Contents
7.5 Laboratory Measurement / Analysis
8.3 Noise Monitoring Parameters
8.5 Monitoring Locations for
Construction Phase
8.6 Baseline Monitoring for Construction
Phase
8.7 Impact Monitoring for Construction
Phase
8.8 Event and Action Plan for
Construction Phase
8.9 Operation
Rail Noise Monitoring
8.10 Monitoring
Equipment and Methodology
8.11 Noise Monitoring
Stations
9.3 Groundborne Noise Monitoring
Parameters and Criteria
10.8 Laboratory
Measurement / Analysis
12.2 Excavation and
Disposal Methodology
12.4 Protective and
Safety Measures
14.3 Choice of
Construction Method
15.2 Baseline Monitoring
Report
15.4 Final EM&A
Review Reports
15.6 Interim
Notifications of Environmental Quality Limit Exceedances
Appendices
Appendix A Environmental Mitigation Implementation
Schedule
Appendix B Project Organisation for Environmental Works
Appendix C Sample Data Sheet for Monitoring
Appendix D Sample Template for Interim Notification
Appendix E Proactive
Environmental Protection Proforma
Tables
Table 2.1 Summary of design of SCL Tai Wai to Hung Hom Section
Table 2.2 Summary of Potential Concurrent Projects
Table 4.1 Audit Requirements and Frequency
Table 6.1 Event / Action Plan for Landscape and Visual during
Construction Stage
Table 7.1 Proposed construction dust monitoring locations
Table 7.2 Summary of Baseline Dust Monitoring Programme
Table 7.3 Summary of construction dust monitoring programme
Table 7.4 Action / Limit Levels for Air Quality
Table 7.5 Event and Action Plan for Air Quality
Table 8.1 Proposed construction airborne noise monitoring locations
Table 8.2 Action and Limit Levels
Table 8.3 Event and Action Plan
Table 8.4 Monitoring Stations during Operation Phase
Table 10.1 Water quality monitoring stations (construction phase –
dredging activities)
Table 10.2 Proposed water quality monitoring programme
Table 10.3 Proposed water quality monitoring programme
Table 10.4 Laboratory analysis for SS
Table 10.5 Action and Limit Levels for Water Quality
Table 10.6 Event and Action Plan for Water Quality
Table 12.1 Requirements for compliance testing
Figures
Figure
1.1 General
Alignment of SCL (Tai Wai to Hung Hom)
Figure
1.2 Locations
of Off-site Works Areas
Figure
1.3 Locations
of Concurrent Projects
Figure
4.1 Survey-cum-excavation
– Former Tai Hom Village
Figure
4.2 Tentative
Extent of Survey-cum-excavation Area at Sacred Hill
Figure
4.3 Buffer
Zone from the Boundary of Lung Tsun Stone Bridge
Figure
5.1 Proposed
Locations for Transplanting Trees for Bat Roosts in Tai Hom Village
Figure
7.1.1 Locations of Proposed Dust Monitoring Stations (Sheet 1 of
7)
Figure
7.1.2 Locations of Proposed Dust Monitoring Stations (Sheet 2 of
7)
Figure
7.1.3 Locations of Proposed Dust Monitoring Stations (Sheet 3 of
7)
Figure
7.1.4 Locations of Proposed Dust Monitoring Stations (Sheet 4 of
7)
Figure
7.1.5 Locations of Proposed Dust Monitoring Stations (Sheet 5 of
7)
Figure
7.1.6 Locations of Proposed Dust Monitoring Stations (Sheet 6 of
7)
Figure
7.1.7 Locations of Proposed Dust Monitoring Stations (Sheet 7 of
7)
Figure
8.1.1a Proposed Noise Barriers and Associated Retaining Walls
(Sheet 1 of 2)
Figure
8.1.1b Proposed Noise Barriers and Associated Retaining Walls
(Sheet 1 of 2)
Figure
8.1.2 Location of Noise Cover near Mei Tin Road
Figure
8.2.1 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise) (Sheet 1 of 6)
Figure
8.2.2 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise) (Sheet 2 of 6)
Figure
8.2.3 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise) (Sheet 3 of 6)
Figure
8.2.4 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise) (Sheet 4 of 6)
Figure
8.2.5 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise)
(Sheet 5 of 6)
Figure
8.2.6 Locations of Proposed Noise Monitoring Stations
(Construction Airborne Noise) (Sheet 6 of 6)
Figure
8.3.1 Locations of Proposed Noise Monitoring Stations (Operational
Airborne Noise) (Sheet 1 of 2)
Figure
8.3.2 Locations of Proposed Noise Monitoring Stations (Operational
Airborne Noise) (Sheet 2 of 2)
Figure
9.1.1 Locations of Proposed Groundborne Noise Monitoring Stations
(Commissioning Test) (Sheet 1 of 3)
Figure
9.1.2 Locations of Proposed Groundborne Noise Monitoring Stations
(Commissioning Test) (Sheet 2 of 3)
Figure
9.1.3 Locations of Proposed Groundborne Noise Monitoring Stations
(Commissioning Test) (Sheet 3 of 3)
Figure
10.1 Locations
of Proposed Water Quality Monitoring Stations
Figure
12.1 Location
of Hot Spot Contamination Area
The Shatin to Central Link (SCL) is one of the railway projects
recommended for implementation in Railway Development Strategy 2000. It is an
integral component of the expanded rail network, which will be required to support
the economic, social and population growth of the HKSAR in the coming
years. In particular, it will
support the urban renewal of the existing Kowloon City District, planned Kai
Tak Development (KTD) and further developments in
The SCL is also one of the ten large-scale infrastructure projects announced by the Chief Executive in his 2007-2008 Policy Address. According to updated information, SCL is targeted to commence construction by mid 2012. For the purposes of the Environmental Impact Assessment (EIA), five EIA Studies have been conducted to cover different sections of the SCL. They include:
·
SCL – Tai Wai to Hung Hom Section [SCL (TAW-HUH)] (hereinafter referred
to as “the Project”, being considered in this EIA) – the extension of Ma On
Shan Line from Tai Wai Station via Hing Keng, Diamond Hill, Kai Tak, To Kwa
Wan, Ma Tau Wai and Ho Man Tin to Hung Hom, and link up with the existing West
Rail Line, along with a proposed stabling sidings option in Diamond Hill (DHS)1;.
·
SCL – Mong Kok East to Hung Hom Section [SCL (MKK-HUH)] – the realignment
work for the existing East Rail Line tracks from the tunnel portal near Oi Man
Estate (Portal 1A) to the proposed North Ventilation Building (NOV) in Hung
Hom;
·
SCL – Hung Hom to Admiralty Section [SCL (HUH-ADM)] – the section from
NOV, Plant Rooms and Emergency Access in Hung Hom across the harbour to the
Causeway Bay Typhoon Shelter (CBTS), Exhibition Station (EXH) and then to ADM;
·
SCL Protection works at Causeway Bay Typhoon Shelter – the section of
approximately 160m long of the SCL tunnel protection works at the crossing over
Central-Wan Chai Bypass (CWB) tunnels, which would be constructed under the CWB
project; and
·
SCL – Stabling Sidings at Hung Hom Freight Yard [SCL (HHS)] – another
stabling sidings option for SCL (TAW – HUH) proposed at the former freight yard
in Hung Hom[1].
The proposed tentative alignment of SCL (TAW-HUH) is shown in Figure 1.1 and the tentative locations of off-site works areas (e.g. office, general storage), off-site works sites (e.g. barging facilities, magazine sites etc) are shown in Figure 1.2.
The purposes of this Environmental Monitoring and Audit (EM&A)
Manual are to:
· Guide the set up of an EM&A programme to ensure compliance with the EIA recommendations;
· Specify the requirements for monitoring equipment;
· Propose environmental monitoring points, monitoring frequency etc.;
· Propose Action and Limit Level; and
· Propose Event and Action Plan.
This
EM&A Manual has been prepared in accordance with the requirements
stipulated in Annex 21 of the Technical Memorandum on the EIA Process
(TM-EIAO). This Manual outlines the monitoring and audit programme for the
construction and operation of the proposed SCL (TAW – HUH) and provides
systematic procedures for monitoring, auditing and minimising environmental
impacts.
This Manual contains the following information:
· Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET), and the Independent Environmental Checker (IEC) under the context of EM&A;
· Project organisation for the EM&A works;
· The basis for, and description of the broad approach underlying the EM&A programme;
· Details of the methodologies to be adopted, including all laboratories and analytical procedures, and details on quality assurance and quality control programme;
· The rationale on which the environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit levels;
· Establishment of Event and Action plans;
· Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints; and
· Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures.
This EM&A Manual is a dynamic document that should be reviewed
regularly and updated as necessary during the construction and operation of the
Project including those updates noted in the EIA.
For the purpose of this manual, the ER shall refer to the Engineer as
defined in the Construction Contract, in cases where the Engineer's powers have
been delegated to the ER, in accordance with the Construction Contract. The ET leader, who shall be responsible
for and in charge of the ET, shall refer to the person delegated the role of
executing the environmental monitoring and audit requirements.
2.1 General Alignment
The SCL (TAW-HUH) is an
approximately
DIH will become an interchange station with the
existing Kwun Tong Line (KTL). The
SCL (TAW – HUH) will interchange with the Kwun Tong Line Extension (KTE) and
the SCL (MKK-HUH) at HOM and HUH respectively. The HOM and HUH are
part of other Designated Projects to be separately implemented.
A new train stabling sidings option will be located
at the Diamond Hill CDA site (i.e. former
The SCL (TAW-HUH) will also
form an important part of the proposed KTD, providing mass transit service not
only to the proposed new commercial and residential developments in the area,
but also the Multi-Purpose Stadium Complex and other leisure facilities planned
at Kai Tak.
The proposed tentative alignment is shown in Figure 1.1 and the
tentative locations of off-site works areas (e.g. office, general storage,
barging facilities, magazine sites etc.) are shown in Figure 1.2. A broad
description of different sections of the alignment is given below.
The SCL (TAW-HUH) departs
from the existing MOL at south of Tai Wai Depot. Leaving the Tai Wai Depot, the track
would maintain on embankment and connect to HIK which is an elevated station.
After departing from HIK with a section of viaduct
and embankment, the alignment then heads towards the Hin Keng portal at the
west of Hin Keng Estate. Once into
the portal, the alignment runs under the Lion Rock. There would not be any at-grade
construction activities within the
From the
A train stabling sidings would be constructed in
the former
2.1.2
Diamond Hill to To Kwa Wan
After leaving the DIH, the SCL (TAW-HUH) runs
adjacent to the Tate’s Cairn Viaduct and crosses Prince Edward Road East to
reach KAT within the Kai Tak Development area, currently a vacant site but with
planned future residential and commercial developments.
The alignment runs towards southwest and enters TKW
near
The alignment runs below
After leaving MTW, the alignment passes
After leaving HOM, the alignment runs below the
Winslow Street underpass and the Chatham Road North embankment and then passes
through the HUH portal adjacent to Sai Sing Funeral Parlour. Out of the HUH portal,
the alignment runs at-grade and heads to HUH.
The tracks for SCL (TAW-HUH) within
extension of the HUH area would be at-grade and would eventually join the
existing West Rail Line (WRL) tunnel near to the junction of Salisbury Road and
Science Museum Road.
The SCL (TAW-HUH) would
interface with the SCL (MKK-HUH) and SCL (HUH-ADM) at new HUH
to be implemented by other Designated Project. Passengers would be able to interchange
at this station.
The HUH would be entirely under the existing podium
deck.
As discussed in Section 2.1.1 to 2.1.3, the alignment will run through different
areas in Tai Wai, Wong Tai Sin, Diamond Hill, Kai Tak, To Kwa Wan and Hung Hom.
Most of these areas are relatively flat terrains except for the areas in Lion
Rock and Chuk Yuen.
