3                            PROJECT dESCRiptION

3.1                       Scope of the Project

3.1.1.1              Further to the recommendations of the Option Assessment and subsequent alignment developments detailed in Section 2 of this report, the preferred Trunk Road T2 is shown in Figure 3.1 and will comprise:

·             a dual two-lane trunk road of approximately 3.0km long with about 2.7km of the trunk road in form of tunnel;

·             ventilation and administration buildings and a traffic control and surveillance system; and

·             associated civil, electrical, mechanical, landscaping and environmental protection and mitigation works.

3.1.1.2              The works for the Trunk Road T2 project are grouped under the following major geographical headings:

a)           The South Apron Section – all works for the Trunk Road T2 Project located at the South Apron of the former Kai Tak Airport, including a ventilation building, a section of at-grade road, a section of depressed road, a section of cut and cover tunnel, a vertical launching shaft for the tunnel boring machines (TBM), a section of twin TBM tunnel and ancillary works.

b)          The Subsea Tunnel Section – all works for the Trunk Road T2 project in the sea between the South Apron and Cha Kwo Ling, including twin subsea TBM tunnels.

c)           The Cha Kwo Ling Section – all works for the Trunk Road T2 project located at the former Cha Kwo Ling Public Cargo Works Area (PCWA), including a section of cut and cover tunnel, a vertical receiving shaft for the TBMs, a section of twin TBM tunnels, a ventilation building and an administration building located inside the Lam Tin Interchange.  The site formation and road works required to form the Lam Tin Interchange including the administration building, are under the scope of the Tseung Kwan O –Lam Tin Tunnel (TKO-LTT) project.

3.1.1.3              Details of the various elements of the selected Trunk Road T2 alignment are described in the sections below. The general horizontal layout of the preferred alignment is shown in Figure 3.1 while the vertical profile is show in Figure 3.2 – Figure 3.2b.

3.2                       South Apron

3.2.1                   Site Clearance

3.2.1.1              Site clearance for the works in the South Apron will include the removal of small trees and shrubs, removal of fences and gates across the site.   At the location of the proposed Barging Point there is an existing temporary structure to be removed at the commencement of the Trunk Road T2 project works.

3.2.2                   At-grade Road

3.2.2.1              The proposed Trunk Road T2 starts at an interface with the Central Kowloon Route (CKR) at Chainage 5758m and is a dual 2-lane road.  The trunk road continues at-grade for approximately 100m along the South Apron until it passes over the existing Jordan Valley Box Culvert (JVBC).

3.2.2.2              The construction of the at-grade section of road will generate small quantities of excavated materials from the, typically 2 to 3 metre deep, trench works and excavation works for the construction of the drainage network, the roads and the foundations for sign gantries. Small amounts of the material excavated for their construction will be temporarily stockpiled and used to backfill the trenches and sign gantry foundations.

3.2.2.3              The layout of the at-grade section, along with the depressed road section, can be seen in Figure 3.3 and a typical section of the at-grade road given in Figure 3.5a.

3.2.3                   Depressed Road Section

3.2.3.1              After the Trunk Road T2 passes over the JVBC it begins to descend, within a depressed road section, for approximately 170m.  This allows the level of the road to lower from the existing South Apron ground level of approximately +5mPD to -3.3mPD, at which point the road achieves sufficient depth for the road to be fully enclosed and the depressed road section connects to a tunnel section.

3.2.3.2              The depressed road section of the Trunk Road T2 will be contained within a reinforced concrete “u-shaped” section, consisting of a slab under the road and retaining walls on both sides of the road section.  The layout of the depressed road section can be seen in Figure 3.3 and a typical section of the depressed road is shown in Figure 3.5b.  The retaining walls will vary in height from 2m high to 10m high, as the road lowers in level, to retain the surrounding South Apron ground level. Tubular or sheet pile walling will be used to support the excavation to allow the construction of the open trough section.  The selection of each type of steel pile walling is related to the method adopted by the contractor.  It is anticipated that the sheet piles will be extracted and removed from site by the contractor for re-use on other projects or left in place and not require disposal.

3.2.3.3              The existing ground water level on the South Apron is at about +3.3mPD, which is based on the results of the ground water monitoring from KL/2009/02.   Therefore, in order to construct the depressed road section in a dry working environment the ground water will be lowered by pumping out of the groundwater within the plan area of the depressed road section.  The sheet pile walling will be driven down to a level to enable control of the ground water flow under the excavation such that dry construction conditions can be maintained.

3.2.3.4              The depressed road section will generate approximately 30,500m3 of excavated materials.  Based upon a review of the geological profile in this area, all of the material excavated will be fill material.  This section is proposed to be the last major section of the alignment to be excavated, with the excavated materials being exported off site via the barging point to a public fill site rather than placed in the stockpile works area. In order to handle this material, and the other materials to be exported form the Trunk Road T2 site, a platform will be constructed within the land of the proposed barging point to allow tipping of the material from trucks to barges.  The platform will be adjustable to allow for the variation in tidal levels.  Good practice dust control procedures for handling the materials will be applied including a 3–sided enclosure on the unloading ramp and water sprays to control dust as the materials are placed in the barges. 

