10a.1.1.1 This section presents the assessment of the landscape and visual impact due to the construction and operation of the IWMF at the Tsang Tsui Ash Lagoon (TTAL) site.
10a.1.1.2 The photomontages and layouts provided in this report are based on a reference design prepared for this EIA study purpose only. The actual design of the IWMF proposal will be subject to further refinement by the DBO contractor during the design stage.
10a.2 Description of Proposed Works
10a.2.1.1 The proposed works in the TTAL site involve the construction and operation of the IWMF, which includes a thermal incineration plant, a sorting and recycling plant, and ancillary and supporting facilities.
10a.2.1.2 The key activities and issues of the proposed works related to the impact on the landscape and visual context include:-
Construction Phase
· Loss of ash lagoon area and vegetation, presence of construction machinery, site formation, and construction of facilities.
Operation Phase
· Presence of the built structures; and
· Waste transportation traffic to and from the IWMF.
10a.3 Environmental Legislation and Standards
10a.3.1.1 The following environmental legislation and standards have been considered:
· Country Parks Ordinance (Cap. 208);
· DSD Technical Circular No. 2/2004 Protection of Natural Rivers and Streams from Adverse Impacts Arising from Construction Works – provides guidelines for the planning and execution of construction works;
· DSD Practice Note No. 1/2005 “Guidelines on Environmental Consideration for River Channel Design”;
· EIAO Guidance Note No. 8/2010 – sets up guidelines for preparation of Landscape and Visual Impact Assessment under EIAO;
· Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Annexes 10 and 18 of Environmental Impact Assessment Ordinance (EIAO) Technical Memorandum;
· ETWB TCW No. 2/2004 Maintenance of Vegetation and Hard Landscape Features – sets out the government departmental responsibilities for maintenance of vegetation and hard landscape features;
· ETWB TCW No.14/2004 Maintenance of Stormwater Drainage Systems and Natural Watercourses – sets out the departmental responsibilities for the maintenance of storm water drainage systems and natural watercourses in government and private lands, as well as the main watercourses designated under the Land Drainage Ordinance;
· ETWB TCW No. 29/2004 Registration of Old and Valuable Trees and Guidelines for their Preservation – provides priority protection to the trees in the Register. Furthermore, the Government has already put in place a comprehensive range of administrative and legislative measures to preserve trees on Government land;
· ETWB TCW No. 5/2005 Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction Works – clarifies and strengthens the existing measures for protection of natural streams / rivers from Government projects and private developments;
· ETWB TCW No. 3/2006 Tree Preservation – defines and covers the reporting of unauthorized tree removal (i.e. felling or transplanting), on both private and unleased Government land;
· GEO Publication No. 1/2000 – “Technical Guidelines on Landscape Treatment and Bio-Engineering for Man-made Slope and Retaining Walls”;
·
Government General Regulation 740 – sets out
restrictions on the preservation and felling of trees in
·
· Protection of Endangered Species of Animals and Plants Ordinance (Cap 586);
· The Forests and Countryside Ordinance (Cap. 96) – prohibits felling, cutting, burning or destroying of trees and growing plants in forests and plantations on government land. Its subsidiary regulations prohibit the picking, felling or possession of listed rare and protected plant species;
· The Forestry Regulations – makes under Section 3 of the Forests and Countryside Ordinance (Cap. 96) defining the list of protected species in Hong Kong;
·
Technical Report of Landscape Value Mapping in
· Town Planning Ordinance and Town Planning (Amendment) Ordinance (Cap. 131); and
· WBTC No. 7/2002 Tree Planting in Public Works – affirms the advocated policy on tree planting which adopts a flexible and balanced approach in the planning and design of public works.
10a.4 Review of Planning and Development Control Framework
10a.4.1.1
A review of the existing and
planned development framework for the proposed works and their surroundings has
been conducted. It aims to:
· Identify issues for the neighbouring planned land uses;
· Identify the potential resources and sensitive receivers; and
· Ensure a high compatibility between the proposed works and the surroundings.
10a.4.2 Existence of Statutory Plans
10a.4.2.1 The following Outline Zoning Plans (OZP) have been reviewed: Sheung Pak Nai & Ha Pak Nai Outline Zoning Plan OZP no. S/YL-PN/9 (Approved – 17.10.2006); Ping Shan OZP no. S/YL-PS/12 (Draft – 5.11.2010); Lam Tei & Yick Yuen OZP no. S/TM-LTYY/6 (Approved – 14.3.2006) and Tuen Mun OZP no. S/TM/27 (Draft – 3.9.2010). The project site is not covered by any OZP and no land use is specified in the statutory plan as per Figure 10a.1. Therefore, there is no proposed change to the OZPs due to the development of the IWMF at the TTAL site.
10a.5 Baseline Study Methodology
10a.5.1.1
The landscape and visual
impacts are assessed separately for the construction phase and the operation
phase. The methodologies to assess landscape and visual impacts are described
below.
10a.5.2 Landscape Baseline Study Methodology
10a.5.2.1 In accordance with the EIA Study Brief, a baseline survey of the existing landscape character areas (LCAs) and landscape resources (LRs) within 500m from the propsed works is undertaken by a combination of site inspections and desktop surveys. The proposed works within and adjacent to the study area are considered.
10a.5.2.2
The baseline survey forms the
basis of the landscape context by describing broadly homogenous units of
similar character. Environmental capital approach is adopted to classify the
landscape into distinct LCAs based on distinct patterns or combinations of
landscape resources / elements that occur consistently in a particular landscape.
“Study of Landscape Value Mapping of Hong Kong” and “Map of Land Utilization in
· Local topography;
·
· Built form, land use and patterns of settlement;
· Scenic spots;
· Details of local materials;
· Natural and artificial coastlines;
· Prominent watercourses and water bodies;
· Cultural and religious identity, and
· Geological features.
Sensitivity of LCAs and LRs
10a.5.2.3 The individual landscape character areas (LCAs) / landscape resources (LRs) are described qualitatively and quantitatively. Their sensitivities are then evaluated and rated as low, medium or high based on the following factors:
· Quality, condition and value of landscape character / resource;
· Importance and rarity of special landscape resources;
· Ability of the landscape to accommodate change without compromising its essential nature;
· Significance of the character / resource in local and regional context; and
· Maturity of the landscape.
10a.5.2.4 The rating of the sensitivity of the LCAs / LRs is assessed as follows:
High |
Important
components of a landscape of particularly distinctive character susceptible
to relatively small changes. |
Medium |
A landscape
of moderately valued characteristics reasonable tolerant to change. |
Low |
Relatively
unimportant landscape, able to absorb significant change. |
Magnitude of Change of LCAs and LRs
10a.5.2.5 Some common factors that are considered in deriving the magnitude of change in assessing landscape impacts are as follows:
· Compatibility of the Project with the landscape resource;
· Duration of impacts under the construction and operation phases;
· Scale of the development; and
· Reversibility of change.
10a.5.2.6 The rating of the magnitude of change of the LCAs / LRs is assessed based on the above criterion as follows:
Large |
LCA or
LR will suffer a large change due to the proposed works. |
Intermediate |
LCA or
LR will suffer a moderate change due to the proposed works. |
Small |
LCA or
LR will suffer a perceptible change due to the proposed works. |
Negligible |
LCA or
LR will suffer no discernible change due to the proposed works. |
10a.5.3
Visual Baseline Study Methodology
10a.5.3.1 The baseline survey of views towards the proposed development is carried out within the zone of visual influence.
10a.5.3.2 The visual envelope (zone of visual influence), according to EIAO GN No. 8/2010, is generally the view shed formed by natural/man-made features such as ridgeline or building blocks. The visual envelope may contain areas that are fully visible, partly visible and non-visible from the proposed works. The visual sensitive receivers (VSRs) are those within the visual envelope whose views will be affected by the proposed works.
Sensitivity of VSRs
10a.5.3.3 The baseline survey describes and records the typical views from the VSRs and their characters and values within the visual envelope at low-level viewpoints (street level) and high-level viewpoints (hillside vantage points). Both present and future VSRs are considered.
10a.5.3.4 In the assessment of the sensitivity of the VSRs, the type of VSR is the key factor to be considered. Those VSRs who view the proposed works from their homes are considered to be highly sensitive as the attractiveness, or otherwise, of the view from their homes would have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life. Those VSRs who view the proposed works from their workplaces / schools are considered to be less sensitive in general as the attractiveness or otherwise of the view from their workplaces / schools would have a less important role in their perception of the quality of the working environment. The sensitivity also depends on whether the workplace is industrial, retail or commercial. For those VSRs who view the proposed works while engaging in outdoor leisure activities, their sensitivity depends on the type of leisure activity. For those VSRs who view the proposed works from public thoroughfares, their sensitivity depends on the speed of travel.
10a.5.3.5 The criteria for ranking the sensitivity of a VSR are:
· Type of representative receiver population;
· Value and quality of the existing view;
· Estimated number of representative receiver population;
· Availability and amenity of alternative views;
· Duration or frequency of views; and
· Degree of visibility.
