13 summary of ENVIRONMENTAL Impacts and Outcomes
13.1.1.1
This EIA study predicted that,
with the implementation of the recommended mitigation measures, the Trunk Road
T2 Project would be environmentally acceptable with no adverse residual impacts
on the population and environmentally sensitive resources. An impact summary is presented in Table 13.1 showing the assessment points (such as
ASRs, NSRs), results of impact predictions, relevant standards or criteria,
extents of exceedances predicted, impact avoidance
measures considered, proposed mitigation measures and residual impacts. Also,
Table 13.2 summarises the environmental outcomes and benefits that accrued
from the environmental considerations and analysis during the EIA process and
the implementation of environmental control measures of the Project. The requirements for the EM&A programme
have been recommended, where necessary, to check for the compliance with
environmental legislation and standards.
Table 13.1 Summary of
Environmental Impacts Associated with the Project
Sensitive Receivers/ Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/ Criteria |
Extent of Exceedance (Without Mitigation) |
Impact Avoidance Measures/ Mitigation Measures |
Residual Impacts (After Implementation of Mitigation Measures) |
Air Quality Impact |
|||||
Construction Phase |
|||||
Existing
ASRs are industrial buildings, commercial buildings, parks at Kowloon Bay and
Kwun Tong and the industrial buildings, residential
buildings and sitting area at Cha Kwo Ling. The planned ASRs are the Commercial,
Comprehensive Development Area, Residential, Government, Institution or
Community, Open Space and Other Specified Uses of Kai Tak Future
Development. A total of 10 Air Sensitive Receivers (ASRs)
have been identified for the construction phase assessment shown in Figures 4.1a and 4.1b, summarised in Table 4.4. |
•
Maximum predicted 1-hour and 24-hour averaged
results of the worst case Tier 1 screening at representative ASRs are 570 µg/m3 and 169 µg/m3
respectively. •
The predicted 1-hour and 24-hour results for the
representative ASR CKL3 for the Tier 2 focused Cha Kwo
Ling assessment area showed no exceedances of the
criterion. There is a small area with exceedance on
the contour plots but this comprises the works areas of the TKO-LTT project
where no ASRs are located and therefore the dust impacts are considered as
insignificant.. •
Maximum predicted annual average TSP
concentrations at representative ASRs is 76.5µg/m3 which indicates
that all ASRs are in full compliance with the criteria. |
•
Annexes
4 and 12 of EIAO-TM; •
1-hour, 24-hour and annual averages for TSP; and •
Air
Quality Objectives (AQOs) |
•
Maximum predicted 1-hour averaged TSP result of
Tier 1 exceeds EIAO-TM (1hr) criterion by up to 4031 µg/m3 •
Maximum predicted 24-hour averaged TSP result of
Tier 1exceeds AQO (24-hr) criterion by up to 1166 µg/m3 Maximum
predicted annual averaged TSP result of Tier 1exceeds AQO (Annual) criterion
by up to 95.2 µg/m3 •
No exceedances for
maximum predicted 1-hour and 24-hour TSP Concentrations of Tier 2 |
•
Watering
of the construction areas 12 times per day to reduce dust emissions by 91.7%,
with reference to the “Control of Open Fugitive Dust Sources” (USEPA
AP-42). The amount of water to be
applied would be 0.91L/m2 for the respective watering frequency; •
Dust
enclosures with watering would be provided along the loading ramps and
conveyor belts for unloading the C&D materials to the barge for dust
suppression; •
3-sided
barriers around the stockpiling areas WA3 and WA4; •
The
dust control measures detailed below shall also be incorporated into the
Contract Specification where practicable as an integral part of good
construction practice: -Use of regular watering to reduce dust
emissions from exposed site surfaces and unpaved roads, particularly during
dry weather; -Use of frequent watering for
particularly dusty construction areas and areas close to ASRs; -Side enclosure and covering of any
aggregate or dusty material storage piles to reduce emissions. Where this is
not practicable owing to frequent usage, watering shall be applied to
aggregate fines; -Open stockpiles shall be avoided or
covered. Prevent placing dusty material storage piles near ASRs; -Tarpaulin covering of all dusty vehicle
loads transported to, from and between site locations; -Establishment and use of vehicle wheel
and body washing facilities at the exit points of the site; -Imposition of speed controls for
vehicles on unpaved site roads, 8 km per hour is the recommended limit; -Routing of vehicles and position of
construction plant should be at the maximum possible distance from ASRs; -Every stock of more than 20 bags of
cement or dry pulverised fuel ash (PFA) should be covered entirely by
impervious sheeting or placed in an area sheltered on the top and the 3
sides; -Cement or dry PFA delivered in bulk
should be stored in a closed silo fitted with an audible high level alarm
which is interlocked with the material filling line and no overfilling is
allowed; and -Loading, unloading, transfer, handling
or storage of bulk cement or dry PFA should be carried out in a totally
enclosed system or facility, and any vent or exhaust should be fitted with an
effective fabric filter or equivalent air pollution control system. |
•
No irreversible
adverse residual impacts will be anticipated. |
Operational
Phase |
|||||
Existing
ASRs are industrial buildings, commercial buildings, parks at Kowloon Bay and
Kwun Tong and the industrial buildings, residential
buildings and sitting area at Cha Kwo Ling. The planned ASRs are the Commercial,
Comprehensive Development Area, Residential, Government, Institution or
Community, Open Space and Other Specified Uses of Kai Tak Future Development. A total of 25 Air Sensitive Receivers (ASRs)
