4                        Noise impact assessment

4.1                   Background

4.1.1.1       Potential construction phase air-borne noise impacts may be generated as a result of the use of powered mechanical equipment (PME) for various construction activities including site formation, cut and cover works, construction of jacking and receiving pits, and formation of intakes and outfalls, as detailed in Section 2 of this report.  Further details of the construction activities, programme and equipment requirements are provided in Section 4.7 below.  No operational noise impacts would be anticipated for this project and have, therefore, not been considered further.

4.2                   Environmental Legislation, Standards and Guidelines

4.2.1             Noise Control Ordinance and Technical Memoranda

4.2.1.1       The Noise Control Ordinance (NCO) and the EIAO provide the statutory framework for noise control.  Assessment procedures and standards relevant to this project are set out in the Technical Memoranda (TM) given below.

·                The TM on Environmental Impact Assessment Process (EIAO-TM);

·                The TM on Noise from Construction Work other than Percussive Piling (GW-TM); and

·                The TM on Noise from Construction Work in Designated Areas (DA-TM).

4.2.1.2       No percussive piling is proposed for the project and as such the Technical Memorandum on Noise from Percussive Piling will not be relevant to the noise assessment and is not discussed further.  Notwithstanding, percussive piling is prohibited at any time on Sundays and public holidays and during the weekday evening and night-time hours (1900-0700hrs, Monday through Saturday) and a Construction Noise Permit (CNP) would be required from the Environmental Protection Department (EPD) if such works were eventually needed.

4.2.2             Noise Standards for Non-restricted Hours

4.2.2.1       Daytime construction noise (excluding percussive piling) between the hours of 0700 and 1900 on weekdays, that is, non-restricted or normal working hours, is governed by the EIAO-TM.  Annex 5 of the EIAO-TM sets out the construction noise assessment limits, which are Leq(30 min) 75dB(A) for domestic premises and hotels, and Leq(30 min) 70dB(A) for educational institutions including kindergartens (or 65dB(A) during examination periods), nurseries and all other places where unaided voice communication is required.  The recommended noise standards are summarised in Table 4.1 below.

Table 4.1      Daytime Construction Noise Limits

Uses

Noise Standard,

Leq, 30 min dB(A)

Domestic premises, hotels and hostels

75

Educational institutions, kindergartens, nurseries and all others where voice communication is required

70

(65 during examination period)

Note:     The above criteria apply to noise sensitive uses which rely on open window for ventilation and should be viewed as the maximum permissible noise levels assessed at 1m from the external façade.

4.2.3             Noise Standards for Restricted Hours

4.2.3.1       During restricted works periods between 1900 and 0700 hours from Monday to Saturday and at any time on Sundays or public holidays, activities involving the use of PME for the purpose of carrying out construction work is prohibited unless a Construction Noise Permit (CNP) has been obtained.

4.2.3.2       The GW-TM provides details of the procedures adopted by the EPD for assessing such applications.  The granting of a CNP is subject to the conditions as stated in the CNP, which may be revoked at any time for failure to comply with the permit conditions.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the Noise Sensitive Receivers (NSRs).  ANLs are assigned depending on the Area Sensitivity Ratings (ASRs) of the study area.  The ANLs for construction works in a “Designated Area” (controlled by the DA-TM) are more stringent than those given in the TM-GW.

4.2.3.3       Under the DA-TM, the use of five types of Specified Powered Mechanical Equipment (SPME), namely hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker, and undertaking three types of Prescribed Construction Works (PCW) within a designated area during restricted hours would require a valid CNP.  The PCW are:

·                Erecting or dismantling of formwork or scaffolding;

·                Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and

·                Hammering.

4.2.3.4       In general, it cannot be presumed that a CNP would be granted for carrying out PCW within a designated area during restricted hours but it may be granted if the relevant ANLs and criteria stipulated in the GW-TM and DA-TM can be met.

4.2.3.5       As defined in the latest Noise Control Designated Area Plan (Plan No. EPD/AN/NT-05), the eastern part of the project area is within the Designated Area.  The corresponding basic noise levels (BNLs) for evening and night-time periods are given in Table 4.2 and the figures in brackets for designated areas would apply to this area.

Table 4.2      Construction Noise Criteria for Activities other than Percussive Piling

Time Period

Basic Noise Levels (BNLs), dB(A)

ASR ‘A’

ASR ‘B’

ASR ‘C’

Evening (1900 to 2300 hrs)[a]

60 (45)

65 (50)

70 (55)

Night-time (2300 to 0700 hrs)

 

45 (30)

50 (35)

55 (40)

NOTE:

[a]          Includes Sunday and Public Holidays during daytime and evening.

               Figures in brackets are BNLs for Specified Powered Mechanical Equipment (SPME) construction work in designated areas.

4.2.3.6       As noise in restricted periods is covered by the NCO, it is not assessed further in this EIA Report under the EIAO and despite any reference made in this EIA Report to construction noise aspects during restricted periods, there is no guarantee that a CNP will be issued for the project construction.  The Noise Control Authority will consider a well justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TM issued under the Noise Control Ordinance.  The Noise Control Authority will take into account contemporary conditions/situation of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in the EIA Report shall bind the Noise Control Authority in making his decision.  If a CNP is to be issued, the Noise Control Authority shall include in it any condition seen fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

4.2.3.7       According to the construction programme detailed in Figure 2.8b, all the proposed construction works are, however, expected to be carried out during non-restricted hours.  In case of any construction activities during restricted hours, it will be the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs.  The Contractor will be required to submit a CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.

4.3                   Noise Sensitive Receivers

4.3.1.1       NSRs have been identified in accordance with Annex 13 of the EIAO-TM which can included domestic premises, temporary housing accommodation, educational institutions, nurseries, hospitals, medical clinics, homes for the aged, convalescent homes, places of public worship, libraries, courts of law, performing arts centres, auditoria, amphitheatres, hostels and country parks.  Noise sensitive receivers present within the 300m study area boundary have been identified.

4.3.1.2       The construction sites are located to the northern side of the Po Lin Monastery, northwest of the Po Lin Monastery near Lin Ping Drive and to the north of the Ngong Ping 360 Terminal and Columbarium.  The existing NSRs selected as representative for both the construction noise assessment are listed in Table 4.3 and illustrated in Figure 4.1 - 4.3.  The details of the NSRs are presented in Appendix C1.

