1                         INTRODUCTION

1.1                    Background

1.1.1.1        The Project Proponent is the Electrical and Mechanical Services Department (EMSD) and the Works Agent is the Architectural Services Department (ArchSD).  Meinhardt Infrastructure & Environment Ltd (MIEL) was commissioned by the ArchSD as the Environmental Impact Assessment (EIA) Consultant to conduct the EIA study for this Project, which will be carried out in parallel with the design work. 

1.2                    The Assignment

1.2.1.1        This Project is to construct and operate a temporary vehicle workshop facility for around 5 years to replace the existing EMSD Hong Kong Workshop in Causeway Bay.  The site is located in a largely industrial area of Sheung On Street, Chai Wan but is in proximity to residential and institutional sensitive receivers.  The location plan of this Project is shown in Figure 1.1.  The site constitutes an area of previously developed reclaimed land which is currently unoccupied and covered in hardstanding, with some trees. 

1.2.1.2        The proposed EMSD Hong Kong Workshop will be a single storey building comprising various facilities for vehicle repair and maintenance operation as well as parking of vehicles when not in operation.  The facility will occupy a site area of about 2,080 m2 and the vehicle repair and maintenance areas will be covered by a steel shelter with a 5.2 m high clearance.  The rest of site will, also, be covered by hardstanding as part of the access road and parking bays.  A detailed description of the Project is provided in Section 3 of the EIA report.

1.2.1.3        This Project is a designated project under Item A.6, Part I, Schedule 2 of the EIAO: “A transport depot located less than 200 m from the nearest boundary of an existing or planned (a) residential area; (b) place of worship; (c) educational institution; or (d) health care institution” and requires an Environmental Impact Assessment (EIA) to be undertaken and an Environmental Permit (EP) to be obtained prior to construction commencement.  An application for the EIA Study Brief under section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by the EMSD on 13 June 2011 with a Project Profile (No. PP-442/2011).  The EIA Study Brief No. ESB-231/2011 was issued by the Environmental Protection Department (EPD) on 20 July 2011. 

1.3                    EIA Study Scope

1.3.1.1        The environmental issues covered in this EIA study and assessment areas, as specified in the EIA Study Brief (No. ESB-231/2011), are presented below:

·               Potential noise and air quality impacts from the construction and operation of the Project to sensitive receivers near the Project;

·               Potential water quality and sewerage impacts from the construction and operation of the Project;

·               Potential waste management implications and land contamination issues arising from the construction and operation of the Project;

·               Potential landscape and visual impacts during the construction and operation of the Project; and

·               Potential cumulative environmental impacts of the Project and associated works, through interaction or in combination with other existing, committed and planned projects in their vicinity, and that those impacts may have a bearing on the environmental acceptability of the Project.

1.4                    Purpose of this EM&A Manual

1.4.1.1        The purpose of this EM&A Manual is to guide the set-up of an EM&A programme to check the compliance with the recommendations of the EIA study for the EMSD Hong Kong Workshop, to assess the effectiveness of the mitigation measures recommended in the EIA report (the Implementation Schedule for Environmental Mitigation Measures (EMIS) is included in Appendix 1.1 of this EM&A Manual), and to identify any further requirements for additional mitigation measures and remedial action.  This EM&A Manual outlines the monitoring and audit programme for the Project.  It aims to provide systematic procedures for the monitoring, auditing and minimising of environmental impacts associated with the activities of the Project. 

