5 NOISE
IMPACT
This chapter presents the findings of the noise assessment for the proposed CKR during both the construction and operational phases. Construction airborne noise associated with the use of Powered Mechanical Equipment (PME) has been conducted. With the implementation of practical mitigation measures, construction noise impacts at most of the neighboring noise sensitive uses would be controlled to acceptable levels. However, for some receivers that are very close to some of the works sites, adverse residual impacts exceeding the construction noise criterion are anticipated even after implementing all practicable mitigation measures. Construction groundborne noise associated with the use of PME has also been conducted at representative noise sensitive receivers along the tunnel and the construction groundborne noise impacts would comply with the noise criteria.
Operational noise impacts associated with road traffic noise and fixed noise sources have also been investigated. With the implementation of mitigation measures, potential noise impacts would comply with the statutory criteria.
Construction Noise during Non-restricted Hours
The Noise Control Ordinance (NCO) (Cap. 400)
provides the statutory framework for noise control in Hong Kong. Assessment procedures and standards are set
out in the respective Technical Memoranda (TM) promulgated under the NCO. The following TMs are applicable to the
assessment and control of construction noise.
·
TM on Noise from Construction Work other than
Percussive Piling (TM-GW);
·
TM on Noise from Percussive Piling (TM-PP); and
·
TM on Noise on Construction Work in Designated
Areas (TM-DA).
To ensure a better environment, the TM-EIAO
promulgated under the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499) has imposed more stringent criteria.
For construction, there is no statutory limit on daytime construction
noise under the NCO and related TMs.
Nevertheless, the TM-EIAO stipulates noise standards of 65 – 75 dB(A)
for daytime construction activities, as shown in the table below.
Table 5.1:
Noise Standards for Construction Activities
Uses |
Noise Standards [1],
Leq (30 mins) dB(A) |
|
0700 to 1900 hours on any day not being a Sunday or general holiday |
1900 to 0700 hours or any time on Sundays or general holiday |
|
All domestic premises including temporary housing
accommodation |
75 |
(See Note 2) |
Hotels and hostels |
75 |
|
Educational institutions including
kindergartens, nurseries and all others where unaided voice communication is
required |
70 65 (During examinations) |
Notes:
[1] The above
standards apply to uses that rely on opened windows for ventilation.
[2] The
criteria laid down in the relevant technical memoranda under the NCO for
designated areas and construction works other than percussive piling may be
used for planning purpose. A
Construction Noise Permit (CNP) shall be required for the carrying out
construction work during the period.
Construction Noise during Restricted Hours
The NCO also provides statutory control on
general construction works during restricted hours (ie 1900 to 0700 hours (of
the next day) from Monday to Saturday and at any time on Sundays or public
holidays). The use of PME for
construction works during restricted hours would require a Construction Noise
Permit (CNP). The TM-GW details the
procedures adopted by EPD for assessing such application. The granting of a CNP is subject to
conditions stated in the CNP and it may be revoked at any time for failure to
comply with the permit conditions.
In addition to the general controls on the use
of PME during restricted hours, the use of Specified Powered Mechanical
Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW)
during the restricted hours in a designated area are controlled by the
TM-DA. Construction plant or equipment
classified as SPME under the TM-DA includes hand-held breakers, bulldozers,
concrete mixer lorries, dump trucks and poker vibrators. The PCW includes the erection or dismantling
of formwork or scaffolding, hammering, handling of rubble, wooden boards, steel
bars, or scaffolding material, and the disposal of rubble through plastic
chutes.
The TM-DA details the procedures that should
generally be adopted by the Authority for assessing the use of SPME during
restricted hours and for determining whether a CNP would be issued.
Maximum noise levels from construction
activities during restricted hours at affected NSRs are controlled under the
TMs and shall not exceed the specified Acceptable Noise Levels (ANLs). These ANLs are stipulated in accordance with
the Area Sensitivity Ratings established for the NSRs. The ANLs for construction works in Designated
Areas are more stringent than those given in the GW-TM and summarized in the
table below.
Table 5.2:
Acceptable Noise Levels for Construction during Restricted Hours
Time
Period |
Acceptable Noise Levels for Area Sensitivity Ratings, dB(A) |
||
A |
B |
C |
|
All weekdays during the evening (1900 to 2300 hours), and general
holidays (including Sundays) during the day and evening (0700 to 2300 hours) |
60 (45) |
65 (50) |
70 (55) |
All days during the night-time (2300 to 0700 hours) |
45 (30) |
50 (35) |
55 (40) |
Note: Figures in brackets are ANLs for SPME
construction work in designated areas
Area Sensitivity
Rating (ASR)
The appropriate ASR for the NSR shall consider under consideration from below table.
Any NSR shall, irrespective of Table 5.3, be assigned an ASR of "C" if it is within 100 m of a zone designated as "Industrial" or "Industrial Estate" on a statutory Outline Zoning Plan, or an ASR of "B" if it is between 100 m and 250 m from such a zone, except in cases where Table 5.3 indicates an ASR of "C".
Table 5.3
Area Sensitivity Ratings (ASRs)
Type of Area containing
NSR |
Degree to which NSR is
affected by IF |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
(i)
Rural area, including country parks or village type developments |
A |
B |
B |
(ii)
Low density residential area consisting of low-rise or isolated high-rise
developments |
A |
B |
C |
(iii)
Urban area |
B |
C |
C |
(iv)
Area other than those above |
B |
B |
C |
Note:
For the purpose of Table 5.3,
the following definitions apply:
"country park"
means an area that is designated as a country park pursuant to section 14 of
the Country Parks Ordinance;
"directly affected"
means that the NSR is at such a location that noise generated by the IF is
readily noticeable at the NSR and is a dominant feature of the noise climate of
the NSR;
"indirectly
affected" means that the NSR is at such a location that noise generated by
the IF, whilst noticeable at the NSR, is not a dominant feature of the noise
climate of the NSR;
"not affected"
means that the NSR is at such a location that noise generated by the IF is not
noticeable at the NSR; and
"urban area" means
an area of high density, diverse development including a mixture of such
elements as industrial activities, major trade or commercial activities and
residential premises.
Despite any description made in this EIA, there
is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a
well-justified CNP application, once filed, for construction works within
restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into
account contemporary conditions / situations of adjoining land uses and any
previous complaints against construction activities at the site before making a
decision in granting a CNP. Nothing in
the EIA report shall bind the Noise Control Authority in making a
decision. If a CNP is to be issued, the
Noise Control Authority shall include in it any conditions demand. Failure to comply with any such conditions
will lead to cancellation of the CNP and prosecution under the NCO.
Percussive Piling
Under the TM-PP, CNPs are also required for
percussive piling involving the use of diesel, pneumatic and / or steam
hammer. This TM specifies the permitted
hours and other conditions for percussive piling. The table below lists the acceptable
percussive piling noise levels for various types of NSR.
Table 5.4:
Acceptable Noise Levels for Percussive Piling
NSR Window Type or Means of Ventilation |
ANL (dB(A)) |
(i) NSR (or part of NSR) with no window or
other opening |
100 |
(ii) NSR with central air conditioning system |
90 |
(iii) NSR with windows or other openings but without central air conditioning system |
85 |
Depending on the numbers and types of piling
machines and the separation from NSRs, percussive piling may be restricted to
12, 5 or 3 hours per day. For NSRs that
are particularly sensitive to noise, such as hospitals, medical clinics,
educational institutions and courts of law, a further reduction of 10 dB(A)
shall be applied to the above ANLs.
Blasting
The administrative and procedural control of
all blasting operations in Hong Kong is vested in the Mines Division of the
Civil Engineering and Development Department (CEDD). The Dangerous Goods (General) Regulations,
Chapter 295 also stipulates that no person shall carry out blasting unless he
possesses a valid mine blasting certificate to be issued by the Mines Division
of CEDD. The Superintendent of Mines
will review the application on a case-by-case basis before issuing the Mine
Blasting Certificate. Although there is
no statutory noise level for blasting, the noise associated with the removal of
debris and rocks are controlled under the TM-EIAO.
Construction Groundborne Noise
Noise arising from general construction works
during normal working hours is governed by the TM-EIAO under the EIAO. The Technical Memorandum for the Assessment
of Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-IND) under the NCO stipulates that noise transmitted
primarily through the structural elements of building, or buildings, shall be
10 dB(A) less than the relevant ANLs.
Based on the same principle for the ground-borne
noise criteria (i.e. ANL-10 dB(A) under the TM-IND), the construction
groundborne noise levels inside domestic premises and schools shall be limited
to 65 dB(A) and 60 dB(A) respectively when compared to the TM-EIAO. The
construction groundborne noise criteria has been summarized in Table 5.5.
For construction works conducted on general holidays, Sundays and weekdays during evening (1900-2300 hrs) and night time (2300-0700 hrs) the following day, the construction groundborne noise level shall be limited to 10 dB(A) below the respective ANLs for the ASR appropriate to those NSRs affected by the Project. A summary of these criteria is given in the table below.
Table 5.5: Construction Groundborne Noise Criteria (Leq
30min, dB(A))
NSR type |
Construction Groundborne
Noise Criteria, dB(A) |
||
Daytime (0700– 1900) except
general holidays and Sunday |
Daytime (0700-1900) during general
holidays and Sundays and all days during Evening (1900-2300 hrs) |
Night-time (2300 – 0700 hrs) |
|
All domestic premises including temporary housing accommodation |
65 |
50/55/60[1,2] |
35/40/45[1,2] |
Hotels and hostel |
|||
Educational institutions including kindergarten, nurseries and all
others where unaided voice communication is required |
60 55 (for during examination) |
N/A[3] |
N/A[3] |
Notes: [1] Based
on the Basic Noise Level for NSRs with Area Sensitivity Ratings of A, B, and
C detailed in the Technical Memorandum on Noise From Construction Work Other
Than Percussive Piling. [2] Construction Noise Permit is required for
works during this period. [3] No sensitive use in educational
institutions during evening and night-time
during normal period and on general holidays and Sunday is
assumed except specified. |
The relevant legislation and associated guidelines
applicable to the operational noise assessment includes:
·
EIAO (Cap. 499);
·
TM for the assessment of Noise from Places other
than Domestic Premises, Public Places or Construction Sites (TM-Places); and
·
Hong Kong Planning Standards and Guidelines (HKPSG).
Road Traffic Noise
The TM-EIAO has stipulated the noise standards
for various noise sources as shown in the following table.
Table 5.6:
Noise Standards for Operational Phase (Road Traffic Noise)
Common Uses |
Noise Standards [1] |
Road
Traffic Noise L10
(1hour) dB(A) |
|
All domestic premises
including temporary housing accommodation |
70 |
Hotels and hostels |
70 |
Offices |
70 |
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
65 |
Places of public worship and
courts of law |
65 |
Hospitals, clinics,
convalescences and homes for the aged, diagnostic rooms, wards |
55 |
Notes:
[1] The above standards apply to uses that
rely on opened windows for ventilation.
Fixed Noise Sources
Operational noise from fixed noise sources is
controlled under the NCO’s Technical Memorandum on Noise from Places other than
Domestic Premises, Public Places or Construction Sites. To plan for a better environment, the TM-EIAO
has specified the following requirements.
·
5 dB(A) below the appropriate ANLs in the Technical
Memorandum on Noise from Places other than Domestic Premises, Public Places or
Construction Sites (TM-IND); or
·
the existing noise levels (For quiet areas with
level 5dB(A) below the ANL).
Table 5.7:
Noise Standards for Operational Phase (Fixed Noise Sources)
Common Uses |
Noise Standards [1] |
Fixed Noise Sources |
|
All domestic premises
including temporary housing accommodation |
(a) 5dB(A) below the appropriate Acceptable
Noise Levels (ANL) shown in Table 2 of the Technical Memorandum for the
Assessment of Noise from Places Other than Domestic Premises, Public Places
or Construction Sites, or (b) the prevailing background noise levels
(For quiet areas with level 5 dB(A) below the ANL) |
Hotels and hostels |
|
Offices |
|
Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required |
|
Places of public worship and
courts of law |
|
Hospitals, clinics,
convalescences and homes for the aged, diagnostic rooms, wards |
The ANLs for different ASR (refers to Table 5.3) during different periods are
summarized in the following table.
Table 5.8:
Acceptable Noise Levels for Fixed Noise Sources
Time Period |
ANL, dB(A) |
ANL-5, dB(A) |
||||
ASR A |
ASR B |
ASR C |
ASR A |
ASR B |
ASR C |
|
Day (0700 to 1900 hours) |
60 |
65 |
70 |
55 |
60 |
65 |
Evening (1900 to 2300 hours) |
60 |
65 |
70 |
55 |
60 |
65 |
Night (2300 to 0700 hours) |
50 |
55 |
60 |
45 |
50 |
55 |
Note: ASR –
Area Sensitivity Rating
Noise from Public Transport Interchange
There are no noise level standards
stipulated for the noise from the operation of public transport interchange
(PTI). Chapter 9 of Hong Kong Planning
Standards and Guidelines (HKPSG) provides considerations for the Project
Proponent to determine the location and layout of a PTI during planning
stage.
Representative NSRs within a distance of 300m from the either side of
the project boundary have been identified.
The first layer of NSRs has been identified and selected for
assessment. These NSRs will cover all
existing sensitive developments (including those occupied before completion of
the construction) for construction noise assessment, and both the existing and
planned developments for operational noise assessment.
Existing Receivers
The existing NSRs are identified by means of topographic maps, aerial photos, land status plans and several site surveys.
Planned/Committed Receivers
Planned/committed NSRs are identified by making reference to relevant
Outline Zoning Plans (OZP), Outline Development Plans, Layout Plans and other
published plans in the vicinity of the alignment, including:
·
South West Kowloon (KPA 20) Outline Zoning Plan
(No. S/K20/27);
·
Tsim Sha Tsui (KPA 1) Outline Zoning Plan (No.
S/K1/26);
·
Yau Ma Tei (KPA 2) Outline Zoning Plan (No.
S/K2/21);
·
Ho Man Tin (KPA 6 & 7) Outline Zoning Plan (No.
S/K7/22);
·
Hung Hom (KPA 9) Outline Zoning Plan (No. S/K9/24);
·
Ma Tau Kok (KPA 10) Outline Zoning Plan (No.
S/K10/20);
·
Kai Tak (KPA 22) Outline Zoning Plan (No. S/K22/4);
and
·
Ngau Tau Kok & Kowloon Bay (KPA 13 & 17)
Outline Zoning Plan (No. S/K13/27)
A list of planned/ committed noise sensitive receivers was identified and summarized below.
West Portion
There are several areas zoned as Governmental, Institution and Community (G/IC) in West Portion. Planning use of these G/IC zone has been requested from Planning Department and a letter from Planning Department showing the potential uses of G/IC sites in West Kowloon latest OZP No. S/K20/27 is shown in Appendix 5.1A. Some of the G/IC uses are identified as noise sensitive receivers including Refuse Collection Point and Street Sleepers’ Shelters, Primary School and Hindu Temple for assessment.
According to the information provided by the respective project
proponents of Street Sleepers’ Shelters and Hindu Temple, the Street Sleepers’
Shelters will be a 4-storey building with sensitive facades facing Ferry Street
and Hau Cheung Street, the Hindu Temple will be a 10-storey building with
sensitive facade facing West Kowloon Highway.
However, there are no confirmed information on the layout of the planned
school, referenced has been made to the existing schools in surrounding. It has therefore been assumed the school is
8-storey. The Coronation is a
residential premises located at OZP No. S/K20/27, which is zoned as R(A)1. The latest layout and number of storey have
been adopted in this assessment, which has already confirmed by site
inspection. There
are no confirmed intake programme of Hindu Temple and Primary School, hence,
these two receivers are not included as construction noise impact assessment.
Central Portion
According to the latest OZP No. S/K7/21, there is a R(B)2 zone next to the planned Project site office which is under construction. However, as no confirmed building layout is available during the preparation of this EIA study, assessments point at the boundary has been selected for airborne construction noise impact assessment.
East Portion
All selected planned / committed receivers at East portion were based on latest Kai Tak Outline Zoning Plan (No. S/K22/4) gazetted on 14 Sept 2012. As no confirmed building layout is available during the preparation of this EIA study, assessment locations have been selected at this area including residential uses, comprehensive development area, planned hospital and planned school. The building height restriction and the population intake of these planned receivers is based on the latest Kai Tak Outline Zoning Plan.
For the planned school, the school layout has assumed as typical school layout and sensitive facades surrounding the building layout are selected for assessment.