Table 4.3      Representative Noise Sensitive Receivers

NSR (1)

Location

Type

No. of Storeys

Minimum Source-Receiver Slant Distance (m)*

NSR1

Columbarium of Po Lin Monastery

Place of public worship

1

18.7

NSR3

Village House No. 68

Residential

2

40.8

NSR4

Village House No. 65

Residential

2

30.8

NSR5

Village House No. 49A

Residential

1

6.5

NSR6(2)

Village House No. 40

Residential

2

24.5

NSR7

Luen Sin Tong

Place of public worship

2

35.5

NSR8

Village House No. 34

Residential

2

26.3

NSR9

Village House

Residential

2

25.7

NSR11(3)

Po Lin Monastery

Place of Public Worship

1

35.9

Notes:

*            Slant distance is the distance from the SR to the location of the PMEs in the nearest works area.  Refer to Appendix C2 for the locations of the notional sources.        

(1)          The numbering of the NSRs is consistent with that of the ASRs in Section 3 of this EIA Report.  SR2 and SR10 are shopping centre and kitchen of the Po Lin Monastery, respectively and, therefore, do not constitute an NSR for this assessment and as such, no NSR2 or NSR10 has been  included in this assessment.

(2)         NSR6 is an abandoned village house but is the closest property to the proposed construction works among the cluster of village houses in this area.  It also offers shielding to 3 village houses behind it.  It has, therefore, been selected to represent the NSRs in this area as a worst case as it would be the worst affected location. 

(3)       NSR11 is the kitchen house of Po Lin Monastery and would normally not be considered as an NSR.  However, it is selected to represent the closest occupied building of the Monastery that would be the worst affected by the construction works. 

4.3.1.3       The photos of the NSRs are also provided in Appendix C1.

4.4                   Existing Conditions

4.4.1.1       The project site is located in a rural area and the surrounding land uses comprise village type development, government or community use such as Po Lin Monastery, with the majority of the area being green belt and Country Park.  The major noise sources would be expected from commercial activities associated with the road access to the village and the Po Lin Monastery and the Ngong Ping 360 cable car.

4.4.1.2       Relevant studies of the baseline noise levels in the Ngong Ping area include the “Outlying Islands Sewerage Stage 1 Phase 1 Ngong Ping Sewage Treatment Works and Sewerage EIA” (EIA Register No. EIA-079/2002), which reported that the prevailing background noise levels in this area ranged from 48dB(A) to 62dB(A) and 45dB(A) to 54dB(A) during the daytime/evening and nighttime respectively. Traffic noise from Ngong Ping Road was determined to be a dominant background noise source, in addition to the loudspeaker announcement by the Po Lin Monastery.

4.5                   Identification of Potential Noise Impacts

4.5.1.1       The potential sources of noise impact during the construction phase of the Project would be the use of PME for various construction activities.  According to the construction programme in Figure 2.8b, the construction of the project would tentatively start in August 2013 and last for about 30 months.  There are seven major construction activities to be carried out which are relevant to the construction noise assessment, as follows:

·                Activity 1: Site formation works (All works areas with Project Area);

·                Activities 2: Construction of Site Office (SO);

·                Activities 3 and 4: Construction of drainage pipelines (Work Sections 1 and 3, Figure 2.9a) and box culverts (Work Sections 4 and 5, Figure 2.9a) using the cut and cover method with stockpiling activities at the stockpile areas (SA1, SO, SA2, SA3 and SA4);

·                Activity 5: Construction of jacking pits (JP1 and JP2, Figure 2.9a) and receiving pits (RP1, RP2, RP3 and RP4, Figure 2.9a) and including mucking-out activities at jacking pits (JP1 and JP2) for the pipe-jacking process in Work Sections 2 and 6; and

·                Activity 6: Construction of manholes, intakes and outfalls (SA1, SA2, SA3, WA3, WA4).

·                Activity 7: Demolition of Site Office (SO) with associated road reinstatement and landscaping works.

4.5.1.2       For the pipe jacking, as the jacking system would be located at the bottom of the pit which is about 6m below ground level, the noise of the jacking machine would be effectively shielded from the sensitive receivers.  Thus, it would not be considered as a potential noise impact during the construction phase.  However, other PMEs such as air compressor, lorry and mobile crane, etc., which would be required for the pipe jacking process would be at ground level and these would be considered as potential noise sources in the noise assessment.

4.6                   Concurrent Projects

4.6.1.1       There are no concurrent projects identified that would have the potential to result in cumulative noise impacts at the NSRs during the same construction period of the Project.

4.7                   Assessment Approach and Assumptions

4.7.1             General Approach

4.7.1.1       In accordance with the EIAO-TM, the methodology outlined in the GW-TM has been used for the construction noise assessment.  The general approach is summarised below:

·                Locate the NSRs which would most likely be affected by the noise from construction works;

·                Determine the items of PME for each discrete construction activity, based on the available information or agreed plant inventories;

·                Assign sound power levels (SWLs) to the proposed PME according to the GW-TM or other sources;

·                Calculate the distance attenuation and screening effects to NSRs from the noise source;

·                Predict the construction noise levels at NSRs in the absence of any mitigation measures; and

·                Include a 3dB(A) façade correction to the predicted noise levels in order to account for the façade effect at each NSR.

4.7.2             Plant Inventory

4.7.2.1       Groups of PME have been assigned to various construction activities of the project and the full plant inventory is presented in Appendix C3.  The key PME to be used for the construction works activities are shown in Table 4.4 below.  The Project Proponent has confirmed this plant inventory as being practical and adequate for completing the construction works within the scheduled timeframe and the is presented in Appendix B1.  The plant inventory has been provided as one option which is considered technically feasible and represents a realistic worst-case scenario for assessment purposes in this EIA.

4.7.2.2       The on-time of each piece of equipment has been estimated with the reference of EIAO-GN 9/2004 to reflect the actual situation and is considered practicable and the percentages of time have been considered when calculating the cumulative Sound Power Levels (SWL) for the construction activities.