3.2.4                   Cut and Cover Tunnel Section

3.2.4.1              From the connection with the depressed road section the Trunk Road T2 continues to descend at a gradient of about 5% within a fully enclosed twin cell rectangular tunnel section (refer to Figure 3.5c), that will be constructed using the cut and cover method.  This reinforced concrete cut and cover section is approximately 570m long (from chainage 6050 to 6620) and reaches a road level of approximately -28.6mPD.  The chainage 6620 is close to the southern edge of the South Apron, at which point the cut and cover tunnel section connects to the subsea tunnel section.

3.2.4.2              The planned programme of works is such that the cut and cover section for the Trunk Road T2 will commence first with the excavated materials being stockpiled on site or directly removed to Public Fill Reception Facilities (PFRF).  The planned stockpile area is for this material is at Works Area 4 (see Section 3.4 below) which has an anticipated capacity of 50,000m3.  Once this capacity is reached further material will be exported off site for disposal at PFRF.  Throughout the duration of the construction works, the materials within the stockpile will be used for backfilling over the completed sections of cut and cover tunnel and so provide a source of material to be managed by the Contractor to avoid importing fill materials for the project and minimise export of excavated materials from the site.

3.2.4.3              During excavation for the cut and cover sections of tunnel at both the South Apron and Cha Kwo Ling, it is anticipated that quantities of underlying marine muds will be excavated.  As these materials are not suitable for disposal at a public fill reception facility (PFRF), they may have to be disposed of to East Sha Chau Contaminated Mud pits.  The preferred alternative is that the marine mud is treated on site by mixing with sand and cement such that as much as possible can be used as fill materials for areas such as the future at-grade roads (e.g. under the at-grade Road D4, the location of which is shown in Figure 3.3) or landscaped areas such as in the promenade areas at the former Cha Kwo Ling Public Cargo Working Area (PCWA).

3.2.4.4              For the majority of the cut and cover sections between Chainages 6050 to 6620 (refer to Figures 3.2 & 3.2a), it is anticipated that diaphragm walling will be used to support the excavation.  However, for the section of tunnel in front of the Public Works Central Laboratory (PWCL) (Chainages 6480 to 6560), it is anticipated that contiguous large diameter bored piles will be used to support the excavation and further limit ground movement adjacent to the PWCL. For the total cut and cover road section, a quantity of approximately 470,000m3 will be excavated for re-use where possible in filling over the tunnel or to be exported via the barging point.

3.2.4.5              For shallower sections of the cut and cover tunnel, either tubular steel or sheet pile walling will be used to support the excavation, depending on the depth of excavation and numbers of layers of propping to be adopted for the excavation. 

3.2.4.6              It is assumed that the Contractor will adopt a “bottom-up” approach for the construction of most of the cut and cover tunnel.  The Contractor will install the diaphragm or pile walling from existing ground level.  The ground between the diaphragm/pile walls would be excavated progressively and temporary steel props installed to stabilise the walls.  Layers of the temporary steel props would be installed as the excavation gets deeper until the final design level for the bottom of the cut and cover tunnel section is reached.  The contractor would then construct the bottom concrete slab of the cut and cover tunnel.  This would be followed by the construction of the top slab of the cut and cover tunnel.  The contractor would then progressively backfill soil onto the top of the cut and cover tunnel, removing the layers of the temporary steel props as the backfilling increases in level, until the level of the backfill has reached the existing South Apron ground level.

3.2.4.7              One anticipated exception to the typical “bottom-up” approach will be at the existing road junction at TD4 and Cheung Yip Street (from Chainages 6445 to 6480).  In order to allow traffic to continue to use the junction, it is envisaged that the contractor would adopt a “top-down” approach to construct the cut and cover tunnel in this area.  This “top-down” approach requires that diaphragm/pile walls are again installed from ground level, but rather than excavating down immediately a small amount of temporary road decking is placed at road level and used to maintain the junction open to traffic while the excavation works are carried on under the temporary decking.  This temporary decking would consist of steel beams and plates, which the contractor would re-use other projects and will not be disposed of under this contract.

3.2.4.8              For the section of cut and cover tunnel from Chainages 6480 to 6620, construction of the tunnel sections would be within a cofferdam constructed within diaphragm walls.  The section of tunnel from Chainages 6480 to 6620 is the section of the Trunk Road T2 where the eastbound and westbound carriageways diverge to achieve a spacing of approximately 13.2m between the two 13.2m diameter circular sections of the subsea tunnel.  This spacing between the two tunnel bores has been selected to provide a conservatively safe block of soil between the two tunnel bores and ensure stability of the two adjacent tunnel sections as they are constructed.  This wider spacing between the carriageways results in an area between the carriageways that is not essential for the permanent works.  Thus, two options were considered, namely to construct the two carriageways in two short independent sections of cut and cover tunnels or to construct a single large cut and cover tunnel section that encompassed both carriageways.  

