W) 3/2006 – Tree Preservation.

Transplanting and reuse of affected trees. 

MTR

Works Sites

Construction Phase

EIAO - TM and ETWB TC(W) 3/2006

DP1,DP2

Table 7.9

CM2a - Compensatory tree planting shall be provided in accordance with ETWB TC(W) 3/2006 – Tree Preservation to compensate for felled trees and maintained until end of the establishment period.

Compensation for the removal of existing trees due to the Project. 

MTR

Works Sites

Construction Phase

EIAO - TM and ETWB TC(W) 3/2006

DP1,DP2

Table 7.9

CM2b - Compensatory shrub planting shall be provided to compensate for the loss of shrub planting in amenity areas.

Compensation for the removal of existing shrub planting due to the Project. 

MTR

Works Sites

Construction Phase

EIAO - TM

DP1,DP2

Table 7.9

CM3 - Control of night-time lighting glare

Minimize the night time glare due to the Project during construction phase

MTR

Works Sites

Construction Phase

EIAO - TM

DP1,DP2

Table 7.9

CM4 - Erection of decorative screen hoarding compatible with the surrounding setting.

Minimize the visual impact of the Project during construction phase

MTR

Works Sites

Construction Phase

EIAO - TM

DP1,DP2

Table 7.9

CM5 - Management of facilities on work sites which give control on the height and disposition/arrangement of all facilities on the works site to minimize visual impact to adjacent VSRs.

Control of height and deposition/arrangement of temporary facilities in works areas

MTR

Works Sites

Construction Phase

EIAO - TM

DP1,DP2

Table 7.9

CM6 - All hard and soft landscape areas disturbed temporarily during construction shall be reinstated on like-to-like basis to the satisfaction of the relevant Government Departments.

Reinstatement of temporary works areas.

MTR

Works Site

Construction Phase

EIAO - TM

DP1,DP2

Operation Phase

 

 

 

 

 

 

Table 7.10

OM1 - Aesthetically pleasing design as regard to the form, material and finishes shall be incorporated to MTR Entrance, Plant Buildings, Ventilation Shafts and associated engineering facilities and HKB so as to blend in the structures to the adjacent landscape and visual context. 

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

NOV, SOV, EXH MTR Entrances, Plant Building, Ventilation Shafts, EAP, ADM Ventilation Shafts and Cooling Tower, HKB and associated engineering facilities,

Detailed Design and Operation Phase

EIAO - TM

DP1

Table 7.10

OM2 - Tree Planting shall be incorporated to provide screening to Plant Buildings and Ventilation Shafts and associated engineering facilities. 

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

NOV, SOV, EXH Entrances, Plant Building, Ventilation Shafts, EAP, HKB and associated engineering facilities,

Detailed Design and Operation Phase

EIAO - TM

DP1

Table 7.10

OM3 - Green Roof shall be proposed to NOV, SOV and Plant Buildings to the east of the EXH to enhance the landscape quality of the structures and mitigate any potential visual impact on adjacent VSRs.

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

NOV, SOV, Plant Buildings to the east of the EXH

Detailed Design and Operation Phase

EIAO - TM

DP1

Table 7.10

OM4 - Climbers shall be incorporated to the ventilation buildings to soften the structure.

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

NOV

Detailed Design and Operation Phase

EIAO - TM

DP1

Table 7.10

OM5 - Landscaped mound is proposed to screen the EXH Ventilation Shafts. 

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

EXH Ventilation Shafts

Detailed Design and Operation Phase

EIAO - TM

DP1

Table 7.10

OM6 - Vertical Greening shall be incorporated on the facade of EXH Plant Building along Convention Avenue.

Enhance the landscape and visual amenity value of the Project and minimize the potential visual impact during operation phase. 

MTR

EXH Plant Building along Convention Avenue

Detailed Design and Operation Phase

EIAO - TM

DP1

Construction Dust Impact

 

Table 8.5

Barging facilities:

(i)      Transportation of spoils to the barging point – Pave all road surfaces within the barging facilities and provide watering once along with the haul road for every working hours to reduce dust emission by 91.7%.  This dust suppression efficiency is derived based on the average haul road traffic, average evaporation rate and an assumed application intensity of 1.0 L/m2 once every working hour. Any potential dust impact and watering mitigation would be subject to the actual site condition.  For example, a construction activity that produces inherently wet conditions or in cases under rainy weather, the above water application intensity may not be unreservedly applied. While the above watering frequency is to be followed, the extent of watering may vary depending on actual site conditions but should be sufficient to maintain an equivalent intensity of no less than 1.0L/m2 to achieve the removal efficiency. The dust levels would be monitored and managed under an EM&A programme as specified in the EM&A Manual.

(ii)     Unloading of spoil materials – Undertake the unloading process within a 3-sided screen with top tipping hall.  Provide water spraying and flexible dust curtains at the discharge point for dust suppression.

(iii)    Vehicles leaving the barging facilities – Pass vehicles through the wheel washing facilities provided at site exits.

To minimize dust impacts

Contractor

All barging points

Construction phase

APCO

N/A

S8.63

For concrete batching plant, the requirements and mitigation measures stipulated in the Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93) shall be followed and implemented.

To minimize dust impact

Contractor

Concrete Batching Plant

Construction phase

APCO

N/A

Table 8.6

During operation of concrete batching plant:

(i)     Unloading of aggregates from the tipper trucks to receiving hopper – unload the aggregates from the tipper trucks to the receiving hopper equipped with enclosures on 3 sides and top cover, and water spraying system.

(ii)    Unloading of cement and PFA from tankers into the silo – Directly load the cement and PFA into the silo via a flexible duct.  Install dust collectors at cement/PFA silos.

(iii)   Storage of aggregates in overhead storage bins – Store the aggregates in fully enclosed overhead storage bins.  Cover the top of overhead storage bins with cladding.  Install water spraying system at the top of storage bins for watering the aggregates, and fully enclose aggregates storage bins.

(iv)  Weighing and batching of cementitious materials – Perform the whole process of weighing and mixing in a fully enclosed environment.  Equip all the mixers with dust collectors.

(v)   Loading of concrete from mixer into transit mixer of a truck – Directly load the concrete from the mixer into the transit mixer of a truck in “wet form”.

(vi)  Tipper trucks and cement tankers leaving the Concrete Batching Plant – Haul road within the site is unpaved.  Install wheel washing pit at the gate of the concrete batching plant.

(vii) Transportation of materials within the plant – Provide watering twice a day would be provided.

To minimize dust impacts

Contractor

Concrete Batching Plant

Construction phase

APCO and Guidance Note on the Best Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2(93)

N/A

S8.89

Watering once every working hour on active works areas, exposed areas and paved haul roads to reduce dust emission by 91.7%.  This dust suppression efficiency is derived based on the average haul road traffic, average evaporation rate and an assumed application intensity of 1.7 L/m2 for Kowloon side and 1.0 L/m2 for Hong Kong side once every working hour. Any potential dust impact and watering mitigation would be subject to the actual site condition.  For example, a construction activity that produces inherently wet conditions or in cases under rainy weather, the above water application intensity may not be unreservedly applied.  While the above watering frequency is to be followed, the extent of watering may vary depending on actual site conditions but should be sufficient to maintain an equivalent intensity of no less than 1.7 L/m2 for Kowloon side and 1.0 L/m2 for Hong Kong sideto achieve the removal efficiency.  The dust levels would be monitored and managed under an EM&A programme as specified in the EM&A Manual.