A board summary of the general design of SCL (TAW –
HUH) is given below:
Table 2.1: Summary of design of SCL
Tai Wai to Hung Hom Section
Type |
Location |
Design |
Alignment
sections |
Tai Wai Depot |
At-grade |
Tai Wai Depot to HIK |
Embankment |
|
HIK to HIK
Portal |
Viaduct +
Embankment + Tunnel |
|
HIK Portal |
Embankment |
|
HIK Portal to
DIH |
Tunnel |
|
DIH to KAT |
Tunnel |
|
KAT to TKW |
Tunnel |
|
TKW to MTW |
Tunnel |
|
MTW to HOM |
Tunnel |
|
HOM to HUH
Portal |
Tunnel |
|
HUH Portal |
From Tunnel
to At-grade |
|
HUH Portal to
WRL Tunnel |
At-grade
section |
|
Stations |
HIK |
Elevated
station |
DIH |
Underground
station |
|
Diamond Hill
Stabling Sidings (DHS) |
Semi-underground |
|
KAT |
Underground
station |
|
TKW |
Underground
station |
|
MTW |
Underground
station |
|
HOM [1] |
Underground
station (by other Designated Project) |
|
HUH [1] |
Semi-underground
station (by other Designated Project) |
|
|
Ma Chai Hang |
At-grade
structure |
Emergency Access/Emergency Escape Access (EA/EEA) |
Wong Tai Sin |
At-grade
structure |
|
Ma Chai Hang |
Integrated
with Ma |
Emergency
Egress Point |
Tam |
At-grade
structure |
Notes:
[1] The
HOM would be implemented under the KTE and The HUH would be implemented under
the SCL (MKK-HUH). Their cumulative impacts have been addressed in
the EIA to fulfil the requirements of the EIA study Brief.
According to the latest programme, the
construction works for SCL (TAW-HUH) would commence in 2012. All major civil contracts would be
completed by 2016. The remaining
station fit-out, track layout etc works would be completed by 2018. This would
however be subject to changes during the on-going design process.
Detailed EIA assessments have been conducted and
presented in the EIA report.
Mitigation measures have also been identified and recommended. The Environmental Mitigation
Implementation Schedule (EMIS) is given in Appendix A. It specifies the extent, locations, time
frame and responsibilities for the implementation of the environmental
mitigation measures identified.
The possible potential concurrent projects in the vicinity of the SCL (TAW-HUH) are identified as follows. Figure 1.3 shows the location and alignment of these concurrent projects.
· Shatin to Central Link – Mong Kok East to Hung Hom Section, Hung Hom to Admiralty Section and Protection Works at Causeway Bay Typhoon Shelter;
·
Central
·
Widening of
· Kai Tak Development;
· Kwun Tong Line Extension & Associated EPIW;
·
HKPU Student Hostel (Phase 3) Development at
·
Ex-San
· Tsz Wan Shan Pedestrian Link;
· Covered Walkway at Kai Tak;
· Comprehensive Development (CDA) at Diamond Hill;
· Submarine Gas Pipelines;
· In-situ Reprovisioning of Sha Tin Water Treatment Works – South Works – Design and Construction; and
· Proposed 132kV Cable Circuits Connecting with Ho Man Tin KCRC Substation and Tsim Sha Tsui Substation (Hung Hom Side).
2.4.1 Summary of Concurrent Projects
The potential impacts of concurrent projects during
the construction and operation of the proposed SCL (TAW-HUH) are
summarised below:
Table 2.2 Summary
of Potential Concurrent Projects
Project |
Potential Cumulative Impacts |
||
(Construction Methodology [2]) |
Construction Phase [1] |
Operational Phase [1] |
|
SCL
(MKK-HUH) (cut-&-cover tunnel) |
· Fugitive dust · Airborne noise · Groundborne noise impact (for receivers near HUH) · Landscape and visual |
· Airborne Noise · Groundborne noise impact (for receivers near HUH) · Landscape and visual |
|
SCL
(HUH-ADM) (Dredging for marine tunnel would not be not concurrent
with the Project) |
· Fugitive dust · Airborne Noise · Ecology · Landscape and Visual |
· Airborne Noise · Landscape and Visual |
|
Protection
Works at |
· Nil |
· Nil |
|
Central Kowloon Route |
· Fugitive dust · Noise · Visual · Water quality |
· Visual |
|
Widening of Gascoigne Road |
· Not concurrent |
· Nil |
|
Kai Tak Development (Package A, B and C) |
· Fugitive dust · Airborne noise · Visual |
· Visual |
|
Housing Authority Development Sites 1A & 1B within Kai
Tak Development (superstructure construction) |
· Fugitive dust · Visual |
· Visual |
|
(nullah modification and landscape works) |
· Fugitive dust · Airborne noise · Visual |
· Visual |
|
Multi-Purpose Stadium Complex within Kai Tak Development (construction method to be established by respective
proponent) |
· Fugitive dust · Airborne noise |
· Nil · |
|
District Cooling System within Kai Tak Development (no dredging required, pumping station is underground and
away from noise and air receivers for the Project, only minor construction
works required for the pipework). |
· Nil |
·
Nil |
|
Trunk Road T2 within Kai Tak Development (at-grade and tunnelling work, but far away from noise and
air receivers for the Project) |
· Nil |
·
Nil |
|
Cruise Terminal within Kai Tak Development (concurrent dredging with that for the project, but far
away from noise and air receivers for the Project) |
· Water quality · |
·
Nil |
|
Other Infrastructure within Kai Tak Development |
· Fugitive dust · Airborne noise · Visual |
·
Visual |
|
Commercial Facilities
Development Above Kai Tak Station |
· Not concurrent |
·
Visual |
|
Kwun Tong Line Extension & Associated EPIW (cut-&-cover station and tunnel) |
· Fugitive dust · Airborne noise · Landscape and visual |
· Groundborne noise · Landscape and visual · |
|
HKPU Student Hostel (Phase 3) Development at (typical superstructure construction) |
· Fugitive dust · Visual |
· Groundborne noise ·
Visual |
|
Ex-San Po Kong Flatted factory (typical superstructure construction) |
· Fugitive Dust · Visual |
· Groundborne noise ·
Visual |
|
Tsz Wan Shan Pedestrian Link (typical
at-grade works for lift and walkway systems) |
· Fugitive dust · Airborne noise · Visual |
·
Visual |
|
Covered Walkway at Kai Tak (typical
walkway construction) |
· No status |
·
No status |
|
Comprehensive Development Area (CDA) at
Diamond Hill |
·
Not
concurrent |
· Noise ·
Visual |
|
Submarine Gas Pipelines |
·
Water Quality |
·
Nil |
|
In-situ Reprovisioning of Sha Tin Water
Treatment Works – South Works – Designs and Construction |
·
Nil |
·
Nil |
|
Proposed 132kV Cable Circuits Connecting
with Ho Man Tin KCRC Substation and Tsim Sha Tsui Substation (Hung Hom Side) |
·
Nil |
·
Nil |
|
Note: [1] Construction phase of SCL (TAW-HUH).
[2]
For the section near SCL (TAW-HUH)
The roles and responsibilities of the
various parties involved in the EM&A process and the organisational structure
of the organisations responsible for implementing the EM&A programme are
outlined below. The proposed project organisation and lines of communication
with respect to environmental protection works are shown in Appendix B.
Engineer
or Engineer’s Representative (ER)
The Engineer is responsible for overseeing
the construction works and for ensuring that the works undertaken by the
Contractor in accordance with the specification and contractual requirements.
The duties and responsibilities of the Engineer with respect to EM&A may
include:
·
Supervise the Contractor’s activities and ensure
that the requirements in the EM&A Manual are fully complied with;
· Inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;
· Participate in joint site inspection undertaken by the Environmental Team (ET); and
· Adhere to the procedures for carrying out complaint investigation.
The
Contractor
The Contractor should report to the Engineer. The duties and responsibilities of the Contractor are:
·
Implement
the EIA recommendations and requirements;
·
Provide
assistance to the ET in carrying out relevant environmental monitoring;
·
Submit
proposals on mitigation measures in case of exceedances of Action and Limit
levels, in accordance with the Event and Action Plans;
·
Implement
measures to reduce environmental impacts where Action and Limit levels are
exceeded until the events are resolved; and
·
Adhere
to the procedures for carrying out complaint investigation in accordance with
Section 14 of this manual.
Environmental
Team (ET)
The
ET should conduct the EM&A programme and ensure the Contractor’s compliance
with the Project’s environmental performance requirements during
construction. The ET should be an
independent party from the Contractor.
The ET should be led and managed by the ET leader. The ET leader should possess at least 7 years of experience in EM&A. The ET should monitor the mitigation measures implemented by the Contractor on a regular basis to ensure the compliance with the intended aims of the measures. The duties and responsibilities of the ET are:
· Monitor the various environmental parameters as required in the EM&A Manual;
· Carry out site inspections to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and anticipate environmental issues for proactive and practicable action before problems arise;
· Analyse the EM&A data, review the success of EM&A programme to confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions, and to identify any adverse environmental impacts arising and report EM&A results to the IEC and the ER;
·
Adhere to the procedures for carrying out
complaint investigation in accordance with Section 14 of this Manual;
·
Liaison
with Independent Environmental Checker (IEC) on all environmental performance
matters, and timely submission of all relevant EM&A proforma for IEC's
approval;
·
Review
the proposals of mitigation measure from the Contractor in the case of
exceedances of Action and Limit levels, in accordance with the Event and Action
Plans;
·
Prepare
reports on the environmental monitoring data and the site environmental
conditions; and
· Timely submission of the EM&A report to the Director of Environmental Protection.
Independent
Environmental Checker (IEC)
The IEC shall advise the ER on environmental issues related to the Project. The IEC shall possess at least 7 years experience in EM&A. The duties and responsibilities of the IEC are:
·
Review
and audit in an independent, objective and professional manner in all aspects
of the EM&A programme;
·
Validate and
confirm the accuracy of monitoring results, monitoring equipment, monitoring
locations, monitoring procedures and locations of sensitive receivers;
·
Carry out random
sample check and audit on monitoring data and sampling procedures, etc;
·
Conduct random
site inspection;
·
Audit the EIA
recommendations and requirements against the status of implementation of
environmental protection measures on site;
·
Review the
effectiveness of environmental mitigation measures and project environmental
performance;
·
On as-needed
basis, verify and certify the environmental acceptability of the Environmental
Permit (EP) holder’s construction methodology (both temporary and permanent
works), relevant design plans and submissions under the EP;
·
Verify the
investigation results of the environmental complaint cases and the effectiveness
of corrective measures;
·
Verify EM&A
report that has been certified by the ET leader; and
·
Provide
feedback on the audit results to the ET or the EP holder according to Event and
Action Plans in the EM&A manual.
A cultural and heritage impact assessment for the Project has been
conducted according to the EIA Study Brief. The assessment has considered both the
construction and operational phases of the project.
The assessment has recommended some mitigation measures for both the
archaeological sites and some of the historical buildings where impacts would
be envisaged.
All the proposed mitigation measures
are presented below and summarised in the EMIS in Appendix A. Appropriate vibration monitoring on the built
heritages will be agreed with Buildings Department (BD)/Geotechnical
Engineering Office (GEO) and implemented under the requirement of the Buildings
Ordinance and/or Blasting Permit.
4.2.1
Previous studies at the former Tai Hom
Village Site reveal that the Tang/ Song Dynasty remains found are both sparse
and redepositied and hence of lesser archaeological significance. However,
assemblage of Tang/ Song archaeological finds within urban setting is
considered rare in
An
Archaeological Action Plan (AAP) following the Guideline for Archaeological
Impact Assessment should be submitted to the Antiquities and Monuments Office
(AMO) for agreement. The project proponent should appoint qualified and
experienced archaeologist(s) with sufficient funding, time and personnel
arrangements to implement the AAP. The AAP should include a detailed plan for
the survey-cum-excavation and a contingency plan to address possible
arrangement if significant archaeological findings are unearthed during the
survey-cum-excavation. Details of the proposal plan with specification for the
survey-cum-excavation should be agreed with AMO prior to the submission of
licence application.
The Former Royal Air Force Hangar, the Old Pillbox and the Stone House
No. 4 would be directly affected by the construction of the DHS and SCL-DIH. As detailed photographic and cartographic recorded
will be recommended to document the Hangar, Old Pillbox and the Stone House
prior to their removal, no other mitigation measure is required during the
operational phase of the SCL. The Old Pillbox would be reinstated as far as
practicable after being temporarily stored during the construction period.
Portions of the hangar frame would also be stored during construction and
placed in areas of the CDA site during operational stage to illustrate the
structural technology used during war time. A model to represent the current
form of the hangar will also be displayed to demonstrate the form and function
of the hangar. The project proponent shall submit a separate Conservation Plan
for these 3 historical buildings.