3.2.4.9              The option of having two independent cut and cover tunnel sections would have resulted in four diaphragm walls (two per carriageway) and would have increased the amount of bentonite material to be disposed of, and would have constrained the subsea tunnelling operations that could take advantage of the larger space in a single cut and cover section as fabrication and operation space for subsea tunnel operations. 

3.2.4.10          Therefore, a single large cut and cover tunnel section has been adopted as the preferred design. For this approach, the two outside walls for the cut and cover tunnel section between Chainages 6480 and 6620 will be constructed using diaphragm walls.  To support the top slab of the tunnel a single central row of columns with barrette pile foundations is adopted. 

3.2.4.11          Construction of this section of cut and cover tunnel will adopt the “bottom-up” approach. Following construction of the bottom slab and walls of the cut and cover tunnel, it is anticipated that the top slab of the cut and cover section would be constructed and previously excavated materials used to partially fill over this section of tunnel up to ground level and form a working area for the TBM ancillary works.  Equipment delivery and spoil removal openings would be left in the top of the cut and cover section with walled shafts up to ground level.  Following completion of all TBM works, these openings in the top slab would be closed and the shafts would be backfilled to ground level using stockpiled material.

3.2.4.12          As described for the depressed road section, the existing ground water level on the South Apron is at about +3.3mPD, based on the results of the ground water monitoring from KL/2009/02.  Therefore, in order to construct the cut and cover tunnel sections in a dry working environment, the ground water will be lowered by pumping out of the water within the plan area of the tunnel section.  The diaphragm/pile walling will be installed down to a level to enable control of the ground water flow under the excavation such that dry construction conditions can be maintained.

3.2.5                   Ventilation Building and Administration Facilities

3.2.5.1              Two ventilation buildings and an administration building are planned for the Trunk Road T2 project.  These buildings are located at, or close to the ends of Trunk Road T2.  At the South Apron, the ventilation building is proposed to be located at Site 3A4,  adjacent to the DSD desilting compound under construction for the Jordan Valley Box Culvert as shown in Figure 3.4.  The ventilation building will be a reinforced concrete structure, two storeys in height, with operation and plant rooms designed to monitor and control the tunnel air from the eastbound and westbound tunnels of the trunk road.  It is anticipated that the building will have a basement to reduce the total height above ground.  The tunnel air will be exhausted from the roof of the ventilation building.  The exhaust from the building will be expelled upwards at a velocity around 8m/s via a stack on the top of the building.  The stack size will be 2 x 25m2 discharging the exhaust vertically at a height of approximately +18mPD.  There will be no mid-tunnel exhaust for this project. 

3.2.5.2              No administration building is located at the South Apron.  For tunnel operation the facilities located on the South Apron will be very minor and limited to kiosks close to the interface with CKR, next to the at-grade road section. This would not generate any operational waste or emissions.

3.3                       Subsea Tunnel Alignment

3.3.1                   Alignment and Construction

3.3.1.1              As mentioned in Section 2, the “deep level” option of alignment Option 1 has been selected as the preferred alignment for detailed assessment in this EIA study.  The length of the subsea tunnel for this preferred option is about 2.1km.  The twin 13.2m diameter tunnel sections are embedded a minimum of 13.2m below the seabed. The typical cross section of each of the subsea tunnel sections is illustrated in Figure 3.5d, and shows the two lane traffic envelope, ventilation ducts, E&M, drainage and services equipment enclosed within a concrete lining.  This concrete lining is made up  of precast concrete segmental units that are joined together to form 1m long rings, that are installed behind the TBM as it progresses towards the receiving shaft.  As described in Section 2, the tunnel is proposed to be constructed using the TBM method in order to avoid disturbance to the seabed and minimise the amount of dredged material to be removed, providing water quality, waste management, marine archaeology and ecology and fisheries benefits.  The TBM method has developed over the last few years to become a reliable method for constructing large diameter highway and railway tunnels with significant environmental benefits over other construction methods.

3.3.1.2              The tunnel alignment follows a southeast-ward direction from the South Apron, passing under the Kwun Tong Typhoon Shelter (KTTS), and its associated breakwaters, and then the sea beyond, before turning further eastward towards the Cha Kwo Ling shoreline.

3.3.1.3              The design and procurement period for the TBM is about 15 to 18 months plus a 5 month mobilisation period.  Two TBMs will be used in parallel to form the twin Trunk Road T2 tunnels (an eastbound tunnel and a westbound tunnel) and both TBMs will be launched from the South Apron, tunnelling towards the receiving pit at Cha Kwo Ling.  The TBM for Bore 1 is proposed to be launched at the end of 2017, while the TBM for Bore 2 will commence in January 2018.

3.3.1.4              The subsea tunnels commence at a 140m long x 45m wide launching shaft within the South Apron (chainage 6480 to 6620), Figure 3.6, and with a lowest level of approximately -29mPD.  The ground level at this location is approximately +5.0mPD.  The subsea tunnel will then run southward under the KTTS, where the lowest tunnel bottom level will reach approximately -42mPD, and then heads towards the Cha Kwo Ling shoreline where it ends at a receiving shaft within the former PWCA and Cha Kwo Ling.  The vertical alignment of the tunnel is shown in Figures 3.2 to 3.2b.  As shown in these figures, the tunnel rises up towards the shorelines but maintains a depth of cover above the tunnel as it passes under the existing seawalls at either end of the tunnel and, therefore, does not result in any seabed loss or disturbance. 