Table 4.4      PME Identified as Major Noise Sources for the Unmitigated Scenario

ID

PME

CNP

No. of Item

SWL, dB(A)

% on time

Total SWL, dB(A)

1

Activity 1 - Site Clearance

1a

Felling of Trees

Saw, Chain, Hand-Held

CNP 202

1

114

50%

111

1b

Removal of Trees

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

114

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

2

Activity 2 – Construction of Site Office

Concrete Lorry Mixer

CNP 044

1

109

50%

112

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

3

Activity 3 – Laying of Pipe by Open-cut Method

3a

Excavation and installation of earth lateral support system

3a-1

Excavation and installation of earth lateral support system – Excavation

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

111

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

3a-2

Excavation and installation of earth lateral support system - Sheet Piling

Piling, vibrating hammer

CNP 172

1

115

50%

112

3a-3

Excavation and installation of earth lateral support system - Delivery of Precast Elements

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

100

3a-4

Excavation and installation of earth lateral support system – Generators and Pumps

Water Pump (Electric)

CNP 281

1

88

50%

100

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

3b

Laying of pipe

Crane, Mobile/Barge Mounted (diesel)

CNP 048

1

112

70%

111

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

Water Pump (Electric)

CNP 281

1

88

50%

Winch (Electric)

CNP 262

1

95

50%

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

3c

Backfilling the trench

3c-1

Backfilling the trench – Filling

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

114

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

3c-2

Backfilling the trench – Compacting

Compactor, Vibratory

CNP 050

1

105

50%

102

3d

Reinstatement of original pavement

Concrete Lorry Mixer

CNP 044

1

109

50%

112

Poker, Vibratory, Hand-held

CNP 170

1

113

50%

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

4

Activity 4 – Construction of Box-culvert

4a

Excavation and installation of earth lateral support system

4a-1

Excavation and installation of earth lateral support system – Excavation

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

111

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

4a-2

Excavation and installation of earth lateral support system – Sheet Piling

Piling, vibrating hammer

CNP 172

1

115

50%

112

4a-3

Excavation and installation of earth lateral support system - Delivery of Precast Elements

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

100

4a-4

Excavation and installation of earth lateral support system – Generators and Pumps

Water Pump (Electric)

CNP 281

1

88

50%

100

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

4b

Erection of formwork, steel fixing and concreting

4b-1

Erection of formwork

Saw, Circular, Wood

CNP 201

1

108

50%

105

Water Pump (Electric)

CNP 281

1

88

50%

4b-2

Steel fixing

Bar Bender and Cutter (Electric)

CNP 021

1

90

80%

90

Water Pump (Electric)

CNP 281

1

88

50%

4b-3

Concreting

Concrete Lorry Mixer

CNP 044

1

109

50%

114

Crane, Mobile/Barge Mounted (diesel)

CNP 048

1

112

70%

Poker, Vibratory, Hand-held

CNP 170

1

113

50%

Water Pump (Electric)

CNP 281

1

88

50%

4c

Backfilling the trench

4c-1

Backfilling the trench – Filling

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

114

Excavator/Loader, Wheeled/Tracked

CNP 081

1

112

70%

4c-2

Backfilling the trench – Compacting

Compactor, Vibratory

CNP 050

1

105

50%

102

4d

Reinstatement of original pavement

Concrete Lorry Mixer

CNP 044

1

109

50%

112

Poker, Vibratory, Hand-held

CNP 170

1

113

50%

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

5

Activity 5 – Laying of Pipe by Pipe-jacking Method

5a

Construction of jacking pits

5a-1

Construction of jacking pits – Excavation

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

122

70%

120

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

5a-2

Construction of jacking pits - Delivery of Precast Elements

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

100

5a-3

Construction of jacking pits - Generators and Pumps

Water Pump (Electric)

CNP 281

1

88

50%

101

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

Air blower (electric)

CNP 006

1

95

50%

5b

Pipe jacking

Crane, Mobile/Barge Mounted (diesel)

CNP 048

1

112

70%

111

Winch (Electric)

CNP 262

1

95

50%

Grout mixer

CNP 105

1

90

80%

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

Pipe jacking machine*

No Noise Impact

1

 

--

Grout pump

CNP 106

1

 

--

Tunnel boring machine*

No Noise Impact

1

 

--

5c

Construction of receiving pits

5c-1

Construction of receiving pits – Excavation

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

122

70%

120

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

5c-2

Construction of receiving pits – Delivery of Precast Elements

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

100

5c-3

Construction of receiving pits – Generators and Pumps

Water Pump (Electric)

CNP 281

1

88

50%

101

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

Air blower (electric)

CNP 006

1

95

50%

5d

Backfilling the pits

5d-1

Backfilling the pits – Filling

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

114

Excavator/Loader, Wheeled/Tracked**

CNP 081

1

112

70%

5d-2

Backfilling the pits – Compacting

Compactor, Vibratory

CNP 050

1

105

50%

102

6

Activity 6 – Construction of Manholes, Inlet and Outfall Structures

6a

Excavation

6a-1

Excavation – Rock Breaking

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

122

70%

120

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

6a-2

Excavation – Spoil Delivery

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

114

Excavator/Loader, Wheeled/Tracked**

CNP 081

1

112

70%

6a-3

Excavation – Generators and Pumps

Water Pump (Electric)

CNP 281

1

88

50%

100

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100

100%

6b

Erection of formwork, steel fixing and concreting

6b-1

Erection of formwork

Saw, Circular, Wood

CNP 201

1

108

50%

105

Water Pump (Electric)

CNP 281

1

88

50%

6b-2

Steel fixing

Bar Bender and Cutter (Electric)

CNP 021

1

90

80%

90

Water Pump (Electric)

CNP 281

1

88

50%

6b-3

Concreting

Concrete Lorry Mixer

CNP 044

1

109

50%

114

Crane, Mobile/Barge Mounted (diesel)

CNP 048

1

112

70%

Poker, Vibratory, Hand-held

CNP 170

1

113

50%

Water Pump (Electric)

CNP 281

1

88

50%

6c

Backfilling

6c-1

Backfilling – Filling

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

114

Excavator/Loader, Wheeled/Tracked**

CNP 081

1

112

70%

6c-2

Backfilling – Compacting

 

Compactor, Vibratory

CNP 050

1

105

50%

102

7

Activity 7 – Demolition of Site Office with associated road reinstatement work and landscaping works

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

122

70%

121

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

117

30%

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

105

30%

Note:

*            Pipe jacking system, grout pump and tunnel boring machine would be located at the bottom of the pit which is about 6m below ground level.  The noise of the machines would be effectively shielded from the sensitive receivers and thus would not be considered as a potential noise source in the construction noise assessment.