4.2.2 Sacred Hill (North Area)
The
archaeological investigation by CEDD has verified the archaeological potential
of the north of the Sacred Hill. Various evidences suggest that the area was
utilized as a burial or living ground, and then turned into a dumping area after the inhabitants
left the area. The study also concluded that the artifact density in the area
to the east, south and north is low.
Since the existing site for the Sacred Hill (North) Area had undergone a
series of reclamation over the past few decades, it is anticipated that the
archaeological potential for the fill material would be low and only the
original top soil layer is considered to have potential for archaeology. The survey-cum-excavation would be
limited to the original soil layer within temporary excavation areas within the
Sacred Hill (North) Study Area. The exact extent of survey-cum-excavation will
be subject to the construction details of the TKW. The tentative area requiring
survey-cum-excavation is shown in Figure
4.2. The exact area of rescue excavation would
be demarcated subject to the findings of the survey/investigation within the
Sacred Hill (North) Study Area.
An
Archaeological Action Plan (AAP) following the Guideline for Archaeological
Impact Assessment should be submitted to the Antiquities and Monuments Office
(AMO) for agreement. The project proponent should appoint qualified and
experienced archaeologist(s) with sufficient funding, time and personnel
arrangements to implement the AAP. The AAP should include a detailed plan for the survey-cum-excavation,
additional boreholes/trenches investigation and a contingency plan to address
possible arrangement if significant archaeological findings are unearthed.
Details of the proposal plan with specification for the survey-cum-excavation
and additional boreholes/trenches investigation should be agreed with AMO prior
to the submission of licence application.
4.2.3
Potential direct impact on the
According to the EIA, differential movements
within the remnants of the
Table 4.1 Audit Requirements and
Frequency
ID |
Structures/ buildings |
Audit Requirements |
Audit frequency |
Archaeological Sites |
|||
VM-1 |
|
· A buffer zone will be maintained between the |
·
On
a weekly basis throughout the construction period for the mined tunnel within
the horizontal buffer zone. |
VM-2 |
|
· A buffer zone to the Pier will be maintained
within which no at-grade construction activities will be carried out. |
·
On
a weekly basis throughout the construction period for the mined tunnel within
the horizontal buffer zone. |
5
Ecology
The EIA Report has assessed the ecologcial
impacts during construction and operational phases. Mitigation measures have been
recommended to ensure compliance of relevant legislative requirements. The mitigation measures and ecological monitoring and audit are given in the sections below.
5.2.1 Habitat Loss
A detailed vegetation survey should be conducted in
the Hin Keng Portal areas to locate and enumerate individuals of Aquilaria sinensis which will
potentially be affected by construction and operation of the Portal.
A suitable site for transplanting all affected
individuals within the footprint area should be identified and assessed for its
suitability. A transplantation plan
should then be drawn up and details of the transplantation methodologies and
programme along with post-transplantation monitoring should be included.
5.2.2 Tree Felling and Vegetation Clearance
Breeding pairs of Little Ringed Plover, Zitting
Cisticola and Plain Prinia were observed in the tall grassland and at the
fringes of the old Kai Tak runway. Nesting birds would be impacted by tree
felling and vegetation removal including cutting of grassland. Precautionary checks of the vegetation
for the presence of nesting bird species of conservation interest should be
carried out before vegetation clearance by a suitably experienced ecologist.
5.2.3 Relocation of Bat Tree
Chinese Fan Palms (Livistona chinensis) within the Project Site may be utilized by
Short-nosed Fruit Bats. A few no.
of trees at DIH will need to be relocated to an adjacent area prior to
construction works (see Figure 5.1).
Any individuals of Chinese Fan Palms that would
need to be relocated due to the proposed works should be checked for the
presence of Fruit Bat roosting.
5.2.4 Water Quality and Hydrology
Indirect water impact to any wetland habitats, such
as streams and coastal habitats, or wetland fauna should be avoided by
implementing water pollution control measures and good site practices (ETWB TCW No. 5/2005, Protection of natural
streams/ rivers from adverse impacts arising from construction works to avoid direct or indirect
impacts on the Tei Lung Hau Stream).
5.2.5
Others
Other mitigation measures are summarised in the EMIS in Appendix A.
To check that the recommended mitigation measures are properly implemented, weekly site audits should be conducted by the ET during construction phase of the Project.
The EIA has recommended landscape and visual mitigation measures to be undertaken during both the construction and operational phases of the project. The design, implementation and maintenance of landscape mitigation measures should be checked to ensure that any potential conflicts between the proposed landscape measures and any other works of the project would be resolved as early as practical without affecting the implementation of the mitigation measures.
The proposed mitigation measures of landscape and visual impacts are summarised in the EMIS in Appendix A. The landscape and visual mitigation measures proposed should be incorporated in the detailed landscape and engineering design. The construction phase mitigation measures should be adopted from the commencement of construction and should be in place throughout the entire construction period. Mitigation measures for the operational phase should be adopted during the detailed design and be built as part of the construction works so that they are in place on commissioning of the Project.
Site audits should be undertaken during the construction phase of the Project to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives. Site inspections should be undertaken by the ET at least once every two weeks during the construction period.
In the event of
non-compliance, the responsibilities of the relevant parties are detailed in
the Event/Action plan provided in Table 6.1.
Table 6.1: Event / Action Plan for
Landscape and Visual during Construction Stage
Action Level |
ET |
IEC |
ER |
Contractor |
Non-conformity on one occasion |
1. Inform the Contractor, the IEC and the ER 2. Discuss remedial actions with the IEC, the ER and the
Contractor 3. Monitor remedial actions until rectification has been
completed |
1. Check inspection report 2. Check the Contractor's working method 3. Discuss with the ET, ER and the Contractor on possible
remedial measures 4. Advise the ER on effectiveness of proposed remedial measures. |
1. Confirm receipt of notification of non-conformity in writing 2. Review and agree on the remedial measures proposed by the
Contractor 3. Supervise implementation of remedial measures |
1. Identify Source and investigate the non-conformity 2. Implement remedial measures 3. Amend working methods agreed with the ER as appropriate 4. Rectify damage and undertake any necessary replacement |
Repeated Non-conformity |
1. Identify Source 2. Inform the Contractor, the IEC and the ER 3. Increase inspection frequency 4. Discuss remedial actions with the IEC, the ER and the
Contractor 5. Monitor remedial actions until rectification has been
completed 6. If non-conformity stops, cease additional monitoring |
1. Check inspection report 2. Check the Contractor's working method 3. Discuss with the ET and the Contractor on possible remedial
measures 4. Advise the ER on effectiveness of proposed remedial measures |
1. Notify the Contractor 2. In consultation with the ET and IEC, agree with the
Contractor on the remedial measures to be implemented 3. Supervise implementation of remedial measures. |
1. Identify Source and investigate the non-conformity 2. Implement remedial measures 3. Amend working methods agreed with the ER as appropriate 4. Rectify damage and undertake any necessary replacement. Stop relevant portion of works
as determined by the ER until the non-conformity is abated. |
Note:
ET –
Environmental Team
IEC –
Independent Environmental Checker
ER –
Engineer’s
Representative
The EIA has considered the potential air quality impacts during both the construction and operational phases of the Project. Fugitive dust would be the key impacts during the construction phases during which excavation, material handling etc would need to be conducted. Impacts during operational phases are unlikely due to the use of electric train system.
All the proposed mitigation measures for controlling fugitive dust during the construction phase are summarised in the EMIS in Appendix A. These mitigation measures include the following:
·
Mitigation measures in form of regular watering
under a good site practice should be adopted. In accordance with the “Control
of Open Fugitive Dust Sources” (USEPA AP-42), watering once per hour on exposed
worksites and haul road in
· For the unloading of spoil from trucks at barging point, installation of 3-sided screen with top cover and the provision of water sprays at the discharge point would be provided for an assumed 50% dust suppression.; and
· Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting or sprayed with water to maintain the entire surface wet and then removed or backfilled or reinstated where practicable within 24 hours of the excavation or unloading
The levels of total suspended particulate (TSP) should be measured by following the standard method as set out in the High Volume Method for Total Suspended Particulates, Part 50 Chapter 1 Appendix B, Title 40 of the Code of Federal Regulations of the USEPA (the HVS method) or by direct reading methods which are capable of producing comparable results as that by the high volume sampling method.
Dust laden in air should be drawn through a high volume sampler (HVS) fitted with a conditioned, pre-weighed filter paper, at a controlled rate. After sampling for 24-hours, the filter paper with the retained dust particles should be collected and returned to the laboratory for drying in a desiccator followed by weighing. The 24-hour average TSP levels should be calculated from the ratio of the mass of particulates retained on the filter paper to the total volume of air sampled.
All relevant data
including temperature, pressure, weather conditions, elapsed-time meter reading
for the start and stop of the sampler, identification and weight of the filter
paper, and any other local atmospheric factors affecting or affected by site
conditions, etc., shall be recorded down in detail. A sample data sheet is shown in Appendix C.
High volume samplers (HVSs) complying with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:
a) 0.6 - 1.7 m3 per minute adjustable flow range;
b) equipped with a timing / control device with +/- 5 minutes accuracy for 24 hours operation;
c) installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
d) capable of providing a minimum exposed area of 406 cm2;
e) flow control accuracy: +/- 2.5% deviation over 24-hour sampling period;
f) equipped with a shelter to protect the filter and sampler;
g) incorporated with an electronic mass flow rate controller or other equivalent devices;
h) equipped with a flow recorder for continuous monitoring;
i) provided with a peaked roof inlet;
j) incorporated with a manometer;
k) able to hold and seal the filter paper to the sampler housing at horizontal position;
l) easily changeable filter; and
m) capable of operating continuously for a 24-hour period.
The ET is responsible for the provision, installation, operation, maintenance, dismantle of the monitoring equipment. They shall ensure that sufficient number of HVSs with an appropriate calibration kit is available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals. All the equipment, calibration kit, filter papers, etc., shall be clearly labelled.
Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter in every six months. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The concern parties such as IEC shall properly document the calibration data for future reference. All the data should be converted into standard temperature and pressure condition.
The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded in the data sheet as mentioned in Appendix C.
If the ET Leader proposes to use a direct reading dust meter to measure TSP levels, he shall submit sufficient information to the IEC to prove that the instrument is capable of achieving a comparable result as that the HVS and can be used for sampling. The instrument shall be calibrated regularly following the requirements specified by the equipment manufacturers.
Wind data monitoring equipment shall also be provided and set up for logging wind speed and wind direction near the dust monitoring locations. The equipment installation location shall be proposed by the ET and agreed with the IEC.
A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.
If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER and the measurement procedures shall be audited by the IEC. Any measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER and IEC. IEC shall regularly audit the measurement performed by the laboratory to ensure the accuracy of measurement results. The ET Leader shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), for his reference.
Filter paper of size 8" x 10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.
After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity-controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard.
All the collected samples shall be kept in a good condition for 6 months before disposal.
Figures 7.1.1 to 7.1.7 show the locations of the proposed construction dust monitoring station. The status and locations of sensitive receivers may change after issuing this manual. If such cases exist, the ET shall propose updated monitoring locations based on criteria below and seek approval from ER and agreement from the IEC and EPD.
Table 7.1 Proposed construction dust monitoring locations
ID |
ASR ID in
EIA |
Location |
DMS-1 |
TAW-6-7 |
|
DMS-2 |
DIH-22-1 |
|
DMS-3 |
DIH-9-1 |
Shek
On House[1] |
DMS-4 |
DIH-14-5 |
Block
1, |
DMS-5 |
DIH-14-4 |
Canossa Primary School (San Po Kong) |
DMS-6 |
TKW-3-2 |
Prosperity
House |
DMS-7 |
TKW-2-2 |
|
DMS-8 |
MTW-16-1 |
|
DMS-9 |
MTW-12-10-1
|
(Lucky
Building ( |
DMS-10 |
HOM-2-5 |
Chat
Ma Mansion |
DMS-11 |
HUH-1-3 |
|
DMS-12
# |
N/A |
Harbourfront
Horizon[1] |
Note:
[1] - Same monitoring location under SCL(HHS)
[2] - Dust monitoring will be carried out under SCL (MKK-HUH)
When alternative monitoring locations are proposed, the proposed site should, as far as practicable:
a) be at the site boundary or such locations close to the major dust emission source;
b) be close to the sensitive receptors; and
c) take into account the prevailing meteorological conditions.
