5.1.1
This
section presents an assessment of the potential water quality impacts
associated with the construction and operation of the proposed Roads D3A &
D4A. Recommendations for mitigation measures
have been provided, where necessary, to minimise the identified water quality
impacts to an acceptable level. All
construction works for the Project will be land-based, and therefore direct
impacts on marine water quality are not expected to arise.
5.2
Environmental Legislation,
Standards and Guidelines
Environmental Impact Assessment
Ordinance (EIAO)
5.2.1
The
Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) is
issued by the EPD under Section 16 of the EIAO.
It specifies the assessment method and criteria that need to be followed
in EIA. Reference sections in the
EIAO-TM provide the details of the assessment criteria and guidelines that are
relevant to the water quality impact assessment, including:
l
Annex 6 Criteria for Evaluating
Water Pollution
l
Annex 14 Guidelines for Assessment
of Water Pollution
Water Pollution Control Ordinance
(WPCO)
5.2.2
The
Water Pollution Control Ordinance (Cap. 358) is the major legislation relating
to the protection and control of water quality in
Table 5.1 Summary of Water Quality Objectives for
Parameters |
Objectives |
Sub-Zone |
Offensive odour, tints |
Not to be present |
Whole zone |
Visible foam, oil scum, litter |
Not to be present |
Whole zone |
E coli |
Not to exceed 1000 per 100 mL,
calculated as the geometric mean of the most recent 5 consecutive samples
taken at intervals between 7 and 21 days |
Inland waters |
Dissolved oxygen (DO) within |
Not less than 2.0 mg/l for 90% of
samples |
Marine waters |
Depth-averaged DO |
Not less than 4.0 mg/l for 90% of
samples |
Marine waters |
DO |
Not less than 4.0 mg/l |
Inland waters |
pH |
To be in the range of 6.5 - 8.5, change
due to human activity not to exceed 0.2 |
Marine waters |
Not to exceed the range of 6.0 -
9.0 due to human activity |
Inland waters |
|
Salinity |
Change due to human activity not
to exceed 10% of ambient |
Whole zone |
Temperature |
Change due to human activity not
to exceed 2oC |
Whole zone |
Suspended solids (SS) |
Not to raise the ambient level by
30% caused by human activity |
Marine waters |
Annual med |
Inland waters |
|
Unionized ammonia (UIA) |
Annual mean not to exceed 0.021
mg(N)/l as unionized form |
Whole zone |
Nutrients |
Shall not cause excessive algal
growth |
Marine waters |
Total inorganic nitrogen (TIN) |
Annual mean depth-averaged inorganic
nitrogen not to exceed 0.4 mg(N)/l |
Marine waters |
5-Day biochemical oxygen demand
(BOD5) |
Not to exceed 5 mg/l |
Inland waters |
Chemical Oxygen Demand (COD) |
Not to exceed 30 mg/l |
Inland waters |
Toxic substances |
Should not attain such levels as
to produce significant toxic, carcinogenic, mutagenic or teratogenic effects
in humans, fish or any other aquatic organisms. |
Whole zone |
Human activity should not cause a
risk to any beneficial use of the aquatic environment. |
Whole zone |
Source:
Statement of Water Quality Objectives (
Water Supplies Department (WSD)
Water Quality Criteria
5.2.3
Besides
the WQOs stipulated under the WPCO, the WSD has specified a set of objectives
for water quality at flushing water intakes. The list is shown in Table
5.2. The target limit for suspended solids (SS) at these intakes is
10mg/l or less.