To minimize dust impact

Contractor

Works areas

Construction phase

APCO

DP1, DP2

S8.89

Enclosing the unloading process at barging point by a 3-sided screen with top tipping hall, provision of water spraying and flexible dust curtains to reduce dust emission

To minimize dust impact

Contractor

All barging points

Construction phase

APCO

N/A

S8.90

Dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation and good site practices:

Ÿ Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

Ÿ Use of frequent watering for particularly dusty construction areas and areas close to ASRs.

Ÿ Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

Ÿ Open stockpiles shall be avoided or covered.  Where possible, prevent placing dusty material storage piles near ASRs.

Ÿ Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

Ÿ Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.

Ÿ Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading area of barging point, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.

Ÿ Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit.

Ÿ Imposition of speed controls for vehicles on site haul roads.

Ÿ Where possible, routing of vehicles and positioning of construction plant shall be at the maximum possible distance from ASRs.

Ÿ Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) shall be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides.

Ÿ Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

 

To minimize dust impacts

Contractor

Works areas

Construction phase

APCO and Air Pollution Control (Construction Dust) Regulation

DP1, DP2 

Airborne Noise Impact    

 

Construction Phase

 

 

 

 

 

 

S9.55

The following good site practices shall be implemented:

Ÿ Only well-maintained plant shall be operated on-site and plant shall be serviced regularly during the construction program

Ÿ Silencers or mufflers on construction equipment shall be utilized and shall be properly maintained during the construction program

Ÿ Mobile plant, if any, shall be sited as far from NSRs as possible

Ÿ Machines and plant (such as trucks) that may be in intermittent use shall be shut down between work periods or shall be throttled down to a minimum

Ÿ Plant known to emit noise strongly in one direction shall, wherever possible, be orientated so that the noise is directed away from the nearby NSRs

Ÿ Material stockpiles and other structures shall be effectively utilized, wherever practicable, in screening noise from on-site construction activities.

To minimize  construction noise impact

 

Contractor

 

Works areas

 

Construction

phase

 

EIAO-TM

 

DP1, DP2, DP3, DP4

S9.56 & Table 9.16

The following quiet PME shall be used:

·            Crane lorry, mobile

·            Crane, mobile

·            Asphalt paver

·            Backhoe with hydraulic breaker

·            Breaker, excavator mounted (hydraulic)

·            Hydraulic breaker

·            Concrete lorry mixer

·            Poker, vibrator, hand-held

·            Concrete pump

·            Crawler crane, mobile

·            Mobile crane

·            Dump truck

·            Excavator

·            Truck

·            Rock drill

·            Lorry

·            Wheel loader

·            Roller vibratory

To minimize construction noise impact

 

Contractor

 

Works areas at:

·   Hung Hom

·   Cross Harbour section up to Breakwater of CBTS

·   Breakwater of CBTS to SOV

·   SOV to EXH

·   EXH

·   EXH to open space at the junction of Expo Drive and Convention Avenue

·   Open space at the junction of Expo Drive and Convention Avenue to north of ADM

·   South of ADM to Overrun Tunnel

Construction

phase

 

EIAO-TM

 

DP1, DP2, DP3, DP4

S9.58 – S9.59 & Table 9.17

Movable noise barrier shall be used for the following PME:

·            Air compressor

·            Asphalt paver

·            Backhoe with hydraulic breaker

·            Bar bender

·            Bar bender and cutter (electric)

·            Breaker, excavator mounted

·            Concrete pump

·            Concrete pump, stationary/lorry mounted

·            Excavator

·            Generator

·            Grout pump

·            Hand held breaker

·            Hydraulic breaker

·            Saw, concrete

To minimize construction noise

impact

 

Contractor

 

Works areas at:

·   Cross Harbour section up to Breakwater of CBTS

·   Breakwater of CBTS to SOV

·   SOV to EXH

·   EXH

·   EXH to open space at the junction of Expo Drive and Convention Avenue

·   Open space at the junction of Expo Drive and Convention Avenue to north of ADM

·   South of ADM to Overrun Tunnel

Construction

phase

EIAO-TM

 

DP1, DP2

S9.60 & Table 9.17

Noise insulating fabric shall be used for

·            Drill rig, rotary type

·            Piling, diaphragm wall, bentonite filtering plant

·            Piling, diaphragm wall, grab and chisel

·            Piling, diaphragm wall, hydraulic extractor

·            Piling, large diameter bored, grab and chisel

·            Piling, hydraulic extractor

·            Piling, earth auger, auger

·            Rock drill, crawler mounted (pneumatic)

To minimize construction noise impact

 

Contractor

 

Works areas at:

·   Cross Harbour section up to Breakwater of CBTS

·   Breakwater of CBTS to SOV

·   SOV to EXH

·   EXH

·   EXH to open space at the junction of Expo Drive and Convention Avenue

·   Open space at the junction of Expo Drive and Convention Avenue to north of ADM

·   South of ADM to Overrun Tunnel

Construction

phase

EIAO-TM

 

DP1, DP2

Operation Phase

 

 

 

 

 

 

S9.70 & Tables 9.119.15

Properly design the fixed plant to meet the maximum permissible sound power levels (Max SWLs) listed in Tables 9.11 to 9.15.

To comply with the noise criteria 

MTR

NOV, SOV, EXH and ADM

Detailed design and operation phases

EIAO-TM and NCO

DP1

S9.70

The following noise reduction measures shall be considered as far as practicable during detailed design of fixed plant equipment:

Ÿ Choose quieter plant such as those which have been effectively silenced.

Ÿ Include noise levels specification when ordering new plant (including chillier and E/M equipment).

Ÿ Locate fixed plant/louver away from any NSRs as far as practicable.

Ÿ Locate fixed plant in walled plant rooms or in specially designed enclosures.

Ÿ Locate noisy machines in a basement or a completely separate building.

Ÿ Install direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosure where necessary.

Ÿ Develop and implement a regularly scheduled plant maintenance programme so that equipment is properly operated and serviced in order to maintain controlled level of noise.  The programme shall be implemented by properly trained personnel.

To minimize fixed noise impacts

MTR

NOV, SOV, EXH and ADM

Detailed design and operation phases

EIAO-TM and NCO

DP1

Groundborne Noise Impact  

 

S10.70

Prior to the operation phase of the Project, a commissioning test will be conducted to ensure compliance of the operational ground-borne noise levels with the adopted noise criteria.

To minimize operation ground-borne noise impacts

MTR

Tunnel alignment

Detailed design and operation Phase

NCO

DP1

Water Quality Impact

 

Construction Phase

 

 

 

 

 

 

S11.200 & 201

All excavation and tunnel construction works will be undertaken within the cofferdam and there will be no open dredging.

Removal of fender piles of Hung Hom Bypass and minor marine piling works will be carried out prior to the construction of the elevated platform adjacent to the cofferdam at Hung Hom Landfall.  Reinstatement of the fender piles will be carried out upon completion of tunnel section. Potential release of sediment due to abovementioned works could be minimized by installation of silt curtains surrounding the works area as appropriate. All excavation and tunnel construction works will be undertaken within the cofferdam and there will be n. No open dredging shall be allowed.

