5                        ECOLOGY

5.1                   Background

5.1.1.1       The EIA has recommended that an EM&A for ecology is undertaken during the construction and operational / post-construction phases of the project. Certain construction phase mitigation measures and EM&A, such as surveys and subsequent transplantation of floral species, for example, would need to be undertaken in the pre-construction phase, or baseline phase of the works.

5.1.1.2       The EM&A objectives are to ensure that the ecological contract works and construction mitigation procedures recommended in the EIA are carried out as specified and are effective.  The baseline phase EM&A will be carried pre-construction before any construction works commence. The construction and operational / post-construction phase EM&A will be carried out as part of the site monitoring and audit programme.

5.2                   Ecology EM&A Procedures

5.2.1.1       The baseline construction phase ecological EM&A will entail the preparation of plans and undertaking surveys required to ensure the baseline conditions are confirmed with respect to species of conservation interest, together with the implementation of species protection measures and transplantation/translocation of species as necessary.  In addition, a broad walk-over survey of the Project Area is recommended to confirm the existing habitats. 

5.2.1.2       The construction phase ecological audit is concerned with checking the effectiveness of the implementation of the ecology transplantation/translocation and protection measures, together with auditing the effectiveness of the overall ecological site mitigation.  The audit of the re-establishment of the enhancement and compensatory planting would extend into the post-construction phase and operational phase (the Contractor’s one year maintenance period) and is discussed in Section 6 of this EM&A Manual. The overall procedures for the ecological EM&A during pre-construction, construction and operation are shown in Figure 5.1.

5.3                   Construction Phase Mitigation and Enhancement Measures

5.3.1                     Protection of Fauna and Floral Species of Conservation Interest

5.3.1.1       Mitigation measures to preserve ecological resources within and at the border of the site works area have been recommended by the EIA.  Ecological mitigation and enhancement measures recommended by the EIA are largely related to the protection of key floral and fauna species as discussed below.     

5.3.2                     Enhancement Planting

5.3.2.1       With the design consideration, the habitats directly affected by the proposed Project have been reduced to a total of 0.47ha which is only about 0.3% of the habitat within the Study Area. The permanently affected total habitat, comprising developed land, plantation woodland, secondary woodland and shrubland, is a small proportion of this at 0.02ha, which is about 0.008% of the available habitat.  The ecological impacts from the proposed project to the various habitats have been ranked between “insignificant” and “minor” and habitat compensation is considered not necessary. 

5.3.2.2       Nonetheless, landscape compensatory planting is recommended as mitigation for the loss of landscape (refer to Section 7 of the EIA Report and Section 6 of this EM&A Manual), but, in addition, this will, also, serve the function as an enhancement to the tree and habitat loss as a result of drainage improvement works. 

5.3.3                     Surface Run-off

5.3.3.1       Minimisation mitigation measures required to protect water quality and the three aquatic faunal species of conservation would comprise controlling surface run-off.   A series of mitigation measures to effective minimise water quality impacts potential arise from the project and accidental spillage have been recommended in Section 5 of the EIA Report and Section 4 of this EM&A Manual.  Strict compliance of these recommendations will ensure the indirect impact to ecology, in particular the aquatic system, will be minimal. These control measures largely follow the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94). The more essential recommendation are briefly summarised below:

·               All works should be undertaken within the dry season, where practical;

·               Perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works and erosion and sedimentation control facilities implemented;

·               Channels (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided to divert the stormwater to silt removal facilities;

·               Oil interceptors should be provided in the drainage system downstream of any oil/fuel pollution sources;

·               Stockpiled material shall be covered by tarpaulin and /or watered as appropriate to prevent windblown dust and surface run off;

·            Overnight stockpiling of earthed material along the exposed trench shall be minimised as far as possible and excavated soil shall be transferred to the designated stockpiling area as soon as possible;

·            All bentonite slurry shall be suitably stored in accordance with Section 5.8.8 of this EIA Report to minimise the chance of spillage;

·               All fuel tanks and storage areas should be provided with locks and sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank to prevent spilled fuel oils; and

·               Pipe jacking areas shall be closely monitored for frac-outs release of bentonite and frac-out area immediately cleaned if they occur.