The ET shall agree with the ER in consultation with the IEC on the position of the HVS for the installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:
a) a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;
b) no two samplers should be placed less than 2 m apart;
c) the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
d) a minimum of 2 m of separation from walls, parapets and penthouses is required for rooftop samplers;
e) a minimum of 2 m separation from any supporting structure, measured horizontally is required;
f) no furnace or incinerator flue is nearby;
g) airflow around the sampler is unrestricted;
h) the sampler is more than 20 m from the dripline;
i) any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;
j) permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
k) a secured supply of electricity is needed to operate the samplers.
Baseline monitoring shall be carried out at all of the designated monitoring locations (see Table 7.1) for at least 14 consecutive days prior to the commissioning of major construction works to obtain 1-hour and 24-hour TSP samples. General meteorological conditions (wind speed, direction and precipitation) and notes regarding any significant adjacent dust producing sources shall also be recorded throughout the baseline monitoring period. The selected baseline monitoring stations should reflect baseline conditions at the impact stations. 1-hour TSP sampling should also be done at least 3 times per day.
During the baseline monitoring, there should not be any major construction or dust generation activities in the vicinity of the monitoring stations. Before commencing baseline monitoring, the ET shall inform the IEC of the baseline monitoring programme such that, if required, the IEC can conduct on-site audit to ensure accuracy of the baseline monitoring results.
In case the baseline monitoring cannot be carried out at the designated monitoring locations, the ET shall propose and carry out the monitoring at alternative locations that can effectively represent the baseline conditions at the impact monitoring locations. The alternative baseline monitoring locations shall be approved by the ER and agreed with the IEC.
In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to ER for approval.
If the ET considers that significant changes
in the ambient conditions have arisen, a repeat of the baseline monitoring may
be carried out to update the baseline levels and air quality criteria, after
consultation and agreement with the ER, the IEC and the EPD.
A summary of the requirements for the baseline dust monitoring is shown in Table 7.2.
Table 7.2 Summary of Baseline Dust Monitoring Programme
Monitoring Period |
Duration |
Parameter |
Frequency |
Baseline Monitoring |
14 consecutive days prior to commencement of
major construction works |
1-hour TSP |
3 times per day |
Continuous 24-hour TSP |
Daily |
The ET shall carry out impact monitoring during the entire construction period. For 24-hour TSP impact monitoring, the sampling frequency shall be at least once in every 6 days at each of the monitoring station. 1-hour TSP monitoring shall be conducted when one documented valid complaint is received. The sampling frequency of 1-hour TSP monitoring shall be at least 3 times in every 6 days when the highest dust impacts are likely to occur. Before commencing impact monitoring, the ET shall inform the IEC of the impact monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the monitoring results.
The specific time to start and stop the 24-hour TSP monitoring shall be clearly defined for each location and be strictly followed by the ET.
In case of non-compliance with the air quality criteria, more frequent monitoring, as specified in the Action Plan in the following section, shall be conducted within the specified timeframe after the result is obtained. This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified, and agreed with the ER and the IEC.
A summary of the requirements for the dust impact monitoring is shown in Table 7.3.
Table 7.3 Summary of construction dust monitoring programme
Monitoring Period |
Duration |
Parameter |
Frequency |
Impact Monitoring |
Throughout the construction period [1] |
24-hour TSP [2] |
Once per 6 days |
Note [1] 1-
hour TSP shall be conducted when one documented valid complaint is received.
[2] 24-hour TSP shall
be conducted when project-related construction activities are being undertaken
within a radius of 500m from monitoring stations.
The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP. Table 7.4 shows the air quality criteria, namely Action and Limit levels to be used.
Table 7.4 Action / Limit Levels for Air Quality
Parameters |
Action |
Limit |
24-hour TSP
Level in mg m-3 |
For baseline
level £ 200 mg m-3, Action level = (baseline level
* 1.3 + Limit level)/2; For baseline
level > 200 mg m-3 Action level = Limit level |
260mg/m3 |
1-hour TSP
Level in mg m-3 |
For baseline
level £ 384 mg m-3, Action level = (baseline level
* 1.3 + Limit level)/2; For baseline
level > 384 mg m-3, Action level = Limit level |
500mg/m3 |
Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Table 7.5 shall be carried out.
Table 7.5 Event and Action Plan for Air Quality
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
||||
1.
Exceedance for one sample |
1. Inform the
IEC, Contractor and ER; 2.
Discuss with the Contractor, IEC and ER on the
remedial measures required; 3.
Repeat measurement to confirm findings; 4.
Increase monitoring frequency |
1.
Check monitoring data submitted by the ET; 2.
Check Contractor’s working method; 3.
Review and advise the ET and ER on the
effectiveness of the proposed remedial measures. |
1.
Confirm receipt of notification of exceedance in
writing; |
1.
Identify source(s), investigate the causes of
exceedance and propose remedial measures; 2.
Implement remedial measures; 3.
Amend working methods agreed with the ER as
appropriate. |
2.
Exceedance for two or more consecutive samples |
1.
Inform the IEC, Contractor and ER; 2.
Discuss with the ER, IEC and Contractor on the
remedial measures required; 3.
Repeat measurements to confirm findings; 4.
Increase monitoring frequency to daily; 5.
If exceedance continues, arrange meeting with
the IEC, ER and Contractor; 6.
If exceedance stops, cease additional
monitoring. |
1.
Check monitoring data submitted by the ET; 2.
Check Contractor’s working method; 3.
Review and advise the ET and ER on the
effectiveness of the proposed remedial measures. |
1.
Confirm receipt of notification of exceedance in
writing; 2.
Notify the Contractor, IEC and ET; 3.
Review and agree on the remedial measures
proposed by the Contractor; 4.
Supervise Implementation of remedial measures. |
1.
Identify source and investigate the causes of
exceedance; 2.
Submit proposals for remedial measures to the ER
with a copy to ET and IEC within three working days of notification; 3.
Implement the agreed proposals; 4.
Amend proposal as appropriate. |
Limit Level |
||||
1. Exceedance
for one sample |
1.
Inform the IEC, Contractor and ER; 2.
Repeat measurement to confirm findings; 3.
Increase monitoring frequency to daily; 4.
Discuss with the ER, IEC and contractor on the
remedial measures and assess the effectiveness. |
1.
Check monitoring data submitted by the ET; 2.
Check the Contractor’s working method; 3.
Discuss with the ET, ER and Contractor on
possible remedial measures; 4.
Review and advise the ER and ET on the
effectiveness of Contractor’s remedial measures. |
1.
Confirm receipt of notification of exceedance in
writing; 2.
Notify the Contractor, IEC and ET; 3.
Review and agree on the remedial measures
proposed by the Contractor; 4.
Supervise implementation of remedial measures. |
1.
Identify source(s) and investigate the causes of
exceedance; 2.
Take immediate action to avoid further
exceedance; 3.
Submit proposals for remedial measures to ER
with a copy to ET and IEC within three working days of notification; 4.
Implement the agreed proposals; 5.
Amend proposal if appropriate. |
2. Exceedance for
two or more consecutive samples |
1.
Notify IEC, Contractor and EPD; 2.
Repeat measurement to confirm findings; 3.
Increase monitoring frequency to daily; 4.
Carry out analysis of the Contractor’s working
procedures with the ER to determine possible mitigation to be implemented; 5.
Arrange meeting with the IEC, Contractor and ER
to discuss the remedial measures to be taken; 6.
Review the effectiveness of the Contractor’s
remedial measures and keep IEC, EPD and ER informed of the results; 7.
If exceedance stops, cease additional
monitoring. |
1.
Check monitoring data submitted by the ET; 2.
Check the Contractor’s working method; 3.
Discuss with ET, ER, and Contractor on the
potential remedial measures; 4.
Review and advise the ER and ET on the effectiveness
of Contractor’s remedial measures. |
1.
Confirm receipt of notification of exceedance in
writing; 2.
Notify the Contractor, IEC and ET; 3.
In consultation with the ET and IEC, agree with
the Contractor on the remedial measures to be implemented; 4.
Supervise the implementation of remedial
measures; 5.
If exceedance continues, consider what portion
of the work is responsible and instruct the Contractor to stop that portion
of work until the exceedance is abated. |
1.
Identify source(s) and investigate the causes of
exceedance; 2.
Take immediate action to avoid further
exceedance; 3.
Submit proposals for remedial measures to the ER
with a copy to the IEC and ET within three working days of notification; 4.
Implement the agreed proposals; 5.
Revise and resubmit proposals if problem still
not under control; 6.
Stop the relevant portion of works as determined
by the ER until the exceedance is abated. |
The EIA has considered the potential airborne noise impacts during both the construction and operational phases of the Project. Construction noise from mechanical equipment would be the key impacts during the construction phases during which excavation, material handling etc would need to be conducted. Trains running on viaduct and embankment sections would also affect the neighbouring sensitive receivers.
8.2.1 Construction Phase
All the proposed mitigation measures for controlling airborne construction noise and operational noise are summarised in the EMIS in Appendix A. These mitigation measures include the following:
· Use of good site practices to limit noise emissions;
· Install temporary hoarding located on the site boundaries between noisy construction activities and NSRs;
· Install movable noise barriers, acoustic mat or full enclosure, screen the noisy plants including air compressor, generators, saw;
· Select “Quiet plants” which comply with the BS 5228 Part 1 or TM standards;
· Sequencing operation of construction plants where practicable;
· Implement a noise monitoring under EM&A programme;
· Louvres should be orientated away from adjacent NSRs, preferably onto main roads which are less sensitive;
· Direct noise mitigation measures including silencers, acoustic louvers and acoustic enclosures should be allowed for in the design for the ventilation building, stations and stabling sidings; and
· The facade for these plant areas / ventilation shafts should have adequate sound insulation properties to minimise the noise emanating through the building fabric.
8.2.2 Operational Phase
A series of noise barriers and noise cover would need to be implemented along the tracks between HIK and Tai Wai Station in order to mitigate the train noise impacts. These mitigation measures include the following and are shown in Figures 8.1.1 – 8.1.2:
· Approx. 350m of noise barrier at a height 2m from the down track level of SCL (TAW-HUH) (P1);
· Approx. 100m of noise barrier at a height 2m from the up track level of SCL (TAW-HUH) (P2);
· Approx. 150m of noise barrier at a height 3m from the up track level of SCL (TAW-HUH) (P3);
· Approx. 300m of noise barrier at a height 7m from the tail track level T2 of TAW (P4); and
· Approx. 50m of noise barrier at a height 3m from the down track level of SCL (TAW-HUH) (P5)
·
Approx. 15m noise cover at the south-west of TAW
near
Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq 30 min shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays.
As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.
As referred to in the Technical Memorandum (TM) issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise measurement, the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level before and after the noise measurement agrees to within 1.0 dB.
Noise measurements should be made in accordance with standard acoustical principles and practices in relation to weather conditions.
The ET is responsible for the provision, installation, operation, maintenance, dismantle of the monitoring equipment. He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. All the equipment and associated instrumentation shall be clearly labelled.
8.5
Monitoring
Locations for Construction Phase
The locations of construction noise monitoring stations are summarised in Table 8.1 and shown in Figures 8.2.1 to 8.2.6.
Table 8.1 Proposed construction airborne noise monitoring locations
ID |
NSR ID in
EIA |
Location |
NMS-CA-1 |
TAW-6-7 |
|
NMS-CA-2 |
DIH-22-1 |
|
NMS-CA-3 |
DIH-9-1 |
Shek
On House [1] |
NMS-CA-4 |
DIH-14-5 |
Block
1, |
NMS-CA-5 |
DIH-14-4 |
Canossa Primary School (San Po Kong) |
NMS-CA-6 |
TKW-3-2 |
Prosperity
House |
NMS-CA-7 |
TKW-2-2 |
|
NMS-CA-8 |
MTW-16-1 |
|
NMS-CA-9 |
MTW-12-10-1
|
Lucky
Building ( |
NMS-CA-10 |
HOM-2-5 |
Chat
Ma Mansion |
NMS-CA-11 |
HUH-1-3 |
|
Note:
[1] - Same monitoring location under SCL(HHS)
When alternative monitoring locations are proposed, the monitoring locations should be chosen based on the following criteria:
· at locations close to the major site activities which are likely to have noise impacts;
· close to the most affected existing noise sensitive receivers; and
· for monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance to the occupants during monitoring.
