7.1.1.1 The Landscape Visual Impact Assessment (LVIA) is carried out in accordance with the requirements of the EIA Study Brief issued by Environmental Protection Department (EPD) and the Technical Memorandum on the Environmental Impact Assessment Process (EIAO-TM). Further guidance is given by EIAO Guidance Note 8/2010 and Annexes 10 and 18 of EIAO-TM. This assessment considers any potential conflicts with landscape planning policy, any likely impacts to landscape resources and character whilst identifying visual impacts in the areas surrounding the project during both the construction and operation stages.
7.1.1.1 The Study Area for the planning review and landscape impact assessment is 500m from the works boundary (within the project boundary is define as the Project Area) which includes the works sites and stockpile areas. Works sites are areas where construction activities will be undertaken and stockpile areas are used for construction stage project offices, material storage and stockpiling activities. The assessment area for the visual impact assessment is defined by the visual envelope of the Project. A recent aerial photograph of Ngong Ping is shown in Figure 7.1, illustrating the Project Area, the 500m Study Area and the visual envelope for the Project.
7.1.1.2
The
scope of the LVIA assessment includes:
· a definition of the scope and contents of the study, including a description of the assessment methodology;
· a review of the relevant planning and development control framework;
· a review of comments received during earlier public consultations and how these comments have been addressed in the design;
· a baseline study providing a comprehensive and accurate description and identification of the sensitivity of the baseline landscape resources, landscape character areas, and visual sensitive receivers (VSRs);
· identification of potential sources of landscape and visual impact during construction and operation of the Project;
· identification of the potential landscape and visual impacts and prediction of their nature, magnitude of change and potential significance, before and after the mitigation measures;
· recommendation of appropriate mitigation measures and associated implementation programmes; and
· an assessment of the acceptability or otherwise of the predicted residual impacts, according to the five criteria set out in Annex 10 of the EIAO-TM.
7.1.1.3 The landscape and visual impact assessment follows the criteria and guidelines as stated in Annexes 10 and 18 of the EIAO TM. Colour photographs showing baseline conditions as well as illustrative materials supporting conclusions are provided.
7.2
Environmental Legislation, Standards and Guidelines
7.2.1.1 The following legislation, standards and guidelines are applicable to the evaluation of landscape and visual impacts associated with the construction and operation of the Project:
· Environmental Impact Assessment Ordinance (EIAO) (Cap. 499) Section 16 and Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), particularly Annexes 3, 10, 11, 18, 20 and 21;
· EIAO Guidance Note 8/2010;
· EIA Study Brief No. ESB-227/2011;
· Ngong Ping Outline Zoning Plan. S/I-NP/6;
·
Planning Department - Landscape Value Mapping of
· Hong Kong Planning Standards and Guidelines, particularly Chapter 4 : Recreation, Open Space and Greening, Chapter 10 Conservation and Chapter 11: Urban Design Guidelines;
· Forests and Countryside Ordinance (Cap. 96);
· Town Planning Ordinance (Cap. 131);
· Country Parks Ordinance (Cap. 208);
· Plant Varieties Protection Ordinance (Cap 490).
· Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586);
· Agriculture, Fisheries and Conversation Department Nature Conservation Practice Note No. 01, 02 (Rev. Jun 2006) and 03;
·
Agriculture, Fisheries and Conversation Department Publication
“Checklist of
· Agriculture, Fisheries and Conversation Department Publication “Rare and Precious Plants of Hong Kong 2003”;
· All relevant guidelines on “Tree Maintenance and Management” and “Greening works” issued by the Greening, Landscape and Tree Management (GLTM) Section of the Development Bureau
· ETWB TCW No. 3/2006 – Tree Preservation;
· ETWB TCW No. 5/2005 – Protection of natural streams/rivers from adverse impacts arising from construction works;
· ETWB TCW No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their Preservation;
· ETWB TCW No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features;
· ETWB TCW No. 13/2003A – Guidelines and Procedures for Environmental Impact Assessment of Government Projects and Proposals Planning for Provision of Noise Barriers;
· HyDTC No. 2/2010 – Control in the Use of Shotcrete (Sprayed Concrete) in Slope Works;
· WBTC No. 7/2002 – Tree Planting in Public Works;
· WBTC No. 17/2000 – Improvement to the Appearance of slopes in connection with WBTC 25/93;
· WBTC No. 25/93 – Control of Visual Impact of Slopes;
· Land Administration Office Instruction (LAOI) Section D-12 – Tree Preservation;
· GEO Publication No. 1/2011 “ Technical Guidelines on Landscape Treatment for Slopes”,; and
· GEO Publication (1999) – Use of Vegetation as Surface Protection on Slopes
7.3.1.1 Landscape and visual impacts have been assessed separately for the construction and operation phases. Landscape and visual impacts are assessed against four criteria, namely:
· All direct and indirect impacts on existing/planned/approved land use and on future outlook;
· Impacts on LANDSCAPE RESOURCES (the physical and cultural components of the landscape);
· Impacts on LANDSCAPE CHARACTER (the aggregate impression created by a combination of resources); and
· Impacts on VISUALLY SENSITIVE RECEIVERS (VSRs) (those people who will see the Project).
7.3.1.2 The landscape and visual impact analysis contains the following:
· Baseline identification of existing/planned/approved land use condition;
· Identification of the impacts on existing/planned/approved land use condition;
· Baseline identification of sensitive receivers (resources, character areas and those in the zone of visual influence) and their sensitivity;
· Identification of the source of landscape and visual impact including the extent and types of impact;
· Assessment of landscape and visual impacts and their magnitude of change during both construction and operation phases;
· Identification of landscape and visual mitigation measures;
· Identification of potential cumulative impacts;
· Assessment of the significance of landscape and visual impacts before mitigation; and
· Assessment of the significance of residual landscape and visual impacts during construction and at Day 1 and Year 10 of operation.
7.3.2.1 The assessment of landscape impacts has involved the following procedures:
·
Identification of the baseline
landscape resources and landscape character areas found within the study area. This is achieved by site visit and desktop study of topographical maps,
information databases and photographs.
·
Assessment of the degree of
sensitivity of the landscape resources/ landscape character areas. This is influenced by a number of factors including:
-
quality
and maturity of landscape resources/characters;
-
rarity
of landscape resources/characters;
-
whether
the landscape resources/ characters are
considered to be of local, regional, national or global importance;
-
whether
there are any statutory or regulatory limitations/requirements relating to the
landscape resources/characters; and
-
ability
of the landscape resources/characters to accommodate change.
7.3.2.2
The sensitivity of each landscape resource and character
area is classified as follows:
High: |
Important landscape
or landscape resource of particularly distinctive character or high
importance, sensitive to relatively small changes. |
Medium: |
Landscape or
landscape resource of moderately valued landscape characteristics reasonably
tolerant to change. |
Low: |
Landscape or
landscape resource of low valued landscape characteristics highly tolerant to
change. |
·
Identification of potential
sources of landscape impacts. These are the various elements of the construction works and operation procedures
that would generate landscape impacts.
·
Identification of the magnitude of
landscape impacts. The
magnitude of the impact (or magnitude of change) depends on a number of factors
including:
-
the
physical extent of the impact,
-
compatibility
of the project with the surrounding landscape,
-
duration
of impacts, i.e. whether it is temporary (short, medium or long term), under
construction and operation phases, and
-
reversibility
of change.
-
The magnitude of landscape impacts is classified as follows:
Large: |
The landscape or
landscape resource would suffer major change. |
Intermediate: |
The landscape or
landscape resource would suffer moderate change. |
Small: |
The landscape or
landscape resource would suffer slight change. |
Negligible: |
The landscape or
landscape resource would suffer no discernible change. |
Nil: |
The landscape or
landscape resource would not suffer any change. |
·
Identification of potential
landscape mitigation measures. Mitigation measures may take the form of:
-
adopting
alternative design/alignment or revisions to the basic engineering or
architectural design to prevent and/or minimize adverse impacts,
-
minimization
of works areas, temporary construction,
-
remedial
measures such as colour and
textural treatment of physical, engineering and building features,
-
compensatory
measures such as the implementation of landscape design measures (e.g. tree
planting, creation of new open space etc) to compensate for unavoidable adverse
impacts and to attempt to generate potentially beneficial long term impacts.
7.3.2.3
A programme for the mitigation measures is provided
and discussed in Section 7.11. The agencies responsible for the funding,
implementation, and maintenance of the mitigation measures are proposed in Table 7.17 and Table 7.18.
·
Predicted significance of
landscape impacts before and after the implementation of the mitigation
measures. By
synthesising the magnitude of the various impacts and the sensitivity of the
various landscape resources /
character areas it is
possible to categorise impacts in a logical, well-reasoned and consistent
fashion. Table 7.1 shows the rationale for dividing the degree
of significance into four thresholds, namely insignificant, slight, moderate,
and significant, depending on the combination of a
negligible-small-intermediate-large magnitude of impact and a low-medium-high
degree of sensitivity of landscape resource/character. The significance of landscape impacts is categorised as follows:
Significant: |
Adverse /
beneficial impact where the proposal would cause significant deterioration or
improvement in existing landscape quality. |
Moderate: |
Adverse /
beneficial impact where the proposal would cause noticeable deterioration or
improvement in existing landscape quality. |
Slight: |
Adverse /
beneficial impact where the proposal would cause barely perceptible
deterioration or improvement in existing landscape quality. |
Insignificant: |
No discernible change in the existing
landscape quality. |
Table 7.1 Relationship between Receptor Sensitivity
and Impact Magnitude in Defining Impact Significance
Magnitude of Impact (Change) |
Large |
Moderate |
Moderate
/ Significant |
Significant |
Intermediate |
Slight /
Moderate |
Moderate |
Moderate
/ Significant |
|
Small |
Slight |
Slight /
Moderate |
Moderate |
|
Negligible |
Insignificant
|
Insignificant |
Insignificant |
|
Nil |
Nil |
Nil |
Nil |
|
|
|
Low |
Medium |
High |
|
|
Receptor
Sensitivity (Landscape
Resource / Landscape Character Area / VSR) |
7.3.3.1
The assessment of visual impacts has involved the
following:
·
Identification of Zones of Visual Influence (ZVIs) during
the construction and operation phase of the project. This is achieved by site visit and desktop study
of topographic maps and photographs, and preparation of cross-section to
determine the visibility of the project from various locations.
·
Identification of Visual Sensitive Receivers (VSRs) within the Zone of Visual Influence
(ZVIs) at construction and operation phases. These are the people who would reside within, work within, play within,
or travel through, the ZVIs.
·
Assessment of the degree of sensitivity to change of the VSRs. Factors considered include:
-
the type
of VSRs, which is classified according to whether the person is at home, at
work, at school, at play, or travelling. Those who view the impact from their
homes are considered to be highly sensitive as the attractiveness or otherwise
of the outlook from their home will have a substantial effect on their
perception of the quality and acceptability of their home environment and their
general quality of life. Those who view the impact from their workplace and at
school are considered to be only moderately sensitive as the attractiveness or
otherwise of the outlook will have a less important, although still material,
effect on their perception of their quality of life. The degree to which this
applies depends on whether the workplace is industrial, retail or commercial.
Those who view the impact whilst taking part in an outdoor leisure activity may
display varying sensitivity depending on the type of leisure activity. Those
who view the impact whilst travelling on a public thoroughfare will also
display varying sensitivity depending on the speed of travel.
-
other
factors which are considered (as required by EIAO GN 8/2002) include the number
of individuals, the value and quality of existing views, the availability and
amenity of alternative views, number of VSRs, the minimum viewing distance of
VSR, the duration or frequency of view, and the degree of visibility.
-
The sensitivity of VSRs is classified as follows:
High: |
The VSRs are
highly sensitive to any change in their viewing experience. |
Medium: |
The VSRs are
moderately sensitive to any change in their viewing experience. |
Low: |
The VSRs are
only slightly sensitive to any change in their viewing experience. |
·
Identification of relative numbers of VSRs. This is expressed in term of whether there are few, medium or many VSRs
in any one category of VSR.
·
Identification of potential sources of visual impacts. These are the various elements of the construction works and operation
procedures that would generate visual impacts.
·
Assessment of the potential magnitude of visual impacts. Factors considered include
-
the
compatibility with the surrounding landscape,
-
the
duration of the impact under the construction and operation phases,
-
the
reversibility of the impact,
-
the
scale of the impact and distance of the source of impact from the viewer, and
-
the
degree of visibility of the impact, and the degree of which the impact
dominates the field of vision of the viewer.
-
The magnitude of visual impacts is classified as
follows:
Large: |
The VSRs would suffer major change in their viewing experience. |
Intermediate: |
The VSRs would suffer moderate change in their viewing experience. |
Small: |
The VSRs would suffer small change in their viewing experience. |
Negligible: |
The VSRs would suffer no discernible change in their viewing
experience. |
·
Identification of potential visual mitigation measures. These may take the form of adopting alternative designs or revisions to
the basic engineering and architectural design to prevent and/or minimise
adverse impacts, remedial measures such as colour and textural treatment of
building features, and tree planting to screen the roads and associated bridge
structures. The agencies responsible for
the funding, implementation, maintenance of the mitigation measures are
identified and their approval-in-principle has been sought.
·
Prediction of the significance of
visual impacts before and after the implementation of the mitigation measures. By synthesising the magnitude of the various visual impacts and the
sensitivity of the VSRs, and the numbers of VSRs that are affected, it is
possible to categorise the degree of significance of the impacts in a logical,
well-reasoned and consistent fashion. Table 7.1 shows the rationale for dividing the
degree of significance into four thresholds, namely, insignificant, slight,
moderate and significant, depending on the combination of a
negligible-small-intermediate-large magnitude of impact and a low-medium-high
degree of sensitivity of VSRs. The significance of visual impacts is categorised as follows:
Significant: |
Adverse /
beneficial impact where the proposal would cause significant deterioration or
improvement in existing visual quality. |
Moderate: |
Adverse /
beneficial impact where the proposal would cause noticeable deterioration or
improvement in existing visual quality. |
Slight: |
Adverse /
beneficial impact where the proposal would cause barely perceptible
deterioration or improvement in existing visual quality. |
Insignificant: |
No discernible change in the existing
visual quality. |
7.3.4
Acceptability of Impacts
7.3.4.1
An overall assessment is made of the acceptability, or otherwise, of the impacts according to the five
criteria set out in Annex 10 of the EIAO TM.
7.3.4.2
It is assumed that funding, implementation and
maintenance agency of the mitigation measures can be satisfactorily resolved
according to the principles in ETWB 3/2006. All mitigation measures in this
report are practical and achievable within the known parameters of funding,
implementation and maintenance agency. The suggested agencies for the funding
and implementation (and subsequent maintenance, if applicable) are indicated in
Table
7.17 and 7.18. Approval-in-principle to the implementation and maintenance of the
proposed mitigation measures is being sought from the appropriate authorities.