have been identified for the operational phase assessment shown in Figures 4.2a and 4.2b, summarised in Table 4.4. |
•
Predicted 1-hour average NO2 Concentration
at 1.5m above ground level: 114 - 199 µg/m3. •
Predicted 24-hour average NO2
Concentration at 1.5m above ground level: 75 - 95 µg/m3. •
Predicted annual average NO2
Concentration at 1.5m above ground level: 64.5 – 74.7 µg/m3. •
Predicted 24-hour Average RSP Concentration at
1.5m above ground level: 55 - 61 µg/m3. •
Predicted annual average RSP Concentration at
1.5m above ground level: 50.2 -53.3 µg/m3. |
•
Annexes 4 and 12 of EIAO-TM; •
Hourly, 24-hour and Annual NO2 and RSP
Concentrations; •
AQOs; and •
Tunnel Air Quality Guidelines specified under the
EPD’s Practice Notes on Control of Air Pollution in Vehicle Tunnel 1995. |
•
No exceedances of the
NO2 or RSP AQOs are predicted. |
•
No mitigation measures are required. |
•
No adverse residual impacts are expected to
occur. |
Airborne Noise |
|||||
Construction Phase |
|||||
There are no existing NSRs within the
South Apron area. Existing NSRs are residential village houses in the Cha Kwo Ling village, mid-rise residential developments in Cha
Kwo Ling and the Tin Hau
Temple. Existing and planned future NSRs have
been identified at both the South Apron and in Cha Kwo
Ling. The selected NSRs for the construction phase are shown in Figures 5.1a and 5.1b. |
•
Maximum Predicted Construction Noise Level ranged
from 69dB(A) to 90 dB(A) |
•
Annex 5 of the EIAO-TM for non-restricted hours: 75dB(A) for domestic premises and hotels, and 70dB(A)
during normal hours for education institutions including kindergartens
(65dB(A) during examination periods), nurseries and all other places where
unaided voice communication is required. |
•
Exceed the relevant criteria by up to 15dB(A). |
•
Use of quieter plant, including Quality Powered
Mechanical Equipment (QPME) is specified for the list of equipment; •
Use of temporary or fixed noise barriers with a
surface density of at least 10kg/m2 to screen noise from movable and stationary
plant; •
Use of enclosures with covers at top and three
sides and a surface density of at least 10kg/m2 to screen noise from
generally static noisy plant such as air compressors; •
Use of acoustic fabric for the silent piling
system, drill rigs, rock drills etc.; •
Proper fitting of silencers and mufflers on the
ventilation fans; and •
Implementation of good site practice. |
•
The mitigated predicted maximum noise level at
all NSRs reduced to within the 75dB(A) noise
criteria. |
Operational Phase
(Traffic Noise) |
|||||
•
Four future hospital developments and a
residential development at the South Apron, and village houses at Cha Kwo Ling Village and two future residential developments
at ex-Cha Kwo Ling Kaolin Mine Site and Yau Tong
Bay (refer to Figures 5.2a and 5.2b) |
•
Without noise mitigation measures, the predicted
noise levels would be in the range of 66.4 to 80.2 dB(A) |
•
Annex 5 of EIAO-TM; and |
•
No exceedances are
predicted. |
•
No direct mitigation measures are required. |
•
Adverse residual impacts would not be anticipated |
Operational
Phase (Fixed Noise) |
|||||
•
Four future hospital developments and a
residential development at the South Apron, and village houses at Cha Kwo Ling Village and two future residential developments
at ex-Cha Kwo Ling Kaolin Mine Site and Yau Tong
Bay (refer to Figures 5.2a and 5.2b) |
•
The operational fixed plant noise impacts at the
identified NSRs have been predicted to comply with the respective criteria
and adverse fixed noise impacts are not anticipated. |
•
Annex 5 of EIAO-TM: ANL-5dB(A)
or prevailing noise level. |
•
No exceedances are
predicted. |
•
No direct mitigation measures are required. |
•
Adverse residual impacts are not anticipated. |
Ground-borne Noise |
|||||
Construction
Phase |
|||||
A future residential development at the
South Apron in Kai Tak, and village houses at Cha Kwo
Ling Village (refer to Figures 5.1a and 5.1b) |
•
No exceedances are
predicted. |
•
Annex 5 of the EIAO-TM for periods between
0700-1900 (except General Holiday & Sunday); The criteria for noise
transmitted primarily through the structural elements of the building or
buildings should be 10dB(A) less than the relevant
acceptable noise level (ANL). |
•
No exceedances are
predicted. |
•
The advancing speed of the TBM should be
restricted to 2m/hr in order to ensure compliance with the daytime
ground-borne noise limits. |
•
Adverse residual impacts would not be expected. |
Water Quality |
|||||
Construction Phase |
|||||
15 WSRs are identified (refer to Figure
6.2 and Table 6.5) |
•
Potential
water pollution sources have been identified as construction run-off,
wastewater discharge from tunnelling and excavation, groundwater hydrology,
contaminated groundwater, sewage effluent, accidental spillages and waste
construction materials. •
No
disturbance to the marine waters or seabed will occur |
•
EIAO-TM; •
WPCO; •
WDO;
and •
ProPECC PN 1/94. |
•
No exceedances are
predicted. |
•
A
list of construction phase mitigation measures including providing perimeter
drains, sand/silt removal facilities and oil interceptors, covering excavated
and construction materials and spill response plans (refer to Section 6.4.8) was proposed for
controlling and minimizing water quality impacts during construction phase;
and •
Construction activities should be subject to a routine
audit programme throughout the construction period. |
•
Impacts
of construction site runoff will be reduced to an acceptable level. |
Operational Phase |
|||||
15 WSRs are identified (refer to Figure
6.2 and Table 6.5) |
•
Impacts may be associated with tunnel run-off |
•
WPCO |
•
No exceedances are predicted. |
•
The road drainage in the tunnel should pass
through oil interceptors to remove oil, and grease before being discharged
into the public storm water drainage system; •
Silt traps and oil interceptors should be cleaned