3.3.1.5              As noted in the text on the South Apron cut and cover tunnel section, construction of the subsea tunnels will commence at the South Apron launching shaft where an area of land is required for construction of the launching shaft for the TBMs (Figure 3.6). The launching shaft will be constructed by open excavation method supported by diaphragm walls. Excavated materials will be backfilled on the completed section of cut and cover tunnel, while excess excavated materials will be disposed off-site to the PFSF.  The TBMs will start boring from the launching shaft and then continue under the KTTS until they reach the receiving shaft at the former PCWA at Cha Kwo Ling (Figure 3.7).  The TBMs will then be dismantled and removed via the receiving shaft.

3.3.1.6              The proposed launching shaft located at the South Apron (chainage 6480 to 6620, Figure 3.6) is where all the construction waste materials from the subsea tunnelling works will be removed.  The mixed largely alluvium and CDG, excavated materials from the TBMs will be dried and pressed to remove excess water and to recycle the bentonite (drilling fluid).  The cleaned drilling fluid will be returned to the TBM system for re-use.  As the TBM works may progress for up to 24 hours per day, 7 days per week, and the public fill facilities are only open during day time hours, a temporary stockpile area will be used to temporarily store the TBM excavated materials until normal working hours and removal by barge from the barging point. 

3.3.1.7              The excavated material will be placed in the temporary stockpile area in Works Area 3 (see Section 3.5 below), adjacent to the launching shaft via an enclosed conveyor system.  Noise barriers will be erected around the stockpile to mitigate noise from the placing of the excavated material onto the stockpile. 

3.3.1.8              During normal working hours (assumed to be 07:00 to 19:00), the excavated materials would be moved from the temporary stockpile area to the barging point via a fully enclosed conveyor system to minimise dust and noise emissions.

3.3.1.9              The planning for the tunnel includes for a cross passage between the twin tunnels at 100m intervals.  The subsea tunnel section is aligned to pass through mainly the alluvium/CDG layers under the seabed.  The cross-passages will be constructed between the tunnel bores and will also encounter alluvium/CDG.  It is anticipated that ground freezing will be used for temporary stabilisation of the walls of the cross-passages until the permanent concrete lining is installed for the cross-passages.  An alternative to ground freezing would be grouting of the ground to form a stable ground condition for excavation.  However, ground freezing is preferred as there would be no grout materials added to the excavated soil which can be disposed off in a similar manner to the rest of the tunnel excavated material and the provision of the ground freezing can be more accurately controlled within the tunnel.  In the case the grouting options are adopted by the contractor, the grout would be added to the soil and this would be treated as an inert material, to be excavated and handled similar to the rest of the tunnel excavated materials. For the subsea section a quantity of approximately 630,000m3 will be excavated for exporting via the barging point.

3.3.1.10          For the planning of the programming of the TBM works, two major options were considered:

a)          The use of two TBM’s, both commencing at the South Apron and progressing to CKL; or

b)          The use of a single TBM commencing at the South Apron and progressing to CKL.  Once the TBM had completed one of the tunnel bores it would either be dismantled and transported back to the South Apron to carry out the second tunnel bore or it would be turned around and shifted onto the alignment of the second tunnel bore to commence tunnelling form CKL back to the South Apron.

3.3.1.11          The use of a single TBM was considered to have significant disadvantages, including;

i)            The overall programme for the tunnel works would be longer and posed a risk to completing the project for the 2021 first year of operation.

ii)          The disassembly and transportation of the TBM from CKL to the South Apron would have involved significant additional construction activities that also posed a risk to the progress of the project.

iii)        The turning of the TBM “around” at the CKL would have required a second set of TBM support facilities, including a second barging point, stationed at the CKL end of the tunnel resulting in increased costs and increased environmental impacts when compared with a single support facility.  The option of a floating TBM support facility moored to either the South Apron or CKL seawall was considered as not preferred due to risk for environmental impact of having the tunnel slurry pumped to a floating support facility moored to the respective seawall.

3.4                       Cha Kwo Ling

3.4.1                   Site Clearance

3.4.1.1              For the works at Cha Kwo Ling, site clearance will include the removal of the former PCWA offices and removal of the existing wall between the PCWA and the training area.

3.4.2                   Cut and Cover Tunnel

3.4.2.1              A cut and cover tunnel in the form of a reinforced concrete box structure will function as both the receiving shaft for the two TBMs and as the cut and cover section connecting between the Trunk Road T2 and the TKO-LTT alignments.  This section of receiving shaft/cut and cover tunnel, of approximately 110m length, will be constructed within the Cha Kwo Ling area.  The tunnel will connect to the TKO-LTT at a road level of approximately -26.9mPD at the Cha Kwo Ling landfall about Chainage 8767m.  For this CKL cut and cover road section, a quantity of approximately 72,000m3 will be excavated for re-use where possible in filling over the tunnel or to be exported via existing roads to the Barging Point proposed at the South Apron.