1.4.1.2        All the environmental legislation of Hong Kong and the Hong Kong Planning Standards and Guidelines serve as the environmental standards and guidelines for the preparation of this EM&A Manual.  In addition, this EM&A Manual has been prepared in accordance with the requirements as stipulated in Annex 21 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

1.4.1.3        This EM&A Manual contains the following information:

·               The responsibilities of the Contractor, Engineer, Environmental Team (ET), and the Independent Environmental Checker (IEC) with respect to the EM&A requirements during the course of the Project;

·               The requirements with respect to the construction schedule and the EM&A programme to track the varying environmental impacts;

·               The details of methodologies to be adopted, including all field laboratories and analytical procedures, and details on the quality assurance and quality control (QA/QC) programme;

·               The rationale on which the environmental monitoring data will be evaluated and interpreted;

·               The definition of Action and Limit levels;

·               The establishment of Event and Action plans;

·               The requirements for reviewing the pollution sources and working procedures required in the event of the non-compliance with environmental criteria and complaints;

·               The requirements for the presentation of EM&A data and appropriate reporting procedures; and

·               The requirements for reviewing the EIA predictions and effectiveness of mitigation measures/environmental management systems and the EM&A programme. 

1.4.1.4        This EM&A Manual is a dynamic document that should be reviewed regularly and updated as necessary during the construction and operation of the Project.

1.5                    Project Programme

1.5.1.1        The construction programme of this Project is shown in Appendix 1.2, based on which this EIA was carried out.  The construction works are planned to be commenced in around August 2012 and completed in November 2013, upon which mobilisation and installation of the equipment will be carried out.  The anticipated operation will be commenced tentatively in February 2014 and completed in July 2017.

·               2012 August:               Commencement of construction works

·               2013 November:         Completion of construction works and mobilisation and installation of equipment

·               2014 February:            Commencement of operation of the Project

·               2017 July:                    Completion of operation of the Project

1.6                    Implementation Programme

1.6.1.1        According to the construction programme shown in Section 1.5 above, the EM&A programme of this Project would be implemented according to the following tentative schedule.  Details should refer to Sections 2-9. 

·               2012 July:                    Baseline monitoring (prior to the commencement of works)

·               2012 August:               Impact monitoring (throughout the construction period)

·               2013 November:         Ceasation and termination of EM&A programme (upon confirmation of substantial completion of the Project and no construction works would be carried out)

1.7                    Impact Prediction Review Procedures

1.7.1.1        The procedures for reviewing the impact prediction in the EIA study will include:

·               Specifying the requirements for submission of EM&A data, including monitoring and audit records;

·               Implementation of Event and Action Plans and follow-up action;

·               Listing all relevant environmental protection and pollution control legislation and the required licenses and permits;

·               Communication with regulators vis a vis offences under relevant environmental ordinances, prosecutions, etc;

·               Waste disposal documentation;

·               Incident reporting and investigations;

·               Resolution of public complaints;

·               Work programmes and methods including any variations to EIA predictions;

·               Design issues, including any variations to EIA predictions; and

·               Review of monitoring and audit criteria, etc. 

1.8                    Assessing Effectiveness of Environmental Management System, Practices and Procedures

1.8.1.1        The effectiveness of environmental management system, practices and procedures for the EM&A Programme should be assessed with reference to the following:

·               Effective monitoring environmental impacts and effectiveness of measures to mitigate its environmental impacts by specifying the environmental parameters and/or impact to be monitored (e.g. monitoring frequency, methodology, locations, equipment/instrumentation, Action/Limit levels to trigger corrective measures) and the auditing procedure and statistical validation of the impacts.

·               Effective auditing of the environmental performance by requiring

a)         Analysis and interpretation of all monitoring and any audit data, to assist in the prevention and mitigation of impacts on the environment;

b)         Examination of all available information related to the investigation of the nature, and causes of actual, potential and cumulative environmental impacts and complaints/queries; and

c)         Proposals for (i) remedial measures for the resolution of impacts; (ii) effective implementation of proposed mitigation measures; (iii) documentation and summary of audit findings; (iv) liaison and consultation of with the public and concerned groups on the effects of project works on the environment audit.

1.9                    Project Organisation

1.9.1              Background

1.9.1.1        The roles and responsibilities of various parties involved in the EM&A process and the organisational structure of the parties responsible for implementing the EM&A programme are outlined below.  The project organisation and lines of communication with respect to environmental protection works are shown in Figure 1.1.