and maintained regularly; and •
The oily contents of oil interceptors should be
transferred to an appropriate disposal facility, or to be collected for
reuse, if possible. |
•
No
adverse water quality impacts are predicted. |
Marine Ecology |
|||||
Construction Phase |
|||||
Eastern
Buffer Water Control Zone (WCZ), the Victoria Harbour WCZ and the Western
Buffer WCZ and other area likely to be impacted by the Project (refer to Figure
6.1) |
•
The
ecological value of the intertidal habitats to be temporarily lost is
generally considered to be very low, does not containing any species of
conservation interest and the duration of any impact is temporary and
reversible in nature. •
Site
run-off may lead to temporary water quality issues and an increase in local
suspended solids for a short period of time. •
Insignificant
effects of increased marine traffic would be anticipated. |
•
Annex 8 of the TM-EIAO; •
Marine Parks Ordinance (Cap. 476); •
Wild Animals Protection Ordinance (Cap. 170); •
Protection of Endangered Species of Animals and
Plants Ordinance (Cap. 586); •
Town Planning Ordinance (Cap. 131); •
Hong Kong Planning Standards and Guidelines
Chapter 10 (HKPSG); •
The World Conservation Union IUCN; •
United Nations Convention on Biodiversity; and •
Convention on the International Trade in
Endangered Species of Flora and Fauna (CITES) |
•
Not
applicable. |
•
Good construction practice measures have been
recommended to be implemented as follows: •
avoid damage and disturbance to the remaining and
surrounding natural habitat; •
placement of equipment in designated areas within
the existing disturbed land; •
spoil heaps should be covered at all times; •
construction activities should be restricted to
the designated works areas; and •
disturbed areas to be reinstated immediately after
completion of the works. |
•
No long-term, unacceptable residual ecological
impacts to marine ecological habitats and associated wildlife. |
Operational Phase |
|||||
Eastern
Buffer Water Control Zone (WCZ), the Victoria Harbour WCZ and the Western
Buffer WCZ and other area likely to be impacted by the Project (refer to Figure
6.1) |
•
No direct impacts are anticipated •
Indirect impacts resulting from the deterioration
of water quality. |
• As for construction phase above. |
• Not
applicable. |
• No specific mitigation measures are required; and • Implementation of the water quality mitigation
measures recommended in the water quality impact assessment. |
• No long-term, unacceptable residual ecological
impacts to marine ecological habitats and associated wildlife. |
Fisheries |
|||||
Construction
Phase |
|||||
Victoria
Harbour Water Control Zone (WCZ), Western Buffer WCZ and Eastern Buffer WCZ (refer
to Figure 6.1) |
•
No significant impacts to fisheries are
anticipated |
•
Annex 9 and Annex 17 of EIAO-TM |
•
Not
applicable. |
•
No specific mitigation measures are required. •
Construction run-off control measures will be
implemented. |
•
No adverse water quality impacts are predicted. |
Operational
Phase |
|||||
Victoria Harbour Water Control
Zone (WCZ), Western Buffer
WCZ and Eastern Buffer WCZ (refer to Figure
6.1) |
•
No significant impacts to fisheries are
anticipated |
•
Annex 9 and Annex 17 of EIAO-TM |
•
Not
applicable. |
•
No specific mitigation measures are required. |
•
No adverse water quality impacts are predicted. |
Landscape and Visual |
|||||
Construction
Phase |
|||||
Landscape
Resources (LRs) and Landscape Character Area (LCAs) within the Study Area Visually
Sensitive Receivers (VSRs) within the Primary Zone of Visual Influence |
•
Moderate to slight (Adverse) significance on LRs. •
Moderate to slight (Adverse) significance on
LCAs. •
Moderate/substantial to insubstantial (Adverse) significance on
VSRs. •
98 trees will be impacted due to the construction
of Project. •
66 trees to be felled and 31 trees to be
transplanted. •
5029 square meters of planting areas and a
temporary loss of 75,300 square metres of hard standing which will be
temporarily lost in the construction phase, and an permanent loss of 8500
square meters of hard standing within the operation phase (Western Works
Area). •
Loss of one tree and 21,500 square metres of hard
standing which will be temporarily lost in the construction phase (Eastern
Works Area). |
•
EIAO
(Cap.499.S.16) and the TM on EIA Process, particularly Annexes 10 and
18; •
EIAO Guidance Note 8/2010; •
Protection of Endangered Species of Animals And
Plants Ordinance (Cap 586); •
Town Planning Ordinance (Cap 131); •
Protection of the Harbour Ordinance (Cap 531); •
Hong Kong Planning Standards and Guidelines
(HKPSG); •
Study on Landscape Value Mapping of Hong Kong; •
Land Administration Office Instruction (LAOI)
Section D-12 - Tree Preservation; •
WBTC No. 25/92 - Allocation of Space for Urban
Street Trees; •
WBTC No. 7/2002 - Tree Planting in Public Works; •
ETWB TC(W) No. 13/2003 - Guidelines and
Procedures for Environmental Impact Assessment of Government Projects and
Proposals; •
ETWB TC(W) No. 13/2003A - Guidelines and
Procedures for Environmental Impact Assessment of Government Projects and
Proposals; Planning for Provision of
Noise Barriers •
ETWB TCW No. 2/2004 - Maintenance of Vegetation
and Hard Landscape Features; •
ETWB TCW No. 29/2004 - Registration of Old and
Valuable Trees (OVTs), and Guidelines for their Preservation; •
ETWB TCW No. 8/2005 - Aesthetics Design of
Ancillary Buildings in Engineering Projects; •
ETWB No. 36/ 2004 - Advisory Committee on the
Appearance of Bridges and Associated Structures (ACABAS); •
ETWB TCW No. 10/2005 - Planting on Footbridges
and Flyovers; •
ETWB TCW No. 3/2006 - Tree Preservation; •
DEVB TCW No. 2/2013 - Greening on Footbridges And
Flyovers •
DEVB TCW No. 3/2013 – Site Coverage of Greenery
on Footbridges And Flyovers •
Hyd - Structures Design Guidelines for highways
& Railways, Third Edition.