Table 5.2 WSD’s
Water Quality Criteria for
Parameter (in mg/l unless otherwise stated) |
Target Limit |
Colour (HU) |
< 20 |
Turbidity (NTU) |
< 10 |
Threshold Odour Number
(odour unit) |
< 100 |
Ammoniacal Nitrogen |
< 1 |
Suspended Solids |
< 10 |
Dissolved Oxygen |
> 2 |
Biochemical Oxygen Demand |
< 10 |
Synthetic Detergents |
< 5 |
E. coli (no. per 100ml) |
< 20,000 |
Technical Memorandum on Effluent
Discharge Standard
5.2.4
Besides
setting the WQOs, the WPCO controls effluent discharging into the WCZs through
a licensing system. Guidance on the
permissible effluent discharges based on the type of receiving waters (foul
sewers, stormwater drains, inland and coastal waters) is provided in the
Technical Memorandum on Standards for Effluents Discharged into Drainage and
Sewerage Systems, Inland and Coastal Waters (TM-DSS). The limits given in the
TM cover the physical, chemical and microbial quality of effluents. Any effluent discharge during the
construction and operational stages should comply with the standards for
effluents discharged into the inshore waters or marine waters of the
Practice Notes
5.2.5
A
practice note (PN) for professional persons was issued by EPD to provide
environmental guidelines for the handling and disposal of construction site
discharges. The Practice Note (PN) for
Professional Persons on Construction Site Drainage (ProPECC PN 1/94) issued by
EPD provides good practice guidelines for dealing with various types of
discharge from a construction site.
Practices outlined in the PN should be followed as far as possible
during construction to minimize the water quality impact due to construction
site drainage.
5.3
Identification of Water Sensitive Receivers
5.3.1
The
Study Area includes all areas within 300m from the Project boundary. Within 300m of the Project Boundary, only one
Water Sensitive Receiver (WSR), namely the proposed cooling water intake of
District Cooling System (DCS) for KTD, was identified. The DCS is planned by EMSD to be implemented
in the KTD area. The associated cooling water intake of DCS would be
considered as a planned WSR. The cooling water intake will be located
along the waterfront of the former Kai Tak airport runway. Location of this WSR is shown in Figure 5.1. No other existing or planned WSRs
were identified within the Study area.
5.4
Description of the
Environment
5.4.1
The
EPD water quality monitoring station VM2 in the
5.4.2
According
to the “2011 Marine Water Quality in Hong Kong”, which is the latest available
information from EPD at the moment of preparing this Report, the baseline water
quality monitoring shows that non-compl
Table 5.3 Baseline Marine Water Quality Condition for
Parameter |
|
WPCO
WQO (in
marine waters) |
|
VM2 |
|||
Temperature (oC) |
22.5 |
Not more than 2
oC in daily temperature range |
|
(16.1-26.7)
|
|||
Salinity |
32.2 |
Not to cause more than 10% change |
|
(29.2-33.5) |
|||
Dissolved Oxygen (DO) (mg/L) |
Depth average |
5.4 |
Not less than 4
mg/L for 90% of the samples |
(3.8-7.5) |
|||
Bottom |
5.4 |
Not less than 2
mg/L for 90% of the samples |
|
(3.5-7.6) |
|||
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
74 |
Not Available |
(55-92) |
|||
Bottom |
74 |
Not Available |
|
(49-93) |
|||
pH |
7.8 |
6.5 - 8.5 (± 0.2 from natural range) |
|
(7.6-8.2) |
|||
Secchi disc Depth (m) |
2.6 |
Not Available |
|
(1.9-3.5) |
|||
Turbidity (NTU) |
3.2 |
Not Available |
|
(1.7-12.5) |
|||
Suspended Solids (SS) (mg/L) |
3.7 |
Not more than 30% increase |
|
(2.1-6.9) |
|||
5-day Biochemical Oxygen Demand (BOD5)
(mg/L) |
0.8 |
Not Available |
|
(0.3-1.4) |
|||
Ammonia Nitrogen (NH3-N) (mg/L) |
0.133 |
Not Available |
|
(0.068-0.283) |
|||
Unionised Ammonia (UIA) (mg/L) |
0.004 |
Not more than
0.021 mg/L for annual mean |
|
(0.001-0.008) |
|||
Nitrite Nitrogen (NO2-N) (mg/L) |
0.029 |
Not Available |
|
(0.011-0.070) |
|||
Nitrate Nitrogen (NO3-N) (mg/L) |
0.146 |
Not Available |
|
(0.065-0.286) |
|||
Total Inorganic Nitrogen (TIN) (mg/L) |
0.31 |
Not more than 0.4
mg/L for annual mean |
|
(0.20-0.50) |
|||
Total Kjeldahl Nitrogen (mg/L) |
0.29 |
Not Available |
|
(0.22-0.43) |
|||
Total Nitrogen (TN) (mg/L) |
0.46 |
Not Available |
|
(0.30-0.65) |
|||
Orthophosphate Phosphorus (OrthoP) (mg/L) |
0.027 |
Not Available |
|
(0.012-0.036) |
|||
Total Phosphorus (TP) (mg/L) |
0.04 |
Not Available |
|
(0.03-0.06) |
|||
Silica (as SiO2) (mg/L) |
0.93 |
Not Available |
|
(0.43-1.37) |
|||
Chlorophyll-a (µg/L) |
2.3 |
Not Available |
|
(0.4-9.1) |
|||
E coli (cfu/100 mL) |
710 |
Not Available |
|
(60-11000) |
|||
Faecal Coliforms (cfu/100 mL) |
1500 |
Not Available |
|
(110-26000) |
Notes:
1.
