2.1.1 In this section, the requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of air quality impact during the construction phase of the Project are presented. As identified in the EIA report, the Project would not cause any adverse operation air quality impacts. Therefore, environmental monitoring and audit is not required during the operation phase.
2.1.2 The objectives of the air quality monitoring shall be:
· to identify the extent of construction dust impact on sensitive receivers;
· to determine the effectiveness of mitigation measures to control fugitive dust emission from activities during the construction phase;
· to audit the compliance of the Contractor with regard to dust control, contract conditions and the relevant dust impact criteria;
· to recommend further mitigation measures if found to be necessary; and
· to comply with Action and Limit (A/L) Levels for air quality as defined in this Manual.
2.2.1 The criteria against which ambient air quality monitoring to be assessed are:
· The Hong Kong Air Quality Objectives (AQOs) for TSP, 24-hour TSP levels of 260 mg m-3; and
· 1-hour TSP limit of 500 mg m-3.
2.2.2 These levels are not to be exceeded at Air Sensitive Receivers (ASRs).
2.2.3 Monitoring and audit of the TSP levels shall be carried out by the ET to ensure that any deteriorating air quality could be readily detected and timely action shall be undertaken to rectify such situation.
2.2.4 1-hour and 24-hour TSP levels shall be measured to indicate the impacts of construction dust on air quality. The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. Upon approval of the ER, 1-hour TSP levels can be measured by direct reading methods which are capable of producing comparable results as that measured by the high volume sampling method, to indicate short event impacts.
2.2.5 All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, other local atmospheric factors affecting or affected by site conditions and work progress of the concerned site etc. shall be recorded in detail. A sample data record sheet is shown in Appendix B.
2.3.1 High volume sampler (HVS) in compliance with the following specifications shall be used for carrying out the 1-hour and 24-hour monitoring:
· 0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;
· equipped with a timing / control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2 ;
· flow control accuracy: ± 2.5% deviation over 24-hour sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter;
· capable of operating continuously for 24-hour period.
2.3.2 The ET shall be responsible for the provision of the monitoring equipment. He shall ensure that sufficient number of HVSs with appropriate calibration kit is available for carrying out the baseline, regular impacts monitoring and ad-hoc monitoring. The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals. All the equipment, calibration kit, filter papers, etc, shall be clearly labelled.
2.3.3 Initial calibration of the dust monitoring equipment shall be conducted upon installation and prior to commissioning at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The calibration data shall be properly documented for future reference by the concerned parties such as the IEC. All the data shall be converted into standard temperature and pressure condition.
2.3.4 The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded on the data sheet as shown in Appendix B.
2.3.5 If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, he shall submit sufficient information to the IEC to prove that the instrument is capable of achieving a comparable result as that of the HVS before it may be used for the 1-hour sampling. The instrument shall also be calibrated regularly, and the 1-hour sampling shall be determined periodically by HVS to check the validity and accuracy of the results measured by direct reading method.
2.3.6 Wind data monitoring equipment shall also be provided and set up at conspicuous locations for logging wind speed and wind direction near to the dust monitoring locations. The equipment installation location shall be proposed by the ET and agreed with the ER and the IEC. For installation and operation of wind data monitoring equipment, the following points shall be observed:
(i) The wind sensors shall be installed 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;
(ii) The wind data shall be captured by a data logger. The data shall be downloaded for analysis at least once a month;
(iii) The wind data monitoring equipment shall be re-calibrated at least once every six months;
(iv) Wind direction should be divided into 16 sectors of 22.5 degrees each.
2.3.7 In exceptional situations, the ET may propose alternative methods to obtain representative wind data upon approval from the ER and agreement from the IEC.
2.4 Laboratory Measurement / Analysis
2.4.1 A clean laboratory with constant temperature and humidity control and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory shall be HOKLAS accredited or other internationally accredited laboratory.
2.4.2 If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the IEC. Measurement performed by the laboratory shall be demonstrated to the satisfaction of the ER and the IEC.
2.4.3 The IEC shall conduct regular audit of the measurement performed by the laboratory so as to ensure the accuracy of measurement results. The ET shall provide the ER with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his/her reference.