7.4
Review of Planning and Development Control Framework
7.4.1.1 The existing and planned development framework surrounding the Project Area has been reviewed to identify any potential conflicts with intended planned land uses, as well as to ensure a high compatibility between the proposed works and the surroundings. Both statutory and non-statutory plans and studies relevant to the project have been considered and mapped in order to identify the project limitations in landscape planning terms.
7.4.1.2 The majority of the Study Area is covered by the Ngong Ping Outline Zoning Plan S/I-NP/6. No currently active Departmental Plans have been developed for the Study Area.
7.4.1.3
The remainder of the study area
is within
7.4.2
Existing Planning
Framework
7.4.2.1 The extent of the planning control framework within the overall study area is shown in Figure 7.2 and summarised in Table 7.2 below.
Table 7.2 Schedule of Administrative Planning Zones
Ref |
Landscape Resources |
Extent (m²) |
R(C) |
Residential (Group C) |
1,893 |
V |
Village Type Development |
46,991 |
G/IC |
Government / Institution / Community |
64,398 |
O |
Open Space |
18,640 |
REC |
Recreation |
12,810 |
OU |
Other Specified Uses |
36,934 |
GB |
Green Belt |
80,375 |
CA |
Conservation Area |
464,723 |
SSSI |
Site of Special Scientific Interest |
126,308 |
LNCP |
|
907,580 |
LSCP |
|
13,668 |
7.4.2.2
The Work Sites within the
project are typically zoned on the Outline Zoning Plan as ‘GB’ (Green Belt) to
the west and ‘V’ (Village Type Development) to the east. The westerly section
of the project (Works Section 6) is outside of the scope of the OZP and lies
within the
7.4.2.3 The works boundary straddles various areas zoned “Green Belt” (“GB”), “Government, Institution or Community” (“G/IC”), “Village Type Development” (“V”), and areas shown as “Road” on the Approved Ngong Ping Outline Zoning Plan (OZP) No. S/I-NP/6. According to the covering Notes 9 of the OZP, uses or development such as local public works, drainage works and such other public works co-ordinated or implemented by Government are always permitted.
7.4.2.4 An area of Works Section 1 intended for Stockpile Area 1 (SA1) (see Figure 2.9b) is zoned as “Conservation Area” (“CA”). According to the covering Notes 10 of the OZP, “uses or development such as local public works, drainage works and such other public works co-ordinated or implemented by Government are always permitted”. However, according to the Remarks of the OZP, “any filling of land or excavation of land or diversion of stream necessary to effect a change of use to the uses or developments always permitted under the covering Notes shall not be undertaken or continued on or after the date of first publication (16.7.1999) in the Gazette of the notice of the draft development permission area plan, without the permission of the Town Planning Board (TPB) under section 16 of the Town Planning Ordinance”.
7.4.2.5 The proposed Project works are specifically located within the various zonings as per the OZP as listed in Table 7.3 below.
Table 7.3 Statutory Designations for Works Sites, and Works Areas
No. |
Works
Item |
Location |
Zoning |
1a |
1500mm
Interception Pipe (2.5m wide trench) |
Works Section 1 A0+00
– A1+20 |
V - Village Type Development |
1b |
Stockpiling Area 1 (SA1) |
Works Section 1 A0+00 |
CA - Conservation Area |
1c |
Intake
A |
Works Section 1 A0+00 |
V - Village Type Development |
2a |
1500mm
Interception Pipe underground pipe jacking |
Works Section 2 A1+20 – A3+00 |
V - Village Type Development |
2b |
Receiving Pit 1 (RP1) 4x5m |
Works Section 2 A1+20 |
V - Village Type Development |
2c |
Works Area 1 (WA1) |
Works Section 2 A1+20 |
V - Village Type Development |
2d |
Jacking Pit 1 (JP1) 4x8m |
Works Section 2 A1+65 |
V - Village Type Development |
2e |
Site Office (SO) |
Works Section 2 A1+90 |
V - Village Type Development |
2f |
Receiving Pit 2 (RP2) 4x5m |
Works Section 2 A3+00 |
GB - Green Belt |
2g |
Works Area 2 (WA2) |
Works Section 2 A3+00 |
GB - Green Belt |
3a |
1500mm
Interception Pipe 2.5m wide trench |
Works Section 3 A3+00
– A4+48 |
GB - Green Belt |
4a |
Box
Culvert: 2.5m x 2.5m (5.5m wide trench) |
Works Section 4 B0+00 – B0+45 |
GB - Green Belt / G/IC - Government / Institution / Community |
4b |
Intake B |
Works Section 4 B0+00 |
GB - Green Belt |
4c |
Stockpiling Area 2 (SA2) |
Works Section 4 B0+20 |
GB - Green Belt |
5a |
Box
Culvert: 3.0m x 2.5m (6.0m
wide trench) |
Works Section 5 B0+45 – B2+24 |
GB - Green Belt / G/IC - Government / Institution / Community |
5b |
Stockpiling Area 3 (SA3) |
Works Section 5 B2+10 |
GB - Green Belt |
5c |
Outfall
A |
Works Section 5 B2+22 |
GB - Green Belt |
6a |
1800mm
Flood Relief Drain underground pipe jacking |
Works Section 6 C0+00 – C1+96 |
|
6b |
Intake C |
Works Section 6 C0+00 |
|
6c |
Receiving Pit 3 (RP3) 4x5m |
Works Section 6 C0+00 |
|
6d |
Works Area 1 (WA3) |
Works Section 6 C0+00 |
|
6e |
Jacking Pit 1 (JP1) 4x8m |
Works Section 6 C1+05 |
|
6f |
Stockpiling Area 4 (SA4) |
Works Section 6 C1+05 |
|
6g |
Receiving Pit 4 (RP4) 4x5m |
Works Section 6 C1+96 |
|
6h |
Works Area 4 (WA4) |
Works Section 6 C1+96 |
|
6i |
Outfall B |
Works Section 6 C1+96 |
|
7.4.2.6 The drainage reserve will become a non build zone but this will not cause any significant impact on the local community. Figures 2.6a – 2.6d outline the extent of the proposed drainage reserve.
7.4.3
Potential Conflicts with
Planning Framework
7.4.3.1 It is considered that the proposed Project would be generally in accordance with the planning goals and objectives for the study area. Two areas are in potential conflict however:
Works Section 1; and
Works Section 6.
7.5
Landscape Baseline Conditions
7.5.1.1 Physical landscape resources are the natural components of the landscape and include geology, topography, soils, vegetation and hydrological features. Human and cultural landscape resources cover a wide swath of human interaction with the land including settlement patterns, religion, medicine, economics, education and local customs. Each landscape resource possesses a varying sensitivity to development. Landscape resources within the study area are described broadly below. As expected for such a rural location, there are large areas of such resources and specific groups are shown on Figure 7.3, with the sensitivity of each summarised in Table 7.5 below. In accordance with the Study Brief, resources have been assessed within a 500m distance limit from the works’ Project Area.
Physical
Landscape Resources
Geology
7.5.1.2 The geology of the peaks around Ngong Ping is volcanic in origin, dominated by Mesozoic rocks that exhibit thin planar layering known as flow banding. These rhyolitic rocks contain both well-formed and shattered crystals. They probably originated as extremely hot ash flows, which later reconstituted to form lava-like flows. On the plateau of Ngong Ping, tuff breccia is exposed comprising 15% angular fragments, with sizes mostly in the range of 30-60 mm, up to a maximum of about 300 mm. The prominent ridges of Tsz Tau Shan, west of Ngong Ping, are primarily composed of tuffaceous sedimentary rocks. About 400m southwest of the Tian Tan Buddha Statue, the ridge is composed of light grey siltstone and tuffaceous siltstone. The layer dips southwest at 11 to 40º, and is less than 50 m thick.
Soils
7.5.1.3 The upper hillsides in the area are starved of soil cover on the volcanic steep slopes and the resultant lack of organic matter to retain water hinders the development of large sized vegetation. Lower slopes have superficial deposits of slope debris including sand, gravel, cobbles and boulders in a silt matrix. However, the plateau at Ngong Ping has a fertile cover of alluvium through the valley made up of silt, sand and gravel.
Topographic Features
7.5.1.4
The study area lies within an
upland plateau of about 100 hectares at approximately 460m above sea level. It is
surrounded by sharp rising peaks with Nei Lak Shan, the sixth highest peak in
Vegetation
7.5.1.5 The study area is well vegetated throughout. A number of distinct vegetation types can be identified:
·
Secondary
· Plantation Woodland: Maturing stands of Acacia confusa are regularly found throughout the village plateau and on the lower hill slopes, planted during the 1970s and 80s;
· Village Margin Scrub: Invasive and pioneer species have invaded land previously farmed and reclaimed abandoned settlements. Typical species include various Bamboos, Ficus hispida, Macaranga tanarius and Mallotus paniculatus. The virulent spread of Lantana camara, a non–indigenous shrub is a concern for the ecology of the area;
·
·
Open
7.5.1.6 Within the study area a number of isolated mature stands of Machilus spp. and Ficus microcarpa are present and may present conflicts to the project work. However, no Old and Valuable Trees (OVT) or rare trees were identified.
Hydrological Features
7.5.1.7 Seasonal run-off from the steep surrounding slopes collects in deep natural gulleys and streams which are liable to flash flooding, causing erosion and potential landslip issues. These water courses contain natural rock features and are important for local ecological populations. Some streams are found within the study area on the plateau, usually covered by scrub woodland. Their sensitivity to change is high.
7.5.1.8 Man made water courses have been developed through the plateau area to contain flash flooding. Constructed from stepped, rock gabions, these have developed localised vegetation and ecosystems within their margins.
Human
and Cultural Landscape Resources
Traditional Village Houses
7.5.1.9
A large percentage of the study
area contains the traditional settlement of
7.5.1.10
The Po Lin Monastery,
established in 1906, is known as "The Sacred Place of the Buddha in the
South" and is the first of the four most popular monasteries in
Tian Tan Buddha
7.5.1.11
A flight of 268 steps from Tei
Tan square lead to the world's largest outdoor bronze statue and the largest seated outdoor bronze Buddha statue.
Walking up the steps, visitors can enjoy a panoramic view of Lantau and the
Ngong Ping Piazza
7.5.1.12
Ngong Ping Piazza opened in
2010 as a brand new tourist facility with strong Buddhist character. The piazza
links the various tourist attractions in Ngong Ping, including the Po Lin
Monastery, the Tian Tan Buddha, Ngong Ping 360 Cable Car,
7.5.1.13
The
7.5.2
Schedule of Landscape
Resources
7.5.2.1 The factors affecting the sensitivity for evaluation of landscape impact are detailed in Section 7.3.2 above. The landscape resources (LDRs) identified within the project area have been grouped into 9 differing groups as shown in Table 7.4 below.
Table 7.4 Schedule of Landscape Resources
Ref |
Landscape Resources |
Landscape Type |
LDR-1 |
Natural Stream Course |
Physical / Natural |
LDR-2 |
Constructed Water Course |
Physical / Human |
LDR-3 |
Natural Topographic Features |
Physical / Natural |
LDR-4 |
|
Physical / Natural |
LDR-5 |
Open |
Physical / Natural |
LDR-6 |
Village Margin Vegetation |
Physical / Natural |
LDR-7 |
Village Housing inc. Gardens |
Physical / Cultural |
LDR-8 |
Religious Institutions / Features |
Cultural |
LDR-9 |
Maintained Amenity Features |
Physical / Human |
7.5.2.2 The identified landscape resources in each group are discussed in more detail below and their sensitivity assessed in accordance with the criteria in Section 7.3.2 above. In accordance with the Study Brief, resources have been assessed within a 500m distance limit from the Project Area. The extents of the groups are shown in Figure 7.3 and photos of the key landscape resources are shown in Figure 7.6.
LDR-1 – Natural Stream Courses
LDR-1.1
– Seasonal
7.5.2.3
This category includes all
natural watercourses on the slopes of the study area. These are generally
steep, boulder strewn waterways, cut directly down the slopes of the
mountainside. They have been noted to be dry during the winter season and, even
during wet season, the higher courses may only provide fast outlets for flash
flooding after rains, feeding the streams of the lower valley. Slope vegetation
tends to collect within the ‘V’ shaped valley cut by these courses, since water
is collected there and a less severe microclimate can establish. The ravines
are sensitive to environmental change and with locations in the protected
LDR-1.2
– Water Courses through
7.5.2.4 These streams are also seasonal but act as collectors from the mountainside channels and as such follow the contours more closely. They have often been dammed, rerouted, culverted and blocked, displaying signs of human interference. During storm surges, these streams can run fast with deep flows and can cause flooding to the local populace. The water courses are very sensitive to environmental change but have already been significantly altered within the village development area. The remaining natural stream sections are restricted to two locations within works Sections 1 and 5. Due to the high influence of human habitation, the sensitivity of this LDR is considered Medium.
LDR-2 – Constructed Water Courses
LDR-2.1
– Open Drainage Channels
7.5.2.5 The problems with village flooding have been addressed previously with short-term drainage improvement measures implemented in 2009 and further measures in 2011. These consist of an open cut drainage channel formed from gabion sections to the north and west of the Ngong Ping tourist village. The construction method allows the development of vegetation and ecosystems within the channel in the same ways as a natural stream course. The channels are, however, newly formed and no complex systems have yet developed. As such their sensitivity is considered Low.
LDR-2.2
– Underground Drainage Channels
7.5.2.6
Sections of the surface water drainage system have been diverted underground
through the new Piazza and around the Po Lin Monastery. Furthermore, a hillside stream section runs
through an underground pipeline from the
LDR-3 – Natural Topographic Features
LDR-3.1
– Rocky Outcrops Surrounding Ngong Ping Columbarium
7.5.2.7
The landscape
areas surrounding the Ngong Ping Columbarium are protected within the
LDR-3.2
– Hillocks Surrounding the Tian Tan Buddha
7.5.2.8
The Tian Tan Buddha is located
atop the largest of one of the many small, rounded hills on the south side of
Ngong Ping on the ridge above the
LDR-3.3
– Hillslopes of Nei Lak Shan
7.5.2.9
This resource falls within the
LDR-4 –
LDR-4.1
– Naturalised Hillside
7.5.2.10 Photos from 1961 show that the hillsides surrounding Ngong Ping Village were free of trees, with just the settlement itself and low lying, surrounding water courses and without having any tree cover. Traditionally the hillsides were typically free of woodland with such vegetation having developed significantly during the last 30 years. Tree planting has been introduced with plantation species (Acacia confusa) becoming mixed with the native hillside secondary woodland that has generated on the hillslopes. A dominant canopy of Machilus chekiangesis and Machilus pauhoi ‘Kanehira’ has developed, supported by a typical understory including Mallotus paniculatus and Viburnum odoratissimum. The development of this woodland on the mountain slopes with the thin soils and a lack of water is marginal. Their sensitivity is considered High.