 

5.3.3.2       The particular measures to protect the ecology of the Lantau North Country Park are summarised below:

·            Major stockpiled areas shall be sited outside of the country parks area (Works Section 6) and away from stream courses as far as practicable;

·            All backfilling material and cement required for Works Section 6 shall be delivered only in the quantities required;

·            No storage of chemical waste in Works Section 6; and

·            No construction plant maintenance facilities in Works Section 6.

5.3.3.3       Also, as detailed in Section 2.5.6 of the EIA Report, the location of Stockpiling Area SA4, has been relocated during the design evolution stage of the project to avoid floral species of conservation interest. In addition to the above, to prevent stream bank erosion and directly affect the stream ecology, treated site drainage shall be discharged via the existing drainage system or diverted to the artificial channel. No site drainage shall be allowed to be discharged at the natural stream bank.

5.4                   Operation Phase Mitigation Measures

5.4.1.1       The operation of the proposed drainage system will provide a by-pass floodway during periods of high flows which will require minimal maintenance requirements. Thus, the project is not anticipated to induce any adverse ecological impacts during the operational phase and operational phase mitigation measures are not required. Nevertheless, if desiliting works at the intakes are found to be required, it is recommended as a precautionary measure that works shall be conducted during the dry season to avoid any secondary impacts due to temporary deterioration of water quality.  No audit of these works would be required.

5.5                   Pre-Construction and Construction Phase EM&A

5.5.1             Background

5.5.1.1       EM&A for ecology is required during the pre-construction and construction phases only and comprises the implementation by the ET of various measures including surveys and transplantation works and the on-going auditing of these measures, together with the Contractor implemented mitigation measures for habitat and species protection, enhancement planting and construction run-off.

5.5.1.2       The key issue for the EM&A is the species of conservation interest.  During the baseline ecology survey in the EIA stage, twenty three floral and faunal species of conservation interest were found within the Study Area, 10 floral species were noted within the Project Area of which two were noted to be within designated working areas (WA/SA).  There is the potential for direct and indirect impacts on these species and the EIA has recommended a series of pre-construction mitigation measures to avoid and minimise the potential impacts.  The success of these measures will, also, be audited during the construction phase.  Pre-construction mitigation measures have also been recommended to protect the potential impacts to the faunal species of conservation interest.  A summary of potential construction impacts to all species of conservation interest recorded is presented in Table 5.1.

Table 5.1       Overall Impacts to Species of Conservation Interest

Species / Group

Location Recorded

Significance of Potential Impacts

 

Study Area (excluding PA)

Project Area (PA)

Designated Area in PA

Direct

Indirect

Flora

 

 

 

 

 

1. Incense Tree

Aquilaria sinensis

Secondary woodland

Plantation woodland and shrubland

 

No

No

2. Ambrosia Orchid

Bulbophyllum ambrosia

-

Riparian shrubland

-

No

Yes

3. Eurya-leaved Camellia

Camellia euryoides

Riparian secondary woodland

Riparian shrubland

WA4

Yes

No

4. Tea

Camellia sinensis

Agricultural land, secondary woodland and shrubland

Developed area

-

No

No

5. Lamb of Tartary

Cibotium barometz

Shrubland, secondary woodland

-

-

No

No

6. Brown Rock-orchid

Coelogyne fimbriata

-

Riparian shrubland

-

No

Yes

7. Heliotrope Ehretia Ehretia acuminata

Developed area

Plantation woodland and shrubland

 