Data source: Marine Water Quality in
2.
Except as specified, data presented
are depth-averaged values calculated by taking the means of three depths:
surface, mid-depth, bottom.
3.
Data presented are annual arithmetic
means of depth-averaged results except for E.
coli and faecal coliforms that are annual geometric means.
4.
Data in brackets indicate the
ranges.
5.5
Assessment Approach and Methodology
5.5.1
The
Study Area includes all areas within 300m from the Project boundary, and covers
relevant water sensitive receivers that have a bearing on the environmental
acceptability of the Project within the Victoria Harbour (Phase 1 and 2) WCZ.
5.5.2
The
water sensitive receivers that may be affected by the land-based construction activities
for the Project have been identified.
Potential sources of water quality impact that may arise during the
land-based construction works were described.
This task included identifying pollutants from point discharges and
non-point sources that could affect the quality of surface water run-off. All the identified sources of potential water
quality impact were then evaluated and their impact significance
determined. The need for mitigation
measures to reduce any identified adverse impacts on water quality to
acceptable levels was determined.
5.6
Identification of Potential Impacts
Construction Phase
5.6.1
No
marine works would be required for the Project.
Potential sources of water quality impact associated with the land-based
construction of the Project have been identified and include:
l
General construction activities;
l
Construction site run-off;
l
Accidental spillage; and
l
Sewage effluent from construction
workforce.
General Construction
Activities
5.6.2
The
land-based construction works could have the potential to cause water
pollution. Various types of construction
activities may generate wastewater.
These include general cleaning and polishing, wheel washing, dust
suppression and utility installation.
These types of wastewater would contain high concentrations of suspended
solids (SS). If uncontrolled, these
effluents could lead to deterioration in water quality.
Construction Site
Run-off
5.6.3
Construction
site run-off would cause potential water quality impacts. Potential pollution sources of site run-off
may include:
l
Run-off and erosion of exposed bare
soil and earth, drainage channel, earth working area and stockpiles.
l
Release of any bentonite slurries,
concrete washings and other grouting materials with construction run-off or
storm water.
l
Wash water from dust suppression
sprays and wheel washing facilities.
l
Fuel, oil and lubricants from
maintenance of construction vehicles and equipment.
5.6.4
During
rainstorms, site run-off would wash away the soil particles on unpaved lands
and areas with the topsoil exposed. The
run-off is generally characterized by high concentrations of SS. Release of uncontrolled site run-off would
increase the SS levels and turbidity in the nearby water environment. Site run-off may also wash away contaminated
soil particles and therefore cause water pollution.
5.6.5
Wind
blown dust would be generated from exposed soil surfaces in the works
areas. It is possible that wind blown
dust would fall directly onto the nearby water bodies when a strong wind
occurs. Dispersion of dust within the
works areas may increase the SS levels in surface run-off causing a potential
impact to the nearby sensitive receivers.
Accidental Spillage
5.6.6
A
large variety of chemicals may be used during construction activities. These chemicals may include petroleum
products, surplus adhesives, spent lubrication oil, grease and mineral oil,
spent acid and alkaline solutions/solvent and other chemicals. Accidental spillage of chemicals in the works
areas may contaminate the surface soils.
The contaminated soil particles may be washed away by construction site
run-off or stormwater drainage which in turn causes water pollution.
Sewage Effluent from
Construction Workforce
5.6.7
During
the construction of the Project, the workforce on site will contribute to the local
population of the area, although the number of workers will vary over the
construction period. Potential impacts may arise from wastewater generated from
eating areas, temporary sanitary facilities and waste disposal areas.
