10                          LANDSCAPE AND VISUAL IMPACT

10.1                   Introduction

This section presents the Landscape and Visual Impact Assessment (LVIA) associated with the proposed CKR. Potential landscape and visual impacts that might occur as a result of the development of this trunk road and its associated structures, have been assessed in accordance with the criteria and guidelines as stated in Annexes 10 and 18 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) and EIAO Guidance Note No. 8/2010 on Preparation of Landscape and Visual Impact Assessment under Environmental Impact Assessment Ordinance. 

Only surface construction activities and permanent structures are assessed in this report. All underground activities and facilities are unlikely to impose landscape and visual impacts, and hence are not assessed. 

10.2                   Scope and Content of the Study

According to EIA Study Brief No. ESB-156/2006, the Study Area for the Landscape Impact Assessment (LIA) shall include all areas within 100 m of the project boundary of the project. The assessment of landscape character areas and landscape resources will include all areas within the Study Area boundary. The assessment area for the visual impact assessment shall be defined by the visual envelope of the Project and associated works.

As discussed in Sections 2.3 to 2.5 of the EIA, a number of alignment options have been considered for the west, east and central portions of the CKR. These options have been evaluated by considering a number of factors including engineering, public comments, environmental factors etc. Figure 10.1 shows the location and preferred alignment of the ~ 4.7 km, dual 3-lane east-west CKR trunk road as well as the ventilation and administration buildings and the works area. Figure 10.1.1, Figure 10.1.2 and Figure 10.1.3 provide further details of the three main Project areas, namely the West, Central and East Portions. Figure 10.2 shows existing aerial views of the CKR, with Figure 10.2.1, Figure 10.2.2 and Figure 10.2.3 providing more detail of the three main Project areas and Figure 10.3.1, Figure 10.3.2 and Figure 10.3.3 illustrating the context and hierarchy of the existing landscape and visual conditions on annotated oblique aerial views of the three main Project areas.

While a summary of the currently agreed key elements is provided below, Section 3 provides full details of Project elements and construction methodologies, as well as the temporary works area, including supporting drawings.  Figures showing key elements of structures, such as plans, elevations and typical design (e.g. of viaducts) are provided in the Impact Assessment sections of the report, including illustration of soft landscaping. 

Tunnel Sections

The tunnel section between Yau Ma Tei and Ma Tau Kok is approximately 3.9 km (including a 370 m long underwater tunnel between Ma Tau Kok and Kai Tak). Drill & blast rock tunnel in the central portion is approximately 2,790 m while the cut-and-cover tunnels proposed at both ends of the tunnel, are approximately 400 m long at Yau Ma Tei and approximately 135 m long at Ma Tau Kok.

The underwater tunnel between Ma Tau Kok and Kai Tak is chosen based on various considerations including minimizing the disturbance to public/marine facilities, environmental impacts, extents of temporary reclamation and technical feasibility.

Ventilation Buildings (VB) and Administration Building

There are three Ventilation Buildings (VBs) and one Administration Building in total:

-         VB at Yau Ma Tei Interchange. Approximate footprint of 5,000 m2 with a building height of approximately 20 m above ground (See Figure 10.10.5, Figure 10.10.6, Figure 10.10.7, Figure 10.10.8, Figure 10.10.9 and Figure 10.10.10 for details).

-         VB at Ho Man Tin. Approximate footprint of 3,300 m2 with a building height of about 10 m above ground (See Figure 10.11.1 and Figure 10.11.2 for details).

-         Ventilation and Administration Building at Kai Tak.  Approximate footprint of 6,200 m2 with a building height of less than 25 m above ground level (See Figure 10.12.3, Figure 10.12.4, Figure 10.12.5 and Figure 10.12.6 for details). 

Slip Roads / Connection Roads

West Portion – There are seven bridges designed for the West Portion connection roads to link CKR with West Kowloon Interchange and Lin Cheung Road, namely Connection B2, B, C, C2, D, E and G (See Figure 10.10.16 for some general details). The connections have been designed to ensure the necessary headroom clearance is achieved on all roads, considering factors such as avoiding the proposed Police Station site and minimising traffic disruption. 

East Portion – Traffic from all destinations in particular from and to Kowloon Bay / Kwun Tong / Kai Tak Development will be connected to CKR via nine proposed slip roads which are known as the Kai Tak Interchange of the CKR. These slip roads are named below and general details are found in Figure 10.12.10.

-         Slip Road S1 – CKR eastbound to Kai Cheung Road eastbound;

-         Slip Road S2 – Kai Cheung Road westbound to CKR westbound;

-         Slip Road S3 – CKR eastbound to Kai Fuk Road eastbound;

-         Slip Road S4 – Kai Fuk Road westbound to CKR westbound;

-         Slip Road S5 – CKR eastbound to Kai Tak Development (case without Trunk Road T2, as T2 will not be available by the time CKR and its east interchange are in place);

-         Slip Road S6 – Kai Tak Development westbound to CKR (case without Trunk Road T2, as T2 will not be available by the time CKR and its east interchange are in place);

-         Slip Road S7 – CKR eastbound to Road D2;

-         Slip Road S8 – Road D2 to CKR westbound; and

-         Slip Road S9 – Kai Fuk Road westbound to Kai Cheung Road eastbound.

Landscaped Decks

West – One landscaped deck is provided at the west portal in Yau Ma Tei in accordance with the ‘Yau Tsim Mong District Aspirations Study Report[1]’ published by YTM District Council in April 2010 which referred to the area of YMT around Kansu Street being developed as an intersection area for north-south and east-west movement of pedestrian and vehicular traffic.  For further details of the western landscape deck, see Figure 10.10.11, Figure 10.10.12, Figure 10.10.13, Figure 10.10.14 and Figure 10.10.15. 

East – Two landscaped deck are provided in the east portion.  One at the Kowloon City Ferry Pier Public Transport Interchange (PTI) where the existing Kowloon City Ferry Pier PTI requires re-provisioning for the duration of CKR east portion construction activities to provide working and construction space. The re-provisioned permanent PTI will remain in the same vicinity as the existing PTI shifting slightly towards To Kwa Wan Road. An accessible landscaped deck on top of the re-provisioned PTI has been proposed for public use.  The other landscape deck will be provided in Kai Tak, between the east tunnel portal of CKR and Kai Tak Development’s depressed road D3, according to the approved Kai Tak Outline Zoning Plan No. S/K22/4. According to the latest design, open space would be provided at the top of the landscaped deck. For further details of the eastern landscape decks, see Figure 10.12.7 and Figure 10.12.8. 

Demolition and / or Re-provisioning Works

The Project will include the following demolition and / or re-provisioning works which are not designated projects under Schedule 2 of EIAO.

-         Yau Ma Tei (YMT) Multi-Storey Car Park Building.  The CKR tunnel will pass beneath the existing YMT multi-storey car park building, affecting its stability and requiring it to be removed.  YMT Public Library will be re-located to a temporary building at Shanghai Street/Market Street Playground during CKR construction stage and existing government offices in the building will be re-located to the adjacent area.  After construction, the current proposal is that the library will be moved to a new government building located at the original position of the YMT multi-storey car park building.  Co-ordination with relevant government departments e.g. GPA for the temporary and permanent arrangements for the government offices are on-going. 

-         Special Clinic Extension Building (SCEB). The existing SCEB at Battery Street is also required to be demolished for the construction of CKR. A new building will be constructed in Queen Elizabeth Hospital to house the special clinic. The existing Methadone Clinic on the ground floor of SCEB will be relocated to a new clinic building within the area of the adjacent Jockey Club Polyclinic Building. 

-         Jade Hawker Bazaar. The existing, single storey, Jade Hawker Bazaar at Battery Street will need to be removed for the construction of the cut and cover tunnel. A temporary building will be built on the existing Kansu Street Rest Garden on the south side of multi-storey car park building to house the affected hawkers of the jade market during construction and after completion of the cut and cover tunnel, the hawkers will move to the new buildings located at the original Jade Hawker Bazaar position.

-         Hong Kong Automobile Association. The existing area (under short term tenancy) for Hong Kong Automobile Association needs to be cleared before the commencement of CKR construction.

-         Re-provisioning of Gascoigne Road Flyover (GRF). A section of GRF flyover between Temple Street and Ferry Street will be re-provided for the construction of CKR tunnel and removal of the existing multi-storey car park building. A temporary flyover will be provided to its north side before demolition of the affected section of the existing flyover, to divert traffic and maintain traffic flow. 

-         Landing Step for Temporary Relocation of Ma Tau Kok Public Pier - order to facilitate the construction of underwater tunnel, the existing Ma Tau Kok Public Pier is required to be demolished and a temporary Ma Tau Kok Public Pier  provided. A landing step is proposed at LCSD promenade (GLA-TK 618 TGLA) near King Wan Street for temporary boarding of the public between the bus drop-off area on King Wan Street and temporary Kowloon City Ferry Pier PTI during CKR construction stage. A small portion of the waiting area inside To Kwa Wan Vehicle Examination Centre is required to provide a minimum width of 2m between the temporary relocated Ma Tau Kok public pier and waiting area (GLA-TK 442 TGLA) of. A temporary covered walkway which directly connects the landing step and temporary PTI will be provided for the pedestrians as a safe, convenient and pleasant access. The public pier will be re-provisioned after the commissioning of CKR works and consistent with the theme of Kai Tak Development. According to the current construction methodology, dredging is not required for the temporary relocation of Ma Tau Kok Public Pier. 

Conservation Works

-         Yau Ma Tei (YMT) Police Station. The cut and cover tunnel of CKR will be constructed partly beneath the YMT Police Station which will therefore need to be decanted prior to construction but will not be demolished. After the commissioning of CKR, the YMT Police Station will be used for other, to be determined, purposes as discussed in the ‘Report on Revitalisation of Yau Ma Tei Police Station’. Conservation of the YMT Police Station is considered desirable not only due to its neo-classical architecture and it being the oldest police station in an urban context that still survives in Hong Kong, but due to its high contextual value (it gives an indication of the original coast line) and the high social value derived from the apparent bond the community has with the building. 

Enhancement Works

-         Ma Tau Kok waterfront area and Kowloon City Ferry Pier Public Transport Interchange (PTI) with cover.  The Ma Tau Kok waterfront area is planned to be part of a continuous waterfront promenade connecting Kwun Tong, Kai Tak, Ma Tau Kok and To Kwa Wan waterfronts as a long term planning proposal, as also highlighted in the approved EIA for Kai Tak Development. Besides providing pleasant public access to the harbourfront, the waterfront promenade will also act as a key green connector linking individual open spaces, residential areas and surrounding areas. Temporary re-provisioning of the existing Kowloon City Ferry Pier PTI is required to facilitate the construction of the cut-and-cover tunnel. According to Chapter 9, Section 4.2.14 of Hong Kong Planning Standards and Guidelines (HKPSG), it is recommended on the planning point-of-view to “locate the facilities (i.e. the PTI in this case) so that there is no line-of-sight of the noise sources at the noise sensitive uses”. A rooftop cover with solid barriers on the sides is proposed to screen the potential noise source of the re-provisioned PTI and provide landscape treatment to the decking as far as possible to enhance the urban environment.

Full Enclosures

Based on the noise impact assessment, noise mitigation measures using a combination of enclosure, semi-enclosure, cantilever and vertical noise barriers will be provided in the west (See Figure 10.10.5, Figure 10.10.6, Figure 10.10.7, Figure 10.10.8, Figure 10.10.9 and Figure 10.10.10 for general details of noise barriers). There are three full enclosures in total

-         West Portal End (approx. 100 m and part of the landscape deck)

-         Re-provisioned of Gascoigne Road Flyover (approx. 200 m)

-         Ferry Street Flyover (approx. 100 m)

Report Content

Following the introduction and this description of the scope of the Study, the report includes the landscape impact assessment, visual impact assessment, and discussion of mitigation measures.

The merits of preservation in totality, in parts or total destruction of existing landscape and the establishment of landscape are evaluated and alternative alignments, designs and construction methods that would avoid or reduce the identified landscape and visual impacts have been evaluated for comparison before adopting other mitigation or compensatory measures to alleviate impacts. The report is laid out as follows:

·         Section 10.3 – A list of the relevant legislation and standards;

·         Section 10.4 – A description of the general assessment methodology and principles;

·         Section 10.5 – A review of the relevant planning and development control framework;

·         Section 10.6 – A review of comments received during Public Consultation and how these have been addressed in the design;

·         Section 10.7 – A baseline study providing a comprehensive and accurate description of the baseline Landscape Resources (LRs) and Landscape Character Areas (LCAs) including their sensitivity;

·         Section 10.8 – A baseline study providing a comprehensive and accurate description of the Visual Sensitive Receivers (VSRs) including their sensitivity;

·         Section 10.9 – Landscape impact assessment including identification of the potential landscape impacts, predication of the magnitude change caused by those potential landscape impacts and their significance before and after the mitigation measures;

·         Section 10.10 – Recommendation of appropriate mitigation measures and associated implementation programmes;

·         Section 10.11 – Visual impact assessment including identification of the potential visual impacts, predication of the magnitude change caused by those potential visual impacts and their significance before and after the mitigation measures; and

·         Section 10.12 – A conclusion as to the acceptability or otherwise of the Project’s predicted residual impacts according to the five criteria set out in Annex 10 of the EIAO-TM, namely ‘beneficial’, ‘acceptable’, ‘acceptable with mitigation measures’, ‘unacceptable’ and ‘undetermined’.

10.3                   Legislation and Standards

The following legislation, standards and guidelines are applicable to the LVIA associated with the construction and operation of the Project:

·         Environmental Impact Assessment Ordinance (Cap.499, S.16) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM), particularly Annexes 10 and 18;

·         Environmental Impact Assessment Ordinance Guidance Note No. 8/2010 – Preparation of Landscape and Visual Impact Assessment;

·         Town Planning Ordinance (Cap 131);

·         Hong Kong Planning Standards and Guidelines (HKPSG);

·         ETWB TCW No. 13/2003 – Guidelines and Procedures for Environmental Impact Assessment of Government Projects and Proposals;

·         ETWB TCW No. 13/2003A – Guidelines and Procedures for Environmental Impact Assessment of Government Projects and Proposals Planning for Provision of Noise Barriers;

·         ETWB TCW No. 2/2004 – Maintenance of Vegetation and Hard Landscape Features;

·         ETWB TCW No. 29/2004 – Registration of Old and Valuable Trees, and Guidelines for their Preservation;

·         ETWB TCW No. 36/2004 – Advisory Committee on the Appearance of Bridges and Associated Structures (ACABAS);

·         ETWB TCW No. 8/2005 – Aesthetic Design of Ancillary Buildings in Engineering Projects;

·         ETWB TCW No. 3/2006 – Tree Preservation;

·         DEVB TCW No. 2/2013 – Greening on Footbridges and Flyovers;

·         WBTC No. 25/92 – Allocation of Space for Urban Street Trees;

·         WBTC No. 25/93 – on Control of Visual Impact of Slopes;

·         WBTC No. 17/2000 – Improvement to the Appearance of Slopes

·         WBTC No. 7/2002 – Tree Planting in Public Works;

·         HyD TC No. 5/2000 – Control in the Use of Shotcrete (Sprayed Concrete) on Slope Works;

·         HyD – Structures Design Guidelines for Highways and Railways. Third Edition. Section 17;

·         HQ/GN/13 – Interim Guidelines for Tree Transplanting Works under Highways Department’s Vegetation Maintenance Ambit;

·         GEO Publication No. 1/2011– Technical Guidelines on Landscape Treatment for Slopes;

·         Land Administration Office Instruction (LAOI) Section D-12 Tree Preservation;

·         LCSD Planting Manual - Part I : General Requirements of Roadside Landscape Areas

·         LCSD Register of Old and Valuable trees; 

·         Greening, Landscape and Tree Management Section - Guidelines on Greening of Noise Barriers (April 2012). 

·         Study on Landscape Value Mapping of Hong Kong; and

·         Transport Planning & Design Manual.

In addition, reference has been made to the following approved studies and EIA reports:

·         Road Works at West Kowloon (EIAO Register No. AEIAR-141/2009) approved with conditions on 23 Sep 2009

·         Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link (EIAO Register No. AEIAR-143/2009) approved with conditions on 28 Sep 2009

·         Kai Tak Airport North Apron Decommissioning EIA Report (EIA-003/1998);

·         Kai Tak Development EIA Report (EIA-157/2008);

·         Final Report on Planning, Landscape and Urban Design Study for Kai Tak Development

·         Comprehensive Feasibility Study for The Revised Scheme of South East Kowloon Development (EIA-059/2001); and

·         Feasibility Study for South East Kowloon Development (SEKDFS), Nov 1998.

·         Preliminary Outline Development Plan (PODP) for Kai Tak Development; and

·         Recommended Outline Development Plan for Kai Tak Development.

Outline Zoning Plans (OZPs) references for the Study are listed in Section 10.5.

10.4                   General Methodology and Principles

Landscape and Visual Impacts have been assessed separately for the construction and operational phase of the Project. The impact significances quoted in the landscape and visual impact assessment are of a negative nature unless otherwise specified.

10.4.1             Landscape Impact Assessment

The assessment of landscape impacts has involved the following procedures:

·         Baseline survey;

·         Assessment of the degree of sensitivity of the existing landscape;

·         Identification of the potential sources of landscape impacts;

·         Assessment of the potential magnitude change caused by landscape impacts; and

·         Predication of significance of landscape impacts before mitigation.

Baseline Survey

To conduct the landscape baseline study that describes the baseline landscape resources (LRs) and landscape character areas (LCAs) found in the Study Area, a desktop review of topographical maps and other relevant information and photographs was undertaken, as well as field surveys. Broad brush tree data were taken from a Detailed Tree Survey completed in October 2010 (submitted separately at the inception and planning stage and key results provided in Annex B) to provide a broad understanding of trees around the Project Site. Landscape elements surveyed include vegetation, rock features, patterns of settlement, land use and water bodies.

Assessment of the Degree of Sensitivity of the Existing Landscape

The individual LCAs and LRs identified in baseline survey were assessed by following factors that influence sensitivity:

·         Quality and maturity;

·         Importance or rarity in local, regional, national or global context;

·         Ability to accommodate change;

·         Overall size within the Study Area; and

·         Whether there are any statutory or regulatory limitations / requirements relating to the LCAs and LRs.

The Sensitivity of each LCA and LR is classified as follows:

·         High: Important landscape resource or landscape of particularly distinctive character or high importance, sensitive to relatively small changes

·         Medium: Landscape resource or landscape of moderately valued landscape characteristics, reasonably tolerant to change

·         Low: Landscape resource or landscape of relatively unimportant landscape characteristics, largely tolerant to change

Identification of the Potential Sources of Landscape Impacts

These are the various elements of the construction works and operational procedures that may generate landscape impacts. Such landscape impacts are described further in Section 10.9 (Landscape Impact Assessment) of this report.

Assessment of the Potential Magnitude of Change caused by Landscape Impacts:

The magnitude of change on each LCA and LR, caused by landscape impacts at both construction and operation phases, is elevated in this report. Information from the Broad brush Tree Survey is considered when determining the magnitude of change, and other factors considered are:

·         The physical extent of the impacts i.e. relative size of affected area compared to the size of the LCAs and LRs in the whole Study Area;

·         Compatibility of the Project with the surrounding landscape;

·         Duration of impacts under construction and operation phases; and

·         Reversibility of change.

The magnitude of change is classified as follows:

·         Large: The LCA or LR would experience a major change

·         Intermediate: The LCA or LR would experience a moderate change

·         Small: The LCA or LR would experience a slight or barely perceptible change

·         Negligible: The LCA or LR would experience no discernible change

Predication of Significance of Landscape Impacts before Mitigation:

The Impact Significance is a definition of the landscape impacts before mitigation.  The landscape impact significance during construction and operation was assessed by combining the sensitivity of the sensitive receiver and the magnitude of change caused by the impacts, according to Table 10.1. Impact significance is taken to be adverse unless stated otherwise as beneficial.

Table 10.1:  Matrix for Impact Significance

Magnitude of Change caused by the Project

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Slight

Slight / Moderate

Moderate

Negligible

Insignificant

Insignificant

Insignificant

 

Low

Medium

High

 

Sensitivity (LCAs, LRs or VSRs)

The degree of Impact Significance is divided into four thresholds:

·         Substantial: Adverse / beneficial impact which will cause significant deterioration or improvement in existing landscape

·         Moderate: Adverse / beneficial impact which will cause noticeable deterioration or improvement in existing landscape

·         Slight: Adverse / beneficial impact which will cause barely perceptible deterioration or improvement in existing landscape

·         Insignificant: No discernible change in the existing landscape

10.4.2             Tree Survey Methodology

To minimize conflicts with existing vegetation, a Detailed Tree Survey in accordance with ETWB 3/2006 was undertaken in October 2010 under the Agreement No. CE 58/2006(HY) for the whole development site. These data were used to facilitate the fine tuning of the proposed detail design for the landscape and ensure that any significant trees, where possible, be protected during both the design and construction periods. A further Detailed Tree Survey will be carried out at a later stage of the Project (mid 2013) when trees within the final agreed works areas will be surveyed individually as the existing site conditions allow.

10.4.3             Visual Impact Assessment

The assessment of visual impacts has involved the followings procedures:

·         Identification of the Zones of Visual Influence (ZVIs);

·         Identification of Visual sensitive receivers (VSRs) within the ZVIs;

·         Assessments of the degree of sensitivity of the VSRs;

·         Identification of potential sources of visual impacts;

·         Assessment of the potential magnitude of change caused by visual impacts; and

·         Predication of significance of visual impacts before mitigation.

Identification of Zone of Visual Influence (ZVIs):

This is achieved by site visit and desktop study of topographic maps and photographs, and preparation of cross-section to determine visibility of the Project from various locations. The ZVIs for both construction and operational phase of the Project are identified.

Identification of Visual Sensitive Receivers (VSRs) within the ZVIs:

These are the people who would reside within, work within, play within, or travel through, the ZVIs.

Assessments of the Degree of Sensitivity of the VSRs:

Factors for considering the degree of sensitivity of the VSRs include:

·         The type of VSRs, which is classified as Residential, Occupational, Recreational or Travelling according to whether the person is at home, at work, at school, at play, or travelling. Those who view the impact from their homes are in general considered to be highly sensitive as the character of view from their home will have a substantial effect on their perception of quality and acceptability of their home environment and their general quality of life. Those who view the impact from their workplace are generally considered to be moderately sensitive as the character of view will have a less important effect on their perception of quality of life. Those who view the impact while taking part in an outdoor recreational activity may display varying sensitivity depending on the type of activity. Those who view the impact while travelling on a public thoroughfare will display varying sensitivity depending on the mode and speed of travel;

·         Estimated number of receiver population expressed in terms of whether there are very few, few, many or very many VSRs in any one category of VSR;

·         Value and quality of existing views;

·         Availability and amenity of alternative views;

·         Duration or frequency of view; and

·         Degree of visibility.

The rating for Sensitivity of the VSRs is classified as below:

·         High: The VSRs are highly sensitive to any change in their viewing experience

·         Medium: The VSRs are moderately sensitive to any change in their viewing experience

·         Low: The VSRs are only slightly sensitive to any change in their viewing experience

Identification of Potential Sources of Visual Impacts:

These are the various elements of the construction works and operational procedures that would generate visual impacts.  Such visual impacts are described further in Section 10.9 (Visual Impact Assessment) of this report.

Assessment of the Potential Magnitude of Change caused by Visual Impacts:

Factors for considering the potential magnitude of visual impacts include:

·         Compatibility with the landscape and character of the surroundings;

·         Duration of impacts during construction and operation phases;

·         Scale of the project when viewed from the VSR;

·         Reversibility of the impact;

·         Viewing distance between the nearest source of impact and VSR; and

·         Potential blockage of views i.e. the extent the impact dominates the field of vision of the viewer.

The magnitude of change is classified as below:

·         Large: The VSRs would suffer a major change in their viewing experience

·         Intermediate: The VSRs would suffer a moderate changes in their viewing experience

·         Small: The VSRs would suffer a small change in their viewing experience

·         Negligible: The VSRs would suffer no discernible changes in their viewing experience

Predication of Significance of Visual Impacts before Mitigation:

The significance of visual impacts is determined by combining the magnitude of the various visual impacts and the sensitivity of the VSRs affected. Impact significance is taken to be adverse unless stated otherwise as beneficial. Table 10.1 shows the rationale for dividing the degree of significance into four thresholds, namely, insignificant, slight, moderate and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of change and a low-medium-high degree of sensitivity of VSR.

The Significance rating is divided into four and defined as below:

·         Substantial: Adverse / beneficial impact where the Project would cause significant deterioration or improvement in existing visual quality

·         Moderate: Adverse / beneficial impact where the Project would cause noticeable deterioration or improvement in existing visual quality

·         Slight: Adverse / beneficial impact where the Project would cause barely perceptible deterioration or improvement in existing visual quality

·         Insignificant: The impacts would cause no discernible change in the existing visual quality

10.4.4             Acceptability of Landscape & Visual Impacts

Measures to mitigate landscape and visual impacts and reduce their significance have been suggested for the Project.  Impact significance is reassessed assuming implementation of appropriate mitigation measures and this is termed ‘Residual Impact’.  The acceptability of impact is judged upon the residual impacts from the Project.  This is explained in further detail under the following headings:

·         Identification of Potential Landscape and Visual Mitigation Measures;

·         Predication of Residual Impacts after Mitigation;

·         Acceptability of the Impacts. 

Identification of Potential Landscape and Visual Mitigation Measures

The identification of the landscape and visual impacts highlight those sources of conflict requiring design solutions or modifications to reduce the impacts, and, if possible, blend the development and associated activities in with the surrounding landscape.  Mitigation measures have considered factors including:

·         Avoiding impact on existing sensitive receivers during construction by carefully designed construction methods;

·         Adopting alternative design or revisions to the basic engineering or the architectural design to prevent and / or minimize adverse impacts;

·         Remedial measures such as colour and textural treatment of physical, engineering and building features;

·         Compensatory measures such as the implementation of landscape design measures (e.g. tree planting, creation of new open space etc.) to compensate for unavoidable adverse impacts and to attempt to generate potentially beneficial long-term impacts; and

·         Screening measures such as through tree and/or shrub planting to screen roads and associated structures.

These measures will alleviate the previously identified landscape and visual impacts as far as possible, both during construction and operation phases, and ensure that the residual impacts are acceptable. The agencies responsible for the funding implementation, management and maintenance of the mitigation measures are identified.

Predication of Residual Impacts after Mitigation

The residual impacts are those which remain after the proposed mitigation measures have been successfully implemented.  Residual impacts are assessed both during the construction period, at the commissioning of the Project on day one and during the Design Year, which is taken to be 10 years after the Project has been opened to normal operation.  During the Design Year the soft landscape mitigation measures are deemed to have reached a level of maturity, which allows them to perform their full original mitigation objectives. 

Prediction of Acceptability of Impacts

The criteria and matrices used to determine the degree of impact described in the above sections.  Both landscape and visual impacts are products of magnitude of change and the relative sensitivity of the sensitive receiver.  Ultimately, the acceptability of the Project is dependent upon the significance of the residual impacts in accordance with the five criteria set out in Annex 10 of the EIAO-TM, namely ‘beneficial’, ‘acceptable’, ‘acceptable with mitigation measures’, ‘unacceptable’ and ‘undetermined’.

10.5                   Review of Planning and Development Control Framework

In this study, relevant Outline Development Plans, Outline Zoning Plans, Layout Plans, Preliminary/ Recommended Outline Development Plan for Kai Tak and any other relevant statutory and development plans are reviewed.  This may identify areas of high landscape value as well as the existing and planned development context and will also have implications on the visual environment and the location, type and numbers of VSRs to be affected. Any guidelines on landscape strategies, landscape framework, urban design concept, building height profiles, designated view corridors, special design areas, landmarks, open space network and landscape links that may affect the appreciation of the Project are also reviewed. Any conflict with published land use plan(s) are highlighted and appropriate follow-up action recommended.

The Central Kowloon Route traverses the central part of the Kowloon Peninsula, and the landscape Study Area falls within Kowloon Planning Areas KPA No. 2 (Yau Ma Tei), KPA No. 6&7 (Ho Man Tin), KPA No. 10 (Ma Tau Kok), KPA No. 13&17 (Ngau Tau Kok and Kowloon Bay), KPA No. 20 (South West Kowloon), and KPA No. 22 (Kai Tak). A review of the existing and planned development framework for the proposed works in the Study Area has been considered. It aims to identify issues for the neighbouring planned land uses, and to ensure a high compatibility between the Project and its surroundings. Figure 10.4 illustrates the OZPs affected by the whole Project, which include:

·         Draft South West Kowloon Outline Zoning Plan (No. S/K20/27) gazetted on 30/03/2012;

·         Draft Yau Ma Tei Outline Zoning Plan (No. S/K2/21) gazetted on 29/10/2010;

·         Approved Ho Man Tin Outline Zoning Plan (No. S/K7/22) gazetted on 13/07/2012;

·         Approved Ma Tau Kok Outline Zoning Plan (No. S/K10/20) gazetted on 14/11/2008

·         Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan (No. S/K13/27) gazetted on 14/10/2011; and

·         Approved Kai Tak Outline Zoning Plan (No. S/K22/4), gazetted on 14/09/2012.   

The ‘Yung Shu Tau Urban Design Conceptual Study’ was carried out in 2009 to study the land use planning and urban design in the West Portion taking into account of some initial ideas collected from the public during consultations in 2008.  The Yung Shu Tau area in Yau Ma Tei was selected as being where cultural and historical heritage are most significant along the CKR Route.  This study report has been reviewed and key information included for the West Portion below. 

For the East Portion particular attention has been made to reports from the ‘Agreement No. CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction’, regarding land use and development and key information is included below. 

10.5.1             West Portion

Outline Zoning Plan (OZPs)

The Project Works Area of the West Portion is located within the Draft South West Kowloon OZP (No. S/K20/27) and Draft Yau Ma Tei OZP (No. S/K2/21) as illustrated in Figure 10.4.1. OZP No. S/K2/21 sets out various building height restrictions as well as building set-back, non-build area and building gap stipulations all of which the Project adheres to.

The Project Works Area/ surface construction activities are predominantly located within Open Space (O) and Government / Institution / Community (G/IC) zoned areas of the affected OZPs and it also a small overlap with Open Space (1) (O1) where it borders this area which is part of the XRL Project.

Much of the CKR road alignment and the CKR ventilation building fall on road/ un-zoned areas and will retain the same use so there is no conflict. Where the connection road passes near Yau Cheung Road and near the tunnel portal, G/IC and O zones area affected. Zones classified as G/IC are intended primarily for the provision of GIC facilities serving the needs of the local residents and/or a wider district, region or the territory.  Some buildings in G/IC zone will be demolished during the construction phase, but these will be re-provisioned in adjacent areas, with the same land use zoning (See Section 10.2). Zones classified as O are intended primarily for the provision of outdoor open-air public space for active and/or passive recreational uses serving the needs of local residents as well as the general public. All areas of public open space affected by the Project will be re-provisioned either at the same location following the completion of temporary works, as a ‘landscape deck’ or at a separate site, as agreed with relevant Government departments. Therefore, it is considered that the Project in the West Portion has no potential conflicts with the existing Planning and Development Control framework.