To minimize release of sediment and contaminants during temporary reclamation.

Contractor

Marine works at Hung Hom Landfall

Construction Phase

EIAO-TM, WPCO

DP3

S11.202

All temporary reclamation works will adopt an approach where temporary seawalls will first be formed to enclose each phase of the temporary reclamation.  Installation of diaphragm wall on temporary reclamation as well as any bulk filling will proceed behind the completed seawall.  Any gaps that may need to be provided for marine access will be shielded by silt curtains to control sediment plume dispersion away from the site.  Demolition of temporary reclamation including the demolition of the diaphragm wall and dredging to the existing seabed levels will also be carried out behind the temporary seawall.  Temporary seawall will be removed after completion of all excavation and dredging works for demolition of the temporary reclamation.

To minimize loss of fines and contaminants during temporary reclamations

Contractor

All temporary reclamation works areas

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 202

During construction of the temporary reclamation, temporary seawall will be partially constructed to protect the nearby seawater intakes from further dredging activities.  For example, the seawalls along the southeast and northeast boundaries of PW1.1 shall be constructed first (above high water mark) so that the seawater intake at the inner water would be protected from the impacts from the remaining dredging activities along the northwest boundary.

To minimize water quality impact upon the cooling water intakes in CBTS from temporary reclamation works

Contractor

Temporary reclamation works areas in CBTS

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 202

Dredging will be carried out by closed grab dredger to minimize release of sediment and other contaminants during dredging.

To minimize loss of fines and contaminants during dredging in CBTS

Contractor

All temporary reclamation and dredging works areas within CBTS

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 202 & Table 11.25

Silt curtains will be deployed to fully enclose the closed grab dredger and shall be extended from water surface to the seabed, as far as practicable, during any dredging operation.

 

To minimize loss of fines and contaminants during dredging in CBTS

Contractor

All temporary reclamation and dredging works areas within CBTS

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 202 & Table 11.23

Silt screens will be installed at the cooling water intakes within the CBTS during the temporary reclamation period.

 

To minimize water quality impact upon the cooling water intakes in CBTS from marine construction activities

Contractor

Cooling water intakes inside CBTS

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 203 & Table 11.24

No more than two dredgers (of about 8 m3 capacity each) shall be operated for dredging within the typhoon shelter at any time for the tunnel construction works.  Moreover, the combined dredging rate for all concurrent dredging works (include dredging works for concurrent projects such as WDII and CWB) to be undertaken within the CBTS shall not exceed 6,000 m3 per day (and 375 m3 per hour with a maximum working period of 16 hours per day) throughout the entire construction period.

To minimize loss of fines and contaminants during dredging in CBTS

Contractor

All dredging works areas within CBTS

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 204

Bulk filling along the IMT tunnel alignment for SCL shall be carried out after the bulk dredging works along the IMT alignment are completed.  Hence, bulk dredging and bulk filling along the IMT alignment shall not be undertaken at the same time.

To minimize loss of fines and contaminants during IMT construction

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 204

Dredging for IMT and SCL2 construction shall be carried out by closed grab dredger to minimize release of sediment and other contaminants during dredging.

To minimize loss of fines and contaminants during dredging in the Victoria Harbour

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 204

No more than one closed grab dredger shall be operated outside the CBTS in the open harbor for SCL construction.

To minimize loss of fines and contaminants from dredging in the Victoria Harbour

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 204

Dredging for temporary reclamation outside the CBTS (at SCL2) shall not be carried out concurrently with the dredging / filling works for IMT construction.

To minimize loss of fines and contaminants from dredging / filling in the Victoria Harbour

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 205 

Floating type or frame type silt curtains shall be deployed around the dredging  operations within 200m from the Hung Hom landfall.

To minimize loss of fines and contaminants from dredging in the Victoria Harbour

Contractor

Construction of northern IMT segment in the near shore region within 200 m from the Hung Hom landfall

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11. 205 & Table 11.23  

Silt screens shall be installed at the cooling water intakes for East Rail Extension, Metropolis and Hong Kong Coliseum (namely 21, 34 and 35 respectively) which are in close vicinity of the northern IMT segment.

 

To protect the beneficial use of water intakes along the Kowloon waterfront from dredging / filling activities

Contractor

Construction of northern IMT segment in the near shore region within 200 m from the Hung Hom landfall

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11.207

If underwater blasting is required for SCL construction, the following precautionary / mitigation measures shall be adopted:

·         Charge shall be placed in cores within the rock in order that there will be no blast directly into the water.

·         In terms of the construction sequence, sediment dredging (within the planned IMT works area) shall be conducted prior to any underwater blasting.

To protect the water quality in Victoria Harbour from any possible underwater blasting

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

Table 11.23
 

Silt screens shall be installed at the WSD Flushing Water Intakes at Kowloon Station, Tai Wan, Quarry Bay and Wan Chai (namely Intakes 14, WSD9, WSD17 and A respectively) during any dredging / filling works outside the CBTS for temporary reclamation at SCL2 or for IMT construction

To protect the beneficial use of flushing water intakes in Victoria Harbour from dredging / filling activities

Contractor

Flushing water intake points in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11.210 - S11.211 & Table 11.24

If the marine works for SCL are to be carried out concurrently with other dredging / filling activities in the Victoria Harbour, the production rates of any dredging / filling work to be undertaken outside the CBTS for SCL construction in the open harbour (including temporary reclamation at SCL2 and IMT construction) shall not exceed 2,500 m3 per day at any time throughout the entire construction period. The hourly production rate for dredging or bulk filling within the open Victoria Harbour (outside the breakwater of CBTS) shall not exceed 156 m3 per hour (if there are other concurrent marine works in Victoria Harbour) and the maximum working hour for the dredging / bulk filling works shall be 16 hours per day. Silt screen shall be deployed at the Kowloon Station Intake to minimize the water quality impact.

If the marine works for SCL are to be carried out with no other concurrent dredging / filling activities in the Victoria Harbour, the production rates of any dredging / filling work to be undertaken outside the CBTS for SCL construction in the open harbour (including temporary reclamation at SCL2 and IMT construction) shall not exceed 4,500 m3 per day at any time throughout the entire construction period. The hourly production rate for dredging or bulk filling within the open Victoria Harbour (outside the breakwater of CBTS) shall not exceed 281 m3 per hour (if there is no other concurrent marine works in Victoria Harbour) and the maximum working hour for the dredging / bulk filling works shall be 16 hours per day. Silt screen shall be deployed at the Kowloon Station Intake to minimize the water quality impact.

To minimize loss of fines and contaminants from dredging / filling in the Victoria Harbour

Contractor

Marine works areas in Victoria Harbour

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11.215

The following good site practices shall be undertaken during filling and dredging:

Ÿ mechanical grabs, if used, shall be designed and maintained to avoid spillage and sealed tightly while being lifted;

Ÿ all vessels shall be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash;

Ÿ all hopper barges and dredgers shall be fitted with tight fitting seals to their bottom openings to prevent leakage of material;

Ÿ construction activities shall not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site or dumping grounds;

Ÿ loading of barges and hoppers shall be controlled to prevent splashing of dredged material into the surrounding water.  Barges or hoppers shall not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation;

Ÿ before commencement of the temporary reclamation works, the holder of the Environmental Permit shall submit plans showing the phased construction of the reclamation, design and operation of the silt curtain.