Section 17; |
•
Moderate to slight (Adverse) significance on LRs. •
Moderate to slight (Adverse) significance on
LCAs. •
significance on LCAs. •
Moderate/ •
98 trees will be impacted due to the construction
of Project. •
66 trees to be felled and 31 trees to be
transplanted. •
5029 square meters of planting areas and a
temporary loss of 75,300 square metres of hard standing which will be
temporarily lost in the construction phase, and an permanent loss of 8500
square meters of hard standing within the operation phase (Western Works
Area). •
Loss of one tree and 21,500 square metres of hard
standing which will be temporarily lost in the construction phase (Eastern
Works Area). •
|
•
All works shall be carefully designed to minimize
impacts on existing landscape resources and visually sensitive receivers.
Existing trees within works area shall be retained and protected. •
Existing trees of good quality and condition that
are unavoidably affected by the works should be transplanted. ·
Large temporary
stockpiles of excavated material shall be covered with unobtrusive sheeting
to prevent dust and dirt spreading to adjacent landscape areas and vegetation,
and to create a neat and tidy visual appearance. ·
Construction
plant and building material shall be orderly and carefully stored in order to
create a neat and tidy visual appearance. ·
Erection of
decorative screen hoarding should be designed to be compatible with the
existing urban context. All lighting in
construction site shall be carefully controlled to minimize light pollution
and night-time glare to nearby residences and GIC user. The contractor shall
consider other security measures, which shall minimize the visual impacts. |
•
Moderate to slight (Adverse) significance on LRs. •
Moderate to slight (Adverse) significance on
LCAs. •
Moderate to insubstantial (Adverse) significance
to VSRs. |
Operational
Phase |
|||||
Landscape Resources (LRs) and
Landscape Character Area (LCAs) within the Study Area Visually Sensitive Receivers (VSRs)
within the Primary Zone of Visual Influence |
•
Slight to
insubstantial (Beneficial) significance on LRs. •
Slight to
insubstantial (Beneficial) significance on LCAs. •
Moderate to
insubstantial (Beneficial) significance on VSRs. •
|
•
As above for
operational phase. |
•
Slight to
insubstantial (Beneficial) significance on LRs. •
Slight to
insubstantial (Beneficial) significance on LCAs. •
Moderate to insubstantial
(Beneficial) significance on VSRs |
•
Compensatory
tree planting shall be incorporated along all roadside amenity areas affected
by the construction works. The required numbers and locations of compensatory
trees shall be determined and agreed with the Government during Tree Removal
Application process under ETWB TCW No. 3/2006. •
Compensatory
tree planting shall be incorporated by the Project. The required numbers of
compensatory trees shall follow the requirements of ETWB TCW No. 3/2006. Loss
of amenity area adjacent to the Kwun Tong By-pass
and planting areas in KTD South Apron will be mitigated by the creation of
the Kai Tak South Apron: Amenity Area, which will be equal to or larger than
the current provision. •
Trees, shrubs
and climbers shall be planted to soften and screen proposed roads, central
medians and associated structures, and to enhance streetscape greening. •
All works area,
excavated area and disturbed area for tunnel construction and temporary road
diversion or any other proposed works shall be reinstated to former
conditions or better, with reasonable landscape treatment and to the
satisfaction of the relevant Government departments. •
Tunnel portals
and all above ground structures shall be sensitively designed to ensure the
element with colour, texture and tonal quality being compatible to the
existing urban context. Trees and shrub planting to minimize the potential
adverse landscape and visual impacts shall be included where space permits.