No

No

8. Chinese New Year Flower

Enkianthus quinqueflorus

Shrubland

Shrubland

WA4

Yes

No

9. Walking-stick Orchid

Geodorum densiflorum

Shrubland

Gabion channel

-

No

No

10. Small-fruited Honeylocust

Gleditsia australis

-

Plantation

 

No

No

11. Chinese Lily

Lilium brownii

Shrubland

-

-

No

No

12. Hong Kong Pavetta

Pavetta hongkongensis

Plantation

-

-

No

No

13. Mrs. Farrer’s Rhododendron Rhododendron farrerae

Riparian plantation

Shrubland

-

No

Yes

14. Rungia pectinata

Secondary Woodland

-

-

No

No

Mammals

 

 

 

 

 

15. Himalayan Leaf-nosed Bat

Hipposideros armiger

Developed area

-

-

No

No

16. Japanese Pipistrelle Pipistrellus abramus

Developed area and plantation

-

-

No

No

Avifauna

 

 

 

 

 

17. Eastern Cattle Egret

Bubulcus coromandus

Gabion channel

-

-

No

No

18. Black Kite

Milvus migrans

Secondary woodland and shrubland

-

-

No

No

19. White-bellied Sea Eagle

Haliaeetus leucogaster

Shrubland

-

-

No

No

20. Eurasian Eagle Owl

Bubo bubo

Shrubland

-

-

No

No

Reptiles

 

 

 

 

 

21. Reeves’ Terrapin

Mauremys reevesii

Stream (sampling point W8)

-

-

Possible(1)

Yes

Amphibians

 

 

 

 

 

22. Lesser Spiny Frog Quasipaa exilispinosa

Stream (sampling point R2, W1 and W2)

-

-

Possible(1)

Yes

Freshwater Macroinvertebrate

23. Stream Crab Somanniathelphusa zanklon

Stream (sampling points R1, R2, R6, W2 and W8)

-

-

Possible(1)

Yes

No of floral species of conservation interest(1)

11

10

2

2

3

No of faunal species conservation interest(2)

9

0

0

0

3

Notes (1):  These aquatic species have limited mobility and were not observed in the works area during the baseline surveys for the EIA study. However, the directly affected stream stretch is a suitable habitat for them and they could be present when the construction works begin.

5.5.2             EM&A Requirements

5.5.2.1       The recommended ecological mitigation requires EM&A activities during both the pre-construction and construction stages and should be prepared, implemented and audited by a qualified ecologist as part of the ET and will consist of the following items detailed in Table 5.2 below:

Table 5.2             EM&A Requirements

Reference

Mitigation Measures

Implementation Phase

Pre-Construction

Construction

1

Audit of Enhancement Planting

-

Y

2

Audit of Run-off control

-

Y

3

Preparation of Updated Baseline Vegetation Survey

Y

-

4

Preparation of Floral Protection Plan

Y

-

5

Auditing of Floral Protection Plan

-

Y

6

Preparation of Floral Transplantation Plan

Y

-

7

Floral Transplantation Works

Y

-

8

Auditing of Transplantation Works

-

Y

9

Preparation of Aquatic Fauna Translocation Plan

Y

-

10

Aquatic Fauna Translocation Survey and Translocation Works

Y

-

11

Audit of overall habitat protection measures

-

Y

 

5.5.2.2       Further details of these EM&A requirements are provided below.

Enhancement Planting and Construction Run-off – Items 1 & 2 (Table 5.2)

 

5.5.2.3       The Environmental Team (ET) (refer to Section 1 for a description of the ET and duties) shall be responsible for auditing the Contractor’s compliance with the recommended with respect to the enhancement planting works and the implementation of the recommended mitigation measures to control construction phase run-off.   Auditing for these tasks will be undertaken solely in the construction phase.   Auditing will be undertaken at least weekly in accordance with accordance with Section 9 of this EM&A Manual. 