10a.5.3.6 The rating of the sensitivity of the VSRs is assessed as follows:
High |
Highly sensitive to any change in their viewing experience. |
Medium |
Moderately sensitivity to any change in their viewing experience. |
Low |
Only slightly sensitive to any change in their viewing experience. |
Magnitude of Change to VSRs
10a.5.3.7 The common factors considered in deriving the magnitude of change in assessing the visual impacts are as follows:
· Compatibility of the Project with the surrounding landscape;
· Duration of impacts under the construction and operation phases;
· Scale of development;
· Reversibility of change;
· Viewing distance; and
· Potential blockage of view.
10a.5.3.8 The rating of the magnitude of change to the VSRs is based on the above criterion assessed as follows:
Large |
VSRs
will suffer a large change due to the proposed works. |
Intermediate |
VSRs
will suffer a moderate change due to the proposed works. |
Small |
VSRs
will suffer a perceptible change due to the proposed works. |
Negligible |
VSRs
will suffer no discernible change due to the proposed works. |
10a.5.4 Impact Significance Threshold Assessment Methodology
Impact Significance Threshold before Mitigation
10a.5.4.1 The assessment of the potential landscape / visual impacts during the construction and operation phases with or without the proposed works is created by synthesizing the “Sensitivity” and “Magnitude of Change” for the LCAs/LRs/VSRs according to the Matrix of Impact Significance Threshold before Mitigation in Table 10a.1.
Table 10a.1 Matrix for Impact Significance Threshold –
Combination and Relationship between Sensitivity and Magnitude of Change
Magnitude of
Change due to the Proposed Works |
|
Sensitivity
of LR/LCA/VSR |
||
Low |
Medium |
High |
||
Large |
Moderate |
Moderate /
Substantial |
Substantial |
|
Intermediate |
Slight /
Moderate |
Moderate |
Moderate /
Substantial |
|
Small |
Slight |
Slight /
Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
Degree of Impact Significance Threshold before Mitigation
10a.5.4.2 The degree of significance is categorized into four thresholds depending on the combination below:
Substantial |
Adverse / beneficial impact where the proposed
works would cause significant deterioration / improvement in the existing
landscape / visual quality. |
Moderate |
Adverse / beneficial impact where the proposed
works would cause noticeable deterioration / improvement in the existing
landscape / visual quality. |
Slight |
Adverse / beneficial impact where the proposed
works would cause barely perceptible deterioration / improvement in the
existing landscape / visual quality. |
Insubstantial |
No discernible change in the existing landscape /
visual quality. |
10a.5.5 Residual Impacts Assessment Methodology
10a.5.5.1
Residual impacts are those
impacts remaining after the proposed mitigation measures have been implemented.
The planting mitigation measures are deemed to have reached a level of maturity
to perform their original design objectives 10 to 15 years after the implementation
of the mitigation measures.
10a.5.5.2
The level of residual impact is
derived from the magnitude of change which the proposed works will cause to the
existing view or landscape character and the ability to the LRs/LCAs/VSRs to tolerate
change, i.e. the quality and sensitivity of the view or landscape character
taking into account the beneficial effects of the proposed mitigation measures.
The significance threshold is derived from the matrix shown in Table 10a.1.
10a.5.5.3
Impacts ranged from
“Substantial” to “Moderate” are considered as non-ideal situations, and
corresponding mitigation measures are recommended. Mitigation measures are also
considered for the purpose of potential landscape and visual enhancement.
10a.5.6 Photomontage Illustration for Selected Views
10a.5.6.1
Representative views from the VSRs
are selected to illustrate the effectiveness of the proposed mitigation
measures and the residual impacts of the proposed works in both short and long
term. For each selected VSR, photomontages are prepared for:
· Existing baseline condition (Day 1 of Construction Phase)
· Development without mitigation
· Development with mitigation (Day 1 of Operation Phase)
· Development with mitigation (10 years of Operation Phase)
10a.5.7 Overall Result of Assessment
10a.5.7.1
In accordance with Annex 10 of
the EIAO TM, an overall assessment is made for the proposed works based on the
residual landscape and visual impacts as follows:
Beneficial |
The proposed works will complement the landscape and visual character of its setting, follow the relevant planning objectives, and improve overall and visual quality. |
Acceptable |
There will be no significant effects on the landscape, no significant visual effects, and no interference with the key views due to the proposed works. |
Acceptable with Mitigation Measures |
There will be some adverse effects due to the proposed works, but the adverse effects can be eliminated, reduced or offset to a large extent by the proposed mitigation measures. |
Unacceptable |
There will be the adverse effects that are considered too excessive and are unable to mitigate practically. |
Undetermined |
Significant adverse effects are likely, but the extent to which they may occur or may be mitigated cannot be determined from the study. Further detailed study will be required for the specific effects in question. |
10a.6.1 Identification of Landscape Resources (LRs)
10a.6.1.1
The details and locations of
LRs are shown Table 10a.2 and Figure 10a.2 respectively.
The photos showing the LRs are presented in Figures 10a.3
to 10a.4.
Table 10a.2 Landscape Resources within Study Area
I.D. no. |
Landscape Resources (LRs) |
Quantity (ha) (Within Project Site /
Within Study Area) |
Description |
LR1 |
Ash Lagoon & Trees |
46 |
· This LR refers to the ash lagoon area that is comprised of the East, Middle and West Lagoons. The project site lies in the northern part of the Middle Lagoon. ·
The ash lagoons are formed for storage of pulverized fuel ash (PFA) generated
from the adjacent power plants. Ash lagoon is an uncommon landscape resource in · The ash dumping activities in the Middle Lagoon ceased for years.Throughout the years, a number of grasses, creepers, groundcovers, and small shrubs have grown. Larger shrubs and even small trees, such as Macaranga tanarius and Leucaena leucocephala, are found at the edge of the lagoon and along the seawall. The trees are mature. At the northern part of the middle lagoon, 47 nos. of trees of three common species (Celtis sinensis, Macaranga tanarius & Bombax ceiba) were recorded in the tree survey. There is no registered Old and Valuable Tree in this LR. · Some portions of the Middle Lagoon are marshy with plants and water ponds. The coverage of water ponds varies with seasons, ranging from approximately 20% to 50% of the Middle Lagoon. The water ponds are mainly located at the southern part of the Middle Lagoon. About 80% area of the north part of the Middle Lagoon is a bare ground with little vegetation. |
LR2 |
Seashore |
4.5 |
·
This LR refers to the artificial seawall along
the edge of ash lagoons. It is in the form of sloping boulders and of typical
man-made exposed seawalls in · Some plants (e.g. Celtis sinensis, Lantana camara and Ficus virens) are found at the seawall. |
LR3 |
Tidal Stream |
1.0 |
·
This LR refers to a semi-natural to man-made
water channel and its tributaries located to the south of the ash lagoons.
The water channel collects water from its tributaries that run down from the
valleys of Castle Peak, and drains the water from west to east towards the · Shrubby vegetation and occasional trees are found along the banks of the water channel. |
LR4 |
Woodland &
Shrubland |
8.8 |
·
This LR refers to the woodland located to the
south of the project site and the shrubland close to the water channel located to the north of this LR. In
the woodland, there are
signs of previous human activities, such as a building structure,
paved / unpaved roads, concrete platform. The shrubland is sparse with low species diversity. ·
The woodland and shrubland are mature. The
trees found in this LR are common species, such as Celtis sinensis, Leucaena
leucocephala, Ligustrum sinense,
Macaranga tanarius, Microcos paniculata, Rhus spp., Sterculia lanceolata, etc. There is no registered Old and
Valuable Tree in this LR. · The area was previously a seaside village. It can be dated back to as early as Neolithic Age according to the pottery and stone tools pieces excavated during an archaeological investigation for Tsang Tsui Archaeological Site (TTAS) carried out in 2000. However, there is little human trace to be observed on site nowadays. Access to this abandoned village is rarely known as the area is covered by dense vegetation with only one access full of gravel and dirt. |
LR5 |
Vegetated Slope |
32.5 |
·
This LR refers to the man-made slopes (cut slopes) and the hillside,
disturbed areas located to the south of the ash lagoons. · The man-made slopes are planted with hydroseeding and woodland mix. Self-seeded trees are also found. The trees found in the slopes are common species, such as Acacia spp., Casuarina equisetifolia, Celtis sinensis, Eucalyptus spp., Ficus spp., Macaranga tanarius, etc. ·
The hillside, disturbed areas are with high population of grasses and
groundcovers. Small trees, mostly Macaranga
tanarius and Leucaena leucocephala,
and shrubs are randomly scattered in the areas. ·
The trees are mature in general. There is no registered Old and
Valuable Tree in this LR. |
LR6 |
Landfill |
3.3 |
· This LR refers to the existing WENT Landfill, which is characterized by heavy trucks, dust, smells, landfill / industrial nature. ·
The access to the WENT Landfill is restricted. |
LR7 |
Seawater of Nim Wan |
72.2 |
·
This LR refers to the |
LR8 |
Factories |
6.3 |
· This LR refers to the grease treatment plant with storage tanks and associated facilities. The facilities are within the boundary of the WENT Landfill. |
LR9 |
|
0.003 |
·
Surrounded by the dense woodland (LR4), there
is Hung Shing and |
10a.6.2 Identification of Landscape Character Areas (LCAs)
10a.6.2.1
The details and locations of
LCAs are shown in Table 10a.3 and Figure 10a.5 respectively.