Roof top greening and vertical greening shall also be provided. |
•
Slight to
insubstantial (Beneficial) significance to LRs on Day 1 and Slight to
insubstantial (Beneficial)
to LRs at Year 10. •
Slight to
insubstantial (Beneficial) significance to LCAs on Day 1 and Slight to insubstantial
(Beneficial) to LRs at Year 10. •
Moderate to
insubstantial (Beneficial) significance on VSRs on Day 1 and Slight to
insubstantial (Beneficial)
to LRs at Year 10. •
152
compensatory trees to be planted, 4900
square meters of amenity area to be provided within the Kai Tak •
South Apron. 15,740 square meters of
planting ara to be provided(trees
and, shrubs) Sensitive architectural treatments to the Ventilation and Tunnel
Portal Buildings including green roof and vertical greening. |
Culture Heritage |
|||||
Construction
Phase |
|||||
The terrestrial and marine archaeology
assessments did not identify any areas of archaeological potential The built heritage survey has identified 11
buildings in Cha Kwo Ling. |
•
No impacts are
predicted. •
No adverse
impacts to any of the buildings have been identified. |
•
Annexes 10 and
19 of EIAO; •
Chapter 10 of
the HKPSG; and •
Antiquities and
Monuments Ordinance (AMO). |
•
Not applicable. |
•
No mitigation
will be required |
•
No adverse
impacts to any of the buildings have been identified. |
Operational
Phase |
|||||
The terrestrial and marine archaeology
assessments did not identify any areas of archaeological potential The built heritage survey has identified 11
buildings in Cha Kwo Ling. |
•
No terrestrial or
marine archaeological potential and no impacts are predicted. •
No adverse
impacts to any of the buildings have been identified. |
•
Annexes 10 and
19 of EIAO; •
Chapter 10 of
the HKPSG; and •
Antiquities and
Monuments Ordinance (AMO). |
•
Not applicable. |
•
No mitigation
will be required |
•
No adverse
impacts to any of the buildings have been identified. |
Waste Management |
|||||
Construction Phase |
|||||
Near the Project Site, the waste
transportation routes and the waste disposal site |
•
Excavated marine
deposit (sediment) buried underneath the South Apron and Cha Kwo Ling works areas for the construction of
cut-and-cover tunnel sections; •
The majority of
the soft C&D material, comprising sand fill, Grade III rock and below and
alluvium, makes up approximately 1.15Mm3. The predicted surplus amount of
this C&D material, in addition to the Grade II or above rock from the
subsea tunnel, totally approximately 975,980m3; •
Site clearance
will likely comprise the 11,846m3 inert C&D materials •
C&D waste
which is not suitable for public fill; •
Chemical waste; •
Sewage; and •
Approximately
1000m3 of general refuse will be generated. •
Site clearance
will generate inert materials in the form of soil, rock and concrete, in
addition to non-inert C&D waste materials such as timber, paper,
vegetation and plastic. •
No marine
sediment will be extracted from the marine waters. As such, the marine deposits to be
generated will be restricted to the sediment located under the reclaimed land
to be excavated during the land-based works at the South Apron and Cha Kwo Ling. |
•
Environmental
Impact Assessment Ordinance (Cap 499); •
Waste Disposal
(Amendment) Ordinance (Cap 354); •
Dumping at Sea
Ordinance (Cap 466); •
Land
(Miscellaneous Provisions) Ordinance (Cap 28); •
Public Health
and Municipal Service Ordinance (Cap 132) – Public Cleansing and Prevention
of Nuisances By-laws; •
Waste Disposal
(Charges for Disposal of Construction Waste) Regulation (Cap 354); •
Waste Disposal
(Chemical Waste) (General) Regulation (Cap 354); •
Environment,
Transport and Works Bureau Technical Circular (Works) No.34/2002 Management
of Dredged /Excavated Sediment; and •
Works Bureau
Technical Circular (WBTC) No. 12/2000 Fill Management. |
•
Not applicable. |
•
Mitigation measures
are required to ensure the proper handling, storage, transportation and
disposal of waste is carried out. Also
measures to ensure that the generation of waste is avoided and minimised and
that waste materials are recycled and treated as far as practicable. (refer
to section 11.4.8.1) •
During
construction phase, regular site inspections and supervision of the waste
management procedures shall be undertaken as part of the EM&A procedures. •
Disposal options
have been proposed. (refer to Table 11.8) |
•
No adverse
residual impacts would be anticipated |
Operational Phase |
|||||
Near the Project Site, the waste
transportation routes and the waste disposal site |
•
No significant
quantities of waste are expected. •
The quantities of
general refuse arising from the Project would be low and mainly arise from
the plant maintenance workshops associated with the ventilation
buildings. •
The quantities
of chemical waste such as lubrication oils, used batteries, paints and
solvents are likely to be generated but the quantities would be small and
insignificant. •
Operational
sewage will be generated but in small quantities. |
•
Waste Disposal
(Amendment) Ordinance (Cap 354) •
Waste Disposal
(Chemical Waste) (General) Regulation (Cap 354); |
•
Not applicable. |
•
No significant
waste implications are predicted |
•
No adverse
residual impacts would be anticipated |
Contaminated
Land |
|||||
Construction
Phase |
|||||
•
Construction workers
would be prone to exposure to any potential contaminated materials during the
construction phase when conducting excavation of the concerned contaminated
sites. The principle exposure routes
would include: -Direct ingestion of contaminated
materials through eating or drinking on-site; and -Dermal contact with contaminated
materials. -A total of 53 soil samples and 13
groundwater samples were collected. |
•
No adverse
impacts due to land contamination anticipated. in
accordance to the site investigation during the EIA stage. •
2 borehole
locations, EH1 and EH3, at which the SI works, were inaccessible during the
site investigation due to site access constraints at Cheung Yip Street. •
There may be
potential land contamination hotspots at Works Area WA2. As this area has
been inaccessible for conducting site investigation during the EIA stage,
land contamination assessment has not been conducted. |
•
Practice Guide
for Investigation and Remediation of Contaminated Land; •
Guidance Note
for Contaminated Land Assessment and Remediation; and •
Guidance Manual
for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land
Management. |
•
No exceedances of the RBRGs criteria for the land
contamination. |
•
No specific