LDR-5 – Open
LDR-5.1
–
7.5.2.11 The natural cover for the hillsides is a mix of grasses and sedges on the thin soil cover of the mountain slopes. Ferns and dispersed shrub vegetation including Gordonia axilliaris are able to develop in moist niches or on thicker localised soil deposits. Steeper slopes generally have thinner soils and are less able to support vegetation, with the diversity reducing until bare rock is exposed. Some species are able to colonise and re-colonise efficiently and the ability to accommodate small scale change is relatively high. As the grass and shrub habitat is the typical cover for much of the upland landscape of the area the sensitivity is considered Medium.
LDR-6 – Village Margin Vegetation
LDR-6.1 – Unmaintained Village Scrub
7.5.2.12 The village areas have experienced a significant change of land use and population over the last 20 years. Areas no longer maintained as garden or farmed have reverted to scrub, with invasive species quickly colonising. Typical plants include mature varieties of garden fruit trees and remnants of woodland trees, tall grasses, Ipomea, Lantana and Alocasia with pioneer tree species Ficus hispida and Macaranga tanarius, also, being prevalent. This is first stage regeneration and these areas are generally able to sustain change and regenerate in the longer term. Due to the mature tree resources present and the overall greening qualities of this LDR, the Sensitivity is considered Medium.
LDR-7 – Village Housing with Gardens
LDR-7.1
– Traditional Housing with Gardens and Orchards
7.5.2.13 The village areas demonstrate typical
LDR-8 – Religious Institutions /
Features
LDR-8.1
–
7.5.2.14 The Monastery is a unique and internationally renowned cultural resource and raison d’etre for the village itself. As a fully working and adapting resource it is able to accommodate change, however, its maturity, rarity and quality make it a High sensitivity resource.
LDR-8.2
–
7.5.2.15 Part of the Po Lin Monastery, the
LDR-8.3
– Ngong Ping Columbarium
7.5.2.16 The columbarium is a relatively new feature of modern design and materials. The building is not generally visible other than from an elevated position due to the surrounding tree cover. It can accommodate change relatively easily and its cultural importance is not as that for other religious features in the district. Sensitivity is, therefore, considered Low.
LDR-8.4
–
7.5.2.17 Hillside graves are found all across
LDR-9 – Maintained Amenity Features
LDR-9.1
– Ngong Ping Themed Village
7.5.2.18 Set on a 1.5 hectare site adjacent to Ngong Ping Cable Car Terminal, the cultural themed village has been architecturally designed and landscaped to reflect the cultural and spiritual integrity of the Ngong Ping area. It has several major attractions including “Walking with Buddha” and the “Monkey's Tale Theatre”, as well as a diverse array of retail, dining and entertainment experiences. Sensitivity is considered Low
LDR-9.2
– Ngong Ping Piazza
7.5.2.19 The Piazza links the various tourist attractions in Ngong Ping,
including the Po Lin Monastery, the Tian Tan Buddha, Ngong Ping 360 cable car,
LDR-9.3
– Tian Tan Buddha
7.5.2.20 Despite its recent construction the Buddha has become a major tourist attraction of some cultural international importance. As a feature it is a unique addition of quality in a conservation setting and despite its modernity the sensitivity is considered to be High
LDR-9.4
– Hiking Paths of Nei Lak Shan
7.5.2.21 The hiking trails have an important role in allowing access for the population into the natural countryside. They are constructed of natural materials with the intention of being low in visual impact and minimising the physical impact of walkers on the environment. The trails are commonplace and can easily be adapted to changing use. Sensitivity in this environment is considered Medium.
LDR-9.5
– Tourists Facilities Around Tian Tan Buddha
7.5.2.22 Within the wooded area surrounding the Buddha exists a series of
paths and features with education and amenity at the core. The Ngong Ping Fun
Walk is only 1.5 km in length yet offers six attractions, namely Misty Lantau,
Ancient Gateway, Tree Walk Exploration,
Summary Schedule of Landscape Resources
7.5.2.23 The Landscape Resources identified within the study area as described above and their sensitivity to change are summarised in Table 7.5 below.
Table 7.5 Summary of Assessment of Sensitivity of Landscape Resources
Ref |
Landscape Resource |
Quality and Maturity (High / Medium / Low) |
Rarity (High /Medium / Low) |
Local / District / Regional Importance |
Statutory Limitations / Requirements* |
Ability to Accommodate Change (High / Medium / Low) |
Sensitivity (High / Medium
/ Low) |
LDR-1 – Natural Stream Courses |
|||||||
LDR-1.1 |
Seasonal |
High |
Medium |
District |
|
Low |
High |
LDR-1.2 |
Water Courses through |
Low |
Medium |
District |
- |
Medium |
Medium |
LDR-2 – Constructed Water Courses |
|||||||
LDR-2.1 |
Open Drainage Channels |
Low |
Low |
Local |
- |
High |
Low |
LDR-2.2 |
Underground Drainage Channels |
Low |
Low |
Local |
- |
High |
Low |
LDR-3 – Natural Topographic Features |
|||||||
LDR-3.1 |
Rocky Outcrops Surrounding Ngong Ping
Columbarium |
High |
Medium |
District |
|
Low |
High |
LDR-3.2 |
Hillocks surrounding Tian Tan Statue |
Medium |
High |
Regional |
SSSI / CA |
Low |
High |
LDR-3.3 |
Hillslopes of Nei Lak Shan |
High |
Medium |
District |
|
Low |
High |
LDR-4 – |
|||||||
LDR-4.1 |
Naturalised Hillside |
High |
Medium |
Local |
|
Low |
High |
LDR-5 – |
|||||||
LDR-5.1 |
|
Medium |
Low |
District |
|
High |
Medium |
LDR-6 – Village Margin Vegetation |
|||||||
LDR-6.1 |
Unmaintained Village Scrub |
Medium |
Low |
Local |
- |
Medium |
Medium |
LDR-7 – Village Housing with Gardens |
|||||||
LDR-7.1 |
Traditional Housing with Gardens and
Orchards |
Medium |
Medium |
District |
- |
Medium |
Medium |
LDR-8 – Religious Institutions /
Features |
|||||||
LDR-8.1 |
|
High |
High |
Regional |
- |
Low |
High |
LDR-8.2 |
|
High |
High |
Regional |
- |
Low |
High |
LDR-8.3 |
Ngong Ping Columbarium |
Low |
Low |
District |
- |
High |
Low |
LDR-8.4 |
|
High |
Medium |
Local |
Varies |
Low |
High |
LDR-9 – Maintained Amenity Features |
|||||||
LDR-9.1 |
Ngong Ping Themed Village |
Low |
Low |
Regional |
- |
High |
Low |
LDR-9.2 |
Ngong Ping Piazza |
Medium |
Low |
Regional |
- |
High |
Low
|
LDR-9.3 |
Tian Tan Buddha |
High |
High |
Regional |
CA |
Medium |
High |
LDR-9.4 |
Hiking Paths of Nei Lak Shan |
Low |
Medium |
District |
|
Medium |
Medium |
LDR-9.5 |
Tourists Facilities around Tian Tan Buddha |
Medium |
Medium |
Regional |
SSSI / CA |
Medium |
Medium |
Notes: * CA =
Conservation Area, SSSI = Site of Special Scientific Interest
7.5.3
Landscape Character
Background
7.5.3.1
In general, a landscape is composed
of, and given its character by, a number of natural and man made features.
These differing Landscape Character Types (LCTs) can all be described as
exhibiting a particular and consistent character or combination of physical
features such as land use, terrain, resources or development pattern and as a
result would exhibit a varied degree of sensitivity to change as brought about
by the Project . The landscape character types have been standardised and
mapped for the whole of
7.5.3.2 The area of Lantau under study is simple and consistent in its character type and exhibits just 3 differing (LCTs) in 5 different Landscape Character Areas (LCAs), as discussed in the section below. All the LCAs exhibit Upland Countryside landscape characteristics. Figure 7.4 indicates the (LCTs) surrounding the study area and these are summarised in Table 7.6 below.
Landscape Character Type
Upland Plateau Landscape
7.5.3.3 These are elevated upland landscapes lying above 300 mPD, which are characterised by flat or undulating topography, forming elevated plateaux. Such landscapes usually contain undulations and hillocks within the overall flatter areas, as well as streams and areas of woodland, due to their relatively sheltered locations. Because of their gentle topography, these areas are more easily cultivated and have often been settled in the past, though in some cases the buildings may lie abandoned with scrub re-colonising abandoned fields. These landscapes are often characterised by a sense of enclosure provided by the surrounding mountains, muted natural colours and a certain remoteness and tranquillity. The Project Area lies completely within this landscape character type.
Peak Landscape
7.5.3.4
These landscapes are formed by
the highest uplands and peaks in
Settled Valley Landscape
7.5.3.5
Lying between spurs or ridges
in uplands in close proximity to urban areas or to the coast, these landscapes
are defined largely by their valley topography. Such valleys usually possess a
distinct valley floor where alluvial or colluvial materials have accumulated,
such that the wider, lower parts of the valleys will have been settled at some
stage. Whilst the valley sides may be thickly wooded, the valley floor often
contains active or abandoned agricultural fields together with a village situated
around a stream. In more recent times, roads, powerlines or major engineering
structures (such as reservoirs) may have been constructed in these landscapes
whilst fields may have been abandoned to make way for village housing or open
storage. Such landscapes usually possess a strong sense of enclosure, whilst
their coherence or visual amenity will vary depending on the extent to which
traditional land uses have been replaced. Within the study area, a small
section in the northwest is located within the adjacent valley system leading
down to
7.5.4
Schedule of Landscape
Character Areas
7.5.4.1 Factors affecting the sensitivity for evaluation of landscape impact are detailed in Section 7.3.2 above. Landscape Character Areas (LCAs) identified within the project area have been grouped into 5 different zones as shown in Table 7.6 below.
Table 7.6 Schedule of Landscape Character Areas
Ref |
Landscape Character Area |
Landscape Character Type |
Extent (m2) |
LCA1 |
Inhabited Land Around |
Upland Plateau Landscape |
477,000 |
LCA2 |
Foothills Surrounding Tian Tan Buddha |
Upland Plateau Landscape |
288,000 |
LCA3 |
Nei Lak Shan |
Peak Landscape |
457,000 |
LCA4 |
Natural Hills Surrounding Ngong Ping |
Peak Landscape |
431,000 |
LCA5 |
Upper Reaches of |
Settled Valley Landscape |
162,000 |
7.5.4.2 The identified Landscape Character Areas in each group are discussed in more detail below and their sensitivity assessed in accordance with the criteria in Section 7.3.2 above. In accordance with the Study Brief, resources have been assessed within a 500m distance limit from the works area boundaries. Photos of the key Landscape Character Areas are shown on Figure 7.7 and the extent of the groups are shown on Figure 7.3.
LCA1
– Inhabited Land Around
7.5.4.3 This area contains the typical features of the character type, including rural settlement with land under, or previously under, agriculture, local woods and streams enclosed within the surrounding mountains. The area has been undergoing change for some time and continues to be able to accommodate such slow changes. Sensitivity is considered as Medium.
LCA2
– Foothills Surrounding Tian Tan Buddha
7.5.4.4 Unlike LCA1, this sub-area is completely tree covered and predominantly under conservation legislation including zoning of a Site of Special Scientific Interest (SSSI). With no settlement here, the only human feature visually apparent is the Tian Tan Buddha Statue. Ability to accommodate change is not as identifiable as for LCA1. Sensitivity is considered High.
LCA3
– Nei Lak Shan
7.5.4.5
The towering mountain is iconic
and dominates the plateau below making it distinct from the surrounding ‘Peak
Landscape’ type. It’s exposed sheer faces are highly visible and the
LCA4
– Natural Hills Surrounding Ngong Ping
7.5.4.6
The general ‘Peak Landscape’ to
the west of Ngong Ping exhibits typical character traits. As it does not have
the same elevation as LCA3, this area is generally covered in grass and shrub
vegetation with rocky outcrops. Designated as
LCA5
– Upper Reaches of
7.5.4.7 This area forms the visual ridge of the large character area formed from the valley floor at Shum Wat. In physical terms it more resembles the characteristics of LCA4 as a ‘Peak Landscape’ but is not visible from the plateau, making it singularly distinct. Sensitivity is considered High.
Summary
Schedule of Landscape Character Areas
7.5.4.8 The Landscape Character Areas identified within the study area as described above and their sensitivity to change are summarised in Table 7.7 below
Table 7.7 Summary of Assessment of Sensitivity of Landscape Character Areas
Ref |
Landscape Character Area |
Landscape Character Type |
Quality and
Maturity (High / Medium / Low) |
Rarity (High / Medium / Low) |
Local / District
/ Regional Importance |
Statutory Limitations
/ Requirements* |
Ability to
Accommodate Change (High / Medium / Low) |
Sensitivity (High / Medium / Low) |
LCA1 |
Inhabited Land Around |
Upland Plateau Landscape |
Medium |
Medium |
Regional |
- |
Medium |
Medium |
LCA2 |
Foothills Surrounding Tian Tan Buddha |
Upland Plateau Landscape |
High |
Medium |
Regional |
SSSI / CA |
Low |
High |
LCA3 |
Nei Lak Shan |
Peak Landscape |
High |
Medium |
Regional |
|
Low |
High |
LCA4 |
Natural Hills Surrounding Ngong Ping |
Peak Landscape |
High |
Medium |
Regional |
|
Low |
High |
LCA5 |
Upper Reaches of |
Settled Valley Landscape |
High |
Medium |
Regional |
|
Low |
High |
Notes: * CA = Conservation Area, SSSI = Site of
Special Scientific Interest
7.6
Visual Baseline Conditions
7.6.1
Visually Sensitive Receivers
7.6.1.1 A number of Visually Sensitive Receivers (VSRs) will be affected by the scope of the Project. VSRs are those people who will potentially view the construction of the project and/or its operation. The Zone of Visual Influence (Visual Envelope) is the area from which any part of the proposed Project would be able to be seen. VSRs will be identified within the Visual Envelope at a distance not more than 3 km from the Project. Beyond this, the effects of distance and the extensive visual context tend to render impacts insignificant.
7.6.1.2 The assessment of visual impacts is considered as a combination of the magnitude of change brought about by the project in relation to receiver sensitivity. Receivers are identified through the definition of the development’s visual envelope (i.e. the area within which views of the development are possible). For the purposes of this study, receivers have been grouped into the following categories below:
Residential: |
Those people who would view the scheme from their home |
Occupational: |
Those people who would view the scheme from their work/study place |
Leisure and Cultural: |
Those people who would view the scheme whilst engaging in leisure, culture or recreation activities including shopping, walking, hiking, worship or sports |
Transportation: |
Those people who would view the scheme from vehicles |
7.6.1.3 The factors affecting the sensitivity of visual receivers are detailed in Section 7.3.3 above and include:
· Value and quality of existing views;
· Availability and amenity of alternative views;
· Type and estimated number of receiver population;
· Duration and frequency of view; and
· Degree of visibility.