Future Land Use Planning at West Portion

With the construction of CKR, some cleared land will have been created by the demolition of certain buildings in the Yau Ma Tei area including the Special Clinic Extension Building (to be re-provisioned in the Queen Elizabeth Hospital) and Hong Kong Automobile Association. As such, CKR will provide a good opportunity to provide new permanent open spaces and facilities. Land use planning has focused around some initial ideas from the ‘Yung Shu Tau Urban Design Conceptual Study’ as detailed below.  Note these are subject to further discussions among government departments and bureaux and the future land use is not yet final. 

Conservation of Yau Ma Tei Police Station

Yau Ma Tei Police Station was gazetted as a Grade 3 historic building in 1998 and is currently recommended for re-classification as a Grade 2 historic building by the Antiquities and Monuments Board.  The police station is to be re-provided independently of the CKR project and the existing building will be converted into a public museum. The existing police station contains a reporting centre with floor area of around 166m² and an equivalent reporting centre is desired by the Police Service to be re-provided in the vicinity of the existing station.

Greening at Ground Level

Since some of the public facilities along Kansu Street will have to be reprovisioned for the construction of CKR, space will be available on the original sites of some of these facilities for greening. This includes the original site of the Yau Ma Tei Specialist Clinic Extension.

During the construction of CKR, the sitting out area on the southern side of Henry G. Leong Yau Ma Tei Community Centre will be occupied for the temporary reprovisioning of the Yau Ma Tei Public Library and Jade Hawker Bazaar. Furthermore, the basketball court to the south of the resting area will be occupied for the construction of the access shaft for construction of the tunnel. Upon the completion of the works, the basketball court and the greening and sitting out facilities will be reprovided in accordance with the existing layouts.

The sitting out area and open area adjacent to the existing Yau Ma Tei Police Station will be used as work sites during the construction of CKR. The existing facilities will be reprovisioned after the completion of the works. Greening will also be provided in the open area on the west of the junction between Ferry Street and Yan Cheung Road.

Yau Ma Tei Multi-storey Carpark Building (YMTCPB)

YMTCPB will be demolished about one year after the commencement of the project. The offices of Social Welfare Department, Lands Department and Transport Department inside the building will be temporarily moved to other buildings. The detailed arrangements are being finalised. For the long-term, these facilities will be re-provisioned within the proposed West Kowloon Government Offices. The existing office of Immigration Department inside YMTCPB will be moved to Tsim Sha Tsui before the project starts and hence will not be affected by the works.

The public library within YMTCPB will be relocated to the sitting out area south of Henry G. Leong Yau Ma Tei Community Centre. The Library and Jade Hawker Bazaar will be accommodated in the same temporary building. The Jade Hawker Bazaar will be on the ground floor. The library will be at 1/F to 3/F. Upon the completion of the works, the public library will be relocated to a new building to be constructed on the original site of the YMTCPB.

10.5.2             Central Portion

Outline Zoning Plans (OZPs)

The Project Works Area of the Central Portion is located within the Approved Ho Man Tin Outline Zoning Plan (No. S/K7/22) as illustrated in Figure 10.4.2.

The Project Works Area/ surface construction activities are all located within Government / Institution / Community (G/IC). The ventilation building of the proposed works will be located on G/IC zoned land.  Zones classified as G/IC here are intended primarily for the provision of GIC facilities serving the needs of the local residents as well as the general public. According to the Notes of the OZP, the proposed ventilation building is neither a Column 1 nor 2 use of the “G/IC” zone.  If this building is included as part of the gazetted road scheme of this Project authorized under the Road (Works, Use and Compensation) Ordinance (Cap 370), it would be deemed to be approved under the Town Planning Ordinance.  If this building is included as part of the gazetted road scheme of this Project authorized under the Road (Works, Use and Compensation) Ordinance (Cap370), it is deemed acceptable under the Town Planning Ordinance. Assuming this to be the case, no potential conflicts are found between the Project around the Central Portion and with the existing Planning and Development Control framework. If not, an amendment to the OZP under Section 12A of the TPO would be required.

10.5.3             East Portion

Outline Zoning Plans (OZPs)

The Project Works Area in the East Portion is located mainly in the Approved Kai Tak Outline Zoning Plan (No. S/K22/4). It also borders and has small overlaps with the Approved Ma Tau Kok Outline Zoning Plan (No. S/K10/20) and Draft Ngau Tau Kok and Kowloon Bay Outline Zoning Plan (No. S/K13/27), as illustrated in Figure 10.4.3.

The Project Works Area / surface construction activities are located within Government / Institution / Community (G/IC), Open Space (O), Open Space (1) (O (1)), Open Space (2) (O (2)), Other Specific Uses (OU), Other Specific Uses –Amenity Area (OU (A)), and Residential (Group A) (R(A)) of OZP No. S/K22/4).

The proposed CKR Project was considered and is incorporated into this OZP for the Kai Tak Development (KTD) by PlanD (OZP No. S/K22/4). Therefore, areas for tunnel portal, depressed road, connection road and ventilation/administration buildings of the CKR Project have been reserved within OZP No. S/K22/4 and comply with the planning intention. The small overlaps into OZPs S/K10/20 and S/K13/27 are all into areas shown as ‘Road’ and will therefore not conflict with the planning intention in these areas. Therefore overall there are no potential conflicts between the Project in the east and with the existing Planning and Development Control framework.

Kai Tak Development (KTD)

The KTD has been designed considering a number of objectives to ensure the creation of a successful urban environment, responsive to its unique context and site conditions. Figure 10.4.4 shows the approved Kai Tak Outline Zoning Plan and the design considerations are set out as below. CKR design follows these considerations to ensure its integration with KTD.

Connectivity with Surrounding Neighbourhoods

Pedestrian linkage and continuity of movement patterns are critical to the success and usability of the area. This will help to revitalize the older areas and ensure high levels of interface and visitation to the new area, with district urban quarters that are responsive to their context. At the same time, transport connections are integrated to support operations within the area, and with other areas.

Creation of Physical and Activity Nodes

The plan is formulated around the creation of district and sub-regional nodes which must function, in urban design terms, as vibrant destinations whether they act as sports hub, commercial centre or tourism-leisure hub. In turn their success is dependent on strong connectivity and transit strategy. Figure 10.4.5 illustrates the proposed sub-districts and their potential connections. 

Establishment of an Active Waterfront

The waterfront is regarded as an enormous natural asset for public accessibility, perambulation and enjoyment. Pedestrian movement shall be continuous, and link together a range of diverse programmes and activities which offer a sequence of promenades, parklands, commercial and retail oriented areas.  This consideration is particularly relevant to CKR along the Ma Tau Kok Waterfront (See following Section on ‘Urban Design Study for Enhancement of Ma Tau Kok Waterfront Area’). 

Establishment of a Continuous Open Space System

The KTD open space framework allows for ‘green’ continuity, informal pedestrian circulation, and connects together leisure, recreational, cultural and commercial areas. It is considered to largely determine the identity of Kai Tak. 

Creation of a Pedestrian Friendly Environment

Apart from a continuous and connective pedestrian system, the pedestrian experience shall be user friendly in terms of comfortable walking radii from public transport, visually contrasting experiences, and environmentally convenient and safe connections, both horizontally and vertically.

Creating Dynamic and Visually Interesting Urban Places

The various planning areas should present a mix of architectural and spatial compositions at various scales as appropriate. While height limitations have been set in various areas, there is a need for an interesting mix of building forms, scales and skyline profile to establish the image and identity of the Kai Tak area.

Integrate Urban Gateways

Gateways must express the various transitions that occur within the Kai Tak area, and between the new development district and the surround area. These can take on a variety of different forms and types, and normally signal points of arrival, changes of pedestrian or vehicular condition, specific types of street function and expressive visual markers.

Legibility, Orientation and Views

It is necessary to provide visual cues that assist the process of orientation. Within the overall spatial framework, this entails the integration of visual corridors and important view sheds to regional or city-wide features, the use of prominent landmark elements, and the serial ‘framing’ of sequential visual experiences throughout the overall movement framework. Figure 10.4.6 illustrates the visual connections and breezeways identified within KTD.

Creation of Streetscape

Whenever possible the creation of coherent and continuous streetscape should form a key consideration of avenue design through ‘joined together’ elements to provide consistent built edge, consistency of height profiles, architectural identity, signage channels, and landscape.

Urban Design Study for Enhancement of Ma Tau Kok Waterfront Area

With a view to enhancing connectivity and accessibility of the Ma Tau Kok waterfront area and responding to community needs, initial urban design concepts were proposed in the Urban Design Study for Enhancement of Ma Tau Kok Waterfront Area, which aimed at providing leisure and recreation uses (e.g. waterfront promenade, multi-purpose activities centre, cultural amenity etc.) and revitalising existing spaces by adopting new uses (e.g., restaurant at the Kowloon City Ferry Pier etc.). These initial ideas on land use planning were not finalized, and have been subject to further consultations with Government departments, stakeholders and other planning, design and construction considerations.

Re-provisioning of the Public Transport Interchange (PTI)

The existing Public Transport Interchange will be re-provisioned after the construction of CKR. It is proposed to maintain similar number of spaces for bus terminus, car and coach parking in the re-provisioned PTI. The PTI will be landscaped to enhance amenity and mixed use was encouraged to enhance vibrancy in the area.

Re-provisioning of Ma Tau Kok public pier

It was proposed that Ma Tau Kok public pier be demolished during construction of CKR and re-provisioned after the commissioning of the Project to provide a viewing deck above the future public pier.

Adaptive Reuse of the decommissioned Vehicular Ferry Pier

It was proposed that the decommissioned vehicular ferry pier be retained with adaptive re-use to provide an Interpretive Centre to exhibit the history of the vehicle ferry services in the harbour context. 

Alternative use of the Vehicle Examination Centre

It was suggested in the public forums that the To Kwa Wan Vehicle Examination Centre be relocated to open up the waterfront and provide community facilities for Ma Tau Kok area. An open pavilion/café and possibly an activity centre could be provided at the existing site upon the relocation of the public facility.

Enhance Vitality of Kowloon City Ferry Pier

The structure of Kowloon City Ferry Pier will not be affected by the construction of CKR.  It is proposed to provide restaurant use on top level of the ferry pier to enhance vitality.   There is an opportunity to provide an elevated waterfront walkway connecting the second level of the proposed Kowloon City Ferry Pier, with the Interpretive Centre, the viewing deck above the re-provisioned public pier and PTI to enhance connectivity to the waterfront promenade.

A 20m-wide Promenade along Ma Tau Kok Waterfront

With the proposed relocation of To Kwa Wan Vehicle Examination Centre, there is an opportunity to provide a 20m-wide promenade along Ma Tau Kok Waterfront. Closure of King Wan Street and opening up of the Vehicular Ferry Pier and To Kwa Wan Vehicle Examination Centre were proposed for further investigation, to provide a continuous promenade along the waterfront. It was further proposed to pedestrianise Long Yuet Street to enhance integration of open spaces, waterfront promenade and the residential area nearby.

Provision of Multi-purpose Activity Centre for the Community

In the public forums, it was suggested that Ma Tau Kok area was lacking community facilities and a multi-purpose activity centre should be built to serve the local community. There were two proposed locations for the centre, one near the primary schools on Kwei Chow Street and other one at the vehicle examination centre site.

 

Overall, it is considered that the Project would be in accordance with the planning goals and objectives for the study areas, as set out in all relevant OZPs and detailed in planning studies and investigations. 

10.6                   Comments on Landscape and Visual Issues Received During Public Forum

A series of public engagement activities are held in parallel with the investigation study initiated by the MMHJV and HyD for the purpose of enhancing public participation in the development of Central Kowloon Route.

The main events are a series of public forums, supplemented by outreach events and monthly newsletters. Yau Ma Tei local culture and the social and land impacts of the projects also studied by on-street surveys and in depth interviews with stakeholders.

Views of the public and concerned parties were obtained at the following presentations and forums:

·        Stage 1 Public Forum on 10 November 2007;

·        Stage 2 Public Forum on 19 January 2008; and

·        Stage 3 Public Forum on 15 March 2008.

·        Public Forum: Specific Issues – Yau Ma Tei Urban Design and the Conservation of Yau Man Tei Police Station on 10 January 2009.

·        Public Forum: Specific Issues – The construction of the Central Kowloon Route section at Kowloon Bay, re-provisioning facilities and enhancement opportunities on 7 Feb 2009.

Issues raised were commonly focused on increasing greening area and providing quality open space. These comments will be addressed by providing landscaped decks on tunnel portals.

10.7                   Landscape Baseline Study

Landscape baseline review comprises the identification of all existing Landscape Resources (LR) and Landscape Character Area (LCA) within 100m of the Project works area. LRs are mapped in Figure 10.5 (key plan) and in further detail in Figure 10.5.1, Figure 10.5.2 and Figure 10.5.3 with illustrative photographs presented in Figure 10.6.1, Figure 10.6.2, Figure 10.6.3, Figure 10.6.4, Figure 10.6.5 and Figure 10.6.6. LCAs are mapped in Figure 10.7 (key plan) and specifically Figure 10.7.1, Figure 10.7.2 and Figure 10.7.3 and illustrative photographs are presented in Figure 10.8.1, Figure 10.8.2 and Figure 10.8.3.

The tree numbers quoted in this report have been estimated based on the tree survey report completed in October 2010 under the CKR and Widening of Gascoigne Road Flyover Investigation under Agreement No. CE 58/2006(HY) and Figure 10.9.1, Figure 10.9.2 and Figure 10.9.3 show trees survey plans based on this survey.  It is noted that an updated tree survey will be conducted for this Project (targeting to be commenced in mid 2013). 

In terms of the visual aspects, baseline information is detailed in Section 10.8.

For ease of reference, each LR, LCA and VSR is given an identity number, which is used in all relevant tables and figures in this report.

10.7.1             Landscape Resources

The Central Kowloon Route traverses the central part of the Kowloon Peninsula, linking West Kowloon in the west to the proposed Kai Tak Development (KTD) in the east, both of which are highly urbanized areas. Given the overall urban and highly developed nature of the Study Area, the focus for identifying LRs in the Study Area, has been on those land based LRs with some planting/ natural vegetation and on water bodies and those LRs falling within the Works Area.    LRs within the Study Area are divided into eight broad types, and key LRs falling outside the Works Area which will not be affected by the Project are included here.  The eight broad LR types are detailed as:

1.         Public Open Space

This broad LR refers to public open spaces containing planting managed by LCSD. The species consist of a wide variety of exotic and native ornamental species, such as Bauhinia spp., Lagerstroemia speciosa, Michelia x alba and Cassia surattensis. The trees are generally mature, with fair to good health condition and fair to high amenity value. The trees generally have fair to good form, are well maintained and act as valuable greening relief for the urban district.

In the West Portion public open space falling outside the Works Area but within the Study Area, is the Tin Hau Temple Complex in the West Portion made up of the Yau Ma Tei Community Centre Rest Garden and the Public Square Street Children’s Playground and Rest Garden on either side of the temples.  There are approximately 45 trees in this LR, mostly within the Yau Ma Tei Community Centre Rest Garden. Trees are dominated by Ficus microcarpa, including one which is 15 m high with a crown spread of 16 m and DBH of 1500 mm which is registered as OVT number LCSD YTM/99.  Other common species include mature Aleurites moluccana and Podocarpus macrophyllus and none of these trees will be affected by the Project since the Works Area does not fall on this LR. 

In the East Portion three areas of open space of note fall outside the Works Area but within the Study Area. The Kowloon Bay Recreation Ground and Sports Ground and Kin Bay Playground near the Auxiliary Police Headquarters at Kai Cheung Road consists of a number of grass pitches, an outdoor running track and outdoor hard courts with some peripheral planting.  Any peripheral planting within the Works Area is included in LR 3.3e for the impact assessment.  Overall, however, this open space will not be affected by the Project as all the facilities are outside the Works Area. Two other areas of open space in the East Portion outside the Works Area are parks. Hoi Sham Park is east of Yuk Yak Street and south of Sun Fung Street. It contains outdoor hard court recreational facilities, toilets and a landscaped park area with over 30 trees both planted and in planters, including mature Ficus microcarpa, Aleurites moluccana and younger Juniperus chinensis.  It is also well known for the Fish Tail Rock which is a key feature of the park, now being attached to it via reclaimed land, where once the rocks were surrounded by water.  King Wan Street Playground lies north of Sun Fung Street and west of King Wan Street. It also has some outdoor hard court recreational facilities as well as approximiately 15 trees including Aleurites moluccana, Delonix regia and Bombax ceiba among the hard paved areas. These parks are rich, green areas and since they lie outside the Works Area, are not expected to be affected by the Project.

Figure 10.5.1, Figure 10.5.2 and Figure 10.5.3 illustrate the location of these public open spaces in the West and East Portions respectively.  No impact is expected on these specific LRs since they fall outside the Works Area. 

2.         Urban Residential / Institutional Open Space

This broad LR refers to open space within private residential developments and institutions, which is not open to the general public. The areas include podium gardens and entrance plazas for residential developments. The planting consists of a wide variety of exotic, ornamental species including Bauhinia spp., Lagerstroemia speciosa and Ficus benjamina. The plants generally have fair to good form, are well maintained and provide favourable greening for residents and facility users.

3.         Roadside Planting

This broad LR refers to amenity planting along roads, central dividers or roundabouts, which provide greening for the extensive hard-paved urban area. Exotic ornamental tree species, such as Aleurites moluccana, Bauhinia spp., Lagerstroemia speciosa and Grevillea robusta, are commonly found along the roadsides of Central Kowloon and are fairly large in size and of fair condition. Shrub species include Duranta repens, Ficus microcarpa ‘Golden’, Hibiscus rosa-sinensis and Rhododendron spp.

In the West Portion various areas of roadside planting fall outside the Works Area but within the Study Area.  The roadside planting along Hoi Fai Road, Hoi Po Road, and Lin Cheung Road; the roadside tree planting along Hoi Ting Road and the junction of Hoi Ting Road/ Hoi Wang Road; Tree planting around the car part at the junction of Waterloo road and Ferry Street, all include the main tree species Bauhinia spp., Aleurites moluccana, and Lagerstroemia speciosa. There is some planting in the vicinity of the bus depot area near the Fire services Department’s West Kowloon Training Centre but this is mainly grasses and young shrubs as the depot is relatively new. There is also some planting along Kwai Yue Lane up near Kwai Chung barging point, including approximately 10 trees of poor quality including Ficus spp. trees and the weedy Leucaena leucocephala. 

Figure 10.5.1 illustrates the location of these roadside planting areas in the West Portions and since these specific LRs fall outside the Works Area, none of the trees are expected to be affected by the Project. 

4.         Vegetation on Man-made Slope

This broad LR refers to the vegetation on man-made slopes formed during site formation works for hillside developments (not site formation for the CKR Project) and slope improvement works. Trees are generally medium size and mainly exotic woodland species such as Acacia confusa, Casuarina equisetifolia and Eucalyptus spp.. This LR can provide a greening connection from flat areas with development / open space to semi-natural hillside vegetation.

5.         Disturbed Area with Wild Grass / Small Shrubs

This broad LR refers to vacant land, overgrown with wild grasses and/or small shrubs and principally refers to small areas at Yau Ma Tei and the large area within the former Kai Tak Airport area.

6.         Lawn Area

This broad LR refers to the grassy surface of the football field at Ho Man Tin East Service Reservoir Playground and the grassy surface of the Ho Man Tin West Fresh Water Service Reservoir. Common lawn grass species such as Axonopus compressus and Cynodon dactylon are found planted on the football field.

(7.        Not Used)

8.         Man-made Shoreline

This broad LR refers to the man-made shoreline of Kowloon Bay along Ma Tau Kok and former Kai Tak Airport area which have little if any landscaping. It also includes a small area of the Yau Ma Tei Typhoon Shelter that lies within the Study Area in the West Portion but is not with the Works Area and is considered to remain unaffected by the Project.

9.         Water Bodies

This LR refers to the two major water bodies within LIA Study Area, namely Kowloon Bay and Kai Tak Nullah and the Kai Tak River that feeds into it.  It also includes a small water body near Kwai Chung barging point which will not be affected by the Project.

The baseline LRs within the works area, together with their sensitivity, are described below, as summarised in Table 10.2 following. All LRs in the West Portion are labelled LR 1.x, all LRs around the Central Portion are labelled LR 2.x and all LRs in the East Portion are labelled LR 3.x, where ‘x’ refers to the broad LR type described above.

10.7.1.1            West Portion

LR1.1a – Public Square Street Playground

This playground is a small paved open area enclosed by planters. There are approximately 15 trees within this LR, with a majority of the exotic palm Livistona chinensis. There are also a number of native Ficus microcarpa as well as specimens of Albizia lebbeck, Aleurites moluccana, Bauhinia blakeana, Cassia surattensis, Crateva unilocularis and Ficus elastica and trees range in height from 3 – 20 m with 2 -22 m crown spread. This small open space is dominated by three mature Albizia lebbeck, Aleurites moluccana and Crateva unilocularis trees at the entrance facing Public Square Street, whose condition is generally fair. The trees in this LR add medium landscape value and overall the LR sensitivity is medium.

LR1.1b – Shanghai Street / Market Street Playground

This playground has two basketball courts, one at either end, with some trees and shrubs planted at the border. The remaining area is covered with hard paving and has limited planting areas. There are about 10 trees within the playground, including Bauhinia spp., Ficus benjamina, Ficus virens and Lagerstroemia speciosa. There is one very good specimen of Ficus virens at the edge of the basketball court facing Shanghai Street which is deemed of high value. The trees in this LR are 5-12 m high with crown spread between 3-14 m. They add medium landscape value and overall the LR sensitivity is medium.

LR1.1c – Bazaar

This LR refers to the concrete paved small bazaar at the junction of Kansu Street and Shanghai Street. The whole area is enclosed by four semi-mature and wide spread Ficus microcarpa trees and one Morus alba tree. The trees range in height between 6 – 12 m and have a crown spread between 8 -18 m. The general condition of the trees is fair, and some of their trunks and exposed roots are merged with the railing. Three of the Ficus microcarpa trees are considered to be of high value; their roots are merged with the railings and they reach between 10-12 m high with crown spreads between 12-18 m.  These trees are valuable streetscape greening in the urban setting and overall the LR sensitivity is high.

LR1.1d – Temple Street / Kansu Street Temporary Rest Garden Garden

This is a small paved open area next to the Yau Ma Tei Carpark Building with childrens’ play equipment. Any plants in this area are young and planted in pots. Species include Michelia x alba and Chrysalidocarpus lutescens. Their general condition is fair. The plants in this LR are portable and provide limited landscape value and overall the LR sensitivity is low.

LR1.1e –Yau Ma Tei Jade Market/ Jade Hawker Bazaar

This Jade Hawker Bazaar near Kansu Street is also called the ‘Yau Ma Tei Jade Market’ and is a major tourist attraction in Hong Kong.  It comprises two single-storey bazaars housed in a single-storey steel shed located on two sites to the north of Kansu Street.  The market sheds and surrounding area contain 10 live trees.  Species are dominated by Morus alba, on average 8 m tall and 5 m crown spread and 300 mm DBH.  Their general condition is fair.  One large Ficus microcarpa grows through the market roof and is approximately 12 m tall, with a DBH of about 500 mm and crown spread of 20 m and another tree growing through the roof is an Aleurites molucanna tree of approximately 12 m height, 480 mm DBH and 10 m crown spread.  The trees in this LR provide landscape value and overall the LR sensitivity is high.

LR1.3a – Roadside Planting along West Kowloon Highway and Tunnel Area

This LR refers to the roadside trees along West Kowloon Highway and Tunnel Area. There are over 1,560 trees planted along the West Kowloon Highway and Tunnel area but a number of these fall outside the works area. The majority of the trees are common woodland plantation species including exotic species Acacia confusa, Acacia mangium, Casuarina equisetifolia, Eucalyptus spp. and Syzygium cumini. There are also over 50 common native Ficus microcarpa trees. On average the trees range in height from 10 m to 15 m with up to 15 m crown spread.  Although the trees themselves are not of particularly high value, the high numbers of trees in this LR add considerable greening value to the landscape and overall the LR sensitivity is high.

LR1.3b – Roadside Planting along Hoi Wang Road, Yan Cheung Road and Ferry Street Area

Approximately 125 trees are planted at the central dividers and roadside along Hoi Wang Road, Yan Cheung Road and around Ferry Street. The species planted at the central dividers include the exotic palms Roystonea regia and Archontophoenix alexandrae. The species planted along the roadside also include exotic Crateva trifoliata, Melaleuca quinquenervia and Livistona chinensis. The trees in this LR range in height from 2 – 10 m with some Roystonea regia palms reaching up to 5 m spread. These are all exotic, planted trees and are located in a number of discrete areas rather than one large area, such that they add medium landscape value. Overall the LR sensitivity is medium.

LR1.3c – Roadside Planting between Lai Cheung Road and Ngo Cheung Road

This LR refers to the viewing garden and roadside planters between Lai Cheung Road and Ngo Cheung Road. The viewing garden has signage of Yau Tsim Mong District Council in the middle, which is surrounded by colourful seasonal flowers, including Lantana montevidensis and Ixora chinensis. Approximately 20 Bauhinia variegata trees, exotic species to Hong Kong, are planted at the back of the viewing garden and additional trees planted along the roadside include a small number of Michelia x alba and Terminalia mantaly ‘Tricolor’.  There are an approximately 25 trees in this LR are between 3 – 5 m tall, mainly exotic and located in a number of discrete areas, so they add medium landscape value. With the other soft landscaping, the overall LR sensitivity is medium.

LR1.3d – Roadside Planting along Canton Road and Public Square Street)

There only about ten trees within the works area along Canton Road. The tree species are all exotic and are comprised of Grevillea robusta and Terminalia catappa growing between 4 – 9 m tall and with crown spread between 3 – 8 m. These trees add medium landscape value and overall this LR has medium sensitivity.

LR1.5a – Disturbed Area at Hau Cheung Street

This LR refers to the vacant land located at Hau Cheung Street. Most of the land is currently occupied by HyD for car parking and storage. The remaining area contains approximately 50 trees dotted around the land with some (approximately 5 %) wild grasses and weeds. The trees scattered on this vacant land are predominantly the weedy species Leucaena leucocephala but also include a couple of other exotic trees such as Acacia confusa, Bauhinia blakeana and Casuarina equisetifolia. These trees add low landscape value and overall this LR sensitivity is low.

LR1.5b – Disturbed Area next to Construction Site at Yau Cheung Road

There are approximately 60 trees in this disturbed area, mainly at the periphery where it borders Hoi Wang Road or Yau Cheung Road. Trees are generally fairly immature and are dominated by the exotic species Acacia confusa, and the weed species Leucaena leucocephala. Around the trees, the area is approximately 90 % covered with wild grasses and weeds. The condition of the trees is poor and they add low landscape value. Overall the LR sensitivity is low.

LR1.5c – Disturbed Area at Kwai Chung

This LR is currently being used by XRL project as a barging point at Kwai Chung underneath Cheung Tsing Bridge. The area is predominantly hard paved and disturbed and is surrounded by an MTR security fence but with some patches of weedy vegetation including approximately 10 trees.  These trees are of low value and include the weed tree species Leucaena leucocephala, Casuarina equisetifolia and Macaranga tanarius. This area is undergoing development and is therefore changing in appearance.  Overall its sensitivity is considered low.

LR1.8a – Man-made Shoreline around Kwai Chung

This LR refers to the man-made shoreline around Kwai Chung, particularly the barging point being used by XRL Project currently. It includes long stretches of concrete seawall as well as rubble breakwaters. It has no landscape treatment and its sensitivity is considered to be low.

10.7.2             Central Portion

LR2.3a – Roadside Planting around Housing Authority Mock-up Centre

Approximately 30 trees are planted around the Housing Authority Mock-up Centre including along the roadside. The species planted include Ficus microcarpa, Melaleuca quinquenervia and Elaeocarpus hainanensis and they range in height from 5 – 6 m with crown spread between 3 – 4 m. These trees are not of high value but do add some greening to the site and overall the LR sensitivity is medium.

LR2.4a – Vegetation on Man-made Slopes along Chung Hau Street and Fat

Approximately 155 trees are located on the man-made slopes along Chung Hau Street and Fat Kwong Street which have been planted there. The dominant species is the woody invasive species Leucaena leucocephala. There are other exotic species such as Albizia lebbeck and Casuarina equisetifolia as well as some native woodland species such as Celtis sinensis, Ficus spp., Macaranga tanarius and Schefflera heptaphylla. The condition of these trees is generally poor due to the crowded growing environment.

There are four mature Ficus spp. growing along the edge of works area. Since these tree have wide and dense crowns with outstanding forms, their landscape value is relatively higher than other trees. Although this LR is artificially made, it does provide a significant greening aspect in the urban area and the LR sensitivity is considered to be high.

10.7.2.1            East Portion

LR3.3a – Roadside Planting along San Ma Tau Street and Bus Terminus

This LR refers to the roadside trees planted along San Ma Tau Street and the Bus terminus. Approximately 30 trees are located at the boundary of the works area, most of them are common, exotic, ornamental species including Phoenix roebelenii, Melaleuca quinquenervia, Bombax ceiba, Albizia lebbeck and Washingtonia robusta; and native species including Bischofia javanica and Ficus virens. They range in height from 2 – 8 m and most of them are mature and generally in fair condition. These trees have medium landscape value and overall the LR sensitivity is medium.

LR3.3b – Roadside Planting along Long Yuet Street

There are approximately 50 trees in this LR along Long Yuet Street and behind the Motor Vehicle Inspection Centre, adjacent to vacant land.  The species include exotic Melaleuca quinquenervia species as well as some native species such as Bischofia javanica and Ficus religiosa. Although one tree is deemed to be of high value, the general condition of the other trees is poor due to the limited growing space and many of them have exposed roots, which crack the concrete paving and their trunks are damaged by the chain-link fence. These tree reach heights of between 3 -10 m and have crown spread between 2 – 8 m.  They add medium landscape value and overall the LR sensitivity is medium.

LR3.3c – Roadside Planting along Kai Cheung Road and Interchange

Approximately 415 trees are located on both sides of Kai Cheung Road within the works area. Almost all of them are planted, exotic species including Albizia lebbeck, Casuarina equisetifolia and Melaleuca quinquenervia; and the weedy, invasive species Leucaena leucocephala. They are generally medium in size and have fair form.

Some young exotic ornamental trees are planted at the junction of Kai Cheung Road and Kai Fuk Road with some Ixora chinensis shrubs planted underneath. Tree species include Bauhinia spp., Delonix regia and Aleurites moluccana in fair condition and these add medium landscape value.  Trees in this LR range in height from 2 – 22 m and have crown spreads between 1 – 12 m and given the man-made nature of the LR and the low maturity, despite high numbers of trees, this LR has medium sensitivity.

LR3.3d – Roadside Planting along Kai Fuk Road

There are approximately 85 trees in this LR (although the majority fall outside the works area).  The trees are made up of a wide range of species including exotic Melaleuca quinquenervia, Phoenix roebelenii and Caryota maxima as well as some native species such as Celtis sinensis and Ficus virens. They range in height from 2 -13 m and with crown spread from 1 – 10 m.  They are generally in fair form and add medium landscape value and overall this LR has medium sensitivity.

LR3.3e – Roadside Planting along Kai Cheung Road, Wan Kwong Road and Wan Chiu Road

There are approximately 50 trees planted along the roadside along Kai Cheung Road, Wan Kwong Road and Wan Chiu road. The species include mainly exotic species such as Albizia lebbeck, Casuarina equisetifolia and Melaleuca quinquenervia. These tree reach heights of between 5 -10 m and have crown spread between 3 – 8 m.  They add medium landscape value to the roadside and overall the LR sensitivity is medium.