The photos showing the LCAs are presented in Figure 10a.6.
Table 10a.3 Landscape Character Areas within Study Area
I.D. no. |
Landscape
Character Areas (LCAs) |
Quantity (ha) (Within Project Site / Within Study Area) |
Description |
LCA1 |
Ash Lagoon |
46 |
· This LCA refers to the ash lagoons. ·
The ash lagoons were formed for storage of pulverized fuel ash (PFA)
generated from the adjacent power plants. It is an uncommon landscape
in · This LCA is characterized by human intervention converting the former ash lagoon into water collection and conservation lagoon of a dumping site nature. · The area is mostly covered with exposed ash, water ponds, medium-tall grasses, small shrubs, stones and creepers due to its past development phases. · The ash lagoons are separated by unpaved roads serving as vehicular accesses for trucks. · The project site lies on the northern part of the Middle Lagoon. The northern part of the East Lagoon located to the east of the project site will be used for the development of the Sludge Treatment Facilities (STF). |
LCA2 |
Landfill Landscape |
9.6 |
· This LCA refers to the degraded land made up of landfill site (LR6), together with their associated access haul roads, artificial cut and fill slopes, modified surface drainage system, waste reception area, leachate treatment system, grease treatment plants, and storage tanks (LR8). · This LCA is characterized by industrial nature lands, construction plants, equipment and heavy trucks. The access to the landfill site and its associated facilities is restricted. |
LCA3 |
Abandoned Village |
15.1 |
· This LCA refers to the abandoned seaside village to the south of the ash lagoon. It can be dated back to as early as Neolithic Age according to the pottery and stone tools pieces excavated during an archaeological investigation for Tsang Tsui Archaeological Site (TTAS), located at the south-western part of this LCA, carried out in 2000. However, there is little human trace to be observed on site nowadays. ·
The only apparent existing human trace is the two-room
building structure, which is the Hung Shing and Dragon Mother · About 10 nos. of graves are found in the TTAS built around 1930s. Some have been abandoned and are in poor condition. · Access to this area is limited as this area is covered by dense vegetation with only one gravel access. · A large portion of this LCA is covered by woodland. · Weeds are extensively found at the area on the southern side of ash lagoon. |
LCA4 |
Barren |
32.3 |
· This LCA refers to the natural and steep hillside slope covered by low grasses and occasional shrubs and small trees. · It comprises of knolls, ridges and spurs with rocky outcrops or boulder fields. · Due to its steep topography and its proximity to the firing range, public access is extremely rare. |
LCA5 |
Inter-tidal Coast Landscape |
76.7 |
·
This LCA covers seawater and the artificial seawall along the edge of ash
lagoons. It is in the form of sloping boulders and of typical man-made exposed
seawalls in ·
It is open and as part of · To the further north of the water body is the coastline of Shekou, which is at a distance of approx. 7km away. · It is characterized by its tranquility and sense of remoteness. |
10a.6.3 Identification of Visual Sensitive Receivers
10a.6.3.1 The details and locations of VSRs are shown in Table 10a.4 and Figure 10a.7 respectively. The photos showing the VSRs are presented in Figure 10a.8.
Table 10a.4 Visual Sensitive Receivers within Visual Envelope
I.D. no. |
Visual
Sensitive Receivers (VSRs) |
Type of VSRs |
Number of VSRs |
Description |
VSR1 |
Footpath Uphill |
Occupational |
Few |
·
This VSR refers to the workers who maintain
and repair the pipe ducts and drainage systems on the slope to the southeast
of the Middle Lagoon. · The maintenance access used by the workers located uphill is restricted. · While the view of the project site is screened off by the heavy vegetation at the ground level, the project site becomes visible to this VSR as they walk uphill along the maintenance access. At about 10m above the ground level, the full view of the project site can be seen by this VSR. |
VSR2 |
Nim Wan Road |
Traveller |
Few |
·
This VSR refers to the travellers who travel
along · The building structures in the project site are screened off by the trees along the roadside. Only a portion of the chimney would be visible to this VSR. |
VSR3 |
Sludge
Treatment Facilities |
Occupational &
Visitors |
Medium |
· This VSR consists of the workers operating the Sludge Treatment Facilities (STF) and the visitors visiting the Environmental Education Centre (EEC) at STF. · The STF workers would carry out indoor works in most circumstances. · The visitors to EEC would have a good view of the architectural and landscape design of the IWMF being coherent with the STF, and the development of the two facilities would be integrated and blended well with each other. |
VSR4 |
Sea of |
Sea Traveller &
Occupational |
Few |
· This VSR includes the sea travelers travelling in the Deep Bay to/from Shekou, workers on vessels carrying waste containers to the WENT Landfill, and workers on fishing vessels. · In normal situations, ships would not sail close to the site. · Owing to the vast and exposed site, the proposed works will be visible by the VSR in a significant way, especially the presence of the high-rise stacks. |
VSR5 |
Ha Pak Lai |
Residents &
Visitors |
Medium |
· This VSR refers to the residents & visitors at Ha Pak Lai, located about 2km to the east of the project site. · As there is a significant distance between the project site and the village, most of the proposed works will be barely seen by the VSR. · The vista to the proposed works would be marginally blocked by the STF to the east of the project site. |
VSR6 |
Black Point
Power Station |
Occupational |
Few |
· This VSR refers to the operators of the Black Point Power Station, located to the southwest of the project site. · The VSR’s view of the buildings in the project site will be fully blocked by the existing slope (range from 20-100mPD) to the northeast of this VSR; only a portion of the chimney will be visible to this VSR. |
10a.7 Sources of Landscape and Visual Impact
10a.7.1 Sources of Landscape Impact
10a.7.1.1 The sources of landscape impact during the construction phase are shown in Table 10a.5.
Table 10a.5 Sources of Landscape Impact during Construction Phase
Code |
Sources of
Landscape Impact during Construction Phase |
LC-01 |
· Removal / transplantation of the existing vegetation at the ash lagoon for site formation / building construction. |
LC-02 |
· Filling of the project site and leveling works at northern and eastern side of project site for the construction of access road (for waste transportation) connected to future access road constructed under the STF Project. The existing shoreline would not be affected. |
LC-03 |
· Loss of the ash lagoons due to site formation works in the Middle Lagoon, including clearance of boulders, and subsequent backfilling and leveling of the site. |
LC-04 |
· Foundation piling works (socketted H pile as recommended). |
LC-05 |
· Construction of new roads connecting the STF site, incinerators, boilers and 150m high chimney in the Middle Lagoon. |
LC-06 |
· Construction of ancillary facilities such as administration building & Environmental Education Centre, steam turbine, refuse bunker, wastewater treatment plant, fly ash silos and treatment facilities, air compressor station, air cooled condenser, oil pump room, etc. in the Middle Lagoon. |
LC-07 |
· Underground excavation and connection for installation of utilities, including waterpipes, plumbing, drains, cables, etc. for the IWMF operation. |
LC-08 |
· Temporary site access, site cabins and heavy machinery. |
10a.7.1.2 The sources of landscape impact during the operation phase are shown in Table 10a.6.
Table 10a.6 Sources of Landscape Impact during Operation Phase
Code |
Sources of
Landscape Impact during Operation Phase |
LO-01 |
· Completed incineration plant & chimney. |
LO-02 |
· Completed ancillary buildings such as new administration building & Environmental Education Centre and elevated bridge for visitors. |
LO-03 |
· Completed chemical storage building and chemical dosing area. |
LO-04 |
· Completed wastewater treatment plant and desalination plant. |
10a.7.2 Sources of Visual Impact
10a.7.2.1 The sources of visual impact during the construction phase are shown in Table 10a.7.
Table 10a.7 Sources of Visual Impact during Construction Phase
Code |
Sources of
Visual Impact during Construction Phase |
VC-01 |
· Visual obstruction by temporary and permanent construction plant and structures. · Visual obstruction by construction activities and traffic within the project site. · Visual obstruction by loss of open sea view. |
VC-02 |
· Visual quality affected due to site formation and bare soil surface. |
VC-03 |
· Visual quality affected due to glare generated by after-dark lighting and welding. |
VC-04 |
· Visual quality affected by dust generated by construction activities and traffic. |
10a.7.2.2 The sources of visual impact during the operation phase are shown in Table 10a.8.