7.6.1.4 Generally the sensitivity of visual receivers for the identified groups can be established as detailed below.
Residential
7.6.1.5 Those who view the scheme from their homes are considered to be highly sensitive to any visual intrusion. This is because the attractiveness, or otherwise, of the view will have a notable effect on a residents’ general quality of life and acceptability of their home environment.
Occupational
7.6.1.6 Those people who view the scheme from their workplace are generally considered relatively less sensitive to visual intrusion. This is because they are normally employed in activities where visual outlook plays a less important role in the perception of the quality of the working environment. They are on the whole classified as a low sensitivity group unless their environmental outlook forms a significant element of their work.
Leisure
and Cultural
7.6.1.7 For those who view the scheme whilst engaging in outdoor leisure pursuits, visual sensitivity varies depending on the type of cultural activity. Those taking a stroll in a park, for example, would be classified as a high sensitivity group compared to football players who would have a low sensitivity rating.
Transportation
7.6.1.8 For those people who view the scheme from public thoroughfares, the degree of visual intrusion experienced depends on the speed of travel and whether views are continuous or only occasional. Generally, the slower the speed of travel and the more continuous the viewing experience, then the greater the degree of sensitivity.
7.6.2
Schedule of Visually
Sensitive Receivers
7.6.2.1 Potentially affected Residential, Occupational, Leisure & Cultural and Transportation VSRs are summarised in Table 7.8 below and their locations shown in Figure 7.5.
Table 7.8 Potential Key Visually Sensitive Receivers (VSRs)
Ref |
Location |
Type of View (rural/developed,
open/restricted, static/transient) |
R-01 |
Residents of |
Rural
/ Restricted / Static |
R-02 |
Residents of |
Rural
/ Open / Static |
R-03 |
Residents of |
Rural
/ Restricted / Static |
R-04 |
Residents of |
Rural
/ Restricted / Static |
O-01 |
Staff at Ngong Ping Cable Car Terminal |
Rural /
Restricted / Static |
O-02 |
Monastery Visitors to Ngong Ping Columbarium |
Rural /
Restricted / Static |
O-03 |
Temporary Workers at Construction Site |
Rural / Open
/ Static |
L-01 |
Users of Ngong Ping 360 Cable Car with Elevated
Views |
Rural / Open
/ Transient |
L-02 |
Tourists moving through Ngong Ping Piazza Viewing
North |
Rural /
Restricted / Transient |
L-03 |
Tourists at
Tian Tan Buddha Viewing South |
Rural / Open
/ Transient |
L-04 |
Hikers on Footpaths in |
Rural / Open
/ Transient |
T-01 |
Users of |
Rural /
Restricted / Transient |
T-02 |
Road Users on |
Rural /
Restricted / Transient |
T-03 |
Road Users on |
Rural /
Restricted / Transient |
T-04 |
Road Users on Village |
Rural /
Restricted / Transient |
7.6.2.2
The identified VSRs in each
group are discussed in more detail below and their sensitivity assessed in
accordance with the criteria in Section 7.3.3 above. The locations are
shown on Figure 7.5 and photos are shown on Figure 7.8.
Residential
R-01: Residents of
7.6.2.3
This VSR includes the
scattered village houses of the natural flood plain at a level of approximately
435mPD in
R-02: Residents of
7.6.2.4
This VSR includes the hillside
village houses facing south over
R-03: Residents of
7.6.2.5 As for VSR1, these receivers include scattered village houses surrounded by Works Section 2. They are generally fairly well concealed within mature gardens and woodland and a number appear uninhabited. The number of dwellings who would be able to view the works in part is restricted to 2 or 3 and with alternative views being available, consequently receiver sensitivity is considered Medium.
R-04: Residents of
7.6.2.6 The Po Lin Monastery is formed by a collection of clustered buildings of different heights and sizes. The outlook is generally on all sides but many buildings obscure each others views. Restricted views to the works are possible from selected buildings and windows within the Monastery. A selection of alternative views is available and the quality of these views is good. Resident numbers with open views are relatively restricted and the receiver sensitivity is considered as Medium.
Occupational
O-01: Staff at Ngong Ping Cable Car Terminal
7.6.2.7 Some workers in this area will be able to circulate the building and have selected aspects on various sides into the surrounding countryside. Such restricted views are generally of good quality with the horizon visible and a selection of alternative views available. With few window opportunities available, relatively low staff numbers and infrequent durations of view, the receiver sensitivity is considered as Low.
O-02: Monastery Visitors to Ngong Ping
Columbarium
7.6.2.8 These receivers are concealed within the enclosed walls of the Columbarium and will only be aware of outside views from the front entrance door and from the slit windows in the walls. Open views to the sky are of importance here. However, due to the low number of receivers, occasional nature of visits and highly restricted views, the receiver sensitivity is considered Low.
O-03: Temporary Workers at Material Storage
Yard
7.6.2.9 The existing construction materials storage yard is predominantly secured behind above-head height security fencing and activity levels are low in intensity, with few staff on hand in this area. The site compound has unrestricted surrounding views, open on all sides to the mountains and sky above the fence line. However, with so few workers are on site, the variety of available views and occasional nature of viewing reception, the sensitivity of this receiver is deemed to be Low.
Leisure
and Cultural
L-01: Users of Ngong Ping 360 Cable Car with
Elevated Views
7.6.2.10 Daily average passenger numbers by August 2009 had reached 4,000 on weekdays, up to 8,000 at weekends and on special occasions such as Lunar New Year holiday, the system has carried as many as 13,000 passengers daily. The system is now operating at its maximum capacity of 108 cabins. As such, there are potentially a very large number of receivers who take a specific interest in viewing the surroundings and its quality, taking many photographs of the countryside. Despite views for the receivers being transitory the high quality of panoramic views existing and the huge numbers of receivers mean that sensitivity is considered High.
L-02: Tourists moving through Ngong Ping
Piazza Viewing North
7.6.2.11
Assuming that the numbers of users
of the cable car is similar to the number of tourists moving through
L-03: Tourists at Tian Tan Buddha Viewing
South
7.6.2.12 Many of the receivers from VSR L-01 and VSR L-02 will, also, become receivers in this category. As a major tourist location, this specific viewpoint offers excellent north views, which are regularly photographed in huge numbers and such photographs frequently distributed digitally around the world. The high quality of the existing view, coupled with the tendency to share the view photographically in huge numbers mean that sensitivity is considered High.
L-04: Hikers on Footpaths in
7.6.2.13 These receivers have wide, changing and excellent views of surrounding high quality landscape with a high appreciation for its quality. Population numbers are limited, however, and the wide availability of alternate views and the fact that hikers are transient and occasional visitors mean that their sensitivity is Medium.
Transportation
T-01: Users of
7.6.2.14 This road is very infrequently travelled and restricted to Columbarium users. Views are changeable but good quality on all sides, sometimes open and sometimes enclosed by trees. With low user numbers and short view duration, receiver sensitivity is considered to be Low.
T-02: Road Users on
7.6.2.15
T-03: Road Users on
7.6.2.16 This VSR includes a variety of traffic, much of which is construction related as well as for those few local residents with vehicles. With frequently changing views of short duration and low user numbers, the sensitivity is considered as Low.
T-04: Road Users on Village
7.6.2.17 Users of VSR T-03 are also restricted as frequenters of this road. Sensitivity for users on this section is, also, considered Low.
Summary
Schedule of Visually Sensitive Receivers
7.6.2.18 The VSRs identified within the study area as described above and their sensitivity to change are summarised in Table 7.9 below.
Table 7.9 Summary of Assessment of Sensitivity of Visually Sensitive Receivers (VSRs)
VSR |
Location |
Estimated number of Receivers (Few / Typical / Many) |
Value and Quality of Existing View (Good / Fair / Poor) |
Availability and Amenity of Alternative views |
Duration and Frequency of Existing view (Stationary / Transitory / Glimpse Frequent / Regular / Occasional) |
Degree of Visibility (Wide / Restricted / Narrow Distant / Near / Adjacent) |
Sensitivity (high / medium / low) |
Residential |
|||||||
R-01 |
Residents of |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Frequent |
Restricted / Adjacent |
Medium |
R-02 |
Residents of |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Frequent |
Wide / Distant |
Medium |
R-03 |
Residents of |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Frequent |
Restricted / Adjacent |
Medium |
R-04 |
Residents of |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Frequent |
Restricted / Distant |
Medium |
Occupational
|
|||||||
O-01 |
Staff at Ngong Ping Cable Car Terminal |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Regular |
Restricted /
Near |
Low |
O-02 |
Monastery visitors to Ngong Ping Columbarium |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Occasional |
Narrow / Adjacent |
Low |
O-03 |
Temporary Workers at
existing Material Storage Yard |
Few |
Good |
Yes / Good
alternatives |
Stationary /
Regular |
Wide / Distant |
Low |
|
|||||||
Leisure
& Cultural |
|||||||
L-01 |
Users of Ngong Ping 360 Cable Car with Elevated
Views |
Many |
Good |
Yes / Good
alternatives |
Transitory /
Occasional |
Wide / Distant |
High |
L-02 |
Tourists moving through Ngong Ping Piazza Viewing
North |
Many |
Good |
Yes / Good
alternatives |
Transitory /
Occasional |
Wide / Distant |
High |
L-03 |
Tourists at
Tian Tan Buddha Viewing South |
Many |
Good |
Yes / Good
alternatives |
Stationary /
Occasional |
Wide / Distant |
High |
L-04 |
Hikers on Footpaths in |
Few |
Good |
Yes / Good
alternatives |
Transitory /
Occasional |
Wide / Distant |
Medium |
Transportation |
|||||||
T-01 |
Users of |
Few |
Good |
Yes / Good
alternatives |
Transitory /
Regular |
Wide / Near |
Low |
T-02 |
Road Users on |
Few |
Good |
Yes / Good
alternatives |
Transitory /
Regular |
Restricted /
Near |
Low |
T-03 |
Road Users on |
Few |
Good |
Yes / Good
alternatives |
Transitory /
Regular |
Wide / Distant |
Low |
T-04 |
Road Users on Village |
Few |
Good |
Yes / Good
alternatives |
Transitory /
Regular |
Restricted /
Near |
Low |
7.7
Potential Sources of Landscape and Visual Impacts
7.7.1.1 The assessment of landscape impacts will result from:
· Identification of the type and sources of impact and their magnitude that would be generated during construction and operation of the project; and
· Identification of the principal landscape impacts primarily in consideration of the degree of change to the baseline conditions. The impacts are considered systematically in terms of landscape elements, the project and its context.
7.7.1.2 The assessment of potential visual impacts will result from:
· Identification of the type and sources of visual impact and their magnitude that would be generated during construction and operation of the scheme; and
· Identification of the principal visual impacts primarily in consideration of the degree of change to the baseline condition.
7.7.1.3 The proposed drainage works will comprise buried underground pipes and box culverts over its entire length and, as such, potential residual landscape and visual impacts during Operation Stage will be restricted to above ground construction works, such as manholes, and intakes and outfalls. During the Construction Stage, excavation by cut and cover of trenches for the pipeline in Works Sections 1 and 3, and for box culvert in Works Sections 4 and 5 will be potentially damaging to existing resources and may have adverse visual implications. The pipeline in Works Sections 2 and 6 will be constructed by trenchless pipe jacking method, as such extensive open cut will not be required and as the works will be underground, the surface works will be limited to the jacking and receiving pits and the intermediate pit areas, thereby significantly reducing the potential visual implications. Also, that the stockpile area SA1 in Conservation Area has been reduced by about half to reduce potential impacts.
7.7.1.4
Figures 2.9a-g outline
the detailed plan and layout of the works. A description and schedule is given
in Table
2.7 in Section 2, detailing the size and configuration of structures
and working areas, including the locations, dimensions and footprint area.
7.7.1.5
During the Construction Stage,
potential Landscape and Visual Impacts would arise from:
· Excavation and construction works for Receiving and Jacking Pits in Works Sections 2 and 6;
· Excavation by cut and cover of trenches for construction of a pipeline and box culvert in Works Sections 1, 3, 4 and 5;
· Stockpiling of excavated and building materials and storage of construction equipment and plant in stockpile areas SA1- 4 and Site Office;
· Off-site construction traffic involving haulage of excavated materials;
· Temporary traffic / road diversions;
· Night-time lighting;
· Temporary works hoardings, noise barriers and enclosures; and
· Contractor’s temporary works areas, including parking areas.
7.7.1.6 During the Operation Stage, potential Residual Landscape and Visual Impacts would be related to the permanent loss of landscape resources, loss of visual amenity from such resources and construction of visible ground related structures:
· Culvert intakes and outfalls;
· Permanent net loss of landscape resources, including a small rocky slope and trees; and
· Loss of visual amenity previously presented by lost landscape resources.
7.8
Landscape Impact Assessment
7.8.1
Identified Impacts to
Landscape Resources
7.8.1.1
The estimated magnitude of
impacts, before implementation of mitigation measures, on the landscape resources
that would occur during the construction and operation phases are quantified
and tabulated in Table
7.10. Those resources which will be affected
by the works are discussed in detail below.
The precise
number of trees to be retained, transplanted, felled and compensated shall be
determined and agreed separately with government during the Tree Felling
Application process under ETWB TC 3/2006.