LR3.5a – Disturbed Area within former Kai Tak Airport

This area is mainly covered by weedy shrubs and herbs such as Lantana camara, Bidens pilosa and some Poaceae spp. which cover approximately 30 % of the area in amongst the old hard surfaces.  Under ten trees are reportedly found in this LR including native species Ficus microcarpa and exotic species Melia azedarach and Terminalia catappa. Most of them are undersized and although they are generally in fair form they add little landscape value, not least due to their low number. Overall this LR has low sensitivity.

LR3.8a – Man-made Shoreline of West Kowloon Bay

This LR refers to the man-made shoreline along Ma Tau Kok Public Pier. It is a rectilinear concrete paved area with limited pot planters around Ma Tau Kok Pier and otherwise no landscape treatment. However, it is an important open area in the surrounding built-up area and may be developed further as a waterfront promenade (Open Space) under OZP No. S/K22/4 (Approved Kai Tak OZP). Overall sensitivity of the LR is considered to be medium.

LR3.8b – Man-made Shoreline around Former Kai Tak Airport

This LR refers to the man-made shoreline around the former Kai Tak Airport apron. It includes the long strips of armour stone breakwaters but has no landscape treatment and its sensitivity is considered to be low.

LR3.9a – Kowloon Bay

This LR refers to inshore part of Kowloon Bay, which is enclosed and tranquil. It consists primarily of water and other features in this LR include jetty, and breakwaters resulting in a landscape that is the transition between land and the more open sea. As this is the only water body in the surrounding built-up area, the LR sensitivity is considered to be medium.

LR3.9b – Kai Tak Nullah

Kai Tak Nullah is the major storm water channel in South-East Kowloon, collecting storm water and effluent from San Po Kong, Diamond Hill, Tsz Wan Shan, Wong Tai Sin, Wang Tau Hom, Lok Fu and Kowloon City. Both sides of the nullah are currently covered by concrete and hard paving and it collects turbid effluent.  Although the current landscape value would be low, under the KTD this nullah is due to be landscaped and enhanced, so its LR sensitivity will become medium.

 

Table 10.2:  List of the Landscape Resources and their Sensitivity

 

LR Code

Name

LR Sensitivity (High/ Medium/ Low)

 

West Portion

 

LR1.1a

Public Square Street Playground

Medium

LR1.1b

Shanghai Street / Market Street Playground

Medium

LR1.1c

Bazaar

High

LR1.1d

Temple Street / Kansu Street Temporary Rest Garden

Low

LR1.1d

Yau Ma Tei Jade Market/ Jade Hawkers Bazaar

High

LR1.3a

Roadside Planting along West Kowloon Highway and Tunnel Area

High

LR1.3b

Roadside Planting along Hoi Wang Road, Yan Cheung Road and Ferry Street Area

Medium

LR1.3c

Roadside Planting between Lai Cheung Road and Ngo Cheung Road

Medium

LR1.3d

Roadside Planting along Canton Road and Public Square Street

Medium

LR1.5a

Disturbed Area at Hau Cheung Street

Low

LR1.5b

Disturbed Area next to Construction Site at Yau Cheung Road

Low

LR1.5c

Disturbed Area at Kwai Chung

Low

LR1.8a

Man-made shoreline around Kwai Chung

Low

 

Central Portion

 

LR2.3a

Roadside Planting around Housing Authority Mock-up Centre

Medium

LR2.4a

Vegetation on Man-made Slopes along Chung Hau Street and Fat Kwong Street

High

 

East Portion

 

LR3.3a

Roadside Planting along San Ma Tau Street and Bus Terminus

Medium

LR3.3b

Roadside Planting along Long Yuet Street

Medium

LR3.3c

Roadside Planting along Kai Cheung Road and Interchange

Medium

LR3.3d

Roadside Planting along Kai Fuk Road

Medium

LR3.3e

Roadside Planting along Kai Cheung road, Wang Kwong Road and Wan Chiu Road

Medium

LR3.5a

Disturbed Area within former Kai Tak Airport

Low

LR3.8a

Man-made Shoreline of West Kowloon Bay

Medium

LR3.8b

Man-made Shoreline around former Kai Tak Airport

Low

LR3.9a

Kowloon Bay

Medium

LR3.9b

Kai Tak Nullah

Medium

10.7.3             Landscape Character Areas

The urban landscapes of Kowloon Peninsula are of widely differing character and quality from west to east.

The West Kowloon and Yau Ma Tei Districts comprise a large part of reclaimed land, which have been further developed into a transportation corridor and high-rise buildings.

The Kowloon City District in central Kowloon is a combination of original industrial urban context along the east coast of Hung Hom and To Kwa Wan, and the hillside residential area in Ho Man Tin.

The former Kai Tak Airport area has been decommissioned and returned to ongoing major development landscape. An industrial urban area is located in the eastern end of the LIA study area in Kowloon Bay District.

The baseline LCAs within the LIA study area, together with their sensitivity, are described below. A total of eight different LCAs are identified within the whole Study Area, as bulleted below, although no more than five different LCAs are found in any one section of the Project. 

·         City Grid Mixed Urban Landscape

·         Industrial Urban Landscape

·         Miscellaneous Urban Fringe Landscape

·         Ongoing Major Development Landscape

·         Residential Complex Landscape

·         Residential Urban Landscape

·         Transportation Corridor Landscape

·         Typhoon Shelter Landscape

The baseline LCAs together with their sensitivity, are described below, as summarised in Table 10.3 following. All LCAs in the West Portion are labelled LCA 1.x, all LCAs around the Central Portion are labelled LCA 2.x and all LCAs in the East Portion are labelled LCA 3.x, where ‘x’ refers to the specific LCA.

10.7.4             West Portion

LCA 1.1 – Transportation Corridor Landscape (West Portion)

This LCA refers to the West Kowloon Highway in the West Portion of CKR and the major section of Ferry Street. It is a linear landscape generally situated on coastal reclamations, and its major features are the highways and railways that define it, but which also include flyovers, noise barriers, signage gantries, clover-leaf interchanges, traffic islands, major car parking areas, footbridges and toll plazas as well as associated miscellaneous roadside land uses. Between the roads and railways are some landscaped embankments and islands, generally with semi-mature amenity vegetation consisting of trees and shrubs. There are an estimated 1390 trees in this LCA with the dominant species all being exotic, mainly Acacia spp., Eucalyptus spp., Casuarina equisetifolia. There are other species recorded in far fewer numbers including some native species such as Sapium sebiferum but also some of the invasive weed species, Leucaena leucocephala. Trees range in size between 2 and 15 m high and up to 12 m crown spread and are moderately mature on average.  The outcome is a particularly linear landscape of rather diverse features. Due to the large degree of landscaping around the Lin Cheung Road West Kowloon interchange, with high numbers of trees adding high greening to the landscape, the sensitivity of this LCA is medium.

LCA 1.2 – Ongoing Major Development Landscape (West Portion & Barging Point)

This LCA refers to the construction site of Express Rail Link and its associated structures (the XRL project). This is a transitional landscape, which is undergoing large-scale development. Some areas consist of land undergoing development whilst others are vacated sites, which are awaiting re-development. They are typically characterised by a flat, low-lying topography, lack of significant vegetation or significant built structures and may include major earthworks, partially completed structures, as well as features such as cranes and earth moving machinery. This LCA is mainly on land reclaimed from the sea and is close to the coast. There are an estimated 570 trees in this LCA nearest the main works area with the dominant species being the the invasive weed species, Leucaena leucocephala and exotic Acacia spp., Casuarina equisetifolia, Archontophoenix alexandrae, Bauhinia blakeana, and Bombax ceiba are example of other species commonly recorded her but in far fewer numbers.

In addition, this LCA contains the land at Kwai Chung currently being used by the XRL Project as a barging point. As well as the barging point, the landscape nearby is developed, with man-made shoreline where many barges can alight as well as the DSD Kwai Chung PreliminaryTreatment Works building and a site undergoing development currently near the elevated.  It has very limited greenery but does include approximately 20 trees in the area, predominantly weed tree species Leucaena leucocephala,  as well as Ficus spp., Casuarina equisetifolia and Macaranga tanarius. This area is undergoing development and is therefore changing in appearance. 

As a result of its indeterminate status or the disturbance caused by ongoing construction work, this landscape currently has an incoherent, desolate and transient character and would have low sensitivity. Due to part of this LCA being made up of the XRL site where landscaping will be carried out, the overall sensitivity of the LCA is conservatively considered to be medium.

LCA 1.3 – City Grid Mixed Urban Landscape (West Portion)

This LCA is found on the older reclamations of Yau Ma Tei. It is some of Hong Kong’s most common and extensive urban landscape. Developed on a largely orthogonal or regular city grid, it consists of mainly retail land uses at street level with medium-rise commercial or residential developments above. Streets are often fairly wide and busy with traffic and the large numbers of people using these areas but the streetscape is utilitarian with little soft landscape treatments. Building stock is of mixed age and character, and vegetation is generally limited to street tree planting and shrub planting in occasional public open spaces. The result is a landscape which is vibrant, colourful and diverse in terms of its street life and land use, but which possesses only limited variety in terms of its urban spaces.

Part of Temple Street is located within this LCA. It is well known for its night market and the busiest flea market at night in the territory. The night market is popular with both tourists and locals alike in the evening and it is common to see the place crowded at dusk. The covered Yau Ma Tei Jade market, another popular tourist attraction, is also located in this LCA and it also includes the market between Waterloo Road and Ferry Street.

In total there are an estimated 60 trees in this LCA, mainly Alstonia scholaris and including others such as Aleurites molluccana, Bauhinia blakeana, Casis surattensis up to 20 m high and with varying maturity.  The landscape amenity, significance and quality of this LCA are moderate with reasonable tolerance to change and therefore, the sensitivity is medium.

LCA 1.4 – Residential Complex Landscape

This LCA is found on the periphery of the major urban area of Yau Ma Tei. It is generally on reclaimed areas of West Kowloon comprising some of Hong Kong’s most recent urban landscapes which consist of extensive comprehensive developments, typically with a large podium containing retail uses, parking or a PTI, with commercial or residential towers above. This LCA is also characterised by its new building stock (often using modern building materials such as glass and steel). Streets in these landscapes are often wide with significant roadside landscape provision and tree planting, with footbridges connecting developments at first floor or podium level. The result is an intensely urban landscape which is often enclosed, angular and colourful and defined to a significant extent by its built form and the spaces they create. LCA 1.4 contains Park Avenue complex, part of Cherry Street Park that surrounds other complexes such as Charming Garden. The sensitivity of this LCA is medium.

LCA 1.5 – Residential Urban Landscape (West Portion)

This LCA refers to an urban landscape largely residential in use with some government/ institutional buildings also, all developed on flat land. LCA1.5 includes the high rise Prosperous Garden residential complex and medium rise Man Cheong Street Residential buildings, as well the community facilities of Yau Ma Tei Police Station and Yau Ma Tei Electric Substation and a number of schools. This LCA takes in the open space of Saigon Street Playground and Skating area and also includes associated roads, footbridges, and retail facilities. Vegetation includes planting in open spaces and within the Prosperous Garden residential complex, with minimal roadside trees and shrub planting (estimated 60 trees in total, including species such as Melaleuca quinquenervia, Albizia lebbeck, and Casuarina equisetifolia). LCA1.5 is a fairly ordered landscape comprising largely built elements softened to a certain extent by the effects of surrounding planting and greenery and overall its sensitivity is medium.

LCA 1.6 – Typhoon Shelter Landscape (West Portion & Barging Point)

This LCA refers to the Ya Ma Tei Typhoon shelter at the periphery of the main West Portion study area and the sea water surrounding the proposed Kwai Chung barging point, in the West Portion. These bodies of water are used by many barges and low quality.  Overall the sensitivity of this LCA is low.

10.7.5             Central Portion

LCA 2.1 – Residential Urban Landscape (Middle)

This LCA refers to the area around Ho Man Tin Estate. It is an urban landscape which is wholly or largely given over to residential land use. Developed comprehensively on flat or terraced land, mainly on the edges of urban areas, residential urban landscape is generally characterized by its medium or high-rise residential estates, set amongst open space, together with associated highways, footbridges, school or community facilities and retail facilities. Vegetation includes roadside trees and shrub planting and planting in open spaces and around the residential estates. The result is a fairly homogeneous, ordered landscape comprising largely built elements softened to a certain extent by the effects of surrounding planting and greenery. LCA 2.1 includes Ho Man Tin (South) Estate, Fat Kwong Street Sports Centre and overall its sensitivity is medium.

LCA 2.2 – Miscellaneous Urban Fringe Landscape

This LCA is found on the periphery of Ho Man Tin around Ho Man Tin West Fresh Water Service Reservoir and Ho Man Tin Park and also includes part of Ho Man Tin Service Reservoir Playground south of Sheung Lok Street and east of Fat Kwong Street. Miscellaneous Urban Fringe Landscape generally has a residual landscape type characteristic of the transition from urban to rural. Typically on hillsides around urban areas that are less easily developed, they might include roads, highways structures, slope works, hillsides, scattered residential development, open space and, as per LCA 2.2, government/community developments such as service reservoirs. This LCA has significant vegetation cover and no particular coherent structure, with features having little formal relationship to each other. In total there are an estimated 150 trees in this LCA, dominated by such species as the invasive weed species, Leucaena leucocephala as well as having other species in lesser numbers such as Macaranga tanarius, Celtis sinesnsis, Ficus spp. and Albizia lebbeck. The trees range in height between 5-10 m on average and are moderately mature on average.  Overall, the sensitivity of this LCA is medium.

10.7.6             East Portion

LCA 3.1 – City Grid Mixed Urban Landscape (East Portion)

This LCA refers to the area around Ma Tau Kok, which is the most common and extensive urban landscape in this district. Developed on a largely orthogonal or regular city grid, the LCA consists of mainly retail land uses at street level with high/medium-rise commercial or residential developments above. Streets are often fairly wide and busy with traffic and the large numbers of people using these areas but the streetscape is utilitarian with little soft landscape treatments. Building stock is of mixed age and character, and vegetation is generally limited to street tree planting and shrub planting in occasional public open spaces. The result is a landscape which is vibrant, colourful and diverse in terms of its street life and land use, but which possesses only limited variety in terms of its urban spaces. LCA 3.1 includes Wyler Gardens and Grand Waterfront residential blocks as well as part of the China Gas company complex. The sensitivity of this LCA is medium.

LCA 3.2 – Ongoing Major Development Landscape (East Portion)

This LCA refer to the former Kai Tak airport area, which is the site for the proposed KTD. These are transitional landscapes currently awaiting large-scale construction. Most of the areas are vacated sites, which are awaiting construction, whilst some of them are undergoing decommissioning. They are typically characterised by a flat, low-lying topography, lack of significant vegetation or significant built structures and may include major earthworks, partially completed structures, as well as features such as cranes and earth moving machinery. This LCA is reclaimed from the sea and largely coastal.  In total there are an estimated 280 trees in this LCA, dominated by such species as the invasive weed species, Leucaena leucocephala and Albizia lebbeck and including other species in lesser numbers such as Aleurites moluccana, Bauhinia spp., Delonix regia, Ficus spp. etc, ranging in height between 4-12 m on average and being moderately mature on average.  The KTD site will be developed into a number of different areas, such as the Ma Tau Kok Waterfront, a Sports Hub, Metro Park, Kai Tak City Centre and South Apron corner, which fall within the Study Area.  Although currently this LCA has low sensitivity due to its overall disturbed and indeterminate status, due to the KTD including the landscaping of the various areas mentioned, the sensitivity of this LCA is considered to be medium for the CKR Project.

 

LCA 3.3 – Industrial Urban Landscape

This LCA is found on the fringe of Kowloon Bay which is low-lying reclaimed land, housing urban areas along the coast. This landscape is defined by its almost exclusively industrial land use. It typically includes areas of industrial buildings, often in very dense arrangements with occasional open areas used for vehicle parking or open storage, comprehensively developed low-rise buildings and some vacant land. Streets are mainly residual spaces, with little or no vegetation and no significant tree numbers are recorded. The unifying characteristics of this LCA type are their large utilitarian buildings, limited coherence of spaces, features and materials, and absence of significant vegetation cover. LCA 3.3 is on the periphery of a larger industrial urban landscape area extending beyond the Study Area, but does include the HK International Trade and Exhibition Centre. The sensitivity of this LCA is low.

LCA 3.4 – Typhoon Shelter Landscape (East Portion)

This LCA is found on the coastal edges of Ma Tau Kok and Kowloon Bay. This LCA type is generally inshore, aquatic landscape formed by the armour stone breakwaters constructed to protect large numbers of moored vessels. Vessels include freighters, fishing vessels, pleasure craft and sampans. Although this LCA consist primarily of water, other features include jetties, pontoons and navigational features resulting in a landscape that is a transitional one between land and sea resulting in an active landscape characterized by a variety of form and colour.  LCA3.4 has a sense of enclosure also and overall the sensitivity of this LCA is medium.

LCA 3.5 - Transportation Corridor Landscape (East Portion)

This area comprises the Kwun Tong Bypass (elevated bypass expressway), Kai Fuk Road, and Kai Cheung Road. Few amenity plantings of low to medium amenity value are found in the central median or at the sides of the corridors although there are an estimated 290 trees in this LCA, dominated by such species as Casuarina equisetifolia and Melaleuca quinquenervia. Trees range in height between 2-22 m and have wide ranging maturity.This LCA is slightly sensitive to highway development and given the number of trees within it, the sensitivity of this area is considered as medium.

 

Table 10.3:  List of the Landscape Character Area and their Sensitivity

 

LCA Code

Name

LCA Sensitivity (High/ Medium/ Low)

 

West Portion

 

LCA1.1

Transportation Corridor Landscape (West Portion)

Medium

LCA1.2

Ongoing Major Development Landscape (West Portion & Barging Point)

Medium

LCA1.3

City Grid Mixed Urban Landscape (West Portion)

Medium

LCA1.4

Residential Complex Landscape

Medium

LCA1.5

Residential Urban Landscape (West Portion)

Medium

LCA1.6

Typhoon Shelter Landscape (West Portion & Barging Point)

Low

 

Central Portion

 

LCA2.1

Residential Urban Landscape (Middle)

Medium

LCA2.2

Miscellaneous Urban Fringe Landscape

Medium

 

East Portion

 

LCA3.1

City Grid Mixed Urban Landscape (East Portion)

Medium

LCA3.2

Ongoing Major Development Landscape (East Portion)

Medium

LCA3.3

Industrial Urban Landscape

Low

LCA3.4

Typhoon Shelter Landscape (East Portion)

Medium

LCA3.5

Transportation Corridor Landscape (East Portion)

Medium

 

10.8                   Visual Baseline Study

The works area of Central Kowloon Route is located in densely populated urban areas with high-rise buildings. Most of the areas are enclosed by high-rise buildings; the Zone of Visual Influence (ZVI) is therefore mainly limited by the first row of buildings. Oblique aerial photographs presented in Figure 10.3.1, Figure 10.3.2 and Figure 10.3.3 show the approximate works area and can help understand the formation of Zone of Visual Influence.

The Zone of Visual Influence (ZVI) is shown in Figure 10.13 (West Portion), Figure 10.14 (Central Portion) and Figure 10.15 (East Portion) and key Visual Sensitive Receivers (VSRs) within the ZVIs are mapped in Figure 10.13.1 (West Portion), Figure 10.14.1 (Central Portion) and Figure 10.15.1 and Figure 10.15.2 (East Portion).

VSRs identified within each of the ZVI around the West Portion, Central Portion and East Portion are detailed below and illustrative photographs of VSRs are presented in Figure 10.16.1, Figure 10.16.2, Figure 10.16.3, Figure 10.16.4, Figure 10.16.5, Figure 10.16.6, Figure 10.17.1, Figure 10.17.2, Figure 10.17.3, Figure 10.18.1, Figure 10.18.2, Figure 10.18.3, Figure 10.18.4, Figure 10.18.5, Figure 10.18.6 and Figure 10.18.7. 

Thirteen Vantage/ View Points (VPs) are selected from which to create photomontages.  These have been selected to represent various views towards the Project from different angles, illustrate key Project features, such as the Landscape Deck in the West Portion and endeavour to represent key VSR views in each location.  VPs are chosen to try and represent the impact on a number of VSRs, where impacts are considered to be similar.  Overall the combination of photomontages for the Project aim to support the assessment of visual impact in the text and provide an idea of the Project outlook.

Five VPs have been selected in the West Portion.  These are:

·         VP1 – Sorrento;

·         VP2 – CAS HQ;

·         VP3 – Man Cheong Buildings;

·         VP4 –Yaumati Catholic Primary School, Tung Kun Street;

·         VP5 – Yau Ma Ti Catholic Primary School, Hoi Wang Road;

Three VPs have been selected in the Middle Ventilation Area.  These are:

·         VP6 – Sheng Kung Hui Tsoi Kung Po Secondary School;

·         VP7 – Sik Man House, Ho Man Tin Estate;

·         VP13 – Oi Man Estate

Five VPs have been selected in the East Portion including one futuristic one within KTD and one aerial one which does not represent any VSRs but gives a good indication of the outlook of the Project in the East Portion. These VPs are:

·         VP8 – Grand Waterfront;

·         VP9 – Megabox;

·         VP10 - Aerial photograph above Kai Tak Runway;

·         VP11 – HK International Trade & Exhibition Centre; and

·         VP12 – Within KTD. 

A key map of all the VPs used to develop photomontages is shown in Figure 10.19 although Figure 10.13, Figure 10.14 and Figure 10.15 also show closer detail of the VP locations in the West, Central Portion and East areas respectively.  The photomontages from these VPs are discussed in the Visual Impact Assessment in Section 10.11. 

10.8.1             West Portion

The West Portion of the VIA study area is in the Yau Ma Tei and Mong Kok Districts with many different uses but overall highly developed.  To the south and west the sea of Victoria Harbour is a key feature and otherwise the visual character is mixed with key transport routes, ongoing development (e.g. XRL and associated structures), modern residential buildings with iconic tall structures (e.g. ICC) and older buildings, some with cultural significance. 

The West Portion of CKR with its associated structures is constructed on flat and low-lying reclaimed land with similar level (average +5mPD) to the whole West Kowloon and Yau Ma Tei District. As the whole area is enclosed by high-rise buildings, the ZVI will be stopped by the first or second row of buildings. Higher levels of tall buildings within this district will not be blocked by buildings in the front and will have a view to the site. However, due to the ongoing major development in nearby locations, such as the Express Rail Link, the quality of existing views has already been degraded. The baseline condition of VSRs within the West Portion ZVI, together with their sensitivity is described below and a summary provided in Table 10.4 following.

Residential VSRs

R1.1

One SilverSea

R1.2

Island Harbourview

R1.13

The Victoria Towers

R1.14

The Hermitage

Residents in high-rise residential building blocks at the edge of ZVI and distant (over 400 m from new connecting road alignment and/or 500 m from proposed ventilation building) from the Project include the VSRs listed above. Since they are the highest buildings in this district, viewers in mid to upper levels will have panoramic views facing due south to Victoria Harbour or due north to north Kowloon and New Territories. Views from lower levels will be partially blocked by existing lower buildings in front or the existing roads and viaducts. The value and quality of the best existing views are good, although they are currently deteriorated by some abandoned land and the extensive ongoing development works of e.g. Express Rail Link. Given these VSRs are distant to the Project, their sensitivities are considered to be medium.

R1.3

Park Avenue

R1.4

Charming Garden

R1.6

8 Waterloo Road

R1.10

Sorrento

R1.11

The Coronation

R1.12

Planned Residential Development above Austin Station

Residents (and future residents in the case of R1.11 and R1.12) in high-rise residential building blocks closer to the Project (less than 400 m from new connecting road alignment and/or less than 500 m from proposed ventilation building) have similar quality of existing views and degrees of visibility at different levels to those high-rise residential building blocks at the edge of ZVI, but being closer, the Project would be more prominent in their view and their sensitivities are considered high, despite some (such as R1.12) having their views to site slightly restricted by other buildings such as Man Cheong Buildings (R1.9).

R1.7

Prosperous Garden

R1.9

Man Cheong Buildings

Other residents in the mid to high rise residential blocks in the inner part of ZVI such as those listed above have a direct and close view to the West Kowloon Highway. For R1.7 particularly, the views from low and mid levels are dominated by the existing elevated road and screening planting along the West Kowloon Highway. The value and quality of the existing view is fair to good but deteriorated by the abandoned land and extensive ongoing development works e.g. Express Rail Link. The sensitivity of these VSRs is high.

R1.5

Wah Tak Building & Tak Cheong Lane High Rise

R1.8

Kansu Street High Rise Buildings

The residents in the older reclamations of Yau Ma Tei like Wah Tak Building and the adjacent building block (R1.5), and the dense residential buildings along Kansu Street (R1.8) have restricted views. Their views are dominated by the existing elevated road and other buildings. Residents living along Kansu Street will have the partial views to the Shanghai Street/ Market Street Playground and Yau Ma Tei Community Centre Rest Garden. The value and quality of the existing view is fair to poor. The sensitivity of these VSRs is medium.

Commercial VSRs

C1.1

Bank of China Tower

C1.2

HSBC Centre

C1.4

ICC & Ritz Carlton Hotel

C1.5

Planned Commercial Development above XRL Terminus

Viewers (and planned users in the case of C1.5) in the above listed VSRs have an open and distant (over 400 m from new connecting road alignment and/or 500 m from proposed ventilation building) views toward the Project. The value and quality of their existing view is good, however they are deteriorated by abandoned land and the ongoing development of the Express Rail Link. Considering the nature of the user group and the distance from the Project Site, the sensitivity of these VSRs is rated as low.

C1.3

Eaton Hotel

C1.6

Keybond Commercial Building

Viewers in Eaton Hotel (C1.3) have a close view to the existing Gascoigne Road Flyover with some buildings and green woodland as a backdrop. Gascoigne Road Flyover is a busy traffic corridor and traffic congestion can be seen from day to day. Viewers in Keybond Commercial Building (C1.6) have a narrow view through to the Project alignment restricted by other buildings including the new Coronation development. The value and quality of the existing views for these VSRs is fair and despite the nature of the user group, given their proximity to the Project their sensitivity is medium.

Government/ Institution/ Community VSRs

GIC1.1

Yau Ma Ti Catholic Primary School (Hoi Wang Road) & Li Kwok Po College

GIC1.2

Hong Kong Community College West Kowloon Campus

GIC1.3

Yaumati Catholic Primary School (Tung Kun Street)

GIC1.4

Yau Ma Tei Division Police Station

GIC1.5

Yau Ma Tei Jockey Club Polyclinic

GIC1.6

Henry G. Leong Yaumatei Community Centre

GIC1.7

Queen Elizabeth Hospital

GIC1.8

Civil Aid Services Headquarter

GIC1.9

Planned GIC Site

Viewers in the VSRs listed above are all reasonably close to (within 120m ), if not under the proposed alignment or works area. These buildings are low to medium rise and at the higher levels may have partial open views towards the Project. At lower levels, many of the views are dominated by existing elevated roads such as that of West Kowloon Highway, Ferry Street or Gascoigne Road. The Existing views are poor to fair depending but are partly deteriorated the ongoing development works in the area e.g. of the Express Rail Link. This VSR type is not highly sensitive but given their proximity to the site, their sensitivity is medium.

GIC1.7

Queen Elizabeth Hospital

Some users in Queen Elizabeth Hospital (GIC1.7) higher levels and in Blocks facing west have an open view to the urban landscape at West Kowloon due to the existing topography. The view is dominated by the dense mid rise building, pencil towers and busy traffic corridor with very little green planting. The sensitivity of this VSR is low.

Occupational VSRs

O1.1

LPG Filling Station at Hau Cheung Street

Users in LPG Filling Station at Hau Cheung Street (O1.1) have a close and direct view to the West Kowloon Highway and the extensive screening planting. The value and quality of the existing view is fair. The sensitivity of this VSR is low due to the occupational and temporary nature of the VSR.

Recreational VSRs

RE1.1

Olympic Plaza

RE1.2

Cherry Street Park

RE1.5

Saigon Street Playground

Users in these VSRs generally have high quality views within their recreational area but these green spaces that they occupy are mainly enclosed or screen by mature planting, such that their views of the Project would be restricted. Users of Saigon Street Playground (RE1.5) are less screened within their playground but surrounded by fairly low quality views. The sensitivity of these VSRs is rated as low.

RE1.3

Public Square Street Rest Garden

RE1.4

Yau Ma Tei Community Centre Rest Garden

RE1.6

Planned Public Open space above future XRL-terminus and surrounding

RE1.7

Planned Public Open space north of Yan Cheung Road

These existing VSRS, namely viewers in Public Square Street Rest Garden (RE1.3) and Yau Ma Tei Community Centre Rest Garden (RE1.4) are enclosed by dense buildings and elevated roads but mature planting within these open spaces screen off and soften parts of these restricted views. These VSRs will be are located very close to the Project alignment or will be re-located due to the Project.  The sensitivity of these VSRs is medium.

Travel/ Transport Related VSRs

T1.1

West Kowloon Highway

West Kowloon Highway (T1.1) is a section of Route 3 in Hong Kong. This dual-3 lane highway runs for 4.2 km, connecting Western Harbour Crossing in the south with Tsing Kwai Highway in the north. This VSR refers to travellers on the section from MTRC Kowloon Station to Olympic Station. One side has a nice open view to Victoria Harbour while the other side has a dense urban view of West Kowloon. Due to high travelling speed on West Kowloon Highway, travellers are insensitive to the views. The sensitivity of this VSR is low.

 


Table 10.4:  List of the VSRs in the West Portion and their Sensitivity

 

* Denotes future VSRs that will not be in existence when construction for the Project starts. 