Table 10a.8 Sources of Visual Impact during Operation Phase
Code |
Sources of
Visual Impact during Operation Phase |
VO-01 |
· Visual quality affected by the completed 150m high chimney, incinerators and boilers. |
VO-02 |
· Visual quality affected by the completed ancillary buildings such as administration building & Environmental Education Centre, steam turbine, refuse bunker, wastewater treatment plant, fly ash silos and treatment facilities, air compressor station, air cooled condenser, oil pump room, etc. on ash lagoon. |
VO-03 |
· Visual quality affected by lighting provision of the development during operation at night. |
VO-04 |
· Visual obstruction by loss of some greenery. |
VO-05 |
· Visual obstruction by blockage to open sea view. |
VO-06 |
· Waste transportation traffic along access road to/from the WENT Landfill. |
10a.8 Landscape Impact Assessment (Before Mitigation)
10a.8.1 Sensitivity of Landscape Resources and Landscape Character Areas
10a.8.1.1 Based on the findings of the baseline study, the “Sensitivity” of the identified LRs and LCAs is assessed and listed in Table 10a.9.
Table 10a.9 Sensitivity of Identified Landscape Resources and Landscape Character Areas
Landscape Resources/ Landscape Character Areas |
Ability to Accommodate Change (Low, Medium,
High) |
Importance (local, regional,
national, global) |
Rarity (Low, Medium,
High) |
Quality of Resource (Low, Medium,
High) |
Maturity of Resource (Mature,
Pre-mature) |
Sensitivity (Low, Medium,
High) |
|||
Landscape Resources |
|||||||||
LR1 Ash Lagoon &
Trees |
· Naturalness is low due to its conversion into a man-made dumping ground with frequent disturbance from CLP’s PFA & dredging activities at the lagoons. · Although site formation works would be carried out at the northern part of the Middle Lagoon, this LR has been previously disturbed by human activities, and its ability to accommodate change is medium. · A number of grasses, creepers, groundcovers, and small shrubs have grown. Larger shrubs and even small trees, such as Macaranga tanarius and Leucaena leucocephala, are found. The trees are mature. None of them are of high landscape value. · Floral diversity is low (29 species). · The landscape value / quality for this landscape resource is considered to be low. |
Medium |
|||||||
Medium |
Local |
Medium |
Low |
Mature |
|||||
LR2 Seashore |
· The seashore is an artificial seawall made up of sloping boulders, already intervened by human. The naturalness is hence low. · Its ability to accommodate change is high. · Some plants (e.g. Celtis sinensis, Lantana camara and Ficus virens) are found. They are of common species and of low landscape value. |
Low |
|||||||
High |
Local |
Low |
Low |
Mature |
|||||
LR3 Tidal Stream |
·
The stream is a semi-natural to man-made water
channel, collecting water from its tributaries that run down from the valleys
of Castle Peak, and draining the water from west to east towards the · Wild vegetation and occasional trees are found along the banks of the water channel. |
Medium |
|||||||
Medium |
Local |
Low |
Medium |
Mature |
|||||
LR4 Woodland &
Shrubland |
·
The woodland is located to the south of the
project site and the shrubland
is located close to the water channel located to the north of this LR. In
the woodland, there are signs
of previous human activities, such as a building structure, paved /
unpaved roads, concrete platform. The shrubland is sparse with low species diversity. · The woodland and shrubland are mature. The trees found in this LR are common species, such as Celtis sinensis, Leucaena leucocephala, Ligustrum sinense, Macaranga tanarius, Microcos paniculata, Rhus spp., Sterculia lanceolata, etc. Trees are scattered around this LR and takes up about 60% of the 8.8 ha of land of this LR. · Floral diversity is not high. · Separated by LR3 and LR5, this LR is detached from the project site. |
Medium |
|||||||
Medium |
Local |
Medium |
Medium |
Mature |
|||||
LR5 Vegetated Slope |
· The LR consists of approx. 32.5 ha of man-made slopes (cut slopes) with reinstated plantation and the hillside, disturbed areas with naturally grown vegetation. · Trees of common species, mostly Macaranga tanarius and Leucaena leucocephala, are scattered around this LR, taking up more than 50% of the total area of this LR. The trees are mature in general. No rare species are recorded. · Floral diversity is not high. |
Low |
|||||||
Medium |
Local |
Low |
Low |
Mature |
|||||
LR6 Landfill |
· This LR refers to existing the WENT Landfill, which is highly disturbed by human activities. Its ability to accommodate change is hence high. |
Low |
|||||||
High |
Local |
Medium |
Low |
Mature |
|||||
LR7 Seawater of Nim Wan |
·
This LR refers to the · Due
to large quantity of seawater in the local area, this resource is not rare. · The landscape quality and value is considered medium. |
Medium |
|||||||
Medium |
Local |
Low |
Medium |
N/A |
|||||
LR8 Factories |
· This LR is completely intervened by man-made structures, such as grease treatment plant, storage tanks, etc. · There are some planting strips in this region. |
Low |
|||||||
High |
Local |
Low |
Low |
Mature |
|||||
LR9 |
·
Surrounded by the dense woodland, there are
traces of destroyed structures. The only building structure exists is the
Hung Shing and Dragon Mother · The temple is a single-storey, two-room building structure. It was re-built in 1980s with cement mortar & steel after fire damage. The landscape value of the temple is considered low. · Separated by LR4, this LR is detached from the project site. |
Medium |
|||||||
Medium |
Local |
Medium |
Medium |
Mature |
|||||
Landscape Character Areas |
|||||||||
LCA1 Ash Lagoon |
· The ash lagoon is frequently disturbed by PFA and dredging activities. · It is characterized by its wasteland nature with vegetation of common species. · It has low species diversity. · It is capable to accommodate change due to its frequent disturbance by human activities. |
Medium |
|||||||
Medium |
Local |
Medium |
Low |
Mature |
|||||
LCA2 Landfill Landscape |
· This LCA is characterized by its industrial environment and is capable to accommodate change. |
Low |
|||||||
High |
Local |
Low |
Low |
Mature |
|||||
LCA3 Abandoned Village |
· A small portion at the southwest part of this LCA is an archaeological site with limited ability to accommodate change. · A large portion of this LCA is covered by woodland with common plant species. · The temple (with about 50 years history) and graves are of low to medium landscape value. |
Medium |
|||||||
Medium |
Local |
Medium |
Medium |
Mature |
|||||
LCA4 Barren |
·
Common plant species of low landscape value
are found in the vegetated slope (LR5). |
Low |
|||||||
Medium |
Local |
Low |
Low |
Mature |
|||||
LCA5 Inter-tidal coastal landscape |
·
The LCA covers the · The landscape quality and value of the LCA is considered medium. |
Medium |
|||||||
Medium |
Local |
Low |
Medium |
N/A |
|||||
10a.8.2 Magnitude of Change of Landscape Resources and Landscape Character Areas
10a.8.2.1 The “Magnitude of Change” of the identified LRs and LCAs is assessed and listed in Table 10a.10.