Overall
The locations of the representative NSRs for noise impact assessment
during both construction and operation of the project are illustrated in
Figures 5.1.1 to 5.3.2, and are summarized in the table
below. Groundborne noise sensitive
receivers have been selected at both portal end and central portion given that
separation distance between these selected noise sensitive receivers to the
rock head level would be minimum along the alignment. Figure 2.3
shows the longitudinal profile of CKR. A
summary of noise sensitive receivers is tabulated in Appendix 5.1. Photos showing existing noise sensitive
receivers are given in Appendix 5.2.
Table 5.9: Representative NSRs for Noise
Impact Assessment
NSR ID |
Description |
Landuse [1] |
No. of Storey |
Construction Phase |
Operational Phase |
||
Airborne |
Groundborne |
Road Traffic Noise |
Fixed Plant Noise |
||||
West
Portion |
|||||||
W-N1A |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
E |
8 |
√ |
X |
√ |
√ |
W-N1B |
Yau Ma Tei Catholic Primary School (Hoi Wang Road) |
E |
8 |
X |
X |
√ |
X |
W-N2 |
Charming Garden Block 12 |
R |
23 |
√ |
X |
√ |
√ |
W-N3 |
Yau Ma Tei Catholic Primary School (Tung Kun Street) |
E |
7 |
√ |
X |
√ |
X |
W-N6 |
Man Cheong Building |
R |
18 |
X |
X |
√ |
X |
W-N6A |
Man Wai Building |
R |
18 |
X |
X |
√ |
X |
W-N7 |
Kum Lam Building |
R |
12 |
√ |
X |
√ |
X |
W-N8 |
Dickson Building |
R |
18 |
√ |
X |
√ |
X |
W-N8A |
Tak Cheong Building |
R |
18 |
√ |
X |
√ |
X |
W-N9A |
Yau Ma Tei Jockey Club Polyclinic |
H |
10 |
X |
X |
√ |
X |
W-N9B |
Yau Ma Tei Jockey Club Polyclinic |
H |
10 |
X |
X |
√ |
X |
W-N10A |
Alhambra Building (West façade) |
R |
15 |
√ |
√ |
√ |
X |
W-N10B |
Alhambra Building (West façade) |
R |
15 |
√ |
X |
X |
X |
W-N10C |
Alhambra Building (North façade) |
R |
15 |
X |
X |
√ |
X |
W-N11 |
Hong Kong Community College (HKCC) of the HK [1] |
E |
19 |
√ |
X |
√ |
X |
W-N14 |
Charming Garden Block 1 |
R |
22 |
X |
X |
√ |
√ |
W-N15 |
HKMA David Li Kwok Po College |
E |
8 |
√ |
X |
√ |
X |
W-N18 |
Hydan Place |
R |
17 |
√ |
X |
√ |
X |
W-N19 |
Methodist College |
E |
6 |
√ |
√ |
√ |
X |
W-N20 |
Tang’s Mansion |
R |
15 |
X |
X |
√ |
X |
W-N21 |
Temple Street No. 56 |
R |
7 |
√ |
X |
√ |
X |
W-N22 |
Kamly Court |
R |
10 |
√ |
X |
√ |
X |
W-N23 |
Hang Wan House |
R |
23 |
√ |
X |
√ |
X |
W-N24 |
Prosperous Garden Block 5 |
R |
27 |
√ |
X |
√ |
X |
W-N25A |
Prosperous Garden Block 1 |
R |
28 |
√ |
X |
√ |
X |
W-N25B |
Prosperous Garden Block 1 |
R |
28 |
X |
X |
√ |
X |
W-N26A |
Prosperous Garden Block 2 |
R |
28 |
X |
X |
√ |
X |
W-N26B |
Prosperous Garden Block 2 |
R |
28 |
X |
X |
√ |
X |
W-N27 |
Prosperous Garden Block 3 |
R |
28 |
X |
X |
√ |
X |
W-N28 |
Wah
Tak Building |
R |
17 |
X |
X |
√ |
X |
W-N29 |
Tin Hau Temple |
W |
1 |
X |
X |
√ |
X |
W-N30 |
The Sorrento |
R |
50 |
X |
X |
√ |
X |
W-N31 |
Shanghai Street No. 217-225 |
R |
5 |
√ |
X |
X |
X |
W-N32 |
Sing On Building |
R |
5 |
√ |
X |
X |
X |
W-P6A, C |
Refuse Collection Point and Street Sleepers’ shelters (Planned) |
GIC |
4 |
√ |
X |
√ |
X |
W-P7A-G |
Primary School (Planned) |
E |
8 |
X |
X |
√ |
X |
W-P8 |
Hindu Temple (Planned) [2] |
W |
10 |
X |
X |
√ |
√ |
W-P9 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P10 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
W-P11 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P12 |
The Coronation |
R |
30 |
√ |
X |
√ |
X |
W-P13 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
W-P14 |
The Coronation |
R |
30 |
X |
X |
√ |
X |
Central
Portion |
|||||||
M-N1 |
Kar Man House, Oi Man Estate |
R |
6 |
√ |
√ |
X |
√ |
M-N2 |
Carmel on the Hill |
R |
25 |
√ |
X |
X |
√ |
M-N3 |
SKH Tsoi Kung Po Secondary School |
E |
8 |
√ |
√ |
X |
√ |
M-N4 |
Man Fuk House Block A |
R |
15 |
√ |
X |
X |
√ |
M-N5 |
Cascades Block A |
R |
18 |
√ |
X |
X |
X |
M-N6 |
Ko Fai House, Kwun Fai Court |
R |
9 |
√ |
√ |
X |
√ |
M-P2 |
Planned Residential Area B (Planned) |
R |
- |
√ |
X |
X |
√ |
M-P3 |
Planned Residential Area B (Planned) |
R |
- |
√ |
X |
X |
√ |
East
Portion |
|||||||
E-N6 |
Grand Waterfront Tower 5 |
R |
51 |
√ |
X |
X |
X |
E-N11 |
Holy Carpenter Primary School |
E |
6 |
√ |
X |
X |
X |
E-N12 |
Grand Waterfront Tower 3 |
R |
51 |
√ |
√ |
X |
X |
E-N13 |
Grand Waterfront Tower 1 |
R |
51 |
√ |
X |
X |
X |
E-N14 |
Chong Chien Court Block J |
R |
13 |
√ |
√ |
X |
X |
E-N15 |
Hang Chien Court Block I |
R |
13 |
√ |
X |
X |
X |
E-N19 |
Buddhist Chi King Primary School |
E |
8 |
√ |
X |
√ |
X |
E-N20 |
Hing Yan Street No. 29 |
R |
7 |
√ |
X |
X |
X |
E-N21 |
Hang Chien Court Block J |
R |
13 |
√ |
X |
X |
X |
E-N22 |
Hang Chien Court Block H |
R |
13 |
√ |
X |
X |
X |
E-P1 |
Site 1L2 (Planned) |
R |
32 |
X |
X |
√ |
X |
E-P6 |
Site 5A4a (Planned) |
CDA |
20 |
X |
X |
√ |
X |
E-P7 |
Site 5A4b (Planned) |
CDA |
35 |
X |
X |
√ |
X |
E-P8 |
Site 1L3 (Planned) |
R |
15 |
X |
X |
√ |
√ |
E-P13A-B |
Site 3C1 – Hospital (Planned) |
H |
14 |
X |
X |
√ |
X |
E-P14A-G |
Site 3B1- Secondary School
(Planned) |
E |
10 |
X |
X |
√ |
√ |
E-P16 |
Site 1L3 (Planned) |
R |
32 |
X |
X |
√ |
X |
E-P20 |
Site 1I3 (Planned) |
R |
32 |
√ |
X |
√ |
X |
Barging Point |
|||||||
B-N1 |
Grand Horizons |
R |
36 |
√ |
X |
X |
X |
Notes:
R – residential; E –
educational; H – clinic/ home for the aged/hospital; W – worship; GIC –
government, institution and community; CDA – Comprehensive Development Area
√ – Include for assessment; X – Not included for assessment. Selected NSRs would better represent the
impacts already.
[1]
Central air-conditioning is provided.
[2]
According to the information provided by the respective project proponent, this
planned temple would have 10 storey high. The tentative layout has also
been adopted in this EIA.
Prevailing Noise Levels
According to the latest design, there are three
ventilation buildings, one near the western portal, one near the eastern portal
and the central ventilation building will locate at the central portion near Ho
Man Tin West Service Reservoir. Noise
measurements have been conducted to establish the prevailing noise levels in
the vicinity of the proposed ventilation buildings where fixed noise sources
are anticipated. Appendix 5.3 shows the measurement locations for prevailing noise levels. A summary of the results is given in the
table below.
Table 5.10:
Measurements of Prevailing Noise Levels
Measurement Location |
Prevailing Noise Levels [1],
dB(A) L eq |
|
Day & Evening [2] |
Night [2] |
|
West Portion (Location A) |
64-68 |
60-61 |
West Portion (Location B) |
65-66 |
55-56 |
Central Portion (Location C) |
73-75 |
70-71 |
Central Portion (Location D) |
73-74 |
69-70 |
East Portion (Location E) |
69-71 |
66-69 |
Note:
[1] Measurements conducted in
November 2011
[2] Day: 0700 to 1900 hours, Evening:
1900 to 2300 hours, Night: 2300 to 0700 hours
Area Sensitivity Rating
The table above shows the NSRs which close to the
ventilation buildings may have potential fixed plant noise impact and these
NSRs have been selected for fixed plant noise assessment. The ASR of NSRs identified for the fixed
plant noise is summarized in the table below.
Table 5.11:
ASR of Representative NSRs for Fixed Plant Noise Assessment
NSR ID |
Landuse [1] |
Type of Area |
Influence Factor (IF) |
Degree to which NSR is
affected by IF |
ASR |
W-N1A |
E |
Urban |
N/A |
N/A |
B |
W-N2 |
R |
Urban |
N/A |
N/A |
B |
W-N14 |
R |
Urban |
West Kowloon Expressway [2] |
Directly |
C |
W-P8 |
W |
Urban |
West Kowloon Expressway [2] |
Directly |
C |
M-N1 |
R |
Urban |
N/A |
N/A |
B |
M-N2 |
R |
Urban |
N/A |
N/A |
B |
M-N3 |
E |
Urban |
N/A |
N/A |
B |
M-N4 |
R |
Urban |
N/A |
N/A |
B |
M-N6 |
R |
Urban |
N/A |
N/A |
B |
M-P2 |
R |
Urban |
N/A |
N/A |
B |
M-P3 |
R |
Urban |
N/A |
N/A |
B |
E-P8 |
R |
Urban |
Kai Fuk Road [3] |
Directly |
C |
E-P14A |
E |
Urban |
Kai Fuk Road [3] |
Directly |
C |
Notes:
[1] R– residential; E – educational; W – Place of public worship
[2] The AADT of West Kowloon Expressway (Station no. 3707) is greater
than 30,000 according to AADT 2011
[3] The AADT of Kai Fuk Road (Station no. 3206) is greater than 30,000
according to AADT 2011
Noise Criteria
A summary of the noise criteria at
representative NSRs which would be subject to the impact of fixed plant noise
is given in the following table. The
prevailing noise level at each NSR would be determined based on measurement results
at the nearest location as shown in the table below.
Table
5.12: Summary of Noise Criteria at NSRs
for Fixed Noise Sources
Location |
NSR |
Time Period [1] |
Prevailing Noise Levels, dB(A) [2] |
ASR |
ANL-5 dB(A) [3] |
Criteria dB(A) [4] |
West Portion (Location A) |
W-N1A, W-N2 |
Day & evening |
64 |
B |
60 |
60 |
Night |
60 |
B |
50 |
50 |
||
West Portion (Location A) |
W-N14 |
Day & evening |
64 |
C |
65 |
64 |
Night |
60 |
C |
55 |
55 |
||
West Portion (Location B) |
WP-8 |
Day & evening |
65 |
C |
65 |
65 |
Night |
55 |
C |
55 |
55 |
||
Central Portion (Location C) |
M-N2, M-N3, M-N4 |
Day & evening |
73 |
B |
60 |
60 |
Night |
70 |
B |
50 |
50 |
||
Central Portion (Location D) |
M-N1, M-N6, M-P2, M-P3 |
Day & evening |
73 |
B |
60 |
60 |
Night |
69 |
B |
50 |
50 |
||
East Portion (Location E) |
E-P8, E-P14A |
Day & evening |
69 |
C |
65 |
65 |
Night |
66 |
C |
55 |
55 |
Note:
[1] Day: 0700 to 1900 hours, Evening: 1900 to 2300
hours, Night: 2300 to 0700 hours.
[2] Prevailing
noise level determined based on the measurement result recorded at the
representative location nearest to the respective NSR.
[3] A 5 dB(A) has been deducted from ANL as specified
in requirement of TM-EIAO.
[4] The Minimum of [2] & [3] is adopted.
5.4 Construction Noise Impact Assessment
5.4.1
Construction
Airborne Noise
Noise Sources
The latest construction methodology is
described in Chapter 3. Based on the construction
methodologies, the major construction works would include the following
activities:
·
Site clearance and formation activities;
·
Structure dismantling;
·
Tunnel construction (including non-blasting
tunneling, drill-and-blast tunneling, underwater tunnel and cut-and-cover);
·
Rock crushing inside the tunnel shaft of West,
Central and East Portions;
·
Construction of approach roads;
·
Portal construction;
·
Diversion of utilities;
·
Spoils removal from underground works &
stockpiling;
·
Backfilling and reinstatement works; and
·
Barging activities.
These construction activities would be carried out with the use of PME including breakers, excavators, lorries, mobile cranes, concrete pumps, concrete mixers, pokers, road rollers, etc. Sound Power Level (SWL) for each PME would be established according to TM-GW and other relevant information as appropriate.
All the works associated with the tunnel works (e.g. holes drilling and rock excavation etc) would be conducted deep inside the tunnel. For the operation of rock crushers in particular, they would be located typically at about 20 to 30m from the portals inside the tunnel. The approximate location of rock crushers are shown in Appendix 5.4C. Although the horizontal distance between the mucking out points and the sensitive receivers of West, Central and East Portions are within 50m, the rock crusher in the Central Portion will however be located over 100m vertically from the mucking out. Hence, only operations of rock crushers at West Portion and East Portion have been assessed.
Assessment Methodology
Construction airborne noise assessment has been
conducted based on the following procedures:
·
Determine the assessment area, and identify
representative NSRs that may be affected by the works;
·
Obtain the construction method and work sequence
for the construction period;
·
Obtain the plant items for each corresponding
construction work sequence;
·
Determine the sound power levels of the plant items
according to the information stated in the TM-GW or other recognized sources of
reference, where appropriate;
·
Calculate the correction factors based on the
distance between the NSRs and the notional noise source positions of the work
sites;
·
Apply corrections for façade, distance, barrier
attenuation, acoustic reflection where applicable;
·
Quantify the level of impact at the NSRs in
accordance with TM-GW;
·
Predict the cumulative noise impacts by any
concurrent construction works in the vicinity; and
·
For any exceedance of noise criteria, all practical
mitigation measures such as alternative construction methodology, quiet plant,
silencer, enclosure, etc, shall be examined to alleviate the predicted noise
impacts as much as practicable.
Utilization Rates and SWLs of Powered Mechanical Equipment
Practically, the PMEs will not be
operating for all times within a work site.
The utilization rates would depend on the construction sequences, work
fronts scale and construction nature. In
this assessment, the utilization rates for each work front during different
periods have been reviewed by the engineer and have been concluded to be
practicable for the purpose of this EIA.
Appendix 5.4A summarizes the adopted
utilization rates and the associated SWL for different construction
sequences.
Noise Assessment Tool
An in-house program has been used
for construction noise calculations.
Initially, the program runs were conducted without any mitigation
measures (i.e. the “Unmitigated Scenario”).
Where noise level exceedance was identified, further runs would be made
assuming different combinations of mitigation measures to be incorporated (i.e.
the “Mitigated Scenario”).
Assessment Results - Unmitigated Scenario
According to the latest engineering
design, the construction works would mainly comprise of the activities as
described in Section 3.5. The corresponding Sound Power
Levels (SWLs) of these activities have been estimated according to the PME’s
SWLs and the assessment methodology in the GW-TM.
Appendices 5.5A to 5.8A present the PME inventory adopted in each construction works area,
including west portion, central portion and east portion.
Appendices 5.5B to 5.8B present the distance between the notional sources and the NSRs,
screening effects due to terrains etc. Appendices 5.5C to 5.8C present the monthly unmitigated noise contribution during the
construction period. Appendices 5.5D to 5.8D also present the unmitigated construction noise impacts at selected
representative NSRs. The predicted
construction noise impacts on the NSRs are summarized in the table below.