Updated Baseline Vegetation Survey – Item 3 (Table 5.1)

 

5.5.2.4       As detailed in the EIA report (Table 6.27), there is predicted to be a direct loss of a few individuals of Camellia euryoides and Enkianthus quinqueflorus as a result of Works Area WA4.  Indirect impacts could occur to the other individuals of Aquilaria sinensis and Gleditsia australis close to Stockpiling Area SA4 and to the orchids Bulbophyllum ambrosia, Coelogyne fimbriata, Rhododendron farrerae, Aquilaria sinensis and Ehretia acuminata close to Stockpiling Area SA4 and WA4. 

5.5.2.5       As there will be a time lapse until the start of the construction contract and given the dynamic nature of the natural environment, it is recommended that prior to the site clearance works, an “Updated Baseline Vegetation Survey” shall be conducted by a qualified ecologist and land surveyor of the Environmental Team (ET) to reconfirm the status of the floral species of conservation interest present in the Project Area within Works Section 6. This will allow a more focused plan of transplantation or protection to be formed. The position of each individual floral species of conservation interest, including those listed in Table 5.1 and any new species found, shall be precisely recorded in 1:500 topographical maps.

5.5.2.6       Based on the survey finding, the Environmental Team (ET) ecologist, in association with the Contractor shall review if these species can be preserved in-situ or have to be transplanted based on the final design of the improvement works.  Wherever possible, priority shall be given to in-situ preservation over off-site transplantation.  An evaluation of the recommended mitigation measures are presented in the EIA Report (Table 6.28), although these will be subject to confirmation following the Updated Baseline Vegetation Survey. 

5.5.2.7       The ecologist(s) of the Environmental Team shall seek the Engineer, the Independent Environmental Checker (IEC), Environmental Protection Department and Agriculture, Fisheries and Conservation Department’s approval on the “Updated Baseline Vegetation Survey”.  The “Updated Baseline Vegetation Survey” report shall be undertaken in the pre-construction phase and the report be submitted at least two months before the works commence.

Floral Protection Plan - Items 4 & 5 (Table 5.2)

 

5.5.2.8       Based upon the findings of the “Updated Baseline Vegetation Survey”, for the individual species of conservation interest that can be in-situ preserved, the ET shall prepare a “Floral Protection Plan” for each species in the pre-construction phase for submission at least one month in advance of the works commencing to specifically define the protection measures required in each case. The possible measures for in-situ preservation include:

·               Restricting access to the floral species of conservation interest by mean of fencing, railing or temporary barriers.  Enclosing or bunding the species shall be considered as the last resort;

·               Restricting the works activities to within designated works area by mean of fencing, railing or temporary barrier; and

·               Controlling site-runoff if the species is located downstream of works area.

5.5.2.9       Whenever possible, it is recommended that solid fencing be erected at the access entrance to the floral species to be protected before the commencement of works to prevent vehicle movements and encroachment of personnel into adjacent areas where these species are located.  All the proposed in-situ preservation measures shall be audited by the ET at least monthly to ensure that the approved “Floral Protection Plan” is properly implemented and that damage does not occur to the flora being protected and, also, the surrounding environment.  In addition, environmental briefing/training sessions should be provided and scheduled for site staff to raise their awareness on environmental protection.

5.5.2.10   The ecologist(s) of the Environmental Team shall seek the Engineer, the Independent Environmental Checker (IEC), Environmental Protection Department and Agriculture, Fisheries and Conservation Department’s approval on the “Floral Protection Plan” prior to implementing the recommendations.

5.5.2.11   The on-going audit of the implementation of the recommendations of the “Floral Protection Plan” will continue into the construction phase and the audit schedule is detailed in Table 5.3 below. 

Floral Transplantation Plan – Item 6, 7 & 8 (Table 5.2)

 

5.5.2.12   Based upon the findings of the “Updated Baseline Vegetation Survey”, for those species that cannot be preserved in-situ, each shall be transplanted. The ET shall submit a detailed “Floral Transplantation Plan” for each species in the pre-construction phase for submission at least two months in advance of the works commencing, which shall include details such as the species and number to be transplanted, the programme and reception site. If the affected individual is deemed not suitable for transplantation due to factors such poor health or anticipated low post-transplantation survival rate, compensatory planting may be considered as an alternative. 