Table 10a.10 Magnitude of Change of Identified Landscape Resources and Landscape Character Areas
|
Landscape Resources/ Landscape Character Areas |
Physical Extent & Landscape |
Magnitude of Change (Negligible,
Small, Intermediate, Large) |
|
Construction |
Operation |
|||
Landscape Resources |
||||
LR1 |
Ash Lagoon &
Trees |
Source
of Impact (Construction Phase) · LC-01, LC-02, LC-03, LC-04, LC-05, LC-06, LC-07, LC-08 Source
of Impact (Operation Phase) · LO-01, LO-02, LO-03, LO-04 Physical
Extent · The Project would require decommissioning of the Middle Lagoon. Site formation works including clearance of boulders and subsequent backfilling of site would be carried out in the Middle Lagoon, forming about 11 hectares of land (about 25% of LR1), followed by foundation works. · Followed by foundation works, the associated roads and drains, superstructures building and installation of plant and equipment for the various systems will be constructed in the project area. · Road works connecting the STF site will be carried out outside the project area, which is located along the northern side of this LCA. Compatibility with surrounding landscape · 23 nos. of trees of common species would need to be transplanted at the middle lagoon where the project work is situated. However, their chance of survival during on-site transplantation would be low. · Currently, the land has been largely formed by PFA that was filled to this site in the previous years. As there is no existing structure in the site area, the works related to the decommissioning of the lagoon would be minimal. · The finished ground level of the IWMF will be at a level higher than the average ground level of the existing Middle Lagoon. Therefore, the forming of the land for the IWMF would involve mainly filling and levelling work. No disposal of PFA will be required during the construction phase. · As the STF will be constructed adjacent to this site before the commencement of this Project, the development of the IWMF at the Middle Lagoon is considered compatible with the surrounding context. Duration
of impact · The duration of impact imposed during the construction (approximately 3 years) and operation phases is long. Reversibility
of Change · The impact is considered permanent and irreversible. |
Large |
Large |
LR2 |
Seashore |
· Located outside works area; no direct/physical impact. · No pier would be constructed along this LR as waste will be transported to the existing berth of the WENT Landfill by marine transport, and then to the IWMF by land transport. |
Negligible |
Negligible |
LR3 |
Tidal Stream |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR4 |
Woodland &
Shrubland |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR5 |
Vegetated Slope |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR6 |
Landfill |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR7 |
Seawater of Nim Wan |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR8 |
Factories |
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LR9 |
|
· Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
Landscape Character Areas |
||||
LCA1 |
Ash Lagoon |
Source
of Impact (Construction Phase) · LC-01, LC-02, LC-03, LC-04, LC-05, LC-06, LC-07, LC-08 Source
of Impact (Operation Phase) · LO-01, LO-02, LO-03, LO-04 Physical
Extent · The Project would require decommissioning of the Middle Lagoon. Site formation works including clearance of boulder, and subsequent backfilling of site would be carried out in the Middle Lagoon, forming about 11 hectares of land (about 25% of LR1) · Followed by foundation works, the associated roads and drains, superstructures building and installation of plant and equipment for the various systems will be constructed in the project area. · Road works connecting the STF site will be carried out outside the project area, which is located along the northern side of this LCA. Compatibility
with Surrounding Landscape · No pier would be constructed along shoreline as waste will be transported to the existing berth of the WENT Landfill by marine transport, and then to the IWMF by land transport. · 23 nos. of trees of common species would need to be transplanted at the Middle Lagoon where the project work is situated. However, their chance of survival during on-site transplantation would be low. · Currently, the land has been largely formed by PFA that was filled to this site in the previous years. As there is no existing structure in the site area, the works related to the decommissioning of the lagoon would be minimal. · The finished ground level of the IWMF will be at a level higher than the average ground level of the existing Middle Lagoon. Therefore, the forming of the land for the IWMF would involve mainly filling and levelling work. No disposal of PFA will be required during the construction phase. · As the STF will be constructed adjacent to this site before the commencement of this Project, the development of the IWMF at the Middle Lagoon is considered compatible with the surrounding context. Duration
of impact · The duration of impact imposed during the construction (approximately 3 years) and operation phases is long. Reversibility
of Change · The impact is considered permanent and irreversible. |
Large |
Large |
LCA2 |
Landfill Landscape |
Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LCA3 |
Abandoned Village |
Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LCA4 |
Barren |
Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
LCA5 |
Inter-tidal Coast Landscape |
Located outside works area; no direct/physical impact. |
Negligible |
Negligible |
10a.8.3 Significance Threshold of Landscape Resources and Landscape Character Areas
10a.8.3.1 Based on the “Sensitivity” as listed in Table 10a.9 and “Magnitude of Change” as listed in Table 10a.10, the degree of significance for LRs and LCAs is identified according to the matrix Table 10a.1. The Significance Threshold of identified LRs and LCAs before mitigation is assessed and listed in Table 10a.11.
Table 10a.11 Significance Threshold of Identified Landscape Resources and Landscape Character Areas before Mitigation
|
Landscape Resources/ Landscape Character Areas |
Sensitivity |
Source of Impact |
Magnitude of Change Before Mitigation |
Impact Significance Threshold Before Mitigation |
||||
Const-ruction |
Operat-ion |
Construction |
Operation |
Construction |
Operation |
||||
Landscape Resources |
|||||||||
LR1 |
Ash Lagoon &
Trees |
Medium |
LC-01 LC-02 LC-03 LC-04
LC-05 LC-06 LC-07 LC-08 |
LO-01 LO-02
LO-03 LO-04 |
Large |
Large |
Substantial |
Substantial |
|
LR2 |
Seashore |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR3 |
Tidal Stream |
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR4 |
Woodland &
Shrubland |
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR5 |
Vegetated Slope |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR6 |
Landfill |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR7 |
Seawater of Nim Wan |
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR8 |
Factories |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LR9 |
|
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
Landscape Character Area |
|||||||||
LCA1 |
Ash Lagoon |
Medium |
LC-01 LC-02 LC-03 LC-04
LC-05 LC-06 LC-07 LC-08 |
LO-01 LO-02
LO-03 LO-04 |
Large |
Large |
Substantial |
Substantial |
|
LCA2 |
Landfill Landscape |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LCA3 |
Abandoned Village |
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LCA4 |
Barren |
Low |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
LCA5 |
Inter-tidal Coast Landscape |
Medium |
Nil |
Nil |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
|
10a.9 Visual Impact Assessment
10a.9.1 Sensitivity of Visual Sensitive Receivers
10a.9.1.1
Based on the findings of the
baseline study, the characteristics and “Sensitivity” of the identified VSRs
are summarized in Table 10a.12.
Table 10a.12 Sensitivity of Identified Visual Sensitive Receivers
I.D. no. |
VSRs |
Type of VSRs |
No. of Individuals (Many, Medium,
Few, Very Few) |
Quality of Existing View (Good, Fair, Poor) |
Availability of Alternative Views (Yes/No) |
Degree of Visibility (Full,
Partial, Glimpse) |
Frequency of View (Very Frequent,
Frequent, Occasional, Rare) |
Sensitivity (Low, Medium,
High) |
|
VSR1 |
· The VSR consists of workers who maintain and repair the pipe ducts and drainage systems on the slope to the southeast of the Middle Lagoon. ·
The maintenance access used by the workers
located uphill is restricted. ·
While the view of the project site is screened
off by the heavy vegetation at the ground level, the project site becomes
visible to this VSR as they walk uphill along the maintenance access. At
about 10m above the ground level, the full view of the project site can be
seen by this VSR. |
Medium |
|||||||
Footpath Uphill |
Occupational |
Few |
Good |
Yes |
Full |
Occasional |
|||
VSR2 |
·
This VSR refers to the travellers who travel
along · The building structures in the project site are screened off by the trees along the roadside. Only a portion of the chimney would be visible to this VSR. |
Low |
|||||||
Nim Wan Road |
Traveller |
Few |
Fair |
Yes |
Glimpse |
Occasional |
|||
VSR3 |
· This VSR consists of the workers operating the STF and the visitors visiting the Environmental Education Centre (EEC) at STF. · The STF workers would carry out indoor works in most circumstances. · The visitors to EEC would have a good view of the architectural and landscape design of the IWMF being coherent with the STF, and the development of the two facilities would be integrated and blended well with each other. · There are alternative views with high amenity value to this VSR. |
Medium |
|||||||
Sludge Treatment Facilities |
Occupational & Visitors |
Medium |
Fair |
Yes |
Full |
Frequent |
|||
VSR4 |
· This VSR includes the sea travelers travelling in the Deep Bay to/from Shekou, workers on vessels carrying waste containers to the WENT Landfill, and workers on fishing vessels. · In normal situations, ships would not sail close to the site. · Owing to the vast and exposed site, the proposed works will be visible by the VSR in a significant way, especially the presence of the high-rise stacks. · There are alternative views with high amenity value to this. |
High |
|||||||
Sea of |
Sea traveller & Occupational |
Medium |
Good |
Yes |
Full |
Occasional |
|||
VSR5 |
· This VSR refers to the residents & visitors at Ha Pak Lai, located about 2km to the east of the project site. · As there is a significant distance between the project site and the village, most of the proposed works will be barely seen by the VSR. · The vista to the proposed works would be marginally blocked by the STF to the east of the project site. |
High |
|||||||
Ha Pak Lai |
Residential & Visitors |
Medium |
Good |
Yes |
Partial |
Frequent |
|||
VSR6 |
· This VSR refers to the operators of the Black Point Power Station, located to the southwest of the project site. · The VSR’s view of the buildings in the project site will be fully blocked by the existing slope (range from 20-100mPD) to the northeast of this VSR. Only a portion of the chimney will be visible to this VSR. |
Low |
|||||||
Black Point Power Station |
Occupational |
Few |
Fair |
Yes |
Partial |
Occasional |
|||
10a.9.2 Magnitude of Change of Visual Sensitive Receivers
10a.9.2.1
The “Magnitude of Change” of
the identified VSRs is assessed and listed in Table 10a.13.
Table 10a.13 Magnitude of Change of Identified Visual Sensitive Receivers
I.D. no. |
VSRs |
Source of Impact |
Compatibility (Good, Fair,
Poor) |
Duration of Impacts (Very Frequent, Frequent,
Occasional, Rare) |
Reversibility of Change (Yes, No) |
Scale of Impact (Large, Medium,
Small) |
Viewing Distance (m) |
Potential Blockage of View (Full, Partial, Glimpse) |
Magnitude of Change (Large, Intermediate, Small, Negligible) |
||
Construction |
Operation |
Construction |
Operation |
||||||||
VSR1 |
Footpath Uphill |
VC-01 VC-02 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-05 |
Fair |
Occasional |
No |
Medium |
300 |
Full |
Intermediate |
Intermediate |
VSR2 |
Nim Wan Road |
VC-01 |
VO-01 VO-03 |
Fair |
Occasional |
No |
Large |
200 |
Glimpse |
Negligible |
Negligible |
VSR3 |
Sludge Treatment Facilities |
VC-01 VC-02 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
Fair |
Frequent |
No |
Medium |
10 |
Full |
Intermediate |
Intermediate |
VSR4 |
Sea of |
VC-01 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
Fair |
Occasional |
No |
Large |
100 |
Full |
Large |
Large |
VSR5 |
Ha Pak Lai |
VC-01 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
Fair |
Frequent |
No |
Medium |
2000 |
Partial |
Intermediate |
Intermediate |
VSR6 |
Black Point Power Station |
VC-01 |
VO-01 VO-03 |
Fair |
Occasional |
No |
Medium |
700 |
Partial |
Small |
Small |
10a.9.3 Significance Threshold of Visual Sensitive Receivers
10a.9.3.1 Based on the “Sensitivity” as listed in Table 10a.12 and “Magnitude of Change” as listed in Table 10a.13, the degree of significance for VSRs is identified according to the matrix shown in Table 10a.1. The Significance Threshold of the VSRs before mitigation is assessed and listed in Table 10a.14.