 

VSR Code

Type of VSRs

VSR Name

Number of Individuals (Very few, Few, Many, Very many)

Quality of Existing View (Poor/ Fair/ Good)

Availability of Alternative Views

Approx. Minimum Distance between VSRs and Impact Sources (Road/Ventilation Building) (m)

Degree of Visibility towards Project (Glimpse/ Partial/ Full)

Duration of View (Short/ Medium/ Long)

Frequency of View (Rare/ Occasional/ Frequent)

Sensitivity (Low, Medium, High)

West Portion

R1.1

Residential

One SilverSea

Very Many

Good

Yes

750/ 920

Full

Long

Frequent

Medium

R1.2

Residential

Island Harbourview

Very Many

Good

Yes

620/ 800

Full

Long

Frequent

Medium

R1.3

Residential

Park Avenue

Very Many

Good

Yes

130/ 400

Partial

Long

Frequent

High

R1.4

Residential

Charming Garden

Very Many

Fair

No

200/ 300

Full

Long

Frequent

High

R1.5

Residential

Wah Tak Building & Tak Cheong Lane High Rise

Few

Fair

No

250/ 540

Partial

Long

Frequent

Medium

R1.6

Residential

8 Waterloo Road

Many

Good

Yes

290/ 740

Partial

Long

Frequent

High

R1.7

Residential

Prosperous Garden

Very Many

Fair

No

240/ 560

Full

Long

Frequent

High

R1.8

Residential

Kansu Street High Rise Buildings

Many

Poor

No

0/ 720

Partial

Long

Frequent

Medium

R1.9

Residential

Man Cheong Buildings

Many

Fair

Yes

150/450

Full

Long

Frequent

High

R1.10

Residential

Sorrento

Very Many

Good

Yes

270/ 480

Full

Long

Frequent

High

R1.11

Residential

The Coronation

Very Many

Good

Yes

30/ 320

Full

Long

Frequent

High

R1.12

Residential

Planned Residential Development above Austin Station

Very Many

Good

Yes

360/ 680

Partial

Long

Frequent

High*

R1.13

Residential

Victoria Towers

Very Many

Good

Yes

700/ 1120

Full

Long

Frequent

Medium

R1.14

Residential

The Hermitage

Very Many

Good

Yes

500/ 680

Full

Long

Frequent

Medium

C1.1

Commercial

Bank of China Tower

Many

Good

Yes

600/ 770

Full

Medium

Occasional

Low

C1.2

Commercial

HSBC Centre

Many

Good

Yes

560/ 750

Full

Medium

Occasional

Low

C1.3

Commercial

Eaton Hotel

Many

Fair

Yes

170/ 1010

Partial

Medium

Occasional

Medium

C1.4

Commercial

ICC & Ritz Carlton Hotel

Very Many

Good

Yes

720/ 840

Full

Medium

Occasional

Low

C1.5

Commercial

Planned Commercial Development above XRL Terminus

Very Many

Fair

Yes

240/ 570

Partial

Medium

Occasional

Low*

C1.6

Commercial

Keybond Commercial Building

Few

Fair

No

160/ 650

Partial

Medium

Occasional

Medium

GIC1.1

Government/ Institution/ Community

Yau Ma Ti Catholic Primary School (Hoi Wang Road) & Li Kwok Po College

Many

Fair

Yes

100/ 200

Partial

Medium

Occasional

Medium

GIC1.2

Government/ Institution/ Community

Hong Kong Community College West Kowloon Campus

Many

Good

Yes

50/ 280

Partial

Medium

Occasional

Medium

GIC1.3

Government/ Institution/ Community

Yaumati Catholic Primary School (Tung Kun Street)

Many

Poor

No

120/ 540

Partial

Medium

Occasional

Medium

GIC1.4

Government/ Institution/ Community

Yau Ma Tei Division Police Station

Many

Poor

No

0/ 610

Partial

Short

Occasional

Medium

GIC1.5

Government/ Institution/ Community

Yau Ma Tei Jockey Club Polyclinic

Many

Poor

No

0/ 700

Partial

Short

Occasional

Medium

GIC1.6

Government/ Institution/ Community

Henry G. Leong Yaumatei Community Centre

Many

Poor

No

20/ 750

Partial

Medium

Occasional

Medium

GIC1.7

Government/ Institution/ Community

Queen Elizabeth Hospital

Many

Fair

Yes

240/1050

Open

Short

Occasional

Low

GIC1.8

Government/ Institution/ Community

Civil Aid Services Headquarter

Many

Fair

Yes

40/ 180

Full

Short

Occasional

Medium

GIC1.9

Government/ Institution/ Community

Planned GIC Site

Few

Poor

Yes

10/ 120

Full

Short

Occasional

Medium*

O1.1

Occupational

LPG Filling Station at Hau Cheung Street

Few

Fair

No

10/ 310

Full

Short

Occasional

Low

RE1.1

Recreational

Olympic Plaza

Few

Good

Yes

130/ 340

Glimpse

Short

Occasional

Low

RE1.2

Recreational

Cherry Street Park

Many

Fair

Yes

80/ 340

Glimpse

Short

Occasional

Low

RE1.3

Recreational

Public Square Street Rest Garden

Few

Fair

No

0/ 580

Full

Short

Occasional

Medium

RE1.4

Recreational

Yau Ma Tei Community Centre Rest Garden

Many

Fair

Yes

30/ 800

Partial

Short

Occasional

Medium

RE1.5

Recreational

Saigon Street Playground

Many

Fair

Yes

90/ 800

Partial

Short

Occasional

Low

RE1.6

Recreational

Planned Public Open Space above future XRL-terminus and surrounding

Many

Fair

Yes

0/ 120

Partial

Short

Occasional

Medium*

RE1.7

Recreational

Planned Public Open space north of Yan Cheung Road

Few

Fair

No

0/ 440

Partial

Short

Occasional

Medium*

T1.1

Travel/ Transport Related

West Kowloon Highway

Many

Good

Yes

0/0

Full

Short

Rare

Low


10.8.2             Central Portion

The Central Portion Area of the VIA study area around Ho Man Tin has two main characters. Proximal to Ventilation Building, two covered service reservoirs provide some greening to the area and a more rural feel.  Surrounding this, the landscape is mainly urban and largely given over to residential buildings but with some other uses such as the Ho Man Tin Government offices and local schools and as one moves towards the east coast around Hung Hom and To Kwa Wan, it becomes more original urban industrial.

The Central Portion Site is located on high ground on man-made slope (average +59mPD) currently occupied by Water Supplies Department. The area where the ventilation building is located is nearly the highest point in this region. In addition to the blockage of view by the service reservoir at western side (average +68mPD), the extent of ZVI is greatly reduced due to adjacent tall buildings. However higher levels of some tall buildings in this district such as 15 Ho Man Tin Hill, Ellery Terrace, Carmel On The Hill and King Man House can still have a direct view to the Project Site. The baseline conditions of VSRs within the Central Portion ZVI, together with their sensitivity, are described below and a summary provided in Table 10.5 following.

Residential VSRs

R2.1

15 Ho Man Tin Hill

R2.2

Ellery Terrace

R2.4

Ho Man Tin Estate (High Rise Building Block)

R2.5

Ho Man Tin Estate

R2.6

Carmel On The Hill

R2.7

Chung Man Court

R2.8

Future Redevelopment of Ex-Valley Road Estate

R2.9

HK Polytechnic University Student Hostel Development

The above listed VSRs, except R2.5, are high rise structures such that some residents have/will have an open view towards the proposed Project Site. R2.1, 2.2, 2.8 and 2.9 are quite distant from the Proposed Project Site (>300 m) whereas R2.4 (including Choi Man House, Yee Man House, Yat Man House, Sik Man House and Kwun Hei Court), R2.6 and 2.7 are all slightly closer. R2.5 is made up of the western buildings of Ho Man Tin Estate which are mid rise residential blocks located close to the proposed Project Site and residents on the upper levels have a direct and nearby view towards it. Due to the existing topography and the height of the buildings, mid and upper levels have a panoramic view of the whole Ho Man Tin District and even to Victoria Harbour and Hong Kong Island on clear days. These viewers have high quality views of an urban nature, including the landscaping in the area such as at Sheung Lok Street Garden (RE2.2) and Ho Man Tin East Service Reservoir (RE2.1) which provides some greening. Although it is likely that the future residential blocks in R2.8 will mainly face south, some viewers may face north towards the Project Site. The views from lower levels of the above listed VSRs may have no view to the Project Site with others having a view that is/will be partially interrupted by adjacent buildings such as Chun Man Court and Ho Man Tin Government Office (GIC2.1) for R2.1 and R2.2, other buildings of the Ho Man Tin Estate for R2.4 and the Future Redevelopment of Ex-Valley Estate for R2.9, and these views are/will be generally of lower quality being more focused to ground level and contained by structures and planting. Primarily considering the viewers in the mid and upper levels of these buildings, their good views to and/or their proximity to the proposed Project Site, the sensitivity of these VSRs is high.

R2.3

Ho Man Tin Estate King Man House

Some residents in Ho Man Tin Estate King Man House (R2.3) have a distant (> 400 m) view towards the proposed Project Site but this is only a glimpse view as it is largely blocked by the Housing Authority Headquarters (GIC2.3). Otherwise their existing views are panoramic over the Ho Man Tin District and even further to the Victoria Harbour and Hong Kong Island on clear days. The views from lower levels of this VSR will be partially blocked by adjacent structures and vegetation and their views will be of lower quality. Considering the glimpse view from viewers in the mid and upper levels, the sensitivity of this VSR is medium.

R2.10

Oi Man Estate

While most residents in Oi Man Estate King (R2.10) are unlikely to be able to see the project site, residents of the higher levels of Kin Man House, are about 80 m from the proposed Project Site at its closest point and have a glimpse view of the site over the Ho Man Tin West Service Reservoir, East Service Reservoir Playground and the general urban surroundings. Some residents of the easternmost flats at higher levels of Lia Man, Po Man, Chung Man and Chiu Man Houses may also have glimpse views towards the Project Site, but most flats face either north of south rather than east towards the site. The views from lower levels of this VSR will be blocked by adjacent structures and vegetation and they will not be able to see the Project Site. Considering the small number of residents with views towards the Project Site and the glimpse views, the sensitivity of this VSR is medium.

Government/ Institution/ Community VSRs

GIC2.1

Ho Man Tin Government Offices

GIC2.2

SKH Tsoi Kung Po Secondary School

GIC2.3

Housing Authority Headquarters

Viewers in the above listed VSRs located near the Ho Man Tin West Fresh Water Service Reservoir are low to medium high buildings and from the higher levels, their views to the proposed Project Site take in the vegetated man-made slope around Ho Man Tin West Service Reservoir ad well as taking in the greenery of the lawn on the top of reservoir. The value and quality of the existing view is fair to good but given these are workers or school children and teachers, their views are occasional and less valued, so the sensitivity of these VSRs is medium.

GIC2.4

Housing Authority Mock-up Centre

This VSR is low-rise buildings located on the top of the Ho Man Tin West Fresh Water Service Reservoir with fairly open views to the lawn on the Services Reservoir and a backdrop of high-rise buildings. The value and quality of the existing view is fair. Towards the proposed ventilation building the view is largely blocked by existing vegetation but this site is currently included in the Works Area. Therefore despite the number of viewers being low and them placing less value in their view due to their working nature, the sensitivity of this VSR is as medium.

Recreational VSRs

RE2.1

Ho Man Tin East Service Reservoir Playground

Views out from this VSR towards the proposed Project Site are fairly contained by the surrounding trees and to some extent the fence such that any views would be partial at best. The existing view focuses on the lawn of the reservoir playground itself, is slightly above from the main Fat Kwong Street to the west and on raised ground commanding fairly open view south, currently dominated by the MTR development area to the south west, and with medium to high buildings as a backdrop. The value and quality of the existing view is fair and the sensitivity of this VSR is medium.

RE2.2

Sheung Lok Street Garden

Viewers in this VSR have a limited view from within the park to the outside surroundings at ground level. In addition any view towards the Project Site is along Sheung Lok Street which is lined with planted trees and vegetation which largely screens any views. Any views to the proposed Project Site would therefore be glimpse at best and combined with the low number and temporary nature the of viewers in this VSR, the sensitivity is low.

Travel/ Transport Related VSRs

T2.1

Fat Kwong Street (near Project  Site)

T2.2

Chung Hau Street and Good Shepherd Street (near Project Site)

Fat Kwong Street is the main artery of the Ho Man Tin area and served mainly by public buses. The section near the proposed Project Site (T2.1) has views to the proposed Project Site limited by roadside and slope planting and the surrounding buildings. Viewers in T2.1 are likely to be faster moving than on T2.2 which includes less major roads. Viewers in T2.2 also have views to the proposed Project Site partially blocked by vegetation. The sensitivity of these VSRs is low.

 


Table 10.5: List of the VSRs around the Central Portion and their Sensitivity

 

* Denotes future VSRs that will not be in existence when construction for the Project starts. 

 

VSR Code

Type of VSRs

VSR Name

Number of Individuals (Very few, Few, Many, Very many)

Quality of Existing View (Poor/ Fair/ Good)

Availability of Alternative Views

Approx. Minimum Distance between VSRs and Impact Sources (Ventilation Building) (m)

Degree of Visibility towards Project (Glimpse/ Partial/ Full)

Duration of View (Short/ Medium/ Long)

Frequency of View (Rare/ Occasional/ Frequent)

Sensitivity (Low, Medium, High)

Central Portion

R2.1

Residential

15 Ho Man Tin Hill

Many

Good

Yes

460

Full

Long

Frequent

High

R2.2

Residential

Ellery Terrace

Many

Good

Yes

330

Full

Long

Frequent

High

R2.3

Residential

Ho Man Tin Estate King Man House

Many

Good

Yes

420

Glimpse

Long

Frequent

Medium

R2.4

Residential

Ho Man Tin Estate (High Rise Building Block)

Many

Good

Yes

150

Full

Long

Frequent

High

R2.5

Residential

Ho Man Tin Estate

Many

Fair

Yes

60

Full

Long

Frequent

High

R2.6

Residential

Carmel On The Hill

Many

Fair

Yes

150

Full

Long

Frequent

High

R2.7

Residential

Chung Man Court

Many

Fair

Yes

180

Full

Long

Frequent

High

R2.8

Residential

Future Redevelopment of Ex-Valley Road Estate

Many

Good

Yes

300

Full

Long

Occasional

High*

R2.9

Residential

HK Polytechnic University Student Hostel Development

Few

Good

Yes

460

Full

Long

Frequent

High

R2.10

Residential

Oi Man Estate

Few

Good

Yes

80

Glimpse

Long

Occasional

Medium

GIC2.1

Government/ Institution/ Community

Ho Man Tin Government Offices

Many

Fair

Yes

60

Partial

Medium

Occasional

Medium

GIC2.2

Government/ Institution/ Community

SKH Tsoi Kung Po Secondary School

Many

Fair

Yes

30

Glimpse

Medium

Occasional

Medium

GIC2.3

Government/ Institution/ Community

Housing Authority Headquarters

Many

Fair

Yes

35

Partial

Medium

Occasional

Medium

GIC2.4

Government/ Institution/ Community

Housing Authority Mock-up Centre

Few

Fair

Yes

60 (but within a separate works area)

Glimpse

Medium

Occasional

Medium

RE2.1

Recreational

Ho Man Tin East Service Reservoir Playground

Many

Fair

Yes

260

Partial

Short

Occasional

Medium

RE2.2

Recreational

Sheung Lok Street Garden

Many

Good

Yes

40

Glimpse

Short

Occasional

Low

T2.1

Travel/ Transport Related

Fat Kwong Street (near Project Site)

Many

Fair

Yes

25

Partial

Short

Rare

Low

T2.2

Travel/ Transport Related

Chung hau Street and Good Shepherd Street (near Project Site)

Many

Fair

Yes

15

Partial

Short

Occasional

Low


10.8.3             East Portion

The East Portion of the VIA study area is in the Kowloon Bay District and dominated by the former Kai Tak Airport which is undergoing development. Surrounding this area of ongoing development, there is and industrial urban area to the east of the Kwun Tong Typhoon Shelter, including the Hong Kong International Trade & Exhibition Centre with some green hills in the background including Kowloon Hill.  To the north of the Kai Tak Development (KTD) area, across the key transport corridor of Prince Edward Road, there is a more residential area, again with a green backdrop of Lion Rock Country Park in the distance.  To the west of KTD is a mixed urban landscape including some commercial and industrial buildings and several residential blocks. 

The East Portion of CKR and its associated structures are constructed by a short cut-and-cover tunnel at Kowloon City Ferry Pier PTI, underwater tunnel across Kowloon Bay and depressed road on KTD Area of the former Kai Tak Airport area. Since the former Kai Tak Airport has been decommissioned and is now an ongoing major development landscape with all buildings already demolished, the ZVI extends to the first row of building along Prince Edward Road and Kwun Tong Bypass. Some high-rise residential or commercial buildings can also have a direct view to the Project Site. The future developments in Kai Tak would also have a close view of the Project. The baseline conditions of VSRs within the East Portion ZVI, together with their sensitivity are described below and a summary provided in Table 10.6 following.

Residential VSRs

R3.1

Wyler Gardens

R3.2

Grand Waterfront

These VSRs are medium to high rise buildings and residents in the mid to upper levels will have a direct view to the Project Site. They are closest to the cut and cover tunnel area and re-provisioning of the PTI with new landscape deck, but still at least 350 m from it, while the proposed tunnel portal on Kai Tak is over 750 m away from each of these VSRs.  In the future, views to the development structures may be partly obscured by developments in Kai Tak, such as the proposed Multi Purpose Stadium Complex. VSRs in lower levels have their views interrupted by the surrounding buildings, the Public Transport Interchange and the little vegetation in the area. Only some of the residents in these buildings have views towards the Project Site, while others are at too low a level or face away from the Project Site. At the higher levels the views are more panoramic and the value and quality of the existing view for R3.2 is good, while that for R3.1 is fair. Overall the sensitivity of these VSRs is high.

R3.3

Sky Tower

Residents in this VSR have an open and distant view towards the Project Site. They are one of the tallest residential building blocks in Ma Tau Kok and residents in mid and upper levels currently enjoy a high quality panoramic view of the surroundings. VSRs in lower levels have their views interrupted by the surrounding buildings. After the completion of Kai Tai Development, the view towards the development will be partially blocked by the proposed Multi Purpose Stadium Complex. This VSR is rated as having high sensitivity, but noting that in the future the proposed CKR development will have less of an impact on it.

R3.4

High Rise Developments along Prince Edward Road West (Including Padek Palace; New Development on Nga Tsin Long Road; Prince Ritz; Tung Sing Court)

R3.5

High Rise Developments along Prince Edward Road East (Carlson Court; Billionaire Royale and Le Billionaire; New Development on Lok Sin Road; The Latitude; Rhythm Garden)

R3.6

Choi Hung Estate

The VSRs listed above are located to the north of former Kai Tak Airport separated by the at-grade and elevated road of Prince Edward Road East. Residents in upper levels will have an open view to the vacant land of former Kai Tak Airport. VSRs in lower levels have a close view to Prince Edward Road East and the elevated road. Prince Edward Road East is a busy traffic corridor and traffic congestion can always be seen. After the completion of Kai Tak Development, the view will be blocked by a proposed open space, residential and commercial development in front of these VSRs. The value and quality of the existing view is fair and open but after the development in Kai Tak is complete, views will largely be blocked. VSRs are therefore rated as having medium sensitivity, but noting that in the future the proposed CKR development will have less, if any, impact on them.

R3.7

Richland Gardens

Richland Gardens (R3.7) is currently the largest residential development in this district adjacent to Kowloon Bay Industrial Area, which consist of 22 high-rise residential building blocks. Depending on the location of different blocks, their visibility and views of the surroundings are different, some may even have an open view to Kowloon Bay and Victoria Harbour over the Kwun Tong Bypass and through the vacant land of the former Kai Tak Airport. After the completion of development in the former Kai Tak Airport, these existing views will be partially blocked by the proposed residential, government, institution or community buildings. The value and quality of the existing view is currently fair and the sensitivity of this VSR rated as is medium, but noting that in the future the proposed CKR development will be largely obscured by the Kai Tak Development. 

R3.8

Planned Residential Development in Kai Tak

Residents in the planned residential developments (R3.8) within former Kai Tai Airport will have an open view to the proposed Multi-Purpose Stadium Complex, regional open space and at higher levels out to Kowloon Bay. The quality of their views will be good and many of them will have direct, relatively close views of the proposed CKR development. The sensitivity of this VSR, when it exists in the future, will be high.

R3.9

Sunrise Villa and New Residential Development at 9 Yuk Yat Street

R3.10

Laguna Verde Complex and Harbourfront Landmark

These buildings are very far from the Project Site (780 m minimum to the tunnel portal and over 1200 m minimum to the ventilation building). R3.9 houses many residents and is slightly closer while R3.10 houses a high number of residents and both have good quality views towards the Project Site.  However given the distance, their sensitivity is medium. 

Commercial/ Residential VSRs

CR3.1

Comprehensive Development Area around Ma Tau Kok Road (photograph at Hing Yan Street)

Viewers in the CR3.1 buildings by the Ma Tau Kok waterfront have a close and open view towards the proposed tunnel portal and through the currently vacant land of the former Kai Tak Airport towards the proposed ventilation building site. After the completion of Kai Tak Development, the view will be screened by a proposed recreational area, likely housing the Multi Purpose Stadium Complex. The value and quality of the existing view is fair and the sensitivity of this VSR is medium.

CR3.2

Planned Commercial/ Residential Development in Kai Tak

Future viewers in the CR3.2 buildings, will mainly face either east towards the Kowloon Bay Industrial Area or west towards Kowloon Bay. Some may have views North West but only a limited number may be able to see the proposed ventilation building.  More of those facing east will have views of the new connecting road and have a close and open view towards the proposed tunnel portal. Also they will be able to see through the currently vacant land of the former Kai Tak Airport towards the proposed ventilation building site. After the completion of Kai Tak Development, the view will be screened by a proposed recreational area, likely housing the Multi Purpose Stadium Complex. The value and quality of the existing view is fair and the sensitivity of this VSR is medium.

Commercial VSRs

C3.1

Newport Centre (partly in CDA of OZP)

Viewers in this VSR have a close view to the vacant land of the former Kai Tak Airport and the site of the proposed tunnel portal. The building is low rise and after the completion of the Kai Tak Development, views of the CKR development will largely be obscured or blocked by a proposed Multi-Purpose Stadium Complex and other proposed open space. The value and quality of the existing view is poor and the sensitivity of this VSR is low.

C3.2

Kapok Industrial Building

Users in this VSR currently have a direct, close view to the all concrete paved bus terminus, ferry pier and Kowloon Bay. The view towards the Project Site is very limited by the Grand Waterfront as well as partially blocked by traffic in the bus terminus. This VSR is adjacent to the cut and cover works area and re-provisioning of the PTI with new landscape deck.  The value and quality of the existing view is poor and the sensitivity of this VSR is low.

C3.3

Kam Fai Commercial Building and Regal Oriental Hotel Hong Kong

C3.4

Tai King Industrial Building

Users in these VSRs have a similar view to VSRs R3.4, R3.5 and R3.6. They are located to the north of former Kai Tak Airport separated by the at-grade and elevated road of Prince Edward Road East.

Viewers in upper levels of these medium rise buildings will have an open view to the vacant land of former Kai Tak Airport. VSRs in lower levels have a close view to Prince Edward Road East and the elevated road. Prince Edward Road East is a busy traffic corridor and traffic congestion can always be seen. After the completion of Kai Tak Development, the view will be blocked by a proposed open space, residential and commercial development in front of these VSRs. The value and quality of the existing view is fair and open but after the development in Kai Tak is complete, these views will largely be blocked. Given the nature and low numbers of viewers in these VSRs, the sensitivity low, and it is noted that in the future the proposed CKR development will have less, if any, impact on them.

C3.5

Skyline Tower

C3.6

Enterprise Square II; Enterprise Square

C3.7

Enterprise Square V and MegaBox; Enterprise Square III; Manhattan Place

C3.8

Hong Kong International Trade & Exhibition Centre

C3.11

Kowloon East 18

C3.12

Billion Centre

C3.13

Nam Fung Commercial Centre

The VSRs listed above are some of the tallest commercial buildings in Kowloon Industrial Area. Viewers at medium to high levels in these buildings have open and panoramic views over the area and even out to Victoria Harbour in some instances. Looking towards the proposed Project Site, they have views of the vacant land of former Kai Tak Airport which deteriorates their view, mainly for viewers in C3.5 and C3.8 which are closer to KTD area. After the completion of Kai Tak Development, the view of VSRs in low and mid levels of C3.5 and C3.8 will have a close view to the proposed Government Buildings (GIC3.1 and GIC3.2) in the front. C3.6, C3.7, C3.11, C3.12 and C3.13 are all slightly further south in the Industrial area and have views of the Kai Tak apron and Kowloon Bay which will also change as the KTD proceeds. Overall the value and quality of the existing view is fair to good, however, considering the nature of these VSRs, their sensitivity is medium.

C3.9

Planned Commercial Development in Kai Tak

Future viewers in this VSR will have a limited view towards the CKR Project Site, largely blocked by the planned residential development in the front (R3.8). Additionally considering the nature of these VSRs, their sensitivity will be low.

C3.10

United Daily News Centre

Viewers in this VSR will have a limited view towards the CKR Project Site. Only viewers at the higher levels will be able to see out over existing buildings to the proposed tunnel portal and roads and the proposed ventilation building will be over 1100 m away. Existing views are of poor quality and the sensitivity of this VSR is low.

C3.14

Industrial Buildings along Wang Kee Street

Viewers in this VSR are in low rise buildings looking out over a car park area and the busy Kwun Tong Bypass, so their existing views are poor. Since they are low rise, they will have limited views past the Project Site immediately in front of them and at best will have a glimpse view towards the ventilation building. Overall their sensitivity is low.

Governmental/ Institution/ Community VSRs

GIC3.1

EMSD Headquarters

Viewers in this VSR have a close view to the vacant land of the former Kai Tak Airport. GIC3.1 is planned for waterfront related commercial, cultural and leisure uses. After the completion of the Kai Tak Development, this VSR will have a partial view to the proposed government building and regional open space. The sensitivity of this VSR is medium.

GIC3.2

Planned Government Buildings in Kai Tak

Future viewers of this VSR will have a close view of the proposed CKR connecting roads and ventilation building with the proposed Multi-Purpose Stadium Complex and regional open space of the KTD in the background. Considering the nature of this VSR, when they come into existence, their sensitivity will be medium.

GIC3.3

Holy Carpenter Primary School

There are very few viewers in this VSR and only those in the few classrooms at higher levels facing north east will have a view of the Project Site, out over the vehicle inspection centre and vehicles lining the road. Their existing view is fair quality from higher levels but given the very few viewers and the nature of this VSR, its sensitivity is low.

GIC3.4

EMSD Workshops

Viewers in this VSR have a close view to the vacant land of the former Kai Tak Airport. After the completion of the Kai Tak Development, views from this VSR towards the CKR ventilation building are likely to be blocked by the Multi-Purpose Stadium Complex although the tunnel portal may still be visible. Given the enclosed nature of this building, the limited numbers of workers inside and the nature of the VSRs, the sensitivity of this VSR is low.

Recreational VSRs

RE3.1

Planned Regional Open Space in Kai Tak

Viewers in these future VSRs will have a panorama view to Kowloon Bay and Victoria Harbour with the East Kowloon urban landscape, Lion Rock and Fei Ngo Shan as the backdrop. The view will be restricted by planting in some locations within the open space and given the more temporary nature of these viewers, their sensitivity is medium.

RE3.2

Planned Multi Purpose Stadium Complex in Kai Tak

Viewers in this future VSRs will mainly be focused inside the stadium complex and their views to the proposed CKR connecting road and ventilation building will largely be screened by landscaping or other structures. However given the high number of viewers in this VSR and that this area borders the CKR connecting road, their sensitivity is medium.

RE3.3

Current and Future Waterfront Promenade at Ma Tau Kok

Viewers in this VSR will have direct views across to the KTD and the area of the proposed tunnel portal. Once development in Kai Tak has been completed the Multi-Purpose Stadium Complex and open space either side of the connecting CKR road will dominate their view. Overall the sensitivity of this VSR is medium.

Occupational VSRs

O3.1

The Hong Kong and China Gas Company Limited Ma Tau Kok Control Centre

O3.2

Petrol Station at Kai Fuk Road

Viewers in these VSRs have immediate views of busy traffic at ground level and cannot get to higher levels to enjoy more open views. The value and quality of their existing views is poor and the sensitivity of these VSRs is low.

Travel/ Transport Related VSRs

T3.1

Kwun Tong Bypass

T3.2

Harbour Traffic

Kwun Tong Bypass (T3.1) is an elevated bypass expressway in Kwun Tong, with three lanes in each direction. This VSR refers to the section indicated in Figure 10.15.1. Travellers in the VSR have a view to the vacant land of the former Kai Tak Airport partly blocked by road railings and other buildings close to the road as well as noise barriers at a section near Richland Gardens. Due to the busy traffic and high travelling speed, the sensitivity of this VSR is low.

Harbour Traffic (T3.2) is referring to any ships or ferries travelling the inshore part of Kowloon Bay. VSR have an open view to East Kowloon and former Kai Tak Airport and views can be good.  Given the transient nature of the viewers and often distance from the Project Site, the sensitivity is low.


Table 10.6: List of the VSRs in East Portion and their Sensitivity

 

* Denotes future VSRs that will not be in existence when construction for the Project starts. 

 

VSR Code

Type of VSRs

VSR Name

Number of Individuals (Very few, Few, Many, Very many)

Quality of Existing View (Poor/ Fair/ Good)

Availability of Alternative Views

Approx. Minimum Distance between VSRs and Impact Sources (Road/Ventilation Building) (m)

Degree of Visibility towards Project (Glimpse/ Partial/ Full)

Duration of View (Short/ Medium/ Long)

Frequency of View (Rare/ Occasional/ Frequent)

Sensitivity (Low, Medium, High)

East Portion

R3.1

Residential

Wyler Gardens

Many

Fair

Yes

540/ 960

Full

Long

Frequent

High

R3.2

Residential

Grand Waterfront

Very Many

Good

Yes

350/ 780

Full

Long

Frequent

High

R3.3

Residential

Sky Tower

Very Many

Good

Yes

740/ 980

Partial

Long

Frequent

High

R3.4

Residential

High Rise Developments along Prince Edward Road West (Including Padek Palace; New Development on Nga Tsin Long Road; Prince Ritz; Tung Sing Court)

Very Many

Fair

Yes

1060/ 1100

Glimpse

Long

Frequent

Medium

R3.5

Residential

High Rise Developments along Prince Edward Road East (Carlson Court; Billionaire Royale and Le Billionaire; New Development on Lok Sin Road; The Latitude; Rhythm Garden)

Very Many

Fair

Yes

1000/ 1100

Glimpse

Long

Frequent

Medium

R3.6

Residential

Choi Hung Estate

Many

Fair

Yes

1060/ 1350

Glimpse

Long

Frequent

Medium

R3.7

Residential

Richland Gardens

Very Many

Fair

Yes

640/ 900

Partial

Long

Frequent

Medium

R3.8

Residential

Planned Residential Development in Kai Tak

Very Many

Good

Yes

120/ 220

Full

Long

Frequent

High*

R3.9

Residential

Sunrise Villa and New Residential Development at 9 Yuk Yat Street

Many

Fair

Yes

780/ 1200

Partial

Long

Frequent

Medium

R3.10

Residential

Laguna Verde Complex and Harbourfront Landmark

Very Many

Good

Yes

1300/ 1800

Full

Long

Frequent

Medium

CR3.1

Commercial/ Residential

Comprehensive Development Area around Ma Tau Kok Road (photograph at Hing Yan Street)

Many

Fair

No

340/ 740

Full

Long

Frequent

Medium

CR3.2

Commercial/ Residential

Planned Commercial/ Residential Development in Kai Tak

Very Many

n/a

Yes

740/ 880

Partial

Long

Rare

Medium

C3.1

Commercial

Newport Centre (partly in CDA of OZP)

Very Few

Poor

No

300/ 640

Partial

Medium

Occasional

Low

C3.2

Commercial

Kapok Industrial Building

Very Few

Poor

No

520/ 960

Glimpse

Medium

Occasional

Low

C3.3

Commercial

Kam Fai Commercial Building and Regal Oriental Hotel Hong Kong

Few

Fair

Yes

960/ 1060

Glimpse

Medium

Occasional

Low

C3.4

Commercial

Tai King Industrial Building

Few

Fair

Yes

1000/ 1200

Glimpse

Medium

Occasional

Low

C3.5

Commercial

Skyline Tower

Many

Fair

No

120/ 500

Full

Medium

Occasional

Medium

C3.6

Commercial

Enterprise Square II; Enterprise Square

Very Many

Fair

Yes

150/ 600

Full

Medium

Occasional

Medium

C3.7

Commercial

Enterprise Square V and MegaBox; Enterprise Square III; Manhattan Place

Very Many

Fair

Yes

100/ 780

Full

Medium

Occasional

Medium

C3.8

Commercial

Hong Kong International Trade & Exhibition Centre

Very Many

Fair

No

10/ 180

Full

Medium

Occasional

Medium

C3.9

Commercial

Planned Commercial Development in Kai Tak

Very Many

Fair

Yes

750/ 850

Partial

Medium

Occasional

Low*

C3.10

Commercial

United Daily News Centre

Very Few

Poor

Yes

700/ 1200

Glimpse

Medium

Occasional

Low

C3.11

Commercial

Kowloon East 18

Many

Fair

Yes

400/ 740

Full

Medium

Occasional

Medium

C3.12

Commercial

Billion Centre

Many

Fair

No

50/ 550

Full

Medium

Occasional

Medium

C3.13

Commercial

Nam Fung Commercial Centre

Few

Fair

Yes

250/ 650

Full

Medium

Occasional

Medium

C3.14

Commercial

Industrial Buildings along Wang Kee Street

Very Few

Poor

No

80/ 460

Full

Medium

Occasional

Low

GIC3.1

Government/ Institution/ Community

EMSD Headquarters

Many

Good

Yes

10/ 260

Full

Medium

Occasional

Medium

GIC3.2

Government/ Institution/ Community

Planned Government Buildings in Kai Tak

Many

Good

Yes

20/ 100

Glimpse

Medium

Occasional

Medium*

GIC3.3

Government/ Institution/ Community

Holy Carpenter Primary School

Very Few

Fair

Yes

650/ 1120

Glimpse

Medium

Occasional

Low

GIC3.4

Government/ Institution/ Community

EMSD Workshops

Few

Fair

Yes

260/ 580

Partial

Medium

Occasional

Low

RE3.1

Recreational

Planned Regional Open Space in Kai Tak

Many

Good

Yes

0/ 120

Full to Partial

Short

Occasional

Medium*

RE3.2

Recreational

Planned Multi Purpose Stadium Complex in Kai Tak

Very Many

Good

Yes

0/ 200

Partial

Short

Occasional

Medium*

RE3.3

Recreational

Current and Future Waterfront Promenade at Ma Tau Kok

Many

Good

Yes

240/ 580

Full

Short

Occasional

Medium

O3.1

Occupational

The Hong Kong and China Gas Company Limited Ma Tau Kok Control Centre

Few

Poor

No

500/ 850

Partial

Short

Occasional

Low

O3.2

Occupational

Petrol Station at Kai Fuk Road

Few

Fair

No

10/ 400

Full

Short

Occasional

Low

T3.1

Transport Related

Kwun Tong Bypass

Many

Fair

Yes

0/ 320

Full

Short

Rare

Low

T3.2

Travel/ Transport Related

Harbour Traffic

Few

Good

Yes

150/ 540

Full

Short

Rare

Low

 


10.9                   Landscape Impact Assessment

10.9.1             Potential Sources of Impact

The proposed CKR is a dual 3-lane east-west trunk road about 4.7km long with about 3.9km in tunnel connecting West Kowloon with the Proposed KTD. Potential landscape (and visual) impacts would be restricted to above ground construction works and operational facilities.  Sources of impacts are expanded upon below concentrating on landscape impacts, which may also be sources of visual impact.  Sources of impact that would potentially only cause visual impact are listed additionally in Section 10.11.1. 