Table 5.13: Predicted Maximum Unmitigated Construction Noise Levels at
NSRs
NSR ID |
NSR Description |
Uses |
Criterion [1] dB(A) |
Unmitigated Noise Level [2] dB(A) |
Exceedance dB(A) |
West Portion |
|||||
W-N1A |
Yau Ma Tei Catholic Primary
School (Hoi Wang Road) |
E |
70 (65) |
82 |
12
(17) |
W-N2 |
Charming Garden Block 12 |
R |
75 |
80 |
5 |
W-N3 |
Yau Ma Tei Catholic Primary
School (Tung Kun Street) |
E |
70 (65) |
92 |
22
(27) |
W-N7 |
Kum Lam Building |
R |
75 |
95 |
20 |
W-N8 |
Dickson Building |
R |
75 |
94 |
19 |
W-N8A |
Tak Cheong Building |
R |
75 |
95 |
20 |
W-N10A |
Alhambra Building (North
façade) |
R |
75 |
89 |
14 |
W-N10B |
Alhambra Building (West
façade) |
R |
75 |
88 |
13 |
W-N11 |
Hong Kong Community College
(HKCC) of the HK[3] |
E |
70 (65) |
85 |
15
(20) |
W-N15 |
HKMA David Li Kwok Po College |
E |
70 (65) |
81 |
11
(16) |
W-N18 |
Hydan Place |
R |
75 |
91 |
16 |
W-N19 |
Methodist College |
E |
70 (65) |
79 |
9
(14) |
W-N21 |
Temple Street No. 56 |
R |
75 |
83 |
8 |
W-N22 |
Kamly Court |
R |
75 |
84 |
9 |
W-N23 |
Hang Wan House |
R |
75 |
86 |
11 |
W-N24 |
Prosperous Garden Block 5 |
R |
75 |
85 |
10 |
W-N25A |
Prosperous Garden Block 1 |
R |
75 |
93 |
18 |
W-N31 |
Shanghai Street No. 217-225 |
R |
75 |
95 |
20 |
W-N32 |
Sing On Building |
R |
75 |
92 |
17 |
W-P6 |
Refuse Collection Point and
Street Sleepers’ Shelters (Planned) |
R |
75 |
84 |
9 |
W-P9 |
The Coronation |
R |
75 |
85 |
10 |
W-P11 |
The Coronation |
R |
75 |
88 |
13 |
W-P12 |
The Coronation |
R |
75 |
84 |
9 |
Central Portion |
|||||
M-N1 |
Kar Man House, Oi Man Estate |
R |
75 |
80 |
5 |
M-N2 |
Carmel on the Hill |
R |
75 |
77 |
2 |
M-N3 |
SKH Tsoi Kung Po Secondary
School |
E |
70 (65) |
83 |
13
(18) |
M-N4 |
Man Fuk House Block A |
R |
75 |
77 |
2 |
M-N5 |
Cascades Block A |
R |
75 |
76 |
1 |
M-N6 |
Ko Fai House, Kwun Fai Court |
R |
75 |
86 |
11 |
M-P2 |
Planned Residential Area B
(Planned) |
R |
75 |
88 |
13 |
M-P3 |
Planned Residential Area B
(Planned) |
R |
75 |
90 |
15 |
East Portion |
|||||
E-N6 |
Grand Waterfront Tower 5 |
R |
75 |
89 |
14 |
E-N11 |
Holy Carpenter Primary School |
E |
70 (65) |
80 |
10
(15) |
E-N12 |
Grand Waterfront Tower 3 |
R |
75 |
89 |
14 |
E-N13 |
Grand Waterfront Tower 1 |
R |
75 |
84 |
9 |
E-N14 |
Chong Chien Court Block J |
R |
75 |
82 |
8 |
E-N15 |
Hang Chien Court Block I |
R |
75 |
91 |
16 |
E-N19 |
Buddhist Chi King Primary
School |
E |
70 (65) |
65 |
- |
E-N20 |
Hing Yan Street No. 29 |
R |
75 |
88 |
13 |
E-N21 |
Hang Chien Court Block J |
R |
75 |
94 |
19 |
E-N22 |
Hang Chien Court Block H |
R |
75 |
90 |
15 |
E-P20 |
Site 1I3 (Planned) |
R |
75 |
77 |
2 |
Barging Point |
|||||
B-N1 |
Grand Horizon |
R |
75 |
66 |
- |
Notes:
[1] Values in parentheses indicate the noise criterion
during examination period of educational institution.
[2] Bolded values mean exceedance of the relevant
noise criteria.
[3] Central air-conditioning is provided, result
is for indicative purpose.
Mitigation Measures
The predicted construction noise levels show that the unmitigated construction noise impacts would exceed the daytime noise criteria. Mitigation measures are therefore required. The following mitigation measures have been considered:
·
Good site practices to limit noise emissions at the
source;
·
Use of quiet plant and working methods;
·
Use of site hoarding as noise barrier to screen
noise at ground level of NSRs;
·
Use of shrouds / temporary noise barriers to screen
noise from relatively static PMEs;
·
Use of large full enclosure to screen all
the plant, wherever practicable;
·
Large full enclosure for mucking out points;
·
Scheduling of construction works outside school
examination periods in critical area; and
·
Alternative use of plant items within one worksite,
wherever practicable.
The above mitigation measures would need to be implemented in all work sites as good practices. It should be noted that whilst “Good Practice” mitigation measures would help to alleviate the noise impacts, some of these measures have not be included in the quantitative assessment as discussed in the following sections. This would ensure a more conservative assessment.
Detailed descriptions of these
mitigation measures are given in the following sections.
Good
Site Practices and Noise Management Techniques
Good site practice and noise management techniques could considerably reduce the noise impact from construction site activities on nearby NSRs. The following measures should be followed during each phase of construction:
·
only well-maintained plant should be operated
on-site and plant should be serviced regularly during the construction
programme;
·
machines and plant (such as trucks, cranes) that
may be in intermittent use should be shut down between work periods or should
be throttled down to a minimum;
·
plant known to emit noise strongly in one
direction, where possible, be orientated so that the noise is directed away
from nearby NSRs;
·
silencers or mufflers on construction equipment
should be properly fitted and maintained during the construction works;
·
mobile plant should be sited as far away from NSRs
as possible and practicable; and
· material stockpiles, site office and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.
The benefits of these techniques can vary according to specific site conditions and operations. The environmental noise climate would certainly be improved through these control practices, although the improvement can only be quantified during implementation when specific site parameters are known. The assessment has therefore not taken into account the effectiveness of “Good Site Practices and Noise Management Techniques”.
Use
of “Quiet” Plant and Working Methods
The use of quiet plant is a feasible solution to tackle adverse noise impacts associated with construction works. It is generally known (supported by field measurement) that particular models of construction equipment are quieter than standard types given in the TM-GW. Whilst it is generally considered too restrictive to specify that the Contractor has to use specific models or items of plant, it is reasonable and practicable to set plant noise performance specifications for specific PME so that some flexibility in selection of plant is allowed. A pragmatic approach would be to request that the Contractor independently verifies the noise level of the plant proposed to be used and demonstrates through furnishing of these results, that the plant proposed to be used on the site meets the requirements.
An inventory of SWLs of quiet plant associated with the construction works is given in EPD’s Quality Powered Mechanical Equipment (QPME) and additional reference is made to typical SWLs for international manufacturer. It should be also noted that while various types of silenced equipment could be found in Hong Kong, EPD when processing a CNP application for evening or night time works may apply the noise levels specified in the TM-GW and TM-DA. CNP applications which contain sufficient details of any particularly quiet items of PME or any special noise control measures which the CNP applicant proposes to employ on the site may be given special consideration by the Noise Control Authority.
A summary of the “Quiet” PMEs adopted and the associated SWLs is given in Appendix 5.4A.
Use
of Site Hoarding
Purpose built temporary noise barriers (approximately 2.5m high) located on the site boundaries between noisy construction activities and NSRs could generally reduce noise levels at low-level zone of NSRs through partial screening. In general, this would provide minimum 5 dB(A) attenuation for the low level receivers. It would be possible for the Contractor to provide these in the form of site hoardings to achieve this attenuation effect, provided that the barriers have no openings or gaps. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period. For conservative assessments, however, the site hoarding has not been taken into consideration in the construction noise assessments.
Use of Temporary Noise
Barrier & Enclosure (with Sufficient Ventilation)
Movable temporary noise barriers that can be located close to noisy plant and be moved concurrently with the plant along a worksite can be very effective for screening noise from NSRs. A typical design which has been used locally is a wooden framed barrier with a small-cantilevered on a skid footing with 25mm thick internal sound absorptive lining. This measure is particularly effective for low level zone of NSRs. A cantilevered top cover would be required to achieve screening benefits at upper floors of NSRs.
Movable barriers will be used for some PME (e.g. asphalt paver, excavator etc). It is anticipated that suitably designed barriers could achieve at least 5 - 10dB(A) reduction. For a conservative assessment, only a reduction of 5dB(A) is assumed. Acoustic mat will be used for other plant items such as trench cutter, piling, oscillator and drilling rig and a 10 dB(A) noise reduction is anticipated. Barrier material with surface mass at least 7kg/m2 is recommended to achieve the predicted screening effect. This assumption has been adopted in other approved EIA Reports.
The use of enclosure (with sufficient ventilation and surface mass at least 10 kg/m2) has been considered in this assessment to shelter relatively static plant including air compressor, generator. The enclosures barriers can provide about 10dB(A) noise reduction.
A summary of the temporary movable
barriers and enclosures adopted for various PMEs, and the associated noise
reduction is given in Appendix 5.4A.
Appendix 5.4B
shows the sketch of typical temporary noise barrier / enclosure.
As
mentioned in Section 3.5.1, the re-provision of the existing Gascoigne Road
Flyover (GRF) at Kansu Street would be carried out in phases. The existing
east-west traffic on GRF (with one traffic lane in each direction) will be
maintained throughout the construction period by the use of temporary bridge
structures to divert the traffic near the demolished YMT multi-storey
car-park. Due to the complex
construction phasing for the re-provisioned of GRF, it has been found
infeasible to install either semi or full enclosure as a temporary noise
mitigation measure for the temporary bridge decking during construction
stage. However, a 2-3m tall temporary
noise barrier will be applied where applicable on the temporary bridge
structures during the construction stage.
The exact extent of the temporary noise barriers would be adjusted to
suit the need for temporary traffic arrangement as well as the phasing of the
permanent re-provisioned GRF. Moreover,
subject to no conflicts with the traffic diversion work, the traffic noise
barriers could be constructed in an earlier stage of the construction programme
in order to provide screening during the construction phase.
Large
Full Enclosure for Mucking Out Points
Another possible mitigation measures
is large full enclosure for entire construction site will be used
during construction of cut-and-cover tunnel and mucking out points. A larger enclosure for the entire construction site of cut-and-cover tunnel would provide better noise attenuation than the use of temporary noise
barriers / acoustic mats. However, the
height of the enclosure for entire construction site of cut-and-cover tunnel would need to be at least 9m in order to accommodate all the plant. Given the nature of construction works, having such a tall barrier would
impose adverse visual impacts to the neighbouring receptors and pedestrians.
In view of the potential nuisance / impacts on the access and engineering feasibility, the use of large enclosure could only be provided for the proposed three mucking out points and is not recommended for the entire construction sites of cut-and-cover tunnel.
According to the current construction methodology, mucking-out points will be located in west, central and east portion as shown in Figure 3.1.1, Figure 3.1.2 and Figure 3.1.3 respectively. Since the mucking out activities will be located in the vicinity of residential premises, noise enclosures would be provided to screen off these loading/unloading activities. Appropriate design would also be adopted for any openings such as access, vents etc to ensure the acoustic integrity of the enclosures. By adopting full noise enclosures, it would minimize the potential construction noise generated by the construction activities. Appendix 5.4C shows the preliminary layout of the mucking out points and the associated noise enclosures.
Sequencing
Operation of Construction Plant Equipment
In practice, some plant items will
operate sequentially within the same work site, and certain reduction of the
predicted noise impacts could be achieved.
However, any additional control on the sequencing of plant will impose a
restrictive constraint to the Contractor on the operation and planning of plant
items, and the implementation of the requirement would be difficult to be
monitored. Hence, sequencing operation
of PME has not been taken into consideration in the construction noise
assessments.
Assessment Results - Mitigated Scenario
With the implementation of the
abovementioned mitigation measures, the construction noise levels at the
affected NSRs are predicted and presented in the following tables. The predicted noise levels at most of the
NSRs would comply with the corresponding noise criteria, except some NSRs near
the works area at Kansu Street and Ferry Street. Non-compliance at these NSRs is due to the
shorter separation distance between the worksites.
Appendices 5.5E to 5.7E present the mitigated noise contribution on a monthly basis during the
construction period. Appendices 5.5F to 5.7F present the predicted mitigated construction noise levels at selected
representative NSRs. The predicted construction noise impacts on the NSRs are
summarized in the table below.
Table 5.14: Predicted Maximum Mitigated Construction Noise Levels at
NSRs
NSR ID |
NSR Description |
Uses |
Criterion [1] dB(A) |
Mitigated Noise Level [2] dB(A) |
Exceedance dB(A) |
West Portion |
|||||
W-N1A |
Yau Ma Tei Catholic Primary
School (Hoi Wang Road) |
E |
70 (65) |
70 |
- (5) |
W-N2 |
Charming Garden Block 12 |
R |
75 |
68 |
- |
W-N3 |
Yau Ma Tei Catholic Primary
School (Tung Kun Street) |
E |
70 (65) |
80 |
10 (15) |
W-N7 |
Kum Lam Building |
R |
75 |
80 |
5 |
W-N8 |
Dickson Building |
R |
75 |
81 |
6 |
W-N8A |
Tak Cheong Building |
R |
75 |
82 |
7 |
W-N10A |
Alhambra Building (West
façade) |
R |
75 |
77 |
2 |
W-N10B |
Alhambra Building (West
façade) |
R |
75 |
75 |
- |
W-N11 |
Hong Kong Community College
(HKCC) of the HK[4] |
E |
70 (65) |
73 |
3 (8) |
W-N15 |
HKMA David Li Kwok Po College |
E |
70 (65) |
70 |
- (5) |
W-N18 |
Hydan Place |
R |
75 |
78 |
3 |
W-N19 |
Methodist College |
E |
70 (65) |
65 |
- |
W-N21 |
Temple Street No. 56 |
R |
75 |
68 |
- |
W-N22 |
Kamly Court |
R |
75 |
69 |
- |
W-N23 |
Hang Wan House |
R |
75 |
72 |
- |
W-N24 |
Prosperous Garden Block 5 |
R |
75 |
72 |
- |
W-N25A |
Prosperous Garden Block 1 |
R |
75 |
81 |
6 |
W-N31 |
Shanghai Street No. 217-225 |
R |
75 |
80 |
5 |
W-N32 |
Sing On Building |
R |
75 |
79 |
4 |
W-P6 |
Refuse Collection Point and
Street Sleepers’ Shelters (Planned) |
R |
75 |
72 |
- |
W-P9 |
The Coronation |
R |
75 |
73 |
- |
W-P11 |
The Coronation |
R |
75 |
77 |
2 |
W-P12 |
The Coronation |
R |
75 |
72 |
- |
Central Portion |
|||||
M-N1 |
Kar Man House, Oi Man Estate |
R |
75 |
66 |
- |
M-N2 |
Carmel on the Hill |
R |
75 |
63 |
- |
M-N3 |
SKH Tsoi Kung Po Secondary
School |
E |
70 (65) |
70 |
- (5) |
M-N4 |
Man Fuk House Block A |
R |
75 |
63 |
- |
M-N5 |
Cascades Block A |
R |
75 |
63 |
- |
M-N6 |
Ko Fai House, Kwun Fai Court |
R |
75 |
73 |
- |
M-P2 |
Planned Residential Area B
(Planned) |
R |
75 |
73 |
- |
M-P3 |
Planned Residential Area B (Planned) |
R |
75 |
75 |
- |
East Portion |
|||||
E-N6 |
Grand Waterfront Tower 5 |
R |
75 |
75 |
- |
E-N11 |
Holy Carpenter Primary School |
E |
70 (65) |
66 |
-
(1) |
E-N12 |
Grand Waterfront Tower 3 |
R |
75 |
75 |
- |
E-N13 |
Grand Waterfront Tower 1 |
R |
75 |
71 |
- |
E-N14 |
Chong Chien Court Block J |
R |
75 |
70 |
- |
E-N15 |
Hang Chien Court Block I |
R |
75 |
76 |
1 |
E-N19 |
Buddhist Chi King Primary
School |
E |
70 (65) |
51 |
- |
E-N20 |
Hing Yan Street No. 29 |
R |
75 |
75 |
- |
E-N21 |
Hang Chien Court Block J |
R |
75 |
79 |
4 |
E-N22 |
Hang Chien Court Block H |
R |
75 |
75 |
- |
E-P20 |
Site 1I3 (Planned) |
R |
75 |
63 |
- |
Notes:
[1] Values in parentheses indicate the noise criterion
during examination period of educational institution.