Table 10a.14 Significance Threshold of Identified Visual Sensitive Receivers before Mitigation
I.D. no. |
VSRs |
Source of Impact |
Sensitivity |
Magnitude of Change Before Mitigation |
Impact Significance Threshold Before Mitigation |
|||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|||
VSR1 |
Footpath Uphill |
VC-01 VC-02 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-05 |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
VSR2 |
Nim Wan Road |
VC-01 |
VO-01 VO-03 |
Low |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
VSR3 |
Sludge Treatment Facilities |
VC-01 VC-02 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
VSR4 |
Sea of |
VC-01 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
High |
Large |
Large |
Substantial |
Substantial |
VSR5 |
Ha Pak Lai |
VC-01 VC-03 VC-04 |
VO-01 VO-02 VO-03 VO-04 VO-06 |
High |
Intermediate |
Intermediate |
Moderate/
Substantial |
Moderate/
Substantial |
VSR6 |
Black Point Power Station |
VC-01 |
VO-01 VO-03 |
Low |
Small |
Small |
Slight |
Slight |
10a.10.1 Mitigation Measure Approaches
10a.10.1.1
The identification of the
landscape and visual impacts highlights the potential primary sources of
impacts and their magnitude of change caused to LRs/LCAs/VSRs. Corresponding
mitigation measures are proposed to avoid and reduce the identified sources of
impacts, and to remedy and compensate unavoidable impact. The potential
landscape and visual enhancement is also considered in the proposed mitigation
measures.
10a.10.2 General Mitigation Measures / Strategies
10a.10.2.1 Minimization of the structure size is an important strategy to alleviate the visual impact. In the design of the building heights and dimensions, the potential visual impact should be taken into consideration in addition to the engineering and other environmental factors. A balance should be struck between a smooth operation of the facilities and minimization of various environmental impacts. In determination of the height of the stack, it is important to alleviate the potential air quality impacts at critical ASRs, while not to result in significant visual intrusion. To determine the optimal height of the stack, wind tunnel tests that consisted of plume visualization were conducted for the stacks in various heights. The stack height of 150m was a balanced solution considering the air quality impacts at critical ASRs and the potential visual impact. For the other structures of the IWMF, their heights and dimensions should be designed with due consideration of requirements to accommodate the necessary equipment and the effective use of land and in order to minimize their size. In this reference design, instead of providing one bulky building at the same height to house all the equipment, structures with different building heights are designed to suit the specific needs of the equipment. The tallest part of the incineration plant is where the incinerators (about 50m) are accommodated, while the other part of the incineration plant and other structures are designed to be at lower heights.
10a.10.2.2
The proposed mitigation
measures shall also take into consideration the future developments in the
vicinity of the proposed works to enhance the compatibility with the surrounding
environment and improve the overall landscape and visual quality. Currently,
the Sludge Treatment Facilities (STF) has been confirmed to be developed to the
east of the TTAL site and will start commissioning before the IWMF. The STF is modern
incineration plant treating sludge generated from sewage treatment works. The STF has a contemporary design
integrated with landscape features such as green roof and landscape areas. With the architectural and landscape design of the IWMF being
coherent with the adjacent STF, the development of the two facilities could be
integrated and blend well in the surrounding landscape. The two developments
would form a harmonic view, and the cumulative landscape and visual impact of
the two developments would be alleviated.
10a.10.2.3 About 27 nos. of trees would be affected by the proposed works. As all the affected trees were with low survival rate after transplanting, these trees are recommended to be felled. Implementation of compensatory planting for heavy standard trees will be of a ratio not less than 1:1 according to tree quantity and total tree trunk diameter lost. The required numbers and locations of compensatory trees would be determined and agreed with Government during the tree felling application process under ETWB TCW 3/2006.
10a.10.2.4
It is expected that the heavy
standard trees would create immediate greening effect. As the affected trees,
which are of low amenity value, would be replaced by heavy standard trees, the
proposed mitigation measures would not only alleviate the impact due to the
project, but also enhance the existing landscape.
10a.10.2.5
The recommended mitigation
measures, which are applicable to individual LR, LCA and VSR, are tabulated in Table 10a.15. The locations where the recommended mitigation
measures to be implemented are shown in the Landscape & Visual Mitigation
Measures Plan (Figure 10a.9) for
reference.
10a.10.2.6
The mitigation measures during
construction will be implemented from the commencement of the works and shall
be applied for the whole duration of the construction period. The mitigation measures during operation will
be included in the detailed design and shall be constructed or built up during
the construction period. Management and
maintenance for all mitigation measures will follow ETWB TCW No. 2/2004
Maintenance of Vegetation and Hard Landscape Features.
10a.10.2.7
In terms of the funding,
implementation, management and maintenance of the recommended mitigation
measures, the Environmental Protection Department will be the responsible
agent. The mitigation measures are considered practical and feasible.
Table 10a.15 Recommended Landscape and Visual Mitigation Measures
ID. No. |
Landscape and
Visual Mitigation Measure |
During Construction Phase |
|
Mitigation for both Landscape & Visual Impacts |
|
MLVC-01 |
Grass-hydroseeded bare
soil surface. |
MLVC-02 |
Provision of Water
Pond as Habitat for Little Grebe A compensatory habitat
for Little Grebe will be provided as an ecological mitigation measure for the
loss of habitat within the project site. This compensatory habitat, which would
be a landscape area with water pond and plants, is also considered as a
landscape mitigation measure for the loss of ash lagoon. The final design of the habitat will be determined in the Habitat
Creation and Management Plan. The compensatory habitat as shown in
Figure 10a.9 and the
photomontages is for illustration purpose. |
MLVC-03 |
Existing Trees Preservation within Works Areas
No trees should be felled or transplanted
unless they are inevitably affected by the proposed works. Affected trees
should be transplanted under circumstance where technically feasible. A tree
survey report should be prepared and a tree felling application should be
submitted to Government during the detailed design stage for approval before the
site formation works commence. The numbers, locations, species and sizes of
the trees to be transplanted or felled should be clearly addressed. All existing trees within work sites shall be properly maintained and
protected for their crowns, trunks and roots. |
MLVC-04 |
Transplanting of Trees to Adjacent Locations The existing
trees recommended to be transplanted shall be directly transplanted to other
locations in vicinity where no construction will take place. The
construction programme should also allow sufficient time for root pruning and rootball
preparation prior to transplanting. |
MLVC-05 |
Compensatory Landscape Planting Implementation of compensatory planting with
heavy standard trees shall be of a ratio not less than 1:1 according to tree
quantity and total tree trunk diameter lost. |
MLVC-06 |
Landscape Design 1)
Early
planting using fast grow trees and tall shrubs at strategic locations within
site will be implemented to block view corridors to the site from the VSRs,
and to locally screen haul roads, excavation works and site preparation
works. 2)
Tree
species of dense tree crown will be used to serve as visual barrier. 3)
Hard
and soft landscape treatment (e.g. trees and shrubs) of open areas within
development will be implemented to provide shade and shelter and a green
appearance from surrounding viewpoints. 4)
Planting strip would be provided along the
periphery of the project site. 5)
Selected
plant species should be suitable for coastal condition. |
MLVC-07 |
Reuse Existing Boulders Boulders cleared from the ash lagoon
during site formation will be reserved and used as part of the landscape
design to preserve its “natural look”. |
MLVC-08 |
Greening Design (Rooftop & Vertical
Greening) 1)
Rooftop and vertical greening (vertical
building envelope) shall be implemented to increase the amenity value of the proposed
works, moderate temperature extremes and enhance building energy performance,
as well as visually improve the development. 2)
Vertical greening shall be implemented for the
lower portion of chimney (~20-25m high). |
Mitigation for
Visual Impacts |
|
MVC-01 |
Visual Mitigation and Aesthetic Design 1)
Recessive colour tone is proposed for the
façade of the ancillary facility buildings (e.g. incinerator plant) to blend
in with the nature. 2)
Architectural feature (e.g. light weight
aluminum structure) is incorporated with the tapered chimney of recessive
colour tone to diminish its “chimney like” appearance. 3)
Stone as a natural material is proposed at
the lower portion of the building façade and the chimney to compliment with
the surrounding environment. 4)
Change of material at different portions of
the building helps to reduce the bulkiness. 5)
Green roof structure (with irrigation and
drainage system) in curvilinear strips is proposed to cover the rectilinear
building bulk. Roof strips of different curvatures are further broken down to
echo with the contour of the hillside slope behind. |
MVC-02 |
Security floodlight for construction areas
shall be controlled at night to avoid excessive glare to the surrounding
receiver. |
MVC-03 |
The construction sequence and construction
programme shall be optimized in order to minimize the duration of impact. |
MVC-04 |
The backfilling materials for site
formation & construction materials / wastes on site shall be stored at a
maximum height of 2m and covered with an impermeable material of visually
un-obtrusive material (in earth tone). |
MVC-05 |
The number of
construction traffic to / from the project site shall be maintained to
practical minimum. |
During Operation Phase |
|
Mitigation for Landscape Impacts |
|
MLO-01 |
Planting Maintenance Proper planting maintenance and
replacement of defective plant species on the new planting areas to enhance
aesthetic and landscape quality shall be provided. |
Mitigation for Visual Impacts |
|
MVO-01 |
Environmental
Education Centre to Promote Waste Reduction An
|
MVO-02 |
Control
of Light The numbers of lights and their intensity shall be controlled to a level good enough to meet the safety requirements at night but not excessive. |
MVO-03 |
Control of
Operation Time The frequency
of waste transportation shall be minimized to practical minimum (e.g. limit
the reception of MSW from 8 am to 8 pm). |
10a.10.3 Residual Impact of Landscape Resources and Landscape Character Areas
10a.10.3.1 The residual impact of each LCA and LR regarding the significance threshold after mitigation is summarized in Table 10a.16.