3.4.2.2              The cut and cover tunnel at CKL is anticipated to be constructed in open excavation supported by diaphragm walls. Excavated materials will initially be transported by trucks back to the stockpile area at the South Apron for re-use or disposal off site.  Following completion of the TBM and cut and cover tunnel construction works the receiving shaft would be backfilled with material transported by road from the South Apron. 

3.4.2.3              Consideration was given to the use of part of the works area WA5 at CKL as a stockpile area for the excavated materials.  However, the use of the South Apron as the stockpile area for the CKL excavated materials was preferred for the following reasons:

i)            The space available at CKL is insufficient to store all of the excavated materials from the CKL cut and cover tunnel section and will be required for the works for the construction of the ventilation building and removal of the TBM.

ii)          The barging point to be set up at the South Apron could be used efficiently to export of the excess excavated materials.

iii)        A proportion of the materials to be excavated at CKL would be marine muds.  The Works Area WA4 at the South Apron is to be set up to treat such materials for re-use as fill material and use of those facilities for treating the CKL would be more efficient rather than having two split facilities. 

3.4.3                   Ventilation Building and Administration Facilities at Cha Kwo Ling

3.4.3.1              One of the Trunk Road T2’s ventilation buildings is located inside the Lam Tin Interchange and is provided for tunnel ventilation.  The building will be located at the end of the connecting section of TKO-LTT tunnel that connects the Cha Kwo Ling end of Trunk Road T2 tunnel as shown in Figure 3.4.  The ventilation building will be three storeys in height with a top level of approximately +18mPD and tunnel air from the two tunnel tubes will be exhausted at the roof of the building, vertically upwards via a stack with a velocity around 6m/s. The stack vents will be 2 x 25m2 venting vertically from the roof of the vent building at +18mPD. 

3.4.3.2              Administration facilities and space for the Trunk Road T2 project will be located within the administration building designed and constructed under the TKO-LTT project.  As stated above, the site formation for the Lam Tin Interchange, including for the Trunk Road T2’s eastern ventilation building, will be part of the scope of the TKO-LTT project and have been assessed under the TKO-LTT EIA.  The administration building will be located within the Lam Tin Interchange and on the Cha Kwo Ling side of Trunk Road T2 (Figure 3.1) and would be composed of administration offices, training office, meeting areas, control rooms, traffic control surveillance system (TCSS) room, and associated areas, such as parking spaces for maintenance and recovery vehicles.

3.5                       Works Areas

3.5.1.1              Five works areas have been identified for locating site offices, stockpiles and using as support areas for the TBM works to construct the undersea tunnel, during the construction period of the Project.  The locations of the works areas are shown in Figure 3.8 and described in Table 3.1 below.

Table 3.1   Details of Proposed Works Areas

Works Area Reference

Location

Current Use

Proposed Use

WA1

At the South Apron adjacent to the site of  T2’s proposed western ventilation building 

Not used

Storage of construction equipment, plant maintenance and cutting and bending of reinforcement along with site offices.

WA2

At the South Apron adjacent to the  Kwun Tong Typhoon shelter seawall

1. (STT)KX2569: Sureguard Logistics Limited-Open storage of goods and dangerous goods

2. (TGLA)GLA-TNK 1334: Water Supplies Dept - Works Area

3. Government Logistics Department-Kowloon Bay Cargo Handling Area

Works area for TBM launching shaft, support facilities for TBM operations and storage area for tunnel lining segments, plant maintenance and Barging Point.

WA3

At the South Apron next to the Kerry Godown Dangerous Goods Storage Facility

Currently used as a bus parking lot.

Stockpiling of excavated materials

WA4

At the South Apron next to the taxiway bridge. 

Currently used to store excavated material from the CEDD contract KL/2009/01.

Stockpiling of excavated materials

WA5

At the former Cha Kwo Ling Public Cargo Working Area

Currently unused.

Works area for TBM retrieval shaft, storage of construction equipment, plant maintenance and cutting and bending of reinforcement along with site offices.

 

3.5.1.2              All of the proposed Works Areas are currently formed on developed land within short distances from the Trunk Road T2 alignment, with some already being used as works areas for on-going construction projects.  None of the sites are vegetated and no tree removal is required for their use.  The potential environmental impacts of these nearby works areas have been assessed together with the main site. 

3.6                       Barging Point

3.6.1.1              The barging point is proposed at the Government Logistics Department Kowloon Bay Cargo Handling Area.  The excavated materials from the TBM will be removed from the site by connecting a conveyor system to the barging point. The capacity of the barging point for removal of the construction waste materials will be a rate of 750m3 per hour, assuming working hours between 07:00 and 19:00 per day

3.6.1.2              The proposed temporary barging point has a vertical seawall face and has been used for berthing and loading/unloading purpose by marine vessels of various Government Departments.  No temporary facilities would be needed to be constructed above the sea.  The barging point will comprise one vehicle unloading ramp only and a conveyor belt unloading chute.