To minimize loss of fines and contaminants from dredging / filling

Contractor

Marine works areas

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11.216

The following mitigation measures are proposed to minimize the potential water quality impacts from the construction works at or close to the seafront:

Ÿ Temporary storage of construction materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction and demolition materials shall be located well away from the seawater front and storm drainage during carrying out of the works.

Ÿ Stockpiling of construction and demolition materials and dusty materials shall be covered and located away from the seawater front and storm drainage.

Ÿ Construction debris and spoil shall be covered up and/or disposed of as soon as possible to avoid being washed into the nearby receiving waters.

To minimize release of construction wastes from construction works at or close to the seafront

Contractor

Construction works at or close to the seafront

Construction Phase

EIAO-TM, WPCO

DP1, DP2, DP3, DP4

S11.217

The following mitigation measures are proposed to minimize the potential water quality impacts from any marine piling works:

Ÿ The potential release of sediment or excavated materials could be controlled through the installation of silt curtains surrounding the working area as necessary.

Ÿ Spoil shall be collected by sealed hopper barges for proper disposal.

To minimize release of sediment and pollutants from marine piling activities

Contractor

Marine piling works areas

Construction Phase

EIAO-TM, WPCO

DP3

S11.218

Silt screens are recommended to be deployed at the seawater intakes during the construction works period.  Regular maintenance of the silt screens and refuse collection shall be performed at the silt screens at regular intervals on a daily basis.  The Contractor shall be responsible for keeping the water behind the silt screen free from floating rubbish and debris during the impact monitoring period.

To avoid the pollutant and refuse entrapment problems at the silt screens to be installed at the water intakes

Contractor

Proposed silt screens at water intakes.

Construction Phase

EIAO-TM, WPCO

DP3, DP4

S11.219

It is recommended that collection and removal of floating refuse shall be performed within the marine construction areas at regular intervals on a daily basis.  The Contractor shall be responsible for keeping the water within the site boundary and the neighbouring water free from rubbish during the dredging works.

To minimize water quality impacts from illegal dumping and littering from marine vessels and runoff from the coastal areas

Contractor

Marine works areas

Construction Phase

EIAO-TM, WPCO, WDO

 DP3, DP4

S11.220 & 221

Any wastewater including washdown waters and any concrete curing waters generated from the casting basin shall be drained to the wastewater treatment unit.  Appropriate treatment process such as sedimentation and oil removal shall be employed for the wastewater treatment units so that any discharge from the casting basin will comply with standards stipulated in the TM-DSS. Recovered oil from any oil interceptor shall be properly contained, labeled and stored on site prior to collection by licensed collectors for disposal. 

During the flooding of the basin with seawater (accomplished by pumps) no escape of water could occur as the cofferdam will still be in place.  Prior to opening a channel through the cofferdam, water inside the basin will be skimmed of floating debris. A period of settling of 24 hours before opening the basin to the sea would allow much of the suspended material to settle out.  The channel through the cofferdam will only be opened with the approval of the Site Engineer to the effect that all reasonable steps had been taken to remove contaminants.

To minimize water quality impacts from the washdown, flooding and draining operation at Shek O Casting Basin

Contractor

Shek O Casting Basin

Construction Phase

EIAO-TM, WPCO

N/A

S11.222 to 11.245

The site practices outlined in ProPECC PN 1/94 “Construction Site Drainage” shall be followed where practicable. 

To minimize water quality impacts from construction site runoff and general construction activities

Contractor

Works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS, WDO, ProPECC PN 1/94

DP1, DP2

S11.246 & 11.247

Construction work force sewage discharges on site are expected to be discharged to the nearby existing trunk sewer or sewage treatment facilities.  If disposal of sewage to public sewerage system is not feasible, appropriate numbers of portable toilets shall be provided by a licensed contractor to serve the construction workers over the construction site to prevent direct disposal of sewage into the water environment.  The Contractor shall also be responsible for waste disposal and maintenance practices.

Notices shall be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment. 

To minimize water quality impacts due to sewage generated from construction workforce

Contractor

Works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS, WDO

DP1, DP2

S11.248

In case seepage of uncontaminated groundwater occurs, groundwater shall be pumped out from the works areas and discharged into the storm system via silt removal facilities.  Uncontaminated groundwater from dewatering process shall also be discharged into the storm system via silt traps.

To minimize impact from discharge of uncontaminated groundwater

Contractor

Works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS

DP1, DP2

S11.249

If land contaminated site is identified from the Stage 2 SI work (refer to Sections 11.188 to 11.191 of the EIA Report), the following mitigation measures shall be implemented for the identified contaminated area.  Any transient pile of contaminated soil / material shall be minimized and shall be bottom-lined, bunded and covered with impervious membrane during rain event to avoid generation of contaminated runoff.  Appropriate intercepting channels and partial shelters shall be provided where necessary to prevent rainwater from collecting within trenches or footing excavations. Any contaminated water and wastewater generated from the decontamination process shall not be directly discharged to public sewers or site drainage. They shall be treated or tanked away as necessary for proper disposal in compliance with the TM-DSS.

To control site run-off generated from any potential contaminated works areas.

 

Contractor

Any potential contaminated areas to be identified from the Stage 2 SI

Construction Phase

EIAO-TM, WPCO, TM-DSS

DP1, DP2

S11.250 & S11.251

No direct discharge of groundwater from contaminated areas shall be adopted.  If land contamination impact and generation of contaminated groundwater is identified from the Stage 2 SI works (refer to Sections 11.189 to 11.192 of the EIA Report), the following mitigation measures shall be adopted.  Any contaminated groundwater shall be either properly treated in compliance with the requirements of the TM-DSS or properly recharged into the ground.  If wastewater treatment is deployed for treating the contaminated groundwater, the wastewater treatment unit shall deploy suitable treatment processes (e.g. oil interceptor / activated carbon) to reduce the pollution level to an acceptable standard and remove any prohibited substances (such as TPH) to an undetectable range. All treated effluent from the wastewater treatment plant shall meet the requirements as stated in TM-DSS and shall be discharged into the foul sewers.

If groundwater recharging wells are deployed, the recharging wells shall be installed as appropriate for recharging the contaminated groundwater back into the ground. The recharging wells shall be selected at places where the groundwater quality will not be affected by the recharge operation as indicated in Section 2.3 of the TM-DSS.  The baseline groundwater quality shall be determined prior to the selection of the recharge wells, and submit a working plan (including the laboratory analytical results showing the quality of groundwater at the proposed recharge location(s) as well as the pollutant levels of groundwater to be recharged) to EPD for agreement. Pollution levels of groundwater to be recharged shall not be higher than pollutant levels of ambient groundwater at the recharge well. Prior to recharge, any prohibited substance such as TPH products shall be removed as necessary by installing the petrol interceptor. The Contractor shall apply for a discharge licence under the WPCO through the Regional Office of EPD for groundwater recharge operation or discharge of treated groundwater.