Table 10a.16 Residual Impact of Identified Landscape Resources and Landscape Character Areas after Mitigation
I.D. no. |
LRs / LCAs |
Recommended Mitigation
Measures |
Residual Impact Significance Threshold after Mitigation |
|||
Construction |
Operation |
Construction |
Operation |
|||
Day 1 |
Year 10 |
|||||
Landscape Resource |
||||||
LR1 |
Ash Lagoon &
Trees |
MLVC-01, MLVC-02, MLVC-03, MLVC-04, MLVC-05, MLVC-06, MLVC-07, MLVC-08 |
MLO-01 |
Moderate |
Slight |
Slight |
LR2 |
Seashore |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR3 |
Tidal Stream |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR4 |
Woodland &
Shrubland |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR5 |
Vegetated Slope |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR6 |
Landfill |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR7 |
Seawater of Nim Wan |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR8 |
Factories |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR9 |
|
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
Landscape Character Area |
||||||
LCA1 |
Ash Lagoon |
MLVC-01,MLVC-02, MLVC-03, MLVC-04, MLVC-05,
MLVC-06, MLVC-07, MLVC-08 |
MLO-01 |
Moderate |
Slight |
Slight |
LCA2 |
Landfill Landscape |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LCA3 |
Abandoned Village |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LCA4 |
Barren |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LCA5 |
Inter-tidal Coast Landscape |
Nil |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
10a.10.4 Residual Impact of Visual Sensitive Receivers
10a.10.4.1
The residual impact of each VSR
regarding the significance threshold after mitigation is summarized in Table 10a.17.
Table 10a.17 Residual Impact of Identified Visual Sensitive Receivers after Mitigation
I.D. no. |
VSRs |
Recommended Mitigation
Measures |
Residual Impact Significance Threshold after Mitigation |
|||
Construction |
Operation |
Construction |
Operation |
|||
Day 1 |
Year 10 |
|||||
VSR1 |
Footpath Uphill |
MLVC-01, MLVC-02, MLVC-03, MLVC-04, MLVC-05,
MLVC-06, MLVC-07, MLVC-08, MVC-01, MVC-02, MVC-03, MVC-04, MVC-05 |
MVO-01, MVO-02, MVO-03, MLO-01 |
Slight / Moderate |
Slight / Moderate |
Slight |
VSR2 |
Nim Wan Road |
MVC-01, MVC-02 MVC-03 |
MVO-01, MVO-02 |
Insubstantial |
Insubstantial |
Insubstantial |
VSR3 |
Sludge Treatment Facilities |
MLVC-01, MLVC-02, MLVC-03, MLVC-04,
MLVC-05, MLVC-06, MLVC-07, MLVC-08, MVC-01, MVC-02, MVC-03, MVC-04, MVC-05 |
MVO-01, MVO-02, MVO-03, MLO-01 |
Slight / Moderate |
Slight / Moderate |
Slight |
VSR4 |
Sea of |
MLVC-01, MLVC-02, MLVC-03, MLVC-04,
MLVC-05, MLVC-06, MLVC-07, MLVC-08, MVC-01, MVC-02, MVC-03, MVC-04, MVC-05 |
MVO-01, MVO-02, MVO-03, MLO-01 |
Moderate / Substantial |
Moderate |
Slight / Moderate |
VSR5 |
Ha Pak Lai |
MLVC-01, MLVC-02, MLVC-03, MLVC-04,
MLVC-05, MLVC-08, MVC-01, MVC-02, MVC-03 |
MVO-01, MVO-02, MVO-03, MLO-01 |
Moderate |
Moderate |
Slight / Moderate |
VSR6 |
Black Point Power Station |
MVC-01, MVC-02 MVC-03 |
MVO-01, MVO-02 |
Insubstantial |
Insubstantial |
Insubstantial |
10a.10.5 Photomontages of Residual Impact of Visual Sensitive Receivers
10a.10.5.1
Table 10a.18 shows the visibility of the VSRs to the proposed works.
Photomontages for illustration are provided accordingly.
Table 10a.18 Visibility of Visual Sensitive Receivers to Proposed Works
I.D. no. |
VSRs |
Figure of Photomontage |
Visibility
of VSR to Proposed Works |
VSR1 |
Footpath Uphill |
· VSR1 has a full view of the proposed works without blockage. |
|
VSR2 |
Nim Wan Road |
Nil |
· VSR2’s view of the proposed works will be mostly blocked by the trees along the roadside. (As the proposed works will be barely seen by this VSR and the visual impact is insubstantial, the corresponding photomontages are not provided.) |
VSR3 |
Sludge Treatment Facilities |
· VSR3 has a full view of the proposed works without blockage. |
|
VSR4 |
Sea of |
· VSR4 has a full view of the proposed works without blockage. |
|
VSR5 |
Ha Pak Lai |
· VSR5 has a partial view of the proposed works. |
|
VSR6 |
Black Point Power Station |
Nil |
· VSR6’s view of the proposed works will be mostly blocked by the existing slope to the northeast of the VSR. (The Black Point Power Station is not accessible by the public. No suitable photo can be used to prepare the photomontages.) |
10a.11.1 Concurrent Projects near Project Site
10a.11.1.1 Table 10a.19 lists the concurrent projects in the vicinity of the project site.
Table 10a.19 Concurrent Projects in the Vicinity of TTAL Site
Concurrent
Projects |
Scope of Project |
WENT Landfill Extension |
· This project involves development
the WENT Landfill Extension (about 200 hectares with capacity of · The proposed WENT Landfill
Extension will be located to the west of the existing WENT Landfill. It will
occupy the West Lagoon and the southern part of the Middle and East Lagoon as
well as the area between the Black Point Power Station and the WENT Landfill. · The
WENT Landfill Extension will be developed in phases. The tentative commencement of the
construction works for Phase 1 is 2016/17. The proposed construction works will involve large-scale
excavation of soil, change in topography, construction of vehicular road
access, operation of large vehicles and machineries, and construction of the associated waste management
ancillary facilities. During the operation phase, waste will be spread and compacted after
loading from vehicles by waste moving equipment. Spoil mound will be formed from
the excavation of the main landfill bowl and will be stored to the Stockpile/
Borrow Area (SBA). Spoil will ultimately be returned to the landfill as daily
cover, formation of haul roads and intermediate/ final capping. After the final stage of the construction
and operation of the WENT Landfill Extension (tentative schedule to be 2028),
the restoration & aftercare phases will take place. The restoration & aftercare works
involve final cap construction, landscaping and treatment works within the
site to restore the site. · The
existing landscape resources and landscape characters to be affected by the
WENT Landfill Extension are mainly those of disturbed land associated with
the SBA and haul roads. The landscape value of the disturbed land is low and
its sensitivity is low too. Yet, it is noted that natural vegetation on the
hillside to the periphery of the SBA will the affected by the WENT Landfill
Extension. Some valuable LCAs (including Inter-tidal Coast Landscape, · In restoration and aftercare
phases, the WENT Landfill Extension will be restored and vegetated to
match with its surroundings in terms of landform and vegetation patterns. Loss of landscape
resources and change in landscape characters in construction & operation
phases will be compensated and enhanced. |
Sludge Treatment Facilities (STF) |
· The STF is designed to treat 2,000 wet tonnes/day of the dewatered sludge generated after the sewage treatment process by fluidized bed incineration technology. · The STF will be located in the northern part of the East Lagoon, adjacent to the TTAL site for the IWMF. · The construction commenced in 2010 for completion in 2013. The proposed construction works involve site clearance and formation, pilling works, construction of the incineration plant and ancillary facilities, roadwork, and utility installation. During operation phase, there will be presence of incineration plant and ancillary facilities, roadwork and land traffic for sludge transportation. ·
The development of STF will cause loss of some of the LR and LCA of ash
lagoon. The ash lagoon was formed for
storage of pulverized fuel ash (PFA) generated from the adjacent power
plants. The area is mostly covered with exposed ash, grasses, creepers, groundcovers,
shrubs and small trees. Some portions have become marshy with grasses and
water ponds. The affected trees in the site area are of low to medium amenity
value. The ash lagoon is an uncommon landscape in |
10a.11.2.1 Based on the current programmes of the concurrent projects (the IWMF, STF and WENT Landfill Extension), the construction of the STF commences first, followed by the construction of the IWMF and then by the construction of the WENT Landfill Extension. The construction phase of the IWMF will occur concurrently during the late construction phase and the operation phase of the STF and during the early construction phase of the WENT Landfill Extension. The operation phase of the IWMF will occur during the operation phase of the STF and the construction, operation, restoration and aftercare phases of the WENT Landfill Extension.