3.6.1.3              Delivery of materials from the temporary stockpile area next to the TBM would be via a fully enclosed conveyor belt.  Delivery of materials from the remainder of the site would be by truck and delivered to the barges by via an adjustable ramp.

3.6.1.4              The ramp is proposed to be enclosed within a permanent enclosed 3-sided tipping hall with built-in water spraying system to reduce dust dispersion.

3.7                       Slope Works

3.7.1.1              There are no slope works proposed for this Trunk Road T2 project. 

3.8                     Sewage and Drainage

3.8.1.1              Stormwater drainage systems will be provided to collect stormwater from the carriageway surfaces.  The stormwater will enter into gullies along the kerb lines.  The gullies will be fitted with sumps to trap silt and grit prior to discharging the stormwater into the stormwater drainage systems.  The drainage systems will eventually discharge the stormwater into the sea at discrete locations.

3.8.1.2              Operational sewage will be generated from the eastern and western ventilation buildings, but, again, in relatively small quantities as summarised in Table 3.2 below, based upon the staffing estimates required for the Trunk Road T2 project.

Table 3.2   Estimated Sewage Generation

Location

Staff

Average Dry Weather Flow (m3/day)

South Apron Landfall (including eastern ventilation building)

2

0.16

Cha Kwo Ling Landfall (including western ventilation building)

70

5.6

 

3.8.1.3              The sewage generated would be discharged to the local drainage systems at these two areas, which have sufficient capacity to handle this small contribution from the Trunk Road T2. 

3.9                       Project Programme

3.9.1.1              The construction works (including testing and commissioning) are anticipated to commence on site in late 2015, with completion of the construction works by the end of 2020, with Trunk Road T2 commencing operation in 2021.  An outline of the anticipated construction programme is shown in Appendix 3A with the general phasing of the works described below.

3.9.1.2              It is anticipated that the normal working hours for surface works will be 07:00 to 19:00, Monday to Friday, with alternative Saturday (excluding General Holidays).  For the tunnelling works, it is assumed that the TBM operations will continue on a shift basis with a typical working period of 20 hours per day, allowing for 4 hours per day “down-time” for the TBM equipment and operators.

3.9.1.3              General phasing of the works on site are detailed below and shown in Figures 3.9a to 3.9n:

·             General site clearance and setting up works areas on South Apron;

·             Stage 1 – Commence works on Launching shaft for TBM works;

·             Stage 2 – Continue works for launching shaft and construct facilities for barging point on the South Apron;

·             Stage 3 – Continue works for launching shaft and set up of mixing area for treatment of excavated marine mud;

·             Stage 4 - Continue works for launching shaft and including excavation works within the launching shaft area.  Excavated materials up to the area WA4’s maximum capacity of 50,000m3 to be stockpiled in WA4 including all marine muds, other excavated materials will be transported to the barging point via the site haul road and exported from site.  Commence works on the eastbound cell of the cut and cover tunnel between Chainages 6050 to 6445;

·             Stage 5 – Construction of cut and cover sections in launching shaft and partial backfilling of launching shaft to use previously excavated materials and to create a platform for the TBM support facilities.  Continue works on the eastbound cell of the cut and cover tunnel between Chainages 6050 to 6445;

·             Stage 6 - Establishment of TBM support facilities in Works Area 2 (WA2) and in area above launching shaft ready for commencement of TBM construction.  Continue construction of the eastbound cell of the cut and cover tunnel between Chainages 6050 to 6445 with excavated materials up to the area’s maximum capacity of 50,000m3 to be stockpiled in WA4 including all marine muds(for treatment as it is delivered to the stockpile area), other excavated materials will be transported to the barging point via the site haul road and exported from site;

·             Stage 7 - Commencement of the eastbound TBM. Completion of the eastbound cell of the cut and cover section between Chainages 6050 to 6445 including backfilling with stockpiled materials, followed by diversion of road TD4 onto the ground over the eastbound cell.  Site clearance at Cha Kwo Ling;

·             Stage 8 - Construction of the westbound cell of the cut and cover tunnel between Chainages 6050 to 6445 with excavated materials up to the areas maximum capacity of 50,000m3 to be stockpiled in WA4 including all marine muds (for treatment as it is delivered to the stockpile area), other excavated materials will be transported to the barging point via the site haul road and exported from site. Commence westbound TBM tunnelling and continue with TBM works in eastbound tunnel.  Commence works for TBM receiving shaft at Cha Kwo Ling;

·             Stage 9 - Completion of the westbound cell of the cut and cover section between Chainages 6050 to 6445 including backfilling with stockpiled materials, followed by construction of at-grade roads on top of tunnel.  Continue with TBM works in eastbound and westbound tunnels;

