12.1.1.1
This EIA study predicted that, with the implementation
of the recommended mitigation measures, the Ngong Ping drainage improvement project
would be environmentally acceptable with no adverse residual impacts on the
population and environmental sensitive resources. Table
12.1 summarises the
environmental outcomes and benefits that accrued from the environmental considerations
and analysis during the EIA process and the implementation of environmental
control measures of the Drainage Improvement Works at Ngong
Ping. The requirements for the EM&A
programme have been recommended, where necessary, to check on project
compliance with environmental legislation and standards.
Table 12.1: Summary
of Key Environmental Outcomes
Area/Issue |
Environmental Outcomes |
The Ngong Ping Drainage Improvement Project |
Following
serious flooding at the Po Lin Monastery, Ngong Ping Bus Terminus, Ngong Ping
Village and areas in the vicinity of the Ngong Ping 360 Terminal in 2008, a
study by the Drainage Services Department (DSD) identified that the flood
protection level of the existing watercourses at the north of Po Lin
Monastery, as well as the upstream and downstream of Ngong Ping 360 Terminal,
is less than 1 in 10 years design return period and recommended a series of
drainage improvement works. The
project will include the following three main areas of improvement works: ·
Northwest of the Po Lin Monastery near ·
Northern side of the Ngong Ping 360 Terminal and
Columbarium (Downstream Section): Flood Relief Drain comprising a new underground box drainage pipe of 198m in length. |
Environmentally Friendly Design Recommended |
While the selected alignment scheme
offers several environmental advantages over other schemes considered during
both the construction and operation phases.
The adoption of the underground drainage design will reduce the
permanent habitat loss to a few manholes only and these manholes have mostly
been located within developed areas rather than natural habitats. Both the loop system and flood relief
drain have been designed to avoid directly affecting the existing stream
ecology and minimising the works in the natural stream section to only a
small bank-side area for construction of Outfall B. Therefore, direct
ecological impacts to the natural stream and associated riparian ecology
would be almost completely eliminated during the construction stage. Given
that streams in the area are hydro-dynamically linked to the Ngong Ping
Stream in the Ngong Ping SSSI which is an important habitat for the endemic
Romer’s Tree Frog as well as other fauna, this is considered a key
environmentally friendly feature of the design. In respect of water quality, as the
existing watercourse would remain untouched overall, with the exception of
only five small areas for the inlets and outfalls, the potential construction
phase water quality impacts would be minimised while still achieving the
overall design objectives. From an ecological and landscape and visual impact, the design of the
alignment has followed existing access roads and paths wherever possible to
avoid impacts to natural habitats and also a trenchless construction method
is proposed for two of the six works sections to minimise the open cut trench
and the removal of habitats and vegetation.
All works and stockpiling area locations have been carefully selected
to avoid natural habitats and species of conservation interest as far as
practical. This also minimises the
amount of waste materials and the noise, dust and construction run-off that
may result. Specifically, the location of Outfall B has been
shifted southwards during the design development by about 13m such that it
would not be located at a rocky cliff face and connect to the existing
shallow pool area near the Columbarium. This has the advantage of making the
Outfall B structure less visually prominent and allows a patch of protected orchids species in the cliff area to be avoided and
retained. Stockpiling Area SA4 has
also been relocated to the east of Works Section 6 to avoid some floral
species of conservation interest. The proposed drainage scheme is overall
further away from key sensitive receivers, thereby helping to reduce the
magnitude of any air and noise impacts. There are no |
Population and Environmentally Sensitive Areas Protected |
With the adoption of the environmentally friendly design in the
preferred option, the major environmental sensitive receivers will be
protected. This preferred option is
determined based on the comparison of the environmental benefits and
dis-benefits of the various options and alternatives and has been selected on
the basis that it minimises environmental impacts and presents overall
environmental benefits over the other options and is considered the optimum
scheme from an environmental perspective.
|
Air Quality |
Potential dust impacts would be generated from excavation activities,
material handling, wind erosion, spoil removal, material delivery, during the
construction phase. Fugitive dust impacts would be controlled by the
implementation of dust suppression measures as stipulated in the Air
Pollution Control (Construction Dust) Regulation, good site practices and
proposed mitigation measures. With the implementation of mitigation measures
in the Air Pollution Control (Construction Dust) Regulation, proposed dust
suppression measures including hourly watering of exposed area, together with
good site practices, 1-hour, 24 hour and annual adverse residual impacts are
predicted to be insignificant. |
Noise |
Without mitigation, given the close proximity of the sensitive
receivers to the works, the noise levels would be anticipated to exceed the
relevant criteria by up to about 18dB(A) at some
NSRs. Mitigation measures are,
therefore, recommended to reduce the noise levels to within the EIAO-TM noise
criterion, including provision of quieter plants, silencers, noise barriers,
enclosures and insulating fabric.