**         For the construction of RP4 and Outfall B at WA4 (task ID 5 and 6), a mini excavator (CNP 082) with SWL in 94 dB(A) will be used instead of the normal excavator (CNP 081) due to lack of space near the works area and access constraints

4.7.2.3       The SWLs of the PME have been taken from Table 3 of the GW-TM.  Where no SWLs are provided for individual PME in the GW-TM, reference has been made to the British Standard 5228: Part 1:2009 Noise Control on Construction and Open Sites, previous similar studies or from other EIA reports or measurements taken in other relevant studies.

4.7.2.4       The proposed plant inventory involves the use of some SPME, as detailed in Section 4.2.3.3, including dump trucks and hand-held vibratory pokers.  As such, should construction works extend into restricted hours, the DA-TM will become effective and further restrictions on the acceptable noise will be imposed.

4.7.3             Construction Sequence

4.7.3.1       As detailed in Section 2.7.3 the works will be undertaken based upon two active work fronts, one for the cut and cover (C&C) works of the drainage pipeline and box culvert and another one for the trenchless drain constructions, after site clearance and the site office (SO) establishment.  The details of construction sequence and the location of the Works Sections can refer to Section 2.7.3 and Figure 2.9a of the report respectively.  

4.7.3.2       For the construction works of the pipeline and the box culvert by cut and cover, it is assumed that the works would be conducted section by section in the specific timeframe according to the construction programme in Figure 2.8b, with each section being approximately 40m in length and taking 2 months to construct.

4.7.4             Assessment Assumptions

4.7.4.1       With reference to Table 4.4 above, for Activity 1, during the tree felling removal activities, the excavator and dump truck would not be operating.  Therefore, the sub-task Activity 1b with the highest SWL of 114dB(A) has been adopted in the unmitigated noise assessment as a worst case scenario.  A similar approach has been adopted for Activity 3, Construction of Pipeline by Cut and Cover Method, with the sub-task Activity 3c with highest SWL of 114dB(A) being adopted in the noise assessment as a worst case scenario as sub-tasks 3a to 3d will not be conducted concurrently during the open cut works area.  Similarly, for Activity 4 for the construction of the box culvert the highest SWL being 114dB(A).  For Activity 6, the construction of Intake C and Outfall B will not be undertaken at the same time and will be constructed one after the other between Months 16 - 18.  Therefore, depending upon the location of the NSR, the task closer to the NSR, that is, with the highest SWL of 120dB(A), has been adopted in the noise assessment.  For example, the total SWL of the PME required for the construction of Outfall B has been adopted in the noise assessment of NSR1. 

4.7.4.2       For the construction of RP4 and Outfall B involving the Construction of Receiving Pits and Outfall Structures (Tasks ID 5 and 6), a mini robot mounted excavator (CNP 082) will be used instead of the normal excavator as a result of site constraints associated with the lack of working space and access near the works area.  The specific plant inventory for construction works at RP4 / Outfall B is given in Table 4.5.

Table 4.5      Specific Plant Inventory for Construction Works at RP4 / Outfall B for the Unmitigated Scenario

ID

PME

CNP

No. of Item

SWL, dB(A)

% on time

Total SWL, dB(A)

5

Activity 5 – Laying of Pipe by Pipe-jacking Method

5c+

Construction of receiving pits

5c-1

Construction of receiving pits – Excavation

 

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

70%

122

120

 

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

30%

105

 

5c-2

Construction of receiving pits - Delivery of Precast Elements

 

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

30%

105

100

5c-3

Construction of receiving pits - Generators and Pumps

 

Water Pump (Electric)

CNP 281

1

50%

88

101

 

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100%

100

 

 

Air blower (electric)

CNP 006

1

50%

95

 

5d+

Backfillig the pits

5d-1

Backfillig the pits – Filling

 

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

30%

117

112

 

Excavator, mini-robot mounted

CNP 082

1

70%

94

 

5d-2

Backfillig the pits – Compacting

 

Compactor, Vibratory

CNP 050

1

50%

105

102

6

Activity 6 – Construction of Manholes, Inlet and Outfall Structures

6a+

Excavation

6a-1

Excavation - Rock Breaking

 

Breaker, Excavator Mounted (Hydraulic)

CNP 028

1

70%

122

120

 

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

30%

105

 

6a-2

Excavation - Spoil Delivery

 

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

30%

117

112

 

Excavator, mini-robot mounted

CNP 082

1

70%

94

 

6a-3

Excavation - Generators and Pumps

 

Water Pump (Electric)

CNP 281

1

50%

88

100

 

Generator, Silenced, 75 dB(A) at 7m

CNP 102

1

100%

100

 

6b+

Erection of formwork, steel fixing and concreting

6b-1

Erection of formwork

 

Saw, Circular, Wood

CNP 201

1

50%

108

105

 

Water Pump (Electric)

CNP 281

1

50%

88

 

6b-2

Steel fixing

 

Bar Bender and Cutter (Electric)

CNP 021

1

80%

90

90

 

Water Pump (Electric)

CNP 281

1

50%

88

 

6b-3

Concreting

 

Concrete Lorry Mixer

CNP 044

1

50%

109

114

 

Crane, Mobile/Barge Mounted (diesel)

CNP 048

1

70%

112

 

 

Poker, Vibratory, Hand-held

CNP 170

1

50%

113

 

 

Water Pump (Electric)

CNP 281

1

50%

88

 

6c+

Backfilling

6c-1

Backfilling – Filling

 

Dump Truck, gross vehicle weight > 38 tonne

CNP 067

1

30%

117

112

 

Excavator, mini-robot mounted

CNP 082

1

70%

94

 

6c-2

Backfilling - Compacting

 

Compactor, Vibratory

CNP 050

1

50%

105

102

4.7.4.3       The noise levels at the ground floor of the receivers have been predicted as these are considered to represent a worst-case condition with the shortest distance between the SRs and the notional noise sources, and a 3dB(A) façade correction has been applied.  Appendix C2 shows the locations of the assumed notional sources of the PMEs in the noise assessment.