[2] Bolded values mean exceedance of the relevant
noise criteria.
[3] No exceedance is predicted during examination
period.
[4] Central air-conditioning is provided, result
is for indicative purpose.
Concurrent Project
As discussed in Chapter 1, the tentative commencement year for the construction of CKR is 2015, and would take about 5 years for completion. All potential concurrent projects, which may have cumulative environmental impacts during the construction and operational phases of CKR, have been identified based on the latest available information and detailed in Section 1.8.
Kai Tak Development (KTD)
As discussed in Section 1.8, the construction of Kai Tak Development would be concurrent with the construction of the CKR east portion. Besides, the KTD EIA has shown that there would cause of noise impact to the NSRs at east portion of CKR, therefore, the cumulative construction noise impacts due to the construction of KTD would be significant.
SCL – Tai Wai to Hung Hom Section
The construction period of the SCL
project is expected to overlap concurrently with the Project. However, the construction impacts from SCL at
the identified NSRs would be screened by nearby buildings, cumulative impact
from construction of SCL and the Project is therefore not anticipated.
Trunk
Road T2 and Infrastructure at South Apron
According to the project proponent of Trunk Road T2, the T2 project is scheduled to commence concurrently with the Project. As the construction impacts from Trunk Road T2 will be out of 300m of the NSRs of CKR, cumulative impact from construction of Trunk Road T2 and the Project is therefore not anticipated.
Proposed Road Improvement in West
Kowloon Reclamation Development
According to the project proponent of this proposed road improvement project, it is scheduled to commence concurrently with the Project. As most of the construction impacts from this proposed road improvement project will be out of 300m of the NSRs of CKR except the Scheme J of the proposed road improvement project which is approximately 240m away from the nearest NSR (W-N1A). The project is still under studied and its EIA is still under preparation, hence, no available information for assessing the cumulative construction airborne noise. Nevertheless, sensitivity test of cumulative construction airborne has been carried out. Similar activity of CKR (workfront 50d – Road works for re-align Ferry Street at-grade road as in Appendix 5.5A) with a SWL of 107 dB(A) is assumed. Given the separation distance between Scheme J and the nearest NSR (W-N1A) is approximately 240m, the SPL at W-N1A is predicted at 53 dB(A) which is 10dB(A) lower than the construction noise impact of 70 dB(A) from CKR, the cumulative impact from construction of this proposed road improvement project and the Project is therefore insignificant.
The Hong Kong Section of
Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL)
According to the approved EIA Study
“Hong Kong Section of Guangzhou - Shenzhen - Hong Kong Express Rail Link”
(AEIAR-143/2009), all the construction works in West Kowloon area is scheduled
to be completed by end of 2014. According to the latest VEP-377/2012 approved by EPD on 26 Oct 2012, the
location of concrete batching plant for XRL will be revised. This concrete batching plant will remain in
the same works area (Works Area V, Zone 1 – WKCD Area). As stated in this VEP, the associated
construction programme of (Works Area V, Zone 1 to Zone 3) will be six-month
beyond the construction programme stated in the XRL EIA, i.e. June 2015. Cumulative construction airborne noise impact
would need to be assessed. However,
given the separation distance between the nearest NSR (W-P12 – The Coronation)
and (Works Area V, Zone 1 to Zone 3) is greater than 300m, the cumulative
construction airborne noise impact is considered insignificant.
Assessment Results - Cumulative Noise Impact with Concurrent Projects
Amongst the NSRs considered, some of
them would experience cumulative construction noise impacts from other
concurrent projects (see Section 1.8). The construction activities
related from the construction Kai Tak Development have been included in the
assessment. The following table
summarizes the results for the selected NSRs.
Table 5.15: Cumulative Noise Impact with Concurrent Projects
NSR ID |
NSR Description |
Uses |
Construction Noise dB(A) |
Criterion dB(A) |
Total [2] dB(A) |
Exceedance
[1] dB(A) |
|
CKR |
KTD |
||||||
E-N6 |
Grand Waterfront Tower 5 |
R |
75 |
78 |
75 |
80 |
5 |
E-N11 |
Holy Carpenter Primary School |
E |
66 |
86 |
70 (65) |
86 |
16 (21) |
E-N12 |
Grand Waterfront Tower 3 |
R |
75 |
78 |
75 |
80 |
5 |
E-N13 |
Grand Waterfront Tower 1 |
R |
71 |
78 |
75 |
79 |
4 |
E-N14 |
Chong Chien Court Block I |
R |
70 |
78 |
75 |
79 |
4 |
E-N15 |
Hang Chien Court Block I |
R |
76 |
78 |
75 |
80 |
5 |
E-N19 |
Buddhist Chi King Primary School |
E |
51 |
68 |
70 (65) |
68 |
- (3) |
E-N20 |
Hing Yan Street No. 29 |
R |
75 |
74 |
75 |
78 |
3 |
E-N21 |
Hang Chien Court Block J |
R |
79 |
78 |
75 |
82 |
7 |
E-N22 |
Hang Chien Court Block H |
R |
75 |
78 |
75 |
80 |
5 |
Notes:
[1] Values in parentheses indicate the noise criterion
during examination period (typical examination period in May, June, November
and December) of educational institution.
[2] Bolded values mean exceedance of the noise
criteria.
From the above table, the cumulative noise impact with a maximum of adverse residual impacts exceeding the construction noise criterion of 1-21 dB(A). The noise impacts due to the Project are only 51-79 dB(A) which were much lower than those contributed by Kai Tak Development (KTD). Adverse residual cumulative impact exceeding the construction noise criterion would be contributed from the construction activities of KTD. However, the EIA study of KTD indicated that all practicable mitigation measures have been fully explored and exhausted to reduce the noise impact arising from construction activities of KTD.
Adverse Residual Noise Impact from the Project Exceeding the Construction Noise Criterion
As discussed above, even with all practicable construction noise mitigation measures adopted, such as the use of quiet PME, temporary movable noise barrier and enclosure, adverse residual impacts exceeding the construction noise criterion are still expected at some NSRs, as summarized in the table below. Only those NSRs with adverse residual construction noise impact from the Project exceeding the construction noise criterion are shown.
Table 5.16: Adverse Residual Impacts at Noise Sensitive Receivers
NSR ID |
NSR Description |
Uses |
Criterion [1] dB(A) |
Maximum Mitigated Noise Level dB(A) |
Exceedance dB(A) |
Duration for Maximum Noise Level (Month) [5] |
W-N1A |
Yau Ma Tei Catholic Primary
School (Hoi Wang Road) |
E |
70 (65) |
70
(69) |
- (4) [2] |
-
(1) |
W-N3 |
Yau Ma Tei Catholic Primary
School (Tung Kun Street) |
E |
70 (65) |
80
(80) |
10 (15) [2] |
6
(2) |
W-N7 |
Kum Lam Building |
R |
75 |
80 |
5 |
1 |
W-N8 |
Dickson Building |
R |
75 |
81 |
6 |
1 |
W-N8A |
Tak Cheong Building |
R |
75 |
82 |
7 |
2 |
W-N10A |
Alhambra Building (North
façade) |
R |
75 |
77 |
2 |
1 |
W-N11 |
Hong Kong Community College
(HKCC) of the HK [6] |
E |
70 (65) |
73
(73) |
3 (8) |
5
(1) |
W-N15 |
HKMA David Li Kwok Po College |
E |
70 (65) |
70
(69) |
- (4) |
-
(1) |
W-N18 |
Hydan Place |
R |
75 |
78 |
3 |
1 |
W-N25A |
Prosperous Garden Block 1 |
R |
75 |
81 |
6 |
3 |
W-N31 |
Shanghai Street No. 217-225 |
R |
75 |
80 |
5 |
1 |
W-N32 |
Sing On Building |
R |
75 |
79 |
4 |
5 |
W-P11 |
The Coronation |
R |
75 |
77 |
2 |
1 |
M-N3 |
SKH Tsoi Kung Po Secondary
School |
E |
70 (65) |
70
(68) |
- (3) [2] |
- (1) |
E-N11 |
Holy Carpenter Primary School |
E |
70 (65) |
66
(66) |
- (1) [2] |
-
(2) |
E-N15 |
Hang Chien Court Block I |
R |
75 |
76 |
1 |
6 |
E-N21 |
Hang Chien Court Block J |
R |
75 |
79 |
4 |
6 |
Notes:
[1] Values in parentheses indicate the noise
criterion during examination period (typical examination period in May, June,
November and December) of educational institution.
[2] Residual impact is only expected during the
examination period (typical examination period in May, June, November and
December) of the educational institution.
[3] In general practice, examination period
should only last for 2 weeks. By scheduling the construction works to avoid the
examination period, the adverse residual impact should be minimised.
[4] Values in parentheses indicate the duration
of adverse residual impact in consideration of the noise criterion during
examination period.
[5] Please refer to Tables 5.17 to 5.20 for the total impact duration for noise exceedance.
[6] Central air-conditioning is provided, result
is for indicative purpose.
The above table indicates that the maximum adverse residual impacts and the associated duration despite of the implementation of all practicable noise mitigation measures.
As discussed in this chapter, extensive mitigation measures have been considered and implemented exhaustively to abate construction noise impacts on neighboring NSRs. These mitigation measures include but not limited to the use of quiet construction plant, movable noise barrier, noise enclosure, acoustic mat etc. With all the mitigation measures implemented, assessment results indicate that the majority of the NSRs would comply with the noise criteria in TM-EIAO. Only a small portion of the NSRs closer to the cut-and-cover tunnel at Kansu Street of West Portion and two NSRs (Hang Chien Court Block I and Block J) of East Portion would have adverse residual construction noise impact and one NSR (Holy Carpenter Primary School) of East Portion would have adverse residual construction noise impact during examination period.
It should be noted that these NSRs near Kansu Street are affected by the construction of the cut-and-cover tunnel (e.g. diaphragm wall installation, excavation, mucking-out etc) and the demolition of the existing GRF. For the construction of the cut-and-cover tunnel in particular, the construction methodology has given prudent considerations at the outset to minimize construction noise as far as practicable to use the top-down approach. By adopting this top-down approach, once the diaphragm walls are completed, cross walls and the ground will be excavated to the tunnel roof level and the tunnel roof slab constructed. This first stage of excavation and roof slab works will be undertaken beneath temporary decking. This decking provides a platform for pedestrian and road traffic whilst also containing the noise and dust produced by the works being carried out beneath. Once the deck is installed, the only noise sources would be the mucking out locations at which full enclosure would be installed. These full enclosure for the mucking out locations could be designed to achieved a minimum noise reduction of 15 dB(A). In order to further mitigate the noise nuisance, the full enclosure for the mucking out location would be further optimized to accommodate mobile construction plant such as lorries and dump trucks to stay inside during loading and unloading activities. All these would alleviate the noise impacts in terms of both the maximum noise level and the duration of impacts.
However, this top-down approach could still inevitably generate some noise nuisance during the installation of diaphragm-walls, initial excavation and the final reinstatement. Hence, the possibility of adopting a large full enclosure with at least 9m to accommodate all the plant including diaphragm wall rigs etc have been considered. However, in view of the limited space available between the proposed diaphragm wall and the buildings frontage along Kansu Street, it would be impractical to provide a large full enclosure in Kansu Street. Besides, given the setting of Kansu Street, having such a tall enclosure would impose adverse visual impacts to the neighboring receivers and pedestrians. It may also cause lot of inconvenience or disturbance to the neighboring commercial activities at street level. On this basis, it is considered not practicable to install a large full enclosure to enclose the entire cut-and-cover tunnel section in Kansu Street.
For the demolition of the existing GRF, given that the demolition activities have to be conducted on the viaduct, it is not practicable to install any full enclosure to provide noise screening. The use of quiet construction plant, movable noise barrier, noise enclosure, acoustic mat etc are the most practicable approach to minimize construction noise impacts and these measures have been included in the noise assessment. The adverse residual construction noise impacts on a small portion of the NSRs as shown in the following table.
Table 5.17: Adverse residual Noise Impacts (Residential Premises)
NSR-ID |
Impact Duration (Month) for Noise Exceedance |
|||
1 –4 dB(A) |
5 dB(A) |
6 dB(A) |
7 dB(A) |
|
W-N7 |
26 |
1 |
- |
- |
W-N8 |
11 |
4 |
1 |
- |
W-N8A |
26 |
5 |
4 |
2 |
W-N10A |
1 |
- |
- |
- |
W-N18 |
10 |
- |
- |
- |
W-N25A |
6 |
- |
3 |
- |
W-N31 |
38 |
1 |
- |
- |
W-N32 |
5 |
- |
- |
- |
W-P11 |
4 |
- |
- |
- |
E-N15 |
6 |
- |
- |
- |
E-N21 |
6 |
- |
- |
- |
It can be noted that most of these
receivers would exceeding the relevant noise criteria by less than
5dB(A). There are only five receivers
with adverse residual construction noise impacts greater than or equal to 5dB(A) from the criterion. These
five receivers include Kum Lam Building (W-N7), Dickson Building (W-N8), Tak Cheong Building (W-N8A), Prosperous Garden
(W-N25A) and Shanghai Street No. 217-225 (W-N31).
Evaluation of
Adverse Residual Impact
Cut-and-cover
tunnel at Kansu Street
Out of these five receivers, the noise impacts on Dickson Building (W-N8) would only exceed the relevant noise criteria up to 6dB(A). The number of months that would be exposed to 5dB(A) or above the relevant criteria would be 5 months. The number of months of noise impact with exceeding the relevant noise criteria by less than 5dB(A) would be 11 months.
The other receiver, Tak Cheong
Building (W-N8A), is located closer to the mucking out location and hence would
be experiencing higher construction noise impacts. According to the analysis, the noise impacts
on Tak Cheong Building (W-N8A) would exceed the relevant noise criteria up to
7dB(A). The number of months that would
be exposed to 7dB(A) above the relevant criteria would be 2 months. The number of
months of noise impact with exceeding the relevant noise criteria up to 5dB(A) or above would be 11 months and the number of months of noise impact with
exceeding the relevant noise criteria by less than 5dB(A) would be 26
months. It should be noticed that
construction activity contributing noise impact with exceeding the relevant
noise criteria by 5dB(A) or above is the construction of diaphragm
wall where located next to this sensitive receiver. Mitigation measures including use of quiet
plant, acoustic mat, insulation fabric, movable noise barrier have already been
applied on this construction activity.
For the period of noise impact with exceeding the relevant noise
criteria by less than 5dB(A) would be 26 months, the main construction activity would be the construction of
cut-and-cover tunnel.
The other two receivers, Kum Lam
Building (W-N7) and Shanghai Street No. 217-225 (W-N31), are located closer to
the construction of access shaft and mucking out location and hence would be
experiencing higher construction noise impacts.
According to the analysis, the noise impacts on Kum Lam Building (W-N7)
and Shanghai Street No. 217-225 (W-N31) would exceed the relevant noise
criteria up to 5dB(A). Both the number
of month of noise impact with exceeding the relevant noise criteria up to
5dB(A) on these two receivers would be 1 month and the number of months of
noise impact with exceeding the relevant noise criteria by less than 5dB(A) on
Kum Lam Building (W-N7) and Shanghai Street No. 217-225 (W-N31) would be 26
months and 38 months respectively.
The
feasibility of having a full enclosure for the entire cut-and-cover tunnel has
also been considered. However, in view of the limited space available between the proposed diaphragm
wall and the buildings frontage along Kansu Street, it would be impractical to
provide a large full enclosure in Kansu Street.
Besides, given the setting of Kansu Street, having such a tall enclosure
would impose adverse visual impacts to the neighboring receivers and
pedestrians. It may also cause lot of
inconvenience or disturbance to the neighboring commercial activities at street
level. On this basis, it is considered
not practicable to install a large full enclosure to enclose the entire
cut-and-cover tunnel section in Kansu Street. All
practicable mitigation measures including the top-down approach along the
cut-and-cover tunnel along Kansu Street, traffic deck, avoidance of unloaded
activity above traffic deck and full enclosure for mucking out location have
been applied and exhausted.