 

To minimize potential water quality impact from discharge of contaminated groundwater

Contractor

Any potential contaminated areas to be identified from the Stage 2 SI

Construction Phase

EIAO-TM, WPCO, TM-DSS

DP1, DP2

S11.252

The following good site practices shall be adopted for the proposed barging points:

Ÿ all vessels shall be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash

Ÿ all hopper barges shall be fitted with tight fitting seals to their bottom openings to prevent leakage of material

Ÿ construction activities shall not cause foam, oil, grease, scum, litter or other objectionable matter to be present on the water within the site

Ÿ loading of barges and hoppers shall be controlled to prevent splashing of material into the surrounding water.  Barges or hoppers shall not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation

To minimize water quality impacts generated from the barging points.

 

Contractor

Barging points

Construction Phase

EIAO-TM, WPCO

N/A

S11.253

There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO.  The discharge quality must meet the requirements specified in the discharge licence.  All the runoff and wastewater generated from the works areas shall be treated so that it satisfies all the standards listed in the TM-DSS.  Minimum distances of 100 m shall be maintained between the discharge points of construction site effluent and the existing seawater intakes.  The beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel washing and general cleaning etc., can minimise water consumption and reduce the effluent discharge volume.  If monitoring of the treated effluent quality from the works areas is required during the construction phase of the Project, the monitoring shall be carried out in accordance with the WPCO license which is under the ambit of Regional Office (RO) of EPD.

To minimize water quality impact from effluent discharges from construction sites

Contractor

All construction works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS

DP1, DP2, DP3, DP4

S11.254

Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities.  The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation shall be observed and complied with for control of chemical wastes.

To minimize water quality impact from accidental spillage of chemical

Contractor

All construction works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS, WDO

DP1, DP2, DP3, DP4

S11.255

Any service shop and maintenance facilities shall be located on hard standings within a bunded area, and sumps and oil interceptors shall be provided.  Maintenance of vehicles and equipment involving activities with potential for leakage and spillage shall only be undertaken within the areas appropriately equipped to control these discharges.

To minimize water quality impact from accidental spillage of chemical

Contractor

All construction works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS, WDO

DP1, DP2, DP3, DP4

S11.256

Disposal of chemical wastes shall be carried out in compliance with the Waste Disposal Ordinance.  The “Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes” published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes.  General requirements are given as follows:

Ÿ Suitable containers shall be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

Ÿ Chemical waste containers shall be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

Ÿ Storage area shall be selected at a safe location on site and adequate space shall be allocated to the storage area.

To minimize water quality impact from accidental spillage of chemical

Contractor

All construction works areas

Construction Phase

EIAO-TM, WPCO, TM-DSS, WDO

DP1, DP2, DP3, DP4

Operation Phase

 

 

 

 

 

 

S11.257

Ÿ  Track drainage channels discharge shall pass through oil/grit interceptors/chambers to remove oil, grease and sediment before discharging into public storm drainage / foul sewerage systems.

Ÿ The silt traps and oil interceptors shall be cleaned and maintained regularly.

Ÿ Oily contents of the oil interceptors shall be transferred to an appropriate disposal facility, or to be collected for reuse, if possible.

To mitigate water quality impact from tunnel run-off from track

MTR

All railway tunnels

Operational Phase

EIAO-TM, WPCO, TM-DSS, WDO

DP2

S11.258

Ÿ Connection of domestic sewage generated from the Project shall be diverted to the foul sewer.   All the discharge should comply with the requirements stipulated in the TM-DSS.

Ÿ For handling, treatment and disposal of other operational stage effluent, the practices outlined in ProPECC PN 5/93 shall be adopted where applicable.

To avoid water quality impact from sewage discharges

 

MTR

All railway stations and ventilation building

Operational Phase

EIAO-TM, WPCO, TM-DSS, ProPECC PN 5/93

DP1

Waste Management Implications 

 

Construction Phase

 

 

 

 

 

 

S12.75

Good Site Practices and Waste Reduction Measures

-       Prepare a Waste Management Plan (WMP) approved by the Engineer/Supervising Officer of the Project based on current practices on construction sites;

-       Training of site personnel in, site cleanliness, proper waste management and chemical handling procedures;

-       Provision of sufficient waste disposal points and regular collection of waste;

-       Appropriate measures to minimize windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

-       Regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors; and

-       Separation of chemical wastes for special handling and appropriate treatment.

To reduce waste management impacts

Contractor

All Work Sites

Construction Phase

Waste Disposal Ordinance (Cap. 354)

 

Land (Miscellaneous Provisions) Ordinance (Cap. 28)

 

DEVB TCW No. 6/2010

DP1, DP2, DP3, DP4

S12.76

Good Site Practices and Waste Reduction Measures (con’t)

-       Sorting of demolition debris and excavated materials from demolition works to recover reusable/ recyclable portions (i.e. soil, broken concrete, metal etc.);

-       Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

-       Encourage collection of aluminum cans by providing separate labeled bins to enable this waste to be segregated from other general refuse generated by the workforce;

-       Proper storage and site practices to minimize the potential for damage or contamination of construction materials;

-       Plan and stock construction materials carefully to minimize amount of waste generated and avoid unnecessary generation of waste; and

-       Training shall be provided to workers about the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, reuse and recycle.

To achieve waste reduction

Contractor

All Work Sites

Construction Phase

Waste Disposal Ordinance (Cap. 354)

 

Land (Miscellaneous Provisions) Ordinance (Cap. 28)

DP1, DP2, DP3, DP4

S12.77

 Good Site Practices and Waste Reduction Measures (con’t)

-       The Contractor shall prepare and implement a WMP as part of the EMP in accordance with ETWB TCW No. 19/2005 which describes the arrangements for avoidance, reuse, recovery, recycling, storage, collection, treatment and disposal of different categories of waste to be generated from the construction activities.  Such a management plan shall incorporate site specific factors, such as the designation of areas for segregation and temporary storage of reusable and recyclable materials.  The EMP shall be submitted to the Engineer for approval.  The Contractor shall implement the waste management practices in the EMP throughout the construction stage of the Project.  The EMP shall be reviewed regularly and updated by the Contractor, preferably in a monthly basis.

To achieve waste reduction

Contractor

All Work Sites

Construction Phase

ETWB TCW No. 19/2005

DP1, DP2, DP3, DP4

S12.78

C&D materials would be reused in other local concurrent projects as far as possible. If all reuse outlets are exhausted during the construction phase, the C&D materials would be disposed of at Taishan, China as a last resort.

To achieve waste reduction

Contractor

All Work Sites

Construction Phase

ETWB TCW No. 19/2005

DP1, DP2, DP3

S12.79

Storage, Collection and Transportation of Waste

Should any temporary storage or stockpiling of waste is required, recommendations to minimize the impacts include:

-       Waste, such as soil, shall be handled and stored well to ensure secure containment, thus minimizing the potential of pollution;

-       Maintain and clean storage areas routinely;

-       Stockpiling area shall be provided with covers and water spraying system to prevent materials from wind-blown or being washed away; and

-       Different locations shall be designated to stockpile each material to enhance reuse.