4.7.4.4       As noted above, as concurrent construction activities of various works elements could occur, the works within 300m from the sensitive receiver and within line of sight of the sensitive receiver is counted as cumulative impact for the worst case scenario.  Table 4.6 summarises the assumed worst case concurrent construction activities for each sensitive receiver with the distance between the SRs and the noise sources.

Table 4.6      Assumed Worst Concurrent Construction Activities for Each Sensitive Receiver

Notional Sources*

Slant Distances from NSRs (m)

NSR 1

NSR 3

NSR 4

NSR 5

NSR 6

NSR 7

NSR 8

NSR 9

NSR 11

Intake A (SA1) (Works Section 1)

--

--

--

--

--

226.2

--

132.0

117.2

Intake B (SA2) (Works Section 4)

--

193.9

172.4

90.1

202.1

--

274.2

--

--

Intake C (WA3) (Works Section 6)

183.3

--

--

--

--

--

--

--

--

Outfall A (SA3) (Works Section 5)

--

40.8

52.6

93.3

283.4

--

--

--

--

Outfall B (WA4) (Works Section 6)

18.7

--

--

--

--

--

--

--

--

JP 1 (SO)

(Works Section 2)

--

--

--

288.6

--

64.3

26.3

39.1

76.0

JP 2 (SA4)

(Works Section 6)

123.1

--

--

--

--

--

--

--

--

RP 1 (WA1)

(Works Section 1)

--

--

--

--

--

120.4

57.2

25.7

42.4

RP 2 (WA2)

(Works Section 2)

--

299.0

248.6

176.1

24.5

--

129.1

167.2

202.5

RP 3 (WA3)

(Works Section 2)

183.3

--

--

--

--

--

--

--

--

RP 4 (WA4)

(Works Section 6)

18.7

--

--

--

--

--

--

--

--

SO (SO)

(Works Section 2)

--

--

--

254.4

--

35.5

35.9

56.2

89.1

Section A1

(Works Section 1)

--

--

--

--

--

196.1

--

99.3

84.1

Section A2

(Works Section 1)

--

--

--

--

--

164.6

99.6

63.7

50.4

Section A3

(Works Section 1)

--

--

--

--

--

127.6

65.4

30.5

35.9

Section A4

(Works Section 3)

--

--

214.1

136.7

33.0

--

141.9

178.6

213.4

Section A5

(Works Section 3)

--

233.2

187.4

104.7

79.2

--

176.6

--

235.1

Section A6

(Works Section 3)

--

193.5

157.7

68.0

119.6

--

208.4

--

261.6

Section B1

(Works Section 4)

--

193.5

163.8

74.8

166.8

--

265.3

--

289.6

Section B2

(Works Section 5)

--

165.7

127.1

37.5

164.6

--

252.0

--

299.7

Section B3

(Works Section 5)

--

134.3

92.1

6.5

175.1

--

275.1

--

--

Section B4

(Works Section 5)

--

101.6

58.1

13.5

192.8

--

--

--

--

Section B5

(Works Section 5)

--

68.8

29.9

42.2

220.3

--

--

--

--

Section B6

(Works Section 5)

--

44.5

33.7

71.9

252.1

--

--

--

--

Note:

*            refer to Appendix C4 for the locations of the notional sources.  Reference in bracket refers to Works Areas as detailed in Table 2.13 or Works Sections detailed in Table 2.7.

“--“        denotes the works site is more than 300m from the NSR or no there is no line of sight from the NSR.

4.7.5             Level of Uncertainty

4.7.5.1       The predictions of construction noise impacts have been based on the methodologies described in the GW-TM under the NCO.  The methodologies which have previously been applied in other EIA studies are generally accepted for use in assessing construction noise impact against the EIAO-TM noise criteria.  In carrying out the assessment, realistic worst case assumptions have been made in order to provide a conservative assessment of potential noise impacts.  The construction noise impact has, therefore, been assessed based on conservative estimates for the types of plant to be utilised and the methods of working.

4.7.5.2       There are some limitations in the approach, such as the accuracy of predictive base data for future conditions, e.g. plant inventory for the proposed construction works.  Uncertainties in the assessment of impacts have been considered when drawing conclusions from the assessment and worst case assessments made overall.

4.8                   Construction Noise Assessment Results

4.8.1             Construction Noise Impact – Unmitigated Scenario

4.8.1.1       A summary of the predicted unmitigated maximum noise levels are provided in Table 4.7 below.  The details of the predicted unmitigated noise levels at the representative NSRs during each construction months are presented in Appendix C4.

Table 4.7      Predicted Unmitigated Construction Noise Levels for Representative NSRs

NSR

Location

Maximum Predicted Construction Noise Level, dB(A)

EIAO -TM Noise Criteria, dB(A)

NSR1

Columbarium of Po Lin Monastery

91

70

NSR3

Village House No. 68

83

75

NSR4

Village House No. 65

81

75

NSR5

Village House No. 49A

93

75

NSR6

Village House No. 40

88

75

NSR7

Luen Sin Tong

85

70

NSR8

Village House No. 34

88

75

NSR9

Village House

89

75

NSR11

Po Lin Monastery

84

70

 

Denotes exceedance of the noise criteria

 

4.8.1.2       The results indicate that the noise levels at all sensitive receivers will exceed the day-time noise criteria of 75dB(A) for the residential developments and 70dB(A) for the places of public worship during the construction activities for varying periods of time.  Based upon these results, noise mitigation measures will be necessary in a number of locations to reduce the noise to acceptable levels.

4.8.2             Mitigation Measures

4.8.2.1       One of the sources of exceedances is identified to be Activity 1 – Site Clearance.  This activity would be conducted along the whole alignment which will become very close to some NSRs (up to 6m).  However, removal of trees would require a top down approach and according to the tree survey conducted for the area, the trees scheduled to be felled are up to a maximum of 14m tall.  Thus, a noise barrier of a sufficient height to screen the high works when cutting at top sections of the trees would not be feasible.