In case the baseline monitoring cannot be carried out at the
designated monitoring locations, the ET shall propose and carry out the
monitoring at alternative locations that can effectively represent the baseline
conditions at the impact monitoring locations. The alternative baseline
monitoring locations shall be approved by the ER and agreed with the IEC and
EPD.
The monitoring station shall normally be at a point 1m from the exterior of the sensitive receiver building facade and be at a position 1.2 m above local ground. If there is problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurements shall be made. For reference, a facade correction of +3 dB(A) shall be made to the free field measurements. The ET shall agree with the IEC and EPD on the monitoring position and the corrections adopted. Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring shall be carried out at the same positions. If changes to the monitoring stations are required upon the baseline monitoring, the ET should propose alternative locations based on the above-mentioned criteria and seek approval from the ER and agreement from the IEC and EPD on the proposal.
8.6
Baseline
Monitoring for Construction Phase
The ET shall carry out baseline noise monitoring prior to the commencement of the construction works. There shall not be any construction activities in the vicinity of the stations during the baseline monitoring. Continuous baseline noise monitoring for the A-weighted levels Leq, L10 and L90 shall be carried out daily for a period of at least two weeks in a sample period of 30 minutes between 0700 and 1900 hrs and 15 minutes (as three consecutive Leq,(5 minutes) readings) for evening time (between 1900 and 2300 hours on normal weekdays), general holidays including Sundays (between 0700 and 2300 hours) and night-time (between 2300 and 0700 on all days). Before commencing baseline monitoring, the ET shall inform the IEC of the baseline monitoring programme such that, if required, the IEC can conduct on-site audit to ensure accuracy of the baseline monitoring results.
In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and EPD to agree on an appropriate set of data to be used as a baseline reference.
8.7
Impact
Monitoring for Construction Phase
During normal construction working hour (0700-1900 Monday to Saturday), monitoring of Leq, 30min noise levels (as six consecutive Leq, 5min readings) shall be carried out at the agreed monitoring locations once every week in accordance with the methodology in the TM-EIAO.
For construction monitoring stations at schools, noise monitoring shall be carried out during the school examination periods. The ET shall liaise with the school’s personnel to ascertain the exact dates and times of all examination periods during the course of the contract.
In case of non-compliance with the construction noise criteria, more frequent monitoring, as specified in the Action Plan, shall be carried out. This additional monitoring shall be continued until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.
8.8
Event
and Action Plan for Construction Phase
The Action and Limit levels for construction noise are defined in Table 8.2.
Table 8.2 Action and
Limit Levels
Time Period |
Action Level |
Limit Level |
0700 - 1900 hours on normal
weekdays |
When one
documented valid complaint is received |
75 dB(A)
* |
Note : If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to
be followed.
* Reduce to 70 dB(A) for schools and 65
dB(A) during school examination periods.
To account for cases in which ambient noise levels, as identified by baseline monitoring, approach or exceed the stipulated Limit Levels prior to the commencement of construction, a Maximum Acceptable Impact Level, which incorporates the baseline noise levels and the identified construction noise Limit Level, may be defined and agreed with the EPD. The amended level will be greater than 75 dB(A) and will represent the maximum acceptable noise level at a specific monitoring station. Correction factors for the effects of acoustic screening and/or architectural features of NSRs may also be applied as specified in the Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM).
Should non-compliance of the criteria occur, action in accordance with the Action Plan in Table 8.3 shall be carried out.
Table 8.3 Event and
Action Plan
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1.
Notify the IEC, Contractor and ER 2.
Discuss with the ER, IEC and Contractor on the
remedial measures required 3.
Increase monitoring frequency to check
mitigation effectiveness |
1.
Review the investigation results submitted by
the contractor; 2.
Review and advise the ET and ER on the
effectiveness of the remedial measures proposed by the Contractor. |
1.
Confirm receipt of notification of complaint in
writing 2.
Notify the Contractor, IEC and ET 3.
Review and agree on the remedial measures
proposed by the Contractor; 4.
Supervise implementation of remedial measures |
1.
Investigate the complaint and propose remedial
measures 2.
Report the results of investigation to the IEC,
ET and ER 3.
Submit noise mitigation proposals to the ER with
copy to the IEC and ET within 3 working days of notification. 4.
Implement noise mitigation proposals |
Limit
Level |
1.
Notify the IEC, Contractor and EPD 2.
Repeat measurement to confirm findings 3.
Increase monitoring frequency 4.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented 5.
Arrange meeting with the IEC, Contractor and ER
to discuss the remedial measures to be taken; 6.
Inform IEC, ER and EPD the causes and actions taken for the exceedances 7.
Assess effectiveness of the Contractor’s
remedial measures and keep IEC, ER and EPD informed of the results |
1.
Check monitoring data submitted by the ET; 2.
Check the Contractor’s working method; 3.
Discuss with the ER, ET and Contractor on the
potential remedial measures 4.
Review and advise the ET and ER on the
effectiveness of the remedial measures proposed by the Contractor. |
1.
Confirm receipt of notification of exceedance in
writing 2.
Notify the Contractor, IEC and ET 3.
In consultation with the ET and IEC, agree with
the Contractor on the remedial measures to be implemented 4.
Supervise the implementation of remedial
measures 5.
If exceedance continues, consider what portion
of the work is responsible and instruct the Contractor to stop that portion of
work until the exceedance is abated |
1.
Identify source and investigate the causes of
exceedance 2.
Take immediate action to avoid further
exceedance 3.
Submit proposals for remedial measures to the ER
with copy to the IEC and ET within 3 working days of notification. 4.
Implement the agreed proposals 5.
Revise and resubmit proposals if problem still
not under control 6.
Stop the relevant portion of works as determined
by the ER until the exceedance is abated |
Prior to the operation phase of the Project, a commissioning test will be conducted for verification of EIA predictions against the assessment goals and checking the compliance of the airborne noise levels with the NCO noise criteria.
Monitoring of Leq,30min train noise levels will be carried out at the proposed monitoring locations during night-time period, i.e.2300-0700 on a monthly basis after SCL (TAW-HUH) is in operation. Background noise levels shall also be measured. It is recommended to conduct the monitoring for the initial start-up of up to 6 months. With full compliance of the noise limit and agreement from IEC, monitoring can be terminated before the end of this 6-month period.
The monitoring equipments and methodology for operation rail noise monitoring should be same as those recommended for construction noise monitoring.
Based on the EIA study, the potentially worst affected
locations were designated for operational airborne noise monitoring as listed
in Table 8.4 and
illustrated in Figures
8.3.1-8.3.2.
Table 8.4 Monitoring Stations during Operation Phase
ID |
NSR ID in EIA |
Location |
NMS-OA-1 |
TAW-P1-2 |
|
NMS-OA-2 |
HUH-1-3 |
|
Note:
[1] - Same monitoring location under SCL(HHS)
The status and location of noise monitoring stations may
change after approval of this Manual. In such cases, and if changes to the
monitoring locations are considered necessary, the ET Leader should propose
updated monitoring stations and seek agreement from the IEC and EPD on the
proposal. If alternative monitoring
locations are proposed, the monitoring locations should be chosen based on the
following criteria:
· Monitoring at NSRs close to the major operation activities which are likely to cause train induced noise impacts;
· Monitoring as close as practicable to the NSRs as defined in the EIAO-TM and IND-TM; and
· Assurance of minimal disturbance to the occupants and working under a safe condition during monitoring.
The monitoring stations should
normally be at a point
Prediction of construction groundborne noise indicates the criteria will be achieved and mitigation measures are not required. In order to ensure proper control of groundborne noise, a noise commissioning test should be conducted by the ET at the proposed groundborne noise monitoring stations (see Table 9.2 below) prior to the operation of the Project to confirm the compliance of the operational groundborne noise levels with the NCO noise criteria.
Since all the predicted groundborne noise impacts comply with the legislative requirements, no mitigation measures are required for construction and operational phases ground-borne noise. Prior to the operation phase of the Project, commissioning test will be conducted to ensure compliance of operation groundborne noise levels with the TM-EIAO relevant noise criteria.
The operational groundborne noise
criteria for the representative NSRs along SCL (TAW–HUH) alignment are tabulated
in Table
9.1
below.
Table 9.1: Operational
groundborne noise criteria
NSR Description |
ASR Rating |
Groundborne
Noise Criteria, LAeq 30mins |
||
Day & Evening |
Night
|
Criteria
Employed |
||
Performing Arts Centre (Ko Shan Theatre) |
B |
55 |
45 |
55[1] |
Educational Institutes, religion premises |
B |
55 |
45 |
55[1] |
C |
60 |
50 |
60[1] |
|
Hotel guestrooms near Hung Hom |
B |
55 |
45 |
45 |
C |
60 |
50 |
50 |
|
Domestic premises along
alignment |
B |
55 |
45 |
45 |
C |
60 |
50 |
50 |
Notes: [1] These NSRs are considered to be
noise sensitive during daytime and evening time only.
As referred to in the Technical Memorandum (TM) issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the groundborne noise monitoring. Immediately prior to and following each noise measurement, the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration level before and after the noise measurement agrees to within 1.0 dB.
The ET is responsible for the provision, installation, operation, maintenance, dismantle of the monitoring equipment. He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. All the equipment and associated instrumentation shall be clearly labelled.
The proposed groundborne noise monitoring stations for commissioning test are summarised in Table 9.2 and shown in Figures 9.1.1 to 9.1.3.
Table
9.2 Proposed groundborne noise monitoring stations for commissioning
test
ID |
NSR ID in EIA |
Description |
NMS-OG-1 |
DIH-1-1 |
|
NMS-OG-2 |
MTW-6-2 |
|
NMS-OG-3 |
HOM-1-1 |
Ko Shan Theatre |
NMS-OG-4 |
HUH-1-3 |
Wing Fung Building[1] |
Note:
[1] - Same monitoring location under SCL(HHS)
The monitoring station shall normally be at the lowest sensitive floor of each designated monitoring location and normally be at a position 1.2 m above ground inside the building structures. The monitoring locations shall also not be significantly affected by background noise level. The exact locations for the monitoring shall be proposed by the ET and agreed with IEC and EPD.
If there is problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurements shall be made. The ET shall agree with the IEC on the monitoring position and the corrections adopted. Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring shall be carried out at the same positions. If changes to the monitoring stations are required upon the baseline monitoring or thereafter, the ET should proposed alternative locations based on the above-mentioned criteria and seek approval from the ER and agreement from the IEC and EPD on the proposal.
Existing Leq(30min) levels should be monitored at the monitoring locations without trains running to obtain the ambient noise levels. After the train noise levels are measured (if measured directly), these ambient levels should be deducted from the measured Leq(30min) levels to obtain the operational noise levels in the absence of ambient noise.
A noise commissioning
test should be conducted by the ET prior to the operation of the Project to
confirm the compliance of the operational ground-borne noise levels with the
NCO noise criteria. The noise commissioning test should be performed at
proposed groundborne noise monitoring locations listed in Table 9.2.
The EIA Report has assessed the water quality impacts
associated with the Project.. According to the EIA Report, the water quality
impact could be minimized with the implementation of mitigation measures. The
water quality monitoring programme as discussed below could ensure the
implementation of the recommended mitigation measures and provide continue
improvements to the environmental conditions.
The EIA Report has recommended construction phase mitigation measures. All the prepared mitigation measures are summarised in the EMIS in Appendix A. The key mitigation measures include the following.
Construction Site Runoff / Site Drainage:
· Construction site runoff and site drainage should be mitigated in accordance with the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94).
Tunneling Works:
· Cut-&-cover/ open cut tunnelling work should be conducted sequentially to limit the amount of construction runoff generated from exposed areas during the wet season (April to September) as far as practicable.
· Uncontaminated discharge should pass through sedimentation tanks prior to off-site discharge
· The wastewater with a high concentration of SS should be treated (e.g. by sedimentation tanks with sufficient retention time) before discharge. Oil interceptors would also be required to remove the oil, lubricants and grease from the wastewater.
· Direct discharge of the bentonite slurry (as a result of D-wall and bored tunnelling construction) is not allowed. It should be reconditioned and reused wherever practicable. Temporary storage locations (typically a properly closed warehouse) should be provided on site for any unused bentonite that needs to be transported away after all the related construction activities are completed. The requirements in ProPECC PN 1/94 should be adhered to in the handling and disposal of bentonite slurries.