From Construction Works

·               Site clearance and site formation works;

·               Provision of elevated and at-grade slip road connections between the tunnel, the road network on the West Kowloon Reclamation including modifications to the YMT Interchange and connection roads at eastern end;

·               Construction of tunnel ramps and a tunnel portal to the west of Ferry Street;

·               Cut and cover tunnel between Ferry Street and Shanghai Street and between To Kwa Wan Road and Kowloon City Ferry Pier;

·               Construction of landscape deck;

·               Construction of underwater tunnel between Kowloon City Ferry Pier and Kai Tak Runway;

·               Construction of ventilation buildings:

(i)              to the west of Ferry Street;

(ii)            at the junction of Chung Hau Street and Fat Kwong Street, near Sheung Lok Street; and,

(iii)           near the tunnel portal in the proposed Kai Tak Development;

·               Construction of administration building near the tunnel portal in the proposed Kai Tak Development;

·               Construction of depressed road between Kai Tak Runway and the Interchange with Kai Cheung Road, Kai Fuk Road and the future Road T2 on the proposed Kai Tak Development;

·               Replacement of a section of at-grade Hoi Wang Road by an elevated road;

·               Construction of noise barriers/enclosures;

·               Demolition and re-provisioning of Government, community and commercial facilities affected by the CKR, including:

(i)              Demolition of Yau Ma Tei Multi-Storey Car Park Building and re-provisioning in same location;

(ii)            Demolition of Special Clinic Extension Building and re-provision in Queen Elizabeth Hospital;

(iii)           Temporary removal of Jade Hawker Bazaar and re-provisioning in same location as well as construction of a temporary building on Kansu Street Rest Garden on the south side of multi-storey car park;

(iv)          Removal of the Hong Kong Automobile Association buildings;

(v)            Re-provisioning of a section of Gascoigne Road Flyover (GRF) between Temple Street and Ferry Street and construction of temporary flyover to its north side. 

(vi)          Demolition of the existing Ma Tau Kok Public Pier and provision of a landing step for its temporary relocation. 

From Construction Site Operation

·               Temporary stockpiling of excavated and building materials and storage of construction equipment and plant at Ma Tau Kok;

·               Temporary noise mitigation measures e.g. barriers, enclosures;

·               Contractor’s temporary works areas, including site offices and parking areas;

·               Proposed barging point at Kwai Chung

From Operation Phase

Sources of impacts in the operation phase would include from the operation of:

·               Tunnel ramps and tunnel portal;

·               Ventilation shafts, ventilation buildings and administration buildings;

·               Landscape deck;

·               Interchange and connection roads including depressed roads and viaducts;

·               Re-provisioned of Government ,and community facilities including;

(i)              Yau Ma Tei Multi-Storey Car Park Building in same location as previously;

(ii)            Special Clinic Extension Building in Queen Elizabeth Hospital;

·               Adverse residual impacts from loss of trees during the construction stage.

10.9.2             Degree of Compatibility of the Project and Associated Works

A major portion of the proposed CKR is tunnel, which is deemed very compatible with the surroundings from a landscape and visual perspective, and where it is underground it is unlikely to impose any landscape or visual impacts.  The above ground structures such as noise barriers, tunnel ramps, tunnel portal, interchange, connection roads and depressed roads are in line with the existing and planned transportation corridor character setting in Yau Ma Tei and have good compatibility.

In the East Portion, extensive work has been done to ensure the CKR development integrates with the KTD and details of the general design considerations have been provided in Section 10.5.3.  Further details regarding specific design considerations in the East Portion, can be found in Section 10.10.1. 

Other above ground structures that could cause landscape and visual impacts, and have varying compatibility with the surroundings, include:

·               Noise Barriers/ Enclosures. These are proposed at some locations on the West Portion viaduct. Details of the noise barriers/enclosures are illustrated in Figure 10.10.5, Figures 10.10.7, Figure 10.10.8, Figure 10.10.9 and Figure 10.10.10.  These have been designed to be as visually unobtrusive as possible while still providing the necessary noise mitigation.  The landscape deck is also a noise barrier as listed below.

·               Proposed Landscape Deck on the West Portion of the CKR Tunnel beyond Ferry Street. This is undergoing detailed design but will generally enhance the area by providing green space in an urban area. Practically, the landscape deck may also act as a noise barrier. Details of the proposed landscape deck are illustrated in Figure 10.10.11, Figure 10.10.12, Figure 10.10.13, Figure 10.10.14 and Figure 10.10.15 and in the Landscape Mitigation Plan in Figure 10.10. 

·               Ventilation Building at Yau Ma Tei Site. Detailed design is being finalised but will generally enhance the area making it highly compatible with the surroundings. Details of the proposed ventilation building are illustrated in Figure 10.10.1, Figure 10.10.2 and Figure 10.10.3 and in the Landscape Mitigation Plan in Figure 10.10. 

·               Ventilation Building at Ho Man Tin. Detailed design is being finalised but will generally enhance the area making it highly compatible with the surroundings. Details of the proposed ventilation building are illustrated in Figure 10.11.1 and Figure 10.11.2 and in the Landscape Mitigation Plan in Figure 10.11. 

·               Ventilation Building at Kai Tak. Detailed design is being finalised but will generally enhance the area making it highly compatible with the surroundings. Details of the proposed ventilation building are illustrated in Figure 10.12.3, Figure 10.12.4, Figure 10.12.5 and Figure 10.12.6 and in the Landscape Mitigation Plan in Figure 10.12. 

·               Proposed Landscape Deck at Kowloon City Ferry Pier PTI, Ma Tau Kok.  This is undergoing detailed design but will make the PTI more amenable by adding a greening aspect in this urban area. Practically, the landscape deck may also act as a noise barrier. The proposed landscape deck location is illustrated in the Landscape Mitigation Plan in Figure 10.12. 

·               Proposed Landscape Deck above Depressed Road in the East Portion, Kai Tak Area.  This is undergoing detailed design but will integrate into the overall landscape master plan of Kai Tak Development, adding green visual relief to this area and making the road more compatible with the surroundings.  The proposed landscape deck location is illustrated in the Landscape Mitigation Plan in Figure 10.12. 

·               Re-provisioned Government, Community Facilities.  These facilities which will be demolished due to the CKR (e.g. Yau Ma Tei Multi-Storey Car Park Building and Kowloon Government Offices) will be re-provisioned in adjacent or nearby locations and designed to blend with the existing environment and meet the needs of public. These buildings will undergo detailed design at a future stage, but it is considered that the re-provisioned buildings will be compatible with their proposed landscape setting.  

·               Temporary Works Sites/ Areas & Barging Points.  There will be temporary works sites / areas in the vicinity of the interchange structures, tunnel, landscaped decks, depressed roads, ventilation buildings and administration building to facilitate the construction process, and these will be within the Works Area Limit.  It is recommended that Construction and Demolition (C&D) material should be transported off-site by barge wherever possible to reduce impacts from road transport.  There is a proposed barging point (currently being used by XRL project) at Kwai Chung underneath Cheung Tsing Bridge. DLO/TW&KT has allocated the site until August 2015 to RDO/HyD.  CKR construction is due to commence at the end of 2015 and therefore should this barging point be used, it will continue its current existing use. Figure 10.2.1 illustrates the location of this proposed Barging Point and gives an indication of the landscape, although the area is undergoing development currently and therefore it is a changing landscape.  In general the area and its surrounding is of poor quality and given it is a barging point currently, the Project is not expected to cause any adverse effect.

As a whole, the proposed CKR and associated works would not create substantial visual instruction to the existing urban environment, particularly at operation, and it is considered to be compatible with the existing and proposed landscape settings, even enhancing it in places. 

10.9.3             Magnitude of Change

When assessing the magnitude of change for LRs and LCAs, tree data from the 2010 Tree Survey Report has been used to help understand the treatment of trees i.e. whether trees within an LR will be retained, transplanted or felled, noting an updated tree survey is targeting to be conducted in mid 2013 and the final details of tree treatment will be recommended under Tree Removal Application for this Project.  In general, unmitigated impact on existing trees are moderately adverse as many of the trees are common species and of moderate amenity value.  (Also there will be a significant number of trees and greenery provided at all ventilation and administration buildings as detailed further in Section 10.10)

There will be substantial adverse unmitigated impact on existing public open spaces and amenity areas in the West Portion, such as Public Square Street Playground, Shanghai Street / Market Street Playground, Bazaar, Temple Street / Kansu Street Temporary Rest Garden and Jade Hawker Bazaar, due to the construction of cut and cover tunnel and temporary site offices and the impact will result in removal of some existing trees within these open spaces. Care has been taken to conserve public open spaces in so far as possible (e.g. Yau Ma Tei community Centre Rest Garden) and those public open spaces that are lost due to the Project will be re-provisioned in nearby locations with similar area. In addition further open space will also be provided, such that overall there will be a net gain of public open space due to the Project. The details of re-provisioning affected public open space will be reviewed during the detailed design stage and further details of re-provisioning and provisioning of open space is provided in Section 10.10. 

For the LCAs, the unmitigated impact will be generally adverse due to the loss of existing vegetation and the vacant land after demolition of existing buildings and completion of cut and cover tunnel.

No change is expected to LRs and LCAs falling outside the Works Area during construction or operation. Additionally the proposed barging point at Kwai Chung is currently being used as a barging point by the XRL project and will continue on the existing use, such that no change is expected here either.

The magnitudes of change for each of the LRs and LCAs listed in detail in the Baseline Study (Section 10.7), are provided in Table 10.7 and Table 10.8 for LRs and LCAs respectively. The tables also provide brief descriptions of the considerations taken into account when assessing the magnitude of change, before the implementation of mitigation measures. 


Table 10.7:  Magnitude of Change for LRs

 

LR Code

Name

Approx. Area within Study Area/ Works Area  (m2)

Approx. Area Under Alignment (m2)

Physical extent of impact (Small/ Medium/ Large)

Compatibility with Surrounding Landscape
(Good /Fair /Poor)

Duration of Impact
(Temporary, Permanent)

Reversibility of Change
(Reversible/ Irreversible)

Magnitude of Change
(Large/ Intermediate/ Small/ Negligible)

 

 

 

 

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

 

 

Description of Impacts during Construction and Operation

 

 

 

West Portion

 

 

 

 

 

 

 

 

 

 

 

LR1.1a

Public Square Street Playground

980/ 980

245

Small

Poor

Fair

Temporary - four years

Permanent

Partly reversible

Irreversible

Large

Intermediate

 

 

All this LR is considered to be open space.  It all falls within the works area and although less than a third is under the alignment, it is due to be cleared for the location of a temporary site office. Due to the alignment, eight trees are proposed for removal; one for felling and seven for transplanting. These transplanted trees are mainly Ficus microcarpa of around 4 m height and Livistona chinensis of 6 m height. The other trees, which are larger in size are not affected by the alignment itself, but assuming the site is cleared for the temporarily site office, will be removed by felling.. 


During construction, this LR will be affected by construction of the connecting road from the tunnel portal and will be the location of temporary site offices.  Construction phase will last approximately four years until commissioning and although the area is small, magnitude of change is considered large since all trees will be removed.
During operation, the affected area is small and already largely hard surface so more compatible, but as some of the greening amenity from the trees will have been lost the magnitude of change is considered intermediate.

 

 

LR1.1b

Shanghai Street / Market Street Playground

1,740/ 1,400

1,075

Medium

Poor

Poor

Mainly permanent

Temporary

Partly reversible

Irreversible

Large

Large

 

 

All this LR is considered public open space and some open hard court pitches lie outside the Study Area.  Approximately half of this LR within the works area is under the alignment. 

During construction, all eleven trees within the LR, including one of high value, will be removed for the construction of the cut and cover tunnel and temporary library.  Nine trees are proposed for transplanting, including four Bauhinia spp. four Lagerstroemia speciosa and one Ficus benjamina.  The Ficus virens tree of high value is too large to be transplanted and will be felled along with the Lagerstroemia speciosa tree.  Overall  the magnitude of change during construction will be large.
During operation magnitude of change will continue to be large.

 

 

LR1.1c

Bazaar

310/ 310

310

Medium

Poor

Fair

Temporary - four years

Permanent

Irreversible

Irreversible

Large

Large

 

 

All this LR is considered public open space.  It all lies within the works area falls under the alignment such that all five trees, including the three considered of high value, will be removed by felling. 

During construction, this LR will be affected by construction of cut and cover tunnel and this phase will last approximately four years until commissioning.  Although the area affected is small, three high value trees will be lost and the area will not be useable as public open space, so overall the magnitude of change is large.
At commissioning and during operation, the whole bazaar, which was public open space, will have been lost, including the greenery, and the magnitude of change will remain large.

 

 

LR1.1d

Temple Street / Kansu Street Temporary Rest Garden

365/ 365

0

Small

Fair

Good

Temporary - four years

n/a

Partly reversible

Reversible

Intermediate

Small

 

 

All of this LR is considered public open space and it all falls within the works area although none of it under the alignment.

During construction, this LR will be cleared for the construction of cut and cover tunnel and be the location of the temporary Jade Market and Government Office.  This phase will last approximately four years until commissioning.  The area is very small, soft landscaping is in moveable planters and no trees will be affected, but the area will not be usable as public open space during the construction phase, and the magnitude of change is intermediate.
At operation this LR it is outside the alignment and the temporary structures will have been removed, so the magnitude of change is small.

 

 

LR1.1e

Jade Hawker Bazaar

1,395/ 1,395

1,120

Large

Poor

Fair

Temporary

Permanent

Partly reversible

Irreversible

Large

Large

 

 

All of this LR is considered public open space.  It all falls within the works area and the majority is under the alignment.

During construction, this LR will be cleared for the construction of cut and cover tunnel and the Jade Hawker Bazaar will be temporarily removed.  The existing stalls will be temporarily reprovisioned at the nearby temporary markets and one of them will be located at the rest garden to the south of Henry G. Leong Yau Ma Tei Community Centre. The other one will be located at the temporary sitting out area at the junction between Temple Street and Kansu Street. This phase will last approximately four years until commissioning. All ten trees in the LR will have to be removed; 9 will be felled and one, the Aleurites molucanna, is proposed for transplanting although due to its large size it is not recommended to be transplanted offsite.  Overall since the public open space of the bazaar and the trees will be removed, the magnitude of change is large.

 

At operation, prior to mitigation, the magnitude of change will remain large.

 

 

LR1.3a

Roadside Planting along West Kowloon Highway and Tunnel Area

83,800/ 23,980

4,225

Large

Poor

Poor

Temporary

Permanent

Partly reversible

Irreversible

Large

Large

 

 

There is approximately 83,800 m2 of this LR in the Study Area, of which a small proportion (23,980 m2) falls within the works area and approximately 4,225 m2 is under the alignment and the proposed ventilation building. Approximately 835 trees within the LR will be removed due to the Project, the majority of which (approximately 755) are deemed unsuitable for transplanting and must be felled, so losing much of the greening within this LR despite approximately 725 trees being retained.  The trees proposed for felling include mainly Acacia confuse, Acacia auriculiformis, Acacia mangium, Casuarina equisetifolia, Eucalyptus spp. and Albizia lebbeck of average 10 m height and those for transplanting are mainly Syzygium cumini on average 7 m high and Chrysalidocarpus lutescens on average 4 m high.
Although some areas of this LR may not be directly impacted by the Project, overall due to the loss of high numbers of trees during construction of the connection roads and ventilation building, the magnitude of change during construction and operation is considered large.

 

 

LR1.3b

Roadside Planting along Hoi Wang Road, Yan Cheung Road and Ferry Street Area

8,270/ 7,390

1,050

Small

Poor

Fair

Temporary

Permanent

Partly reversible

Irreversible

Intermediate

Small

 

 

Approximately 7,390 m2 of this planting along Hoi Wan Road, Yan Cheung road and Ferry Street Area falls within the works area but a small proportion (1,050 m2) is under the alignment.  It is estimated that 30 of the existing 125 trees will be removed and the majority of these (25) such as Roystonea regia trees, Bombax ceiba and

Melaleuca quinquenervia are suitable for transplantation. 

During construction this LR will be affected by the construction of the tunnel portal and connection road and magnitude of change is considered intermediate.
During operation the magnitude of change is considered to reduce to small.

 

 

LR1.3c

Roadside Planting between Lai Cheung Road and Ngo Cheung Road

4,620/ 4,555

485

Intermediate

Poor

Fair

Temporary

Permanent

Partly reversible

Irreversible

Intermediate

Small

 

 

Approximately 4,555 m2 of this LR falls within the works area but only a small proportion of that falls under the alignment.  It is considered that 15 of the 25 trees would need to be removed due to the Project, mainly Bauhinia blakeana trees. Most of these trees can be transplanted rather than felled and overall just two Bauhinia blakeana are recommended for felling, while 13 trees, including Bauhinia blakeana and Michelia x alba around 4 m high, are recommended for transplantation.  Nevertheless, during construction the Project would be poorly compatible with the remaining softscape planting in this LR and it will lose much of its greening value during construction of the connection road and landscape deck.

 

Overall the magnitude of change is intermediate during construction and at operation magnitude of change will reduce to small.

 

 

LR1.3d

Roadside Planting along Canton Road and Public Square Street

455/ 455

0

Small

Fair

Fair

Temporary

Permanent

Partly reversible

Irreversible

Small

Small

 

 

All this LR falls with the works area, but none is under the alignment.  Still it is considered that approximately 5 trees would need to be removed due to the Project at the border of the works area, but all are considered able to be transplanted rather than felled.

During construction, this LR will be affected by construction of cut and cover tunnel and connecting roads, but there is little impact on the trees and overall the magnitude of change is small.
During operation magnitude of change will remain small as a small area will be permanently affected.

 

 

LR1.5a

Disturbed Area at Hau Cheung Street

3,950/ 3,950

1,880

Medium

Fair

Fair

Temporary

Permanent

Partly reversible

Irreversible

Intermediate

Small

 

 

All this LR falls within the works area, but only around half is under the alignment and will be permanently changed by the Project.  The remaining area will only be temporarily required by the Project and while most of the trees would have to be felled (35 out of an estimated 50 in the LR), they are mainly weedy species of low value such as Leucaena leucocephala. 

During construction this LR will be affected by the construction of connection roads for the cut and cover tunnel.  Although a relatively large open, disturbed area is affected, given the low value of trees and the fact this LR is already a disturbed area with low landscape value and fair compatibility, the magnitude of change is considered intermediate. 
During operation the magnitude of change will reduce to small.

 

 

LR1.5b

Disturbed Area next to Construction Site at Yau Cheung Road

3,715/ 355

45

Small

Fair

Good

Temporary

Permanent

Partly reversible

Irreversible

Small

Small

 

 

The majority of this LR falls outside the works area and only 355 m2 lies within it, with just two very small patches falling under the alignment.  Ten of the existing 60 low value trees are proposed to be felled but half of these are either dead or the weed species Leucaena leucocephala and the remainder are exotic Acacia confusa.  Since most of this space is outside the works area, the Project will hardly affect the openness of this LR and given the low value of trees, disturbed nature and general low landscape value the Project is fair compatible during construction and more so at operation.

During construction this LR will be affected by the construction of the connection roads and magnitude of change is considered intermediate.
This area has been marked for re-provisioning works but before mitigation, the magnitude of change is considered small during operation.

 

 

LR1.5c

Disturbed Area at Kwai Chung

10,360 / 10,360

0

Small

Good

Good

Temporary

n/a

Reversible

n/a

Small

Negligible

 

 

All of this LR falls within the works area and it is the proposed barging point for this Project.  The site is being used as a barging point already for the XRL Project and therefore this Project is highly compatible and compared with the current use the magnitude of change is considered small.  No loss of the existing trees is expected but taking the worst case scenario the existing trees are weedy and common species of low value and number and therefore the magnitude of change is also small if they were felled. Overall the magnitude of change at construction is small


At operation this location will no longer be used by the Project and it will not be affected by the Project.

 

Man-made shoreline around Kwai Chung

 

 

LR1.8a

Man-made shoreline around Kwai Chung

4,610 / 224

0

Small

Good

Good

Temporary

n/a

Reversible

n/a

Small

Negligible

 

 

All of this LR falls within the works area and it is the proposed barging point for this Project.  The site is being used as a barging point already for the XRL Project and therefore this Project is highly compatible and compared with the current use the magnitude of change is considered small.  No loss of the existing trees is expected but taking the worst case scenario the existing trees are weedy and common species of low value and number and therefore the magnitude of change is also small if they were felled. Overall the magnitude of change at construction is small


At operation this location will no longer be used by the Project and it will not be affected by the Project.

 

 

 

Central Portion

 

 

 

 

 

 

 

 

 

 

 

LR2.3a

Roadside Planting around Housing Authority Mock-up Centre

130/ 130

0

Small

Fair

Good

Temporary

n/a

Reversible

Reversible

Small

Small

 

 

None of this LR falls under the alignment but the Housing Authority Mock-up Centre is proposed as a storage area and taking worst case scenario all the trees (approximately 30 including Ficus microcarpa, Melaleuca quinquenervia and Elaeocarpus hainanensis ranging in height from 5 – 6 m with crown spread between 3 – 4 m) will be affected during construction of the Project due to the earthworks necessary for the construction of the ventilation building. It is considered that 20 will be suitable for transplanting and 10 will have to be felled.

During construction, the Housing Authority Mock-up Centre is proposed to be used as a storage area.  Given the very small area of this LR affected and the low quality of the trees, the magnitude of change to this LR is small.
During operation, this site will no longer be required by the Project and but there will be some adverse residual impact from the construction phase and magnitude of change will remain small but reversible.

 

 

LR2.4a

Vegetation on Man-made Slopes off Chung Hau Street and Fat Kwong Street

10, 455/ 6,160

2,635

Small

Poor

Poor

Temporary

Permanent

Partly reversible

Irreversible

Large

Large

 

 

The majority of this LR within the works area is not under the proposed location of the ventilation building and route for the access road and at this location the main CKR route is underground. 

Without mitigation, the majority of trees in this LR (110 of approximately 155) may have to be removed, mostly felled (only two considered suitable for transplanting).  The greening aspect of this LR would therefore change considerably.  There are also a number of trees considered to be of high value will be affected by the Project; although they do not fall directly under the proposed ventilation building or access road, it is considered that they will be felled.


Overall the magnitude of change is large during construction and operation.

 

 

 

East Portion

 

 

 

 

 

 

 

 

 

 

 

LR3.3a

Roadside Planting along San Ma Tau Street and Bus Terminus

1,620/ 1,620

1,040

Small

Poor

Fair

Temporary

Permanent

Partly reversible

Irreversible

Intermediate

Small

 

 

This LR within the works area falls largely on land that is only temporarily required by the Project during construction. 

During construction, this LR will be affected by construction of cut and cover tunnel and is required for the repositioning of the Kowloon City Ferry Pier Public Transport Interchange (PTI) and metered parking facility and five of the 30 trees in the LR would have to be felled.  These include Carica papaya, Ficus japonica trees average 4 m high and the palm species Washingtonia robusta reaching up to 14 m tall but with just 2 m crown spread. Although the area affected is 1,040 m2, not many trees are affected and the magnitude of change is intermediate. 
During operation the area will be covered over and magnitude of change is considered to reduce to small.

 

 

LR3.3b

Roadside Planting along Long Yuet Street

450/ 45

0

Small

Fair

Good

Temporary

Permanent

Reversible

Irreversible

Small

Negligible

 

 

Only approximately 45 m2 of this LR falls within the works area and none under the alignment.

During construction some of this LR falls is adjacent to land required temporarily by the Project and it is considered that two trees will have to be felled, an Aleurites moluccana and a Macaranga tanarius averaging 10 m.  Overall the magnitude of change is small.
During operation none of this LR falls under the alignment and the magnitude of change is considered negligible.

 

 

LR3.3c

Roadside Planting along Kai Cheung Road and Interchange

10,020/ 9,455

5,845

Large

Poor

Poor

Temporary

Permanent

Partly reversible

Irreversible

Large

Large

 

 

Over half of this LR within the works area is under the alignment and will therefore be permanently affected by the Project while the rest is on land only temporarily required during construction.  Of the estimated 415 trees in this LR 160 would need to be removed (Approximately 155 felled, of which at least half are exotic Casuarina equisetifolia and about 35 are weed species Leucaena leucocephala; and five including Albizia lebbeck, Aleurites moluccana and Bauhinia spp. transplanted) due to the Project.

The overall magnitude of change is considered large during construction and operation.

 

 

LR3.3d

Roadside Planting along Kai Fuk Road

650/ 70

70

Small

Poor

Fair

Temporary

Permanent

Irreversible

Irreversible

Small

Small

 

 

All of this LR inside the works area,  falls under the alignment. Of the estimated 85 trees in the LR, it is considered that 10 would be felled (including Albizia lebbeck, Bauhinia spp. too large to transplant and one dead tree) and 5 would be transplanted (including Bischofia javanica, Chrysalidocarpus lutescens and Spathodea campanulata). These trees would need to be removed due the construction of a connection road but most trees will be retained and overall the magnitude of change is small during construction and operation.

 

 

LR3.3e

Roadside Planting along Kai Cheung Road, Wang Kwong Road and Wang Chiu Road

2,490/ 2,135

0

Small

Good

Good

Temporary

Permanent

Irreversible

Irreversible

Small

Negligible

 

 

This LR is within the works area but none of it falls under the alignment.  Of the approximately 50 trees in the LR, none would need to be removed during the construction or operation of the Project. At construction the construction vehicles on the road may have some minor effect on the roadside trees, but at operation the Project is not considered to affect this LR.  Therefore the magnitude of change is small during construction and negligible at operation.

 

 

LR3.5a

Disturbed Area within former Kai Tak Airport

5,850/ 125

20

Small

Fair

Fair

Temporary

Permanent

Partly reversible

Irreversible

Intermediate

Small

 

 

The former Kai Tak Airport is approximately 79,490 m2 large but just 5,850 m2 falls within the works area and almost none under the alignment. The area within the works area is estimated to have only10 including Ficus microcarpa, Melia azedarach and Terminalia catappa. Five trees are considered suitable for transplanting (Melia azedarach) and the remainder suitable for retention, so no live trees will be felled in this LR.. 

During construction this LR would be affected by the construction of the depressed road, access road to the ventilation building and temporary storage and stockpiling.  The site is also part of the KTD which is undergoing change and the general open, flat aspect of the former Kai Tak Airport will largely change, but mainly due to the KTD. Therefore overall the magnitude of change from this Project is intermediate.

During operation temporary impact would have gone but the site changed in nature and use (as will the surrounding KTD), so the magnitude of change is considered small. 

 

 

LR3.8a

Man-made Shoreline of West Kowloon Bay

5,785/ 2,400

770

Small

Fair

Good

Temporary

n/a

Reversible

Irreversible

Small

Negligible

 

 

This LR falls within the works area at a point where the road alignment is underground and the impact would be temporary during construction of the cut and cover tunnel and underwater tunnel at this point.  During operation some of this LR is required for a waterfront promenade.

Overall given the size affected during construction is fairly small, the magnitude of change is small during construction and negligible during operation prior to mitigation.

 

 

LR3.8b

Man-made Shoreline around former Kai Tak Airport

9,080/ 3,845

0

Small

Fair

Good

Temporary

n/a

Reversible

Irreversible

Small

Negligible

 

 

None of this LR falls under the above ground alignment as the CKR is underground at this point.  The impact would therefore be temporary during construction.  During operation this LR will be affected by the Kai Tak Development Project (KTD) rather than the CKR Project.

Overall the magnitude of change from CKR Project is small during construction and negligible during operation.

 

 

LR3.9a

Kowloon Bay

190,920/ 92,275

19,540

Medium

Fair

Good

Temporary

n/a

Reversible

n/a

Large

Negligible

 

 

This LR will be affected by any marine traffic associated with the Project and how the underwater tunnel is constructed will affect the impact during construction.  Assuming temporary reclamation is required, a large magnitude of change is expected during construction.

During operation, the alignment will be underground and this LR should suffer negligible impact.

 

 

LR3.9b

Kai Tak Nullah

8,965/ 1,790

1,430

Small

Poor

Poor

Temporary

Permanent

Reversible

Irreversible

Small

Small

 

 

Some of this LR falls under the alignment of the connection road and will be permanently affected by the Project.  However under the KTD, the nullah is due to be enhanced.