Table 7.10 Schedule of Landscape Resources Impacted during Construction and Operation
Ref. |
Works Section / Area |
Type of Resource |
Area of Resources Affected (m2) |
Surveyed No. of Trees Within
Project Area |
Estimated No.
of Trees Retained |
Estimated No. of Trees
Transplanted |
Estimated No. of Trees Felled |
Reprovision |
|
Construction |
Operation |
||||||||
1a |
1500mm
Interception Pipe |
1.1b / 1.2d / 4.1 |
160 |
80 |
85 |
71 |
0 |
14 |
Water course margins shall be reinstated where disturbed. / Compensatory tree planting
within the project area |
1b |
Stockpiling
Area 1 (SA1) |
4.1 |
100 |
50 |
3 |
3 |
0 |
0 |
None |
1c |
Intake
A |
4.1 |
70 |
25 |
0 |
0 |
0 |
0 |
None |
2a |
1500mm
Interception Pipe |
6.1 / 7.1 |
0 |
0 |
116 |
101 |
0 |
15 |
On Site 1:1 Compensatory Tree Planting |
2b |
Receiving
Pit 1 (RP1) |
6.1 |
20 |
0 |
2 |
1 |
0 |
1 |
On Site 1:1 Compensatory Tree Planting |
2c |
Works
Area 1 (WA1) |
6.1 |
100 |
0 |
0 |
0 |
0 |
0 |
None |
2d |
Jacking
Pit 1 (JP1) |
- |
0 |
0 |
0 |
0 |
0 |
0 |
None |
2e |
Site
Office (SO) |
- |
0 |
0 |
5 |
5 |
0 |
0 |
None |
2f |
Receiving
Pit 2 (RP2) |
6.1 |
20 |
0 |
0 |
0 |
0 |
0 |
Land reinstated |
2g |
Works
Area 2 (WA2) |
6.1 |
80 |
80 |
0 |
0 |
0 |
0 |
Land reinstated |
3a |
1500mm
Interception Pipe |
1.2c/6.1 |
600 |
600 |
73 |
58 |
0 |
15 |
Water courses will be reinstated where disturbed/ |
4a |
Box Culvert: 2.5m x 2.5m |
6.1 |
230 |
230 |
16 |
4 |
0 |
12 |
On site 1:1 Compensatory Tree Planting / Land Reinstated over Culvert |
4b |
Intake
B |
6.1 |
40 |
20 |
1 |
0 |
0 |
1 |
On site 1:1 Compensatory Tree Planting |
4c |
Stockpiling
Area 2 (SA2) |
6.1 |
875 |
0 |
47 |
26 |
0 |
21 |
Compensatory Tree Planting |
5a |
Box Culvert: 3.0m x 2.5m |
4.1 |
100 |
100 |
57 |
19 |
0 |
38 |
On site 1:1 Compensatory Tree Planting/ Land Reinstated over Culvert |
7.1 |
800 |
0 |
|||||||
5b |
Stockpiling
Area 3 (SA3) |
7.1 |
2300 |
800 |
64 |
53 |
0 |
11 |
Compensatory Tree Planting/ Land Reinstated over Culvert |
5c |
Outfall
A |
7.1 |
40 |
20 |
0 |
0 |
0 |
0 |
None |
6a |
1800mm
Flood Relief Drain |
- |
0 |
0 |
130 |
114 |
0 |
16 |
On site 1:1 Compensatory Tree Planting |
6b |
Intake
C |
2.1 |
40 |
20 |
0 |
0 |
0 |
0 |
None |
6c |
Receiving
Pit 3 (RP3) |
2.1 |
20 |
0 |
0 |
0 |
0 |
0 |
None |
6d |
Works
Area 3 (WA3) |
2.1 |
100 |
0 |
0 |
0 |
0 |
0 |
None |
6e |
Jacking
Pit 2 (JP2) |
5.1 |
20 |
0 |
2 |
0 |
0 |
2 |
On site 1:1 Compensatory Tree
Planting |
6f |
Stockpiling
Area 4 (SA4) |
5.1 |
300 |
0 |
6 |
2 |
0 |
4 |
Land Reinstated/ Localised Compensatory Tree Planting |
6g |
Receiving
Pit 4 (RP4) |
5.1 |
20 |
0 |
0 |
0 |
0 |
0 |
None |
6h |
Works
Area 4 (WA4) |
5.1 |
100 |
0 |
4 |
0 |
0 |
4 |
On site 1:1 Compensatory Tree Planting |
6i |
Outfall
B |
5.1 |
40 |
20 |
1 |
0 |
0 |
1 |
On site 1:1 Compensatory Tree Planting |
TOTAL |
|
6175 |
2045 |
612 |
457 |
0 |
155 |
About 89 heavy standard trees / 3711m2 of hydroseeding |
7.8.2
Magnitude of Impacts to
Landscape Resources
7.8.2.1 The factors affecting the magnitude of change for assessing landscape impacts are detailed in Section 7.3.2 and include:
· Compatibility of the project with the surrounding landscape;
· Duration of impacts under construction and operation phases;
· Scale of development; and
· Reversibility of change.
7.8.2.2 As noted in Section 7.3.2, the magnitude of change in the landscape will be classified as follows:
Large: |
Notable change in the landscape characteristics over an extensive area ranging to very intensive change over a more limited area |
Intermediate: |
Moderate changes in a local area |
Small: |
Virtually imperceptible change in any components of the landscape |
Negligible: |
Indiscernible change to landscape characteristics |
7.8.2.3 The magnitude of predicted impacts on landscape resources are discussed below.
LDR-1
– Natural Stream Courses
LDR-1.1 – Seasonal
7.8.2.4 Impacts are possible at four locations:-
· LDR-1.1a - Intake A / SA1 - where streams from the east converge on the Conservation Area and are diverted into the existing water tank;
· LDR 1.1b - Works Section 1 (Chainage A1+00), proposed stormpipe will run underneath the existing open channel and temporary drainage system will be provided during construction of the proposed stormpipe for about 4 months. The existing condition will be reinstated upon completion of the proposed works;
· LDR 1.1c - Works Section 5 (Chainage B1+80), where a downhill stream enters the Project Area but does not conflict with the project works; and
· LDR 1.1d - Works Section 6, where Outfall B, will permanently discharge into the existing watercourse and the receiving pit RP4 and associated works area (WA4) are adjacently located. Minor long term impacts to the edge condition of the stream are anticipated.
7.8.2.5 In all the above situations, the impacts are localised and predominantly temporary. The works will not affect the flow or capacity of the water courses upstream and the compatibility of the impact is good through operation phase. The magnitude of change to this resource is considered to be Small during Construction Stage and Negligible during Operation Stage.
LDR-1.2 – Water Courses through
7.8.2.6
LDR 1.2a - Four natural water
courses run through the valley area. The main course runs along the north side
of the
7.8.2.7
LDR 1.2b - The second section
of natural water course is a short gulley joining the main channel close to the
bridge behind the
7.8.2.8
LDR 1.2c - The
third course runs alongside the east side of the roadway in Section 3 within
the village woodland margin vegetation. The course cuts a channel, shallow at
the north and deeper where it terminates at the vegetation area near Section 4
to the south at about 2m below road level. This seasonal drainage ditch will be
affected by the works in section 3, particularly its west bank. Reprovision of
a similar profiled drainage ditch will be required as part of the project
works.
7.8.2.9 LDR 1.2d - The fourth course runs along the project boundary on the south side of Works Section 1. Trench excavation for the proposed works will mainly be carried out on the existing access road in the near vicinity with adequate protective measures to avoid the impact to the stream. Where required, the existing stream will be reinstated similar to its original condition upon works completion.
LDR-2
– Constructed Water Courses
LDR-2.1 – Open Drainage Channels
7.8.2.10
Works will be confined to three
areas that meet the existing open channel, namely the construction of Intake B
on the section near to Ngong Ping Piazza, construction of Outfall A behind the
LDR-2.2 – Underground Drainage Channels
7.8.2.11 The underground section leading from Lin Chi Temple to the main channel will be impacted by Works Section 5 of the works at Chainage B1+10–B1+55 and require to be part excavated during construction. Reinstatement as a naturalised surface stream above the box culvert may be undertaken as part of the mitigation measures in this area following construction. The Magnitude of Change to resources is considered to be Negligible during Construction Stage and Negligible during Operation Stage.
LDR-3
– Natural Topographic Features
LDR-3.1 – Rocky Outcrops Surrounding Ngong
Ping Columbarium
7.8.2.12
Excavation for Receiving Pit 4
(RP4) will impact this resource locally. Works here are confined to the area
required for construction of Outfall B which has been restricted to approximately
90m2. However it should be noted that the construction method of
pipe jacking has been adopted through this area of
LDR-3.2 – Hillocks surrounding Tian Tan
Statue
7.8.2.13 This resource is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LDR-3.3 – Hillslopes of Nei Lak Shan
7.8.2.14 This resource is not anticipated to be impacted by the since no Project activities take place within or close to the resource boundary.
LDR-4
–
LDR-4.1 – Naturalised Hillside
7.8.2.15 Woodland blocks are anticipated to be affected in four main areas as follows:
· LDR 4.1a - Intake A / SA1, where the woodland margin of the Conservation Area is potentially impacted at the periphery, although no trees are anticipated to be removed, 4 No. large trees will need to be crown pruned and protected;
· LDR 4.1b - Works Section 1 (Chainage A0+50 to A1+10), where at least 2 No. large trees with trunk diameter over 0.45m and 10 other trees are in direct conflict with the works and will need to be removed. Refinements to the alignment during detail design shall focus on retaining some of these trees;
· LDR 4.1c - Works Section 3 (Chainage A3+20 to A3+50), where woodland is in the Site Area but not directly impacted by the works; and
· LDR 4.1d - Works Section 5 (Chainage B0+60 to B0+90), where a 300m2 area of woodland is within the site area and 2 No. trees are in direct conflict with the works and 1 large tree will be required to be removed.
7.8.2.16 The Magnitude of Change to this resource is considered to be Small during Construction Stage and Small during Operation Stage.
LDR-5
– Open
LDR-5.1 –
7.8.2.17
This resource is located within
Works Section 6 within the
LDR-6 – Village Margin Vegetation
LDR-6.1
– Unmaintained Village Scrub
7.8.2.18 Impacts are anticipated from construction activities within Works Sections 2, 3 and 4. Works Section 2 will be constructed using the pipe jacking method, minimising the impacts overall and restricting the area of any impact to Receiving Pit RP1, RP2 and Works Area WA1 and WA2. A net loss of vegetation of 110m2 is anticipated in Works Section 2 however without loss of any trees. In Works Section 3, open cut and cover trenching affects an area of 150m with a 2.5m wide trench which results in habitat loss of at least 825m2 of vegetation and removal of 3 No. trees. Works Section 4 requires clearance of a further 835m2, principally for Stockpile Area SA2. Whilst 16 No. trees are in direct conflict with the trenching for the permanent works and require to be felled, approximately 14 further trees are required to be crown pruned to enable temporary works space required for access and stockpiling of materials. Given the vegetation and tree losses, the Magnitude of Change to this resource is considered to be Intermediate during Construction Stage. As no permanent works are involved above ground it is anticipated that natural regeneration of shrub and trees would quickly take place upon reinstatement of the ground at completion of the works. Impacts may still be considered Small during Operation Stage however due to the permanent loss of the existing resources.
LDR-7
– Village Housing with Gardens
LDR-7.1 – Traditional Housing with Gardens
and Orchards
7.8.2.19 The site works area in Works Sections 1 and 2 slightly intrude on an area of hillside residences and gardens, although little physical impact is anticipated during the construction works since the majority of areas are set back from the project boundary there may be slight incursions. However, permanent works in Works Section 5 will interface directly with the village area, where 840m2 of trenching will take place, resulting in the loss of at least 35 trees. The temporary stockpile area (SA3) in this section is predicted to affect 2400m2 of tree covered orchard and garden, causing both temporary and permanent adverse impacts to more than 50 No. trees in the area. 8 No. trees are identified for retention and pruning whilst other trees will be protected within the works area. The Magnitude of Change to resources is considered to be Intermediate during Construction Stage. As no permanent works are involved above ground it is anticipated that natural regeneration of shrub and trees would quickly take place upon reinstatement of the ground and that villagers may reutilise the land in a similar manner as before the works. Impacts may still be considered Small during Operation Stage due to the permanent loss of the existing resources.
LDR-8
– Religious Institutions / Features
LDR-8.1 –
7.8.2.20 This resource is not anticipated to be impacted by the works since no Project activities take place within the resource boundary.
LDR-8.2 –
7.8.2.21 This resource is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LDR-8.3 – Ngong Ping Columbarium
7.8.2.22 Potential impacts are restricted to access issues at the Columbarium entrance as the small path is, also, the only means for access to WA4. Construction plant and materials will need to utilise this access point and waste material must also be brought out through here in order to avoid wider impacts to the surrounding natural resources. The Magnitude of Change to this resource is considered to be Negligible during Construction Stage. There are no Operation Stage impacts foreseen.
LDR-8.4 –
7.8.2.23 These resources are not anticipated to be impacted by the works. The closest grave sites are located in Works Section 6 but all are outside of the Project boundary.
LDR-9
– Maintained Amenity Features
LDR-9.1 – Ngong Ping Themed Village
7.8.2.24 This resource is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LDR-9.2 – Ngong Ping Piazza
7.8.2.25
Works Sections 2, 3 and 4 of
the works rely on construction access from Ngong Ping Piazza via
LDR-9.3 – Tian Tan Buddha
7.8.2.26 This resource is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LDR-9.4 – Hiking Paths of Nei Lak Shan
7.8.2.27 Access to the hiking trails through the Conservation Area at the east of Works Section 1 of the works may be slightly disrupted during the Construction Phase. Similarly, trails start from the access road in Section 6 within the Project boundary but no direct impact is anticipated. The Magnitude of Change to this resource is considered to be Negligible during Construction Stage. There are no Operation Stage impacts foreseen.
LDR-9.5
– Tourists Facilities around Tian Tan Buddha
7.8.2.28 This resource is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
7.8.3
Magnitude of Impact to
Landscape Character
7.8.3.1 The factors affecting the magnitude of change for assessing landscape character and the classification of impacts are detailed in Section 7.3.2 and Section 7.8.2 above. The magnitude of predicted impacts on landscape character are discussed below.
LCA1
– Inhabited Land Around
7.8.3.2 All the proposed construction works are contained within this LCA. They are relatively small in scale and not visible above the tree line apart from locally at elevated points and are, therefore, well contained within the existing landscape character setting. Ngong Ping Village has been in a state of change for the last 30 years, with recent developments, such as the construction of the Tian Tan Buddha, Po Lin Monastery Expansion, Ngong Ping Themed Village and Ngong Ping 360 Cable car, all having been significant construction projects and the scale of the proposed works are minor by comparison. The majority of permanent works are underground and will not be visible following the Construction Phase. The Magnitude of Change to this resource is considered to be Small during the Construction Stage and with almost no discernible change to the existing character anticipated following removal of construction works plant and accommodation, the change is considered Negligible during Operation Stage.
LCA2
– Foothills Surrounding Tian Tan Buddha
7.8.3.3 This area is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LCA3
– Nei Lak Shan
7.8.3.4 This area is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LCA3
– Natural Hills Surrounding Ngong Ping
7.8.3.5 This area is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
LCA4
– Upper Reaches of
7.8.3.6 This area is not anticipated to be impacted by the works since no Project activities take place within or close to the resource boundary.
7.8.4
Schedule of Impacts to
Landscape Resources and Landscape Character
7.8.4.1
The magnitude of the impacts, before
implementation of mitigation measures, on the Landscape Resources and Landscape Character Areas
that would occur in the construction and operation phases are summarised in Table
7.11 and
7.12 below.
Only those resources and character areas which are affected by the
project are listed. All impacts are adverse unless otherwise stated.