Gascoigne
Road Flyover (Ferry Street)
The other receiver, Prosperous Garden (W-N25A), is located closer to the re-aligned Ferry Street (at-grade) and hence would be experiencing higher construction noise impacts. According to the analysis, the noise impacts on Prosperous Garden (W-N25A) would exceed the relevant noise criteria up to 6dB(A). The number of months of noise impact with exceeding the relevant noise criteria up to 5dB(A) or above would be 3 months and the number of months of noise impact with exceeding the relevant noise criteria by less than 5dB(A) would be 6 months. It should be noticed that construction activity contributing noise impact with exceeding the relevant noise criteria by 6dB(A) is the construction of foundation for noise enclosure on GRF Flyover (Ferry Street Section) where located next to this sensitive receiver. The number of PME used has been reviewed as practicable for the construction programme, the dominate noise source would be concrete lorry mixer, bored piling and vibratory compactor for the construction of noise enclosure foundation, mitigation measures including use of quiet plant, acoustic mat, insulation fabric and movable noise barrier have already been applied on this construction activity. However given the short separation distance of around 25m, W-N25A would be experiencing higher construction noise impacts. For the period of noise impact with exceeding the relevant noise criteria by less than 5dB(A) would be 26 months, the main construction activity would be the construction of cut-and-cover tunnel.
The feasibility of having a full enclosure for the entire Gascoigne Road Flyover has been considered. However, in view of the limited space available on the Gascoigne Road Flyover, it would be impractical to provide a large full enclosure on the existing structure. As explained in the above paragraphs, all the practicable mitigation measures (including moveable barrier/ enclosure, quiet PME and scheduling of works) have been implemented. Hence, the adverse residual noise impacts have been minimized.
The magnitude of the residual impacts is assessed in accordance with Section 4.4.3 of the TM-EIAO below.
Table 5.18: Assessment of Residual Impacts
Criteria |
Assessment |
Effects on public health and health of biota or risk of life. |
The extent of noise nuisance would be unlikely to induce public health
concern. |
Magnitude of the adverse environmental impacts. |
Residual impacts exceeding the construction noise criterion of between
1-4 dB(A) could occur at up to
most of the NSRs, while there are receivers will have 5-7 dB(A) exceedance
during the construction phase upon worse case scenarios. |
Geographic extent of the adverse environmental impacts. |
The geographic extent of the adverse impacts from noise is anticipated
to be limited to within about 50m from the CKR project works area. |
Duration and frequency of the adverse environmental impacts. |
The adverse residual construction noise impacts of CKR will be from 1
to 39 months and are, therefore, temporary and reversible. |
Likely size of the community or the environmental that may be affected
by the adverse impacts. |
About 650 flats would be affected. In
addition, pedestrians within immediate vicinity will be temporarily affected. |
Degree to which the adverse environmental impacts are reversible or
irreversible. |
Construction phase impacts should be reversible. |
Ecological context. |
Not Applicable |
Degree of disruption to sites of cultural heritage. |
Very minimal as there would be appropriate mitigation measures, e.g.
proposed underpinning scheme, for protecting the Yau Ma Tei Police Station as
described in Section 12.6. |
International and regional importance. |
The impacts are localized and not of international and regional
importance. |
Likelihood and degree of uncertainty of adverse environmental impacts |
The impacts predicted are based upon worst case assumptions and as
such, would not occur to the extent predicted on all occasions. However, the
assessment has been made using approved modelling techniques and the degree
of certainty on the results is high. |
The adverse residual impacts exceeding the construction noise criterion on school during examination and non-examination periods are presented in Table 5.19 and Table 5.20. For assessment purpose, it is assumed that examination periods would be in May, June, November and December and they are considered to exceed the noise criterion for school examination periods.
Table 5.19 shows the adverse residual impacts exceeding the construction noise
criterion on school during their normal period. Most of the schools during
their normal period (i.e. non-examination period) would be subject to
construction noise impacts complying with the criterion, except the Yau Ma Tei
Catholic Primary School (Tung Kun Street) (W-N3) and Hong Kong Community
College (HKCC) of the HK (W-N11).
Yau Ma Tei Catholic Primary School
(Tung Kun Street) (W-N3) is at around 15m from Road works for re-align Ferry
Street at-grade road (Worksite S50d) which involves the construction of road and
piling works for the noise barrier. The
number of PME used has been reviewed as practicable for the construction
programme, the dominate noise source would be concrete lorry mixer and bored
piling for the construction of noise enclosure foundation. However given the short separation distance
of around 15m, W-N3 would be experiencing higher construction noise impacts. The
predicted exceedance on W-N3 would be up to 10 dB(A) for 6 months and the
number of months of noise impact with exceeding the relevant noise criteria
would be 9 months. The feasibility of having a full enclosure
for the Ferry Street at-grade road has been considered. However, since the construction work is
located between Ferry Street at-grade road and Ching Ping Street, a full
enclosure that could allow machinery to work safety would likely occupy certain
areas onto the existing road and hence would affect the existing traffic. On this basis, it is considered not practicable to install a large full
enclosure to enclose the Ferry Street at-grade road.
Hong Kong Community College (HKCC) of the HK (W-N11) is at around 80m from the filling embankment works and construction of retaining wall (Worksite S12) and around 60m from the Construct Noise Barrier and Diversion of Hoi Wang Road (Worksite S24b) which involves the construction of Hoi Wang Road and piling works for the semi-enclosure. The number of PME used has been reviewed as practicable for the construction programme, however given the separation distance of around 60m and W-N11 would be experiencing higher construction noise impacts. The predicted exceedance on W-N11 would be up to 3dB(A) for 5 months and the number of months of noise impact with exceeding the relevant noise criteria would be 14 months. The feasibility of having a full enclosure for the Hoi Wang Street has been considered. However, since Hoi Wang Road should be maintained operating during the construction, temporary traffic management (TTM) will be required and hence the full enclosure is not feasible.
All the practicable mitigation measures including use of quiet plant, acoustic mat, insulation fabric, movable noise barrier and scheduling of works have already been applied and exhausted on these construction activity. Hence, the adverse residual noise impacts have been minimized. To further reduce the noise impacts, it is proposed the Contractor should closely liaise with the school to avoid noisy construction works during examination period. The construction works should be carried out at summer holiday as far as possible. Furthermore, W-N11 has already provided with central conditioning, no further mitigation measures are required.
Table 5.19: Adverse residual Noise Impacts (Educational Institution
During Normal Period)
NSR-ID |
Impact Duration (Month) for Noise Exceedance |
|||||||
1dB(A) |
2dB(A) |
3dB(A) |
4dB(A) |
5dB(A) |
6dB(A) |
7dB(A) |
>=8 dB(A) |
|
W-N3 |
- |
3 |
- |
- |
- |
- |
- |
6 |
W-N11[1] |
9 |
- |
5 |
- |
- |
- |
- |
- |
Note:
[1] Central air-conditioning is provided, result
is for indicative purpose.
Further analysis has also been conducted to evaluate the potential noise impacts by adopting the noise criterion for examination period. It can be seen that a number of the schools along the alignment would be affected by construction noise during their examination periods. For assessment purpose, it is assumed that examination periods would be in May, June, November and December. The duration for construction noise impacts with exceedance during the school examination periods is shown in the table below.
Table 5.20: Adverse Residual Noise Impacts (Educational Institution
During Examination Period) [1]
NSR-ID |
Impact Duration (Month) for Noise Exceedance |
|||||||
1dB(A) |
2dB(A) |
3dB(A) |
4dB(A) |
5dB(A) |
6dB(A) |
7dB(A) |
>=8dB(A) |
|
W-N1A |
2 |
3 |
- |
1 |
- |
- |
- |
- |
W-N3 |
2 |
2 |
- |
- |
- |
- |
1 |
2 |
W-N11[2] |
- |
1 |
1 |
3 |
- |
3 |
- |
1 |
W-N15 |
- |
- |
1 |
1 |
- |
- |
- |
- |
M-N3 |
3 |
4 |
1 |
- |
- |
- |
- |
- |
E-N11 |
2 |
- |
- |
- |
- |
- |
- |
- |
Note:
[1] Typical examination period in May, June,
November and December.
[2] Central air-conditioning is provided, result
is for indicative purpose.
5.4.2
Construction
Groundborne Noise
Construction Groundborne Noise Sources
Potential construction groundborne
noise impacts on NSRs during the construction phase will arise mainly from the
operation of PME (hydraulic breaker, handheld breaker and drilling rig/ rock
drill) for drill-and-blast (D&B) activities within the tunnel. As construction activities will be conducted
during daytime, i.e. 0700-1900 on any day not being Sundays or general holidays
unless there is a need to extend the working sessions to the restricted hours
defined under the NCO. In such case, the
Contractor will apply for CNP for the carrying out of the works. Hence, construction groundborne noise
assessment will only be carried out during daytime only.
Construction Groundborne Noise Assessment Methodology
The method used to predict construction groundborne noise is based on the U.S. Department of Transportation “High-Speed Ground Transportation Noise and Vibration Impact Assessment”, 1998. The vibration level Lv,rms at a distance R from the source is related to the vibration source level at a reference distance Ro. The conversion from vibration levels to groundborne noise levels is determined by the following factors:
Cdist: Distance
attenuation
Cdamping: Soil
damping loss across the geological media
Cbuilding: Coupling
loss into building foundation
Cfloor: Coupling
loss per floor
Cnoise: Conversion
factor from floor vibration levels to noise levels
Cmulti: Noise
level increase due to multiple sources
Ccum: Cumulative
effect due to neighbouring sites
The predicted groundborne noise level Lp inside the noise
sensitive rooms is given by the following equation.
Lp = Lv,rms + Cdist + C damping +
Cbuilding + Cfloor + Cnoise + Cmulti +
Ccum
Reference Vibration Sources
The reference vibration sources of
the PME were extracted from Kowloon Southern Link EIA which is the in-situ
measurements. The geology consists of
mainly granite, which is considered similar to the geology along the
alignment. The measurements records are
considered the most appropriate available information for the purpose of
assessing construction groundborne noise.
The reference vibration sources of the PME are listed in the table
below.
Table 5.21: Reference vibration
sources of PME
PME |
Construction Site |
Vibration (rms) at the
reference distance (5.5m) from the source |
Vibration (ppv) at distance
(2m) from source |
Drilling Rig |
Salisbury Road Overrun Tunnel |
0.536 mm/s |
- |
Handheld breaker |
New World Centre site |
0.279 mm/s |
- |
Hydraulic breaker |
TST site |
0.298 mm/s |
- |
Pipeline |
MTRC TST Modification |
- |
19.3 mm/s |
Sources: Appendix 7-1 of KSL EIA
Soil Damping Loss
Internal losses of soil would cause the vibration amplitude to decay against the propagation distance and the decay relationship is based on the equation set out in the Transportation Noise Reference Book:
The velocity amplitude V is dependent on the frequency f in Hz, the soil or rock loss factor h, the wave speed c in m/s, the distance R from the source to the NSR. The properties of soil materials are based on Ungar and Bender and reproduced in the table below.
Table 5.22: Wave propagation
properties of soils
Soil Type |
Longitudinal Wave Speed c,
m/s |
Loss Factor, h |
Density, g/cm3 |
Rock |
3500 |
0.01 |
2.65 |
Clay, clayey soil |
1500 |
0.5 |
1.7 |
Coupling Loss into Building Structures
This represents the change in the incident ground-surface vibration due to the presence of the piled building foundation. The empirical values based on the guidance set out in the Transportation Noise Reference Book are given in the table below.
Table 5.23: Loss factor for
coupling into building foundation
Frequency |
Octave Band Frequencies, Hz |
|||||
16 |
31.5 |
63 |
125 |
250 |
500 |
|
Loss factor for coupling into
building foundation, dB |
-7 |
-7 |
-10 |
-13 |
-14 |
-14 |
Coupling Loss Per Floor
This represents the floor-to-floor vibration transmission attenuation. In multi-storey buildings, a common value for the attenuation of vibration from floor-to-floor is approximately 1dB attenuation in the upper floor regions at low frequencies and greater than 3dB attenuation at lower floors at high frequencies. Coupling loss of –1 dB reduction per floor is assumed for conservative assessment.
Conversion from Floor Vibration to Noise Levels
Conversion from floor vibration
levels to indoor reverberant noise levels is based on standard acoustic
principles. The conversion factor is
dependent on the surface area S of the room in m2, the radiation
efficiency η, the volume of the room V in m3 and the room
reverberation time RT in seconds. These
values are summarized in the table below and will be adopted for the present
study.
Table 5.24: Conversion factors
from floor vibration levels to indoor reverberant noise levels
NSR Description |
Conversion Cnoise |
Hotel guestrooms and residential units |
-27 |
School classrooms |
-27 |
Evaluation of Construction Ground-borne Noise Impacts
Detailed assessments have been conducted for three construction equipment (hydraulic breaker, hand-held breaker and drill rig/ rock drill), for tunneling works including drill-and-blast and mechanical excavation along the tunnel, the results are summarised in the table below. The detailed assessment results were shown in Appendix 5.9.
Table 5.25: Unmitigated Construction Groundborne Noise
NSR ID |
Use |
Predicted Noise Level, dB(A) |
Daytime Noise Criteria, dB(A)[1] |
Mitigation measure required? |
W-N10A |
Residential |
46 |
65 |
No |
W-N19 |
Education |
28 |
60 (55) |
No |
M-N1 |
Residential |
28 |
65 |
No |
M-N3 |
Education |
<20 |
60 (55) |
No |
M-N6 |
Residential |
<20 |
65 |
No |
E-N13 |
Residential |
25 |
65 |
No |
E-N14 |
Residential |
29 |
65 |
No |
Notes:
[1] Values in parentheses indicate the noise criterion
during examination period (typical examination period in May, June, November
and December) of educational institution.
Based on the assessment result as shown in the table above, the predicted construction groundborne noise levels from the tunneling work will not exceed the daytime construction groundborne noise criteria and hence no mitigation measures are required.
5.5 Operational Noise Impact Assessment
5.5.1
Road
Traffic Noise Assessment
Study Area and Project Road Extent
The CKR will be mainly underground based on the current design. Road traffic noise from the open road sections near both ends of the tunnel portals is therefore anticipated. There are no open road sections of CKR in Central Portion.
Since the Central Portion of CKR would not have any slips, traffic noise impact assessment for the Project will be separated into two areas, namely the West Portion and East Portion. With reference to the EIA Study Brief for this Project (ESB-156/2006), the study area for noise impact assessment should generally be defined by a distance of 300m from the boundary of the Project.
For the purpose of this assessment, roads will be classified as the following categories in the table below. Figures 5.4 and Figure 5.5 illustrate the extent of project roads in West Portion and East Portion respectively.
Category |
Road |
West Portion |
|
New road (By CKR) |
All part of CKR including
main and slip roads |
Material changes to existing road (By CKR) |
1. Re-provisioning of Gascoigne Road Flyover (GRF) 2. Section of Gascoigne Road Flyover (Ferry Street section) and at-grade road next to
Prosperous Garden 3. Re-alignment of Hoi Wang Road 4. Widening of Lai Cheung Road |
Planned roads (By others) |
Road D1(A)N, D1A(S), Road Works in West Kowloon and Proposed Road
Improvement Works in West Kowloon Reclamation Development Phase 1 |
Existing roads |
West Kowloon Highway, Nathan Road, etc |
East Portion |
|
New road (By CKR) |
All part of CKR including main and slip roads, Re-aligned Kai Fuk Road |
Planned roads (By others) |
D2, D3, D4 and T2 |
Existing roads |
Kai Cheung Road, Kwun Tong Bypass, etc |
Assessment Methodology
Determination of Assessment Year and Traffic Flow
During the operational phase, operation of the CKR could cause traffic noise impact on the nearby NSRs. The road carriageways involved within the assessment area, including the proposed CKR, existing roads and roads of other committed projects have been included for assessment.
The calculation method stated in the UK Department of the Transport "Calculation of road Traffic Noise" (CRTN) will be adopted. The predicted noise levels at the building facades include 2.5 dB(A) facade reflection and correction factors for effects due to gradient, distance, view angle, road surface and barriers.
In the preparation for noise prediction, the project road scheme and surrounding road networks within the Study Area have been included in the model with parameters of road width, surface type and traffic condition.
According to Clause 3.4.7.2 (vi)
(a1) of the EIA Study Brief for the Project, three scenarios would need to be carried out
as followings:
1) Unmitigated scenario at assessment year;
2) Mitigated scenario at assessment year; and
3) Prevailing scenario for indirect technical remedies eligibility assessment.
The assessment year for unmitigated and mitigated scenarios which is the future road traffic noise shall be calculated based on the peak hour traffic flow in respect of maximum traffic projection within the next 15 years upon commencement of operation of the Project.
