6                        lANDSCAPE AND vISUAL IMpact Assessment

6.1                   Background

6.1.1.1       The EIA has recommended that EM&A for landscape and visual resources is undertaken during the construction and operational phases of the project.   The design, implementation and maintenance of landscape mitigation measures is a key aspect of this and should be checked to ensure that they are fully realised and that potential conflicts between the proposed landscape measures and any other project works and operational requirements are resolved at the earliest possible date and without compromise to the intention of the mitigation measures.  In addition, the implementation of the mitigation measures recommended by the EIA will be monitored through the site audit programme.

6.2                   Mitigation Measures

6.2.1.1       The Landscape and Visual Assessment of the EIA recommended a series of mitigation measures to ameliorate the landscape and visual impacts of the project.  These measures include the following:

·               adoption of construction methods to minimise both landscape and visual impacts, particularly in sensitive locations;

·               localized refinement of the Project Area and drainage alignment to minimise loss of landscape resources, where practical;

·               minimising working areas as far as possible;

·               protection and retention of existing vegetation where possible; and

·               reinstatement of disturbed areas and compensatory planting.

 

6.2.1.2       The measures for both the construction and operation stages as recommended in the EIA are summarised in Table 6.1 and 6.2 below and provided in the Environmental Mitigation Implementation Schedule in Appendix A: 

Table 6.1       Proposed Construction Stage Mitigation Measures

ID No.*

Landscape / Visual Mitigation Measure

CM1

No-intrusion Zone

To maximize protection of existing resources including watercourses existing trees, ground vegetation and the associated understory habitats a “No-intrusion Zone” will be designated to various areas within and along the site boundary with rigid and durable fencing for each individual no-intrusion zone.

 

Regular checks will be carried out to ensure that the work site boundaries are not exceeded, hoarding is properly maintained and that no damage is being caused to these protected areas.

CM2

 

Erection of Screen Hoardings

A temporary screen hoarding shall be erected around the north side of the Site Office (SO) area to screen activities from local receivers. It shall be designed and to be compatible with the existing rural context, with visually unobtrusive design and colours where appropriate. 

CM3

Control of night-time lighting

No night time work shall be programmed avoiding light pollution to visual receivers.

Notes:  * CM = Construction Mitigation; OM = Operation Mitigation

 

Table 6.2             Proposed Operation Stage Mitigation Measures

ID No.*

Landscape / Visual Mitigation Measure

OM1

 

Compensatory Tree Planting

Suitable land pockets within the project area will be used for the implementation of compensatory mitigation to offset the net loss of key landscape resources and improve visual amenity.

A compensatory tree planting proposal including locations of tree compensation will be submitted separately to seek relevant government department’s approval, in accordance with ETWB TCW No. 3/2006.

OM2

 

Horizontal Greening

Following installation of underground culverts, pit excavation or utilization of land for works or stockpiling, the ground shall be backfilled, leveled and soiled as necessary for reinstatement prior to hydroseeding.

OM3

Reinstatement of Natural Water Courses

Where water courses have been affected by the works new, naturalised streams paths shall be provided as far as applicable, using excavated local rocks and stones in order to create a pleasing visual impression and potential enhanced ecological habitat.

Notes:  * CM = Construction Mitigation; OM = Operation Mitigation

 

6.3                   Construction and Operational Phase Audit

6.3.1.1        A specialist Landscape Sub-Contractor should be employed by the Contractor for the implementation of landscape construction works and subsequent maintenance operations during the establishment period.  It is proposed that the planting works will be on-site and the planting should be completed during the construction contract.  The monitoring of the planting establishment should be undertaken for a 12 month period which could extend throughout the Contractor’s one-year maintenance period, which will be within the first operational year of the project.

6.3.1.2        All measures undertaken by both the Contractor and the specialist Landscape Sub-Contractor during the construction phase and first year of the operational phase shall be audited by a Registered Landscape Architect, as a member of the Environmental Team (ET) (see Section 1), on a regular basis to ensure compliance with the intended aims of the measures.  Site inspections should be undertaken at least once every two weeks throughout the construction period and once every two months during the operational phase, which will comprise the 12 months of the Contractor’s maintenance period.  The broad scope of the audit is detailed below but should also be undertaken with reference to the more specific checklist provided in Table 6.3.  Operational phase auditing will be comprise monitoring of the establishment of the landscape planting only and, thus, only the items below concerning this period are relevant to the operational phase.