Table 7.11 Summary of Magnitude of Impacts to Landscape Resources before Mitigation
LDR |
Description |
Source
of Impact |
Extent of
Impact (Full
/ Part / Slight) |
Duration of
Impact (Short
/ Med / Long) |
Compatibility of
Impact (Good
/ Fair / Poor) |
Reversibility of
Change (Yes
/ No) |
Magnitude
of Change |
|||||
Con |
Op |
Con |
Op |
Con |
Op |
|
Con |
Op |
||||
Notes* SA – Stockpile Area / RP – Receiving
Pit / WA – Works Area / JP - Jacking Pit / Works Section Chainage - 1+80 =
180m |
||||||||||||
LDR-1.1 |
Seasonal
|
Intake A, SA1, RP1, WA1, Outfall B, RP4,
WA4. Works Section 5 B1+80 |
Slight |
Slight |
Med |
Long |
Poor |
Good |
No |
Small |
Negligible |
|
LDR-1.2 |
Water
Courses through |
Works Section
1- A0+40–A1+00 Works Section
5- B1+60–B2+24 Outfall B |
Slight |
Slight |
Med |
Long |
Poor |
Fair |
Yes |
Small |
Small |
|
LDR-2.1 |
Open
Drainage Channels |
Intake B, Outfall A, SA3, Intake C |
Part |
Part |
Med |
Long |
Fair |
Good |
No |
Small |
Negligible |
|
LDR-2.2 |
Underground
Drainage Channels |
Works Section
1- A0+90–A1+00 Works Section 5- B1+10–B1+55 |
Slight |
Slight |
Med |
Long |
Good |
Good |
No |
Negligible |
Negligible |
|
LDR-3.1 |
Rocky
Outcrops Surrounding Ngong Ping Columbarium |
Works Section
6- C1+50–C2+12 Outfall B, RP4, WA4. |
Slight |
Slight |
Med |
Long |
Poor |
Fair |
No |
Small |
Small |
|
LDR-3.2 |
Hillocks
surrounding Tian Tan Statue |
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-3.3 |
Hillslopes
of Nei Lak Shan |
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-4.1 |
Naturalised
Hillside |
Intake A, SA1, RP1, WA1, Works Section
1- A0+90–A1+10 Works Section
3- A3+20–A3+50, Works Section 5- B0+60–B0+90 |
Slight |
Slight |
Med |
Long |
Poor |
Fair |
Yes |
Small |
Small |
|
LDR-5.1 |
|
Outfall B, RP4, WA4. JP2, SA4. |
Slight |
Slight |
Med |
Long |
Poor |
Good |
Yes |
Small |
Negligible |
|
LDR-6.1 |
Unmaintained
Village Scrub |
WA2, RP2, SO,
SA2, Works Section
3- A3+00 - A4+40 Works Section
4- B0+00 - B0+50 |
Part |
Part |
Med |
Long |
Poor |
Good |
Yes |
Inter’ |
Small |
|
LDR-7.1 |
Traditional
Housing with Gardens and Orchards |
Works Section
1- A0+00 – A1+20 Works Section
2- A1+20 – A3+00 Works Section
5- B0+45 – B2+22 |
Part |
Part |
Med |
Long |
Poor |
Good |
Yes |
Inter’ |
Small |
|
LDR-8.1 |
|
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-8.2 |
|
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-8.3 |
Ngong
Ping Columbarium |
Outfall
B, RP4, WA4 |
Slight |
Nil |
Med |
Nil |
Poor |
Nil |
Yes |
Negligible |
Nil |
|
LDR-8.4 |
|
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-9.1 |
Ngong
Ping Themed Village |
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-9.2 |
Ngong
Ping Piazza |
Works Section 4- B0+00 - B0+20 |
Slight |
- |
Med |
- |
Poor |
- |
Yes |
Negligible |
Nil |
|
LDR-9.3 |
Tian
Tan Buddha |
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
LDR-9.4 |
Hiking
Paths of Nei Lak Shan |
Works Section 1- A0+00–A0+10 |
Slight |
Slight |
Med |
Long |
Poor |
Fair |
Yes |
Negligible |
Nil |
|
LDR-9.5 |
Tourists
Facilities around Tian Tan Buddha |
None |
- |
- |
- |
- |
- |
- |
- |
Nil |
Nil |
|
Table 7.12 Summary of Magnitude of Impacts to Landscape Character Areas before Mitigation
LCA |
Description |
Source
of Impact |
Extent of
Impact (Full
/ Part / Slight) |
Duration of
Impact (Short
/ Med / Long) |
Compatibility of
Change (Good
/ Fair / Poor) |
Reversibility of
Change |
Magnitude
of Change |
||||
Con |
Op |
Con |
Op |
Con |
Op |
|
Con |
Op |
|||
LCA1 |
Inhabited Land Around |
All
Construction Works |
Slight |
Slight |
Med |
Long |
Fair |
Good |
Yes |
Small |
Negligible |
LCA2 |
Foothills Surrounding Tian Tan Buddha |
None |
- |
- |
- |
- |
- |
- |
- |
- |
- |
LCA3 |
Nei Lak Shan |
None |
- |
- |
- |
- |
- |
- |
- |
- |
- |
LCA4 |
Natural Hills Surrounding Ngong Ping |
None |
- |
- |
- |
- |
- |
- |
- |
- |
- |
LCA5 |
Upper Reaches of |
None |
- |
- |
- |
- |
- |
- |
- |
- |
- |
7.9.1
Magnitude of Impact to
Visual Receivers
7.9.1.1 As detailed in Section 7.3.3, the magnitude of visual impact could result from the following:
· The context and proximity of the VSR’s location to the project;
· Other views available from the VSR’s location;
· The number of people normally present at a VSR location;
· The characteristic of the VSR (for example, resident, working, studying, etc);
· The frequency and length of the view of the proposed scheme from the VSR’s location;
· The quality of the existing view from the VSR’s location and its ability to absorb change; and
· The magnitude of change brought about by the project in relation to the overall view from the location of each VSR.
7.9.1.2 Factors affecting the magnitude of change include:
· Compatibility of the project with the surrounding landscape;
· Duration of impacts under construction and operation phases;
· Scale of development;
· Reversibility of change;
· Viewing distance; and
· Potential blockage of view.
7.9.1.3 The magnitude of change to the receivers will be classified as follows:
Large: |
e.g. the majority of viewers affected / major change in view |
Intermediate: |
e.g. many viewers affected / moderate change in view |
Small: |
e.g. few viewers affected / minor change in view |
Negligible: |
e.g. very few viewers affected / no discernible change in view |
7.9.1.4 The magnitude of predicted impacts on residential, occupational, leisure and cultural and transportation visually sensitive receivers is discussed below.
Residential
R-01: Residents of
7.9.1.5 Those residents in immediately proximity to the works are restricted to house numbers 49A, 58, 59, 64 and 65. They will have clear views of excavation and culvert construction for the duration of the project works including construction of Outfall A, Intake B, as well as the Stockpiling Areas 2 and 3. Most receivers have oblique views through the village settlement but the clearance of vegetation will open up clearer views. Residents viewing Works Section 4 may, also, have views of the required haul road. It is considered that since the works are relatively small in scale, they can generally be absorbed into the surrounding landscape and will fail to completely block the views of any receivers. The Magnitude of Change to these receivers is considered to be Intermediate during Construction Stage and Small during Operation Stage.
R-02: Residents of
7.9.1.6 The high position of these receivers means that views to the works are generally concealed behind lower ground and only those immediately on the access road have unobstructed views including house number 40 over Reception Pit 2 / Works Area 2 and house numbers 34 and 35 over Jacking Pit 1 and the Site Office. Other works affecting these residents include the construction of Intake A and the Stockpile Area 1 behind the existing water tank, although these are generally well concealed within trees. The site office may be the most conspicuous element of the construction site, however the quality of view in this area is already poorer than the surroundings. Further loss of visual amenity may occur from felling of trees in the area. The Magnitude of Change to these receivers is considered to be Intermediate during Construction Stage but Negligible during Operation Stage where no above ground works are undertaken.
R-03: Residents of
7.9.1.7 House number 39 to the south of Reception Pit 2 / Works Area 2 is currently obscured by plantation woodland but will have clear north views to the works after clearance of this vegetation for trenching on Section 3. The Jacking and Reception Pits (JA1, RP1 RP2), Works Areas 1 and 2 and the Site Office will be conspicuous during construction with a number of houses directly adjacent and looking onto the works. However, little or nothing of the project will be visible during the Operation Stage in this area, due to the ultimate underground nature of the proposed drainage improvement pipelines and box culvert. The Magnitude of Change to these receivers is considered to be Intermediate during Construction Stage and Negligible during Operation Stage.
R-04: Residents of
7.9.1.8 Restricted views to the Site Office, Jacking Pit 1, Reception Pit 1 and Works Area 1 are possible from selected buildings and windows within the Monastery, potentially at close range. However, the works are small scale in the general view and easily absorbed into the current surroundings. The Magnitude of change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
Occupational
O-01: Staff at Ngong Ping Cable Car Terminal
7.9.1.9 Views from these receivers are restricted to Works Section 6, with the Works Area 3, Jacking Pit 3 and Intake C being in direct view. Partial views to Stockpile Area 4 are possible. The viewing distance is approximately 80 meters and due to the small scale in comparison to the surroundings the Magnitude of change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
O-02: Monastery Visitors to Ngong Ping
Columbarium
7.9.1.10 These receivers are concealed within the enclosed walls of the Columbarium and will only be aware of any works from the front entrance door upon arrival and departure. The sources of impact are from Outfall B and the Works Area 4 at Reception Pit 4. They will be screened by temporary noise barriers which will be directly visible as will be any potential construction traffic to and from the works site. The Magnitude of change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
O-03: Temporary Workers at Construction Site
7.9.1.11 With adjacent views to Works Sections 3 and 5, these receivers are potentially able to view a large proportion of the works including cut and cover trenching and construction of the pipeline and box culvert. Further impacts from loss of amenity from removed vegetation are, also, anticipated. During the operational phase, the pipeline and box culvert shall be buried and change in the view will be hardly discernable. The Magnitude of Change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
Leisure
and Cultural
L-01: Users of Ngong Ping 360 Cable Car with
Elevated Views
7.9.1.12 Receivers are in elevated position and shall be able to view directly onto Works Section 6 from as close as a 20m distance. Works Areas 3 and 4, Jacking Pit 2, Reception Pits 3 and 4, Outfall B and Intake C should all be visible. During the operational stage, the works will be largely underground, with only some permanent structures remaining, including Intake C and Outfall A, which will not unduly intrude into the overall views. Outfall B, however, will not be visible during the operational phase as it will be concealed from elevated views by the surrounding topography and vegetation. Since the Works Areas 3 and 4 are very small in scale and not obscuring or dominating other views the Magnitude of Change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
L-02: Tourists moving through Ngong Ping
Piazza Viewing North
7.9.1.13 Works Section 4 of the works can be visible to receivers, especially those visiting the restaurant on the boundary of the site. The box culvert works and construction of Intake B will be most conspicuous, whilst the Stockpiling Area 4 and temporary haul road will add to the scale of the works. A number of trees will be lost in this area for the trenching works and this will further affect loss of amenity view. However, the works are located away from the main tourist thoroughfare and do not form part of the main focus view towards the Monastery or the Tian Tan Buddha. The Magnitude of Change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
L-03: Tourists at Tian Tan Buddha Viewing
South
7.9.1.14 The nearest works site in Works Section 4 is 190m from the viewing platform of the Buddha. Other areas of the project may have occasional glimpse views but it is unlikely to differentiate them within the general variety of the village, where they are obscured. At such a distance the works are easily absorbed into the general view but Works Section 4 will remain at the forefront and be apparent, although not conspicuous. The Magnitude of Change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
L-04: Hikers on Footpaths in
7.9.1.15 Hikers on distant trails may be able to view parts of all the works areas on occasion, however it shall be difficult to clearly make them out within the context of the village development. At the east end of the project works, the trails meet the works and only here can Works Section 1, Stockpile Area 1 and Intake A be clearly observed. The Magnitude of Change to these receivers, therefore, is considered to be Small during Construction Stage and Negligible during Operation Stage.
Transportation
T-01: Users of
7.9.1.16 Works Section 6 runs under and adjacent to the road and all associated works will be visible during construction. The nature of the works being predominantly underground through the use of pipe jacking means that impacts shall be limited to the Jacking Pits, Reception Pits and the associated Works Areas, whilst Intake C alone will remain visible during Operation Stage. The Magnitude of change to these receivers is considered to be Intermediate during Construction Stage and Negligible during Operation Stage.
T-02: Road Users on
7.9.1.17 Receivers shall be able to see part of the construction of Works Section 5 including the box culvert, Outfall A and Stockpile Area 3, whilst at Works Section 6, Intake C, Receiving Pit 3 and the Works Area 3 would all be visible, all at close distance. Within the overall development scale the works are fairly compatible and the Magnitude of change to these receivers is considered to be Small during Construction Stage and Negligible during Operation Stage.
T-03: Road Users on
7.9.1.18 For the duration of the travel distance the works in Works Sections 3 and 4 will be readily apparent, being immediately next to the road on the east side. During construction, potential for restricted road width and temporary access along Works Section 3 during trenching work will further highlight the works. The Magnitude of Change to these receivers, therefore, is considered to be Large during Construction Stage and Negligible during Operation Stage.
T-04: Road Users on Village
7.9.1.19 Along Works Sections 1 and 2, receivers shall continually pass directly through the Project area, being particularly proximate through the trenching works in Works Section 1. The works will dominate the continuing view at all points during construction and the Magnitude of change to receivers is considered to be Large during Construction Stage and Negligible during Operation Stage.
7.9.2
Schedule of Impacts to
Visually Sensitive Receivers
7.9.2.1 The magnitude of the impacts, before implementation of mitigation measures, on the identified Visually Sensitive Receivers that would occur in the construction and operation phases are tabulated in Table 7.13 below. All impacts are adverse unless otherwise stated.
Table 7.13 Magnitude of Impacts on Visually Sensitive Receivers before Mitigation
VSR |
Location |
Source of Impact |
Distance To Source |
Compatibility
with Surroundings (Good /
Fair / Poor) |
Scale of
Development (Small /
Med / Large) |
Duration of
Impacts (Short /
Med / Long) |
Reversibility
of change (Yes /
No) |
Potential
blockage of view (Full /
Part / Nil) |
Magnitude of
Change (Large /
Intermediate / Small /
Negligible) |
||||||
Con |
Op |
Con |
Op |
Con |
Op |
Con |
Op |
Con |
Op |
Con |
Op |
||||
R-01 |
Residents of |
Outfall A, Intake B, SA2, SA3, Temporary haul
road, S4/5 box culvert construction |
Adjacent |
Fair |
Good |
Med |
Small |
Med |
Long |
No |
Yes |
Part |
Nil |
Inter’ |
Small |
R-02 |
Residents of |
Intake A, SA1, JP1, RP1, RP2, WA1, WA2, SO, S1/3 box culvert
construction |
Adjacent |
Fair |
Good |
Med |
Small |
Med |
Long |
No |
Yes |
Part |
Nil |
Inter’ |
Neg’ |
R-03 |
Residents of |
SA1, JP1, RP1, RP2, WA1, WA2, SO |
Adjacent |
Fair |
Good |
Med |
Small |
Med |
Long |
No |
Yes |
Part |
Nil |
Inter’ |
Neg’ |
R-04 |
Residents of |
SA1, JP1, RP1, SO |
Adjacent |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
O-01 |
Staff at Ngong Ping Cable Car
Terminal |
Intake C. RP3, WA3, SA4. |
80m |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
O-02 |
Monastery visitors to Ngong Ping
Columbarium |
Outfall B, RP4, WA4. |
Adjacent |
Poor |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Part |
Nil |
Small |
Neg’ |
O-03 |
Temporary Workers at Material
Storage Yard |
S3 box culvert construction |
Adjacent |
Good |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
L-01 |
Users of Ngong Ping 360 Cable
Car with Elevated Views |
Intake C. JP2, RP3, WA3, SA4, Outfall B, RP4, WA4. |
20m |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
L-02 |
Tourists moving through Ngong
Ping Piazza Viewing North |
Intake B, SA2, S4, box culvert construction |
Adjacent |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
L-03 |
Tourists at Tian Tan Buddha Viewing South |
Intake B, SA2, S4, box culvert construction |
190m |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
L-04 |
Hikers on Footpaths in |
Undetermined. Potential partial view of all areas. |
Varies.