Based on the current programme, the
CKR main works is planned for completion by late 2020. The ultimate year is then 2035 (i.e. 15 years
upon commissioning). However, traffic
forecast at 2036 has been predicted for conservation assumption for unmitigated and mitigated scenarios. The noise assessment for prevailing year would
adopt the year before the works to construct the road (i.e. 2014/2015).
Noise Model Setup
The road networks within the Study Area and the traffic flow within 300m assessment area have been summarised in Appendix 5.10. The extent of road sections paved with friction course materials have been provided by Highways Department and are shown in Appendix 5.11. The use of noise absorptive paving materials on project roads can theoretically reduce the traffic noise impact. As per the values specified in CRTN, the use of pervious road surface on road surface can reduce the basic noise level by 3.5 dB(A), as compared to that of 1.0 dB(A) for common impervious paving. This information has been included in the road traffic noise model accordingly.
In accordance with HyD Guidance Notes RD/GN/032, the extent of friction course has been considered in the unmitigated scenario and will cover the main road with design speed greater than 80 km/hr.
The standard 0.8m solid parapet
along main road and slip road of CKR has also been included in the
assessment. The graphic plot of the road
traffic noise model is shown in
Appendix 5.12.
Consideration of Noise Mitigation Measures
Consideration of noise mitigation measures will follow Annex 13 of TM-EIAO and EIAO Guidance Note “Road Traffic Noise Impact Assessment under the Environmental Impact Assessment Ordinance” [GN 12/2010].
Where the predicted noise impacts
exceed the noise criteria, direct mitigation measures shall be considered on
the proposed road to reduce the noise from the project road to a level such
that:
·
It is not higher than the standard; and
·
It has no significant contribution to the overall
noise from other existing roads, if the cumulative noise level, i.e. noise from
the new road together with other existing roads exceeds the standard (i.e. not
more than 1.0 dB(A))
According to EPD’s Guidance Note 12/2010, in the case where NSRs are still exposed to noise levels exceeding the relevant noise criteria after the implementation of all direct mitigation measures, the total number of existing dwellings, classrooms and other noise sensitive elements which may qualify for indirect technical remedies, the associated costs and any implications for such implementation should be identified and estimated. The eligibility of the affected premises for indirect technical remedies is determined with reference to the following three criteria:
·
the predicted overall noise level must be above a
specified noise level (e.g. 70 dB(A) for domestic premises and 65 dB(A) for
education institutions, all in L10,1hr);
·
the predicted overall noise level is at least 1.0
dB(A) more than the prevailing traffic noise level, i.e. the total traffic
noise level existing before the works to construct the road were commenced; and
·
the contribution to the increase in the predicted
overall noise level from the road project must be at least 1.0dB(A).
For planned noise sensitive uses are also subject to potential road traffic noise impacts and hence the overall noise levels for maximum projected traffic within 15 years will be predicted. In the case where the planned NSRs are exposed to excessive noise levels, direct mitigation measures shall be proposed to ensure compliance of the relevant noise criteria.
Evaluation of Unmitigated Road Traffic Noise Impact
The predicted road traffic noise
levels at the representative NSRs for both the West Portion and East Portion of
CKR are summarized in the table below.
Appendix 5.13 and
Appendix 5.14 show the detailed breakdown of road traffic noise impacts of West
Portion and East Portion respectively.
Table 5.27: Unmitigated
Road Traffic Noise Impact in Year 2036
NSR ID |
Uses [1] |
Noise Criteria, L10(1 hr) dB(A) |
Predicted Project Road Noise Level, L10 (1hr)
dB(A) [2] |
Predicted Overall Noise Level, L10 (1hr)
dB(A) [3] |
Contribution from Project Roads, L10 (1hr) dB(A) |
Affected Floor |
No. of dwellings/ classroom per floor assumed [4] |
West
Portion |
|||||||
W-N1A |
E |
65 |
66 – 67 |
73 – 74 |
1.0 – 1.2 |
1/F – 8/F |
1 |
W-N1B |
E |
65 |
61 |
68 |
0.8
– 0.9 |
- |
- |
W-N2 |
R |
70 |
64
- 68 |
71 – 72 |
0.7 – 2.2 |
6/F – 23/F |
5 |
W-N3 |
E |
65 |
69 – 71 |
77 – 78 |
0.8 – 0.9 |
1/F – 7/F |
4 |
W-N6 |
R |
70 |
63
– 69 |
72 – 73 |
0.6 – 2.2 |
6/F – 18/F |
6 |
W-N6A |
R |
70 |
58
- 67 |
74 – 77 |
0.1 – 1.0 |
18/F |
6 |
W-N7 |
R |
70 |
75 – 78 |
79 |
2.4 – 5.1 |
1/F – 12/F |
2 |
W-N8 |
R |
70 |
68
– 81 |
79 – 82 |
0.4 – 6.9 |
2/F – 18/F |
2 |
W-N8A |
R |
70 |
69
– 82 |
80 – 83 |
0.3 – 6.5 |
2/F – 18/F |
2 |
W-N9A |
H |
55 |
65 – 75 |
74 – 77 |
0.5 – 4.2 |
1/F – 10/F |
- |
W-N9B |
H |
55 |
67 – 77 |
72 – 78 |
1.9 – 7.4 |
1/F – 10/F |
- |
W-N10A |
R |
70 |
67
– 79 |
72 – 79 |
1.7 – 9.6 |
1/F – 15/F |
6 |
W-N10C |
R |
70 |
67
- 82 |
75 – 84 |
0.7 – 4.0 |
2/F – 15/F |
6 |
W-N11[5] |
E |
65 |
75 – 76 |
78 – 79 |
2.2 – 4.1 |
1/F – 19/F |
3 |
W-N14 |
R |
70 |
62
– 63 |
77 |
0.1
– 0.2 |
- |
- |
W-N15 |
E |
65 |
57 |
73 |
0.1 |
- |
- |
W-N18 |
R |
70 |
73 – 76 |
77 – 78 |
1.8 – 4.9 |
1/F – 17/F |
1 |
W-N19 |
E |
65 |
67 – 68 |
79 – 81 |
0.2 – 0.3 |
1/F – 6/F |
3 |
W-N20 |
R |
70 |
63
– 71 |
78 – 80 |
0.1 – 0.9 |
8/F – 15/F |
3 |
W-N21 |
R |
70 |
62
– 69 |
76 – 77 |
0.1 – 0.9 |
- |
- |
W-N22 |
R |
70 |
63
– 70 |
76 – 77 |
0.2 – 1.2 |
8/F – 10/F |
2 |
W-N23 |
R |
70 |
60
– 73 |
75 – 78 |
0.1 – 2.9 |
10/F – 23/F |
3 |
W-N24 |
R |
70 |
62
– 74 |
73 – 76 |
0.3 – 4.3 |
3/F – 27/F |
14 |
W-N25A |
R |
70 |
71 – 77 |
76 – 79 |
1.7 – 4.8 |
1/F – 28/F |
3 |
W-N25B |
R |
70 |
70
– 74 |
75 – 77 |
1.8 – 3.5 |
1/F – 28/F |
2 |
W-N26A |
R |
70 |
71 – 75 |
75 – 77 |
2.0 – 4.0 |
1/F – 28/F |
2 |
W-N26B |
R |
70 |
71 – 75 |
76 – 78 |
1.9 – 3.3 |
1/F – 28/F |
2 |
W-N27 |
R |
70 |
69
– 72 |
75 – 77 |
1.2 – 1.7 |
1/F – 28/F |
4 |
W-N28 |
R |
70 |
65
– 68 |
78
– 79 |
0.2
– 0.4 |
- |
- |
W-N29 |
W |
65 |
66 |
74 |
0.7 |
1/F |
N/A |
W-N30 |
R |
70 |
58
– 60 |
73 – 75 |
0.1 – 0.3 |
- |
- |
W-P6A |
R |
70 |
60 |
73 – 74 |
0.2
– 0.3 |
- |
- |
W-P6C |
R |
70 |
70
– 72 |
72 – 74 |
4.2 – 5.7 |
1/F – 5/F |
N/A |
W-P7A |
E |
65 |
58
– 68 |
72 – 78 |
0.2 – 0.6 |
5/F – 8/F |
N/A |
W-P7B |
E |
65 |
60
– 70 |
72 – 75 |
0.3 – 1.7 |
5/F – 8/F |
N/A |
W-P7C |
E |
65 |
49
– 59 |
57 – 62 |
0.9
– 3.0 |
- |
- |
W-P7D |
E |
65 |
54
– 64 |
66 – 68 |
0.3 – 1.6 |
6/F – 8/F |
N/A |
W-P7E |
E |
65 |
57
– 65 |
67 – 70 |
0.4 – 1.9 |
5/F – 8/F |
N/A |
W-P7F |
E |
65 |
66 – 71 |
68 – 73 |
4.0 – 6.0 |
1/F – 8/F |
N/A |
W-P7G |
E |
65 |
62
– 68 |
72 – 75 |
0.5 – 1.1 |
5/F – 8/F |
N/A |
W-P8 |
W |
65 |
65
– 70 |
76 – 77 |
0.4 – 1.1 |
2/F – 10/F |
N/A |
W-P9 |
R |
70 |
63
– 65 |
68 – 71 |
1.4 – 2.0 |
29/F – 38/F |
2 |
W-P10 |
R |
70 |
66
– 67 |
72 |
1.2 – 1.7 |
1/F – 30/F |
3 |
W-P11 |
R |
70 |
75 – 77 |
76 – 78 |
7.0 – 9.5 |
1/F – 30/F |
2 |
W-P12 |
R |
70 |
67
– 68 |
72 – 73 |
1.3 – 1.7 |
1/F – 30/F |
1 |
W-P13 |
R |
70 |
73 – 74 |
75 – 76 |
5.3 – 5.9 |
1/F – 30/F |
2 |
W-P14 |
R |
70 |
74 – 75 |
75 – 76 |
6.2 – 7.4 |
1/F – 30/F |
2 |
East
Portion |
|||||||
E-N19 |
E |
65 |
15 |
73 – 76 |
0.0 |
- |
- |
E-P1 |
R |
70 |
41
– 64 |
68 – 71 |
0.0 – 0.9 |
- |
- |
E-P6 |
CDA |
70 |
55
– 57 |
63 |
0.9
– 1.4 |
- |
- |
E-P7 |
CDA |
70 |
55
– 62 |
63 – 65 |
0.5
– 3.7 |
- |
- |
E-P8 |
R |
70 |
41
– 53 |
67 – 72 |
0.0 – 0.1 |
- |
- |
E-P13A |
H |
55 |
68 – 70 |
79 – 81 |
0.4 – 0.7 |
1/F – 14/F |
N/A |
E-P13B |
H |
55 |
63 – 65 |
78 – 80 |
0.1 – 0.2 |
1/F – 14/F |
N/A |
E-P14A |
E |
65 |
75 – 76 |
76 – 77 |
8.6 – 9.9 |
1/F – 10/F |
N/A |
E-P14B |
E |
65 |
78 |
79 |
7.7 – 8.6 |
1/F – 10/F |
N/A |
E-P14C |
E |
65 |
74 – 75 |
76 |
5.4 – 6.5 |
1/F – 10/F |
N/A |
E-P14D |
E |
65 |
46
– 55 |
46 – 55 |
7.9
– 9.6 |
- |
- |
E-P14E |
E |
65 |
62 |
64 – 65 |
2.5
– 4.2 |
- |
- |
E-P14F |
E |
65 |
64
– 66 |
65 – 67 |
5.5 – 6.2 |
4/F – 10/F |
N/A |
E-P14G |
E |
65 |
47
– 50 |
47
– 50 |
17.8
– 25.6 |
- |
- |
E-P16 |
R |
70 |
42
– 60 |
70 |
0.0 – 0.5 |
- |
- |
E-P20 |
R |
70 |
64
– 66 |
68 – 70 |
1.7 – 2.7 |
- |
- |
Notes:
[1] R – residential; E – educational; H – clinic/ home for the
aged/hospital; W – worship; GIC – government, institution and community; CDA –
Comprehensive Development Area
[2] Bold figure
denotes the noise level from Project Roads is over the relevant TM-EIAO
noise criteria.
[3] Bold figure
denotes the noise exceedance which is over the relevant TM-EIAO noise criteria
and the contribution from new roads to the overall noise level is equal to or
higher than 1.0 dB(A) /
noise levels from Project Road is over the relevant TM-EIAO noise criteria.
[4] N/A denotes
the number of dwellings / classroom cannot be determined due to planned uses.
[5] Central air-conditioning is provided, result is for indicative
purpose.
West Portion
The predicted cumulative road traffic noise level for the residential NSRs at W-N2, W-N6, W-N6A, W-N7, W-N8, W-N8A, W-N10A, W-N10C, W-N18, W-N20, W-N22, W-N23, W-N24, W-N25A, W-N25B, W-N26A, W-N26B, W-N27, W-P6C, W-P9, W-P10, W-P11, W-P12, W-P13 and W-P14 is 68 – 84 dB(A) which exceed the stipulated noise criterion of 70dB(A) and significant contribution from project roads is predicted. Noise mitigation measures are required for these receivers.
The predicted cumulative road
traffic noise level for the educational institutions NSRs at W-N1A, W-N3,
W-N11, W-N19, W-P7A, W-P7B, W-P7D, W-P7E, W-P7F and W-P7G is 57 – 81 dB(A) which exceed the stipulated noise criterion of 65dB(A) and
significant contribution from project roads is predicted. The predicted noise levels from project roads
at W-N1A, W-N3,
W-N11, W-N19, W-P7A-B and W-P7F-G has
already exceed the noise criterion of 65dB(A).
Noise mitigation measures are required for these receivers.
The predicted noise levels from
project roads for the place of public worships NSRs at W-N29 and
W-P8 has already exceed the stipulated noise criterion of 65dB(A). Noise mitigation measures are
required for these receivers.
The predicted cumulative road
traffic noise level for the clinic at W-N9A and W-N9B is 72 – 78 dB(A) which exceed the stipulated noise criterion of 55dB(A) and significant contribution from project roads is predicted.
Noise mitigation measures are required for these receivers.
East Portion
The predicted cumulative road traffic noise level for the Site 3C1 – Hospital (EP13A-B) is 78 – 81 dB(A) which exceed the stipulated noise criterion of 55 dB(A). Although the contribution from Project Roads is lesser than 1.0 dB(A) which is considered insignificant, the noise level from the Project Roads itself exceed the noise criteria of 55 dB(A). Nevertheless, according to the Kai Tak Development EIA (KTD EIA), the hospital will be noise insulated and will not rely on opened windows for ventilation. Hence, no direct mitigation measure is required.
The predicted cumulative road
traffic noise level for the Site 3B1 – School (EP14A-G) is 46 – 79 dB(A) which exceed the stipulated noise criterion of 65
dB(A). The contribution from Project
Roads is greater than 1.0 dB(A) which is considered significant, the noise
level from the Project Roads itself also exceed the noise criteria of 65
dB(A). Hence, mitigation measure is
required.
Recommended Noise Mitigation Measures
Exceedance of noise criteria are found in various sensitive receivers for both existing and planned uses, noise mitigation measures should therefore be required. According to the Section 6.1, Annex 13 of TM-EIAO, noise mitigation measures starting from direct ones should be considered and evaluated. Direct mitigation measures as listed below are recommended in the proposed CKR:
·
Low-noise road surfacing;
·
Noise barrier/ enclosure; and
·
Building orientation.
The mitigation measures in form of low-noise road surfacing and noise barrier/ enclosure above are at-source mitigation measures and were further elaborated in the following paragraphs.
When all practicable at-source mitigation measures have been exhausted, at-receiver mitigation measures would be considered in terms of building orientation, modification of layout plan and setback requirement for the planned NSRs, and consideration of provision of noise insulation for the existing NSRs where justified and eligible and liaise with relevant stakeholders.
West Portion
Use of low noise road surfacing (LNRS)
There are two areas of roads which are already paved with LNRS which are Gascoigne Road Flyover and Ferry Street at-grade road. Under the CKR project, it is also still recommended that these two areas should be paved with LNRS. The extent of LNRS is showed in Figure 5.6a & Figure 5.6b.
Noise barrier/enclosure
In view of practicability, the erection of noise barrier/ semi-enclosure along the new road sections are considered as effective mitigation measures in tackling the road traffic noise impact to sensitive receivers.
Permanent noise mitigation measures including noise barrier/ semi-enclosure/ full noise enclosure will be provided on the permanent structures prior to operation. The location of noise mitigation measures are described in the following paragraphs.