4.8.2.2       Therefore, in order to mitigate the exceedances from the site clearance works, which is largely as a result of the use of the chain saw in close proximity to the NSRs, it is recommended that a quieter chain saw be used to mitigate the exceedances.  The chain saw can be replaced with an electric chain saw with a lower noise level to reduce the noise impact to the residents during tree felling.  A commonly available model, for example, the Husqvarna 316 Electric Chain Saw, has a rated maximum noise emission level of 103dB(A), which is 11dB(A) lower than the diesel powered chain saw previously assumed.  Such electricity powered chain saws will effectively reduce construction noise emissions during site clearance and, thus, an electric saw with a SWL of 103dB(A) or lower is recommended for use in Activity 1.  The brochure for the Husqvarna 316 Electric Chain Saw has been included in Appendix C5.

4.8.2.3       Use of other quiet equipment with lower SWL has been recommended to reduce the noise impacts for this Project.  The list of assumed quieter equipment, and their respective SWLs, is presented in Table 4.8 below.

Table 4.8      Mitigated Quiet PMEs

PME

Reference*

SWL, dB(A)

Tracked excavator fitted with hydraulic rock breaker

BS D8/13#

110

Concrete lorry mixer

BS D6/33

96

Tracked mobile crane (132kW, 55t)

BS C3/29

98

Dump Truck

BS D9/39

103

Tracked excavator (14t)

BS C2/7

98

Generator, Super Silenced, 70 dB(A) at 7m

CNP 103

95

Poker vibratory

BS C4/34

97

Hand Held Electric Circular Saw, 150mm Blade

BS D7/75

105

Electric Chain-Saw, Hand-held

Ref 1+

103

Water Pump, Submersible (Electric)

CNP 283

85

Note:

*            reference to the British Standard BS5228-1:2009 Code of practice for noise and vibration control on construction and open sites – Part 1: Noise.

+            Reference was made to Husqvarna Model 316 Electric Chain Saw, rated power being 1600W and guaranteed maximum noise emissions being 103dB(A) as provided by manufacturer.

#            Sheetpile installation would be part of the earth lateral support system.  An excavator with a mounted vibrating hammer, with a noise level similar to a breaker, would be used for this installation work.  Therefore, the assessment has been made with reference to an excavator mounted breaker.

4.8.2.4       Due to severe space constraints within the village, the installation of fixed temporary barriers of 2.5m high along the site boundary are not considered feasible for most of the areas as there is not sufficient space to provide the deep foundations needed to compensate for the wind loading that would occur on barriers of this height. 

4.8.2.5       In respect of WA4 which is adjacent to the Columbarium (NSR1), the Columbarium itself is surrounded by two solid boundary walls of about 2.5m high and about 200mm thick which are sufficient to act as a fixed barrier.  However, at intervals along the wall, vertical gaps in the wall are present which would reduce the attenuation properties of the boundary wall.  As such, it is recommended that, during the construction phase at WA4, the gaps in the wall, along the front edge of the Columbarium facing the works, be covered with acoustic fabric or small barrier sections to increase the screening to NSR1 from the noise during the construction of Outfall B and RP4.  A noise attenuation level of 10dB(A) for the PME, as detailed in Table 4.9 below, has been assumed for the upgraded Columbarium boundary wall.  It should be noted that the access gate to the facility will not be affected.  If acoustic fabric is not used, any barrier material should have a surface density of at least 10kg/m2.  Figure 4.4 shows the cross section between the construction works site and public in NSR1 demonstrating how the boundary wall can shield the public within the Columbarium from works at WA4.

Table 4.9      Noise Attenuation of PMEs from the Fixed Temporary Noise Barrier for NSR1

PME

Reduction Level (dB(A))

Tracked mobile crane (132kW, 55t)

10

Poker vibratory

10

Concrete lorry mixer

10

Hand Held Electric Circular Saw, 150mm Blade

10

Tracked excavator fitted with hydraulic rock breaker

10

Dump Truck

10

Air blower (electric)

10

Bar Bender and Cutter (Electric)

10

Compactor, Vibratory

10

Excavator, mini-robot mounted

10

Generator, Super Silenced, 70 dB(A) at 7m

10

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

10

Water Pump, Submersible (Electric)

10

 

4.8.2.6       As fixed temporary barriers along the works boundary are not feasible, with reference to the EIA Report of Kwun Tong Line Extension (AEIAR-154/2010), the following mitigation measures have been recommended to reduce the noise impacts from specific PMEs:

·                Use of mobile temporary noise barriers at individual movable and stationary PMEs.  The barriers should be about 2m high which considering the low rise residential sensitive receivers would be considered sufficient for screening purposes.  The barrier material shall have a surface density of at least 10kg/m2 to effectively provide noise screening.  With reference to EIAO Guidance Note No.9/2004, noise reductions of 5dB(A) and 10dB(A) can be achieved by direct application of the noise barriers to movable and stationary plant, respectively; and

·                Use of enclosures with covers at the top and three sides and a surface density of at least 10kg/m2 to screen noise from generally static noisy plant, such as air compressors.

4.8.2.7       Table 4.10 below summarises the mitigation measures to be adopted for PMEs being operated in all the works areas and the respective reductions in noise levels.

Table 4.10    Mitigation Measures and Assumed Effectiveness for PMEs

PME

Mitigation Measures

Reduction Level (dB(A))

Bar Bender and Cutter (Electric)

Noise Enclosure

10

Tracked excavator fitted with hydraulic rock breaker

Temporary Noise barrier

5

Tracked excavator (14t)

Temporary Noise barrier

5

Generator, Super Silenced, 70 dB(A) at 7m

Noise Enclosure

10

Hand Held Electric Circular Saw, 150mm Blade

Noise Enclosure

10

 

4.8.3             Construction Noise Impact – Mitigated Scenario

4.8.3.1       The mitigated sound power levels for the construction equipment are presented in Appendix C6.  After the implementation of the noise mitigation measures recommended above, the noise levels at NSR5 would still exceed the criteria.  Residual impacts of between 4-11dB(A) are predicted.  The details of the predicted noise levels at the NSRs with the implementation of the practicable mitigation measures detailed above during the construction works are presented in Appendix C7, with a summary provided in Table 4.11 below.