mitigation measures are required in accordance to site investigation during
the EIA stage. •
Supplementary SI
to complete the land contamination assessment for borehole locations EH1 and
EH3 and further reconnaissance visits to WA2, would be conducted when these
sites become accessible. A supplementary CAP, CAR and/or RAP and RR (if
remediation work is necessary) should be submitted to EPD for endorsement
before commencement of construction works at these sites. |
•
No adverse
residual impacts are anticipated. |
Operational Phase |
|||||
•
No sensitive
receivers have been identified. |
•
Not applicable. |
•
Practice Guide
for Investigation and Remediation of Contaminated Land; •
Guidance Note
for Contaminated Land Assessment and Remediation; and •
Guidance Manual for
Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management.. |
•
Not applicable. |
•
Provided that
the necessary remediation action and measures have been fully implemented,
.no specific mitigation measures are required. |
•
Not applicable. |
Table 13.2 Summary of Key Environmental Outcomes
Area/Issue |
Environmental Outcomes and Mitigation
Measures |
Trunk
Road T2 Project |
As a part of the strategic road network within the South East Kowloon
Development, Route 6 forms an east west express link between West Kowloon and
Tseung Kwan O. Route 6 comprises the Central Kowloon Route (CKR), Trunk Road
T2 and Tseung Kwan O–Lam Tin Tunnel (TKO-LTT). This Assignment covers the
provision of the Trunk Road T2 and the main elements of the works comprise
the construction of Trunk Road T2 and its connections with the CKR at the
north apron area and the TKO-LTT to the south in the Cha Kwo
Ling area. The preferred Trunk Road T2
will comprise: 1.
a
dual two-lane trunk road of approximately 3.0km long with about
2.7km of the trunk road in form of tunnel; 2.
ventilation and
administration buildings and a traffic control and surveillance system; and 3.
associated civil, electrical, mechanical, landscaping and
environmental protection and mitigation works. |
Environmentally
Friendly Design Recommended |
The preferred alignment for the
Trunk Road T2 provides the best environmental option resulting in
significantly less environmental impacts, including reduced quantities of
excavated material, no dredging of potentially contaminated marine deposits,
reduced impacts on fisheries, water quality and marine ecology and operation
noise and air quality benefits. In addition, the TBM
method has been selected as the preferred method of tunnel construction,
which also, has notable environmental benefits. Air and Noise: As a sub-marine tunnel would be constructed by
TBM method, noise and dust from this operation would be contained underground
from the point of the launching shaft, minimising construction phase impacts
to the environment on the South Apron, particularly for existing sensitive
receivers (SRs) at the southern end of the alignment in Cha Kwo Ling. The operational air emissions would be vented
via a high level shaft from the ventilation buildings, enhancing dispersion
and resulting in low level impacts at the SRs at both the South Apron and Cha
Kwo Ling. Water Quality: As TBM is used to construct the Trunk Road T2, dredging
and reclamation is not required. The TBM tunnel would be deep enough to avoid
the seabed and marine deposits. It would be avoided to pass under the
existing breakwaters to the KTTS and the existing twin submarine outfalls of
the KTSTW and hence avoid the need to excavate and temporarily re-provide
both of these features and thus reduce further disturbance to the seabed and
marine sediment deposits. The TBM
would also be launched and received from shafts on land which would also
avoid deterioration of water quality and any disturbance to the seawalls and
marine environment. Construction
run-off from the land based works could potentially affect the marine waters
if not controlled. Marine Ecology
and Fisheries: As the
Trunk Road T2 project will be built on largely developed or disturbed land, terrestrial ecological impacts are not expected. As the Trunk Road T2 project is largely in tunnel
to be constructed by TBM, there would be no disturbance to the marine
environment. LVIA: On completion of the project, as the majority
of the Trunk Road T2 project works is either underground or used for
temporary construction and associated works, except for the Ventilation
Building and Tunnel Portal Buildings. In the operational phase these impacts will be
mitigated by provision of new roadside trees and shrub planting and a new
public amenity area, termed the Kai Tak South Apron Public Open Space. In
addition, the aforementioned buildings and portal will be mitigated by
sensitive and contemporary architectural detailing, including green roofs,
textual and tonal finishes, and screen planting. These are envisioned to
blend the Project into the proposed surrounding landscape. It is considered
that the residual landscape and visual impacts of the proposed Project are acceptable
with mitigation measures during construction and operational phases. Cultural
Heritage: Study of the marine and
terrestrial archaeology did not reveal any areas of archaeological potential
in the Trunk Road T2 area and as such no impacts are expected. In terms of
built heritage, the only resources are located in the Cha Kwo
Ling Village but these will not be significantly affected and no mitigation
is required. Waste
Management: The bulk
material constructed by TBM from the sub-sea tunnel will be alluvial material
which is not contaminated and can be reused in other projects once
dewatered. Some uncontaminated marine
sediments will be produced from the land based foundation works but it is
proposed to treat and reuse this material on site. |
Population
and Environmentally Sensitive Areas Protected |
With the
adoption of the environmentally friendly design in the preferred option, the
major environmental sensitive receivers will be protected. This preferred option is determined based
on the comparison of the environmental benefits and dis-benefits of the
various options and alternatives and has been selected on the basis that it
minimises environmental impacts and presents overall environmental benefits
over the other options and is considered the optimum scheme from an
environmental perspective. |
Air Quality |
Construction Dust Impact: Potential air quality
impacts from the construction works for the Trunk Road T2 construction works
would mainly be related to construction dust from excavation, materials
handling, spoil removal and wind erosion.