Given the high traffic flow of CKR, around total of 8000 veh/hr for both bounds, a full enclosure at the west portal is proposed. Since The Coronation (W-P11, W-P13 and W-P14) would have a full view of the CKR main road and slip roads, noise mitigation measures apart from the full enclosure (F01) for the CKR is recommended to erect along the slips road. Six 5m with 3m cantilevered section type noise barriers (C01 to C06) are recommended to erect at slip roads of CKR including Connection A, C2, D and E and Lin Cheung Road. A semi-enclosure (S01) covering south bound of Lin Cheung Road is recommended. A 3.8m vertical barrier (V02) is recommended to erect at Connection D. A 5.8m vertical barrier (V03) is recommended to erect at Connection E. All the above mitigation measures are proposed to protect The Coronation (W-P11, W-P13 and W-P14), YMT Catholic Primary School (W-N1), Charming Garden (W-N2), the planned Street Sleepers’ Shelters (W-P6) and planned school (W-P7). Another 4m vertical barrier (V01) at Lin Cheung Road is recommended to protect the planned Hindu Temple (W-P8).
For the re-aligned Hoi Wang Road, given the close proximity to high-rising The Coronation (W-P11, W-P13 and W-P14) and the planned Street Sleepers’ Shelters (W-P6) and planned school (W-P7). A semi-enclosure (S02) covering both south bound and north bound with opening at west is recommended.
For the re-provisioned Gascoigne Road Flyover (Kansu Street section), given the close proximity to high-rising buildings on both side and high traffic flow, around total of 4000 veh/hr of both bound, exceedance of road traffic noise criteria is anticipated. However, taken into consideration of ventilation system and the fire safety requirement, a 200m full enclosure (F03) covering both south bound and north bound is recommended. Moreover, there is a semi-enclosure (S03) covering south bound with opening at south and an extension of 5m from the central divider located at the west of full enclosure to protect Prosperous Garden (W-N25A). There is another semi-enclosure (S04) covering both south bound and north bound with opening at south located at the west of full enclosure to protect Prosperous Garden (W-N25A). A 3.3m vertical barrier (V05) is recommended to protect The Coronation and Dickson Building. A 3.8m vertical barrier (V06) at the central divider underneath the semi-enclosure is recommended to protect The Coronation. There is another semi-enclosure (S05) covering both south and north bounds with opening at north located at the east of full enclosure to protect the high-rising building (W-N10A) at south. A 4.3m vertical barrier (V07) and 2.8m vertical barrier (V08) on the central divider are also recommended to protect the YMT Jockey Club Polyclinic (W-N9B) due to a more stringent noise criteria of 55dB(A).
For the Gascoigne Road Flyover (Ferry Street section), about 110m full enclosure (F02) is recommended to protect Prosperous Garden, The Coronation and the planned school (W-P7).
For the Ferry Street at-grade road, a 5m with 1m cantilevered section barrier (C07) is recommended to protect the Prosperous Garden and YMT Catholic Primary School.
For the Widening of Lai Cheung Road, one 4m vertical barrier (V04) is recommended to protect the planned Sleepers’ Shelter (W-P6) and the planned school (W-P7).
The extent of noise barrier,
semi-enclosure and full enclosure is summarized in table below and showed in
Figures 5.6c to 5.6e. The noise reduction could also
be further enhanced by installing absorptive material on the noise barrier,
semi-enclosure and full enclosure.
Cross-section drawings of the noise mitigation measures are shown in
Figures 5.6f to 5.6n.
Building orientation
For W-P7,
since there is no building layout of this sensitive receiver during the
preparation of this study, the sensitive facades are selected at the boundary
of a typical building layout block for worst-case scenario. To avoid noise impact from the project roads,
it is recommended to avoid any sensitive facade facing the re-aligned Hoi Wang
Road as shown in
Figure 5.6c.
Table 5.28: Recommended
Noise Mitigation Measures
Noise Mitigation Measures ID |
Location |
Type of Noise Mitigation Measures [1] |
Height above road level (m) |
Approximate mPD |
Approximate Length (m) |
Benefited NSRs |
|
Representative Existing NSR |
Representative Planned NSR |
||||||
F01 |
West portal of CKR |
Full enclosure including landscape deck |
9 |
5.9 – 22.5 |
250 |
W-N1A, W-N2 |
W-P6, W-P7, W-P11, W-P13,
W-P14 |
F02 |
Gascoigne Road Flyover (Ferry Street section) |
Full enclosure |
10 |
22 |
110 |
W-N3, W-N25B, W-N26A, W-N26B,
W-N27, |
W-P6, W-P7, W-P10, W-P12 |
F03 |
Gascoigne Road Flyover (Kansu Street section) (NB+SB) |
Full enclosure |
7 |
19.5 – 21 |
200 |
W-N7, W-N8, W-N8A, W-N9A,
W-N9B, W-N18, W-N32 |
- |
S01 |
Lin Cheung Road |
Semi-enclosure with opening at west |
10 |
11.5 – 12.6 |
120 |
- |
W-P11, W-P13 |
S02 |
Re-aligned Hoi Wang Road |
Semi-enclosure with opening at west |
10 |
10.5 – 17.7 |
270 |
W-N2 |
W-P6, W-P7, W-P11, W-P13,
W-P14 |
S03 |
Gascoigne Road Flyover (Ferry Street section) (SB) |
Semi-enclosure with opening at south |
7 |
19.8 – 20.1 |
85 |
W-N9A, W-N24, W-N25A |
- |
S04 |
Gascoigne Road Flyover (Kansu Street section) (NB+SB) |
Semi-enclosure with opening at south |
7 |
18.1 – 19.5 |
45 |
W-9A, W-N24, W-N25A |
- |
S05 |
Gascoigne Road Flyover (Kansu Street section) (NB+SB) |
Semi-enclosure with opening at north |
7 |
21 |
60 |
W-N10A, W-N10C |
|
C01 |
Connection E |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
12.8 – 16.1 |
155 |
- |
W-P11, W-P13,
W-P14 |
C02 |
Lin Cheung Road |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
12.6 – 17.1 |
85 |
- |
W-P11, W-P13,
W-P14 |
C03 |
Lin Cheung Road |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
11.8 – 12.7 |
85 |
- |
W-P11, W-P13, W-P14 |
C04 |
Connection D |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
14.1 – 20.6 |
190 |
- |
W-P11, W-P13, W-P14 |
C05 |
Connection C2 |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
22.8 – 24.9 |
120 |
- |
W-P11, W-P13, W-P14 |
C06 |
Connection A |
5m high with 3m cantilever at 45o cantilevered barrier |
7.1 |
12.9 – 13.9 |
170 |
- |
W-P11, W-P13, W-P14 |
C07 |
Ferry Street Road (At-grade) |
5m high with 1m cantilever at 45o cantilevered barrier |
5.7 |
9.5 – 9.6 |
160 |
W-N3, W-N25B, W-N26A, W-N26B,
W-N27 |
- |
V01 |
Lin Cheung Road |
4m vertical barrier |
4 |
7.9 – 9.7 |
120 |
- |
W-P8 |
V02 |
Connection D |
3.8m vertical barrier |
3.8 |
10.8 – 17.3 |
190 |
W-N2 |
- |
V03 |
Connection E |
5.8m vertical barrier |
5.8 |
11.7 – 14.6 |
100 |
W-N2 |
- |
V04 |
Widening of Lai Cheung Road |
4m vertical barrier |
4 |
8.5 – 8.6 |
50 |
- |
W-P6, W-P7 |
V05 |
Gascoigne Road Flyover (Ferry Street section) (SB) |
3.3m vertical barrier |
3.3 |
15.3 – 16.3 |
110 |
W-N8 |
W-P10, W-P12 |
V06 |
Gascoigne Road Flyover (Ferry Street section) (central divider) |
3.8m vertical barrier |
3.8 |
15 – 15.8 |
100 |
- |
W-P10, W-P12 |
V07 |
Gascoigne Road Flyover (Kansu Street section) (SB) |
4.3m vertical barrier |
4.3 |
19.3 |
60 |
W-N9B |
- |
V08 |
Gascoigne Road Flyover (Kansu Street section) (central divider) |
2.8m vertical barrier |
2.8 |
17.8 |
60 |
W-N9B |
- |
Notes:
[1] The side(s) of noise
mitigation measures facing to the road traffic will be installed with absorptive materials/ panels.
East Portion
Use of low noise road surfacing (LNRS)
In accordance with HyD Guidance Notes RD/GN/032, the extent of friction course has been considered in the unmitigated scenario and will cover the main road with design speed greater than 80 km/hr. The extent of LNRS is showed in Figure 5.7a & Figure 5.7b.
Building orientation
According to KTD EIA, the layout of noise sensitive uses, e.g. planned schools may be arranged in a way to avoid the sensitive facades of the classrooms facing Project Roads or as the last resort all the classrooms should be noise insulated with air-conditioners to avoid unacceptable traffic noise impacts from the surrounding road network. In this principle, a sensitive test for selecting sensitive facades of the classrooms (E-P14D-E) not facing Project Roads has been carried out and discussed in the following.
The recommended noise mitigation measures for West Portion and East Portion were shown in Figures 5.6a to 5.6n and Figure 5.7a to 5.7c respectively.
Evaluation of Mitigated Road Traffic Noise Impact
With the implementation of recommended noise mitigation measures for West Portion as shown in the table above, the predicted road traffic noise levels at the representative NSRs in the vicinity of both West Portion and East Portion of CKR are summarized in the table below. Appendix 5.15 and Appendix 5.16 show the detailed breakdown of road traffic noise impacts of West Portion and East Portion respectively. Appendix 5.17 shows the sample calculation of road traffic noise.
Table 5.29: Mitigated Road Traffic Noise Impact in Year
2036
NSR ID |
Uses [1] |
Noise Criteria L10(1 hr) dB(A) |
Predicted Project Road Noise Level L10 (1hr) dB(A) [3] |
Predicted Overall Noise Level L10 (1hr) dB(A) [3] |
Contribution from Project Roads, L10 (1hr) dB(A) |
West
Portion |
|||||
W-N1A |
E |
65 |
63
– 64 |
72 – 73 |
0.4 – 0.6 |
W-N1B |
E |
65 |
60 |
68 |
0.8
– 0.9 |
W-N2 |
R |
70 |
53
– 62 |
70 – 71 |
0.0 – 0.8 |
W-N3 |
E |
65 |
53
– 63 |
74 – 77 |
0.1
– 0.2 |
W-N6 |
R |
70 |
50
– 58 |
70 – 72 |
0.0 – 0.3 |
W-N6A |
R |
70 |
50
– 58 |
72 – 77 |
0.0 – 0.1 |
W-N7 |
R |
70 |
47
– 60 |
74 – 76 |
0.0 – 0.2 |
W-N8 |
R |
70 |
46
– 65 |
73 – 79 |
0.0 – 0.7 |
W-N8A |
R |
70 |
44
– 64 |
74 – 80 |
0.0 – 0.5 |
W-N9A |
H |
55 |
39
– 45 |
73 – 74 |
0.0 |
W-N9B |
H |
55 |
41
– 55 |
70 |
0.0 – 0.1 |
W-N10A |
R |
70 |
39
– 54 |
69 – 70 |
0.0 – 0.1 |
W-N10C |
R |
70 |
39
– 53 |
75
– 79 |
0.0 |
W-N11[4] |
E |
65 |
71 – 72 |
75 – 78 |
1.2 – 1.9 |
W-N14 |
R |
70 |
62
– 63 |
77 |
0.1
– 0.2 |
W-N15 |
E |
65 |
57 |
73 |
0.1 |
W-N18 |
R |
70 |
45
– 58 |
72 – 76 |
0.0 – 0.2 |
W-N19 |
E |
65 |
61
– 63 |
79 – 81 |
0.0 – 0.1 |
W-N20 |
R |
70 |
50
– 58 |
78 – 80 |
0.0 – 0.1 |
W-N21 |
R |
70 |
47
– 50 |
76 – 77 |
0.0 |
W-N22 |
R |
70 |
47
– 50 |
75 – 77 |
0.0 |
W-N23 |
R |
70 |
41
– 53 |
73 – 78 |
0.0 – 0.1 |
W-N24 |
R |
70 |
42
– 56 |
72 – 73 |
0.0 – 0.1 |
W-N25A |
R |
70 |
53
– 63 |
71 – 74 |
0.0 – 0.6 |
W-N25B |
R |
70 |
49
– 62 |
64 – 70 |
0.1
– 0.9 |
W-N26A |
R |
70 |
51
– 62 |
67 – 69 |
0.1 – 1.2 |
W-N26B |
R |
70 |
51
– 63 |
65 – 71 |
0.1 – 0.9 |
W-N27 |
R |
70 |
56
– 63 |
71 – 74 |
0.1 – 0.5 |
W-N28 |
R |
70 |
62
– 64 |
78 |
0.1 – 0.2 |
W-N29 |
W |
65 |
53 |
73 |
0.0 |
W-N30 |
R |
70 |
58
– 60 |
73 – 75 |
0.1 – 0.2 |
W-P6A |
R |
70 |
60 |
73 – 74 |
0.1
– 0.3 |
W-P6C |
R |
70 |
67 |
69 – 70 |
2.6
– 3.4 |
W-P7A |
E |
65 |
39
– 52 |
70 – 77 |
0.0 |
W-P7B |
E |
65 |
40
– 54 |
62
– 67 |
0.0
– 0.2 |
W-P7C |
E |
65 |
40
– 49 |
53 – 58 |
0.1
– 0.6 |
W-P7D |
E |
65 |
39
– 50 |
59
– 61 |
0.0
– 0.4 |
W-P7E |
E |
65 |
41
– 52 |
58
– 63 |
0.1
– 0.4 |
W-P7F |
E |
65 |
61
– 63 |
65 – 68 |
2.1 – 2.6 |
W-P7G |
E |
65 |
59
– 63 |
71 – 74 |
0.2
– 0.3 |
W-P8 |
W |
65 |
58
– 65 |
75 – 76 |
0.1 – 0.4 |
W-P9 |
R |
70 |
54
– 60 |
64 – 69 |
0.4
– 0.7 |
W-P10 |
R |
70 |
56
– 62 |
70 |
0.2 – 0.7 |
W-P11 |
R |
70 |
63
– 65 |
68 – 70 |
1.3 – 1.6 |
W-P12 |
R |
70 |
56
– 62 |
70 – 71 |
0.2 – 0.7 |
W-P13 |
R |
70 |
58
– 63 |
70 |
0.3 – 0.9 |
W-P14 |
R |
70 |
59
– 64 |
68
– 70 |
0.5
– 1.1 |
East
Portion |
|||||
E-P14A |
E |
65 |
75 – 76 |
76 – 77 |
8.6 – 9.9 |
E-P14B |
E |
65 |
78 |
79 |
7.7 – 8.6 |
E-P14C |
E |
65 |
74 – 75 |
76 |
5.4 – 6.5 |
E-P14D |
E |
65 |
46
– 55 |
46 – 55 |
7.9
– 9.6 |
E-P14E |
E |
65 |
62 |
64 – 65 |
2.5
– 4.2 |
E-P14F |
E |
65 |
64
– 66 |
65 – 67 |
5.5 – 6.2 |
E-P14G |
E |
65 |
47
– 50 |
47
– 50 |
17.8
– 25.6 |
Notes:
[1] R – residential; E – educational; H – clinic/ home for the
aged/hospital; W – worship; GIC – government, institution and community
[2] Bold figure denotes the noise level from Project Roads is over the
relevant TM-EIAO noise criteria.
[3] Bold figure denotes the noise exceedance which is over the relevant
TM-EIAO noise criteria and the contribution from new roads to the overall noise
level is equal to or higher than 1.0 dB(A) / noise levels from Project Road is
over the relevant TM-EIAO noise criteria.
[4] Central
air-conditioning is provided, result is for indicative purpose.
Given there are three full noise enclosures (F01, F02 and F03) recommended for mitigating the road traffic noise, it should be noted that road traffic noise generated inside the full noise enclosures would however reverberates within the structure. Nevertheless, according to research findings, the noise emission from enclosure portal would not be significant provided that a tunnel length equivalent to approximately 2-3 times of diameter are installed with absorptive panels [1], [2]&[3]. For the proposed full enclosures, absorptive panels would be installed along the entire length except at locations such as daylight panels and for safety reason.
West Portion
With the implementation of recommended noise mitigation measures, all NSRs except Hong Kong Community College (HKCC) of the HK (W-N11) and the planned school (W-P7F) will comply with the TM-EIAO noise criteria.
However, W-N11 has already provided with central conditioning, no further mitigation measures are required.