Eastern works are adjacent |
Good |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
T-01 |
Users of |
Intake C. JP2, RP3, WA3,
SA4, |
Adjacent |
Poor |
Good |
Med |
Small |
Med |
Long |
No |
Yes |
Part |
Nil |
Inter’ |
Neg’ |
T-02 |
Road Users on |
Outfall A, SA3, S5 box culvert construction Intake
C, RP3, WA3, |
15m |
Fair |
Good |
Small |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Small |
Neg’ |
T-03 |
Road Users on |
Intake B, SA2, S3/4 box culvert construction |
Adjacent |
Fair |
Good |
Large |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Large |
Neg’ |
T-04 |
Road Users on Village |
Intake A, SA1, JP1, RP1, RP2, WA1, WA2, SO, S1 box culvert
construction |
Adjacent |
Fair |
Good |
Large |
Small |
Med |
Long |
No |
Yes |
Nil |
Nil |
Large |
Neg’ |
Notes:
Con = Construction Phase; Op = Operation Phase; Inter’ = Intermediate; Neg’ =
Negligible
7.10
Impact Significance Threshold
7.10.1.1 The analysis of the landscape and visual impacts during construction and operation are presented in the following form of matrix to ascertain the Significance Threshold, as detailed in Table 7.1 above.
7.10.1.2 The degree of impact or Significance
Threshold is considered as follows:
Significant: |
adverse / beneficial impact where the proposal would cause significant deterioration or improvement in the existing landscape/visual quality |
Moderate: |
adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in the existing landscape/visual quality |
Slight: |
adverse / beneficial impact where the proposal would cause barely perceptible deterioration or improvement in the existing landscape/visual quality |
Insignificant: |
no discernible change in the existing landscape/visual quality |
7.10.1.3 The Significance
Threshold of those impacts, before implementation of mitigation measures, on
the Landscape Resources, Landscape Character Areas and Visually Sensitive Receivers
that would occur in the construction and operation phases is summarised in Table 7.14 - 7.16, respectively, below. All impacts are adverse
unless stated.
Table 7.14 Significance Threshold of Landscape Resources
Ref (LDR) |
Description |
Sensitivity |
Magnitude of Change |
Significance Threshold WITHOUT Mitigation |
||
Construction |
Operation |
Construction |
Operation |
|||
LDR-1.1 |
Seasonal |
High |
Small |
Negligible |
Moderate |
Insignificant |
LDR-1.2 |
Water Courses through |
Medium |
Small |
Small |
Moderate |
Slight |
LDR-2.1 |
Open Drainage Channels |
Low |
Small |
Negligible |
Slight |
Insignificant |
LDR-2.2 |
Underground Drainage Channels |
Low |
Negligible |
Negligible |
Insignificant |
Insignificant |
LDR-3.1 |
Rocky Outcrops Surrounding Ngong Ping
Columbarium |
High |
Small |
Small |
Moderate |
Moderate |
LDR-3.2 |
Hillocks surrounding Tian Tan Statue |
High |
Nil |
Nil |
Nil |
Nil |
LDR-3.3 |
Hillslopes of Nei Lak Shan |
High |
Nil |
Nil |
Nil |
Nil |
LDR-4.1 |
Naturalised Hillside |
High |
Small |
Small |
Moderate |
Moderate |
LDR-5.1 |
|
Medium |
Small |
Negligible |
Slight |
Insignificant |
LDR-6.1 |
Unmaintained Village Scrub |
Medium |
Intermediate |
Small |
Moderate |
Slight |
LDR-7.1 |
Traditional Housing with Gardens and
Orchards |
Medium |
Intermediate |
Small |
Moderate |
Slight |
LDR-8.1 |
|
High |
Nil |
Nil |
Nil |
Nil |
LDR-8.2 |
|
High |
Nil |
Nil |
Nil |
Nil |
LDR-8.3 |
Ngong Ping Columbarium |
Low |
Negligible |
Nil |
Insignificant |
Nil |
LDR-8.4 |
|
High |
Nil |
Nil |
Nil |
Nil |
LDR-9.1 |
Ngong Ping Themed Village |
Low |
Nil |
Nil |
Nil |
Nil |
LDR-9.2 |
Ngong Ping Piazza |
Low |
Negligible |
Nil |
Insignificant |
Nil |
LDR-9.3 |
Tian Tan Buddha |
High |
Nil |
Nil |
Nil |
Nil |
LDR-9.4 |
Hiking Paths of Nei Lak Shan |
Medium |
Negligible |
Nil |
Insignificant |
Nil |
LDR-9.5 |
Tourists Facilities around Tian Tan Buddha |
Medium |
Nil |
Nil |
Nil |
Nil |
Table 7.15 Significance Threshold of Landscape Character Units
Ref (LCA) |
Description |
Sensitivity |
Magnitude
of Change |
Significance
Threshold WITHOUT Mitigation |
||
Construction |
Operation |
Construction |
Operation |
|||
LCA-01 |
Inhabited Land Around |
Medium |
Small |
Negligible |
Slight |
Insignificant |
LCA-02 |
Foothills Surrounding Tian Tan Buddha |
High |
Nil |
Nil |
Nil |
Nil |
LCA-03 |
Nei Lak Shan |
High |
Nil |
Nil |
Nil |
Nil |
LCA-04 |
Natural Hills Surrounding Ngong Ping |
High |
Nil |
Nil |
Nil |
Nil |
LCA-05 |
Upper Reaches of |
High |
Nil |
Nil |
Nil |
Nil |
Table 7.16 Significance Threshold of Visually Sensitive Receivers
Ref (VSR) |
Description |
Sensitivity |
Magnitude
of Change |
Significance
Threshold WITHOUT Mitigation |
||
Construction |
Operation |
Construction |
Operation |
|||
R-01 |
Residents of |
Medium |
Intermediate |
Small |
Moderate |
Slight |
R-02 |
Residents of |
Medium |
Intermediate |
Negligible |
Moderate |
Insignificant |
R-03 |
Residents of |
Medium |
Intermediate |
Negligible |
Moderate |
Insignificant |
R-04 |
Residents of |
Medium |
Small |
Negligible |
Slight |
Insignificant |
O-01 |
Staff at Ngong
Ping Cable Car Terminal |
Low |
Small |
Negligible |
Slight |
Insignificant |
O-02 |
Monastery visitors
to Ngong Ping Columbarium |
Low |
Small |
Negligible |
Slight |
Insignificant |
O-03 |
Temporary Workers
at Material Storage Yard |
Low |
Small |
Negligible |
Slight |
Insignificant |
L-01 |
Users of Ngong
Ping 360 Cable Car with Elevated Views |
High |
Small |
Negligible |
Moderate |
Insignificant |
L-02 |
Tourists moving
through Ngong Ping Piazza Viewing North |
High |
Small |
Negligible |
Moderate |
Insignificant |
L-03 |
Tourists at Tian Tan Buddha Viewing South |
High |
Small |
Negligible |
Moderate |
Insignificant |
L-04 |
Hikers on
Footpaths in |
Medium |
Small |
Negligible |
Slight |
Insignificant |
T-01 |
Users of |
Low |
Intermediate |
Negligible |
Slight |
Insignificant |
T-02 |
Road Users on |
Low |
Small |
Negligible |
Slight |
Insignificant |
T-03 |
Road Users on |
Low |
Large |
Negligible |
Moderate |
Insignificant |
T-04 |
Road Users on Village |
Low |
Large |
Negligible |
Moderate |
Insignificant |
7.11.1.1 Potential reduction to
environmental impacts, including landscape and visual impacts, have been
considered during the development of the project design. The measures, as detailed in Section
2.5, have attempted to both avoid impacts on highly sensitive landscape
resources, particularly in the
7.11.1.2 A major consideration in
minimising impacts has been the selection of a pipe jacking construction
method, which significantly reduces the area and volume of ground excavation
required for below ground drainage systems.
Such a system has been adopted for both Works Section 2, which is
immediately adjacent to the majority of local residents, and for Works Section
6 in the
7.11.1.3 There are a number of other mitigation measures which will be employed to lessen the impact of the various elements of the project specifically upon landscape and visual receivers, both during the construction and operational phases. These recommended landscape and visual mitigation measures are scheduled in Table 7.17 and 7.18.
Table 7.17 Recommended Construction Phase Landscape and Visual Mitigation Measures
ID No.* |
Type |
Landscape / Visual Mitigation Measure |
Funding / Implementation |
Management / Maintenance |
CM1 |
Site Practice – Landscape |
No-intrusion Zone To maximize protection of existing resources
including watercourses, existing trees, ground vegetation and the associated
understory habitats a “No-intrusion Zone” will be designated to various areas
within and along the site boundary with rigid and durable fencing for each
individual no-intrusion zone. (see Figure 7.9a – 7.9c) Regular checks will be carried out to ensure that
the work site boundaries are not exceeded, hoarding is properly maintained
and that no damage is being caused to these protected areas. |
DSD |
Contractor |
CM2 |
Site Practice – Visual |
Erection of Screen Hoardings A temporary screen hoarding shall be erected
around the north side of the Site Office (SO) area to screen activities from
local receivers. It shall be designed and to be compatible with the existing
rural context, with visually unobtrusive design and colours where
appropriate. |
DSD |
Contractor |
CM3 |
Site Practice – Visual |
Control of night-time
lighting No night time work shall be programmed avoiding
light pollution to visual receivers. |
DSD |
Contractor |
Notes: * CM = Construction
Mitigation;
Table 7.18 Recommended Operational Phase Landscape and Visual Mitigation Measures
ID No.* |
Type |
Landscape / Visual Mitigation Measure |
Funding / Implement-ation |
Management / Maintenance |
OM1 |
Design / Planning – Landscape / Visual |
Compensatory Tree Planting Suitable land pockets within the project area will
be used for the implementation of compensatory mitigation to offset the net
loss of key landscape resources and improve visual amenity. A
compensatory tree planting proposal including locations of tree compensation
will be submitted separately to seek relevant government department’s
approval, in accordance with ETWB TCW No. 3/2006. |
DSD |
DSD/
DLO/ AFCD |
OM2 |
Design / Planning – Landscape / Visual |
Horizontal Greening Following
installation of underground culverts, pit excavation or utilization of land
for works or stockpiling, the ground shall be backfilled, leveled and soiled
as necessary for reinstatement prior to hydroseeding. |
DSD |
DSD / DLO / AFCD |
OM3 |
Design / Planning – Landscape / Visual |
Reinstatement of Natural Water Courses Where water courses have been affected by the
works new, naturalised stream paths shall be provided as far as applicable,
using excavated local rocks and stones, in order to create a pleasing visual
impression and potential enhanced ecological habitat. (see Figure 7.9b) |
DSD |
DSD |
Notes: * CM = Construction
Mitigation;
7.11.1.4 Given that the recommended measures are tried and tested techniques, the level of uncertainty for their effective implementation would be small. Notwithstanding, the EM&A programme will be implemented to ensure all mitigation measures are effective.
7.11.2
Tree Planting and
Greening
7.11.2.1 Within the Project boundary, the tree survey identified 612 existing trees of which 155 trees will be affected by the proposed works. It is proposed that 457 trees to be retained, whilst 155 trees are required to be felled. No transplantation of trees is proposed under this project. The tree survey report is presented in Appendix F1. Recommendations for tree felling, transplantation and retention are based on the following criteria:
· the rarity value of the species of trees involved;
· the health, condition, quality and maturity of the tree;
· the site conditions in terms of suitability for transplantation
· the suitability of the species for successful transplantation; and
· the environmental impact and amenity value of the tree.
7.11.2.2 There are no Registered Old and Valuable Trees in the project area.
The majority of trees are in conflict with activities in the temporary works
areas. Application and approval for removal for all trees shall be obtained in
accordance with ETWB TCW No. 3/2006. The actual numbers of trees to be
retained, felled and transplanted shall be subject to this process.
7.11.2.3 Compensatory planting is required to be made under ETWB TCW No. 3/2006. It should be noted that of the 155 trees proposed to be felled under the works, 65 are already dead On-site compensatory planting of about 89 new heavy standard trees will be undertaken. It is considered that tree planting within the site project areas alone provides sufficient opportunity to meet the compensatory requirements in both qualitative and quantitative terms, which has also been optimized in consideration of the land constraints and the likelihood of rapid invasion of vegetation from surrounding areas taking hold.
7.11.2.4 The following locations will be used for on-site tree planting and greening. Preliminary design plans for the areas can be seen on Figures 7.9a to 7.9e with proposed tree planting highlighted. The minimum areas of other greening will be subject to variation due to factors such as plant growth etc. and are tabulated below in Table 7.19. The precise number of trees to be retained, transplanted, felled and compensated shall be determined and agreed separately with government during the Tree Felling Application process under ETWB TC 3/2006.
Table 7.19 Compensatory Tree Planting and Greening
Location |
Area of Hydroseeding (m2)* |
Compensatory Tree Planting |
Stockpile Area 2 (SA2) |
687 |
12 |
Stockpile Area 3 (SA3) |
1713 |
12 |
Stockpile Area 4 (SA4) ( |
298 |
3 |
Works Area 2 (WA2) |
146 |
1 |
Works Area 4 (WA4) |
98 |
0 |
Works Section 2 Trench |
0 |
2 |
Works Section 3 Trench |
496 |
19 |
Works Section 5 Trench |
273 |
0 |
Works Section 6 Trench |
0 |
0 |
Ngong Ping Sewage Treatment
Plant |
0 |
40 |
TOTAL* |
3711 |
89 trees |
7.11.3.1 Since the nature of the Project means that there are no permanent
above ground structures, photomontages have not been adopted for this Report. Only 5 small elements will be visible
following completion, being the drainage pipe Intakes A, B and C and Outfalls A
and B. These are all low lying structures located below surrounding ground
level and generally inconspicuous. The use of photomontages as a tool to
demonstrate the value of employed mitigation measures at is therefore not
appropriate for this project.
7.12.1.1 The following sections examine the ‘significance’ of impacts on Landscape Resources, Landscape Character and VSRs following both construction and operation stage mitigation measures. The Significance Threshold of those impacts that would occur in the construction and operation phases is summarised in Table 7.20 and 7.21 below and illustrated on Figures 7.10 to 7.13. Residual impacts associated with these works have been assessed but no quantification of residual impacts is required.