Given the small area affected, the magnitude of change due to the CKR Project is small during construction and operation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Notes

x.1       Public Open Space

x.2       Urban Residential / Institutional Open Space    

x.3       Roadside Planting

x.4       Vegetation on Man-made Slope

x.5       Disturbed Area with Wild Grass / Small Shrubs

x.6       Lawn Area

x.7       NOT USED

x.8       Man-made Shoreline   

x.9       Water Bodies  

 

Table 10.8:  Magnitude of Change for LCAs

 

LCA Code

Name

Approx. Area of LCA (ha)

Approx. Area within Works Area/ Under Alignment (ha)

Physical extent of the impact  (Small/ Medium/ Large)

Compatibility with Surrounding Landscape
(Good /Fair /Poor)

Duration of Impact
(Temporary, Permanent)

Reversibility of Change
(Reversible/ Irreversible)

Magnitude of Change
(Large/ Intermediate/ Small/ Negligible)

 

 

 

 

 

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

 

 

Description of Impacts during Construction and Operation

 

West Portion

 

 

 

 

 

 

 

 

 

 

 

LCA1.1

Transportation Corridor Landscape

37.58

7.73/ 1.52

Large

Fair

Fair

Temporary

Permanent

Partly Reversible

Irreversible

Large

Large

 

 

During construction this LCA will be affected by the construction of the connection road, tunnel portal, ventilation building and temporary traffic and road diversions.  Roughly half the trees in this LCA will be affected by the Project (approximately 630 trees require felling and 70 will be transplanted.  The trees to be felled are mainly exotic, common species such as Acacia spp. but the loss of greenery will cause a large change on this LCA and the magnitude of change is considered large.  Due to the loss of trees, magnitude of change at operation will continue to be large.

 

 

LCA1.2

Ongoing Major Development Landscape (West Portion & Barging Point)

17.32

10.37/ 4.33

Large

Good

Good

Temporary

Permanent

Partly Reversible

Irreversible

Small

Small

 

 

During construction this LCA will be affected by the construction of the connection road, tunnel portal including landscape deck, temporary storage area and site office.  Over half the trees in this LCA will be affected by the Project (approximately 280 of 580).  225 will  require felling and 55 transplanting.  The trees felled are mainly exotic, common species such as Acacia spp. and weedy species and given this landscape is generally compatible with the Project under construction, the magnitude of change during construction and at operation is small.

 

 

LCA1.3

City Grid Mixed Urban Landscape (West Portion)

13.18

2.67/0.59

Large

Poor

Fair

Temporary

Permanent

Partly Reversible

Irreversible

Intermediate

Small

 

 

During construction this LCA will be affected by the construction of cut and cover tunnel, tunnel portal including landscape deck, demolition of existing buildings and community facilities and construction of temporary community facilities. Approximately half of the trees in this LCA will be affected by the Project, (45 of 60) with 20 requiring felling and 25 considered suitable for transplanting.  During construction the Project is poorly compatible with the surrounding landscape but only a small area is affected and relatively few trees lost, meaning magnitude of change is considered intermediate.
During operation, the Project will be fairly compatible with this landscape and particularly given the small area affected, the magnitude of change is considered small.

 

 

LCA1.4

Residential Complex Landscape

3.86

0.02/0.00

Medium

n/a

n/a

n/a

n/a

n/a

n/a

Negligible

Negligible

 

 

A tiny corner of this LCA is reportedly in the Project works area, but in effect it lies outside and the Project will not affect it.

 

 

LCA1.5

Residential Urban Landscape (West Portion)

7.04

1.98/0.38

Medium

Poor

Fair

Temporary

Permanent

Partly Reversible

Irreversible

Intermediate

Small

 

 

During construction this LCA will be affected by the construction of cut and cover tunnel, tunnel portal including landscape deck and demolition of some existing buildings and community facilities.  Approximately ten trees in this LCA will be affected by the Project and require felling.  During construction the Project is poorly compatible with the surrounding landscape but only a small area is affected and relatively few trees lost, meaning magnitude of change is considered intermediate.
During operation, the Project will be fairly compatible with this landscape and particularly given the small area affected, the magnitude of change is considered small.

 

 

LCA1.6

Typhoon Shelter Landscape (West Portion & Barging Point)

6.5

 

0/0

Small

Good

Good

Temporary

n/a

Reversible

n/a

Small

Negligible

 

 

During construction this LCA will be affected by barges transporting materials to/from the works area. Barge use is normal within this LCA and an existing use such that at worst the Project will cause a small change during construction

At operation barges  will no longer be used by the Project and this LCA will not be affected by the Project.

 

 

 

Central Portion

 

 

 

 

 

 

 

 

 

 

 

LCA2.1

Residential Urban Landscape (Middle)

2.72

0.00

n/a

n/a

n/a

n/a

n/a

n/a

n/a

Negligible

Negligible

 

 

This LCA is not affected by the Project.

 

 

LCA2.2

Miscellaneous Urban Fringe Landscape

7.99

1.34/0.32

Small

Poor

Fair

Temporary

Permanent

Partly Reversible

Irreversible

Intermediate

Intermediate

 

 

During construction this LCA will be affected by the construction of the ventilation building, access road and temporary works.  A large number of the trees in this LCA would have to be felled (currently estimated at 110) and 5 are considered suitable for transplanting.  Although the area affected is very small, the loss of greenery will magnitude of change on this LCA and the magnitude of change is considered intermediate.   Due to the loss of trees, magnitude of change at operation will continue to be intermediate.

 

 

 

East Portion

 

 

 

 

 

 

 

 

 

 

 

LCA3.1

City Grid Mixed Urban Landscape (East Portion)

10.80

0.82/ 0.49

Small

Fair

Good

Temporary

Permanent

Reversible

n/a

Small

Negligible

 

 

This LCA will be temporarily affected by the works area for this Project, but the impact to landscape will be reversible and temporary. 

 

 

LCA3.2

Ongoing Major Development Landscape (East Portion)

62.23

24.24/ 10.38

Large

Good

Good

Temporary

Permanent

Partly Reversible

Irreversible

Large

Intermediate

 

 

During construction this LCA will be affected by the construction of the cut and cover tunnel and PTI re-provision at Ma Tau Kok as well as the ventilation building, depressed road, tunnel portal, other connecting roads and temporary works in the main Kai Tak area.  An estimated 70 trees in this LCA would have to be felled while 15 are considered suitable for transplanting.  Despite the Project being compatible with this LCA, mainly due to the loss of greenery the magnitude of change is considered intermediate.  
Due to the loss of trees, the magnitude of change at operation will continue to be intermediate.

 

 

LCA3.3

Industrial Urban Landscape

17.86

0.58/ 0.00

n/a

n/a

n/a

n/a

n/a

n/a

n/a

Negligible

Negligible

 

 

This LCA is not affected by the Project.

 

 

LCA3.4

Typhoon Shelter Landscape (East Portion)

22.13

10.67/ 1.83

Medium

Fair

Fair

Temporary

n/a

Partly Reversible

n/a

Intermediate

Negligible

 

 

During construction this LCA will be affected by the construction of the underwater tunnel, temporary barging point and increased marine traffic.  How the underwater tunnel is constructed will affect the impact during construction.  For worst case scenario intermediate magnitude of change is suggested during construction.
During operation, the alignment will be underground and this LCA should suffer negligible impact.

 

 

LCA3.5

Transportation Corridor Landscape

7.97

4.14/ 1.35

Medium

Fair

Fair

Temporary

Permanent

Partly Reversible

Irreversible

Intermediate

Small

 

 

During construction this LCA will be affected by the construction of the connection road and temporary works.  An estimated 95 trees in this LCA would have to be felled while 5 are considered suitable for transplanting an therefore during construction there will be some disturbance of this LCA and the magnitude of change is intermediate, but during operation the Project is fairly compatible and the magnitude of change will reduce to small.

 

 

 


10.9.4             Significance of Landscape Impacts

Using the sensitivities of the LRs and LCAs described in the Baseline Study (Section 10.7) and the magnitude of landscape change experienced by each, ascertained in Table 10.7 and Table 10.8, the matrix shown in Table 10.1 has been used to calculate the significance of landscape impacts before mitigation as shown in Table 10.9 and Table 10.10, for LRs and LCAs respectively. 

Before mitigation, during construction and operation, substantial impacts are mainly experienced in the West Portion by public open space resources i.e. Public Square Street Playground (LR1.1a), Shanghai Street / Market Street Playground (LR1.1b), Bazaar (LR1.1c), Jade Hawker Bazzar (LR1.1e) but also by the Roadside Planting along West Kowloon Highway and Tunnel Area (LR1.3a) where high numbers of trees will be removed. In the Central Portion area, substantial impacts are experienced during construction and operation and before mitigation by Vegetation on Man-made Slopes along Chung Hau Street and Fat Kwong Street (LR2.4a) and in the East Portion substantial impacts are experienced during construction and before mitigation by Roadside Planting along Kai Cheung Road and Interchange (LR3.3c).

Before mitigation, during construction and operation, substantial impacts are only experienced by the Transportation Corridor Landscape in the West Portion (LCA1.1) where high numbers of trees will be removed. All other impacts to LCAs are moderate or less prior to mitigation.  At operation prior to mitigation, moderate impacts are experienced one LCA in each or the Project Areas; the Transportation Corridor Landscape in the West Portion (LCA1.1), Miscellaneous Urban Fringe Landscape (LCA2.1) around the Central Portion and Ongoing Major Development Landscape in the East Portion (LCA3.2) i.e. at KTD. 

Using the mitigation measures described in Section 10.10, the residual impact for construction and operation day 1 and year 10 for LRs and LCAs are provided in Table 10.9 and Table 10.10 respectively. 

For all the impacts that are classified as substantial for LRs, measures involving the protection, preservation, transplantation and compensation of trees (MM8, MM9, MM10) are key to their mitigation. In addition, impacts to public open space resources are greatly mitigated by their re-provisioning (MM14) as well as landscape enhancement of these areas (MM15). MM15 is particularly relevant to mitigate the impact on LR1.3a which largely suffers due to a loss of greening, and as features such as the Landscape Deck in the West Portion have been provided to help increase the greening aspect of the Project. Although erosion control (MM6) is generally considered good practice, it is particularly relevant in reducing impacts to landscape resources on slopes (e.g. LR2.4a) or with large areas of planting (LR1.3a). With the implementation of these mitigation measures, residual impacts on all LRs are considered to be ‘slightly adverse’ at worst by year 10 of operation. They are ‘slightly adverse’ at day 1 of operation for most LRs also, except areas of public open space where re-provisioning will take time to establish and where there has been substantial loss of trees and the re-planting will also take time to establish and confer mitigation (e.g. LR1.3a Roadside Planting along West Kowloon Highway and Tunnel Area.

A number of LRs in the East Portion are considered to benefit from the Project once mitigation measures have been implemented. These include Roadside Planting along San Ma Tau Street and Bus Terminus (LR3.3a). A new Public Transport Interchange (PTI) will be developed here, with substantial landscaping, (including a landscaped covered area).LRs which interface with the KTD and will also mutually benefit from the integration of the CKR and KTD designs. These LRs are Disturbed Area within former Kai Tak Airport (LR3.5a), Man-made Shoreline around former Kai Tak Airport (LR3.8b) as well as the Man-made Shoreline of West Kowloon Bay (LR3.8a) which has been selected to become part of a waterfront promenade and will benefit from the Project. 

The same mitigation measures used for LRs are relevant to reducing the significance of impacts on the LCAs and in addition, assuming landscape character is also partly influenced by the appearance of the landscape, MM12 (Green Roof) can help to add greening to an LCA affected by loss of greening.  In particular for LCA1.1, the measures involving the protection, preservation, transplantation and compensation of trees (MM8, MM9, MM10) as well as landscape enhancement (MM15) (including by provision of a landscape deck) and green roof (MM12) are key to the mitigation and compensation of the loss of greenery originally caused by the Project.  With these mitigation measures impact on LCA1.1 is reduced to moderate at construction.  At operation day 1 after mitigation, all impacts on LCAs are ‘slightly adverse’ at worst and by year 10 it is considered that impacts on all LCAs are insignificant.

 


Table 10.9:  Significance of Impact on LRs, both before and upon Mitigation

 

LR Code

Name

LR Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible

Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Recommended Mitigation Measures (MM)

Residual Impact Significance UPON Mitigation (Significant/ Moderate/ Slight/ Insignificant)

 

 

 

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation Day 1

Operation Year 10

 

West Portion

 

 

 

 

 

 

 

 

 

 

LR1.1a

Public Square Street Playground

Medium

Large

Intermediate

Substantial

Moderate

1, 8, 9 ,10, 14

1, 14

Moderate

Slight

Insignificant

LR1.1b

Shanghai Street /Market Street Playground

Medium

Large

Large

Substantial

Substantial

1, 8, 9 ,10, 14

1, 14

Moderate

Moderate

Slight

LR1.1c

Bazaar

High

Large

Large

Substantial

Substantial

1, 8, 9 ,10, 14

1, 14

Moderate

Moderate

Slight

LR1.1d

Temple Street / Kansu Street Temporary Rest Garden

Low

Intermediate

Small

Moderate

Slight

1, 8, 9 ,10, 14,

14

Slight

Insignificant

Insignificant

LR1.1e

Jade Hawker Bazaar

High

Large

Large

Substantial

Substantial

1, 8, 9 ,10, 14,

1, 14

Moderate

Moderate

Slight

LR1.3a

Roadside Planting along West Kowloon Highway and Tunnel Area

High

Large

Large

Substantial

Substantial

1, 6, 8, 9, 10, 13, 15

1, 15

Moderate

Moderate

Slight

LR1.3b

Roadside Planting along Hoi Wang Road, Yan Cheung Road and Ferry Street Area

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 15

1, 15

Slight

Slight

Insignificant

LR1.3c

Roadside Planting between Lai Cheung Road and Ngo Cheung Road

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Slight

Insignificant

LR1.3d

Roadside Planting along Canton Road and Public Square Street

Medium

Small

Small

Slight

Slight

1, 8, 9, 10, 15

1, 15

Slight

Insignificant

Insignificant

LR1.5a

Disturbed Area at Hau Cheung Street

Low

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Insignificant

Insignificant

LR1.5b

Disturbed Area next to Construction Site at Yau Cheung Road

Low

Small

Small

Slight

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Insignificant

Insignificant

LR1.5c

Disturbed Area at Kwai Chung

Low

Small

Negligible

Slight

Insignificant

1, 8,9,10

n/a

Slight

Insignificant

Insignificant

LR1.8a

Man-made shoreline around Kwai Chung

Low

Small

Negligible

Slight

Insignificant

1

n/a

Slight

Insignificant

Insignificant

 

Central Portion

 

 

 

 

 

 

 

 

 

 

LR2.3a

Roadside Planting around Housing Authority Mock-up Centre

Medium

Small

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Insignificant

Insignificant

LR2.4a

Vegetation on Man-made Slopes along Chung Hau Street and Fat Kwong Street

High

Large

Large

Substantial

Substantial

1, 6, 8, 9, 10, 13, 15

1, 15

Moderate

Moderate

Slight

 

East Portion

 

 

 

 

 

 

 

 

 

 

LR3.3a

Roadside Planting along San Ma Tau Street and Bus Terminus

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 15

1, 15

Slight

Slight beneficial

Slight beneficial

LR3.3b

Roadside Planting along Long Yuet Street

Medium

Small

Negligible

Slight

Insignificant

1, 8, 9, 10, 15

1, 15

Insignificant

Insignificant

Insignificant

LR3.3c

Roadside Planting along Kai Cheung Road and Interchange

Medium

Large

Large

Substantial

Moderate

1, 8, 9, 10, 13 15

1, 15

Moderate

Slight

Insignificant

LR3.3d

Roadside Planting along Kai Fuk Road

Medium

Small

Small

Slight

Slight

1, 8, 9, 10, 15

1, 15

Slight

Insignificant

Insignificant

LR3.3e

Roadside Planting along Kai Cheung Road, Wang Kwong Road and Wang Chiu Road

Medium

Small

Negligible

Slight

Insignificant

1, 8, 9, 10, 15

1, 15

Slight

Insignificant

Insignificant

LR3.5a

Disturbed Area within former Kai Tak Airport

Low

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Slight beneficial

Slight beneficial

LR3.8a

Man-made Shoreline of West Kowloon Bay

Medium

Small

Negligible

Slight

Insignificant

1, 8, 9, 10, 13, 15

1, 14, 15

Slight

Slight beneficial

Slight beneficial

LR3.8b

Man-made Shoreline around former Kai Tak Airport

Low

Small

Negligible

Slight

Insignificant

1, 8, 9, 10, 13, 15

1, 14, 15

Slight

Slight beneficial

Slight beneficial

LR3.9a

Kowloon Bay

Medium

Large

Negligible

Slight

Insignificant

1

n/a

Insignificant

Insignificant

Insignificant

LR3.9b

Kai Tak Nullah

Medium

Small

Small

Slight

Slight

1, 15

1

Insignificant

Insignificant

Insignificant

Note – Full details of mitigation measures are provided in Section 10.10 but summary titles are:

MM1      Detailed Design - Landscape. 

MM2      Detailed Design - Visual. 

MM3      Good Site Management. 

MM4      Screen Hoarding. 

MM5      Lighting Control during Construction.

MM6      Erosion Control. 

MM7      Not used

MM8      Tree Protection & Preservation

MM9      Tree Transplantation –

MM10    Compensatory Planting

MM11    Screen Planting

MM12    Green Roof

MM13    Reinstatement

MM14    Re-provisioning of Public Open Space

MM15    Landscape enhancement

MM16    Lighting Control during Operation


Table 10.10: Significance of Impact on LCAs, both before and upon Mitigation

 

 

 

 

 

 

 

 

 

 

 

 

LCA Code

Name

LCA Sensitivity (High/ Medium/ Low)

Magnitude of Change (Large/ Intermediate/ Small/ Negligible

Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/ Insignificant)

Recommended Mitigation Measures

Residual Impact Significance UPON Mitigation (Significant/ Moderate/ Slight/ Insignificant)

 

 

 

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation Day 1

Operation Year 10

 

West Portion

 

 

 

 

 

 

 

 

 

 

LCA1.1

Transportation Corridor Landscape

(West Portion)

Medium

Large

Large

Substantial

Moderate

1, 8, 9, 10, 13, 15

1, 15

Moderate

Slight

Insignificant

LCA1.2

Ongoing Major Development Landscape (West Portion & Barging Point)

Medium

Small

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Slight

Insignificant

Insignificant

LCA1.3

City Grid Mixed Urban Landscape

(West Portion)

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9 ,10, 14, 15

1, 14, 15

Slight

Insignificant

Insignificant

LCA1.4

Residential Complex Landscape

Medium

Negligible

Negligible

Insignificant

Insignificant

n/a

n/a

Insignificant

Insignificant

Insignificant

LCA1.5

Residential Urban Landscape (West Portion)

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9 ,10, 14, 15

1, 14, 15

Slight

 

 

LCA1.6

Typhoon Shelter Landscape (West Portion & Barging Point)

Low

Small

Negligible

Slight

Insignificant

n/a

n/a

Slight

Insignificant

Insignificant

 

Central Portion

 

 

 

 

 

 

 

 

 

 

LCA2.1

Residential Urban Landscape (Middle)

Medium

Negligible

Negligible

Insignificant

Insignificant

n/a

n/a

Insignificant

Insignificant

Insignificant

LCA2.2

Miscellaneous Urban Fringe Landscape

Medium

Intermediate

Intermediate

Moderate

Moderate

1, 8, 9 ,10, 13, 14 ,15

1, 15

Slight

Slight

Insignificant

 

East Portion

 

 

 

 

 

 

 

 

 

 

LCA3.1

City Grid Mixed Urban Landscape

(East Portion)

Medium

Small

Negligible

Slight

Insignificant

1, 8, 9 ,10, 14, 15

n/a

Slight

Insignificant

Insignificant

LCA3.2

Ongoing Major Development Landscape (East Portion)

Medium

Large

Intermediate

Moderate

Moderate

1, 8, 9, 10, 13, 15

1, 15

Slight

Slight

Insignificant

LCA3.3

Industrial Urban Landscape

Low

Negligible

Negligible

Insignificant

Insignificant

n/a

n/a

Insignificant

Insignificant

Insignificant

LCA3.4

Typhoon Shelter Landscape (East Portion)

Medium

Intermediate

Negligible

Moderate

Insignificant

1

n/a

Moderate

Insignificant

Insignificant

LCA3.5

Transportation Corridor Landscape

(East Portion)

Medium

Intermediate

Small

Moderate

Slight

1, 8, 9, 10, 13, 15

1, 15

Moderate

Slight

Insignificant

Note – Full details of mitigation measures are provided in Section 10.10 but summary titles are:

MM1      Detailed Design - Landscape. 

MM2      Detailed Design - Visual. 

MM3      Good Site Management. 

MM4      Screen Hoarding. 

MM5      Lighting Control during Construction.

MM6      Erosion Control. 

MM7      Not used

MM8      Tree Protection & Preservation

MM9      Tree Transplantation –

MM10    Compensatory Planting

MM11    Screen Planting

MM12    Green Roof

MM13    Reinstatement

MM14    Re-provisioning of Public Open Space

MM15    Landscape enhancement

MM16    Lighting Control during Operation

 

 


10.10              Landscape and Visual Mitigation Measures

During the current landscape and visual impact assessment, mitigation measures to avoid, reduce or remedy impacts have all been considered, with highest priority given to impact avoidance and reduction. The mitigation measures proposed are not only concerned with damage reduction but also include consideration of potential enhancement of the existing landscape.

At the Project design stage, many factors have already been considered to avoid or reduce potential landscape and visual impacts. The exact route of the CKR and locations of above ground structures including connection roads and ventilation and administration buildings, have been carefully considered against key constraints and opinions, taking into account potential LVIA impacts amongst other factors. Similarly the necessity for the underwater tunnel between Ma Tau Kok with KTD and its construction method has also been carefully considered, against key constraints and opinions, current legislation and taking into account potential LVIA impacts amongst other factors.

As well as design mitigation measures, measures to reduce and/or compensate for particular unavoidable impacts during the construction and/or operation of the Project are also proposed. Certain measures should be adopted during the detailed design and be built as part of the construction works so that they are in place at the date of commissioning of the project and in place during the operational life of the Project. Other measures should be adopted from the commencement of construction and remain in place throughout the entire construction period. 

Generally, mitigation measures should be implemented as early as possible. Mitigation measures have not been assigned as ‘design’, ‘construction’ or ‘operation’ mitigation measures due to their often encompassing different phases of the Project. For example although soft landscape mitigation measures may be implemented during construction, their full effect will often not be appreciated for 10 years. Equally detailed design measures may reduce construction impacts but will also reduce operation impacts. 

Specific design consideration and principles for the Project are outlined below while the proposed landscape and visual mitigation measures for the detailed design, construction and operation of the Project are given in Section 10.10.2.

 

10.10.1        Specific Design Considerations

Compatibility with the Surrounding Environmental and Development Characters

New structures must be designed to be compatible with their surroundings e.g. the western connection bridges must be designed to match the existing flyovers in Yau Ma Tei Interchange. 

In the East Portion, design considerations have taken into account the Kai Tak Development (KTD) design to ensure the two projects integrate well together. Considerations specific to this area are listed in Section 10.5.3. 

Creating a Comprehensive Green Network

CEDD’s ‘Greening Master Plan’ (GMP) should be used as a guideline to creating a comprehensive green network in all three above ground areas. In the West, the GMP suggests a ‘Coastal Scenery’ theme around Yau Ma Tei to tie in with the West Kowloon waterfront character and a ‘Green Kaleidoscope’ theme for the core Mong Kok area using a variety of planting designs and species to enhance the environment and reinforce existing landmark characters.

A significant number of trees and greenery will be provided around ventilation and administration buildings. For trees unavoidably affected by the Project that have to be removed, where practical, transplantation will be chosen as the top priority method of removal but if this is not possible or practical (e.g. the tree is too large or has a low survival rate) compensatory planting will be provided for trees unavoidably felled. While most of this will be on-site compensation, some off-site compensation will be required from felling in all sections as detailed further in Table 10.11.

Landscape decks can be used to beautify the area and provide additional greening space.  One landscape deck is provided in the West Portion (also serving as a noise barrier) and another in the East Portion over the depressed road.

Public Open Space

Affected open space is all in the West Portion and impacts are due to the construction of cut-and-cover tunnel and connecting road. All areas of public open space affected by the Project will be re-provisioned either at the same location following the completion of temporary works, or at a separate site, as agreed with relevant Government departments as detailed further in Table 10.11.

Preservation of Cultural Heritage

Efforts must be made to ensure structures of cultural heritage are preserved e.g. the YMT Police Station in the West Portion with its neo-classical architecture is the oldest police station in an urban context that still survives in Hong Kong and gives an indication of the original coast line. The community also apparently feel strong bond to the building. Therefore efforts have been made to conserve the building, which will be decanted prior to construction and used for other purposes once CKR is operational.

Duration of Construction

Design measures must take into account the duration of their construction and should be kept to a practical minimum to reduce landscape and visual impacts.

Minimising Impact of the Underwater Tunnel Construction

The length of the temporary reclamation proposed is the minimum because the alignment of the underwater tunnel follows the shortest path connecting Ma Tau Kok with KTD taking into the need to avoiding resumption of private properties and making effective connection with the road network in KTD.  The area of the temporary reclamation will be split into Stage 1 and 2 and will be 1.8 ha and 2.0 ha respectively and will be the minimum extent of reclamation required for constructing the underwater tunnel according to experience acquired in constructing the underwater tunnel of the Central-Wan Chai Bypass in Causeway Bay Typhoon Shelter. 

 

10.10.2        Proposed Landscape and Visual Mitigation Measures

Table 10.11 below details the proposed landscape and visual mitigation measures for the Project during construction and operation and indicates the Funding, Implementation, Management and Maintenance agencies for each measure. Landscape Mitigation Plans are shown in Figure 10.11, Figure 10.12 and Figure 10.13.

 


Table 10.11:  Proposed Landscape and Visual Mitigation Measures

 

Id No.

Landscape and Visual Mitigation Measure

Funding Agency

Implementation Agency

Maintenance/ Management Agency

MM1

Detailed Design - Landscape. All works shall be carefully designed to minimize impacts on existing landscape resources and visually sensitive receivers, particularly those of high value or high sensitivity.  For this purpose, the extent of the works area will be minimised and existing trees within the works area shall be avoided were practicable.

 

Designs which ensure the construction time frame is kept to a practical minimum should also be considered. 

 

HyD

HyD’s Contractor

n/a

MM2

Detailed Design - Visual. Tunnel portals and all structures above ground including noise barriers shall be sensitively designed with colour, texture and tonal quality being compatible with the existing urban context. 

 

The ‘natural terrain’ idea will be applied to the design of ventilation and administration buildings.

 

For noise barriers/ enclosures, the colour of the structural frames and the frame of the glazing panels shall give a natural look and match with the colour of the adjacent buildings in the area.

 

Designs which ensure the construction time frame is kept to a practical minimum should also be considered. 

 

HyD

HyD

Building proponent/ HyD

MM3

Good Site Management. Large temporary stockpiles of excavated material shall be covered with unobtrusive sheeting to prevent dust and dirt spreading to adjacent landscape areas and vegetation, and to create a neat and tidy visual appearance.
Construction plant and building material shall be orderly and carefully stored in order to create a neat and tidy visual appearance.

 

HyD

HyD’s Contractor

n/a

MM4

Screen Hoarding. Decorative screen hoarding should be erected to screen the public from the construction area.  It should be designed to be compatible with the existing urban context.

 

HyD

HyD’s Contractor

n/a

MM5

Lighting Control during Construction. All lighting in the construction site shall be carefully controlled to minimize light pollution and night-time glare to nearby residencies and GIC. The contractor shall consider other security measures, which shall minimize the visual impacts.

 

HyD

HyD’s Contractor

n/a

MM6

Erosion Control. The potential for soil erosion shall be reduced by minimizing the extent of vegetation disturbance on site and by providing a protective cover over newly exposed soil.

 

HyD

HyD’s Contractor

n/a

MM7

Not used

 

 

 

MM8

Tree Protection & Preservation. Exiting trees to be retained within the Project Site should be carefully protected during construction. Note no Registered Old and Valuable Trees are located within Works Area and none of the affected trees are LCSD champion Trees or Registered Old and Valuable Trees, neither are they rare or endangered species, but mainly common exotic trees. Tree protection measures will be detailed at the Tree Removal Application stage and plans submitted to the relevant Government Department for approval in due course in accordance with ETWB TC no. 3/2006. Care should be taken to preserve as many trees as possible by avoidance (also see MM1). 

 

HyD

HyD’s Contractor

n/a

MM9

Tree Transplantation.  For trees unavoidably affected by the Project that have to be removed, where practical transplantation will be chosen as the top priority method of removal. If this is not possible or practical (e.g. the tree is too large or has a low survival rate) compensatory planting will be provided for trees unavoidably felled (See MM10). For trees unavoidably affected by the Project works that are transplanted, transplantation must be carried out in accordance with ETWBTC 2/2004 and 3/2006.

 

According to the 2010 Tree Survey, of the 2812 trees surveyed, approximately 163 trees affected by the Project are suitable for transplantation and onsite planting sites were identified for these trees. Due to Project re-alignment, other projects development (e.g. XRL) and the updated Tree Survey due to be carried out in mid 2013, however, the numbers of trees affected by the Project has been reduced, particularly in the West Portion and therefore the number of trees that will require transplanting may reduce also. Since final numbers have not been confirmed, a worst case scenario of approximately 160 trees requiring transplantation is estimated.

 

HyD

HyD’s Contractor

HyD/LCSD

MM10

Compensatory Planting. For trees unavoidably affected by the Project that have to be removed, where practical transplantation will be chosen as the top priority method of removal but if this is not possible or practical (e.g. the tree is too large or has a low survival rate) compensatory planting will be provided for trees unavoidably felled. All felled trees shall be compensated for by planting trees to the satisfaction of relevant Government departments. Required numbers and locations of compensatory trees shall be determined and agreed separately with Government during the Tree Felling Application process under ETWBTC 3/2006. 

Compensatory tree planting may be incorporated into public open spaces and along roadside amenity areas affected by the construction works and therefore be part of the wider planting plans.

 

According to the 2010 Tree Survey, 2,401heavy standard trees with 80mm DBH trees would have been required to compensate for the loss of about 1141 trees with 192,030mm total DBH that would have been felled by the Project.  This allowed for 1:1 DBH compenstation ratio and 1:2 quantity compensation ratio. If 100mm (rather than 80mm) DBH heavy standard trees are used for compensatory planting, just 1,921 trees would be required for compensatory planting rather than 2,401.

 

Due to Project re-alignment, other projects development (e.g. XRL) and the updated Tree Survey due to be carried out in mid 2013, the numbers of trees affected by the Project has been reduced, particularly in the West Portion. Although the final treatment of trees numbers will be subject to the final Tree Felling Application, it is now estimated that approximately 300 trees that were previously due to be felled, will no longer be affected by the Project..

 

Assuming a 5 m centre to centre spacing for planting 100mm DBH heavy standard trees, an approximate area of 21 m2 is required for each compensatory tree. It has been estimated that each area is able to absorb the following number of compensatory trees and transplanting trees:East Portion - 505 in KTD and 75 in Ma Tau Kok; Central Portion area – 26; West Portion – 765 i.e. TOTAL 1371.