After these mitigation measures are adopted, the noise levels at all
but one representative NSR would meet the relevant criteria. Further
mitigation has been proposed to install a temporary noise barrier of 2.5m in
height or in a height which can provide sufficient screening of the vibrating
hammer between the NSR and the open cut trench along the 44m segment in order
to further mitigate noise impacts. However, one NSR, a village house
very close the works, would subject to residual impacts of between 4-6dB(A). As such,
all practicable noise mitigation measures will be exhausted to minimise the
residual impacts, e.g. good site practices such as orientating the noisy
plant away from the nearby NSRs, intermittent use of plant, proper fitting of
silencers and mufflers on the construction equipment, avoidance of noisy
construction works during the examination period etc. Residual impacts have been assessed and
concluded to be temporary, reversible and unlikely to induce public health
concern to the community and as such, are considered to be acceptable. |
Water Quality |
While direct impacts to the natural stream
are minimised, the limited works required for the intake and outfalls will be
undertaken in the dry season wherever possible. Other water quality impacts from
construction activities would be in the form of construction run-off and this
will be controlled by implementing the recommended mitigation measures, such
as covering or reinstating exposed areas as soon as possible and confining
stockpiling to designated areas, to minimise construction run-off and
particularly on-site treatment of any contaminated wastewater prior to
discharge. Adverse residual impacts would not be
anticipated. No operational impacts
are predicted and environmental resources are being
protected by the mitigation measures. |
Ecology |
The potential
ecological impacts have been substantially reduced by adoption of the
terrestrial by-pass routing instead of direct widening and training of the
natural Potential indirect
impacts due to sedimentation and contamination will be controlled through a
series of mitigation measures. Ecological mitigation
measures have focused on the protection of species of conservation interest
that may be affected. Two floral
species of conservation interest in Works Area WA4 will be transplanted. Two floral species near WA4 will require
suitable protection. Three aquatic faunal species that could be affected by
the trench crossing section in Works Section 1 or as a result of works in
WA4/Outfall B in Works Section 6 will be translocated prior to the works. |
Landscape and Visual |
The Project would be generally in accordance with the planning goals
and objectives for the study areas but two areas are in potential conflict
however, as follows: ·
Stockpile Area 1 (SA1);
and ·
Works Section 6 The project has unavoidable Landscape and Visual Impacts resulting
primarily from areas of excavation for trenches, construction pits for the
trenchless excavation and the formation of intakes and outfalls, temporary
works and stockpile sites. However, as
the drainage design has minimized vegetation removal as much as possible by
building along existing access roads, paths or development areas as much as
possible, adopting trenchless construction where practicable and utilizing an
underground pipeline scheme, no Significant Adverse Residual Impacts to
Landscape Resources, Landscape Character or VSRs are generated by the Project
at any stage. A total of 612 existing trees have been surveyed covering the Project
Area. Some 155 trees will be affected by the proposed works and 155 are
proposed to be felled of which 65 are dead trees. Those
trees found to be directly conflict with the construction works which cannot
be retained have not been considered suitable for transplantation. None of these are Registered Old and
Valuable Trees. The compensatory planting regime would include planting of a
minimum of 89 heavy standard trees at a compensation level of 1:1, in
addition to 3711m2 of hydroseeding. |
Cultural Heritage |
The archaeology assessment did not identify any
areas of archaeological potential and no impacts are predicted. There are no |
Waste Management Implications |
Construction waste arisings have been identified based on the
proposed construction activities and would comprise C&D materials
(including excavated materials, materials from demolition works and site
formation), general refuse from workforce, chemical waste from maintenance of
construction plant and equipment and sewage from on-site staff and workers. Provided that the identified waste arisings
are to be handled, transported and disposed of using approved methods and the
recommended good site practices are to be followed, adverse environmental
impacts would not be expected during the construction phase. The types of waste generated during the operation of the project
would be limited to inert materials (e.g. sand, boulder, etc) and non-inert
materials (e.g. rubbish, tree debris, etc) removed from the maintenance of
the drainage system will but as the quantities will be negligible, adverse
impacts would not be expected during the operational phase of the project. |