Table 4.11    Predicted Mitigated Construction Noise Levels and Duration at Representative NSRs

NSR

Range of Predicted Construction Noise Level, dB(A)

EIAO -TM Noise Criteria, dB(A)

Period Exceeding the Noise Standard

Remarks

NSR1

55 – 70

70

--

--

NSR3

50 – 71

75

--

--

NSR4

50 – 74

75

--

--

NSR5

48 – 86

75

Up to 1 week

Month 1:

Tree removal works with SPL of 79dB(A) to the NSR which will be affected for 2 – 3 days only.

 

Between Month 21 – 24:

Construction works for the box culvert (Activity 4) at Chainage B0+45 to B2+22

, with SPL of up to 86dB(A) to the NSR in these 3-4 days. 

NSR6

48 – 72

75

--

--

NSR7

50 – 70

70

--

--

NSR8

51 – 73

75

--

--

NSR9

52 – 73

75

--

--

NSR11

49 – 69

70

--

--

 

Denotes exceedance of the noise criteria

 

 

4.8.3.2       The NSR5 will be affected by the site clearance works in the first month.  It should be noted that site clearance works will apply to the whole alignment which is about 1km long in total and the clearance works as a whole would only last for 1 month.  Thus, in reality, the affected NSRs would suffer from exceedances from site clearance for 2 – 3 days only.  The exceedances at NSR 5 will be about 4 dB(A) but for this short duration only.  An electric chain saw has already been assumed and no further practical mitigation measures are considered to be available,

4.8.3.3       In addition to the exceedance from the site clearance works, the exceedance at NSR5 would, also, be related to the sheet piling works during the box culvert construction (Activity 4) between Chainages B0+45 to B2+22 between Months 21 and 24 (Works Section 5).  Further practicable mitigation measures, such as a fixed temporary noise barrier, have, therefore, been considered at this NSR to be implemented during this activity. 

4.8.3.4       The noise exceedance would only be induced during sheet piling works which is assumed to be carried out by a hydraulic breaker.  Calculations have showed that with the maximum SWL of Activity 4 being 107dB(A), NSR5 would suffer from exceedances only when construction works are carried out within 22m either side of the NSR.  Hence, the actual box-culvert works where exceedances would be anticipated would be for a total alignment length of about 44m only.  Sheet piling works within this particular 44m segment would take about 3 – 4 days only to complete.  The extent of the segment is shown in Figure 4.5.

4.8.3.5       Since NSR5 is a single storey village house, a fixed noise barrier of 3m in height can be installed between the NSR and the open cut trench along the 44m segment in order to further mitigate the construction noise impacts from the sheet piling work.  Other PMEs, such as excavator, and vibratory poker, would also benefit from the barrier.  The plant inventory assessed for Activity 4 (renumbered as Activity 4+ below) when construction works are in close proximity to NSR5 is given in Table 4.12 below and Appendix C6.  An illustration of the positioning of the barrier is given in Figure 4.6.

Table 4.12    Further Mitigated Plant Inventory for Activity 4+ with Additional Noise Barrier near NSR5

ID

PME

Ref

No of Item

% on time

SWL, dB(A)

Mitigation Measures and Attenuation

Total SWL, dB(A)

4+

Activity 4+ – Construction of Box-culvert with additional Noise Barrier

4a

Excavation and installation of earth lateral support system

4a-1

Excavation and installation of earth lateral support system - Excavation

 

Tracked excavator (14t)

BS C2/7

1

70%

98

Fixed Noise barrier

-5

100

 

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

30%

105

 

 

 

4a-2

Excavation and installation of earth lateral support system - Sheet Piling

Tracked excavator fitted with hydraulic rock breaker

BS D8/13

1

50%

110

Fixed Noise barrier

-5

102

4a-3

Excavation and installation of earth lateral support system - Delivery of Precast Elements

 

Lorry, 5.5 tonne < gross vehicle weight <= 38 tonne

CNP 145

1

30%

105

 

 

100

4a-4

Excavation and installation of earth lateral support system - Generators and Pumps

 

Water Pump, Submersible (Electric)

CNP 283

1

50%

85

Fixed Noise Barrier

-5

86

 

Generator, Super Silenced, 70 dB(A) at 7m

CNP 103

1

100%

95

Noise Enclosure

-10

 

4b

Erection of formwork, steel fixing and concreting

4b-1

Erection of formwork

 

Hand Held Electric Circular Saw, 150mm Blade

BS D7/75

1

50%

105

Noise Enclosure

-10

92

 

Water Pump, Submersible (Electric)

CNP 283

1

50%

85

Fixed Noise Barrier

-5

 

4b-2

Steel fixing

 

Bar Bender and Cutter (Electric)

CNP 021

1

80%

90

Noise Enclosure

-10

81

 

Water Pump, Submersible (Electric)

CNP 283

1

50%

85

Fixed Noise Barrier

-5

 

4b-3

Concreting

 

Concrete lorry mixer

BS D6/33

1

50%

96

 

 

96

 

Tracked mobile crane (132kW, 55t)

BS C3/29

1

70%

98

Fixed Noise Barrier

-5

 

 

Poker vibratory

BS C4/34

1

50%

97

Fixed Noise barrier

-5

 

 

Water Pump, Submersible (Electric)

CNP 283

1

50%

85

Fixed Noise Barrier

-5

 

4c

Backfilling the trench

4c-1

Backfilling the trench - Filling

 

Dump Truck

BS D9/39

1

30%

103

 

 

99

 

Tracked excavator (14t)

BS C2/7

1

70%

98

Fixed Noise barrier

-5

 

4c-2

Backfilling the trench - Compacting

 

Compactor, Vibratory

CNP 050

1

50%

105

Fixed Noise barrier

-5

97

4d

Reinstatement of original pavement

 

Concrete lorry mixer

BS D6/33

1

50%

96

 

 

95

 

Poker vibratory

BS C4/34

1

50%

97

Fixed Noise barrier

-5

 

 

Generator, Super Silenced, 70 dB(A) at 7m

CNP 103

1

100%

95

Noise Enclosure

-10

 

 

4.8.3.6       With the additional noise barrier, the construction noise impacts at NSR5 are further mitigated to 81dB(A) at the worst case separation distance of 6m only and exceedances would not be anticipated until construction works are carried out within 13m of NSR5, representing a segment of about 24m, as shown in Figure 4.5.  The construction works within the 13m zone would be undertaken in about 3 days and, therefore, the exceedance duration is also reduced.  Table 4.13 below shows the calculation of noise impact at different separation distances from NSR5 with (Activity 4+) and without (Activity 4) the proposed noise barrier.