Operation Phase
5.6.8
The
identified potential sources of impact on water quality during the operation
phase would be runoff from the road surfaces, which may contain small amount of
oil and grit leaked from passing vehicles.
However, impacts upon water quality will be minimal provided that the
road works are designed with adequate drainage systems and appropriate silt
trap, as required.
5.7
Prediction and Evaluation of Impacts
Construction Phase
General Construction Activities
5.7.1
Effluent
discharged from temporary site facilities should be controlled to prevent
direct discharge to the neighbouring marine waters and storm drains. Such effluent may include wastewater
resulting from wheel washing of site vehicles at site entrances, discharge of
debris and rubbish such as packaging, construction materials and refuse. Adoption of the guidelines and good site
practices for handling and disposal of construction discharges as part of the
construction site management practices (as given in Sections 5.8.1 to 5.8.13) would minimized the potential impacts.
Construction Site Run-off
5.7.2
Construction
site run-off and drainage may cause local water quality impacts. Increase in SS arising from the construction
site could block the drainage channels.
High concentrations of suspended degradable organic material in marine
water could lead to reduction in DO levels in the water column.
5.7.3
It
is important that proper site practice and good site management be followed to
prevent run-off with high level of SS from entering the surrounding
waters. With the implementation of
appropriate measures to control run-off and drainage from the construction
site, disturbance of water bodies would be avoided and deterioration in water
quality would be minimal. Thus,
unacceptable impacts on the water quality are not expected, provided that the
recommended measures described in Sections 5.8.1 to 5.8.13 are properly implemented.
Accidental Spillage
5.7.4
The
use of engine oil and lubricants, and their storage as waste materials has the
potential to create impacts on the water quality if spillage occurs and enters
adjacent water environment. Waste oil
may infiltrate into the surface soil layer, or run-off into marine water
environment, increasing hydrocarbon levels.
The potential impacts could however be mitigated by practical mitigation
measures and good site practices (as given in Sections 5.8.14 to 5.8.16).
Sewage Effluent from Construction Workforce
5.7.5
Domestic
sewage would be generated from the workforce during the construction
phase. However, this temporary sewage
can be adequately treated by interim sewage treatment facilities, such as
portable chemical toilets. Provided that sewage is not discharged directly into
stormwater drains or marine waters adjacent to the construction site, and
temporary sanitary facilities are used and properly maintained, it is unlikely
that sewage generated from the site would have a significant water quality
impact. Mitigation measures and good site
practices given in Sections 5.8.17 to 5.8.18 should be implemented.
Operation Phase
5.7.6
The
identified potential source of impact on water quality during the operation
phase of the Project is runoff from the road surfaces. The road run-off may
contain minimal amount of oil, grease and grit that may cause water quality
impacts to the receiving waters of
5.8
Recommended Water Quality Mitigation Measures
Construction Phase
Construction Site Run-off and General Construction
Activities
Construction
Site Run-off
5.8.2
Surface
run-off from construction sites should be discharged into storm drains via
adequately designed sand/silt removal facilities such as sand traps, silt traps
and sedimentation basins. Channels or
earth bunds or sand bag barriers should be provided on site to properly direct
stormwater to such silt removal facilities.
Perimeter channels should be provided on site boundaries where necessary
to intercept storm run-off from outside the site so that it will not wash
across the site. Catchpits and perimeter
channels should be constructed in advance of site formation works and
earthworks.
5.8.3
Silt
removal facilities, channels and manholes should be maintained and the
deposited silt and grit should be removed regularly, at the onset of and after
each rainstorm to prevent local flooding.
Any practical options for the diversion and re-alignment of drainage
should comply with both engineering and environmental requirements in order to
provide adequate hydraulic capacity of all drains. Minimum distance of
5.8.4
Construction
works should be programmed to minimize soil excavation works in rainy seasons
(April to September). If excavation in
soil cannot be avoided in these months or at any time of year when rainstorms
are likely, for the purpose of preventing soil erosion, temporary exposed slope
surfaces should be covered e.g. by tarpaulin, and temporary access roads should
be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided
(e.g. along the crest / edge of excavation) to prevent storm runoff from
washing across exposed soil surfaces.
Arrangements should always be in place in such a way that adequate surface
protection measures can be safely carried out well before the arrival of a
rainstorm.