5.5.2.13   The ecologist(s) of the Environmental Team shall seek the Engineer, the Independent Environmental Checker (IEC), Environmental Protection Department and Agriculture, Fisheries and Conservation Department’s approval of the “Floral Transplantation Plan”, including the receptor site(s), before implementing the recommendations of the plan.   The transplantation works will be undertaken in the pre-construction phase and at least 1 week before works commence.

5.5.2.14   Following the transplantation, in order to ensure the transplantation is providing an effective mitigation measure, post-transplantation monitoring would be required during the construction phase. The post-transplantation monitoring shall be conducted monthly for the first 12 months and then quarterly for a further 12 months.  Given the works contract is approximately 30 months, all the post-transplantation monitoring would be undertaken within the construction phase.  Should the survival rate of the transplanted individual be found to be unacceptably low, then the Environmental Team shall propose alternative compensation methods, such as seed collection or planting of new individuals of the same species after the works area has been reinstated. If required, a “Compensatory Planting Plan” shall be prepared by the ET and submitted to the Engineer, the Independent Environmental Checker (IEC), Environmental Protection Department and Agriculture, Fisheries and Conservation Department’s for approval before implementing the recommendations of the plan.  The “Compensatory Planting Plan” shall include details of the implementation programme and methodology for any proposed compensatory planting for species of conservation interest.

Aquatic Fauna Translocation Plan – Item 9 (Table 5.2)

 

5.5.2.15   Although the fauna species of conservation interest in the natural streams were not recorded within the Project Area, as the stream and tributaries are connected, these species could be present in the Project Area at the time the works commence.  Therefore, as an avoidance measure, it is considered necessary to prepare an “Aquatic Fauna Translocation Plan”.  A qualified ecologist as part of the ET shall prepare and submit an “Aquatic Fauna Translocation Plan” in the pre-construction phase at least two months in advance of the works commencing, which shall include details such as the species, potential numbers, methodology for survey and translocation for each species, the programme and reception sites.

5.5.2.16   The ET shall seek approval of the “Aquatic Fauna Translocation Plan” by the Engineer, the Independent Environmental Checker (IEC), Agriculture, Fisheries and Conservation Department’s and the DEP. 

Aquatic Fauna Translocation Survey – Item 10 (Table 5.2)

 

5.5.2.17   Based upon the approval of the “Aquatic Fauna Translocation Plan”, and “Aquatic Fauna Translocation Survey” will be conducted at the affected sections of the stream courses, at Works Sections 1 and 6, prior to site clearance works.  The survey shall be conducted by a qualified ecologist as part of the ET and cover the stretch of the stream course 5m upstream and downstream of the works and identify potential receptor sites. Any aquatic fauna species of conservation found shall be collected and translocated to the approved translocation receptor site on the same survey date. Since the species are mostly nocturnal, the translocation survey shall be conducted at night-time.  However, the translocation works shall be undertaken in the pre-construction phase no more than a week before the relevant site works.

5.5.2.18   An “Aquatic Fauna Translocation Survey” report shall be prepared by a qualified ecologist of the Environmental Team (ET) and submitted within 2 weeks of the translocation works for approved by the Engineer, the Independent Environmental Checker (IEC), Agriculture, Fisheries and Conservation Department’s and the DEP.