Table 4.13    Further Mitigated Scenario for NSR5

Activity ID

Activity SWL, dB(A)

Separation Distance, m

Distance Attenuation, dB(A)

Noise Impact at NSR5

Activity 4

107

22

-32

75

13

-27

80

10

-25

82

6

-21

86

Activity 4+

102

22

-32

70

13

-27

75

10

-25

77

6

-21

81

 

4.8.3.7       Notwithstanding the above measures, good site practices are, also, recommended to reduce noise levels as far as possible.  These measures include the following:

·                Only well-maintained plant should be operated on-site and PME should be serviced regularly during the construction programme;

·                Silencers or mufflers on construction equipment should be utilised and properly maintained throughout the construction programme;

·                Any mobile PME should be sited as far from NSRs as possible;

·                Machines and PME that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·                PME known to emit noise strongly in one direction should be orientated to direct away from the nearby NSRs;

·                Material stockpiles and other structures should be effectively utilised, wherever practicable, in screening noise from on-site construction activities;

·                Use of acoustic enclosure, in accordance with EPD’s A Practical Guide for the Reduction of Noise from Construction Works; and

·                Re-scheduling of works should be considered to ameliorate the residual impact.

4.8.3.8       Given that the recommended measures have been tried and tested and previously implemented on construction sites in Hong Kong, the level of uncertainty of the effective implementation of the mitigation measures would be small. Notwithstanding, the EM&A programme will be implemented to ensure all mitigation measures are effective.

4.9                   Cumulative Impacts

4.9.1.1       As discussed in Section 2, there are no known concurrent projects in the Study Area that may cause cumulative impacts with the Project.

4.10               Residual Impacts

4.10.1.1   The residual impacts refer to the net impacts after mitigation, taking into account the background environmental conditions and the impacts from existing, committed and planned projects.  Residual impacts associated with the construction have been assessed but no quantification of residual impacts is required.

4.10.1.2   Although all practicable mitigation measures have been applied, NSR5 will still be subject to residual impacts of up to 6dB(A) for a maximum duration of about 1 week. NSR5 will be affected by the site clearance works for a few days, and will be further affected by Activity 4 for a duration of 3 days.

4.10.1.3   The magnitude of the residual impacts has been assessed in accordance with Section 4.4.3 of the EIAO-TM in Table 4.14 below.

Table 4.14    Assessment of Residual Impacts from Construction Noise

Criteria

Assessment

Effects on public health and health of biota or risk to life.

The extent of noise nuisance would be unlikely to induce public health concern.

Magnitude of the adverse environmental impacts.

Residual impacts of between 4-6dB(A) could occur at 1 NSR during the construction phase based upon worse case scenarios.

Geographic extent of the adverse environmental impacts.

The geographic extent of the adverse impacts from noise will not be large and is anticipated to be limited to within about 40m from the drainage improvement project works area.

Duration and frequency of the adverse environmental impacts.

The construction noise impacts of the project will be maximum of 1 week only and are, therefore, temporary and reversible.

Likely size of the community or the environment that may be affected by the adverse impacts.

2 residents could be affected.  In addition, pedestrians within immediate vicinity will be temporarily affected.  The size of the community can be considered small and acceptable.

Degree to which the adverse environmental impacts are reversible or irreversible.

Construction phase impacts should be reversible.

Ecological context.

Not Applicable

Degree of disruption to sites of cultural heritage.

Minimal as there would be no important cultural heritage resources in the immediate vicinity of works sites

International and regional importance.

The impacts are localised and not of international and regional importance.

Likelihood and degree of uncertainty of adverse environmental impacts.

The impacts predicted are based upon worst case assumptions and as such, would not occur to the extent predicted on all occasions.  However, the assessment has been made using approved mathematical modelling techniques and the degree of certainty on the results is high.

 

4.10.1.4   Based upon the above, the following factors should be considered in determining the residual impacts:

·                The noise impacts are not predicted to significantly affect health or cause loss of life;

·                The predicted impacts are short term, temporary and reversible;

·                Impacts are localised and not of international and regional importance;

·                The geographic extent of the adverse impacts is confined to small areas around the works sites at two specific locations only and would not unduly affect the welfare of the local community or adjacent agricultural activities;

·                The mitigation measures proposed will reduce the overall levels of impacts; and

·                The study area has not shown itself to be fragile or undisturbed.

4.10.1.5   As such, given the benefits of the project to the local community and the very short term nature of the residual impacts predicted, the residual impacts associated with the construction phase exceedances for the drainage improvement works would be considered minor and acceptable.

4.11               Environmental Monitoring and Audit

4.11.1.1   The assessment has concluded that, despite the implementation of the maximum practicable extent of mitigation measures, adverse residual impacts during the construction phase will occur as a result of the implementation of the project.  As such, it is recommended that construction phase environmental monitoring and audit (EM&A) is undertaken to ensure that impacts do not occur beyond unavoidable levels.  It is noted that during the construction process, episodes of noise higher levels may occur and it will be the function of the EM&A process to identify these events and take the necessary action such as, for example, temporarily adjustment of the number of plant to be used or an equivalent measure as necessary.

4.11.1.2   Further details of the specific EM&A requirements are detailed in Section 10 of this report and in the EM&A Manual under separate cover. The procedure for complaints will include the provision of a hotline number for the public to use when required.

4.12               Summary and Conclusions

4.12.1.1   The results of the construction noise assessment indicate that the noise levels at 1 NSR, after the implementation of all practical direct mitigation measures, would still exceed the stipulated noise criteria in some locations for a short duration of 1 week only.  However, the residual impacts have been assessed and concluded to be temporary, reversible and unlikely to induce public health concerns to the community and as such, are considered to be minor and acceptable.