5.8.5
Earthworks
final surfaces should be well compacted and the subsequent permanent work or
surface protection should be carried out immediately after the final surfaces
are formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting
channels should be provided where necessary.
5.8.6
Measures
should be taken to minimize the ingress of rainwater into trenches. If
excavation of trenches in wet seasons is necessary, they should be dug and backfilled
in short sections. Rainwater pumped out
from trenches or foundation excavations should be discharged into storm drains
via silt removal facilities.
5.8.7
Open
stockpiles of construction materials (e.g. aggregates, sand and fill material)
on sites should be covered with tarpaulin or similar fabric during
rainstorms.
5.8.8
Manholes
(including newly constructed ones) should always be adequately covered and
temporarily sealed so as to prevent silt, construction materials or debris from
getting into the drainage system, and to prevent storm run-off from getting
into foul sewers. Discharge of surface
run-off into foul sewers must always be prevented in order not to unduly
overload the foul sewerage system.
5.8.9
Good site practices
should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from the site
area. It is recommended to clean the
construction sites on a regular basis.
Boring
and Drilling Water
Wheel
Washing Water
5.8.11
All
vehicles and plant should be cleaned before they leave a construction site to
minimize the deposition of earth, mud, debris on roads. A wheel washing bay should be provided at every
site exit if practicable and wash-water should have sand and silt settled out
or removed before discharging into storm drains. The section of construction road between the
wheel washing bay and the public road should be paved with backfall to reduce
vehicle tracking of soil and to prevent site run-off from entering public road
drains.
Acid
Cleaning, Etching and Pickling Wastewater
5.8.12
Acidic
wastewater generated from acid cleaning, etching, pickling and similar
activities should be neutralized to within the pH range of 6 to 10 before
discharging into foul sewers.
Effluent
Discharge
5.8.13
There
is a need to apply to EPD for a discharge licence for discharge of effluent
from the construction site under the WPCO.
The discharge quality must meet the requirements specified in the
discharge licence. All the runoff and
wastewater generated from the works areas should be treated so that it
satisfies all the standards listed in the TM-DSS. Minimum distance of
Accidental Spillage
5.8.15
Any
service shop and maintenance facilities should be located on hard standings
within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these discharges.
5.8.16
Disposal
of chemical wastes should be carried out in compl
l
Suitable containers should be used
to hold the chemical wastes to avoid leakage or spillage during storage,
handling and transport.
l
Chemical waste containers should be
suitably labelled, to notify and warn the personnel who are handling the
wastes, to avoid accidents.
l
Storage area should be selected at a
safe location on site and adequate space should be allocated to the storage
area.
Sewage Effluent from Construction Workforce
Operation Phase
l
The road drainage should be directed
through silt traps in the gully inlets to remove silt and grit before entering
the public storm water drainage system; and
l
The silt traps should be regularly
cleaned and maintained in good working condition.
5.9
Evaluation of Residual Impacts
5.9.1
With
the full implementation of the recommended mitigation measures for the
construction and operation phases of the proposed Project, no adverse residual
impacts on water quality are anticipated.
5.10
Environmental Monitoring and Audit Requirements
5.10.1
No
adverse water quality impact would be expected during the construction and
operation of the Project, provided recommended mitigation measures are properly
implemented. Water quality monitoring is
therefore not considered necessary.
However, it is recommended that regular site inspections during the
construction phase should be undertaken to inspect the construction activities
and works areas in order to ensure the recommended mitigation measures are
properly implemented.
Construction Phase
5.11.1
Water
quality impacts from land-based construction are associated with the general
construction activities, construction site run-off, accidental spillage, and
sewage effluent from construction workforce. Impacts can be controlled to
comply with the WPCO standards by implementing the recommended mitigation
measures. No unacceptable residual impacts on water quality are
anticipated. Regular site inspections
should be undertaken routinely to inspect the construction activities and works
areas in order to ensure the recommended mitigation measures are properly
implemented.
Operation Phase
5.11.2
The
only source of potential impact on water quality during the operation phase
will be runoff from the road surfaces. It
is anticipated that the water quality impacts associated with the operation
phase would be minimal and acceptable, provided that the recommended mitigated
measures for the surface water drainage system are properly implemented.