1.9.2              The Engineer

1.9.2.1        The Engineer is responsible for overseeing the construction works and ensuring the works to be undertaken by the Contractor in accordance with the specifications and contractual requirements.  The duties and responsibilities of the Engineer with respect to the EM&A programme include:

·               To supervise the Contractor’s activities and ensure the requirements in the EM&A Manual to be fully complied with;

·               To inform the Contractor when action is required to reduce the environmental impacts in accordance with the Event and Action Plans;

·               To lead the regular site inspections and audits attended by the Contractor and Environmental Team (ET); and

·               To adhere to the procedures for carrying out the complaint investigation.

1.9.3              Contractor

1.9.3.1        The Contractor should report to the Engineer.  The duties and responsibilities of the Contractor are:

·               To implement the recommendations and requirements of the EIA study;

·               To provide assistance to the ET in carrying out the relevant environmental monitoring;

·               To submit the proposals of mitigation measures in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans;

·               To implement the mitigation measures to reduce the environmental impacts where the Action and Limit levels are exceeded until the events are resolved; and

·               To adhere to the procedures for carrying out the complaint investigation as required in the EM&A Manual. 

1.9.4              Environmental Team (ET)

1.9.4.1        The ET will conduct the EM&A programme to ensure the Contractor’s compliance with the Project’s environmental requirements during the construction phase. 

1.9.4.2        The ET should be led and managed by an Environmental Team Leader (ETL), who should possess at least 7 years of experience in EM&A.  The ET should monitor the mitigation measures implemented by the Contractor on a regular basis to ensure the compliance with the intended aims of the mitigation measures.  The duties and responsibilities of the ET are:

·               To monitor various environmental parameters as required in the EM&A Manual;

·               To carry out site inspections to investigate and audit the Contractor’s site practices, equipment and work methodologies with respect to the pollution control and environmental mitigation, and anticipate the environmental issues for the proactive and practicable action before problems arising;

·               To analyse the EM&A data, review the success of EM&A programme to confirm the adequacy of mitigation measures implemented, and the validity of the EIA predictions and to identify any adverse environmental impacts arising and report the EM&A results to the Independent Environmental Checker (IEC), Contractor, and Engineer;

·               To prepare the reports of environmental monitoring data and site environmental conditions; and

·               To review the proposals of mitigation measures by the Contractor in case of exceedances of the Action and Limit levels, in accordance with the Event and Action Plans.

1.9.5              Independent Environmental Checker (IEC)

1.9.5.1        The IEC should advise the Engineer on the environmental issues related to the Project.  The IEC should possess at least 7 years of experience in EM&A.  The duties and responsibilities of the IEC are:

·               To review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;

·               To validate and confirm the accuracy of the monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers;

·               To carry out random sample checking and audit of the environmental monitoring data and sampling procedures, etc;

·               To conduct random site inspections during construction;

·               To audit the recommendations and requirements of the EIA study against the status of the implementation of environmental protection measures on-site;

·               To review the effectiveness of the environmental mitigation measures and environmental performance of the Project;

·               On as-needed basis, to verify and certify the environmental acceptability of the Environmental Permit (EP) holder’s construction methodology (both temporary and permanent works), relevant design plans and submissions under the EP;

·               To verify the investigation results of the environmental complaints and the effectiveness of corrective measures;

·               To verify the EM&A reports that have been certified by the ETL; and

·               To provide feedback of the audit results to the ET/EP holder according to the Event and Action Plans in the EM&A manual.

1.10                Structure of this EM&A Manual

1.10.1.1    Following this introductory section, the remainder of the EM&A Manual is set out as follows:

·               Section 2 sets out EM&A requirements for noise;

·               Section 3 sets out EM&A requirements for air quality;

·               Section 4 sets out EM&A requirements for water quality;

·               Section 5 details auditing requirements for waste management implication and land contamination;

·               Section 6 details auditing requirements for landscape and visual impact;

·               Section 7 describes the scope and frequency of the environmental site audits and sets out the general requirements of the EM&A programme; and

·               Section 8 details the EM&A reporting requirements; and

·               Section 9 describes the termination of the EM&A programme.