10a.11.2.2 The combined landscape impacts due to the construction and operation of the IWMF, STF and the WENT Landfill Extension include loss of LCAs (including the Ash Lagoon Landscape, Inter-tidal Coast Landscape, Upland and Hillside Landscape, Settled Valley Landscape, Coastal Upland and Hillside Landscape) and LRs (including ash lagoon, agricultural land, mangrove and swamp, shrubland, grassland, woodland and streams). The impacts will be in terms of permanent change and loss. The magnitude of change due to the construction and operation of the projects, especially the WENT Landfill Extension, is large, and the cumulative impact will be significant.
10a.11.2.3 The proposed mitigation measures during the construction and operation phases of the projects include:-
· WENT Landfill Extension: advanced screening tree planting, boundary green belt planting, temporary landscape treatment as green surface cover, existing tree preservation, etc.;
· STF: Re-use of topsoil in the construction of the soft landscape, existing trees preservation, transplanting of trees to adjacent locations, compensatory landscape planting, etc.; and
· IWMF: Grass-hydroseeded bare soil surface, provision of water pond as habitat for Little Grebe, existing trees preservation, transplanting of trees to adjacent locations, compensatory landscape planting, proper landscape design, reuse of existing boulders, greening design (rooftop & vertical greening), etc.
10a.11.2.4 Before the construction and operation of the WENT Landfill Extension, the cumulative impact of the IWMF and STF could be alleviated with the implementation of the proposed mitigation measures. With the landscape design of the IWMF being coherent with the adjacent STF, the development of the two facilities could be integrated and blend well in the surrounding landscape. The two developments would form a harmonic view. Besides, since the IWMF, STF and the existing Black Point Power Station, which is located near the project site, are industrial facilities of similar nature, the development of the IWMF is considered compatible with surrounding context.
10a.11.2.5 However, after the commencement of the construction and operation of the WENT Landfill Extension, the residual cumulative impact after implementation of the proposed mitigation measures will still be significant, considering the large-scale site formation, phase by phase in terms of site area, during the construction and operation of the WENT Landfill Extension.
10a.11.2.6 After the completion of the construction and operation phases of the WENT Landfill Extension, the restoration & aftercare phases of the WENT Landfill Extension will commence. Meanwhile, the IWMF and STF would be in Year 8 and Year 11 of the operation phase respectively. During the restoration phase of the WENT Landfill Extension, the mature advanced planting at the WENT Landfill Extension can act as screening effect for the WENT Landfill Extension in human eye level. During the aftercare phase of the WENT Landfill Extension, the compensatory planting at the WENT Landfill Extension will be under germination, providing preliminary vegetation cover for site area of the WENT Landfill Extension. At that time, the WENT Landfill Extension will become compatible with the surrounding IWMF and STF in which various landscape mitigation measures, such as landscape planting, green roof, vertical greening, have been implemented for a substantial period of time. The cumulative impact will be marginally acceptable with mitigation measures.
10a.11.2.7 After the whole period of restoration and aftercare phases of the WENT Landfill Extension, the impact due to the WENT Landfill Extension would be greatly mitigated by semi-mature compensatory woodland, shrubland and grassland with the proper mitigation maintenance, e.g. thinning of pioneer trees and enhancement planting of native tree species. The IWMF, STF and resorted WENT Landfill Extension would blend well and be merged as a whole. No significant residual cumulative impact is anticipated.
10a.12.1.1 During the construction phase, the impact to the landscape resources and landscape character areas would be “insubstantial”, except the Ash Lagoon (LR1 & LCA1). The impact to the Ash Lagoon (LR1 & LCA1) before mitigation would be “substantial”.
10a.12.1.2 During the operation phase, the proposed works has negligible impact to most of the landscape resources and landscape character areas, except the Ash Lagoon (LR1 & LCA1) where the project site locates. The impact to the Ash Lagoon would be “substantial”. Mitigation measures including proper landscape design blending the facilities into the surroundings, rooftop/vertical greening design, landscape treatment, provision of compensatory habitat for Little Grebe, etc. are anticipated to mitigate the landscape impact and enhance the overall landscape quality of the environment. The long-term residual impact to the Ash Lagoon would be reduced to “slight” in both day 1 and year 10 of operation.
10a.12.1.3 Surrounded by facilities of similar nature (e.g. STF, Black Point Power Station), the development of the IWMF at TTAL is considered compatible with the surrounding context. With the landscape design of the IWMF being coherent with the adjacent STF, the development of the two facilities could be integrated and blend well in the surrounding landscape. The two developments would form a harmonic view, and the cumulative landscape impact of the two developments would be alleviated. Another concurrent project is the WENT Landfill Extension. The construction phase of the IWMF will occur concurrently during the early construction phase of the WENT Landfill Extension while the operation phase of the IWMF will occur during the construction, operation, restoration and aftercare phases of the WENT Landfill Extension. The construction and operation of the WENT Landfill Extension will cause significant cumulative impact to the area due to large-scale site formation. During the restoration & aftercare phases of the WENT Landfill Extension, the IWMF and STF would be in Year 8 and Year 11 of the operation phase respectively. The mature advanced planting at the WENT Landfill Extension can act as screening effect for the WENT Landfill Extension, and the compensatory planting at the WENT Landfill Extension will be provide preliminary vegetation cover for site area of the WENT Landfill Extension. The WENT Landfill Extension will become compatible with the surrounding IWMF and STF in which various landscape mitigation measures, such as landscape planting, green roof, vertical greening, have been implemented for a substantial period of time. After the whole period of restoration and aftercare phases of the WENT Landfill Extension, the impact due to the WENT Landfill Extension would be greatly mitigated by semi-mature compensatory woodland, shrubland and grassland. The IWMF, STF and resorted WENT Landfill Extension would blend well and be merged as a whole. No significant residual cumulative impact is anticipated.
10a.12.2.1
The visual impact to most of
the visual sensitive receivers during the construction phase would be
“moderate”, and the visual impact to sea travellers of Deep Bay (VSR4) would be
“substantial”. After the implementation of the mitigation measures, the
residual impact to the sea travellers of
10a.12.2.2 The visual impact to most of the visual sensitive receivers during the operation phase would be “moderate”, and the visual impact to the residents/visitors of Ha Pak Lai (VSR5) and the sea travellers of Deep Bay (VSR4) would be “moderate/substantial” and “substantial” respectively. After the implementation of the proposed mitigation measures, the residual impact to most of the visual sensitive receivers would be reduced to “slight”, and the residual impact to the residents/visitors of Ha Pak Lai (VSR5) and the sea travellers of Deep Bay (VSR4) would be “slight/moderate” in year 10 of operation.
10a.12.2.3 Regarding the visual impacts during waste transportation / handling and its cumulative visual impacts, the impact is expected to be insignificant. During the operation stage, MSW will be contained in containers and transported to the berth of WENT Landfill from the Refuse Transfer Stations (RTSs) through marine transport. This is the current mode of transportation to transfer MSW from the RTSs to the WENT Landfill. After arriving berth of the WENT Landfill, the container will be transported to the IWMF by land transport and MSW will then be discharged from the containers to the bunker at the IWMF reception hall, which is enclosed in a covered building. The potential visual impact due to waste transportation / handling is anticipated to be minimal.
10a.12.2.4
As mentioned in Section 10a.12.1.3, the development of the IWMF at TTAL is surrounded by
facilities of similar
nature (e.g. STF, Black Point Power Station). The IWMF is considered compatible
with the surrounding context. With the architectural and landscape design of
the IWMF being coherent with the adjacent STF, the development of the two
facilities could be integrated and blend well in the surrounding landscape. The
two developments would form a harmonic view, and the cumulative visual impact
of the two developments would be alleviated.
10a.12.3 Overall Residual Impact
10a.12.3.1 In conclusion, the potential landscape and visual impacts can be effectively reduced by implementing the proposed mitigation measures during the construction and operation phases. With reference to criteria defined in Annex 10 of the EIAO TM, the overall residual impact is considered as “acceptable with mitigation measures” after implementing the mitigation measures.