·             Stage 10 - Completion of the westbound cell of the cut and cover section between Chainages 6050 to 6445 including backfilling with stockpiled materials, followed by construction of at-grade roads on top of tunnel.  Commence construction works for the cut and cover tunnel section between Chainages 6445 to 6480, Construction of the depressed road section between Chainages 5880 to 6050 with excavated materials to be stockpiled in WA4. Continue with TBM works in eastbound and westbound tunnels;

·             Stage 11 - Construction of the depressed road section between Chainages 5880 to 6050 with excavated materials to be stockpiled in WA4.  Continue construction works of the cut and cover tunnel section between Chainages 6445 to 6480, with excavated materials to be stockpiled in Works Area WA4, other excavated materials will be transported to the barging point via the site haul road and exported from site. Commence construction of western and eastern ventilation buildings.  Completion of westbound and eastbound TBM tunnels; 

·             Stage 12 – Completion of construction works of the cut and cover tunnel section between Chainages 6445 to 6480, with fill material being used from the stockpile area in WA4. Construction of western and eastern ventilation buildings.  Completion of receiving shaft for TBM at Cha Kwo Ling;

·             Stage 13 - . Construction of the cut and cover tunnel section between Chainages 6445 to 6480, with excavated materials to be stockpiled in WA4.Other excavated materials will be transported to the barging point via the site haul road and exported from site. Completion of western and eastern ventilation buildings.  Completion of receiving shaft for TBM at Cha Kwo Ling; and.

·             Stage 14 - Completion of all Trunk Road T2 civil works and installation of finishes and Traffic Control and Surveillance System (TCSS).  Other at-grade works for South Apron development carried out.

3.9.1.4              The following programme assumptions are recognised as key to the determination of the overall construction programme.

·             The works area WA2 must be constructed early in the contract to allow for the barging point to remove the current stockpile materials from the former contract KL/2009/01

·             The design and procurement of the TBM is assumed to take 18 months from the commencement of the contract to mobilisation of the first TBM on site.

·             The construction of the launching shaft at the South Apron will be complete and a working platform at ground level created over it to allow for the establishment of the TBM support facilities.

·             Two TBMs are assumed for the construction of the tunnel, both progressing from the South Apron. 

·             The section of cut and cover tunnel under the future road D4 (and partially under the existing road TD4) will be constructed in phases with temporary traffic arrangements to shift the traffic on TD4 to create space for the construction of each cell.

3.10                   Concurrent Projects

3.10.1               Interface with CKR

3.10.1.1          Similar to Trunk Road T2, the construction of CKR is initially planned to commence construction in early 2015 for completion in 2020 and commencing operation in 2021. (Figure 3.11)   As the projects are likely to be constructed concurrently and will be operational at the same time, detailed coordination of the interfacing construction activities will be required, including construction access and temporary stockpiling areas.

3.10.2               Interface with TKO-LTT

3.10.2.1          Similar to Trunk Road T2, the construction of TKO-LTT is initially planned to commence construction in early 2016 for completion in 2020, and commencing operation in in 2021. (Figure 3.12)   As the projects are likely to be constructed concurrently and will be operational at the same time, detailed coordination of the interfacing construction activities will be required, including construction access, temporary stockpiling areas and arrangement of Trunk Road T2’s ventilation / administration buildings.

3.10.3               South Apron Works

3.10.3.1          The South Apron area had already been fully decontaminated by the Decommissioning of the Former Kai Tak Airport other than the North Apron project in accordance with the Environmental Permit No. EP-285/2008 and these works are no longer on-going.  Other infrastructure works to be carried on the South Apron as part of the Kai Tak Development are anticipated to be carried out concurrently with the Trunk Road T2 project, including:

l    footbridges FB-02 and 03;

l    Road D4;

l    construction of the KTD roads L10 and L18;

l    extension of Kai Hing Road; and 

l    the Centre of Excellence in Paediatrics at Site C of Site 3C1 of KTD which will start construction in 2013 for completion by 2017. 

3.10.3.2          The locations of these infrastructure works are shown in Figure 3.10.   These concurrent projects are generally minor works that would generally involve insignificant quantities of excavated materials for the construction of the drainage network for the roads and foundations for sign gantries.  For the footbridges there would, also, be the construction of bored pile foundations which will generate some excavated material. 

3.10.4               Other Concurrent Projects

3.10.4.1          In addition to the interface with the major concurrent projects described above, there would be a footbridge FB-06 at the outlet of Tsui Ping Nullah and a site formation and infrastructure works project at the ex-Cha Kwo Ling Kaolin Mine Site adjacent to TKO-LTT’s Lam Tin Interchange.  Details of other concurrent projects during either the construction and/or the operational phases, together with details of how these are assessed in the EIA, are described in the summary table of concurrent projects included as Appendix 3C.

3.11                   Traffic Data and Assumptions

3.11.1.1          A Local Area Model was developed to provide traffic forecasts for EIA purposes.  The EIA requires cumulative traffic forecasts and, hence, EIA flows were produced assuming the entire Route 6 (including CKR, TKO-LTT and T2) were all in place by the programmed first operational year of  2021.