To minimize potential adverse environmental impacts arising from waste storage

Contractor

Work Sites

Construction Phase

-

DP1, DP2, DP3, DP4

S12.80

Storage, Collection and Transportation of Waste (con’t)

Waste haulier with appropriate permits shall be employed by the Contractor for the collection and transportation of waste from works areas to respective disposal outlets. The following suggestions shall be enforced to minimize the potential adverse impacts:

-       Remove waste in timely manner

-       Waste collectors shall only collect wastes prescribed by their permits

-       Impacts during transportation, such as dust and odour, shall be mitigated by the use of covered trucks or in enclosed containers

-       Obtain relevant waste disposal permits from the appropriate authorities, in accordance with the Waste Disposal Ordinance (Cap. 354), Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 345) and the Land (Miscellaneous Provisions) Ordinance (Cap. 28)

-       Waste shall be disposed of at licensed waste disposal facilities

-       Maintain records of quantities of waste generated, recycled and disposed 

To minimize potential adverse environmental impacts arising from waste collection and disposal

Contractor

Work Sites

Construction Phase

-

DP1, DP2, DP3, DP4

S12.81

Storage, Collection and Transportation of Waste (con’t)

-       Implementation of trip ticket system with reference to DevB TC(W) No.6/2010 to monitor disposal of waste and to control fly-tipping at PFRFs or landfills.  A recording system for the amount of waste generated, recycled and disposed (including disposal sites) shall be proposed.

To minimize potential adverse environmental impacts arising from waste collection and disposal

Contractor

Work Sites

Construction Phase

DEVB TCW No. 6/2010

DP1, DP2, DP3, DP4

S12.83 – 12.86

Sorting of C&D Materials

-       Sorting to be performed to recover the inert materials, reusable and recyclable materials before disposal off-site. 

-       Specific areas shall be provided by the Contractors for sorting and to provide temporary storage areas for the sorted materials. 

-       The C&D materials shall at least be segregated into inert and non-inert materials, in which the inert portion could be reused and recycled as far as practicable before delivery to PFRFs as mentioned for beneficial use in other projects.  While opportunities for reusing the non-inert portion shall be investigated before disposal of at designated landfills.

-       Possibility of reusing the spoil in the Project will be continuously investigated in the detailed design and construction stages, it includes backfilling to cut and cover construction works for the Hung Hom south and north approach tunnels.

To minimize potential adverse environmental impacts during the handling, transportation and disposal of C&D materials

Contractor

Work Sites

Construction Phase

DEVB TCW No. 6/2010ETWB TCW No. 33/2002

ETWB TCW No. 19/2005

 

DP1, DP2, DP3

S12.88

Sediments

-       The basic requirements and procedures for excavated / dredged sediment disposal specified under ETWB TC(W) No. 34/2002 shall be followed. MFC is managing the disposal facilities in Hong Kong for the dredged and excavated sediment, while EPD is the authority of issuing marine dumping permit under the Dumping at Sea Ordinance.

To ensure the sediment to be disposed of in an authorized and least impacted way

Contractor

All works areas with sediments concern

Construction Phase

ETWB TC(W) No. 34/2002 & Dumping at Sea Ordinance

DP1, DP2, DP3, DP4

S12.89

Sediments (con’t)

-       The contractor for the excavation / dredging works shall apply for the site allocations of marine sediment disposal based on the prior agreement with MFC/CEDD. A request for reservation of sediment disposal space have been submitted to MFC for onward discussions of disposal approach and feasible disposal sites and the letter is attached in Appendix 12.6. The Project proponent shall also be responsible for the application of all necessary permits from relevant authorities, including the dumping permit as required under DASO from EPD, for the disposal of dredged and excavated sediment prior to the commencement of the excavation works.

To determine the best handling and disposal option of the sediments

MTR / Contractor

All works areas with sediments concern

Detailed Design Stage and Construction Phase

ETWB TC(W) No. 34/2002 & Dumping at Sea Ordinance

DP1, DP2, DP3, DP4

S12.91 – 12.94

Sediments (con’t)

-       Stockpiling of contaminated sediments shall be avoided as far as possible. If temporary stockpiling of contaminated sediments is necessary, the excavated sediment shall be covered by tarpaulin and the area shall be placed within earth bunds or sand bags to prevent leachate from entering the ground, nearby drains and/or surrounding water bodies.  The stockpiling areas shall be completely paved or covered by linings in order to avoid contamination to underlying soil or groundwater.  Separate and clearly defined areas shall be provided for stockpiling of contaminated and uncontaminated materials.  Leachate, if any, shall be collected and discharged according to the Water Pollution Control Ordinance (WPCO).

-       In order to minimise the potential odour / dust emissions during excavation and transportation of the sediment, the excavated sediments shall be wetted during excavation / material handling and shall be properly covered when placed on trucks or barges.  Loading of the excavated sediment to the barge shall be controlled to avoid splashing and overflowing of the sediment slurry to the surrounding water.

-       The barge transporting the sediments to the designated disposal sites shall be equipped with tight fitting seals to prevent leakage and shall not be filled to a level that would cause overflow of materials or laden water during loading or transportation.  In addition, monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by the DEP.

-       In order to minimise the exposure to contaminated materials, workers shall, when necessary, wear appropriate personal protective equipments (PPE) when handling contaminated sediments.  Adequate washing and cleaning facilities shall also be provided on site.

To ensure handling  of sediments are in accordance to statutory requirements

Contractor

Work Sites, Sediment disposal sites

Construction Phase

ETWB TC(W) No. 34/2002 & Dumping at Sea Ordinance

DP1, DP2, DP3, DP4

S12.95

Sediments (con’t)

-       A possible arrangement for Type 3 disposal is by geosynthetic containment. A geosynthetic containment method is a method whereby the sediments are sealed in geosynthetic containers and, at the disposal site, the containers would be dropped into the designated contaminated mud pit where they would be covered by further mud disposal and later by the mud pit capping, thereby meeting the requirements for fully confined mud disposal. The technology is readily available for the manufacture of the geosynthetic containers to the project-specific requirements. Similar disposal methods have been used for projects in Europe, the USA and Japan and the issues of fill retention by the geosynthetic fabrics, possible rupture of the containers and sediment loss due to impact of the container on the seabed have been addressed.

To ensure handling  of sediments are in accordance to statutory requirements

Contractor

Work Sites, Sediment disposal sites

Construction Phase

ETWB TC(W) No. 34/2002 & Dumping at Sea Ordinance

DP1, DP2, DP3, DP4

S12.97

Containers for Storage of Chemical Waste

The Contractor shall register with EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Containers used for storage of chemical waste shall:

-       Be compatible with the chemical wastes being stored, maintained in good condition and securely sealed;

-       Have a capacity of less than 450 litters unless the specifications have been approved by EPD; and

-       Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Waste Disposal (Chemical Waste) (General) Regulation.

To register with EPD as a Chemical waste producer and store chemical waste in appropriate  containers

Contractor

Work Sites

Construction Phase

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

DP1, DP2, DP3, DP4

S12.98

Chemical Waste Storage Area

-       Be clearly labeled to indicate corresponding chemical characteristics of the chemical waste and used for storage of chemical waste only;

-       Be enclosed on at least 3 sides;

-       Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

-       Have adequate ventilation;

-       Be covered to prevent rainfall from entering; and

-       Be properly arranged so that incompatible materials are adequately separated.

