The EIA concluded that the impact of direct loss and indirect disturbance of fish ponds due to the Project was relatively minor with the implementation of mitigation measures.
The proposed mitigation measures of fisheries are summarised in the Project Implementation Schedule (PIS) in Appendix 2-2.
Site audits shall be undertaken during the construction phase of the Project to check that the proposed fisheries mitigation measures are properly implemented and maintained as per their intended objectives. Site inspections shall be undertaken by the ET at least one per week during the routine environmental audit as detailed in Section 13.