Without mitigation measures, dust impacts to the nearby ASRs will
exceed the respective TSP criteria. However, with the implementation of
hourly watering of all exposed areas and mitigation measures as defined in
the Air Pollution Control (Construction Dust) Regulation, provision of dust
enclosures at the conveyor belts, 3-sided barriers at the stockpiling areas
and good site practices, adverse 1-hour, 24-hour or annual residual impacts
would not occur. The predicted air impact would be unlikely to induce public
health concern. Operational
Impact:
Potential air quality impact during the
operational phase of Trunk Road T2 and other major existing road networks
would be dominated by vehicle gaseous emissions, mainly NO2 and
RSP, either from open roads, or via the proposed tunnel portals and
ventilation buildings. No exceedances of the
hourly, 24 hourly and annual NO2 or 24 hourly and annual RSP AQOs are
predicted and as such, no mitigation measures are required. No adverse
residual impacts during the operational phase are predicted. |
Noise |
Construction
Air-borne Noise: Without mitigation, noise impacts are
predicted to exceed the relevant criteria by up to 15dB(A). The high level of unmitigated construction
noise impacts are due to the limited separation distance between the NSRs and
the works sites. Mitigation measures
are, therefore, recommended to reduce the noise levels to within the EIAO-TM
noise criterion, including provision of quieter plants, silencers, noise
barriers, enclosures and acoustic fabric. After these mitigation
measures are adopted, the noise levels at all
representative NSRs would meet the relevant noise criteria. No adverse
residual impacts would be anticipated during the construction phase. However,
construction air-borne noise monitoring would be required to ensure
compliance with respective criteria. Construction
Ground-borne Noise: With a 10dB(A) prediction safety factor,
the daytime noise criteria of 65dB(A) is fulfilled at all the NSRs under
unmitigated condition. In order to
ensure compliance with the daytime ground-borne noise limits, the advancing
speed of the TBM should be restricted to 2m/hr. Operation
Fixed Plant Noise: The operation fixed plant noise impacts at
the identified NSRs have been predicted to comply with the respective
criteria and adverse fixed noise impacts are not anticipated. As such, no mitigation measures are required. However, prior to the
operation of the Trunk Road T2 project, the Contractor should conduct noise
commissioning tests for all major fixed noise sources to ensure the noise
emission comply with the EIA report assessed scenario. Operation
Traffic Noise: Exceedances of respective operational traffic noise are anticipated at some of
the NSRs. However, the affected NSRs
are anticipated to be equipped with centralised air conditioning systems and
will, therefore, not rely on openable windows for
ventilation. Thus, no direct mitigation measures are required. |
Water
Quality |
Potential
water pollution sources have been identified as construction run-off,
wastewater discharge from tunnelling and excavation, contaminated
groundwater, sewage effluent, accidental spillages and waste construction
materials. Mitigation measures
including providing perimeter drains, sand/silt removal facilities and oil
interceptors, covering excavated and construction materials and spill
response plans have been recommended to mitigate any adverse water quality
impacts. Based on the implementation
of the mitigation measures, no adverse water quality impacts are predicted. No
significant adverse residual impacts during the construction and operational
phases are anticipated, provided that the above mitigation measures are
implemented. |
Marine
Ecology |
Construction Phase: In order to avoid the marine ecological
impacts during construction phase, TBM method of tunnelling has been adopted
instead of the IMT method. As such, there will be no permanent habitat loss
predicted. The potential for
construction stage site run-off may lead to temporary water quality issues
and an increase in local suspended solids for a short period of time during
construction phase. However, these
impacts are predicted to be minor and can be further controlled by the
implementation of the recommendations in the Water Quality Impact Assessment
and ProPECC PN 1/94 Construction Site Drainage and,
thus, they would be temporary and negligible with good site practices in
place during the construction phase. With implementation of the mitigation measures,
the Trunk Road T2 project would have no long-term, unacceptable residual
ecological impacts to marine ecological habitats and associated wildlife
during construction phase Operational Phase: Minor impacts to marine ecological
resources due to potential accident spillages of chemical/oil and road surface
run-off have been predicted as a result of the operation of the Trunk Road T2
project and no ecological specific mitigation measures are required. The implementation of the mitigation
measures recommended in the Water Quality Impact Assessment, including
provision of adequate drainage system with silt traps and oil interceptors,
will help to minimise any impacts further. |
Fisheries |
No construction or operational
impacts to the marine environment are predicted and, therefore, mitigation
measures are not required for fisheries resources given that the water
quality mitigation measures will be implemented as necessary. |
Landscape and Visual |
On completion of the Project, the majority of Trunk
Road T2 is underground, except for the low rise (+17mPD) Ventilation
Building, Tunnel Portal Building and refuse collection building. In the
Western Works Area, there will be a temporary loss of 75,300 square metres
and a permanent loss of 8500 square meters of hard standing and, 5029 square
meters of planting areas will be permanently lost. This will be mitigated by
15,740 square meters of planting areas and 4,900 square meters of Amenity
Area as referred to in the report as RE10 Kai Tak
South Apron: Amenity Area. 98 trees
will be impacted upon. 67 trees are recommended to be felled and 31 are
proposed to be transplanted to a location that will be identified at a later
stage of the project. Extensive compensatory planting will include 152 trees
in accordance with ETWB TCW No. 3/2006 (refer to Figure 9.11.2). In the Eastern Works Area one tree and
an approximate area of 21,500 square metres of hard standing will be lost.