To prepare appropriate  storage areas for chemical waste at works areas

Contractor

Work Sites

Construction Phase

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

DP1, DP2, DP3, DP4

S12.99

Chemical Waste

-       Lubricants, waste oils and other chemical wastes would be generated during the maintenance of vehicles and mechanical equipments.  Used lubricants shall be collected and stored in individual containers which are fully labelled in English and Chinese and stored in a designated secure place. 

To clearly label the chemical waste at works areas

Contractor

Work Sites

Construction Phase

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

DP1, DP2, DP3, DP4

S12.100

Collection and Disposal of Chemical Waste

A trip-ticket system shall be operated in accordance with the Waste Disposal (Chemical Waste) (General) Regulation to monitor all movements of chemical waste.  The Contractor shall employ a licensed collector to transport and dispose of the chemical wastes, to either the approved CWTC at Tsing Yi, or another licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

To monitor the generation, reuse and disposal of chemical waste

Contractor

Work Sites

Construction Phase

Waste Disposal (Chemical Waste) (General) Regulation

DP1, DP2, DP3, DP4

S12.101

General Refuse

General refuse shall be stored in enclosed bins or compaction units separate from C&D materials and chemical waste.  A reputable waste collector shall be employed by the contractor to remove general refuse from the site, separately from C&D materials and chemical wastes.  Preferably, an enclosed and covered area shall be provided to reduce the occurrence of wind-blown light material.

To properly store and separate from other C&D materials for subsequent collection and disposal

Contractor

Work Sites

Construction Phase

-

DP1, DP2, DP3, DP4

S12.102

General Refuse (con’t)

The recyclable component of general refuse, such as aluminum cans, paper and cleansed plastic containers shall be separated from other waste.  Provision and collection of recycling bins for different types of recyclable waste shall be set up by the Contractor.  The Contractor shall also be responsible for arranging recycling companies to collect these materials.

To facilitate recycling of recyclable portions of refuse

Contractor

Work Sites

Construction Phase

-

DP1, DP2, DP3, DP4

S12.103

General Refuse (con’t)

The Contractor shall carry out an education programme for workers in avoiding, reducing, reusing and recycling of materials generation.  Posters and leaflets advising on the use of the bins shall also be provided in the sites as reminders.

To raise workers’ awareness on recycling issue

Contractor

Work Sites

Construction Phase

-

DP1, DP2, DP3, DP4

Operation Phase

 

 

 

 

 

 

S12.106 – 12.107

Chemical Waste

-       The requirements given in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes would be followed in handling of chemical waste as in construction phase.  A trip-ticket system would be adopted by the operator to monitor disposal of chemical waste.

-       Non-recyclable chemical waste shall be disposed of at appropriate facility like CWTC by licensed collectors.  Recyclable chemical waste shall be collected and transported off-site by licensed collectors.

To avoid environmental impacts in handling, storage and disposal of chemical waste

MTR

All facilities

Operation Phase

Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes

 

Waste Disposal (Chemical Waste) (General) Regulation

DP1, DP2

S12.108 – 12.109

General Refuse

-       Recycling of waste paper, aluminum cans and plastic bottles shall be encouraged, it is recommended to place clearly labelled recycling bins at designated locations which could be accessed conveniently.  Other general refuse shall be separated from chemical and industrial waste by providing separated bins for storage to maximize the recyclable volume.

-       A reputable licensed waste collector shall be employed to remove general refuse on a daily basis to minimize odour, pest and litter impacts.

To separate general refuse from other waste types and proper disposal of the refuse

MTR

All facilities

Operation Phase

Public Health and Municipal Services Ordinance (Cap. 132)

DP1, DP2

S12.110

Industrial Waste

-       Industrial waste, generated mainly from the maintenance works, shall be separated from other types of waste during disposal.  Moreover, steel shall be sorted out for their resalable value.  A licensed collector shall be employed for the collection of industrial waste.

To recycle useful materials from industrial waste and proper disposal

MTR

All facilities

Operation Phase

-

DP1, DP2

Land Contamination Impact  

 

S13.23– 13.24

For construction works at sites under the current stage of site investigation (Stage 1 SI):

Ÿ Precautionary measures such as visual inspection are recommended to be undertaken during construction activities that disturb soil.  The inspection process shall involve a visual observation of excavated soils for discolouration and the presence of oils, together with identifying the presence of odours, which may also indicate soil and/or groundwater contamination. 

Ÿ If soil materials suspected to be contaminated are encountered during excavation, sampling and testing shall be undertaken to verify the presence of contamination.  The soil extracted during demolition, excavation and cut & cover construction shall be temporary stockpiled.  Shall concentrations of contaminants of concern (COCs) exceed relevant RBRGs as indicated by laboratory analyses, remediation works shall be undertaken with reference to the Contamination Assessment Report (CAR) and Remediation Action Plans (RAP).

To act as a general precautionary measure to screen soils for the presence contamination during excavation works for Cut-and-Cover.

Contractor

Within Project Boundary where signs of contamination is identified

During excavation works for Cut-and-Cover

Guidance Note for Contaminated Land Assessment and Remediation

 

Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

DP1, DP2

S13.30

For some sites with currently no SI proposed (i.e. sites ID 2-02, 2-18, 2-22, 2-23, 2-27, 2-28), to be conservative, visual inspection shall be conducted during demolition and excavation  to detect any abnormal colour, smell or other characteristics of the soil, due to the nearby land use and/ or construction method.  If abnormal colour, smell or other characteristics of contamination are identified for any of these sites, sampling and testing shall be undertaken to verify the presence of contamination.  The soil extracted during demolition, excavation and cut & cover construction shall be temporary stockpiled.  Should the concentrations of contaminants of concern (COCs) exceed relevant RBRGs as indicated by laboratory analyses, remediation works shall be undertaken with reference to the CAR and RAP.

 

To act as a general precautionary measure to screen soils for the presence contamination during excavation works for Cut-and-Cover.

Contractor

Areas with no SI proposed (Sites ID 2-02, 2-18, 2-22, 2-23, 2-27, 2-28)

During excavation works for Cut-and-Cover

Guidance Note for Contaminated Land Assessment and Remediation

 

Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

DP1, DP2

S13.36 –

13.38

For areas inaccessible for proper site appraisal and investigation (Stage 2 SI)   

(i) Site 2-15

Ÿ Upon site access being granted, visual inspection shall be carried out where intrusive works and soil excavation is encountered, for attention on any potential contamination due to its current operation

Ÿ A supplementary CAP shall then be submitted to EPD for endorsement.

Ÿ  A CAR/RAP shall be prepared and submitted to EPD for endorsement on completion of the SI and analytical testing.

Ÿ Shall remediation be undertaken a Remediation Report (RR) shall be prepared and submitted to EPD for endorsement to demonstrate that the decontamination work is adequate and is carried out in accordance with the endorsed CAR and RAP.  Information such as soil treatment/ disposal records (including trip tickets), confirmatory sampling results, and photographs shall be included in the aforesaid RR. 