 

In the worst case scenario (using 2010 Tree Survey Report felling number) this approximate calculation estimates it will be necessary to agree additional receptor sites for approximately 550 compensatory trees, but given the reduction in felled trees in the West Portion, this number is likely to reduce.   

 

HyD

HyD

HyD/LCSD (LCSD for roadside planting)

MM11

Screen planting.  Tall screen/buffer trees, shrubs and climbers should be planted, in so far as is possible, to soften and screen proposed structures such as roads and central strip, vertical edges and buildings and to enhance streetscape greening effect where appropriate.  Indiscriminate selection of tree species for screening should be avoided and the principle of ‘right tree for the right place’ followed.  This detail will be provided at the Detailed Design stage.

This measure may additionally form part of the compensatory planting and will improve and create a pleasant pedestrian environment.

 

HyD

HyD

HyD/LCSD

MM12

Green Roof.  Roof greening will be established on ventilation and administration buildings to reduce exposure to untreated concrete surfaces and particularly mitigate visual impact to VSRs at high levels.

 

HyD

HyD

Building proponent

MM13

Reinstatement.  All works areas, excavated areas and disturbed areas for tunnel construction and temporary road diversion or any other proposed works shall be reinstated to former conditions or better, with reasonable landscape treatment and to the satisfaction of the relevant Government departments.  (Specific mitigation for disturbance to public open space is detailed separately under MM14).

HyD

HyD

Relevant Government departments

MM14

Re-provising of Public Open Space.  All areas of public open space affected by the Project will be re-provisioned either at the same location following the completion of temporary works, or at a separate site, as agreed with relevant Government departments.  Open space should be re-provisioned in an enhanced manner.

 

Under the proposed development, approximately 980 m2 of Public Square Street Playground (LR1.1a), 1,400m2 of Shanghai Street / Market Street Playground (LR1.1b), 310m2 of the Bazaar (LR1.1c), and 365m2 of Temple Street / Kansu Street Temporary Rest Garden (LR1.1d) will be temporarily closed and affected during the construction stage. Following construction, the same areas affected will be re-provisioned in situ for the Public Square Street Playground (LR1.1a) and Temple Street / Kansu Street Temporary Rest Garden (LR1.1d).  Similarly the same area of the Shanghai Street / Market Street Playground (LR1.1b) and of the Bazaar (LR1.1c) will be re-provisioned/ reinstated. The Yau Ma Tei Jade market (LR1.1e Jade Hawker Bazaar) will be demolished during construction, re-sited to a temporary location and ultimately reinstated back at its original location, underneath the alignment. In addition some new open space areas are proposed; the original Yau Ma Tei Specialist Clinic Extension Site and Proposed Yau Mau Tei Landscape Deck are both new public open spaces, such that overall more public open space will be re-provisioned/ reinstated than is taken during construction. 

 

Summary of Public Open Space Landscape Resource Affected

ID

Landscape Resource Affected

Approx. Existing Area

Approx. Area taken during Construction

Approx. Area to be
re-provisioned / reinstated

LR1.1a

Public Square Street Playground

980  m2

980  m2

980  m2

LR1.1b

Shanghai Street / Market Street Playground

1,400 m2

1,400 m2

1,400 m2

LR1.1c

Jade Hawker Bazaar (West)

310 m2

310 m2

310 m2

LR1.1d

Temple Street / Kansu Street Temporary Rest Garden (Currently zoned as G/IC)

365 m2

365 m2

365 m2

LR1.1e

Ya Ma Tei Jade Market/ Jade Hawker Bazaar

1,395 m2

1,395 m2

1,395 m2

Summary of Proposed New Open Space

Item no.

Proposed Open Space

Approx. Area

1

Proposed open space at the original Yau Ma Tei Specialist Clinic Extension site

710 m2

2

Proposed Yau Ma Tei Landscape Deck

31,000 m2

Total

 

31,710 m2

HyD

HyD

LCSD / ArchSD (Hard landscape works)

MM15

Landscape Enhancement.  Implement a comprehensive landscape plan to maximize the greening opportunity and create a unique landscape for the project to blend in with the surrounding, including in re-provisioned areas. In particular,:

-          landscape enhancement of re-provisioned Public Transport Interchange;

-          landscape deck on tunnel portals;

-          viaduct planters for trailer planting,

-          vertical greening of piers and walls with climbers or trailer planting;

-          roadside planting i.e. planting along central dividers and on road islands e.g. in the middle of roundabouts. 

(Roadside planting i.e. at the road edge and not in the central divider or road island, and vertical greening may be considered part of Screen Planting)

 

Purpose-built maintenance access without temporary traffic arrangement must be provided and detailed design of landscape decks and planting, including details of maintenance access locations, will be sent to maintenance and management parties for endorsement and ensures these mitigation measures are feasible. 

 

 

HyD

HyD

Contractor/ Other Government Departments. E.g. HyD, LandsD, LCSD (1)

 

MM16

Lighting Control during Operation.  Roadside lighting and that at the ventilation and administration buildings should be controlled so as to minimize the visual impacts at night. For the enclosed noise barriers, lighting will be provided by two rows of continuous fluorescent lights mounted along the ceiling of the noise enclosure so drivers see continuous lines on the ceiling..

HyD

HyD

HyD

 

 

 

 

 

(1)

Contractor responsible during the agreed establishment and maintenance period.  Other designated management & maintenance agents to take up maintenance and management of landscaping after end of agreed period, as guided by ETWB TC(W) No. 2/2004 ‘Maintenance of Vegetation and Hard Landscape Features’ i.e. HyD within the boundary of expressways; LandsD on unallocated/unleased Government land not maintained by other departments; LCSD along non-expressway public roads. 


10.10.3        Cumulative Landscape Impact

West Portion

Part of the works area at the west of tunnel portal is interfaced with proposed tunnel works and ventilation building of Express Rail Link (XRL). As the construction methods of XRL are similarly by cut and cover tunnel, the potential impacts on existing landscape resources will be the similar. There is also a barging point at Kwai Chung currently being used by XRL which is proposed to remain as a barging point for CKR. XRL project construction started in January 2010, prior to CKR and a number of trees within the works area that is currently XRL but will be handed over to CKR in January 2015, have already been removed for the XRL project. Landscape impacts due to the CKR Project in this area are therefore reduced. 

Central Portion

Works area for Central Portion is not interfaced with nearby major development such as Kwun Tong Line Extension. Therefore, no cumulative landscape impact is anticipated.

East Portion

Part of the works area within To Kwa Wan and former Kai Tak Airport are interfaced with KTD. The impact on existing landscape recourses will be the same during the construction period and will be enhanced during the operation period.

The KTD project commenced in 2009 with completion of the project beyond 2020 in seven packages. CKR will be commissioned earlier.

 

10.11              Visual Impact Assessment

10.11.1        Potential Sources of Visual Impact

Visual impacts may be caused by various factors during construction and operation and these are similar to sources of landscape impacts as described in Section 10.9.1.  In addition to the landscape impacts described in Section 10.9.1, additional potential sources of visual impact are described below:

From Construction Site & Operation

·               Noise barriers, in the form of noise enclosures, semi-enclosures, cantilever and vertical barriers;

·               Temporary traffic and road diversions;

·               Temporary construction traffic;

·               Night time lighting;

·               Dust during dry weather. 

10.11.2        Magnitude of Change

Some details regarding the impacts experienced by VSRs in each section are provided below and the magnitude of change on each of the VSRs that were listed in the Baseline Study (Section 10.8), are provided in Table 10.12. 

Regarding the compatibility of the Project with the surroundings, this has been discussed in Section 10.9.2.  The Project is generally thought to be compatible with the surroundings during operation and less so during the site formation, demolition and construction works and this is not repeated in the Table 10.12.  Largely because of this, visual impacts are often considered more severe during construction compared to operation and this is also reflected Table 10.12.

All 13 VPs are mapped in Figure 10.19 and also shown for each section in Figure 10.13 (West Portion), Figure 10.14 (Central Portion) and Figure 10.15 (East Portion).  Photomontages are provided in Figure 10.20, Figure 10.21, Figure 10.22, Figure 10.23, Figure 10.24, Figure 10.25, Figure 10.26, Figure 10.27, Figure 10.28, Figure 10.29, Figure 10.30, Figure 10.31 and Figure 10.32. 

West Portion

Prior to mitigation, visual impacts in this area are primarily because of the construction of connection road, cut and cover tunnel, ventilation building and the erecting noise barriers including a landscape deck.  During construction this will also involve impacts from excavation works, stockpiling of excavated materials; general work sites and works area, traffic diversions, obstruction of views arising from hoarding as well as the removal of trees, either by felling or transplanting which will also be an impact felt during operation. 

The re-provisioning of a short section of GRF before widening will be constructed and commissioned at about the same time as the demolition of Yau Ma Tei Carpark Building. As the re-provisioned section of GRF is only slightly shifted to the north of the existing alignment while maintaining the same number of lanes and height, there would be no additional visual impact to the construction and operation phase of CKR. The landscape and visual impact assessment of widening of GRF is subject to another EIA study under EIA study brief (ESB-155/2006).

In general, the closer the VSRs to the impacts, the larger the magnitude of change as there will be higher potential that views from these VSRs will be fully or partially blocked by the construction activities.

Photomontages for this area are shown in Figure 10.20, Figure 10.21, Figure 10.22, Figure 10.23 and Figure 10.24, taking into consideration other developments in the area, such as XRL and proposed GIC buildings.  They help illustrate the conclusions reached as to the severity of visual impacts both prior to mitigation, and following implementation of mitigation measures. 

Central Portion

The impacts in this area are primarily due to the construction of the ventilation building and access road, as well as the associated removal of trees, either by felling or transplanting. Temporary works sites and temporary noise mitigation measures, traffic diversions, and hoarding may also cause some obstruction of views.

Similarly, to in the West Portion, the closer the VSRs to the impacts, the more likely that visual impact will be significant, although this is not necessarily true with viewers at lower levels whose views to the Project Site are sometimes blocked by vegetation and/or existing structures whereas viewers at higher elevations further from the site may have more open views to it.

Photomontages for this area are shown in Figure 10.25, Figure 10.26 and Figure 10.32 and help illustrate the conclusions reached as to the severity of visual impacts both prior to mitigation, and following implementation of mitigation measures. 

East Portion

The impacts in this area are primarily due to the construction of all above ground structures including the depressed road and other connection roads, landscape decks, ventilation and administration building, tunnel portals, cut and cover tunnel, and works associated with building the underwater tunnel.  During construction this will also involve impacts from excavation works, excavated material stockpiles, as well as the associated removal of trees, either by felling or transplanting. In addition the temporary works sites, temporary noise mitigation measures, traffic diversions and hoarding may obstruct views.

As per the other areas, the closer the VSRs to the impacts, the more likely that visual impact will be significant, although this is not necessarily true with viewers at lower levels whose views to the Project Site are sometimes blocked by vegetation and/or existing structures whereas viewers at higher elevations further from the site may have more open views to it.

In addition, in the East Portion some VSRs will lose their views to the CKR site once KTD has been fully built, so significance of visual impacts may change over time.

Photomontages for this area are shown in Figure 10.27, Figure 10.28, Figure 10.29, Figure 10.30 and Figure 10.31 and take into consideration the complex ongoing development at Kai Tak.  They help illustrate how the CKR integrates with the KTD and support the conclusions reached as to the severity of visual impacts both prior to mitigation, and following implementation of mitigation measures. 


Table 10.12 Magnitude of Change on VSRs

 

VSR Code

Type of VSRs

VSR Name

Approx. Min Distance between VSR & Impact Sources (Road/ Building) (m)

Scale of the Development (Small, Medium, Large)

Description of Key Impacts

Duration of Impacts (Construction/ Operation)

Potential Blockage of View (Full/Partial/Nil)

Reversibility of Change (Construction/ Operation)

Magnitude of Change
(Negligible / Small / Intermediate / Large)

Construction

Operation

West Portion

R1.1

Residential

One SilverSea

750/ 920

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building and connection roads will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R1.2

Residential

Island Harbourview

620/ 800

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building and connection road will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R1.3

Residential

Park Avenue

130/ 400

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building and connection roads will be visible but since the ventilation building is particular is distant, the new developments will form part of the view rather than block it;
• Although some residents at high levels facing the Project Site will have full views of it, for many facing the right direction, their views of the Project Site will be blocked by other buildings such as Charming Garden (R1.4) and their views will not be adversely affected.
• Although this VSR Group is near the connecting road alignment, they are at least 400 m from the proposed ventilation building.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R1.4

Residential

Charming Garden

200/ 300

Medium

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible and given their proximity, will be noticeable in their current view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

R1.5

Residential

Wah Tak Building & Tak Cheong Lane High Rise

250/ 540

Medium

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and, to a lesser degree, the ventilation building;
• The connection roads will be partially visible but they are far from the ventilation building with restricted view dominated by Ferry Street in the foreground and this element will not change their view to very much.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

R1.6

Residential

8 Waterloo Road

290/ 740

Medium

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and, to a lesser degree, the ventilation building;
• The connection roads will be partly visible but they are far from the ventilation building and this VSR has restricted views to the site so the Project will not change the view very much.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

R1.7

Residential

Prosperous Garden

240/ 560

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and, to a lesser degree, the ventilation building;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• Construction of fully enclosed noise barrier over Ferry Street;
• Construction of landscape deck;
• The enclosed noise barrier over Ferry Street, connection roads and tunnel portal will be highly visible due to their proximity to the site and will largely change their view, however this VSR group is distant to the ventilation building and this element will not change their view to such an extent and at operation the change is intermediate.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

R1.8

Residential

Kansu Street High Rise Buildings

0/ 720

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and, to a lesser degree, the ventilation building;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• The connection road and tunnel portal will be largely visible due to their proximity to the site and will largely change their view, in some cases blocking it.  They are distant to the ventilation building and this element will not change their view to such an extent but given they border the tunnel portal and connection road, the magnitude of change will remain large at operation.

Temporary/ Permanent

Full

Partly reversible/ Irreversible

Large

Large

R1.9

Residential

Man Cheong Building

150/450

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and, to a lesser degree, the ventilation building;


• The connection roads and tunnel portal will be visible due to their proximity to the site and will largely change their view, however the ventilation building is further away and beyond the Planned Public Open Space above the future XRL-terminus and this element will not change their view to such an extent.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

R1.10

Residential

Sorrento

270/ 480

Large

• Construction of cut and cover tunnel, tunnel portal, connection road and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible in their view and given their proximity, will party block their current view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

R1.11

Residential

The Coronation

30/ 320

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck, fully enclosed noise barrier over Ferry Street and the ventilation building;
• The connection roads, landscape deck, fully enclosed noise barrier over Ferry Street and tunnel portal will be highly visible due to the VSR's proximity to the site and will largely change their view.  The ventilation building will also change their view to an extent. Given they are so close to the tunnel portal, connection roads and landscape deck the impact will remain large at operation.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Large

R1.12

Residential

Planned Residential Development above Austin Station

360/ 680

Medium

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building, connection roads and tunnel portal will be in their view but since they are reasonably distant and will be viewing the site from higher levels, it will form part of the view rather than block it.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Small

R1.13

Residential

Victoria Towers

700/ 1120

Small

• Construction of cut and cover tunnel, tunnel portal, connection road and ventilation building;
• The ventilation building, connection roads and tunnel portal will be in their view but since they are very distant and view the site from higher levels, it will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R1.14

Residential

The Hermitage

500/ 680

Small

• Construction of cut and cover tunnel, tunnel portal, connection road and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible in their view but since they are very distant and view the site from higher levels, it will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C1.1

Commercial

Bank of China Tower

600/ 770

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building and connection road will be visible in their view but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C1.2

Commercial

HSBC Centre

560/ 750

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building and connection road will be visible in their view but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C1.3

Commercial

Eaton Hotel

170/ 1010

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads and, to a lesser degree, the landscape deck and ventilation building;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building;
• The connection road and tunnel portal will be fairly visible due to their proximity to this site and will change the view a little, however most rooms face north where the alignment will be underground and the ventilation building is distant so this element will not change the view very much.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C1.4

Commercial

ICC & Ritz Carlton Hotel

720/ 840

Small

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible in their view but since they are reasonably distant and will be viewing the site from higher levels, it will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C1.5

Commercial

Planned Commercial Development above XRL Terminus

240/ 570

Medium

• Construction of cut and cover tunnel, tunnel portal, connection road and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible in their view but since they are reasonably distant and will be viewing the site from higher levels, it will form part of the view rather than block it.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Small

C1.6

Commercial

Keybond Commercial Building

160/ 650

Medium

• Construction of cut and cover tunnel, tunnel portal, connection road and, to a lesser degree, the landscape deck and ventilation building;
• The connection roads and tunnel portal will be visible due to their proximity to the site and will change the view but views from this VSR to the site are restricted.  The ventilation building is further away, may be blocked by other buildings and additionally is beyond the Planned Public Open Space above the future XRL-terminus and the landscape deck is largely blocked by the Coronation.  Therefore these elements will not change their view much if at all.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

GIC1.1

Government/ Institution/ Community

Yau Ma Ti Catholic Primary School (Hoi Wang Road) & Li Kwok Po College

100/ 200

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and ventilation building;
• The ventilation building, connection roads and tunnel portal may be visible given their proximity, but the new GIC1.9 buildings are likely to block their current view to a larger extent, so the overall change from the Project is intermediate during construction (assuming GIC1.9 does not exist) and small during operation (assuming GIC1.9 is in existence).

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

GIC1.2

Government/ Institution/ Community

Hong Kong Community College West Kowloon Campus

50/ 280

Large

• Construction of cut and cover tunnel, connection roads, landscape deck, ventilation building and to a lesser degree the tunnel portal;
• The ventilation building, connection roads, landscape deck will be visible and given their proximity, will party block their current view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

GIC1.3

Government/ Institution/ Community

Yaumati Catholic Primary School (Tung Kun Street)

120/ 540

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck, fully enclosed noise barrier over Ferry Street and ventilation building;
• The ventilation building, connection roads and tunnel portal will be visible in their view and given their proximity, will party block their current view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

GIC1.4

Government/ Institution/ Community

Yau Ma Tei Division Police Station

0/ 610

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads and noise barriers;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• The connection roads, noise barriers and tunnel portal will be highly visible due to their proximity to the site and will largely change their view.  Given VSRs at this site will remain close to the tunnel portal and connection road alignment during operation, the change will remain large at operation.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Large

GIC1.5

Government/ Institution/ Community

Yau Ma Tei Jockey Club Polyclinic

0/ 700

Large

• Construction of cut and cover tunnel, tunnel portal and connection roads;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• The connection road and tunnel portal will be highly visible due to their proximity to the site and will largely change their view.  Given they partially fall within the tunnel portal and connection road alignment, the change will remain large at operation.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Large

GIC1.6

Government/ Institution/ Community

Henry G. Leong Yaumatei Community Centre

20/ 750

Large

• Construction of cut and cover tunnel, tunnel portal, and connection road;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• The connection road and tunnel portal will be highly visible due to their proximity to the site and will largely change their view. 

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

GIC1.7

Government/ Institution/ Community

Queen Elizabeth Hospital

240/1050

Medium

• Construction of cut and cover tunnel, tunnel portal, connection road and, to a lesser degree, the ventilation building;


• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building;

• The connection road and tunnel portal will be fairly visible from higher levels of this location and the view will change a little.  However this is not a high rise VSR and views to site are partial.  In addition the ventilation building is distant so this element will not change the view very much.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

GIC1.8

Government/ Institution/ Community

Civil Aid Services Headquarter

40/ 180

Large

• Construction of connection roads, noise barriers, landscape deck and the ventilation building;
• The ventilation building, connection roads with noise barriers and landscape deck will be visible and given their proximity, will party block their current view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

GIC1.9

Government/ Institution/ Community

Planned GIC Site

10/ 120

Large

• Construction of connection roads, noise barriers, landscape deck and the ventilation building;
• The ventilation building, connection roads with noise barriers and landscape deck will be visible to these future VSR and given their proximity, will party block the view that currently exists here.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

n/a

Intermediate

O1.1

Occupational

LPG Filling Station at Hau Cheung Street

10/ 310

Large

• Construction of connection roads, noise barriers (including full enclosure at Ferry Street), landscape deck and the ventilation building and to a lesser degree the cut and cover tunnel and tunnel portal;
• The connection roads, noise barriers and landscape deck will be highly visible due to their proximity to the site and will largely change their view.  The ventilation building will also change their view to an extent. Given they are so close to these elements the change will remain large at operation.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Large

RE1.1

Recreational

Olympic Plaza

130/ 340

Medium

• Construction of connection roads and ventilation building;
• The ventilation building and connection roads will be visible but since these VSRs only have partial views to site, are at ground level and the ventilation building in particular is distant, the magnitude of change at construction and operation is small.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

RE1.2

Recreational

Cherry Street Park

80/ 340

Medium

• Construction of connection roads and ventilation building;
• The ventilation building and connection roads will be visible but since these VSRs only have partial views to site, are at ground level and the ventilation building in particular is distant, the magnitude of change at construction and operation is small.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

RE1.3

Recreational

Public Square Street Rest Garden

0/ 580

Large

• Construction of cut and cover tunnel, tunnel portal, connection roads, landscape deck and to a lesser degree the ventilation building;
• The connection road alignment passes over this VSR, so their views will be largely changed during cut and cover work at construction but will be less impacted during operation, particularly given this VSR has clear views to the existing elevated Ferry Street which already partly blocks their view.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Intermediate

RE1.4

Recreational

Yau Ma Tei Community Centre Rest Garden

30/ 800

Large

• Construction of cut and cover tunnel, tunnel portal, and connection roads;
• Demolition of Yau Ma Tei Specialist Clinic Extension and Yau Ma Tei Car Park Building close by;
• Impacts from the connection roads and tunnel portal, despite being close by, will be partly shielded from view by the Henry G. Leong Yaumatei Community Centre.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

RE1.5

Recreational

Saigon Street Playground

90/ 800

Small

• Construction of cut and cover tunnel, tunnel portal and connection road and possibly the ventilation building to a lesser degree;
• The connection roads and tunnel portal will be visible due to their proximity but this VSR has limited views as many views to site are blocked by the YMT Electric Substation;
• The ventilation building is further away beyond the Planned Public Open Space above the future XRL-terminus and therefore will not change their view much, if at all.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

RE1.6

Recreational

Planned Public Open Space above future XRL-terminus and surrounding

0/ 120

Large

• This VSR is only due to come into existence after CKR is commissioned.
• The connection roads, landscape deck, tunnel portal and ventilation building will all be visible during operation and due to their proximity may cause intermediate change of view.

n/a / Permanent

Partial

n/a / Irreversible

n/a

Intermediate

RE1.7

Recreational

Planned Public Open space north of Yan Cheung Road

0/ 440

Large

• This VSR is only due to come into existence after CKR is commissioned.
• The connection roads, landscape deck, tunnel portal and ventilation building will all be visible during operation and due to their proximity may cause intermediate change of view.

n/a / Permanent

Partial

n/a / Irreversible

n/a

Intermediate

T1.1

Travel/ Transport Related

West Kowloon Highway

0/0

Large

• Construction of connection roads, landscape deck, ventilation building and to a lesser degree the cut and cover tunnel and portal;
• The ventilation building, landscape deck and connection roads will be visible but there is particular compatibility of this Project with travelling and this VSR's views are transient so the Project it will not block them.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

Central Portion

R2.1

Residential

15 Ho Man Tin Hill

460

Small

• Construction of the ventilation building;
• The ventilation building will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

R2.2

Residential

Ellery Terrace

330

Small

• Construction of the ventilation building;
• The ventilation building will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

R2.3

Residential

Ho Man Tin Estate King Man House

420

Small

• Construction of the ventilation building;
• The ventilation building will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

R2.4

Residential

Ho Man Tin Estate (High Rise Building Block)

150

Small

• Construction of the ventilation building;
• The ventilation building will be visible but partly blocked by other buildings in between and some existing vegetation.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R2.5

Residential

Ho Man Tin Estate

60

Small

• Construction of the ventilation building;
• The ventilation building will be highly visible due to its proximity.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Intermediate

R2.6

Residential

Carmel On The Hill

150

Small

• Construction of the ventilation building;
• The ventilation building will be visible in their view but partly blocked by other buildings in between.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R2.7

Residential

Chung Man Court

180

Small

• Construction of the ventilation building;
• The ventilation building will be visible but partly blocked by other buildings in between.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R2.8

Residential

Future Redevelopment of Ex-Valley Road Estate

300

Small

• Construction of the ventilation building;
• The ventilation building may just be visible to this VSR, although given the topography, this will only occur should the development be built to a very high level and/or the ventilation building reach above a certain height.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Small

R2.9

Residential

HK Polytechnic University Student Hostel Development

460

Small

• Construction of the ventilation building;
• The ventilation building will be visible but since they are distant, will form part of the view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

R2.10

Residential

Oi Man Estate

80

Small

• Construction of the ventilation building;

• The ventilation building will just be visible over existing vegetation and the existing reservoir, to residents at higher levels, but will integrate into the existing view rather than block it.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

GIC2.1

Government/ Institution/ Community

Ho Man Tin Government Offices

60

Small

• Construction of the ventilation building;
• The ventilation building will be highly visible due to its proximity.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Intermediate

GIC2.2

Government/ Institution/ Community

SKH Tsoi Kung Po Secondary School

30

Small

• Construction of the ventilation building;
• The ventilation building will be highly visible due to its proximity.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

large

Intermediate

GIC2.3

Government/ Institution/ Community

Housing Authority Headquarters

35

Small

• Construction of the ventilation building;

• The ventilation building will be highly visible due to its proximity.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Intermediate

GIC2.4

Government/ Institution/ Community

Housing Authority Mock-up Centre

60 (but within a separate works area)

Small

• Construction of the ventilation building;
• Use of this GIC site as a works area during construction will largely change the views for these VSRs;
• At operation, the ventilation building will be visible but partly blocked by vegetation and natural topography.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

RE2.1

Recreational

Ho Man Tin East Service Reservoir Playground

260

Small

• Construction of the ventilation building;

• Use of the Housing Authority Mock-up Centre as temporary storage area during construction;

• At operation, the ventilation building will be visible but largely blocked by vegetation surrounding the reservoir.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

RE2.2

Recreational

Sheung Lok Street Garden

40

Small

• Construction of the ventilation building;
• The ventilation building is unlikely to be visible in their view but during construction, some of the works may be visible.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

T2.1

Travel/ Transport Related

Fat Kwong Street (near Project Site)

25

Small

• Construction ventilation building;
• The ventilation building will be visible in their view but largely blocked by vegetation on the planted slopes, which will largely screen the new building.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

T2.2

Travel/ Transport Related

Chung Hau Street and Good Shepherd Street (near Project Site)

15

Small

• Construction ventilation building;
• The ventilation building will be visible in their view but largely blocked by vegetation on the planted slopes, which will largely screen the new building.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

East Portion 

R3.1

Residential

Wyler Gardens

540/ 960

Large

• Construction of cut and cover tunnel, temporary reclamation and PTI reinstatement which these VSRs are right next to.
• Across the water, construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operations, the cut and cover will no longer be visible and the PTI reinstated;
• The views of the tunnel portal, depressed road, ventilation and buildings and connecting roads will integrate with KTD and not cause a large change in view in themselves.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

R3.2

Residential

Grand Waterfront

350/ 780

Large

• Construction of cut and cover tunnel, temporary reclamation and PTI reinstatement which these VSRs are right next to.
• Across the water, construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operations, the cut and cover will no longer be visible and the PTI reinstated;
• The views of the tunnel portal, depressed road, ventilation and buildings and connecting roads will integrate with KTD and not cause a large change in view in themselves.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

R3.3

Residential

Sky Tower

740/ 980

Medium

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• The views of these elements will integrate with KTD at operation and ultimately be blocked by the proposed Multi Purpose Stadium Complex proposed at KTD, so CKR structures in themselves will not cause a large change in view.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R3.4

Residential

High Rise Developments along Prince Edward Road West (Including Padek Palace; New Development on Nga Tsin Long Road; Prince Ritz; Tung Sing Court)

1060/ 1100

Small

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• The views of these elements will integrate with KTD at operation and these VSRs will have limited, if any, views to the CKR development structures as they will be blocked by such structures as the planned commercial development (C3.9) and planned residential developments (R3.8) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

R3.5

Residential

High Rise Developments along Prince Edward Road East (Carlson Court; Billionaire Royale and Le Billionaire; New Development on Lok Sin Road; The Latitude; Rhythm Garden)

1000/ 1100

Small

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;

• The views of these elements will integrate with KTD at operation and these VSRs will have limited, if any, views to the CKR development structures as they will be blocked by such structures as the planned commercial development (C3.9) and planned residential developments (R3.8) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

R3.6

Residential

Choi Hung Estate

1060/ 1350

Small

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;

• The views of these elements will integrate with KTD at operation and these VSRs will have limited, if any, views to the CKR development structures as they will be blocked by such structures as the planned commercial development (C3.9) and planned GIC developments (GIC3.2) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

R3.7

Residential

Richland Gardens

640/ 900

Medium

• Residents at higher levels will have views to the construction of the ventilation and administration buildings and connecting roads as well as the tunnel portal and depressed road to a lesser degree in the distance;
• The views of these elements will integrate with KTD at operation and these VSRs' views to the CKR development structures will be partly blocked by such structures as the planned residential developments (R3.9) and GIC developments (GIC3.2) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R3.8

Residential

Planned Residential Development in Kai Tak

120/ 220

Large

• Once built, residents at higher levels may have views to the ventilation and administration buildings and connecting roads in the foreground and possibly the tunnel portal and depressed road in the distance;
• At operation, the views of these elements will integrate with KTD and the proposed Multi Purpose Stadium Complex (RE3.2) and proposed GIC structures (GIC3.2) in Kai Tak will partly or totally block many of these VSRs' views to CKR structures.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Intermediate

R3.9

Residential

Sunrise Villa and New Residential Development at 9 Yuk Yat Street

780/ 1200

Small

• Unlike residents in Wyler Gardens, residents at high levels of this VSR have their view to the cut and cover tunnel works to its north blocked by other buildings and mainly face towards the KTD south apron
• Key impacts will be from construction of the  tunnel portal, depressed road;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

R3.10

Residential

Laguna Verde Complex and Harbourfront Landmark

1300/ 1800

Small

• Residents of this VSR facing north have their panoramic views to the construction of the  tunnel portal, depressed road, ventilation and administration buildings and connecting roads in the Kai Tak area;
• They will also view changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic in the distance;
• The may also have limited views of construction of the cut and cover tunnel works and PTI reinstatement;
• Since this VSR is so far from the Project Site, the changes make up a small part of their view and impacts will be small;
• At operation, their views of CKR elements will also integrate with KTD.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

CR3.1

Commercial/ Residential

Comprehensive Development Area around Ma Tau Kok Road (photograph at Hing Yan Street)

340/ 740

Medium

• Construction of the tunnel portal, temporary reclamation, depressed road and to a lesser degree the ventilation and administration buildings and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operation, views of CKR elements in Kai Tak will be blocked for some of these viewers by the proposed Multi Purpose Stadium Complex.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

CR3.2

Commercial/ Residential

Planned Commercial/ Residential Development in Kai Tak

740/ 880

Small

• Once built, views in these developments will be affected by the operation of the connecting roads;
• They may also have distant views the ventilation and administration buildings, depressed road and tunnel portal but once development in KTD area is complete, these views will be largely screened by other buildings and the connecting roads to the east will blend with the existing.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Small

C3.1

Commercial

Newport Centre (partly in CDA of OZP)

300/ 640

Medium

• Construction of the tunnel portal, temporary reclamation, depressed road close by across the water and to a lesser degree the ventilation and administration buildings and connecting roads in the distance;

• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;

• At operation, views of CKR elements will integrate into KTD and may be blocked or not be prominent.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.2

Commercial

Kapok Industrial Building

520/ 960

Large

• Construction of cut and cover tunnel, temporary reclamation and PTI reinstatement which these VSRs are right next to.
• Across the water, construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operations, the cut and cover will no longer be visible and the PTI reinstated;
• The views of the tunnel portal, depressed road, ventilation and buildings and connecting roads will integrate with KTD and not cause a large change in view in themselves.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

C3.3

Commercial

Kam Fai Commercial Building and Regal Oriental Hotel Hong Kong

960/ 1060

Small

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• The views of these elements will integrate with KTD at operation these VSRs will have limited, if any views, to the CKR development structures as they will be blocked by such structures as the planned commercial development (C3.9) and planned residential developments (R3.8) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

C3.4

Commercial

Tai King Industrial Building

1000/ 1200

Small

• Residents at higher levels will have views to the construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• The views of these elements will integrate with KTD at operation these VSRs will have limited, if any views, to the CKR development structures as they will be blocked by such structures as the planned commercial development (C3.9) and planned residential developments (R3.8) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Negligible

C3.5

Commercial

Skyline Tower

120/ 500

Medium

• Viewers at higher levels will have views to the construction of the ventilation and administration buildings and connecting roads and may be able to see the tunnel portal and depressed road construction to a lesser degree in the distance;
• This VSR also has views of Kai Cheung Road nearby, which will be within the works area during construction;
• Views of CKR elements will integrate with KTD at operation and this VSR's views of them will be largely blocked by such structures as the planned GIC developments (GIC3.1 and GIC3.2) in Kai Tak.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.6

Commercial

Enterprise Square II; Enterprise Square

150/ 600

Small

• For viewers at higher levels, main impacts will be from construction of the connecting roads and the ventilation and administration buildings in the distance;
• The connecting roads will affect this VSR most, being closest, but will blend well with the existing view of Kwun Tong Bypass;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.7

Commercial

Enterprise Square V and MegaBox; Enterprise Square III; Manhattan Place

100/ 780

Small

• For viewers at higher levels, main impacts will be from construction of the connecting roads and the ventilation and administration buildings in the distance;
• The connecting roads will affect this VSR most, being closest, but will blend well with the existing view of Kwun Tong Bypass;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.8

Commercial

Hong Kong International Trade & Exhibition Centre

10/ 180

Large

• Viewers at higher levels will have views to the construction of the ventilation and administration buildings and connecting roads and the tunnel portal and depressed road construction to a lesser degree in the distance;

• This VSR is right next to construction of the ventilation and administration buildings and these elements will party block some of their views;

• CKR elements will integrate with KTD at operation but many connecting roads directly border this VSR and so the magnitude of change will remain large.