For W-P7, since there is no building
layout of this sensitive receiver during the preparation of this study, the
sensitive facades are selected at the boundary of a typical building layout
block for worst-case scenario. To avoid
noise impact from the project roads, it is recommended to avoid any sensitive
facade facing the re-aligned Hoi Wang Road as shown in Figure 5.6c. Relevant government authorities
including the Education Bureau, Planning Department and Architecture Service
Department have no objection on this recommendation (Appendix 5.18). Relevant document from
Education Bureau is shown in Appendix 5.18. Nevertheless, during the design
stage of this planned school, appropriate school layout could be revised for
agreement with EPD.
The noise
reduction of the noise mitigation measures is presented in table below.
Table 5.30: Noise Reduction of Noise
Mitigation Measures
Location |
Noise Mitigation Measures ID. |
Existing NSRs |
Planned NSRs |
||
NSR ID. |
Approximate Noise Reduction, dB(A) |
NSR ID. |
Approximate Noise Reduction, dB(A) |
||
West Portion Portal |
F01, S01, S02, C01, C02, C03,
C04, C05, C06, V01, V02, V03, V04 |
W-P11, W-P13,
W-P14 |
5-9 |
W-P8 |
1 |
W-N1A, W-N1B, W-N2 |
1-2 |
W-P6,
W-P7 |
1-10 |
||
Gascoigne Road Flyover (Kansu
Street Section) |
F03, S04, S05, V07, V08 |
W-N6, W-N6A, W-N7, W-N8, W-N8A,
W-N9A, W-N9B, W-N10A, W-N10C, W-N18, W-N19, W-N24 |
1-8 |
- |
- |
Gascoigne Road Flyover (Ferry
Street Section) |
F02, S03, C07, V06 |
W-N3, W-N25A, W-N25B, W-N26A,
W-N26B, W-N27, W-P10; W-P12 |
1-10 |
W-P6,
W-P7 |
1-10 |
East Portion
With the sensitive facade of the
classroom not facing the Project Roads (E-P14D-E, G), although the noise contribution from the project roads is greater
than 1.0dB(A), the predicted overall road traffic noise level is 47 – 65 dB(A)
which do not exceed the stipulated noise criterion of 65 dB(A) as shown in Figure 5.7a, Figure 5.7b and Figure 5.7c. Hence, no further mitigation
measure is required. Relevant government
authorities including the Education Bureau, Planning Department and
Architecture Service Department have no objection on this recommendation (Appendix 5.18). Relevant document from
Education Bureau is shown in Appendix 5.18. Nevertheless, during the design
stage of this planned school, appropriate school layout could be revised for
agreement with EPD.
Evaluation of
Eligibility of Indirect Technical Remedies
As
mentioned in Section 5.5.1, in the
case where NSRs are still exposed to noise levels exceeding the relevant noise
criteria after the implementation of all direct mitigation measures, the total
number of existing dwellings, classrooms and other noise sensitive elements
which may qualify for indirect technical remedies should be identified. However, except for the planned schools in
West Portion (W-P7F) and East Portion (E-P14A, E-P14B, E-P14C & E-P14F),
for those NSRs with cumulative noise level exceed the relevant noise criteria,
i.e. 70 dB(A) for residential and 65 dB(A) for educational institutions, the
noise contribution from “Project Road” would be lesser than 1.0 dB(A). The assessment results of the prevailing
scenarios of West Portion and East Portion are shown in Appendix 5.15A and Appendix 5.16A respectively. Hence, irrespective of the prevailing noise
level, all the NSRs would not satisfy the eligibility assessment criteria.
For the two planned schools, it has been agreed with Education Bureau that non-sensitive façade facing to CKR would be incorporated into the design to abate the noise impacts.
Evaluation of Protected and Benefitted Noise Sensitive Uses with
the Noise Mitigation Measures
To study the noise performance of the project, traffic noise levels at the residential, schools and other noise sensitive uses including hospital/ clinic and place of worship which have a direct line of sight to the Project have been predicted. The numbers of dwellings, classrooms and other noise sensitive uses that would be benefited from and be protected by the provision of noise mitigation measures have been calculated. The definition of “exposed”, “benefited” and “protected” noise sensitive uses are defined as follow:
·
Exposed
– Noise sensitive uses
with unmitigated noise level greater than relevant noise criteria
· Benefited – Exposed noise sensitive uses with a noise reduction of 1.0 dB(A) or greater in overall noise level with the noise mitigation measures in place
·
Protected
– Exposed noise
sensitive uses with an overall noise level not
greater than relevant
noise criteria with the noise mitigation measures
in place
Number of
dwellings and classrooms that would be benefited from and be protected by the provision of noise mitigation measures will be identified for existing residential
and schools respectively, while hospital/ clinic and place of worship will be identified as number of floors. Moreover, the planned noise sensitive uses do
not have detailed numbers of dwellings/ classrooms, the benefitted/ protected
will be identified as the number of floors.
Results of existing and planned noise sensitive uses are presented in tables below.
Table 5.31: Summary of Protected and Benefitted
Noise Sensitive Uses (Existing Uses)
Noise Sensitive Uses |
Total No. of Dwellings/ Classrooms/ Noise Sensitive
Uses Considered |
Unmitigated Scenario |
Mitigated Scenario |
||
No. of Exposed Dwellings/ Classrooms/
Noise Sensitive Uses |
No. of Exposed Dwellings/ Classrooms/
Noise Sensitive Uses |
Protected Dwellings/ Classrooms/ Noise
Sensitive Uses |
Benefitted Dwellings/ Classrooms/ Noise
Sensitive Uses |
||
West
Portion |
|||||
Dwellings |
2218 |
2176 |
1532 |
644 |
1586 |
Classrooms |
159 |
159 |
159 |
0 |
85 |
Hospital/
Clinic [1] |
20 |
20 |
20 |
0 |
18 |
Place
of Worships [1] |
1 |
1 |
1 |
0 |
0 |
East
Portion |
|||||
Classrooms |
40 |
40 |
40 |
0 |
0 |
Notes:
[1] Number of floors
Table 5.32: Summary of Protected
and Benefitted Noise Sensitive Uses (Planned Uses)
Noise Sensitive Uses |
Total No. of Floors of Dwellings/ Classrooms/ Noise Sensitive
Uses Considered |
Unmitigated Scenario |
Mitigated Scenario |
||
No. of Exposed Floors of Dwellings/
Classrooms/ Noise Sensitive Uses |
No. of Exposed Floors of Dwellings/ Classrooms/ Noise Sensitive
Uses |
Protected Floors of Dwellings/ Classrooms/
Noise Sensitive Uses |
Benefitted Floors Dwellings/ Classrooms/
Noise Sensitive Uses |
||
West
Portion |
|||||
Dwellings
[1] |
8 |
8 |
4 |
4 |
4 |
Classrooms
[1] |
56 |
48 |
25 |
23 |
40 |
Place
of Worships [1] |
10 |
10 |
10 |
0 |
0 |
East
Portion |
|||||
Dwellings
[1] |
166 |
26 |
26 |
0 |
0 |
Classrooms
[1] |
70 |
37 |
37 |
0 |
0 |
Hospital/
Clinic [1] |
28 |
28 |
28 |
0 |
0 |
Notes:
[1] Number of floors
5.5.2
Fixed
Plant Noise Assessment
Noise Sources
Ventilation buildings
Potential noise impacts from operation of planned fixed plant including ventilation buildings of the CKR on the nearby NSRs have been assessed quantitatively.
Cumulative impact from the ventilation buildings for planned projects including the Express Rail Link (XRL) and Kai Tak Development (KTD) would also been considered in the fixed plant noise assessment. A summary of the fixed noise sources for CKR is summarized in table below and the locations of fixed noise sources are shown in Figure 5.8, Figure 5.9 & Figure 5.10.
Table 5.33: Summary of
Fixed Plant Noise Sources
Fixed Plant Noise Source |
Fixed Plant Noise ID. |
West Portion |
|
West Ventilation Building (by CKR) |
WVSF 1-5 |
Ventilation Building (by XRL) |
XRL10A-C, XRLMKA-B |
Sub Station (by XRL) |
XRLS1 |
Central Portion |
|
Central Ventilation Building (by CKR) |
CVSF 1-9 |
East Portion |
|
West Ventilation Building (by CKR) |
EVSF 1-5 |
Ventilation Building (existing Kai Tak Tunnel Ventilation Building) |
KTD-KTT |
Sewage Pumping Station (by KTD) |
KTD-PS1A, KTD-PS2 |
Sub-station (by KTD) |
KTD-1P4 |
Ventilation Building (by T2) [1] |
T2-VB |
Note:
[1] The location of ventilation building of T2 is out of 300m
of fixed noise sensitive receivers under CKR, therefore, it has considered not
including in this assessment.
Permanent Kowloon City Ferry Pier Public Transport Interchange (PTI)
Construction Phase
Section 3.2.8 has explained that the existing PTI would need to be temporarily relocated to allow for the construction of the section of cut-and-cover tunnel underneath. Given the tight site constraints and the need to maintain the PTI operational to serve the local communities, it is required to relocate the temporary PTI with different construction stages to suit construction sequence.
However, the need to allow satisfactory operation of the temporary PTI and the need for associated temporary traffic management at different stages require decking over of the site in order that most of the construction activities (except the mucking out activities) are conducted underneath the temporary steel decking. Hence, not until the very late stage when most of the underground structures are completed, it would not be practicable to install temporary foundations structures to support a temporary roof to cover the temporary PTI.
Nevertheless, although a temporary roof is not feasible for the temporary PTI, it is still recommended to erect some noise barriers along works areas as much as practicable. A tentative extent is shown in Figure 5.11. It should be noted that the exact extent of the temporary noise barriers would need to be adjusted to suit the need for temporary traffic management.
Under the site situation, it would be practicable to adopt temporary noise barrier with about 4m tall which is taller than typical site hoarding. The surface density of the noise barrier should also be enhanced to improve its sound insulation. It is recommended that the material to be used for the noise barrier should achieve a minimum surface density of 7kg/m2. In order to maximize the possibility of enhancing its performance in noise screening, it is further recommended to have the top section cantilevered towards the temporary PTI. A typical section of this 4m tall temporary noise barrier is illustrated in Figure 5.11.
Operational Phase
Based on the current design of CKR, the existing Ma Tau Kok bus terminus will be re-provisioned to the south of the Grand Waterfront and the existing Ma Tau Kok Public Pier will also be re-located. The location of permanent PTI and the Ma Tau Kok Public Pier is shown in Figure 5.12. Two deck options (Option A - Landscape Deck Open for Public Access and Option B - Landscape Deck not Open for Pedestrian Access) have been developed and the final decision will depend on the outcome from public consultation activities which is not available during the preparation of this EIA. The potential noise impact from operation of this PTI has been assessed qualitatively.
The re-provisioned PTI will design
to no direct line-of-sight of the noise sources at the noise sensitive uses in
accordance to the HKPSG. The potential
noise impacts at NSRs due to the operation of the PTI is subject to design and
could be avoided by providing rooftop of PTI and proper mitigation measures
such as barrier, silencer, louvers orientation, etc. The proposed accessible landscape deck and
solid wall with pedestrian access for the permanent PTI is shown in Figure 5.13. The design for the pedestrian
access would be subject to detailed design.
Therefore, adverse noise impacts on existing NSRs are not anticipated.
Assessment Methodology
The following general procedures have been adopted for the operation noise assessment.
·
Identify and locate representative NSRs that may be
affected by the noise sources;
·
Determine the noise criteria for both daytime and
nighttime;
·
Use standard acoustic principle for attenuation and
directivity; and
·
Determine the maximum sound power levels (SWLs) of
the fixed noise sources.
If exceedance to the noise criteria is found for one NSR, the initial
SWL of the dominant sources to that NSR would be gradually lowered until the
corrected SPL at that NSR meets the acceptable level. The process would be repeated for other
representative NSRs with exceedance of the noise criteria until all corrected SPLs at the representative NSRs
meet the noise criteria. The maximum
allowable SWLs of the proposed fixed plant have been predicted by this approach.
Evaluation of Fixed Plant Noise Impact
The predicted maximum allowable Sound Power Level (SWL) is summarized in the table below. Detailed calculations are presented in Appendix 5.19.
Table 5.34: Maximum
Allowable SWL for the Ventilation Buildings
Location |
Plant Item |
Plant ID |
Maximum allowable Sound Power Level, dB(A) |
|
Daytime |
Night-time |
|||
West Portion |
Ventilation
|
WVSF-1 |
104 |
104 |
|
Building |
WVSF-2 |
104 |
104 |
|
|
WVSF-3 |
104 |
104 |
|
|
WVSF-4 |
104 |
104 |
|
|
WVSF-5 |
104 |
104 |
Central Portion |
Ventilation
|
MVSF-1 |
90 |
80 |
|
Building |
MVSF-2 |
88 |
78 |
|
|
MVSF-3 |
88 |
78 |
|
|
MVSF-4 |
90 |
80 |
|
|
MVSF-5 |
95 |
85 |
|
|
MVSF-6 |
90 |
80 |
|
|
MVSF-7 |
90 |
80 |
|
|
MVSF-8 |
90 |
80 |
|
|
MVSF-9 |
90 |
80 |
East Portion |
Ventilation
|
EVSF-1 |
105 |
95 |
|
Building |
EVSF-2 |
110 |
100 |
|
|
EVSF-3 |
110 |
100 |
|
|
EVSF-4 |
110 |
100 |
|
|
EVSF-5 |
110 |
100 |
The equipment should be free of the characteristics of tonality, impulsiveness and intermittency. If the selected equipment could not be free of characteristics of tonality, impulsiveness and intermittency, the maximum SWL should be reduced in accordance with the correction factors, in the range of 3 to 6 dB(A), as given in Section 3.3 of TM-IND.
It should be noted that the detailed design of the ventilation buildings (e.g. the louver details) are yet to be developed. Hence, the Contractor shall review the latest design and update the noise assessment to ensure that the stipulated facade noise levels in Table 5.12 can be achieved.
The Contractor shall install acoustic
silencers, noise barriers and acoustic louvers where appropriate to ensure that
the specified maximum SWLs shown in the table above will not be exceeded.
Mitigation Measures
The detailed design should incorporate the following good practice in order to minimize the nuisance on the neighboring NSRs. In case the Contractor would change the design and locations of the vents, they would need to comply with the legislative maximum impacts at the receivers.
·
Louvres should be orientated away from adjacent
NSRs, preferably onto main roads which are less sensitive.
·
Direct noise mitigation measures including
silencers, acoustic louvers and acoustic enclosures should be allowed for in
the design for the ventilation building.
·
The façade for these ventilation shafts should have
adequate sound insulation properties to minimise the noise emanating through
the building fabric.
Construction airborne noise assessment has been conducted. All practicable mitigation measures have been exhausted to minimise the noise impacts. These mitigation measures include the optimisation of construction methodology (i.e. schedule of using PME), quiet plant, temporary noise barrier and good site practices. However, given the site constraints, some of the receivers (See Table 5.16) would still be subject to adverse residual impacts exceeding the construction noise criterion.
Residual impacts exceeding the construction noise criterion have been assessed and considered the impacts are temporary and reversible. With all the proposed mitigation measures, the adverse residual impact exceeding the construction noise criterion has been reduced to be minimal.
Construction groundborne noise assessment has also been conducted. No exceedance of noise criteria is predicted and hence no mitigation measures are required.
For the operational phase, mitigation measures
with low noise road surface, noise barrier, semi-enclosure and full enclosure
are required to fulfill the EIAO criteria.
After implemented all these proposed mitigation measures, it is
anticipated an approximate number of 1600 existing dwellings and 90
existing classrooms will be benefited from and 640 existing dwellings will be
protected by the noise mitigation measures, an approximately of 4 floors of
planned dwellings and 40 floors of planned classrooms will be benefitted from
and an approximately of 4 floors of planned dwellings and 20 floors of planned
classrooms protected by the noise mitigation measures.
Maximum sound power levels allowed to be
emitted from louvers of fixed noise sources at ventilation buildings at West
Portion, Central Portion and East Portion were predicted. The re-provisioned PTI will also designed to
no direct line-of-sight of the noise sources at the noise sensitive uses. With the proper selection of plant and
adoption of noise control measure such as acoustic silencers, noise barriers,
acoustic louvers, the NSRs located in the vicinity of these fixed noise sources
would not be affected.
[1] Woehner,
H.. (1992). Sound Propagation at Tunnel
Openings
[2] Road
Works at West Kowloon EIA, 2009 – Traffic Noise Impact Assessment (Portal and
Openings of Underpass)
[3] Kiyoshi Nagakura, Dr. Eng. (2005). Prediction
and Mitigation of Noise form Shinkansen Tunnel Portals. Quarterly Report OF
RTRI. Vol. 46 (1). Railway Technical Research Institute.