2.4.4 Filter paper of size 8"x10" shall be labelled before sampling. It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hour and be pre-weighed before use for the sampling.
2.4.5 After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper shall then be returned to the laboratory for reconditioning in the humidity-controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1mg. The balance shall be regularly calibrated against a traceable standard.
2.4.6 All the collected samples shall be kept in a good condition for 6 months before disposal.
2.5.1 The dust monitoring locations are shown in Figure 2.1 and 2.2. The selected monitoring locations are the air sensitive receivers located in the vicinity of construction sites. The proposed air quality monitoring locations are listed in Table 2.1 below.
Table 2.1 Proposed Air Quality Monitoring Stations
Station |
EIA ID |
Location |
AM1 |
CL1 |
Tin Hau Temple |
AM2 |
CL6 |
Sai Tso Wan Recreation Ground |
AM3 |
||
AM4 |
CL16 |
Sitting-out Area at Cha Kwo Ling Village |
AM5 |
CT2 |
Ocean Shore Tower 1 |
AM6 |
CT5 |
Park Central Tower 6 |
2.5.2 The status and locations of the air quality sensitive receivers may change after issuing this Manual. The ET shall propose updated monitoring locations and seek approval from ER and IEC and agreement from EPD on the proposal.
2.5.3 When alternative monitoring locations are proposed, the following criteria, as far as practicable, shall be followed:
(i) at the site boundary or such locations close to the major dust emission source;
(ii) close to the air sensitive receivers;
(iii) proper position/sitting and orientation of the monitoring equipment; and
(iv) take into account the prevailing meteorological conditions.
2.5.4 The ET shall agree with the IEC on the position of the HVS for installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:
(i) a horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
(ii) no two samplers shall be placed less than 2 meter apart;
(iii) the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
(iv) a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
(v) a minimum of 2 metres of separation from any supporting structure, measured horizontally is required;
(vi) no furnace or incinerator flue is nearby;
(vii) airflow around the sampler is unrestricted;
(viii) the sampler is more than 20 metres from the dripline;
(ix) any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;
(x) permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
(xi) a secured supply of electricity is needed to operate the samplers.
2.6.1 Baseline monitoring shall be carried out to determine the ambient 1-hour and 24‑hour TSP levels at the monitoring locations prior to the commencement of the Project works. During the baseline monitoring, there shall not be any construction or dust generating activities in the vicinity of the monitoring stations. The baseline monitoring will provide data for the determination of the appropriate Action levels with the Limit levels set against statutory or otherwise agreed limits.
2.6.2 Before commencing the baseline monitoring, the ET shall inform the IEC of the baseline monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the baseline monitoring results.
2.6.3 Baseline monitoring shall be carried out at all of the designated monitoring locations for at least 14 consecutive days prior to the commissioning of the construction works to obtain daily 24-hour TSP samples. 1-hour sampling shall also be done at least 3 times per day while the highest dust impact is expected.
2.6.4 In case the baseline monitoring cannot be carried out at the designated monitoring locations during the baseline monitoring period, the ET Leader shall carry out the monitoring at alternative locations which can effectively represent the baseline conditions at the impact monitoring locations. The alternative baseline monitoring location shall be approved by the ER and agreed with IEC.
2.6.5 In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with the IEC and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to ER for approval.
2.6.6 Baseline checking of ambient TSP levels shall be carried out every three months at each monitoring location, when no dusty works activities are in operation. If the ET considers that significant changes in the ambient conditions have arisen, a repeat of the baseline monitoring may be carried out to update the baseline levels. The revised baseline levels, in turn, the air quality criteria, shall be agreed with the IEC and EPD.
2.7.1 The ET shall carry out impact monitoring during construction phase of the Project. For regular impact monitoring, a sampling frequency of at least once in every six-days shall be strictly observed at all of the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least three times in every six days shall be undertaken when the highest dust impact occurs.
2.7.2 Before commencing the impact monitoring, the ET shall inform the IEC of the impact monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the impact monitoring results.