Mitigation for the felled tree has been included within the compensatory
trees for the Western Works Area. The site will be reinstated and handed over
for future development of Cha Kwo Ling Promenade
Park under a separate project. Details of the landscape proposals for the
Western Works Area will be reviewed within the detail design stage. It is
considered there will be no substantial adverse landscape and visual impacts
by the Project during the operation phase. Through the construction stage the
following mitigation measures will be followed: (a)
All
works shall be carefully designed to minimize impacts on existing landscape
resources and visually sensitive receivers. Existing trees within works area
shall be retained and protected where practical. (b)
Existing
trees that are unavoidably affected by the works should be transplanted where
practical. (c)
Topsoil,
where identified, shall be stripped and stored for re-use in the construction
of the soft landscape works, wherever practicable. (d)
The potential for soil
erosion shall be reduced by minimizing the extent of vegetation disturbance
on site and by providing a protective cover over newly exposed soil. (e)
Large
temporary stockpiles of excavated material shall be covered with unobtrusive
sheeting to prevent dust and dirt spreading to adjacent landscape areas and
vegetation, and to create a neat and tidy visual appearance. (f)
Construction
plant and building material shall be orderly and carefully stored in order to
create a neat and tidy visual appearance. (g)
Erection
of decorative screen hoarding should be designed to be compatible with the
existing urban context. (h)
All
lighting in construction sites shall be carefully controlled to minimize
light pollution and night-time glare to nearby residences and GIC user. Through
the operational phase the following mitigation measures will be implemented: (a)
Provision
of a new public open space, termed the Kai Tak South Apron Public Open Space. (b)
Compensatory
tree planting shall be incorporated along all roadside amenity areas affected
by the construction works. The required numbers and locations of compensatory
trees shall be determined and agreed with the Government during Tree Removal
Application process under ETWB TCW No. 3/2006. (c)
Compensatory
tree planting shall be incorporated into any public open spaces affected by
the construction works. The required numbers and locations of compensatory
trees shall be determined and agreed with the Government during Tree Removal
Application process under ETWB TCW No. 3/2006 (d)
Trees
and shrubs shall be planted to soften and screen proposed roads, central medians
and associated structure, and to enhance streetscape greening. (e)
All
works areas, excavated area and disturbed area for tunnel construction and
temporary road diversion or any other proposed works shall be reinstated to
former conditions or better, with reasonable landscape treatment and to the
satisfaction of the relevant Government departments. (f)
The
tunnel portal and refuse collection building would be sensitively designed
and proposed to be no higher than 17mPD (Figures 9.12.1 – 9.12.4). Mitigation measures including vertical
greening and tree planting are proposed to be provided. The overall visual impacts on the
surrounding VSRs would not be significant and could be considered positive to
a certain extent. The above mitigation
measures for construction and operational phases will reduce landscape and
visual impacts of the Project to acceptable levels. |
Cultural
Heritage |
The terrestrial and marine
archaeology assessments did not identify any areas of archaeological
potential and no impacts are predicted.
However, any antiquity or supposed antiquity discovered during the
course of the excavation works will be reported to the AMO immediately. The
built heritage survey identified 11 buildings in Cha Kwo
Ling. However, no adverse impacts to
any of the buildings have been identified during either the construction or
operational phases of the project and no mitigation will be required. |
Waste
Management Implication and Land Contamination |
The construction of the Trunk Road
T2 will involve a number of activities which will generate waste that can be
broadly be classified into distinct categories based on its nature and the
options for disposal. These include: ·
Excavated marine deposit (sediment) buried
underneath the South Apron works area for the construction of cut-and-cover
tunnel sections; ·
Excavated C&D materials suitable for
public fill, including the alluvium from the sub-marine tunnel construction; ·
C&D waste which is not suitable for
public fill; ·
Chemical waste; ·
Sewage; and ·
General refuse. There are remaining SI works at
EH1 & EH3 and further reconnaissance visits to inaccessible Works Area
WA2 to be conducted when these sites become accessible. Supplementary CAP, CAR and/or RAP and RR
(if remediation work is necessary) should be submitted to EPD for endorsement
before commencement of construction works at these sites. With the
implementation of the recommended mitigation measures, there would be no
adverse residual impacts associated with the handling, storage, transportation
or disposal of the waste generated by the Trunk Road T2 project during the
construction and operational phases. As there
were no exceedances of the criteria for the land
contamination for the Trunk Road T2 project, there would be no adverse impacts
due to land contamination anticipated. |