3.11.1.2          The first operational year for the Trunk Road T2 is 2021.  Design year peak hour traffic forecasts have, therefore, been prepared for the years 2021, 2026 and 2036 which reflect the full operation of the Trunk Road T2 for the purpose of Traffic Impact Assessment (TIA).  For the purpose of EIA, traffic data for the prevailing year of 2009 and the forecast scenarios of 2021, 2026 and 2036 (i.e. opening year and 15 years after opening) will be developed.  A summary of the traffic data and the road links included in the EIA are presented in Appendix 3D.

3.11.1.3          For the air impact assessment, specific information on the traffic forecasts is required to conform to the latest EMFAC-HK formats.  Specifically, the following information has been provided:

·             Peak hour traffic forecasts in the units of veh/hr (exact years to be confirmed) of major roads within 500m radius coverage of the Project (including the exposed sections of Trunk Road T2 and roads in Kai Tak South Apron);

·             Forecasts broken down into 16 vehicle types as stated in the EMFAC-HK;

·             Design speed for the road sections;

·             Trips (veh) per day expressed as a daily profile (broken down by hour);

·             Vehicle kilometres travelled (VKT) which is calculated by multiplying the flows within the corresponding roads lengths within the 500m coverage, broken down by the 16 vehicle types; and

·             Daily profile (broken down by hour) of average vehicle travel speeds.

3.11.1.4          The relevant traffic forecasts for EIA purposes have been presented in Technical Notes No.TN2 and TN3, and submitted to Transport Department for review.  Letters from Transport Department confirming no adverse comments are also included in Appendix 3D.

3.12                   Environmental Conditions in the Absence of the Project and Environmental Benefits

3.12.1.1          The proposed Trunk Road T2, together with the Central Kowloon Route (CKR) and Tseung Kwan O Lam Tin Tunnel (TKO-LTT) will form the new strategic highway network, namely the Route 6 linking the Kowloon West with the Kowloon East.  Trunk Road T2 will connect with CKR at Kowloon Bay to the Kowloon West and TKO-LTT at Cha Kwo Ling to Tseung Kwan O.  Without Trunk Road T2, there is a significant missing link in Route 6.

3.12.1.2          From a road connectivity perspective, in the absence of Trunk Road T2, TKO-LTT would serve the Hong Kong Island to Tseung Kwan O traffic unaffected (through the Eastern Harbour Crossing), but significantly less so for Central Kowloon to Tseung Kwan O traffic.  On an independently-operated basis, that is without Trunk Road T2, TKO-LTT functions primarily as a “bridging” link between Tseung Kwan O and Lam Tin/Kwun Tong only.  Traffic toward Central Kowloon from Lam Tin, Yau Tong, Tseung Kwan O from either the existing TKO Tunnel or the future TKO-LTT would mainly rely on the district and strategic roads, including Kwun Tong Bypass, Kwun Tong Road and Kai Fuk Road and would result in the notable increase in the usage of these roads with the traffic growth and may experience capacity issues.

3.12.1.3          Thus, Trunk Road T2 is considered a necessity to be in place in order to provide connection between CKR and TKO-LTT as Trunk Road T2 is a parallel route to the existing Kwun Tong Bypass.  It would cater the traffic growth within the Kowloon East area after commissioning of CKR and TKO-LTT, and would, also, relieve traffic congestion of the district and strategic roads, Kwun Tong Bypass, Kwun Tong Road and Kai Fuk Road etc within the Kwun Tong area.

3.12.1.4          Without the Trunk Road T2 connection, the existing roads passing through the highly populated areas of Kwun Tong and Kowloon Bay would become more congested and result in potentially increased noise and air pollution impacts on sensitive receivers adjacent to these roads.  The Trunk Road T2 will divert some of this traffic away from this urban area providing some environmental improvement to the surrounding environment.  While the Trunk Road T2 will pass through the future Kai Tak Development on the South Apron, the project is largely in tunnel and the planned developments that would be sensitive to air and noise impacts are being suitably planned with measures including setbacks and centralised air conditioning.  Based on above and the adopted tunnel alignment for the Truck Road T2, the magnitude of population affected would be minimised and much lower than those that would benefit from its construction. 

3.13                   Designated Projects Under the EIAO

3.13.1.1          The Trunk Road T2 project constitutes a Schedule 2 designated project (DP) under the EIAO requiring an Environmental Permit (EP) to be granted by the Director of Environmental Protection (DEP) before it may be either constructed or operated.  By the nature of the alignment and design of Trunk Road T2, the project is a designated project with elements including Items A.1 and A.7 under Schedule 2 of the EIAO.  Table 3.3 summarises the identified individual DP under this Project.

Table 3.3    Schedule 2 Designated Project under this Project

Designated Project

Nature of Works

Part I of Schedule 2

Reason for Inclusion

DP1

Trunk Road T2

Items A.1 and A.7

Trunk road and road tunnel more than 800m in length

Note:  Before the Trunk Road T2 project starts construction, the public cargo working areas at Kwun Tong and Cha Kwo Ling will be decommissioned.  Thus, Item B.4, Part I, Schedule 2 of the EIAO is not considered relevant.