Construction Sewage Effluent:
· Adequate numbers of portable toilets should be provided for handling the construction sewage generated by the workforce. The portable toilets should be maintained in a reasonable state, which will not deter the workers from utilizing these portable toilets. Overnight sewerage should be collected by licensed collectors regularly.
Groundwater from Contaminated Area:
·
No direct discharge of groundwater from
contaminated areas should be adopted. Prior to the excavation works within
these potentially contaminated areas, the groundwater quality should be
reviewed with reference to the site investigation data in the EIA report for
compliance to the Technical Memorandum on Standards for Effluents Discharged
into Drainage on Sewerage Systems, Inland and Coastal Waters (TM-Water) and the
existence of prohibited substance should be confirmed. The review results
should be submitted to EPD for examination If the review results indicated that
the groundwater to be generated from the excavation works would be
contaminated, the contaminated groundwater should be either properly treated in
compliance with the requirements of
the TM-Water or properly recharged into the ground.
·
If wastewater treatment is deployed, the wastewater
treatment unit shall deploy suitable treatment process (e.g. oil interceptor /
activated carbon) to reduce the pollution level to an acceptable standard and
remove any prohibited substances (e.g. TPH) to undetectable range. All treated
effluent from wastewater treatment plant shall meet the requirements as stated
in TM-Water and should be discharged into the foul sewers.
· If groundwater recharging wells are deployed, recharging wells should be installed as appropriate for recharging the contaminated groundwater back into the ground. The recharging wells should be selected at places where the groundwater quality will not be affected by the recharge operation as indicated in the Section 2.3 of TM-Water. The baseline groundwater quality shall be determined prior to the selection of the recharge wells, and submit a working plan (including the laboratory analytical results showing the quality of groundwater at the proposed recharge location(s) as well as the pollutant levels of groundwater to be recharged) to EPD for agreement. Pollution levels of groundwater to be recharged shall not be higher than pollutant levels of ambient groundwater at the recharge well. Prior to recharge, any prohibited substances such as TPH products should be removed as necessary by installing the petrol interceptor. The Contractor should apply for a discharge licence under the WPCO through the Regional Office of EPD for groundwater recharge operation or discharge of treated groundwater.
Dredging Works:
·
Install efficient silt curtains at the point of
seawall dredging to control the dispersion of SS;
·
Water quality monitoring should be implemented to
ensure effective control of water pollution and recommend additional mitigation
measures required;
·
The decent speed of grabs should be controlled to
minimize the seabed impact and to reduce the volume of over-dredging; and
·
All vessels should be sized so that adequate
clearance is maintained between vessels and the seabed in all tide conditions,
to ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash.
Barging Point:
·
All barges should be fitted with tight bottom seals
to prevent leakage of materials during transport;
·
Barges or hoppers should not be filled to a level
that will cause overflow of materials or polluted water during loading or
transportation;
·
All vessels should be sized so that adequate
clearance is maintained between vessels and the seabed in all tide conditions,
to ensure that undue turbidity is not generated by turbulence from vessel
movement or propeller wash; and
·
Loading of barges and hoppers should be controlled
to prevent splashing of material into the surrounding water.
To check that the recommend mitigation measures are
properly implemented, weekly site audits should be conducted by the ET during
construction phase of the Project.
Water quality monitoring at inshore waters during SCL (TAW–HUH) construction is not required, marine water quality monitoring, however, shall be carried out while dredging activities are conducting.
The water quality
monitoring stations and control stations of SCL (TAW–HUH) are shown in Figure
10.1. The co-ordinates of the proposed
monitoring stations (construction phase – dredging activities) are listed in Table 10.1. As shown in Figure
10.1, the proposed locations are classified as
Impact Station and Control Station according to their functions. The ET shall seek approval from IEC and EPD for any
alternative monitoring locations.
Table
10.1 Water
quality monitoring stations (construction phase – dredging activities)
Station |
Description |
Easting |
Northing |
IS-1 |
Impact Station for Dredging
Activities |
838450 |
819399 |
CS-1 |
Control Station for IS-1 |
838170 |
818903 |
CS-2 |
Control Station for IS-1 |
838912 |
818997 |
The monitoring shall normally be established by measuring the Dissolved Oxygen (DO), temperature, turbidity, pH, salinity and Suspended Solids (SS) at all designated locations as specified in Section 10.3 above.
The measurements shall be taken at all designated monitoring stations including control stations, 3 days per week, at mid-flood and mid-ebb tides. Tidal range of individual flood and ebb tides should be not less than 0.5m.
All the monitoring shall be taken at 3 water depths, namely 1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth station may be omitted. Should the water depth be less than 3m, only the mid-depth station will be monitored.
Replicate in-situ measurements and samples collected from each independent sampling event shall be collected to ensure a robust statistically interpretable database. DO, pH value, salinity, temperature and turbidity should be measured in-situ whereas SS should be determined by an accredited laboratory.
Other relevant data shall also be recorded, including monitoring location/ position, time, water depth, tidal stages, weather conditions and any special phenomena or work underway at the construction site.
Baseline conditions for marine water quality shall be established and agreed with EPD prior to the commencement of dredging works. The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the dredging works and to demonstrate the suitability of the proposed impact and control monitoring stations.
The baseline monitoring shall be conducted for at least 4 weeks prior to the commencement of dredging works. The proposed water quality monitoring schedule shall be submitted to EPD by the ET at least 2 weeks before the first day of the monitoring month. The interval between two sets of monitoring shall not be less than 36 hours. EPD shall also be notified immediately for any changes in schedule.
There should be no marine work in the vicinity of the stations during the baseline monitoring. The monitoring programme may overlap with other non-project marine activities. The monitoring exercise should be scheduled as far as possible to avoid concurrent dredging / backfilling activities around the monitoring stations such that representative ambient data could be sampled.
As it is likely to have concurrent activities such as dredging works of Proposed Cruise Terminal at Kai Tak, the ET shall seek approval from the IEC and EPD on an appropriate set of data, such as EPD’s routine monitoring data, baseline monitoring data for cruise terminal, etc, to be used with the baseline data collected by this study to establish the Action/ Limit Levels. The determination of Action/Limit Levels will be discussed in Section 10.9.
Table
10.2 summarises
the proposed monitoring frequency and water quality parameters for baseline
monitoring.
Table 10.2 Proposed water quality monitoring programme
|
Baseline
Monitoring |
Monitoring
Period |
At least 4 weeks prior to the commencement of
dredging work |
Monitoring Frequency |
3 Days in a
Week, at mid-flood and mid-ebb tides |
Monitoring Locations |
IS-1, CS-1,
CS-2 |
Monitoring Parameters |
DO,
temperature, turbidity, pH, salinity and SS |
Intervals between 2 Sets of
Monitoring |
Not less
than 36 hours |
|
Individual
flood and ebb tides not less than 0.5m |
The impact monitoring shall be conducted during dredging period. The purpose of impact monitoring is to ensure the implementation of the recommended mitigation measures, provide effective control of any malpractices, and provide continuous improvements to the environmental conditions. The proposed water quality monitoring schedule shall be submitted to EPD by the ET at least 2 weeks before the first day of the monitoring month. The interval between two sets of monitoring shall not be less than 36 hours. EPD shall also be notified immediately for any changes in schedule.
In case of project-related exceedances of Action
and/or Limit Levels, the impact moniotring frequency shall be increased
according to the requirement of Event and Action Plan. The details of Event
Action Plan will be discussed in Section
10.10.
Table
10.3 summarises
the proposed monitoring frequency and water quality parameters for and impact
monitoring.
Table 10.3 Proposed water quality monitoring programme
|
Impact
Monitoring |
Monitoring
Period |
During dredging period |
Monitoring Frequency |
3 Days in a
Week, at mid-flood and mid-ebb
tides |
Monitoring Locations |
IS-1, CS-1,
CS-2 |
Monitoring Parameters |
DO,
temperature, turbidity, pH, salinity and SS |
Intervals between 2 Sets of
Monitoring |
Not less
than 36 hours |
|
Individual
flood and ebb tides not less than 0.5m |
Dissolved
Oxygen and Temperature Measuring Equipment
The dissolved oxygen (DO) measuring instruments should be portable and weatherproof. The equipment should also complete with cable and sensor, and DC power source. It should be capable of measuring:
· a DO level in the range of 0 - 20 mg/L and 0 - 200% saturation; and
· a temperature of 0 - 45 degree Celsius.
The equipment should have a membrane electrode with automatic temperature compensation complete with a cable.
Should salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO measuring instruments prior to each measurement.
Turbidity
Measuring Equipments
The turbidity measuring instruments should be a portable and weatherproof with DC power source. It should have a photoelectric sensor capable of measuring turbidity level between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument).
Salinity
Measuring Equipments
A portable salinometer capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) should be provided for measuring salinity of the water at each monitoring location.
pH
Measuring Equipments
A portable pH meter capable of measuring a
pH range between 0.0 and 14.0 shall be provided under the specified conditions
(e.g., Orion Model 250A or an approved similar instrument).
Positioning
Equipments
A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message ‘screen pop-up’ facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office), or other equipment instrument of similar accuracy, should be provided and used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.
Water
Depth Detector
A portable, battery-operated echo sounder should be used for water depths determination at each designated monitoring station. The detector can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
Water
Sampler
A water sampler is required for SS monitoring. It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).
Sample
Containers and Storage
Water samples for SS determinations should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and shipment to the testing laboratory. The samples shall be delivered to the laboratory within 24 hours of collection and be analysed as soon as possible after collection.
Calibration
of In-Situ Instruments
The pH meter, DO meter and turbidimeter shall be checked and calibrated before use. DO meter and turbidimeter shall be certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at quarterly basis throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring station.
Back-up
Equipment and Vessels
Sufficient stocks of spare parts shall be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, malfunction, etc.
The water quality monitoring will involve
three monitoring stations and measurements should be conducted within the
prescribed tidal conditions in order to ensure the measurement/samples are
representative. A multi-probe monitoring equipment set integrated with water
sampler(s) is highly recommended to improve the monitoring efficiency. Depending on the actually operation,
more than one field survey vessels might be required simultaneously to ensure
the monitoring are conducted within the acceptable monitoring period. The ET
shall also consider the use of unattended automatic sampling/monitoring devices
at fixed stations where monitoring are required throughout the construction
period. The use of such unattended automatic devices, however, shall be subject
to the approval of the ER, IEC and
At least 3 replicate samples from each independent sampling event are required for the suspended solids measurement which shall be carried in a HOKLAS or international accredited laboratory. Sufficient water samples shall be collected at the monitoring stations for carrying out the laboratory measurement and analysis. The laboratory determination work shall start within 24 hours after collection of the water samples. The analysis for SS is presented in Table 10.4.
Table 10.4 Laboratory analysis
for SS
Parameters |
Analytical Method |
Reporting Limit |
Suspended
Solid (SS) |
APHA 2540-D |
0.1
mg/L |
The Action and Limit levels for water quality are defined in Table 10.5.
Table 10.5 Action and Limit
Levels for Water Quality
Parameters |
Action
Level |
Limit Level |
DO in mg/L (Surface,
Middle & Bottom) |
Surface and Middle 5 percentile of baseline data for
surface and middle layer Bottom 5 percentile of baseline data for
bottom layer |
Surface and Middle 4 mg/L except 5 mg/l for FCZ or 1%-ile of baseline data for surface
and middle layer Bottom 2 mg/L or 1%-ile of baseline data for bottom
layer |
SS in mg/L
(depth-averaged) |
95 percentile of baseline data or
120% of upstream control station's SS at the same tide of the same day |
99 percentile of baseline data or
130% of upstream control station's SS at the same tide of the same day |
Turbidity in NTU (depth-averaged) |
95
percentile of baseline data or 120% of upstream control station's Turbidity
at the same tide of the same day |
99 percentile
of baseline or 130% of upstream control station's Turbidity at the same tide
of the same day |
Notes: 1. "depth-averaged" is
calculated by taking the arithmetic means of reading of all three depths.
2. For DO, non-compliance of the water
quality limits occurs when monitoring result is lower than the limits.
3. For turbidity, SS, non-compliance
of the water quality limits occurs when monitoring result is higher than the
limits.
4. All the figures given in the table
are used for reference only and the EPD may amend the figures whenever it is
considered as necessary.
