7
Landscape
7.1.1.1
The
EIA has recommended that EM&A for landscape and visual resources is
undertaken during the construction and operational phases of the project. The design, implementation and maintenance of
landscape mitigation measures is a key aspect of this and should be checked to
ensure that they are fully realised and that potential conflicts between the
proposed landscape measures and any other project works and operational
requirements are resolved at the earliest possible date and without compromise
to the intention of the mitigation measures.
In addition, the implementation of the mitigation measures recommended
by the EIA will be monitored through the site audit programme.
7.2.1.1
The Landscape
and Visual Assessment of the EIA recommended a series of mitigation measures to
ameliorate the landscape and visual impacts of the project. These measures include the following:
· adoption of construction methods to minimise both landscape and visual impacts, particularly in sensitive locations;
· localised refinement of the Project Area to minimise loss of landscape resources, where practical;
· minimising working areas as far as possible;
· protection and retention of existing vegetation where possible; and
· reinstatement of disturbed areas and compensatory planting.
7.2.1.2
The
mitigation measures for both the construction and operation stages as
recommended in the EIA are summarised in Table 7.1
and Table 7.2
below and provided in the Environmental Mitigation Implementation Schedule in Appendix
A:
Table 7.1 Construction Phase Mitigation Measures
ID No. |
Landscape and Visual Mitigation Measure |
CM1 |
All works shall be
carefully designed to minimize impacts on existing landscape resources and
visually sensitive receivers. Existing trees within works area shall be
retained and protected. |
CM2 |
Existing trees of
good quality and condition that are unavoidably affected by the works should
be transplanted. |
CM3 |
Not used |
CM4 |
Not used. |
CM5 |
Large temporary
stockpiles of excavated material shall be covered with unobtrusive sheeting
to prevent dust and dirt spreading to adjacent landscape areas and vegetation,
and to create a neat and tidy visual appearance. |
CM6 |
Construction plant
and building material shall be orderly and carefully stored in order to
create a neat and tidy visual appearance. |
CM7 |
Erection of decorative
screen hoarding should be designed to be compatible with the existing urban
context. |
CM8 |
All lighting in
construction site shall be carefully controlled to minimize light pollution
and night-time glare to nearby residences and GIC user. The contractor shall
consider other security measures, which shall minimize the visual impacts. |
Table 7.2 Operation Phase Mitigation Measures
Id
No. |
Operation
Phase Landscape and Visual Mitigation Measures |
OM1 |
Compensatory tree
planting shall be incorporated along roadside amenity areas affected by the
construction works. The required numbers of compensatory trees shall follow
the requirements of
ETWB TCW No. 3/2006. |
OM2 |
Compensatory tree
planting shall be incorporated by the Project. The required numbers of
compensatory trees shall follow the requirements of ETWB TCW No. 3/2006. Loss
of amenity area adjacent to the Kwun Tong By-pass
and planting areas in KTD South Apron will be mitigated by the creation of
the Kai Tak South Apron: Amenity Area, which will be equal to or larger than
the current provision. |
OM3 |
Trees, shrubs and
climbers shall be planted to soften and screen proposed roads, central
medians and associated structures, and to enhance streetscape greening. |
OM4 |
All works areas,
excavated areas and disturbed areas for tunnel construction and temporary
road diversion or any other proposed works shall be reinstated to former
conditions or better, with landscape treatment and to the satisfaction of the
relevant Government departments. |
OM5 |
Tunnel portals and all above ground structures
shall be sensitively designed to ensure the element with colour, texture and
tonal quality being compatible to the existing urban context. Trees and shrub
planting to minimize the potential adverse landscape and visual impacts shall
be included where space permits. Roof top greening and vertical greening
shall also be provided. |
7.3 Construction and Operational Phase Audit
7.3.1.1
A
specialist Landscape Sub-Contractor should be employed by the Contractor for
the implementation of landscape construction works and subsequent maintenance
operations during the establishment period.
It is proposed that the planting works will be on-site and the planting
should be completed during the construction contract. The monitoring of the planting establishment
should be undertaken for a 12 month period which could extend throughout the
Contractor’s one-year maintenance period, which will be within the first
operational year of the project.
7.3.1.2
All
measures undertaken by both the Contractor and the specialist Landscape
Sub-Contractor during the construction phase and first year of the operational
phase shall be audited by a Registered Landscape Architect, as a member of the
Environmental Team (ET), on a regular basis to ensure compliance with the
intended aims of the measures. Site
inspections should be undertaken at least once every two weeks throughout the
construction period and once every two months during the operational phase,
which will comprise the 12 months of the Contractor’s maintenance period. The broad scope of the audit is detailed
below but should also be undertaken with reference to the more specific
checklist provided in Table 7.3.