7.12.2
Residual Impacts on
Landscape Resources
Construction Phase
7.12.2.1 Construction Phase mitigation measures are best employed in the avoidance of valuable landscape resources. Despite the use of pipe jacking technique for Works Sections 2 and 6, there remain potentially losses of trees in Works Sections 1, 2, 3, 4, 5 and 6, which result predominantly from clearance for temporary works access, particularly those areas required for stockpiling. Construction phase impact to trees has been addressed by minimising the requirements of Works and Stockpile Areas for the Project and carefully designating the extents of works areas to avoid trees as best as possible. Further work during detail design should focus further on this and in identifying minor alignment adjustments to the permanent works which may also assist in this regard.
7.12.2.2 No Significant Adverse Impacts are anticipated during Construction.
7.12.2.3 Moderate Adverse Residual Impacts are the most significant impacts anticipated and are predicted in the following resources, all related to permanent loss of mature trees:-
·
LDR-4.1 – Naturalised Hillside
· LDR-6.1 – Unmaintained Village Scrub; and
· LDR-7.1 – Traditional Housing with Gardens and Orchards.
Operation Phase
7.12.2.4 The utilisation of landscape mitigation measures during operation is to some extent able to offset the impacts generated during construction stage. Compensatory planting of native species in a form more suitable to habitat creation may produce benefits in the long term.
7.12.2.5 No Significant Adverse Impacts are anticipated during Operation.
7.12.2.6 Slight / Moderate Adverse Residual Impacts at Day 1 and Slight Adverse Residual Impacts at Year 10 are the most significant anticipated and are predicted in the following resources:
·
LDR-4.1 – Naturalised Hillside
7.12.3
Residual Impacts on
Landscape Character
Construction Phase
7.12.3.1 Only one Landscape Character Area is impacted by the project and construction works are of a small enough scale that they can be easily absorbed in the landscape character, either with or without mitigation measures. .
7.12.3.2 No Significant Adverse Impacts are anticipated during Construction.
7.12.3.3 Slight Adverse Residual Impacts are the most significant anticipated and are predicted in the following area:
·
LCA-01 – Inhabited Land around
Operation Phase
7.12.3.4 The utilisation of landscape mitigation measures during operation is able to offset the impacts generated during construction stage particularly by reinstating land to good order.
7.12.3.5 No Significant Adverse Impacts are anticipated during Operation.
7.12.3.6 Negligible Adverse Residual Impacts are the most significant anticipated at Day
1 and Year 10 and are predicted in the following area:
·
LCA-01 – Inhabited Land around
7.12.4
Residual Impacts on Visually Sensitive Receivers
Construction Phase
7.12.4.1 The works are located close to village areas and local residents are not surprisingly most affected by the project. Where the works can be screened by sensitive use of hoardings this will assist in mitigation, but in many cases elevated views over the works mean these measures are not totally beneficial.
7.12.4.2 No Significant Adverse Impacts are anticipated during Construction.
7.12.4.3 Moderate Adverse Residual Impacts are the most significant anticipated and are predicted in the following area:-
·
R-01 – Residents of
·
R-02 - Residents of
·
R-03 - Residents of
·
T-03 - Road Users on
·
T-04 - Road Users on Village
Operation Phase
7.12.4.4 The utilisation of landscape planting works during operation is able to offset the impacts generated during construction stage particularly by reinstating land to good order.
7.12.4.5 No Significant Adverse Impacts are anticipated during Operation.
7.12.4.6 Slight Adverse Residual Impacts at Day 1 and Negligible Adverse Residual Impacts at Year 10 are the most significant anticipated and are predicted in the following area:-
·
R-01 - Residents of
Table 7.20 Significance of Residual Landscape Impacts
Ref (LCA) |
Description |
Sensitivity |
Magnitude of Change |
Significance Threshold WITHOUT Mitigation |
Mitigation Measures |
Significance Threshold WITH Mitigation |
|
||||
Con |
Op |
Con |
Op |
Con |
Day 1 |
Year 10 |
|
||||
Landscape Resources |
|
||||||||||
LDR-1.1 |
Seasonal |
High |
Small |
Negligible |
Moderate |
Insignificant |
CM1 OM3 |
Moderate |
Insignificant |
Insignificant |
|
LDR-1.2 |
Water Courses through |
Medium |
Small |
Small |
Moderate |
Slight |
CM1 OM3 |
Moderate |
Insignificant |
Slight (Beneficial) |
|
LDR-2.1 |
Open Drainage Channels |
Low |
Small |
Negligible |
Slight |
Insignificant |
OM3 |
Slight |
Insignificant |
Insignificant |
|
LDR-2.2 |
Underground Drainage Channels |
Low |
Negligible |
Negligible |
Insignificant |
Insignificant |
- |
Insignificant |
Insignificant |
Insignificant |
|
LDR-3.1 |
Rocky Outcrops Surrounding Ngong Ping
Columbarium |
High |
Small |
Small |
Moderate |
Moderate |
CM1 OM2 |
Slight |
Insignificant |
Insignificant |
|
LDR-3.2 |
Hillocks surrounding Tian Tan Statue |
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-3.3 |
Hillslopes of Nei Lak Shan |
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-4.1 |
Naturalised Hillside |
High |
Small |
Small |
Moderate |
Moderate |
CM1 OM1,OM2 |
Moderate |
Moderate |
Slight |
|
LDR-5.1 |
|
Medium |
Small |
Negligible |
Slight |
Insignificant |
CM1 OM2 |
Slight |
Insignificant |
Insignificant |
|
LDR-6.1 |
Unmaintained Village Scrub |
Medium |
Intermediate |
Small |
Moderate |
Slight |
CM1 OM1,OM2 |
Moderate |
Moderate |
Slight |
|
LDR-7.1 |
Traditional Housing with Gardens and
Orchards |
Medium |
Intermediate |
Small |
Moderate |
Slight |
CM1 OM1,OM2 |
Moderate |
Moderate |
Slight |
|
LDR-8.1 |
|
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-8.2 |
|
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-8.3 |
Ngong Ping Columbarium |
Low |
Negligible |
Nil |
Insignificant |
Nil |
- |
Insignificant |
Nil |
Nil |
|
LDR-8.4 |
|
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-9.1 |
Ngong Ping Themed Village |
Low |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-9.2 |
Ngong Ping Piazza |
Low |
Negligible |
Nil |
Insignificant |
Nil |
- |
Insignificant |
Nil |
Nil |
|
LDR-9.3 |
Tian Tan Buddha |
High |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
LDR-9.4 |
Hiking Paths of Nei Lak Shan |
Medium |
Negligible |
Nil |
Insignificant |
Nil |
- |
Insignificant |
Insignificant |
Insignificant |
|
LDR-9.5 |
Tourists Facilities around Tian Tan Buddha |
Medium |
Nil |
Nil |
Nil |
Nil |
- |
Nil |
Nil |
Nil |
|
Landscape Character Areas |
|
||||||||||
LCA-01 |
Inhabited Land Around |
Medium |
Small |
Negligible |
Slight |
Insignificant |
CM1,2,3 OM1,2,3 |
Slight |
Insignificant |
Insignificant |
Notes: Con = Construction
Phase; Op = Operation Phase
Table 7.21 Significance of Residual Visual Impacts
Ref (VSR) |
Description |
Sensitivity to Change |
Magnitude of Change |
Significance Threshold WITHOUT Mitigation |
Mitigation Measures |
Significance Threshold WITH Mitigation |
||||
Con |
Op |
Con |
Op |
Construction |
Day 1 |
Year 10 |
||||
Residential VSRs |
||||||||||
R-01 |
Residents of |
Medium |
Intermediate |
Small |
Moderate |
Slight |
CM 2, 3 |
Moderate |
Slight |
Insignificant |
R-02 |
Residents of |
Medium |
Intermediate |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Moderate |
Insignificant |
Insignificant |
R-03 |
Residents of |
Medium |
Intermediate |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Moderate |
Insignificant |
Insignificant |
R-04 |
Residents of |
Medium |
Small |
Negligible |
Slight |
Insignificant |
CM 1,2 |
Slight |
Insignificant |
Insignificant |
Occupational VSRs |
||||||||||
O-01 |
Staff at Ngong Ping Cable Car Terminal |
Low |
Small |
Negligible |
Slight |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
O-02 |
Monastery visitors to Ngong Ping Columbarium |
Low |
Small |
Negligible |
Slight |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
O-03 |
Temporary Workers at Material Storage Yard |
Low |
Small |
Negligible |
Slight |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
Leisure & Cultural VSRs |
||||||||||
L-01 |
Users of Ngong Ping 360 Cable Car with Elevated
Views |
High |
Small |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
L-02 |
Tourists moving through Ngong Ping Piazza Viewing
North |
High |
Small |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
L-03 |
Tourists at
Tian Tan Buddha Viewing South |
High |
Small |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
L-04 |
Hikers on Footpaths in |
Medium |
Small |
Negligible |
Slight |
Insignificant |
CM 3,4 |
Slight |
Insignificant |
Insignificant |
Transportation
VSRs |
||||||||||
T-01 |
Users of |
Low |
Intermediate |
Negligible |
Slight |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
T-02 |
Road Users on |
Low |
Small |
Negligible |
Slight |
Insignificant |
CM 2,3 |
Slight |
Insignificant |
Insignificant |
T-03 |
Road Users on |
Low |
Large |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Moderate |
Insignificant |
Insignificant |
T-04 |
Road Users on Village |
Low |
Large |
Negligible |
Moderate |
Insignificant |
CM 2,3 |
Moderate |
Insignificant |
Insignificant |
7.13.1.1 No planned or concurrent projects have been identified. Currently works are being undertaken by Po Lin Monastery for construction of The Grand Hall of Ten Thousand Buddhas which includes a shrine hall, an exhibition hall, a meditation hall, an abbot's chamber, a scripture library and other multi-functional facilities. This construction is scheduled for completion in 2012 and will not coincide with the drainage improvement works.
7.14
Environmental Monitoring and Audit
7.14.1.1 The landscape and visual mitigation measures proposed shall be incorporated in the Construction Contract including the protection of existing trees, conservation of topsoil, and the requirements for successful establishment and growth of new tree planting and shrubs, so as to ensure the effectiveness of the mitigation measures described above. The designs shall be checked by the Project Proponent to ensure that further measures are fully incorporated in order that potential conflicts with civil engineering, geo-technical, structural, lighting, signage, drainage, underground utility and operational requirements are resolved prior to construction. Any changes to the mitigation measures that may be recommended to meet alterations in the baseline conditions or to match on-going EM&A shall also be incorporated as early as possible into in the contract documentation.
7.14.1.2 The design, implementation and maintenance of mitigation measures shall be checked regularly by the Environmental Team (ET) during the Environmental Monitoring and Audit (EM&A) to ensure that they are fully realised and compliant with the intended aims of the measures. Any potential conflicts among the proposed mitigation measures, the project works, and operational requirements should also be identified and resolved early.
7.14.1.3 The extent of the agreed works areas shall be regularly checked during the construction phase by the Environmental Team (ET). Any trespass by the Contractor outside the limit of the works leading to damage to existing trees shall be reported to the Independent Environmental Checker and Engineer’s Representative. Further details of the specific EM&A requirements are detailed in Section 10 of this report and in the EM&A Manual under separate cover.
7.14.2.1 A specialist landscape sub-contractor should be employed by the works Contractor for the implementation of tree and landscape works and subsequent maintenance operations during the establishment period. The planting should commence during the construction contract and monitoring of the planting establishment should be undertaken for a 12 month period which could extend throughout the Contractor’s one-year maintenance period, which will be within the first operational year of the project. Further details of the specific EM&A requirements are detailed in Section 10 of this report and in the EM&A Manual under separate cover.
7.15.1.1 The project has unavoidable Landscape and Visual Impacts resulting primarily from areas of excavation for trenches, construction pits for the trenchless excavation and the formation of intakes and outfalls arising during the construction phase. Further potential impacts are caused from temporary works and stockpile sites. In summary:
·
The project is generally compatible with the statutory planning
framework;
·
Impacts have been minimised through careful consideration of alternatives
and selection of alternative construction techniques; and
·
No Significant Adverse Residual Impacts to Landscape Resources, Landscape
Character or VSRs are generated by the Project at any stage.
7.15.1.2 It is considered that the Project would be generally in accordance with the planning goals and objectives for the study areas. Two areas are in potential conflict however, as follows:
· Stockpile Area 1 (SA1).
· Works Section 6.
7.15.1.3 The following permanent loss of landscape resources is anticipated:
· 90m2 of natural rock and vegetation at the outfall close to the Ngong Ping Columbarium;
· A total of 612 existing trees have been surveyed covering the Project Area. Some 155 trees are proposed to be felled of which 65 are dead trees. Those trees found to be directly in conflict with the construction works which cannot be retained have not been considered suitable for transplantation. None of the trees identified for removal are Registered Old and Valuable Trees. Application and approval for removal for all trees shall be obtained in accordance with Environment Transport and Works Bureau Technical Circular (Works) No, 3/2006.
7.15.1.4 A total of 15 VSRs are identified within the project. Moderate Adverse Visual Impacts might be anticipated during Construction Phase to 8 VSR’s without mitigation. During Operational Phase Slight Adverse Impacts may remain at Year 10 to VSR-01, Residents of Ngong Ping Village surrounding Works Sections 4&5.
7.15.1.5 The following mitigation measures are proposed to be undertaken:
Construction Phase
· No-intrusion Zone;
· Decoration of Hoarding; and
Control of night-time
lighting glare, however, currently no night-time working is proposed.
Operation Phase
· Compensatory Tree Planting - A minimum of 89 new trees will be provided within the site areas of the project;
· Horizontal Greening - Ground reinstatement with 3711m2 of hydroseeding;
· Reinstatement of Water Courses affected by the Project with reuse of existing local rocks and stones;
7.15.1.6 Following the introduction of landscape mitigation measures, the
most notable Construction Phase Residual Impacts to Landscape Resources are Moderate Adverse in 6 resource areas.
During Operation Phase the most notable Residual Impacts are Moderate Adverse at Day 1 and Slight at Year 10.
7.15.1.7 Following the introduction of landscape and visual mitigation
measures, the most notable Construction Phase Residual Impacts to Landscape
Character Areas are Slight Adverse in
1 area. During Operation Phase Impacts are Insignificant
at Day 1 and at Year 10.
7.15.1.8 Following the introduction of visual mitigation measures, the most notable Construction Phase Residual Impacts to VSR’s are Moderate Adverse in 5 areas. During Operation Phase the most notable Impacts are Slight Adverse at Day 1 to just 1 VSR and Insignificant to all VSR’s at Year 10.
7.15.1.9 With reference to the criteria defined in Annex 10 of the EIAO-TM, it is considered that the Adverse Landscape and Visual Impacts resulting during Construction and Operation Stages are considered Acceptable with the prescribed Mitigation Measures applied.