Should non-compliance of the criteria occur, action in accordance with the Action Plan in Table 10.6 shall be carried out.
Table
10.6 Event and
Action Plan for Water Quality
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action level being exceeded
by one sampling day |
1.
Inform IEC, contractor and ER; 2.
Check monitoring data, all plant, equipment and
Contractor's working methods; and 3.
Discuss remedial measures with IEC and
Contractor and ER |
1.
Discuss with ET, ER and Contractor on the
implemented mitigation measures; 2.
Review proposals on remedial measures submitted
by Contractor and advise the ER accordingly; and 3.
Review and advise the ET and ER on the
effectiveness of he implemented mitigation measures. |
1.
Discuss with IEC, ET and Contractor on the
implemented mitigation measures; and 2.
Make agreement on the remedial measures to be
implemented. 3.
Supervise the implementation of agreed remedial
measures |
1.
Identify
source(s) of impact; 2.
Inform the ER and confirm notification of the
non-compliance in writing; 3.
Rectify unacceptable practice; 4.
Check all plant and equipment; 5.
Consider changes of working methods; 6.
Discuss with ER, ET and IEC and propose remedial
measures to IEC and ER; and 7.
Implement the agreed mitigation measures. |
Action level
being exceeded by more than one consecutive sampling days |
1.
Repeat in-situ measurement on next day of
exceedance to confirm findings; 2.
Inform IEC, contractor and ER; 3.
Check monitoring data, all plant, equipment and
Contractor's working methods; 4.
Discuss remedial measures with IEC, contractor
and ER 5.
Ensure remedial measures are implemented |
1.
Discuss with ET Contractor and ER on the implemented mitigation
measures; 2.
Review the proposed remedial measures submitted
by Contractor and advise the ER accordingly; and 3.
Review and advise the ET and ER on the
effectiveness of the implemented mitigation measures. |
1.
Discuss with ET, IEC and Cotnractor on the
proposed mitigation measures; 2.
Make agreement on the remedial measures to be
implemented; and 3.
Discuss with ET IEC and Contractor on the
effectiveness of the implemented remedial measures. |
1.
Identify source(s) of impact; 2.
Inform the ER and confirm notification of the
non-compliance in writing; 3.
Rectify unacceptable practice; 4.
Check all plant and equipment and consider
changes of working methods; 5.
Discuss with ET, IEC and ER and submit proposal
of remedial measures to ER and IEC within 3 working days of notification; an 6.
Implement the agreed mitigation measures. |
Limit level being exceeded by
one sampling day |
1.
Repeat measurement on next day of exceedance to
confirm findings; 2.
Inform IEC, contractor and ER; 3.
Rectify unacceptable practice; 4.
Check monitoring data, all plant, equipment and
Contractor's working methods; 5.
Consider changes of working methods 6.
Discuss mitigation measures with IEC, ER and
Contractor; and 7.
Ensure the agreed remedial measures are
implemented; |
1.
Discuss with ET , Contractor and ER on possible
remedial actions; 2.
Review the proposed remedial measures submitted
by Contractor and advise the ER accordingly; and 3.
Review and advise the ET and ER on the
effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC, ET and Contractor on the
implemented remedial measures; 2.
Request Contractor to critically review the
working methods; 3.
Make agreement on the remedial measures to be
implemented; and 4.
Discuss with ET, IEC and Contractor on the
effectiveness of the implemented remedial measures. |
1.
Identify source(s) of impact; 2.
Inform the ER and confirm notification of the
non-compliance in writing; 3.
Rectify unacceptable practice; 4.
Check all plant and equipment and consider
changes of working methods; 5.
Discuss with ET, IEC and ER and submit proposal
of additional mitigation measures to ER within 3 working days of
notification; and 6.
Implement the agreed remedial measures. |
Limit level being exceeded by more than one
consecutive sampling days |
1.
Inform IEC, contractor, ER and EPD 2.
Check monitoring data, all plant, equipment and
Contractor's working methods; 3.
Discuss mitigation measures with IEC, ER and
Contractor; and 4.
Ensure mitigation measures are implemented; and 5.
Increase the monitoring frequency to daily until
no exceedance of Limit Level for two consecutive days. |
1.
Discuss with ET, ER and Contractor on possible
remedial actions; 2.
Review the proposed mitigation measures
submitted by Contractor and advise the ER accordingly; and 3.
Review and advise the ET and ER on the
effectiveness of the implemented mitigation measures. |
1.
Discuss with IEC, ET and Contractor on the
implemented mitigation measures; 2.
Request Contractor to critically review the
working methods; 3.
Make agreement on the remedial measures to be
implemented 4.
Discuss with ET and IEC on the effectiveness of
the implemented mitigation measures; and 5.
Consider and instruct, if necessary, the
Contractor to slow down or to stop all or part of the dredging activities
until no exceedance of Limit level. |
1.
Identify source(s) of impact; 2.
Inform the ER and confirm notification of the
non-compliance in writing; 3.
Rectify unacceptable practice; 4.
Check all plant and equipment and consider
changes of working methods; 5.
Discuss with ET, IEC and ER and submit proposal of additional
mitigation measures to ER and IEC
within 3 working days of notification; 6.
Implement the agreed mitigation measures. 7.
As directed by the ER, to slow down or to stop
all or part of the dredging activities until no exceedance of Limit level. |
The quantity and timing for the generation of waste during the construction phase have been estimated. Measures including the opportunity for on-site sorting, reusing excavated materials etc, are devised in the construction methodology to minimise the surplus materials to be disposed off-site. Proper disposal of chemical waste should be via a licensed waste collector. All the proposed mitigation measures are stipulated in the EIA Report and summarised in the EMIS in Appendix A.
The types and quantities of waste that would be generated during the operational phase have been assessed. It is anticipated there would not be any insurmountable impacts during the operational phase. A trip-ticket system should be operated to monitor all movements of chemical wastes which will be collected by a licensed collector to a licensed facility for final treatment and disposal. Recommendations have been made to ensure proper treatment and proper disposal of these wastes in the EIA Report and summarised in the EMIS in Appendix A. The mitigation measures should form the basis of the Environmental Management Plan (EMP).
EM&A requirements are required for waste management during the construction phase only and the effective management of waste arising during the construction phase will be monitored through the site audit programme. The aims of the waste audit are:
· to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and
· to encourage the reuse and recycling of material.
The Contractor shall be required to pay attention to the environmental standard and guidelines and carry out appropriate waste management and obtain the relevant licence/permits for waste disposal. The ET shall ensure that the Contractor has obtained from the appropriate authorities the necessary waste disposal permits or licences including:
· Chemical Waste Permits/licenses under the Waste Disposal Ordinance (Cap 354);
· Public Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap 28);
· Marine Dumping Permit under the Dumping at Sea Ordinance (Cap 466); and
· Effluent Discharge Licence under the Water Pollution Control Ordinance.
The Contractor shall refer to the relevant booklets issued by the DEP when applying for the licence/permit and the ET shall refer to these booklets for auditing purposes.
Regular audits and site inspections should be carried out during construction phase by the ET to ensure that the recommended good site practices and other recommended mitigation measures are properly implemented by the Contractor. The audits should concern all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal. Apart from site inspection, documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation and contract requirements.
The requirements of the environmental audit programme are set out in Section 14 of this Manual. The audit programme will verify the implementation status and evaluate the effectiveness of the mitigation measures.
A land contamination
assessment has been conducted and historical information such as site
geological information, ground condition, aerial photos have been collated.
After consideration of other remediation options, it has been estimated that
approximately 39 m3 of soil near the former
Prior to commencement of soil remedial works, the area requiring remediation should be clearly marked out on site and the surface levels recorded. Excavation of contaminated material should be undertaken using dedicated earth-moving plant that should be thoroughly cleaned (e.g. jet-washed) following completion of excavation works.
An area extending to 3.5m radius from the sample location should be excavated to the depth given in Figure 12.1 (i.e. a circular area of 7m diameter centred on the drillhole location).
Excavated contaminated soils should not be stockpiled on site, but should immediately be loaded onto trucks and taken to the landfill site. All trucks carrying contaminated material should be adequately covered by sheet to prevent dispersion of contamination during transportation.
Although the contaminated soils is situated above the groundwater table, due to the fluctuation of the groundwater table, the remediation contractor should pay attention to the selection of suitable groundwater lowering schemes and discharge points if the groundwater table is higher than the contaminated soils during excavation. The remediation contractor should also obtain a valid Water Pollution Control Ordinance (WPCO) discharge licence from EPD where applicable.
Given the EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites of: Petrol Filling Stations, Boatyards and Car Repair/Dismantling Workshops has been superseded by the new Practice Guide (PG) for Investigation and Remediation of Contaminated Land in August 2011, the remediation contractor should carry out the remediation works in accordance with the procedure set out in the new PG and other Ordinance relevant to the works.
The entire remediation programme should be supervised by an on-site Decontamination Specialist (to be appointed by the Contractor), who should have at least 7 years experience in contamination assessment or decontamination. All relevant method statements prepared by the remediation contractor should be reviewed and approved by the Decontamination Specialist before proceeding with the works.
Following completion of excavation to the specified depth, at least one sample from the base of the excavation and three samples evenly distributed along the boundary of the excavation shall be taken for carrying out the compliance testing. The compliance testing requirements are shown in Table 12.1.
Table 12.1 Requirements
for compliance testing
Locations |
Testing Requirement |
Acceptance Criteria |
2209/SCL/EDH127 |
PCBs |
RBRGs (Industrial category) |
If the analysis indicates continued presence of contamination, the excavation shall be extended a further 0.5m depth or 1m wide with material disposed of as described above, and a further sample taken for compliance testing. The process of excavation, sampling and compliance testing should continue until all contaminated materials are removed. The excavated areas should then be backfilled using suitable clean fill material.
The contaminants present on the site are at relatively low levels, and are not expected to pose serious acute health risk to the site workforce. However, it is good practice to ensure that remediation workers are adequately protected to ensure that there are no significant residual risks. The following health and safety precautions are therefore recommended:
· Personal Protective Equipment (PPE) such as safety hat, chemical protective gloves, masks, eye goggles, protective clothing (upgraded if contact with contaminated material cannot be avoided) and protective footwear etc. must be provided to staff, which would be involved in the remediation work. No works should be allowed without the suitable PPE.
· Workers should inspect and check their PPE before, during and after use. In cases where any of the PPE is broken, the worker shall stop work immediately and inform the on-site registered safety officer. The worker is not allowed to re-start his work until the broken PPE is replaced.
· Hand washing basins or other washing facilities shall be provided in areas easily accessible to all workers.
· Workers should always maintain basic hygiene standard (e.g. hand wash before leaving the contaminated work zone). Workers shall also be responsible for cleaning and storing their own PPE in a secure place before leaving the site.
· Eating, drinking and smoking must be strictly prohibited within the site areas.
It should be noted that these precautions are additional to any other health and safety requirements that will apply on the site such as those requiring protective footwear and headgear.
12.5 Remediation Reports
A Remediation Report (RR) to demonstrate adequate clean-up shall be prepared by the Contractor and submitted to EPD after review/ verification by ER, ET and IEC necessary for endorsement prior to the commencement of any construction/ development works within the sites. No construction/ development works shall be carried out prior to the endorsement of the RR.
13.1 Introduction
Blasting activities regarding the storage, transport and use of explosives should be supervised and audited by the competent site staff to ensure strict compliance with the blasting permit conditions.
The recommended mitigation measures as outlined in
the EMIS included in Appendix A of this EM&A
Manual should be implemented to meet the EIAO-TM requirements.
Site inspection provides a direct means to initiate and enforce specified environmental protection and pollution control measures. These shall be undertaken routinely to inspect construction activities in order to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented. Site inspection is one of the most effective tools to enforce the environmental protection requirements at the works area.
The ET shall be responsible for formulating the environmental site inspection programme as well as the deficiency and action reporting system, and for carrying out the site inspections. The proposal for rectification, if any, should be prepared and submitted to the ET Leader and IEC by the Contractor.
Regular site inspections shall be carried out and led by the ER and attended by the Contractor and ET at least once per week during the construction phase. The areas of inspection shall not be limited to the environmental situation, pollution control and mitigation measures within the site. It should also review the environmental situations outside the works area which is likely to be affected, directly or indirectly, by the construction site activities of the Project. The ET shall make reference to the following information in conducting the inspection. During the inspection, the following information should be referred to:
(i) EIA Report recommendations on environmental protection and pollution control mitigation measures;
(ii) works progress and programme;
(iii) individual works methodology proposals (which shall include the proposal on associated pollution control measures);
(iv) contract specifications on environmental protection;
(v) relevant environmental protection and pollution control legislations; and
(vi) previous site inspection results.