Operational phase auditing will be comprise monitoring of the establishment of
the landscape planting only and, thus, only the items below concerning this
period are relevant to the operational phase.
· the extent of the agreed works areas should be regularly checked during the construction phase. Any trespass by the Contractor outside the limit of the works, including any damage to existing trees and soft landscape areas shall be prohibited;
· the progress of the engineering works should be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken;
· all existing trees and vegetation within the study area which are not directly affected by the works are retained and protected;
· the methods of protecting existing vegetation proposed by the Contractor are acceptable and enforced;
· preparation, lifting transport and re-planting operations for any transplanted trees;
· all landscaping works are carried out in accordance with the specifications;
· the planting of new trees, shrubs, groundcover, climbers, ferns, grasses and other plans, together with the replanting of any transplanted trees are carried out properly and within the right season; and
· all necessary horticultural operations and replacement planting are undertaken throughout the Establishment Period to ensure the healthy establishment and growth of both transplanted trees and all newly established plants.
Table 7.3 Construction/Operational Phase Audit Checklist for Ecology Issues
Area
of Works |
Items to be Monitored |
Advance planting |
Monitoring of implementation and
maintenance of planting, and against possible incursion, physical damage,
fire, pollution, surface erosion, etc. |
Protection of all trees and existing soft
landscape areas to be retained |
Identification and demarcation of
trees / vegetation to be retained, erection of physical protection (e.g.
fencing), monitoring against possible incursion, physical damage, fire,
pollution, surface erosion, etc. |
Clearance of existing vegetation |
Identification and demarcation of
trees / vegetation to be cleared, checking of extent of works to minimise
damage, monitoring of adjacent areas against possible incursion, physical
damage, fire, pollution, surface erosion, etc. |
Pruning of trees |
Identification and demarcation of
trees / vegetation to be pruned, monitoring of extent of pruning to minimise
damage, timing of operations, implementation of all stages of preparatory and
pruning works, and maintenance of pruned vegetation, etc. |
Plant supply |
Monitoring of operations relating to
the supply of specialist plant material (including the collecting,
germination and growth of plants from seed) to ensure that plants will be
available in time to be used within the construction works. |
Soiling, planting, etc. |
Monitoring of implementation and maintenance of soiling and planting works and against possible incursion, physical damage, fire, pollution, surface erosion, etc. |
Site fencing and hoarding |
Implementation and maintenance, to
ensure compliance with agreed designs and check that it matches the
surrounding environment and does not cause visual intrusion. |
Architectural treatment of engineering
works. |
Implementation and maintenance of mitigation measures, to ensure compliance with agreed designs as applicable. |
Establishment Works |
Monitoring of implementation of maintenance operations during Establishment Period |
7.3.1.3
In the
event of non compliance the responsibilities of the relevant parties is
detailed in the Event /Action plan provided 1n Table 7.4.
Table 7.4 Event / Action Plan for Construction/Operational Phase for Ecology Issues
Action Level |
ET |
IEC |
ER |
Contractor |
Non-conformity on one occasion |
1. Identify Source 2. Inform the IEC and the ER 3. Discuss remedial actions with the IEC, the ER and the Contractor 4. Monitor remedial actions until rectification has been completed |
1. Check report 2. Check the Contractor's working method 3. Discuss
with the ET and the Contractor on possible remedial measures 4. Advise the ER
on effectiveness of proposed remedial measures. 5. Check implementation
of remedial measures. |
1. Notify Contractor 2. Ensure remedial measures are properly implemented |
1. Amend working methods 2. Rectify damage and undertake any necessary replacement |
Repeated Non-conformity |
1. Identify Source 2. Inform the IEC and the ER 3. Increase monitoring frequency 4. Discuss remedial actions with the IEC, the ER and the Contractor 5. Monitor remedial actions until rectification has been completed 6. If
exceedance stops, cease additional monitoring |
1. Check monitoring report 2. Check the Contractor's
working method 3. Discuss with the ET and
the Contractor on possible remedial measures 4. Advise the ER on
effectiveness of proposed remedial measures 5. Supervise implementation of remedial measures. |
1. Notify the Contractor 2. Ensure remedial measures are properly implemented |
1. Amend working methods 2. Rectify damage and undertake any necessary replacement |
Note: ET –
Environmental Team, IEC – Independent Environmental Checker, ER – Engineer’s
Representative