General Habitat Protection – Item 11 (Table 5.2)

 

5.5.2.19   Audit of habitat protection measures in order to avoid damage and disturbance to the species of conservation interest in close proximity to the works and overall habitats will be undertaken weekly during the construction phase as follows:

·               ensure fencing around Works and Stockpiling Areas and hoarding around the Site Office before commencement of works to prevent vehicle movements and encroachment of personnel into adjacent areas;

·               ensure that work site boundaries are not breached and that damage does not occur to surrounding areas;

·               provided and scheduled environmental briefing/training sessions for site staff to raise their awareness on environmental protection;

·               ensure placement of equipment is within designated areas within the existing disturbed land;

·               ensure construction activities are restricted to within the proposed works boundary;

·               ensure spoil heaps are be covered at all times;

·               ensure that disturbed areas are reinstated immediately after completion of the works;

·               ensure all in the natural stream are undertaken during the dry season; and

·               ensure enhancement planting works undertaken.

5.5.2.20   The schedule for these works is provided in Table 5.3 below.

Table 5.3      Audit Schedule for Ecological EM&A Works

Specification Number (Table 5.2)

Pre-Construction Phase

Construction Phase

1, 2 & 11

-

Enhancement planting implementation, construction run-off and habitat protection mitigation measures.

Weekly audit

3

Updated Baseline Vegetation Survey.

Submit for approval at least two months before works commence.

-

 

4

Preparation of Floral Protection Plan.

Submit for approval at least one month before works commence.

-

5

-

Audit of Floral Protection Plan.

Monthly audit of the implementation of Floral Protection Plan until construction works completed and the site is reinstated.

6

Preparation of Floral Transplantation Plan. 

Submit for approval at least two months before works commence.

-

7

Floral Transplantation Works

Undertake at least one week before works commence.   

 

8

 

Audit of Floral Transplantation Plan.

Monthly audit of the transplanted species in terms of number, health and survival rate of the transplanted individual for the first 12 months after the transplantation.

 

Quarterly audit the transplanted species in terms of number, health and survival rate of the transplanted individual between months 12 to 24 after the transplantation.

9

Aquatic Fauna Translocation Plan.

Submit for approval at least two months before works commence.

-

10

Aquatic Fauna Translocation Survey and Translocation Works

To be conducted no more than a week before works.

 

Aquatic Fauna Translocation Survey Report

Submit within two weeks after the translocation survey.

-

 

5.5.2.21   The Environmental Team (ET) (refer to Section 1 for a description of the ET and duties) shall be responsible for conducting the EM&A programme and ensuring the Contractor’s compliance with the project’s environmental performance requirements and the approved flora and fauna conservation requirement during the construction phase. 

5.5.2.22   For the overall audit of habitat protection, in the event of non-compliance, the Event /Action plan detailed in Table 5.4 below should be implemented.


Table 5.4       Event / Action Plan for Ecological Monitoring

Action Level

ET

IEC

ER

Contractor

Non-conformity   on one occasion

Identify Source

Inform the IEC and the ER

Discuss remedial actions with the IEC, the ER and the Contractor

Monitor remedial actions until rectification has been completed

Check report

Check the  Contractor's working method

Discuss with the ET and the  Contractor on possible remedial measures

Advise the ER on effectiveness of proposed remedial measures.

Check implementation of remedial measures.

Notify Contractor

Ensure remedial measures are properly implemented

Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the works in the case of a serious non-conformity until situation rectified.

Amend working methods

Rectify damage and undertake any necessary replacement

Repeated Non conformity

Identify Source

Inform the IC(E) and the ER

Increase monitoring frequency

Discuss remedial actions with the  IC(E), the ER and the Contractor

Monitor remedial actions until rectification has been completed

If exceedance stops, cease additional monitoring

Check monitoring report

Check the Contractor's working method

Discuss with the ES and the Contractor on possible remedial measures

Advise the ER on effectiveness of proposed remedial measures

Supervise implementation of  remedial measures

Notify the  Contractor

Ensure remedial measures are properly implemented

Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the works in the case of a serious non-conformity until situation rectified.

Amend working methods

Rectify damage and undertake any necessary replacement

Note:  ET – Environmental Team, IEC – Independent Checker (Environmental), ER – Engineer’s Representative