The Contractor shall keep the ER and ET Leader updated with all relevant environmental related information on the construction contract necessary for him to carry out the site inspections. Site inspection results and associated recommendations for improvements to the environmental protection and pollution control efforts should be recorded and followed up by the Contractor in an agreed time-frame. The Contractor shall follow the procedures and time-frame as stipulated in the environmental site inspection, and the deficiency and action reporting system formulated by the ET, to report on any remedial measures subsequent to the site inspections.
The ER, ET and the Contractor should also carry out ad-hoc site inspections if significant environmental problems are identified. Inspections may also be required subsequent to receipt of a valid environmental complaint, or as part of the investigation work, as specified in the Action Plan for the EM&A programme.
There are statutory requirements on environmental protection and pollution control requirements with which construction activities must comply.
In order that the works comply with all method statements of works should be submitted by the Contractor to the ER for approval and to the ET Leader to ensure sufficient environmental protection and pollution control measures have been included. The Environmental Mitigation Implementation schedule (EMIS) is summarised in Appendix A. Any proposed changes to the mitigation measures shall be certified by the ET Leader and verified by the IEC as conforming to the relevant information and recommendations contained in the EIA Report.
The ER and ET shall also review the progress and programme of the works to check that relevant environmental legislations have not been violated, and that any foreseeable potential for violating laws can be prevented.
The Contractor should provide the update of the relevant documents to the ET Leader so that checking can be carried out. The document shall at least include the updated Works Progress Reports, updated Works Programme, method statements, any application letters for different licences / permits under the environmental protection laws, and copies of all valid licences / permits. The site diary and environmental records shall also be available for inspection by the relevant parties.
After reviewing the document, the ET shall advise the IEC and Contractor of any non-compliance with legislative requirements on environmental protection and pollution control so that they can timely take follow-up actions as appropriate. If the follow-up actions may still result in potential violation of environmental protection and pollution control requirements, the ER and ET should provide further advice to the Contractor to take remedial action to resolve the problem.
Upon receipt of the advice, the Contractor shall undertake immediate actions to correct the situation. The ER and ET shall follow up to ensure that appropriate action has been taken in order to satisfy legal requirements.
At times during the construction phase the
Contractor may submit method statements for various aspects of construction.
This state of affairs would only apply to those construction methods that the
EIA has not imposed conditions while for construction methods that have been
assessed in the EIA, the Contractor is bound to follow the requirements and
recommendations in the EIA study. The Contractor’s options for alternative
construction methods may introduce adverse environmental impacts into the
Project. It is the responsibility of the Contractor and ET, in accordance with
established standards, guidelines and EIA study recommendations and
requirements, to review and determine the adequacy of the environmental
protection and pollution control measures in the Contractor’s proposal in order
to ensure no unacceptable impacts would result. To achieve this end, the ET
shall provide a copy of the Proactive Environmental Protection Proforma as
shown in Appendix
E to
the IEC for approval. The IEC should audit the review of the construction
method and endorse the proposal on the basis of no adverse environmental
impacts.
The following procedures should be undertaken upon receipt of any environmental complaint:
(i) The Contractor to log complaint and date of receipt onto the complaint database and inform the ER, ET and IEC immediately;
(ii) The Contractor to investigate, with the ER and ET, the complaint to determine its validity, and assess whether the source of the problem is due to construction works of the Project with the support of additional monitoring frequency and stations, if necessary;
(iii) The Contractor to identify remedial measures in consultation with the IEC, ET and ER if a complaint is valid and due to the construction works of the Project;
(iv) The Contractor to implement the remedial measures as required by the ER and to agree with the ET and IEC any additional monitoring frequency and stations, where necessary, for checking the effectiveness of the remedial measures;
(v) The ER, ET and IEC to review the effectiveness of the Contractor's remedial measures and the updated situation;
(vi) The ET to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur;
(vii) If the complaint is referred by the EPD, the Contractor to prepare interim report on the status of the complaint investigation and follow-up actions stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD; and
(viii) The ET to record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.
Reports can be provided in an electronic medium upon agreeing the format with the ER and EPD. This would enable a transition from a paper / historic and reactive approach to an electronic / real time proactive approach. All the monitoring data (baseline and impact) shall also be submitted on diskettes or other approved media. The formats for air quality, noise and water quality monitoring data to be submitted shall be separately agreed.
The ET is responsible for establishing and maintaining a dedicated website throughout the entire construction period for publishing all the relevant environmental monitoring data (including but not limited to the baseline and impact monitoring). The ET shall propose the format and functionality of the website for agreement with the ER and IEC prior to publishing of data. Once the monitoring data are available (e.g. noise, dust, water quality etc) and vetted by the IEC, the ET is responsible to upload the relevant data to the dedicated website.
Types of reports that the ET shall prepare and submit include baseline monitoring report, monthly EM&A report and final EM&A review report. In accordance with Annex 21 of the EIAO-TM, a copy of the monthly and final review EM&A reports shall be made available to the Director of Environmental Protection.
The ET should prepare and submit a Baseline Environmental Monitoring Report at least one month before commencement of construction of the Project. Copies of the Baseline Environmental Monitoring Report should be submitted to the IEC, ER and EPD. The ET should liaise with the relevant parties on the exact number of copies require.
The baseline monitoring report shall include at least the following:
(i) up to half a page executive summary;
(ii) brief project background information;
(iii) drawings showing locations of the baseline monitoring stations;
(iv) monitoring results (in both hard and diskette copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· parameters monitored;
· monitoring locations;
· monitoring date, time, frequency and duration; and
· quality assurance (QA) / quality control (QC) results and detection limits;
(v) details of influencing factors, including:
· major activities, if any, being carried out on the site during the period;
· weather conditions during the period; and
· other factors which might affect monitoring results;
(vi) determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data,
(vii) revisions for inclusion in the EM&A Manual; and
(viii) comments, recommendations and conclusions.
The results and findings of all EM&A work required in the Manual shall be recorded in the monthly EM&A reports prepared by the ET and endorsed by the IEC. The EM&A report shall be prepared and submitted to EPD within 10 working days of the end of each reporting month, with the first report due the month after construction commences. Copies of each monthly EM&A report shall be submitted to the following parties: the IEC, the ER and EPD. Before submission of the first EM&A report, the ET shall liaise with the parties on the required number of copies and format of the monthly reports in both hard copy and electronic medium.
The ET shall review the number and location of monitoring stations and parameters every six months, or on as needed basis, in order to cater for any changes in the surrounding environment and the nature of works in progress.
First
Monthly EM&A Report
The first monthly EM&A report shall include at least the following:
(i) Executive summary (1-2 pages):
· breaches of Action and Limit levels;
· complaint log;
· notifications of any summons and successful prosecutions;
· reporting changes; and
· future key issues.
(ii) Basic project information:
· project organisation including key personnel contact names and telephone numbers;
· programme;
· management structure, and
· works undertaken during the month.
(iii) Environmental status:
· advice on the status of statutory environmental compliance such as the status of compliance with the environmental permit (EP) conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;
· works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc); and
· drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations (with co-ordinates of the monitoring locations).
(iv) A brief summary of EM&A requirements including:
· all monitoring parameters;
· environmental quality performance limits (Action and Limit levels);
· Event-Action Plans;
· environmental mitigation measures, as recommended in the project EIA study final report; and
· environmental requirements in contract documents.
(v) Implementation status:
· advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA.
(vi) Monitoring results (in both hard and diskette copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· monitoring parameters;
· monitoring locations;
· monitoring date, time, frequency, and duration;
· weather conditions during the period;
· any other factors which might affect the monitoring results; and
· QA/QC results and detection limits.
(vii) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
· record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
· record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(viii) Others
· an account of the future key issues as reviewed from the works programme and work method statements;
· advice on the solid and liquid waste management status;
· record of any project changes from that originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc); and
· comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.
Subsequent
EM&A Reports
Subsequent monthly EM&A reports shall include the following:
(i) Executive summary (1 - 2 pages):
· breaches of Action and Limit levels;
· complaints log;
· notifications of any summons and successful prosecutions;
· reporting changes; and
· future key issues.
(ii) Basic project information:
· project organisation including key personnel contact names and telephone numbers;
· programme;
· management structure;
· work undertaken during the month; and
· any updates as needed to the scope of works and construction methodologies.
(iii) Environmental status:
· advice on the status of statutory environmental compliance, the status of compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;
· works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc.); and
· drawing showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
(iv) Implementation status:
· advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report.
(v) Monitoring results (in both hard and diskette copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment used and calibration details;
· monitoring parameters;
· monitoring locations;
· monitoring date, time, frequency, and duration;
· weather conditions during the period;
· any other factors which might affect the monitoring results; and
· QA / QC results and detection limits.
(vi) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
· record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
· record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
· record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
· review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
· description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(vii) Others
· an account of the future key issues as reviewed from the works programme and work method statements;
· advice on the solid and liquid waste management status;
· record of any project changes from that originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc); and
· comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for example, any improvement in the EM&A programme) and conclusions.
(viii) Appendices
· Action and Limit levels;
· graphical plots of trends of the monitoring parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
a) major activities being carried out on site during the period;
b) weather conditions during the period; and
c) any other factors that might affect the monitoring results.
· monitoring schedule for the present and next reporting period;
· cumulative statistics on complaints, notifications of summons and successful prosecutions; and
· outstanding issues and deficiencies.
The
EM&A programme should be terminated upon the completion of the construction
activities that have the potential to result in significant environmental
impacts.
Prior to the proposed termination, it may be advisable to consult relevant local communities. The proposed termination should only be implemented after the proposal has been endorsed by the IEC, the Engineer and the Project Proponent followed by approval from the Director of Environmental Protection.
The final EM&A report should contain at least the following information:
(i) Executive summary (1 - 2 pages);
(ii) Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
(iii) Basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of work undertaken during the course of the project or past twelve months;
(iv) A brief summary of EM&A requirements including:
· environmental mitigation measures, as recommended in the project EIA Report;
· environmental impact hypotheses tested;
· environmental quality performance limits (Action and Limit levels);
· all monitoring parameters;
· Event and Action Plans;
(v) A summary of the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report, summarised in the updated implementation schedule;
(vi) Graphical plots and the statistical analysis of the trends of monitoring parameters over the course of the project, including the post-project monitoring for all monitoring stations annotated against:
· the major activities being carried out on site during the period;
· weather conditions during the period; and
· any other factors which might affect the monitoring results;
(vii) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
(viii) A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;
(ix) A description of the actions taken in the event of non-compliance;
(x) A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up procedures taken;
(xi) A summary record of notifications of summons and successful prosecutions for breaches of the current environmental protection / pollution control legislation, locations and nature of the breaches, investigation follow-up actions taken and results;
(xii) A review of the validity of EIA predictions and identification of shortcomings in EIA recommendations;
(xiii) Comments (for examples, a review of the effectiveness and efficiency of the mitigation measures and of the performance of the environmental management system, that is, of the overall EM&A programme); and
(xiv) Recommendations and conclusions (for example, a review of success of the overall EM&A programme to cost-effectively identify deterioration and to initiate prompt effective mitigatory action when necessary).
No site-based documents (such as monitoring field records, laboratory analysis records, site inspection forms, etc.) are required to be included in the monthly EM&A reports. However, any such document shall be well kept by the ET and be ready for inspection upon request. All relevant information shall be clearly and systematically recorded in the document. Monitoring data shall also be recorded in magnetic media form, and the software copy must be available upon request. Data format shall be agreed with EPD. All documents and data shall be kept for at least one year following completion of the construction contract.
With reference to the Event and Action Plans, when the environmental quality performance limits are exceeded and if they are proven to be valid, the ET should immediately notify the IEC and EPD, as appropriate. The notification should be followed up with advice to the IEC and EPD on the results of the investigation, proposed actions and success of the actions taken, with any necessary follow-up proposals. A sample template for the interim notification is presented in Appendix D.
[1] The
ultimate suitability of using either the DHS or HHS or a combination of both
sites for train stabling would be subject to the findings of detailed
engineering and EIA studies.