·               the extent of the agreed works areas should be regularly checked during the construction phase.  Any trespass by the Contractor outside the limit of the works, including any damage to existing trees and woodland shall be prohibited;

 

·               the progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken;

·               all existing trees and vegetation within the study area which are not directly affected by the works are retained and protected;

 

·               the methods of protecting existing vegetation proposed by the Contractor are acceptable and enforced;

 

·               preparation, lifting transport and re-planting operations for any transplanted trees;

 

·               all landscaping works are carried out in accordance with the specifications;

 

·               the planting of new trees, shrubs, groundcover, climbers, ferns, grasses and other plans, together with the replanting of any transplanted trees are carried out properly and within the right season; and

 

·               all necessary horticultural operations and replacement planting are undertaken throughout the Establishment Period to ensure the healthy establishment and growth of both transplanted trees and all newly established plants.

 

Table 6.3             Construction/Operational Phase Audit Checklist for Ecology Issues

Area of Works

Items to be Monitored

Advance planting

Monitoring of implementation and maintenance of planting, and against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Protection of all trees and woodland blocks to be retained

Identification and demarcation of trees / vegetation to be retained, erection of physical protection (e.g. fencing), monitoring against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Clearance of existing vegetation

Identification and demarcation of trees / vegetation to be cleared, checking of extent of works to minimise damage, monitoring of adjacent areas against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Pruning of trees

Identification and demarcation of trees / vegetation to be pruned, monitoring of extent of pruning to minimise damage, timing of operations, implementation of all stages of preparatory and pruning works, and maintenance of pruned vegetation, etc.

Plant supply

Monitoring of operations relating to the supply of specialist plant material (including the collecting, germination and growth of plants from seed) to ensure that plants will be available in time to be used within the construction works.

Soiling, planting, etc.

Monitoring of implementation and maintenance of soiling and planting works and against possible incursion, physical damage, fire, pollution, surface erosion, etc.

Site fencing and hoarding

Implementation and maintenance, to ensure compliance with agreed designs and check that it matches the surrounding environment and does not cause visual intrusion.

Architectural treatment of engineering works.

Implementation and maintenance of mitigation measures, to ensure compliance with agreed designs as applicable.

Establishment Works

Monitoring of implementation of maintenance operations during Establishment Period

 

6.3.1.3        In the event of non compliance the responsibilities of the relevant parties is detailed in the Event /Action plan provided on Table 6.4.

Table 6.4       Event / Action Plan for Construction/Operational Phase for Ecology Issues

Action Level

ET

IEC

ER

Contractor

Non-conformity   on one occasion

1. Identify Source

2. Inform the IEC and the ER

3. Discuss remedial actions with the IEC, the ER and the Contractor

4. Monitor remedial actions until rectification has been completed

1. Check report

2. Check the  Contractor's working method

3. Discuss with the ET and the  Contractor on possible remedial measures

4. Advise the ER on effectiveness of proposed remedial measures.

5. Check implementation of remedial measures.

1. Notify Contractor

2. Ensure remedial measures are properly implemented

1. Amend working methods

2. Rectify damage and undertake any necessary replacement

Repeated Non-conformity

1. Identify Source

2. Inform the IEC and the ER

3. Increase monitoring frequency

4. Discuss remedial actions with the  IEC, the ER and the Contractor

5. Monitor remedial actions until rectification has been completed

6. If exceedance stops, cease additional monitoring

1. Check monitoring report

2. Check the Contractor's working method

3. Discuss with the ET and the Contractor on possible remedial measures

4. Advise the ER on effectiveness of proposed remedial measures

5. Supervise implementation of remedial measures.

1. Notify the  Contractor

2. Ensure remedial measures are properly implemented

1. Amend working methods

2. Rectify damage and undertake any necessary replacement

Note:  ET – Environmental Team, IEC – Independent Environmental Checker, ER – Engineer’s Representative