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Large

Large

C3.9

Commercial

Planned Commercial Development in Kai Tak

750/ 850

Small

• Once development in KTD area is complete, this VSR's views to the CKR elements will be largely screened by other buildings and the CKR is being designed to complement the KTD, so no adverse visual impact is expected.

n/a / Permanent

Nil

n/a / Irreversible

n/a

Negligible

C3.10

Commercial

United Daily News Centre

700/ 1200

Medium

• Unlike residents in Wyler Gardens, viewers at high levels of this VSR have their view to the cut and cover tunnel works just to its north blocked by other buildings and mainly face towards the KTD south apron
• Key impacts will be from construction of the tunnel portal, depressed road;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.11

Commercial

Kowloon East 18

400/ 740

Small

• For viewers at higher levels, main impacts will be from construction of the connecting roads and the ventilation and administration buildings in the distance;
• The connecting roads will affect this VSR most, being closest, but will blend well with the existing view of Kwun Tong Bypass;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

C3.12

Commercial

Billion Centre

50/ 550

Medium

• Construction of the connecting roads and possibly the ventilation and administration buildings;
• The connecting roads will affect this VSR most, being so close, but will blend well with the existing view of Kwun Tong Bypass;
• Other elements of the Project are unlikely to be visible as blocked by e.g. Kwun Tong Bypass;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

C3.13

Commercial

Nam Fung Commercial Centre

250/ 650

Small

• For viewers at higher levels, main impacts will be from construction of the connecting roads and the ventilation and administration buildings in the distance;
• The connecting roads will affect this VSR most, being closest, but will blend well with the existing view of Kwun Tong Bypass;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

C3.14

Commercial

Industrial Buildings along Wang Kee Street

80/ 460

Medium

• Construction of the connecting roads and possibly the ventilation and administration buildings;
• This VSR is low rise and so its views will likely be limited to the new connecting road which will blend with the existing view of e.g. Kwun Tong Bypass;
• Other elements of the Project are unlikely to be visible as blocked by e.g. Kwun Tong Bypass;
• The ventilation building may be visible but since this VSR is distant from it, it will form part of the view rather than block it;
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Small

Small

GIC3.1

Government/ Institution/ Community

EMSD Headquarters

10/ 260

Medium

• Construction of the ventilation and administration building and connecting roads for the existing viewers;

• Once development in KTD area is complete, this VSR is close to the CKR connecting roads and the ventilation and administration buildings, so these will partially block the view;

• Key changes of view will also be caused by KTD structures such as the planned residential buildings (R3.8), Multi Purpose Stadium Complex (RE3.2) and Regional Open Space (RE3.1)

Temporary/ Permanent

Partial

Partly reversible/ Irreversible

Intermediate

Small

GIC3.2

Government/ Institution/ Community

Planned Government Buildings in Kai Tak

20/ 100

Medium

• Once development in KTD area is complete, this VSR is close to the CKR connecting roads and the ventilation and administration buildings, so these will partially block the view;
• Key changes of view will also be caused by KTD structures such as the planned residential buildings (R3.8), Multi Purpose Stadium Complex (RE3.2) and Regional Open Space (RE3.1)

n/a / Permanent

Partial

Partly reversible/ Irreversible

n/a

Small

GIC3.3

Government/ Institution/ Community

Holy Carpenter Primary School

650/ 1120

Large

• Viewers in this VSR have their view to the cut and cover tunnel works just to its north blocked by the vehicle inspection centre and any relevant views are mainly of KTD;
• Key impacts will be from construction of the  tunnel portal and depressed road; and
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• This VSR also borders the works area so views during construction are likely to be changes by construction traffic, etc.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

GIC3.4

Government/ Institution/ Community

EMSD Workshops

260/ 580

Medium

• Construction of the tunnel portal, temporary reclamation, depressed road close by across the water and to a lesser degree the ventilation and administration buildings and connecting roads in the distance;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operation, views of CKR elements will integrate into KTD and may be blocked or not be prominent.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

RE3.1

Recreational

Planned Regional Open Space in Kai Tak

0/ 120

Small

• Once development in KTD area is complete, this VSR's views to the CKR elements will be largely screened by other buildings and the CKR is being designed to complement the KTD, so no adverse visual impact is expected.

n/a / Permanent

Nil

n/a e/ Irreversible

n/a

Negligible

RE3.2

Recreational

Planned Multi Purpose Stadium Complex in Kai Tak

0/ 200

Small

• Once development in KTD area is complete, this VSR's views to the CKR elements will be largely screened by other buildings and the CKR is being designed to complement the KTD, so no adverse visual impact is expected.

n/a Permanent

Nil

Partly reversible/ Irreversible

n/a

Negligible

RE3.3

Recreational

Current and Future Waterfront Promenade at Ma Tau Kok

240/ 580

Large

• Construction of cut and cover tunnel, temporary reclamation and PTI reinstatement which these VSRs are right next to.
• Across the water, construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• At operations, the cut and cover will no longer be visible and the PTI reinstated;
• The views of the tunnel portal, depressed road, ventilation and buildings and connecting roads will integrate with KTD and not cause a large change in view in themselves.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

O3.1

Occupational

The Hong Kong and China Gas Company Limited Ma Tau Kok Control Centre

500/ 850

Large 

• Construction of cut and cover tunnel, temporary reclamation and PTI reinstatement which these VSRs are very near to.
• Across the water, for this ground level VSR, construction of the tunnel portal, depressed road, ventilation and administration buildings and connecting roads will largely be blocked by buildings and they cannot see the waterfront, so changes here will also not cause impact;
• At operation, the cut and cover will no longer be visible, the PTI reinstated and CKR elements across Kowloon Bay interfacing with KTD will not be visible. 

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Large

Small

O3.2

Occupational

Petrol Station at Kai Fuk Road

10/ 400

Large

• Construction of the connecting roads and possibly the ventilation and administration buildings;


• The connecting roads will affect this ground level VSR most, being so close, but will blend well with the existing view of Kwun Tong Bypass;


• Other elements of the Project are unlikely to be visible as blocked by e.g. Kwun Tong Bypass;


• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

T3.1

Transport Related

Kwun Tong Bypass

0/ 320

Small

• Construction of ventilation and administration buildings and connecting road. 
• Being close to the CKR works area and with elevated views, the magnitude of change will be intermediate during construction but minimal during operation. 
• Key changes of view will be caused by KTD structures rather than CKR structures which will have limited impact.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

T3.2

Travel/ Transport Related

Harbour Traffic

150/ 540

Small

• Construction of cut and cover tunnel, temporary reclamation, tunnel portal, depressed road, ventilation and administration building and connecting roads;
• Changes to Ma Tau Kok waterfront e.g. Pier changes and extra marine traffic;
• The cut and cover tunnel will be most visible to this VSR as well as the tunnel portal to a degree, but during operation general view for this VSR will only change minimally due to CKR and most changes in this area will be due to KTD.

Temporary/ Permanent

Nil

Partly reversible/ Irreversible

Intermediate

Small

 


10.11.3        Significance of Visual Impacts

Using the sensitivities of the VSRs described in the Baseline Study (Section 10.8) and the magnitude of change on each VSR ascertained in Table 10.12, the matrix shown in Table 10.13 has been used to calculate the significance of visual impacts before mitigation as shown in Table 10.11.   

Before mitigation, during construction, substantial impacts are experienced by a number of VSR in each area of the Project. In the West Portion high rise residential buildings with open views of a large extent of the Project, particularly if close to it, are substantially affected as well as a number of G/IC buildings again particularly those within the Works Area or very close to the Project.  One recreational VSR is also substantially impacted during construction; the Public Square Street Rest Garden viewers.  By day 1 of operation, substantial impacts are only felt by two residential VSRs (Kansu Street High Rise Buildings and The Coronation) and two G/IC VSRs (Yau Ma Tei Division Police Station and Yau Ma Tei Jockey Club Polyclinic. In the Central Portion area, substantial impacts during construction prior to mitigation are mainly experienced by G/IC VSRs including Ho Man Tin Government Offices (GIC2.1), SKH Tsoi Kung Po Secondary School (GIC2.2), Housing Authority Headquarters (GIC2.3) and Housing Authority Mock-up Centre (GIC2.4) but also by one residential VSR, the Ho Man Tin Estate (R2.5). Oi Man Estate (R2.10) only experience slight impacts during construction prior to mitigation.  All impacts in the Central Portion reduce to moderate or slight at operation day 1 prior to mitigation, except for impacts on Oi Man Estate (R.2.10) which are already insignificant at this stage.  In the East Portion, substantial impacts during construction prior to mitigation, are mainly experienced by viewers in high rise residential buildings such as Wyler Gardens (R3.1), Grand Waterfront (R3.2) and Sky Tower (R3.3) but viewers in the Hong Kong International Trade & Exhibition Centre (C3.8) and along the Current and Future Waterfront Promenade at Ma Tau Kok (RE3.3) are also considered to experience substantial impacts.  All these impacts reduce to moderate or slight at operation day 1 prior to mitigation

Using the mitigation measures described in Section 10.10, the residual impact for construction and operation day 1 and year 10 are also provided in Table 10.13.  Measures to mitigate visual impacts are largely general and although they can be applied to specific elements of the Project (e.g. Landscape enhancement – landscape deck), most of them are required in combination to contribute to the mitigation of visual impacts on a particular VSR. Generally visual mitigation measures are not considered to reduce visual impacts to a lower significance level at construction and are most effective at operation, therefore substantial impacts, as described above, may still be experienced by a number of VSRs during construction.

For all the impacts that are classified as substantial at operation prior to mitigation, measures to consider visual aspects in detailed design (MM 2), Green Roofs (MM12) and Landscape Enhancement (MM15) are key to their mitigation.  MM15 in particular aims to maximize greening opportunities, including through provision of landscape decks in the West and East Portions, including planters on viaducts, providing roadside planting, on buildings and greening vertical walls and piers which all enhances the visual aspect of the Project to those looking on.  In addition, the protection, preservation, transplantation and compensation of trees (MM8, MM9, MM10) are very important in retaining a green aspect and reducing visual impacts. Other slightly more general measures such as good site management (MM3), screen hoarding (MM4), controlling lighting during construction and operation (MM5 and MM16) are also important visual mitigation measures. 

With the implementation of these mitigation measures, residual impacts at day 1 of operation are considered to be ‘moderately adverse’ for six VSRs, the Kansu Street High Rise Buildings (R1.8) and The Coronation (R1.11) as well as four GIC VSRs: Yau Ma Tei Division Police Station (GIC1.4), Yau Ma Tei Jockey Club Polyclinic (GIC1.5), and Henry G. Leong Yaumatei Community Centre (GIC1.6).  Impacts on all other VSRs are ‘slightly adverse’ or insignificant. By year 10 of operation however, all impacts have reduced to ‘slightly adverse’ at worst and a number of VSRs are considered to benefit from the Project.  The viewers along the Current and Future Waterfront Promenade at Ma Tau Kok (RE3.3) are considered to benefit moderately, while four VSRs will slightly benefit. These are the viewers in the Comprehensive Development Area around Ma Tau Kok Road (CR3.1), Newport Centre (C3.1), Kapok Industrial Building (C3.2) and Holy Carpenter Primary School (GIC3.3). These beneficial impacts are due to the enhanced waterfront promenade at Ma Tau Kok.


Table 10.13 Significance of Visual Impact on VSRs, both before and upon Mitigation

* Denotes future VSRs that will not be in existence when construction for the Project starts. 

Measures to mitigate visual impacts are largely general.  Although they can be applied to specific elements of the Project (e.g. Landscape enhancement – landscape deck), most of them are required in combination to contribute to the mitigation of visual impacts on a particular VSR.  

 

Id No.

VSR Type

VSR Name

Sensitivity

Magnitude of Change BEFORE Mitigation (Negligible, Small, Intermediate, Large)

Impact Significance BEFORE Mitigation (Insignificant, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact Significance UPON Mitigation
(Insignificant, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction & Operation

Construction

Operation Day 1

Operation Year 10

West Portion

R1.1

Residential

One SilverSea

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R1.2

Residential

Island Harbourview

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R1.3

Residential

Park Avenue

High

Intermediate

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R1.4

Residential

Charming Garden

High

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R1.5

Residential

Wah Tak Building & Tak Cheong Lane High Rise

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R1.6

Residential

8 Waterloo Road

High

Intermediate

Small

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R1.7

Residential

Prosperous Garden

High

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R1.8

Residential

Kansu Street High Rise Buildings

Medium

Large

Large

Substantial

Substantial

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Moderate

Slight

R1.9

Residential

Man Cheong Building

High

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R1.10

Residential

Sorrento

High

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R1.11

Residential

The Coronation

High

Large

Large

Substantial

Substantial

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Moderate

Slight

R1.12

Residential

Planned Residential Development above Austin Station

High*

n/a

Small

n/a

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

R1.13

Residential

Victoria Towers

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R1.14

Residential

The Hermitage

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C1.1

Commercial

Bank of China Tower

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C1.2

Commercial

HSBC Centre

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C1.3

Commercial

Eaton Hotel

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C1.4

Commercial

ICC & Ritz Carlton Hotel

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C1.5

Commercial

Planned Commercial Development above XRL Terminus

Low*

n/a

Small

n/a

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

C1.6

Commercial

Keybond Commercial Building

Medium

Large

Intermediate

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

GIC1.1

Government/ Institution/ Community

Yau Ma Ti Catholic Primary School (Hoi Wang Road) & Li Kwok Po College

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

GIC1.2

Government/ Institution/ Community

Hong Kong Community College West Kowloon Campus

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC1.3

Government/ Institution/ Community

Yaumati Catholic Primary School (Tung Kun Street)

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC1.4

Government/ Institution/ Community

Yau Ma Tei Division Police Station

Medium

Large

Large

Substantial

Substantial

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Moderate

Slight

GIC1.5

Government/ Institution/ Community

Yau Ma Tei Jockey Club Polyclinic

Medium

Large

Large

Substantial

Substantial

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Moderate

Slight

GIC1.6

Government/ Institution/ Community

Henry G. Leong Yaumatei Community Centre

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Moderate

Slight

GIC1.7

Government/ Institution/ Community

Queen Elizabeth Hospital

Low

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

GIC1.8

Government/ Institution/ Community

Civil Aid Services Headquarter

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC1.9

Government/ Institution/ Community

Planned GIC Site

Medium*

n/a

Intermediate

n/a

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

O1.1

Occupational

LPG Filling Station at Hau Cheung Street

Low

Large

Large

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

RE1.1

Recreational

Olympic Plaza

Low

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

RE1.2

Recreational

Cherry Street Park

Low

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Slight

Insignificant

RE1.3

Recreational

Public Square Street Rest Garden

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

RE1.4

Recreational

Yau Ma Tei Community Centre Rest Garden

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

RE1.5

Recreational

Saigon Street Playground

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Insignificant

RE1.6

Recreational

Planned Public Open Space above future XRL-terminus and surrounding

Medium*

n/a

Intermediate

n/a

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

RE1.7

Recreational

Planned Public Open space north of Yan Cheung Road

Medium*

n/a

Intermediate

n/a

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

T1.1

Travel/ Transport Related

West Kowloon Highway

Low

Intermediate

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

Central Portion

R2.1

Residential

15 Ho Man Tin Hill

High

Small

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.2

Residential

Ellery Terrace

High

Small

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.3

Residential

Ho Man Tin Estate King Man House

Medium

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Slight

Insignificant

R2.4

Residential

Ho Man Tin Estate (High Rise Building Block)

High

Intermediate

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.5

Residential

Ho Man Tin Estate

High

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R2.6

Residential

Carmel On The Hill

High

Intermediate

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.7

Residential

Chung Man Court

High

Intermediate

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.8

Residential

Future Redevelopment of Ex-Valley Road Estate

High*

n/a

Small

n/a

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

R2.9

Residential

HK Polytechnic University Student Hostel Development

High

Small

Small

Moderate

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R2.10

Residential

Oi Man Estate

Medium

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 16

Slight

Insignificant

Insignificant

GIC2.1

Government/ Institution/ Community

Ho Man Tin Government Offices

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC2.2

Government/ Institution/ Community

SKH Tsoi Kung Po Secondary School

Medium

large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC2.3

Government/ Institution/ Community

Housing Authority Headquarters

Medium

Large

Intermediate

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

GIC2.4

Government/ Institution/ Community

Housing Authority Mock-up Centre

Medium

Large

Small

Substantial

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Insignificant

Insignificant

RE2.1

Recreational

Ho Man Tin East Service Reservoir Playground

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

RE2.2

Recreational

Sheung Lok Street Garden

Low

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

T2.1

Travel/ Transport Related

Fat Kwong Street (near Project Site)

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

T2.2

Travel/ Transport Related

Chung hau Street and Good Shepherd Street (near Project Site)

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

East Portion

R3.1

Residential

Wyler Gardens

High

Large

Small

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R3.2

Residential

Grand Waterfront

High

Large

Small

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R3.3

Residential

Sky Tower

High

Intermediate

Small

Substantial

Moderate

2, 3, 4, 5, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

R3.4

Residential

High Rise Developments along Prince Edward Road West (Including Padek Palace; New Development on Nga Tsin Long Road; Prince Ritz; Tung Sing Court)

Medium

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

R3.5

Residential

High Rise Developments along Prince Edward Road East (Carlson Court; Billionaire Royale and Le Billionaire; New Development on Lok Sin Road; The Latitude; Rhythm Garden)

Medium

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

R3.6

Residential

Choi Hung Estate

Medium

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

R3.7

Residential

Richland Gardens

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R3.8

Residential

Planned Residential Development in Kai Tak

High*

n/a

Intermediate

n/a

Moderate

2, 3, 4, 5, 11, 12, 13, 15, 16

n/a

Slight

Insignificant

R3.9

Residential

Sunrise Villa and New Residential Development at 9 Yuk Yat Street

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

R3.10

Residential

Laguna Verde Complex and Harbourfront Landmark

Medium

Small

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

CR3.1

Commercial/ Residential

Comprehensive Development Area around Ma Tau Kok Road (photograph at Hing Yan Street)

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Slightly beneficial

CR3.2

Commercial/ Residential

Planned Commercial/ Residential Development in Kai Tak

Medium*

n/a

Small

n/a

Slight

2, 3, 4, 5, 11, 12, 13, 15, 16

n/a

Insignificant

Insignificant

C3.1

Commercial

Newport Centre (partly in CDA of OZP)

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Slightly beneficial

C3.2

Commercial

Kapok Industrial Building

Low

Large

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Slightly beneficial

C3.3

Commercial

Kam Fai Commercial Building and Regal Oriental Hotel Hong Kong

Low

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

C3.4

Commercial

Tai King Industrial Building

Low

Small

Negligible

Slight

Insignificant

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

C3.5

Commercial

Skyline Tower

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.6

Commercial

Enterprise Square II; Enterprise Square

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.7

Commercial

Enterprise Square V and MegaBox; Enterprise Square III; Manhattan Place

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.8

Commercial

Hong Kong International Trade & Exhibition Centre

Medium

Large

Large

Substantial

Moderate

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Slight

Insignificant

C3.9

Commercial

Planned Commercial Development in Kai Tak

Low*

n/a

Negligible

n/a

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

n/a

Insignificant

Insignificant

C3.10

Commercial

United Daily News Centre

Low

Intermediate

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Slight

Insignificant

C3.11

Commercial

Kowloon East 18

Medium

Small

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.12

Commercial

Billion Centre

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.13

Commercial

Nam Fung Commercial Centre

Medium

Small

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

C3.14

Commercial

Industrial Buildings along Wang Kee Street

Low

Small

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Slight

Insignificant

GIC3.1

Government/ Institution/ Community

EMSD Headquarters

Medium

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

GIC3.2

Government/ Institution/ Community

Planned Government Buildings in Kai Tak

Medium*

n/a

Small

n/a

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

n/a

Insignificant

Insignificant

GIC3.3

Government/ Institution/ Community

Holy Carpenter Primary School

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Slightly beneficial

GIC3.4

Government/ Institution/ Community

EMSD Workshops

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Insignificant

RE3.1

Recreational

Planned Regional Open Space in Kai Tak

Medium*

n/a

Negligible

n/a

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

n/a

Insignificant

Insignificant

RE3.2

Recreational

Planned Multi Purpose Stadium Complex in Kai Tak

Medium*

n/a

Negligible

n/a

Insignificant

2, 3, 4, 5, 11, 12, 13, 15, 16

n/a

Insignificant

Insignificant

RE3.3

Recreational

Current and Future Waterfront Promenade at Ma Tau Kok

Medium

Large

Small

Substantial

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Substantial

Insignificant

Moderately beneficial

O3.1

Occupational

The Hong Kong and China Gas Company Limited Ma Tau Kok Control Centre

Low

Large

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Insignificant

Insignificant

O3.2

Occupational

Petrol Station at Kai Fuk Road

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

T3.1

Transport Related

Kwun Tong Bypass

Low

Intermediate

Small

Moderate

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Moderate

Slight

Insignificant

T3.2

Travel/ Transport Related

Harbour Traffic

Low

Intermediate

Small

Slight

Slight

2, 3, 4, 5, 8, 9, 11, 12, 13, 15, 16

Slight

Insignificant

Insignificant

10.11.4        Cumulative Visual Impact

West Portion

Since the CKR will use the same cut-and-cover tunnel construction method as the Kowloon Southern Link, VSRs within this ZVI will receive similar viewing experience during the construction phase. The construction works of CKR will commence after the completion of Kowloon Southern Link, so it will not cause accumulated impacts to the VSRs.

Part of the working areas will interface with Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link (XRL), which commenced in January 2010 prior to CKR. Construction methods are similar, and no addition visual impacts to adjacent VSRs are expected.

The development of widening options of Gasgoine Road Flyover (GRF) is divided into two parts: west section and east section. The west section refers to the west of Nathan Road from the Ferry Street to Nathan Road with the east section being the portion from Nathan Road to Chatham Road. The west section of GRF will interface with CKR.

In order to facilitate the construction of CKR, some buildings along the west section such as Yau Ma Tei Specialist Clinic Extension, Yau Ma Tei Carpark Building and Kowloon Government Office will be demolished. Moreover, in order to allow the traffic flow in the existing flyover to not be affected during the construction of CKR, a new deck must be provided on the north side of the existing flyover before the demolition of the existing flyover. The re-provisioned deck at the north of existing GRF will serve as a permanent deck for maintaining the single 2-lane 2-way traffic flow during and after the demolition of the existing GRF. The piers of the deck will be supported by the CKR tunnel structure. The re-provisioned deck will be designed to allow future widening on both sides of the deck without additional piers. Therefore, the widening works at west section will not require constructing new piers for the widening section.

As the works area of GRF is enclosed by CKR and the construction period of the west section is almost parallel to CKR, no additional impacts are expected. 

Central Portion

There are two MTR projects that should be considered for cumulative impacts with CKR around the Central Portion: the Ho Man Tin Station of the Kwun Tong Line Extension (KTE) from Yau Ma Tei Station to a new Wampoa station (started and due to complete in 2015); and the Tai Wai to Hung Hom Section (TAW-HUH) of the Shatin-Central Link (SCL) (due to start construction in 2012 and complete in 2018).  The projects are mainly underground but both will use a new station at Ho Man Tin.  This station will be located to the south of the Central Portion, at the ex-Valley Road Estate site which is not visible from the Central Portion site due to topography, however, one pedestrian lift will be constructed under KTE, adjacent to the proposed works area for the MVB, near Fat Kwong Street but given the small nature of the works for this, it is thought unlikely to cause additional visual impact and overall adjacent and planned VSRs are not expected to suffer any greater visual impacts due to other projects considered.

East Portion

The alignment of CKR passes through the KTD and it has been coordinated and fully incorporated into the design of KTD. The SCL (TAW-HUH) is also an integral part of KTD, running across the north of the site and integrating with CKR. Therefore, no additional visual impact to adjacent or planned VSRs are expected.

10.12              Conclusion

As the majority of the CKR is underground, landscape and visual impacts would be restricted to above ground construction works and operational facilities only. It is considered there will be no substantial adverse landscape and visual impacts to the surrounding sensitive receivers during the operation phase.

Based on the 2010 Tree Survey, about 1304 trees will be affected by the works and need to be removed by felling or transplanting, while approximately 2812 will be retained.  The 2010 Tree Survey estimated approximately 163 trees would be suitable for transplanting and approximately 1141 trees will not be suitable for transplanting and would therefore require felling. Due to the Project re-alignment and other projects development (e.g. XRL), the number of trees affected by the CKR Project has reduced since the 2010 Tree Survey. An updated Tree Survey will be carried out (due to commence mid 2013) and tree treatments will only be finalised during the Tree Removal Application.

For trees unavoidably affected by the Project that have to be removed, where practical, transplantation will be chosen as the top priority method of removal but if this is not possible or practical (e.g. the tree is too large or has a low survival rate), compensatory planting will be provided for trees unavoidably felled. The felled trees will be compensated for mainly within the Project Boundary including on the future landscape deck near the western tunnel portal but it is likely that it will be necessary to agree additional receptor sites for some compensatory trees (and possibly transplanted trees). Using worst case scenario numbers, current estimates predict additional receptor sites will be required for approximately 550 trees but given the reduced numbers of trees now affected by the Project, particularly in the West Portion, this number is likely to be reduced.

No Registered Old and Valuable Trees are located within the Works Area and none of the affected trees are LCSD champion Trees or Registered Old and Valuable Trees, neither are they rare or endangered species, but mainly common exotic trees. All the trees with high amenity values that are unavoidably affected by the works would be transplanted where possible. Detailed tree preservation, transplanting and felling including compensatory planting proposals will be submitted to the relevant Government Department for approval in due course in accordance with ETWB TC no. 3/2006.

Part of the public open spaces within the Works Area will be permanently taken by connection road, tunnel portal, ventilation building or re-provisioned community facilities, particularly in the West Portion. All areas of public open space affected by the Project will be re-provisioned either at the same location following the completion of temporary works, or at a separate site, as agreed with relevant Government departments and under the proposed development.  Overall more public open space will be re-provisioned/ reinstated than is taken during construction providing a net benefit to the regional environment.

A number of LRs in the East Portion are also considered to benefit from the Project at operation once mitigation measures have been implemented. These include Roadside Planting along San Ma Tau Street and Bus Terminus (LR3.3a), Disturbed Area within former Kai Tak Airport (LR3.5a), Man-made Shoreline around former Kai Tak Airport (LR3.8b) as well as the Man-made Shoreline of West Kowloon Bay (LR3.8a).  

Impact on Landscape Character Areas (LCAs) during construction would be primarily due to construction activities including associated temporary works for the construction of cut and cover tunnel, temporary reclamation, ventilation and administration buildings and connecting roads. After implementation of mitigation measures, there would be moderate adverse residual impacts on the Transport Corridor Landscape (LCA1.1) in the West Portion and the Typhoon Shelter (LCA3.4) and Transportation Corridor Landscape (LCA3.5) in the East Portion during construction. The rest of the LCAs would experience slight or insignificant residual impacts at this stage. With the implementation of mitigation measures, at the design year (operation year 10), impacts from the Project on all the LCAs would be insignificant.

Visual impact during the construction phase would be primarily due to construction activities such as excavation for cut and fill, temporary reclamation, piling and demolition of existing buildings as well as actual construction of new structures such as the ventilation and administration buildings, depressed and connecting roads and tunnel portals including landscape deck. With implementation of mitigation measures during construction, there would still be some substantial impacts on VSRs adjacent or close to the CKR especially residential and GIC VSRs while residual impacts on VSRs further away from the works would be moderate to slight adverse except for those who will be shielded from the view by future development in the former Kai Tak Airport area and not be affected by the Project. After the implementation of mitigation measures in operation year 10, visual impacts on all VSRs will be insignificant with the exception of some slight adverse visual impacts on residential and GIC VSRs that are close to the tunnel portal in the West Portion.

Considerable effort has been made to integrate the CKR with KTD and overall the former Kai Tak Airport area will be enhanced. A number of CKR VSRs close to the Ma Tau Kok waterfront, which will be converted into a landscaped promenade, will also slightly benefit from the CKR Project at operation, while viewers along the current and future waterfront here will benefit moderately. 

Overall, it is considered that the adverse residual landscape and visual impacts of the proposed Project are considered as acceptable with mitigation measures during construction and operation phase.