Ÿ No construction work shall be carried out prior to the endorsement of the RR by EPD.

(i)    To identify areas with land contamination concern, report laboratory results and propose remediation measures if necessary.

 

(ii)   To ensure remediation works have been undertaken to before the commencement of any construction works of the Project.

 

Contractor

Areas unable to be accessed during Stage 1 SI (Site 2-15)

After land resumption and prior to the construction works commencement at the site

Guidance Note for Contaminated Land Assessment and Remediation

 

Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

 

DP1, DP2

S13.39

Potential Remediation of Contaminated Soil

Ÿ Excavation profiles must be properly designed and executed with attention to the relevant requirements for environment, health and safety;

Ÿ Excavation shall be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils;

Ÿ Supply of suitable clean backfill material is needed after excavation;

Ÿ If remediation is required with chemical oxidation proposed as a contaminant mass reduction technology, chemicals will be securely and separately stored away from sources of ignition or oxidisable items.  Handling will be undertaken by personnel with appropriate training and personal protective equipment (PPE).

Ÿ Vehicles containing any excavated materials shall be suitably covered to limit potential dust emissions or contaminated wastewater run-off, and truck bodies and tailgates shall be sealed to prevent any discharge during transport or during wet conditions;

Ÿ Speed control for the trucks carrying contaminated materials shall be enforced;

Ÿ Vehicle wheel and body washing facilities at the site’s exit points shall be established and used; and

Ÿ Pollution control measures for air emissions e.g. from biopile blower, noise emissions e.g. from blower, and water discharges e.g. runoff control shall be implemented and complied with relevant regulations and guidelines.

To remediate contaminated soil

Contractor

 Identified contaminated sites 

Site remediation

Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards and Car Repair /Dismantling Workshop

DP1, DP2

S13. 40

In order to minimize the potential adverse effects on health and safety of construction workers during the course of site remediation, the Occupation Safety and Health Ordinance (OSHO) (Chapter 509) and its subsidiary Regulations shall be followed by all site personnel working on the site at all times. In addition, the following basic health and safety measures shall be implemented as far as possible:

Ÿ Set up a list of safety measures for site workers;

Ÿ Provide written information and training on safety for site workers;

Ÿ Keep a log-book and plan showing the contaminated zones and clean zones;

Ÿ Maintain a hygienic working environment;

Ÿ Avoid dust generation;

Ÿ Provide face and respiratory protection gear to site workers;

Ÿ Provide personal protective clothing (e.g. chemical resistant jackboot, liquid tight gloves) to site workers; and

Ÿ Provide first aid training and materials to site workers.

To minimise the potentially adverse effects on health and safety of construction workers during the course of site remediation.

Contractor

Identified contaminated sites 

Site remediation and prior to construction phase

Guidance Note for Contaminated Land Assessment and Remediation

 

Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management

DP1, DP2

Hazard to Life

 

S14.31

Blasting activities should be supervised and audited by competent site staff to ensure strict compliance with the blasting permit conditions. The following general recommendation should also be considered:

·       The security plan should address different alert security level to reduce opportunity for arson / deliberate initiation of explosives. The corresponding security procedure should be implemented with respect to prevailing security alert status announced by the Government.

·       Adverse weather working guideline should be developed to clearly define procedure for marine transport of explosives during thunderstorm, bad visibility (fog) etc.

·       In case a blast cannot proceed after the Contractor’s explosives delivery vessel has already accepted delivery at the TKO Area 137 Pier, contingency plans should be developed subject to prior discussions with both Marine Department and Mines Division.

To ensure safe marine transport of explosives

MTR / Contractor

Works area/ pontoon and along explosives marine transport route

Construction phase

Dangerous Goods Ordinance

DP2

S14.32

The following measures should be considered for safe marine transport of explosives:

·       Detonator compartment shall be isolated from the rest of the explosives.

·       Location for stopping and unloading from vessel to be provided beside the work pontoon free from obstacles, hot work, etc. during time of unloading.

·       Develop procedure to ensure that berthing space at the pontoon is available for the explosives vessel. Confirmation of berthing space should be communicated to vessel captain before delivery. If berthing space at the pontoon cannot be secure, delivery should not commence.

·       During preparation of the explosives at the works pontoon, hot work or other activities should not be permitted in the vicinity of the explosives offloading or preparation activities.

·       Ensure lining is provided within the hold on the vessel and in good condition before transportation.

·       Ensure that packaging of detonators remains intact until handed over at blasting site.

·       Emergency plan to include prevention of fire spreading and reducing likelihood of prolonged fire leading to explosion.

·       Use only experienced captains with good safety record.

·       Ensure that cartridged emulsion packages are damage free before every trip.

·       During preparation of the explosives at the works pontoon, special precautions may need to be taken around the pontoon area as the marine traffic is only halted/evacuated once all the blastholes have been charged and the blast is ready to be fired.

To ensure safe marine transport of explosives

MTR / Contractor

Works area/ pontoon/ along explosives marine transport route

Construction phase

Dangerous Goods Ordinance

DP2

S14.35

Ensure that cartridged emulsion with high water content shall be preferred. Also, the emulsion with perchlorate formulation shall be avoided.

To ensure safe explosives to be used.

MTR / Contractor

-

Construction phase

Dangerous Goods Ordinance

DP1,DP2

S14.36

If disposal is required for small quantities, disposal shall be made in a controlled and safe manner by a Registered Shotfirer.

To minimize the hazard to life issue in relation to use of explosives

MTR / Contractor

Works area

Construction phase

Dangerous Goods Ordinance

DP1,DP2

S14.37

Contingencies shall be developed for disposal of large quantities of explosives subject to prior discussions with Mines Division.

To minimize the hazard to life issue in relation to use of explosives

MTR / Contractor

-

Construction phase

Dangerous Goods Ordinance

DP1,DP2

S14.39

Subsequent to the consultation with HKCG and according to their requirements for works within the vicinity of submarine gas pipelines the following safety measures are recommended:

·       There should be a procedure to ensure that the crew do not drop the anchor within the no-anchoring zone accidentally;

·       HKCG should be notified about the blasting schedule in written format within a reasonable period of time prior to blasting in order to ensure the gas safety during the construction period. Also, agreed emergency response plan with HKCG should be established.

·       HKCG should be consulted, and method statement to be forwarded to HKCG for comment, prior to the commencement of site works (one week in advance); and

·       HKCG should be informed immediately of any suspected damage, by way of their emergency control centre, telephone: 28806999, which is manned 24 hours.

To minimize the hazard to life issue in relation to fuel gas safety

MTR / Contractor

Within the vicinity of the submarine gas pipelines

Construction phase

Dangerous Goods Ordinance

DP2

 

Remarks:

DP1: A railway and its associated stations 

DP2: A railway tunnel more than 800m in length between portals 

DP3: Reclamation works (including associated dredging works) of more than 1 ha in size with a boundary of which is less than 100m from a seawater intake point or resulting in 5% decrease in cross sectional area calculated on the basis of 0.0mPD in a sea channel

DP4: A dredging operation at the cross harbour section exceeding 500,000 m3 or a dredging operation which is less than 100m from a seawater intake point

N/A: Not applicable