2.7.3 The specific time to start and stop the 24-hour TSP monitoring shall be clearly defined for each location and be strictly followed by the field operator.
2.7.4 In case of non-compliance with the air quality criteria, more frequent monitoring, as specified in the Action Plan in Section 2.8, shall be conducted within the 24 hours after the result is obtained. This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified.
2.8.1 The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 1-hour and 24-hour TSP. Table 2.2 shows the air quality criteria, namely Action and Limit levels to be used. Should non-compliance of the air quality criteria occur, action in accordance with the Action Plan in Table 2.3 shall be carried out.
Table 2.2 Action and Limit Levels for Air Quality (Dust)
Parameter |
Action Level (1) |
Limit Level |
TSP (24 hour average) |
BL £ 200 mg m-3, AL = (BL * 1.3 + LL)/2 BL > 200 mg m-3, AL = LL |
260 mg m-3 |
TSP (1 hour average) |
BL £ 384 mg m-3, AL = (BL * 1.3 + LL)/2 BL > 384 mg m-3, AL = LL |
500 mg m-3 |
Note: (1) BL = Baseline level, AL = Action level, LL = Limit level.
Table 2.3 Event and Action Plan for Air Quality (Dust)
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action level being exceeded by one sampling |
1. Identify source, investigate the causes of complaint and propose remedial measures; 2. Inform IEC and ER; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method. |
1. Notify Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
Action level being exceeded by two or more consecutive sampling |
1. Identify source; 2. Inform IEC and ER; 3. Advise the ER on the effectiveness of the proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on remedial actions required; 7. If exceedance continues, arrange meeting with IEC and ER; 8. If exceedance stops, cease additional monitoring.
|
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial measures; 4. Advise the ET on the effectiveness of the proposed remedial measures; 5. Supervise Implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented.
|
1. Submit proposals for remedial actions to IEC within three working days of notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
Limit level being exceeded by one sampling |
1. Identify source, investigate the causes of exceedance and propose remedial measures; 2. Inform Contractor ,IEC, ER, and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results. |
1. Check monitoring data submitted by ET; 2. Check Contractor’s working method; 3. Discuss with ET and Contractor on possible remedial measures; 4. Advise the ER on the effectiveness of the proposed remedial measures; 5. Supervise implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within three working days of notification; 3. Implement the agreed proposals; 4. Amend proposal if appropriate. |
Limit level being exceeded by two or more consecutive sampling |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER to discuss the remedial actions to be taken; 7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the potential remedial actions; 2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly; 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of exceedance in writing; 2. Notify Contractor; 3. In consolidation with the IEC, agree with the Contractor on the remedial measures to be implemented; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within three working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under control; 5. Stop the relevant portion of works as determined by the ER until the exceedance is abated. |
2.9.1 Mitigation measures for dust control have been recommended in the EIA Report. The Contractor shall be responsible for the design and implementation of these measures.
2.9.2 Recommended mitigation measures to minimise the adverse impacts on air quality during construction phases are detailed in Sections 2.9.3 below.
2.9.3 To ensure compliance with the guideline level and AQO at the ASRs, the Air Pollution Control (Construction Dust) Regulation should be implemented and good site practices should be incorporated in the contract clauses to minimize construction dust impact. A number of below dust suppression measures are proposed to be implemented.
· Watering eight times a day on active works areas, exposed areas and paved haul roads to reduce dust emission by 87.5%;
· Enclosing the unloading process at barging point by a 3-sided screen with top tipping hall, provision of water spraying and flexible dust curtains to reduce dust emission by 90%;
· Use of regular watering, with complete coverage, to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.
· Use of frequent watering for particularly dusty construction areas and areas close to ASRs.
· Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.
· Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs.
· Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.
· Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.
· Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading points, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.
· Provision of not less than 2.4m high hoarding from ground level along site boundary where adjoins a road, streets or other accessible to the public except for a site entrance or exit.
· Imposition of speed controls for vehicles on unpaved site roads. Ten kilometers per hour is the recommended limit.
· Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.
· Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.
2.9.4 The implementation schedule for the recommended air quality mitigation measures is presented in Appendix C.